MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation...

38
MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1

Transcript of MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation...

Page 1: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

MTAT.03.244 Software Economics

Software Cost Estimation

Dietmar Pfahl

(based on materials by Marlon Dumas)

1

Page 2: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

For Discussion

• It is hopeless to accurately estimate software costs. Most often than not, such estimates are wrong. So why should we bother?

• We have 6 months and 10 analysts/developers, so it will take 6 months and 60 person-months. Why bother about estimating the cost?

3

Parkinson's Law If we have 4 person-years, it will take 4 person-years

If your upper limit is 300K, it will take 300K

Page 3: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

4

Page 4: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Two lessons

• You can be uncertain of an estimate, but you first need to have an estimate to be uncertain of

• You can change your plan, but you first need to have a plan to change

5

Page 5: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

What is a Good Estimate?

“A good estimate is an estimate that provides a clear enough view of the project reality to allow the project leadership to make good decisions about how to control the project to hit its targets.”

Steve McConnel

Software Estimation: Demystifying the Black Art

6

Page 6: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Good (ARTfUL) Estimates

• Accurate (reasonably)

• Reliable (reasonably)

• Traceable: we should know where the effort will go into and why?

• Updatable: it should be easy to “refine” with new data

7

Page 7: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

There are lies, dammed lies and statistics.

• What about a method to estimate software costs from a high-level architecture, that is:

• within 20% of the actual size 50% of the time

• within 30% of the actual size 66% of the time

• Decomposes effort/cost into four project phases

• Can we use it and how?

8

Page 8: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Cone of Uncertainty

Craig Larman Agile & Iterative Development

9

Page 9: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Effort Estimation Methods

1. Parkinson’s Law (?)

2. Estimation by analogy (nearest neighbour)

• This project is 20% more complex than the previous

3. Expert judgement, individual or collective:

• Wideband Delphi

• Planning Poker

4. Statistical (parametric) methods

10

+ Any of 2 to 4 with decomposition…

Page 10: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Wide-Band Delphi

Ask each team member their estimate

Apply personal experience,

Look at completed projects,

Extrapolate from modules known to date

Collect and share in a meeting: discuss why/how different people made their estimate

Repeat

When stable, remove H, L and Size = Avg. of Four

See: http://www.stellman-greene.com/ch03

12

Page 11: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Agile Variant: Planning Poker

1. Product owner reads a user story, answers questions

2. Simultaneously: each team member pulls a card with their estimate (e.g. in “story points”, “ideal” days, etc.)

3. The holders of smallest and the largest estimate give reasons (others discuss too)

4. Repeat from 2 until convergence

13

Page 12: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Statistical Methods • Evidence-based scheduling:

www.joelonsoftware.com/items/2007/10/26.html

• Fitting a function-points-to-effort function using history

www.math.vu.nl/~x/ipm/ipm.pdf

• Parametric cost models

• COCOMO II.2000 (Boehm et al.)

• Costar and Cost Xpert (based on COCOMO II)

• SLIM-Estimate

• Construx Estimate, KnowledgePlan, TruePlanning, ... 14

Page 13: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Principle of Parametric Estimation

• It took me one month to fully develop (end-to-end) a small software application of 1000 LOC

• Can I develop an application of 10000 LOC in 10 months?

• I have four friends with similar experience as mine

• Can we develop an application of 10000 LOC in 2 months?

Hints: Brook’s law, Farr & Nanus study

15

Page 14: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Non-Linear Productivity

• There is overwhelming evidence that, except for simple projects, development effort goes up exponentially with size, so this is probably wrong:

Effort = P x Size

• This might be closer to the mark:

Effort = A x M x SizeB

where A is a constant derived from historical data, and M is dependent on each project (effort multiplier), and B is dependent on the complexity of the project

16

Page 15: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Approach 1 - Discretize

17

Proceedings 5th Software Measurement European Forum, Milan 2008

129

It is evident that the “base productivity” can be often a value not very significant to

determine the final effort, but in any case you have to start by an initial value. The first effort

driver in order to calibrate the “base productivity” is the functional dimension of the projects.

