MTA Maryland’s Experience with a Brown Field Installation

31
November 29, 2018 CBTC Case Study – MTA Maryland’s Experience with a Brown Field Installation 1

Transcript of MTA Maryland’s Experience with a Brown Field Installation

Page 1: MTA Maryland’s Experience with a Brown Field Installation

November 29, 2018

CBTC Case Study –MTA Maryland’s Experience with a Brown Field Installation

1

Page 2: MTA Maryland’s Experience with a Brown Field Installation

AGENDA

♦ Overview of MTA Metro♦ Project Background♦ Project Overview♦ HAB Solution♦ Challenges and Solutions♦ Questions

2

Page 3: MTA Maryland’s Experience with a Brown Field Installation

MTA METRO AT A GLANCE

♦ Grade separated♦ 11th Largest in the US – Nearly 15 Million Passenger

Trips Annually♦ 15.5 miles long

• Owings Mills to Johns Hopkins Hospital♦ Dedicated inbound and outbound track♦ Single Maintenance and Storage Yard♦ 14 mainline stations (6 above ground/ 8 underground)♦ Powered by 750 VDC Third Rail♦ Current Fleet of 100 Vehicles and Train Control

System are 35 years old• Original Railcars – Budd Company• Original Train Control – Ansaldo Breda

♦ Headway• 8 Minutes Peak• 10 to 15 Minutes Off-peak

Page 4: MTA Maryland’s Experience with a Brown Field Installation

METRO HISTORY

4

• Phase 1 Section A (Northwest Line): was completed in November 1983 and it extends northwest from downtown Baltimore. It consists of a 5.55-mile underground section and a 2-mile aerial section.

• Phase 2 Section B (Northwest Line extension): was completed in July of 1987 and operates at grade level. It extends for 6 miles.

• Phase 3 Section C (Northeast Line): was completed in 1996. It is 1.5 miles long and it operates Northeast underground from the city center.

Page 5: MTA Maryland’s Experience with a Brown Field Installation

Train Control Project Overview♦ Data Communications System (DCS):

• Fiber Optic Cable System (FOCS)• Ground Based Network (GBN)• Wireless Communication System (WCS)

♦ Solid State Interlockings with existing signals, switches, and snow melters

♦ CBTC – Zone Controllers and Carborne Controllers

♦ ATS: Hardware/software and interfaces to SCADA, “Next Train Arrival” messaging, and Google Transit

♦ Axle counters♦ Yard Test Track♦ Removal of existing track circuits

Page 6: MTA Maryland’s Experience with a Brown Field Installation

Phased Installation for Brownfield Success

P2SSI Installation – Continue

revenue operation with existing fleet

P3 Install and commission backup/primary ATS

P1 Install and Commission new DCS P4

Install and commission CBTC wayside and room equipment in

segments

P5Delivery and dynamic testing of

new railcars. New cars increase, old cars decrease

P6Install new wayside cables and

remove AF track circuits in sections

All work will begin at OM and move towards JH

Page 7: MTA Maryland’s Experience with a Brown Field Installation

Migration/Cutover Planning

♦ Phase 1 – DCS (Fiber, GBN, WCS)• All fiber and network hardware installed. • Wireless access points installed• No cutovers during Phase 1• Utilize existing conduit as much as possible

o Remove unused cables – highway encroachment, sound phoneo Move wayside cable replacement from Phase 2 to Phase 6 – allowing conduits

to be freed later in the project.

Page 8: MTA Maryland’s Experience with a Brown Field Installation

Migration/Cutover Planning – Phase 1 DCS

Page 9: MTA Maryland’s Experience with a Brown Field Installation

Migration/Cutover Planning – Phase 1 DCS

♦ In order to progress work to Phase 2 before Phase 1 is complete, a portion of the North Ring will be closed as the first SSI locations go into service.

