Multi-level Risk Management for the Port of Miami...
Transcript of Multi-level Risk Management for the Port of Miami...
Multi-level Risk Management for
the Port of Miami Tunnel Project
Eldon Abbott
WSP Parsons Brinckerhoff -- Retired
Reliance Engineers, LLC
Project Team
Florida Department of Transportaion
Port of Miami
City of Miami
Miami Dade County
Nosssman, LLP – Legal Advisors
Jeffery A. Parker & Associates, Inc. –
Financial Advisors
PB Team as Owner’s Rep
Project Team
Miami Access Tunnel – Concessionaire,
LLC
Meridiam Infrastructure - Majority Equity
Partner
Bouygues Travaux Publics – Minority Equity
Partner
Contractor – Bouygues Civil Works Florida
Port of Miami
Port of Miami Operations
The 12th largest national cargo port & top containerized seaport in Florida
3.5 million cruise passengers in 2004
9.2 million tons of cargo shipped in 2004
$17 billion in economic output
Cargo traffic and cruise traffic divided on the Port
PORT ACCESS: EXISTING TRUCK ROUTES
THROUGH DOWNTOWN MIAMI
6
Port growth is
constrained
by current
access
Trucks
currently
travel through
NE 1st and
2nd Avenues,
and
5th and 6th
Streets
Port
of
Miami
PB’s Project Re-evaluation
Scope
MacArthur Causeway Bridge widening
Tunnel and underground work – Bored Tunnel or Immersed Tube Tunnel?
Road work on Watson Island
Road work on Dodge Island
Watson Island development
Geotechnical
Tunnel Alignment
MacArthur Causeway Bridge
Widening
Tunnel & Underground Work
Typical Section
Tunnel & Underground Work
Bored Tunnel Profile
Surface Roads
Watson Island
Surface RoadsDodge Island Connection to New Port Road Network
Bored Tunnel Engineering
IssuesGeotechnical conditions
Shallow cover
Potential for high water inflows
Deep cut and cover
Buoyancy
Material disposal
Limited construction work area
Permitting
Immersed Tube Tunnel -
Watson Island
EXTENDED
ITT
EXTENDED
ITT
Immersed Tube Tunnel - Port of
Miami
EXTENDED
ITT
EXTENDED
ITT
Immersed Tube Tunnel
Profile
ITT
ITT Typical Section
Immersed Tube Tunnel – Channel Dredging
Issues – Interference with Port Operations
Wharf Crossing at Port: C&C
Section
Geotechnical Basics – Conceptual
Design: Tunnel Boring Locations
Geotechnical Conditions – Jack-Up Barge Drilling
in Channel
Geotechnical Basics
Photo of Core Recovered in Channel
Geotechnical Basics
Miami & Ft. Thompson Limestone
Primary Geologic Strata
Geotechnical Basics -
Video Images Down Borehole
Watson Island Developments
PARROT
JUNGLE
FUTURE
PARKPARKING
CHILDREN’S
MUSEUM
MIAMI
ISLAND
GARDENS
PROPOSED
Bored Tunnel
Advantages
No Dredging thus Reduced Environmental Impact
EPB TBM State of the Art for Subaquatic Conditions
Lower Impact on Port Operations
Tunnels can be Extended to Reduce Amount of C&C
Sections
Constraints
Increased Risk from Unforeseen Ground Conditions
Still has Potential High-Water Inflow Quantities
Buoyancy Issues
Muck Disposal
Immersed Tube Tunnel
Advantages
Less Risk Construction Method
Use Conventional Construction Equipment
Constraints
Environmental Impacts/Permits
Major Interruptions to Port Operations
Requires Dredging/Blasting
Spoils Disposal
Requires Extensive Deep Cut-and-Cover Sections
Groundwater Control is Difficult & Expensive
TUNNEL PERMITTING & Regulatory Issues
Potential Permits Required
FDEP (or SFWMD) Environmental Resource Permit (ERP)
• surface water encroachments
• sovereign submerged lands lease or other consent of
use
• stormwater treatment (and dewatering plan approval if
dewatering is contemplated)
Miami-Dade DERM
• Class I Marine Construction Permit
• Class II Stormwater Discharge
USACE Individual Permit
• surface water encroachments
• potential offshore disposal of excavated material.