Table 1 shows the “base productivity” for Java related to the functional dimension in FP:

with the growth of dimension, the productivity decreases by two points; there are five classes

of projects. The productivity is expressed in fp/person month.

Table 1

Applying these values to the dimension in FP of a project we obtain a base work effort of

the software development project in Month/person or in Days/person (usually we consider a

month of 21 days).

This effort should cover all the activities concerning the software project according to the

RUP (Rational Unified Process) disciplines.

For example if there is a project valued 574 FP, from the table above we obtain a “base

productivity” of 16 fp/month and thus a “base work effort” of 35.87 Month/person(574/16) or

753 days/person.

In the case of EMP it is to consider not only the functional dimension of EMP (in Nesma

FP) but also the functional dimension of the application on which the maintenance will be

applied to for selecting the base productivity, (for example if we had an EMP for our projects

of 574 FP, we will choose a productivity of 16 fp/month, independently of the EMP Nesma

functional dimension in FP).

4. The “Productivity Factors”

Every project has its own characteristics, so it is clear that the range of productivity can be

very large! The most critical step in evaluating the effort of the project is to consider all the

factors that can influence the productivity. Through the Functional Requirements it is

possible to measure the functional dimension in Function Points.

The Technical and Quality requirements should give us information about the factors that

influence productivity. But how can we measure them? And, above all, which are these

factors?

In 2003 in CSI Piemonte was done an investigation to find them and to evaluate the

impact that they have on productivity (growing or decreasing it).

To determine the impact of productivity factors it was chosen an approach like COCOMO [6]

(the productivity factor is the multiplication of several cost drivers).

Cf. • www.ISBSG.org • Capers Jones database

Source: Function Point: how to transform them in effort? by Gianfranco Lanza

http://www.dpo.it/smef2008/papers/smef08_proc_203_lanza.pdf

Page 16: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Quick Exercise

• An application for managing construction equipment rentals has an estimated size of 400 FPs

• How much effort will it take?

18

Page 17: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Approach 2 – Interpolate

Nonlinear relationship when exponent > 1

0

2 0 0 0

4 0 0 0

6 0 0 0

8 0 0 0

1 0 0 0 0

1 2 0 0 0

1 4 0 0 0

1 6 0 0 0

0 5 0 0 1 0 0 0

K S L O C

Pe

rso

n M

on

ths B = 1 .2 2 6

B = 1 .0 0

B = 0 .9 1

20

Page 18: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

COCOMO - Constructive Cost Model

• Developed at USC (Barry Boehm et al.) based on a database of 63-161 projects

• First version of COCOMO (now COCOMO 81) Most recent version COCOMO II.2000

• Based on statistical model building (fitting actual data to equation)

• Not very accurate with default database - should be calibrated based on company-specific historical data

21

Page 19: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

COCOMO II Designed for an iterative development method

(MBASE)

More refined set of cost drivers (6-17)

Multiple exponential scale drivers:

PM = a x Sizeb x Π EMi (i = 1 to 6 or 17)

where a = 2.94

b = 0.91 + 0.01 x Σ SFj (j = 1 to 5)

22

Page 20: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

COCOMO II models • COCOMO II incorporates a range of sub-models that

produce increasingly detailed software estimates.

• Sub-models in COCOMO II:

• Early design model. Used when requirements are available but design has not yet started (6 cost drivers).

• Post-architecture model. Used once the system architecture has been designed and more information about the system is available (17 cost drivers).

• Application composition model. Used when software is composed from existing parts.

• Reuse model. Used to compute the effort of integrating reusable components.