Page 10: MTA Maryland’s Experience with a Brown Field Installation

Migration/Cutover Planning

♦ Phase 2 – SSI Installation OM to JH• Microlok installation begins at OM working towards JH. • Testing will be conducted during non-revenue service from Midnight to

4AM. • Over and Back (Existing to New) is accomplished by removing and

replacing plug couplers into defined mating connections• Existing fleet is in operation with Microlok control of all existing track circuit

equipment. • Requires interface to existing train management system and existing track

circuits. Existing ATS provides control and monitoring during Phase 2.• Locations will be released for revenue service once installed, tested, and

safety certified.

Page 11: MTA Maryland’s Experience with a Brown Field Installation

Existing Equipment

11

Page 12: MTA Maryland’s Experience with a Brown Field Installation

Phase 1 - DCS

12

Page 13: MTA Maryland’s Experience with a Brown Field Installation

Installation and Testing

13

Page 14: MTA Maryland’s Experience with a Brown Field Installation

Non-Revenue Operation

14

Page 15: MTA Maryland’s Experience with a Brown Field Installation

Safety Certified Revenue Service

15

Page 16: MTA Maryland’s Experience with a Brown Field Installation

Migration/Cutover Planning

♦ Phase 3 – Primary/Backup ATS• MTA has a Primary OCC and a Backup OCC, which also serves as a training

location. • Migration to the new ATS will take advantage of the existence of a BOCC by

installing, testing, and commissioning in that location first. Allowing system to be fully implemented and tested.

• BOCC will control and monitor the line while the new ATS equipment is installed and commissioned in the MOCC.

• Once the MOCC is tested and commissioned, the system will be entirely controlled and monitored by the new ATS.

• Requires interface to existing SCADA System. o Existing ATS will continue to serve to gather field I/O for MTA’s SCADA system. An

intermediate server with serve as data pass-through to the new ATS. This provides a clear demarcation of responsibility for the two system. SCADA will remain in service after the project is complete.

Page 17: MTA Maryland’s Experience with a Brown Field Installation

Migration/Cutover Planning

DCS Backbone B

DCS Backbone A

Main OCC LAN α & β to OCC Server Room

Color Laser Printer Pool

(x4)

MOCC (Metro Operation Control Centre) MOCC Server Room

Cabling to Backbone(existing Fiber Optic)

Cabling to MOCC(CAT6 & Fiber Optic)

ATS Server MTASYS001

SAN

Patch Panel

PWR & GND

ATS System

KVM & Console Switch

PWR & GND

ATS Rack 001

DB ServerMTAHST001

Interfaces

SCADA

CIS

Google Transit

CBTC System

Frontam

Zone Controller

Twenty Remote Workstation Locations(exact locations, and QTY. TBD via RFI)

24" 24" 24"

ATS WorkstationMTACWS001

24" 24" 24"

24" 24" 24"

ATS WorkstationMTACWS002

24" 24" 24"

24" 24" 24"

ATS WorkstationMTACWS003

24" 24" 24"

ATS WorkstationMTACWS###

(x20)

24" 24" 24"

Typical Field + Depot + Test Track (x11)

Interfaces

MLK

WirelessATS LATS wrkstATS LATS α

L3 Switch αPatch Panel

PWR & GND

ATS System

L3 Switch β

PWR & GND

ATS LATS β

KVM Switch

DCS SW ADCS SW B

DCSsystem

Main BOCC LAN α & β to BOCC Server Room

Color Laser Printer Pool

(x4)

BOCC (Backup Operation Control Centre) Main Shop TC&C

ATS Server MTASYS101

SAN

Patch Panel

PWR & GND

ATS System

KVM & Console Switch

PWR & GND

ATS Rack 101

OVW ServerMTAOVW101

Interfaces

SCADA

CIS

Google Transit

CBTC System

Frontam

Zone Controller

24" 24" 24"

ATS WorkstationMTACWS101

24" 24" 24"

24" 24" 24"

ATS WorkstationMTACWS102

24" 24" 24"

24" 24" 24"

ATS WorkstationMTACWS103

24" 24" 24"

DCSsystem

MIMIC Panel(1x1 matrix of 55” Panels)

