MSD II Week 6 UpdateP13265: Motorcycle Safety Lighting and Portable Electronics Charging System
![Page 2: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/2.jpg)
Mike: Action Items Status• Lens Covers
o Incompleteo Still waiting on shell
• Bike Wiring Harness/ Tx Boxo In Progress (almost complete)o Test fit on bike, confirmed fit w/no permanent mods.
• Wireless XBee Testo Completeo Captured waveforms from bike for all light sources
• Assist Tyler with Shello In Progress
![Page 3: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/3.jpg)
Mike: Action Items Status
![Page 4: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/4.jpg)
Mike: Next Steps for Week 7
• Finish board population w/TJ ~5 hrs• Edit/ complete Tech Report ~ 10 Hours• Assist Tyler with Shell~ 10 Hours• Begin lens covers? ~5 hrs
![Page 5: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/5.jpg)
Tyler: Action Items Status
• Finish New Moldo In Progresso More, various setbacks, near completion
• Shell Assemblyo Incomplete:o Pending completion of new shell
• Poster Worko Incomplete:o All time this week was dedicated to getting the mold
done.
![Page 6: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/6.jpg)
Tyler: Next Steps for Week 7
• Shell/Backpack Assembly ~ 15 Hours
• Tech Paper ~ 4 Hours
• Complete Assembly Plan ~ 4 Hourso Will be completed as backpack is assembled
• Poster Work ~ 6 Hours
![Page 7: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/7.jpg)
Ben: Action Items Status• Electronics box
o Finished but must be narrowed before gluing
• Quick Connecto Testing was performed this weekend, with the length of the male end
confirmed (along with the mounting of the female end).
![Page 8: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/8.jpg)
Ben: Next Steps for Week 7
• Reduce box width- 5 hourso Must reduce the width of the top piece, bottom
piece, both short sides, and redrill top in new corners
• Install standoffs- ~2 hourso Placement of all standoffs must be precise
• Tech papero I will write my section for Friday
![Page 9: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/9.jpg)
Eric: Action Item Status
• MSP430 Developmento Incomplete, In Progress, Complete:o Explain
• Board Build and Testingo Incomplete, In Progress, Complete:o Explain
![Page 10: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/10.jpg)
Eric: Next Steps for Week 7
• NS #1 ~ # Hourso Explain
• NS #2 ~ # Hourso Explain
• NS #3 ~ # Hourso Explain
![Page 11: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/11.jpg)
TJ: Action Items Status
• Populate PCBso In Progress:o Should have adapters today and will complete final
rework Friday afternoon
• Test XBee's in Lab and on Bikeo In Progress:o Dev Kit issues resolved with current limiting resistorso Bike signals captures and will be replicated in lab
• EDGE Updateo In Progresso Site cleanup and more formatting additions
![Page 12: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/12.jpg)
TJ: Next Steps for Week 7• Populate and Debug PCBs ~ 10 Hours
o Finish all rework and go through Test Plan
• XBee Lab Test ~ 2 Hourso Replicate motorcycle signals and ensure correct
signal transmission
• Assemble Tech Paper Rough Draft ~ 5 Hourso Put together segments and add additional
information
![Page 13: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/13.jpg)
Killian: Action Items Status
• Refine Sketcheso Completeo Sketches, done, scanned into photoshop and started
to apply gradient. Initial linework for illustrator renderings has begun, need to group sections and start to apply color/gradients
• Backpack Assemblyo In progresso Cut out a bunch of the cross sections, getting control
panel 3-D printed
• Poster Layouto In progresso Discussed gameplan with Tyler and Mike
![Page 14: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/14.jpg)
![Page 15: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/15.jpg)
https://www.facebook.com/photo.php?v=10201084405291756&ref=notif¬if_t=video_tag
![Page 16: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/16.jpg)
Killian: Next Steps for Week 7
• Complete Photoshop and Illustrator Renderings ~ 6 Hourso Just need to finish applying everything and possibly
do a few other sketches of inserting items (phone, laptop, tablet)
• Assist with Assembly ~ 7 Hourso Help with shell shaping and vacuum forming,
painting control panel
• Draw up Outlines of Poster, begin inserting text and graphics ~ 3 Hourso Hope to have a pretty set layout by next week
![Page 17: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/17.jpg)
Major Week 7 Action Items Mike - Complete Tx Box Tyler - Backpack Assembly Ben - Finish Electronics box, quick connect Eric - TJ - Populate and Debug PCBs Killian - Renderings and Assembly
![Page 18: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/18.jpg)
Lessons Learned• Mike
• Tylero Make sure to double check other peoples work
thoroughly if your work is dependent on theirs. It's not okay to assume the thought of every problem that could arise.
• Beno Double check offset calculations
![Page 19: MSD II Week 6 Update](https://reader035.fdocuments.in/reader035/viewer/2022062813/5681662a550346895dd98cb8/html5/thumbnails/19.jpg)
Lessons Learned cont.
• Eric
• TJo SMT population takes a long time and first revisions
of boards often need to be reworked and modified for prototyping applications
• Killiano You can print two items at once with 3-D printers, 3-
D printing quality is very limited in the innovation center