From I. Sommerville’s Software Engineering 23

Page 21: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Use of COCOMO II models

From I. Sommerville’s Software Engineering 24

Page 22: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Cost Factors Significant factors of development cost:

scale drivers are sources of exponential effort variation

cost drivers are sources of linear effort variation

product, platform, personnel and project attributes

effort multipliers associated with cost driver ratings

Defined to be as objective as possible

Each factor is rated between very low and very high per rating guidelines

relevant effort multipliers adjust the cost up or down

25

Page 23: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Scale Drivers Precedentedness (PREC)

Degree to which system is new/past experience applies

Development Flexibility (FLEX)

Need to conform with specified requirements

Architecture/Risk Resolution (RESL)

Degree of design thoroughness and risk elimination

Team Cohesion (TEAM)

Need to synchronize stakeholders and minimize conflict

Process Maturity (PMAT)

SEI CMM process maturity rating 26

Page 24: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Scale Factors

Sum scale factors SFi across all of the factors to determine a scale exponent, B, using B = .91 + .01 S SFi

Scale Factors (Wi) Very Low Low Nominal High Very High Extra High

Precedentedness(PREC)

thoroughlyunprecedented

largelyunprecedented

somewhatunprecedented

generallyfamiliar

largelyfamiliar

throughlyfamiliar

DevelopmentFlexibility (FLEX)

rigorous occasionalrelaxation

somerelaxation

generalconformity

someconformity

generalgoals

Architecture/RiskResolution (RESL)*

little (20%) some (40%) often (60%) generally(75%)

mostly(90%)

full (100%)

Team Cohesion(TEAM)

very difficultinteractions

some difficultinteractions

basicallycooperativeinteractions

largelycooperative

highlycooperative

seamlessinteractions

Process Maturity(PMAT)

Weighted average of “Yes” answers to CMM Maturity Questionnaire

* % significant module interfaces specified, % significant risks eliminated

27

Page 25: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Precedentedness (PREC) and Development Flexibility (FLEX)

Feature Very Low Nominal / High Extra High

Precedentedness

Organizational understanding of productobjectives

General Considerable Thorough

Experience in working with related softwaresystems

Moderate Considerable Extensive

Concurrent development of associated newhardware and operational procedures

Extensive Moderate Some

Need for innovative data processingarchitectures, algorithms

Considerable Some Minimal

Development Flexibility

Need for software conformance with pre-established requirements

Full Considerable Basic

Need for software conformance withexternal interface specifications

Full Considerable Basic

Premium on early completion High Medium Low

28

Page 26: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Architecture / Risk Resolution (RESL) Use a subjective weighted average of:

Characteristic Very Low Low Nominal High Very High Extra High

Risk Management Plan identifies all criticalrisk items, establishes milestones forresolving them by PDR.

None Little Some Generally Mostly Fully

Schedule, budget, and internal milestonesthrough PDR compatible with RiskManagement Plan

None Little Some Generally Mostly Fully

Percent of development schedule devotedto establishing architecture, given generalproduct objectives

5 10 17 25 33 40

Percent of required top software architectsavailable to project

20 40 60 80 100 120

Tool support available for resolving riskitems, developing and verifyingarchitectural specs

None Little Some Good Strong Full

Level of uncertainty in Key architecturedrivers: mission, user interface, COTS,hardware, technology, performance.

Extreme Significant Considerable Some Little Very Little

Number and criticality of risk items > 10Critical

5-10Critical

2-4Critical

1Critical

> 5 Non-Critical

< 5 Non-Critical

29

Page 27: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Team Cohesion (TEAM) Use a subjective weighted average of the

characteristics to account for project turbulence and entropy due to difficulties in synchronizing the project's stakeholders.

Stakeholders include users, customers, developers, maintainers, interfacers, and others

Characteristic Very Low Low Nominal High Very High Extra High

Consistency of stakeholderobjectives and cultures

Little Some Basic Considerable Strong Full

Ability, willingness of stakeholders toaccommodate other stakeholders'objectives

Little Some Basic Considerable Strong Full

Experience of stakeholders inoperating as a team

None Little Little Basic Considerable Extensive

Stakeholder teambuilding to achieveshared vision and commitments

None Little Little Basic Considerable Extensive

30

Page 28: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Process Maturity (PMAT) Two methods based on the Software Engineering

Institute's Capability Maturity Model (CMM)

Method 1: Overall Maturity Level (CMM Level 1 through 5)

Method 2: Key Process Areas (see next slide)

31

Page 29: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Key Process Areas Decide the percentage of compliance for each of

the KPAs as determined by a judgment-based averaging across the goals for all 18 Key Process Areas.

