Multiple Project & Constraints

11
Multiple Projects & Constraints 1

description

Project Appraisal & Finance

Transcript of Multiple Project & Constraints

Multiple Projects & Constaints

Multiple Projects & Constraints11CONSTRAINTSProject dependence, capital rationing and project indivisibility are factors that restrict isolated project selection. If the acceptance and rejection of one influences the cash flow stream of the other or affects the acceptance and rejection of others, then the two projects are said to be economically dependent. The three types of economic dependency are as follows:1. Mutual exclusiveness2. Negative dependency3. Positive dependency (complementariness).2Capital rationing occurs when funds available are not adequate to undertake all the projects that are acceptable otherwise. It also arises because of internal limitation or an external constraint.

A project cannot be accepted or rejected partially, it is indivisible, and has to be accepted or rejected in totality.3Methods for Comparison:Factors like economic dependency, capital rationing or project indivisibility emphasize the need for comparison of projects.45Method of Ranking6Method Of RankingRanking all the projects in decreasing order of the NPVs, IRRs, or BCRs.

NPV method:The intermediate cash flow is re-invested at a rate of return equal to the cost of capital of the firm.IRR method:Cash flow is re-invested at a rate of return equal to or greater than the Fisherian rate of return.BCR criterion:The intermediate funds are reinvested at a rate of return greater than the Fisherian rate of return.

Accepting all projects in that order until the capital budget is exhausted.7Joel Dean is seriously impaired by problems:

Conflict in ranking as per discounted cash flow criteriaProject indivisibilityFeasibility combinations Approach

Sources of Conflicts:Size DisparityTime DisparityLife DisparityEXAMPLE

8All combination of feasible projects should be defined, given the capital rationing constraint and project dependencies. Then choosing a combination having the highest NPV is known as the feasible combination procedure.

Problems: There are two major problems related to this method (i) Because of the discounted cash flow criteria, conflict arises in the ranking. (ii) Indivisibility of the project.

9Mathematical Programming Approach103 ModelsLinear programming model: Assumes that the objective function and the constraint equation are linear while the decision variables are continuous.Integer linear programming model: It is presupposed that decision variables assume a value of 0 or 1.Advantages of the method: It overcomes the problem of partial projects which besets the linear programming model and. (b) It is capable of handling virtually any kind of project interdependency like mutual exclusiveness, contingency and complementary.Goal programming model: It solves the programming problem of minimizing the absolute deviation from specific goals in order of the established priority structure.11Ishaan Trivedi Ritesh Kumar PatroSaurav SharmaRahul ChitlangiaVineet GadiaTHANK YOU12