Matrox Extio Receiver (1)

Cabling to BOCC(CAT6 & Fiber Optic)

SCADA

DCS system

Cabling to Backbone(New Fiber Optic)

Provided by Installer

Cabling to Backbone(existing Fiber Optic)

Cabling to Backbone(New Fiber Optic)

Provided by Installer

12

Page 18: MTA Maryland’s Experience with a Brown Field Installation

Migration/Cutover Planning

♦ Phase 4 – CBTC Goes Into Service• Install and commission wayside and on-board CBTC for the Pilot Train (3

Married Pair Train)• Low speed testing can occur on the test track at Wabash Yard. Full-speed

testing will occur on the main-line• Mixed mode operation begins. Non-CBTC Trains will operate with fixed

block. CBTC Trains will utilize MAL• Phase 4 culminates in revenue service of the

o SSIo ZCo Existing cab codeso New ATS

Page 19: MTA Maryland’s Experience with a Brown Field Installation

Migration/Cutover Planning

Page 20: MTA Maryland’s Experience with a Brown Field Installation

Migration/Cutover Planning♦ Phase 5 – Installation and dynamic testing of all new car

equipment. New cars increase, old cars decrease• Mixed mode operation continues.

Page 21: MTA Maryland’s Experience with a Brown Field Installation

Migration/Cutover Planning

♦ Phase 6 – Install new wayside cables and Remove AF track circuits in sections.

• All new vehicles will be in service under CBTC Control. • Axle counters will be installed.• Wayside cables will be installed as track circuit cables are

removed and conduits are made available.

Page 22: MTA Maryland’s Experience with a Brown Field Installation

Hitachi Ansaldo Baltimore Offering

Page 23: MTA Maryland’s Experience with a Brown Field Installation

Challenges and Solutions

♦ Space Limitations♦ Infrastructure Limitations♦ On-going Maintenance and Repairs♦ Other Projects♦ Mixed Fleet Operation♦ Training and Existing Skillsets

Page 24: MTA Maryland’s Experience with a Brown Field Installation

Space Limitations

24

Page 25: MTA Maryland’s Experience with a Brown Field Installation

Space Limitations

25

Page 26: MTA Maryland’s Experience with a Brown Field Installation

Space Limitations

26

Page 27: MTA Maryland’s Experience with a Brown Field Installation

Infrastructure Limitations

27

Page 28: MTA Maryland’s Experience with a Brown Field Installation

On-going Maintenance/Repairs and Other Projects

Maintenance/Repairs Project WorkQ3/4 2018 – 3rd Rail Heater Controls Conduit Identification/Space LiberationQ4 2018 – Tie and Rail Repairs Inner Duct InstallationQ1 2019 – JH Interlocking Replacement DCS Fiber InstallationQ2 2019 – Asbestos Removal SSI InstallationsQ1 2020 – State Center/Charles Center Interlocking Replacement – Permanent Magnet Motors

SC/CC SSI CompleteCBTC Installation

Q1 2021 – Rogers Avenue, Reisterstown Plaza, Northwest Yard Interlockings

Continued mixed-mode operation. Other projects must consider SSI rather than Relays

• Coordinate early and often• Flexibility – Permanent Magnet Motors• Plan for changes

Page 29: MTA Maryland’s Experience with a Brown Field Installation

Mixed Fleet Operation

Phased Migration Maintain track Circuits while implementing CBTC

Develop Operational Scenarios

Interface to existing TTM followed by migration to new ATS

Page 30: MTA Maryland’s Experience with a Brown Field Installation

Training

Training Planning with Contractor

Identify new skillsets required

Early work with Union

Page 31: MTA Maryland’s Experience with a Brown Field Installation

Vernon G. Hartsock, PMPDeputy Chief/Chief Engineer

Maryland Transit AdministrationOffice of Engineering & Construction6 Saint Paul Street, Room 736, Baltimore MD 21202Office: 410-767-3323 Fax: [email protected]

QUESTIONS