Key Process Areas Almost Always(>90%)

Frequently(60-90%)

About Half(40-60%)

Occasionally(10-40%)

Rarely If Ever(<10%)

Does NotApply

Don'tKnow

1 RequirementsManagement

2 Software ProjectPlanning

3 Software ProjectTracking and Oversight

4 Software SubcontractManagement

(See COCOMO II Model Definition Manual for remaining details)

32

Page 30: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

A company takes on a project in a new domain. The client has not defined the process to be used and has not allowed time for risk analysis. The company has a CMM level 2 rating.

Precedenteness - new project – 0.4

Development flexibility - no client involvement - Very high – 0.1

Architecture/risk resolution - No risk analysis - V. Low – 0.5

Team cohesion - new team – nominal – 0.3

Process maturity - some control – nominal – 0.3

Scale factor = 1.17.

Example of Scale Factors

From I. Sommerville’s Software Engineering 33

Page 31: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Cost Drivers (Post-Architectural Model)

Product Factors

Reliability (RELY)

Data (DATA)

Complexity (CPLX)

Reusability (RUSE)

Documentation (DOCU)

Platform Factors

Time constraint (TIME)

Storage constraint (STOR)

Platform volatility (PVOL)

Personnel factors

Analyst capability (ACAP)

Program capability (PCAP)

Applications experience (APEX)

Platform experience (PLEX)

Language and tool experience (LTEX)

Personnel continuity (PCON)

Project Factors

Software tools (TOOL)

Multisite development (SITE)

Required schedule (SCED) 34

Page 32: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Example Cost Driver - Required Software Reliability (RELY)

Measures the extent to which the software must perform its intended function over a period of time.

Ask: what is the effect of a software failure?

Very Low Low Nominal High Very High Extra High

RELY slight

inconvenience

low, easily

recoverable

losses

moderate,

easily

recoverable

losses

high financial

loss

risk to human

life

35

Page 33: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Example Effort Multiplier Values for RELY

Very Low Low High Very High

Slight Inconvenience

Low, Easily Recoverable

Losses

High Financial Loss

Risk to Human Life

1.15

0.75

0.88

1.39

1.0

Moderate, Easily Recoverable Losses

Nominal

E.g. a highly reliable system costs 39% more than a nominally reliable system 1.39/1.0=1.39)

or a highly reliable system costs 85% more than a very low reliability system (1.39/.75=1.85)

36

Page 34: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

COCOMO II – Schedule Estimation

D = c x Ed x SCED%/100

where c = 3.67

d = 0.33 + 0.2 x [b - 1.01]

SCED% = percentage of required schedule compression

37

Page 35: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Nominal versus Optimal Time

38

Page 36: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Cocomo II Exercise

• See separate handout

• Use the following resources:

• COCOMO II Data Sheet

• Model Definition Manual

• Online cost Cocomo II calculator (see list of Cocomo Resources under the course’s “Readings” page)

39

Page 37: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Final Word of Caution

COCOMO and similar models are just MODELS

COCOMO comes calibrated by a set of projects that might not reflect a particular project’s context

Should be combined with expert assessment – for example, combine Cocomo with estimates based on the Work Breakdown Structures

Cost estimation should be followed by continuous cost control (more on this next week)

41

Page 38: MTAT.03.244 Software Economics - ut · MTAT.03.244 Software Economics Software Cost Estimation Dietmar Pfahl (based on materials by Marlon Dumas) 1 . For Discussion • It is hopeless

Re: Homework 3

Effort and schedule estimation for your system can be done using one of the following methods:

• Using Cocomo II (post-architectural).

• Explain your choice of cost and scale drivers

• Add a comment after your estimate to discuss how credible you find the estimate given by Cocomo

• Wideband Delphi using the method in http://www.stellman-greene.com/images/stories/LectureNotes/03%20estimation.pdf

• Or planning poker over each individual feature

• Provide table of feature and estimate in person-days 42