FDEP Construction Permit
• erosion/sedimentation control
U.S. Coast Guard (USCG) Bridge Permit
• bridge construction or modification
Risk Assessment during
Preliminary Engineering
FDOT Goal:
Determine and quantify in $ value the risk associated with the bored tunnels
Objective:
Develop a risk sharing mechanism with potential Concessionaires to keep the bids “affordable”
INDUSTRY FORUM
Port of Miami Tunnel
December 5, 2005
Issues for Discussion: Engineering
/ Geotechnical
To what level of completeness should engineering documents be prepared before bidding? Does this depend on the procurement model (DBOM or concession models)?
What will happen to the material from the dredging and/or boring operations?
How much geotechnical information is enough?
What additional type(s) of geotechnical testing and analysis is required at this time?
Issues for Discussion:
Construction MethodBecause of potential environmental
impacts and impacts to Port operation, recent efforts have focused on the bored tunnel option.
Does the immersed tube tunnel make more sense as the construction method?
Would you be willing to bid on this option as an alternate?
Issues for Discussion:
Construction Risk
Is the level of risk associated with the
bored tunnel manageable?
What methods and actions should be
taken to mitigate this risk?
What risk-sharing concepts should be
considered for this project?
Why Public-Private Approach?
Project complexity
Tunnel construction and operation are
atypical for FDOT
Need for private sector innovation and
efficiencies
Share risks with experienced partners
Significant but finite local / state funding
available for project
Financial leveraging power of PPP’s
-37- Draft 4 – Feb 28, 2006
Industry Input
Comments received from 9 contractors /
engineers
Reactions to options for financial
structuring of geotechnical risk sharing
Reactions to proposed owner
geotechnical testing program
Suggestions based upon successful
experiences
A Multi-Level Strategy
Conduct additional Geotechnical Studies
Industry Input to these studies
Geotechnical Data + Baseline Report
Performance Specifications
Insurable Risks
Detailed Unit Costs
Owner’s Contingency Reserve
Consideration of Time
Force Majeure - Named Storms
Risk Assessment Workshops
FDOT and the Owner’s Rep Team conducted
several Risk Assessment workshops at
strategic points during the RFP preparation
stage.
43 Significant risks were identified and
quantified through these workshops
These 43 risks, if they all occurred, would have
potential cost impact between $95 and $185
Million
Tunnel Buoyancy Issue
Showing Ballast in
Invert used to
Counteract Buoyancy
Ballast
Counteract Buoyancy
Risks identified for Bored Tunnel
Potential for uncontrolled groundwater inflow into tunnel during excavation
Controlling discharge of excavated material
Prevention of “Frac-out” into Biscayne Bay waters above tunnel alignment.
Large diameter TBM / Heavy Cutterhead / Low Bearing Capacity Soil Layers / Tight Construction Tolerances.
Potential for Presence of large (?) voids.
Port of Miami Tunnel Risk
Assessment
Extract from the risk register
Port of Miami TunnelRisk Analysis set the stage for risk sharing
with DBOM Concessionaire
Extract
www.portofmiamitunnel.com
Tunneling Profile Section & Cross Passages
• Tunnels are approximately 4200 ft. long
• +40 ft. under the bottom of Government Cut &
approximately 120 ft. below the surface at deepest
point
• 5% Grade
• 5 cross passages
Major Construction Period Risks
Design – performance specifications (outcome rather
than input based)
Permitting led by with FDOT support
Differing site conditions (geology, existing bridge
foundations)
Changed conditions measured against Geotechnical
Baseline Report, compliance with “Subsurface
Methods Plan” submitted as part of proposal
Contingency fund with $10M “deductible”, $150M
“FDOT tranch” and $20M “concessionaire tranche
Other Major Construction Period
Risks
Other key risks also rely on baseline reports:
Hazardous materials
management/remediation
Utilities and underground piles
Force Majeure strictly defined, with named
windstorm and terrorism being self-insured by
FDOT
FDOT Risk Sharing
PhilosophyExtract from the Project Information Memorandum
“A key driver in FDOT’s decision to procure the tunnel using a concession approach is the opportunity to access private expertise in managing, mitigating and valuing geotechnical risk. Therefore significant geotechnical risk will be transferred to the private sector”
“Concessionaire will be responsible for overruns due to Baseline Geotechnical Conditions” given in the GBR.
And
“FDOT will share substantial amounts of risk for overruns due to changed geotechnical conditions”
FDOT Changed Condition Risk
Allocation
Uninsured Losses (x) Risk Allocation
x < $10 million 100% Concessionaire
$10 m < x < $160 m 100 % FDOT
$160 m < x < $180 m 100 % Concessionaire
X > $180 m
Either Party has the right to
Terminate Contract or
negotiate mutually
acceptable agreement for
cost sharing.
