Transcript of MSPC12 - 8 Billion Reasons... why ARM chose Project Server 2010
8 Billion Reasons…Why ARM Chose Project Server 2010
Philip Stanbury-JonesPMO DirectorARM
0
PresenterPhilip Stanbury-Jones – PMO Director
Processor IPPhysical IPSW Dev Tools
The world’s leading semiconductor IP
company
The Architecture for the Digital World®
Why ARM chose Project Server 2010 Some of the stuff we think is cool
Inside view of ARM’s project
process
Where we were & the problems
we had
Checklists save lives - and projects
Proceed at risk, report reality
Flexible, self defining, improving
process
The deciding factors
Insight into ARM’s
implementation
Slicing & dicing the enterprise
Integrated real-time reporting
data
Uncertainty Modelling
Final thoughts on deploying EPM
Agenda
Why ARM chose Project Server 2010
Where we were & the problems we had Project Management methodology established over 15
years
Growing business reliant on a diverse set of bespoke & ageing systems
Needed a solution that could deliver A scalable and maintainable PMIS platform Enterprise wide consistency, flexibility, reporting & analysis Accessibility for a diverse client computing landscape At least the features provided by the current system, integrated in
one place
Phase 1 Phase next…
1-5 year resource planning Scenario based modelling Product lifecycle & analysis Enhanced customer &
sales integration HR planning integration Process visualization User configurable
notifications & digests
MSP schedule Single role-based web
portal for all users Project & product approval Project status information Timesheets with PjM
approval Cross projects resource
management & capacity Deliverable & sales
integration
Document management Stage assessments &
design review system Risks, issues and change
management Minutes & actions Checklist improvement
management POC assessment for
finance Reporting & analysis
The ARM PMIS feature set
Checklists save lives and projects The problem of extreme complexity
“This has never been a problem before”
There are bad and good checklists
But we don’t like checklists!“The truly great are daring, innovative, they improvise, take risks. They do not have protocols and checklists”
Proceed at risk, report reality
Stage Entry ‘Assessments’ Checklist based Defined for an overall project type Assess risk of continuing Provide external governance & approval Empower the project manager to report reality and proceed at risk Report and manage misalignments
Initial Investigation
Develop & Test
Detailed Investigation
Trial Release
Proposal
The ARM Project Framework
Flexible, self defining, improving process
Initial Investigation
Develop & Test
Detailed Investigation
Trial Release
Proposal
The ARM Project Framework
Specification Review
Schedule Review
Block Review
Test Review
Trial Plan Review
....Suggestions
The deciding factors Needed a solution that could deliver
A scalable and maintainable PMIS platform Enterprise wide consistency, flexibility, reporting & analysis Accessibility for a diverse client computing landscape At least the features provided by the current system, integrated in
one place
Q4 2009 Many integrated EPM offerings in the marketplace Microsoft only option to support delivery of ARM’s specific
requirements CPS UK recommended MS partner
Some stuff we thinkis cool…
PWA standard site structure
Slicing & dicing the enterprise
Integrated real-time reporting data SharePoint & Project server combined in real-time data mart Weekly, monthly and event based snapshot data mart for
trending SAP employee, product, contract and customer ETL to data
mart
Data exposed through SSRS web parts for the web application screens Business Objects universes Pre-built Excel sheets provided centrally by the PMO
Integrated real-time reporting data
Integrated real time reporting
Excel ad-hoc analysis
Modelling Schedule UncertaintyUsing Microsoft Project 2010
demo
And finally…
Some takeaways Integrating Project Server & SharePoint 2010 provides a
platform that has huge potential to meet diverse business requirements
Reporting of consistent and accessible data is key to adoption and benefits realisation
ARM current status first 800 users live, across 5 locationsAdditional 1000 to take live during 2012
You can find out more about the CPS Technical Implementation from session PC324
And finally....
What we thought we were attacking
Go-LiveGo-Live
Post Go-Live
What we were really attacking
www.msprojectconference.com
Your feedback is very important to us! You can fill out session evaluations by logging into MyPC on your laptop or mobile device
evaluation prizes daily
Should you win an evaluation prize, you may claim it at the Registration Desk on Level 3
MYPCfill out evaluations & win prizes!
© 2012 Microsoft Corporation. All rights reserved. Microsoft, Windows, Windows Vista and other product names are or may be registered trademarks and/or trademarks in the U.S. and/or other countries.The information herein is for informational purposes only and represents the current view of Microsoft Corporation as of the date of this presentation. Because Microsoft must respond to changing market conditions, it should not be interpreted
to be a commitment on the part of Microsoft, and Microsoft cannot guarantee the accuracy of any information provided after the date of this presentation. MICROSOFT MAKES NO WARRANTIES, EXPRESS, IMPLIED OR STATUTORY, AS TO THE INFORMATION IN THIS PRESENTATION.