Risk Category
Risk Allocation
FDOTConcessionair
eShared
Political X
Financial X
Traffic & Revenue X
Right-of-Way X
Permits/Government Approvals X
Utilities XProcurement XConstruction XOperations & Maintenance XHand-Back XForce Majeure XChange in Law XContamination XGeotechnical X
SUMMARY RISK ALLOCATIONS
-50- Draft 4 – Feb 28, 2006
Insurable Risks
FDOT retaining insurance advisors
Insurable risks to be identified in draft
RFP
List to be refined with Short-listed firms
Insured events will not be compensated
from Geotechnical Contingency Reserve
Premiums are Concessionaire’s
responsibility
Lessons Learned
Risk allocation – clearly defined so that D/B teams can price their risk.
Permits must be filed and preliminary Order of Conditions obtained for pricing. Permitting Agencies imposed strict conditions on
protection of Manatees and clear waters of Biscayne Bay
Contamination must be identified and “baselined” for pricing.
Utility work & responsible parties for performing work must be identified for pricing
Lessons Learned
All ROW must be secured if innovation is the
goal from proposers
Third party issues & mitigation measures
should be given in the documents
Staging areas & dates available in
documents
All geotechnical data for design &
construction should be obtained in advance
especially with a shortened bid period.
www.portofmiamitunnel.com
TUNNEL BORING MACHINE EB & WB
BREAK-IN, BREAKOUT & TUNNEL
Mining of the Eastbound Tunnel began on November 11, 2011 and was
completed on July 31, 2012 (751 Rings & 4,186 LF)
Mining of the Westbound Mining began October 29, 2012 and was completed
on May 6, 2013 (745 Rings & 4,152 LF)
• 2 bored tunnels each 4,200 ft. long
• Tunnel bore 42 ft. with 37ft. ID
• 8 piece rings using 5.6ft wide by 24 in. thick segments
• 5% maximum grade and a tight horizontal curve Rmin= 1,000 ft.
• Low ground cover : from ABOVE grade to 0.5 to 1.5 Tunnel Diameters
• Tunnel Separation: 1/3 to 1 ¼ Tunnel Dia. (edge to edge)
www.portofmiamitunnel.com
TUNNEL BORES: THE TASK
Cutterhead
Diameter
42.3 feet
361 foot
long trailing
gear
Total TBM
Length
428.5 feet
POMT Tunnel Boring Machine
Cutter Soil Mixing
www.portofmiamitunnel.com
Soil Mix walls
And soil
improvement
EXCAVATION OF LAUNCH SHAFT
www.portofmiamitunnel.com
Tension Tie downs
Challenging
Geologic Conditions
6 foot diameter test boring!
Seismic cone penetrometer testing
Seismic Acquisition
Three basic elements:
1) Source: sea = airgun (compressed air)
2) Receiver: sea = hydrophones
3) Geometric layout that establishes
the relationship between source &
receiver
24-channel
hydrophone
streamer
compressed air source,
two 10 cu-inch Bolt airguns
Walker Marine
Geophysical
survey vessel
Slide credit, Dr. Donald F. McNeill, Ph.D., PG
Geologic Profile
ForUpper Fort Thompson Formation
Anastasia Formation
Key Largo Formation (Lower FTF)
Tamiami Formation
Miami Formation
110 ft +/-
Looking East at Government Cut
FORMATION GROUTING IN THE KEY
LARGO FORMATION
•Formation Grouting
along the tunnel
alignment during 2012
•Grouting ran 24 hrs
during non-cruise days
(3 or 4 days per week)
A total of ~64,000 cy of
grout was placed, ~27%
of the formation volume.
Grouting for unplanned
interventions, muck
conditioning, and tail
void grout confinement.
Inside Diameter 37 ft
Bored Tunnel Length 4,206 LF
www.portofmiamitunnel.com
CROSS PASSAGES – GROUND FREEZING PROCESS
• 44 freezing pipes were installed
• Estimated freeze time once brine installed at -22◦F was 40 days.
• A small cooling unit was installed in the second tunnel to cool the
lining segments and ensure efficient “closing” of ice ring.
• Steel support frame was installed to prevent movements of the
first tunnel due to ice pressures.
• Steel door was installed as “fail safe” to be closed in case of an
emergency during excavation.
Port of Miami Tunnel
Estimated project construction cost -
$607 million
Final Construction cost - $667 million
Most of the increase ($50 Million) was
due to additional grouting performed
under Government Cut shipping channel
Open for Traffic
Aug 3, 2014