MS for Tank Installation_R1

6
Document Title METHOD STATEMENT FOR FRP TANK INSTALLATION WORKS Document No. KTS/CLIENT/MS-008 Revision History Rev Description Date Prepared by 00 Issue for Review and Approval 20/02/2014 01 Issue for Review and Approval -Added sterilization of Pipe 08/10/2014 1. SCOPE & DESCRIPTION OF WORK This method statement applicable for all FRP tank installation works within CLIENT project. It is set to establish the steps for carrying out FRP tank to ensure conformance to contract and regulatory requirements. 1.1. Responsibility

description

Method Statement for tank installation, sterilization and cleaning of the water tank, including health and safety measure required during installation

Transcript of MS for Tank Installation_R1

  • Document Title METHOD STATEMENT FOR FRP TANK INSTALLATION WORKS

    Document No. KTS/CLIENT/MS-008

    Revision History

    Rev Description Date Prepared by

    00 Issue for Review and Approval 20/02/2014

    01 Issue for Review and Approval

    -Added sterilization of Pipe 08/10/2014

    1. SCOPE & DESCRIPTION OF WORK

    This method statement applicable for all FRP tank installation works within CLIENT project. It is set to

    establish the steps for carrying out FRP tank to ensure conformance to contract and regulatory

    requirements.

    1.1. Responsibility

  • METHOD STATEMENT FOR FRP TANK INSTALLATION WORKS

    Prepared by: KIM TECHNOLOGY & SYSTEMS ENGINEERING PTE LTD Page 2 Revision: 01 Date: 08 October 2014

    It will be the responsibility of Project Manager to ensure all the necessary safety precautions are set in place

    prior to carrying out the work. Tank installation shall be done by authorized, trained and experienced crew in

    the supervision of Site Supervisors / Engineers.

    2. PRELIMINARIES

    All tank materials shall be inspected, accepted and shall conform to the approved material

    specification and size or capacity. Refer below:

    Tank Name Block / Level Size Effective Capacity

    NEWater Make Up Tank D / Lower 1st 23m x 6m x 2mH 180cu.m

    Domestic Water Transfer Tank D / Lower 1st 4m x 5m x 2mH 30cu.m

    Domestic Water Storage Tank A / 6th Storey 4m x 5m x 2mH 27cu.m

    Domestic Water Storage Tank B / Roof 3m x 3m x 3mH 16cu.m

    Domestic Water Storage Tank C / Roof 5m x 4m x 3mH 47cu.m

    Tank shall be constructed in accordance to the approved drawing.

    Before the commencement of any cleaning and sterilization work, the licensed water service

    plumber shall notify the Authority on prescribed forms of the work to be carried out.

    All statutory safety requirements as well as other necessary and relevant safety measures shall be

    complied with at all times to ensure that it is safe to enter the tank during cleaning

    3. WORK PROCEDURE

    1.1. Installation Procedure

    Mark the location of the hold down bolts to be drilled into the RC stumps

    Check that the holes drilled into the RC stumps are correct and vertically positioned. Insert drop in

    anchors

    Lift and install the steel skid base in place. Ensure that the supports are leveled and spaced

    accordingly prior to tank assembly

    Identify and mark the location of flange outlets

    Core a hole for the openings

  • METHOD STATEMENT FOR FRP TANK INSTALLATION WORKS

    Prepared by: KIM TECHNOLOGY & SYSTEMS ENGINEERING PTE LTD Page 3 Revision: 01 Date: 08 October 2014

    Layout the bottom panels and the flanges downwards on the skid base.

    Assemble the bottom part of the tank first

    Use PVC foam sealant to stick on the adjoining flange of one panel

    Bring the two panels together

    Put the bolts to the flange holes and screw the nuts with washers

    Do not tighten yet, repeat the above procedure on the next panel until the bottom part is completed

    After the bottom part is completed, continue the same procedure to assemble the side panels in

    section of 5panels each up to the full height of tank

    PVC foam sealant to be put on the junction before putting on the cleats.

    For each cleat, fix the bolt inside the tank and screw on the nut with washers outside the tank and

    tighten.

    Connect the angle stays to the cleats as indicated in the assembly plan, but do not tighten until all

    the stays are in position.

    After all the plate stays have been assembled, tighten the bolts and nuts commencing with those in

    the bottom followed in turn by those on each side.

    Install the top panels including manhole access following the above steps

    Install the cat ladders

    Install its associated fittings such as the overflow pipes, air vents, nettings, tank manhole covers,

    etc and ancillary equipment

    Sample of Installed FRP GRP Tank

    1.2. Inspection & Cleaning Procedure

  • METHOD STATEMENT FOR FRP TANK INSTALLATION WORKS

    Prepared by: KIM TECHNOLOGY & SYSTEMS ENGINEERING PTE LTD Page 4 Revision: 01 Date: 08 October 2014

    Before the commencement of any cleaning and sterilization work, a joint inspection with CLIENT or

    its representative shall be present to check on the condition of the water storage tank (including its

    associated fittings such as the overflow pipes, air vents, nettings, tank manhole covers, etc and

    ancillary equipment).

    All remedial works to the tank, its associated fittings and ancillary equipment arising from the joint

    inspection shall be carried out before commencement of cleaning work.

    Adequate signboards shall be displayed to indicate that the water tanks are undergoing cleaning

    and sterilization.

    The water in the tank shall be used to around 150 to 200 mm above the bottom of the tank before

    the tank is isolated and the outlet pipes shut off.

    The external of the tank and the tank manhole covers shall be cleaned before the tank covers are

    opened.

    All tank manhole covers shall be opened to admit light and for ventilation and access. It shall be

    ensured that the tank is isolated and all outlet pipes are shut.

    All workers involved in the cleaning work must be certified by a medical doctor to be free from

    water-borne diseases.

    All workers involved in the cleaning work shall wash, clean and disinfect themselves thoroughly

    before entering the tank.

    All workers involved in the cleaning work must observe safety measures at all times and must be

    properly equipped with the necessary safety equipment and gear.

    Equipment and tools used shall not have sharp edges that may damage the inside of the tank.

    The equipment and tools shall be exclusively used for the cleaning of potable water tanks only and

    shall be disinfected before every use.

    To prevent sludge and sediments from entering the outlet pipes, all outlets of these pipes shall be

    covered. The sludge and sediments shall be placed in containers for disposal at authorized

    dumping grounds.

    The internal of the tank including the floors, walls, roof, internal of the tank manhole covers, etc

    shall then be cleaned using appropriate methods such as scrubbing, pressure jet, etc, Sediments

    and solids shall be collected in containers for disposal at authorized dumping grounds.

    The roof and sides of the tank walls above the overflow level shall be cleaned and disinfected too.

    Chlorine solution of 200 mg/litre shall be applied onto the internal surfaces of the roof and sides of

    the tank walls above the overflow level (by spraying or brushing) and left there for at least 30

    minutes after they have been cleaned and washed.

  • METHOD STATEMENT FOR FRP TANK INSTALLATION WORKS

    Prepared by: KIM TECHNOLOGY & SYSTEMS ENGINEERING PTE LTD Page 5 Revision: 01 Date: 08 October 2014

    The entire tank (including the roof and sides of the tank walls above the overflow level) shall be

    thoroughly washed and flushed until it is clean and free from dirt, solids, chemicals or other foreign

    matter which may affect the quality of water stored and supplied.

    1.3. Sterilization Procedure

    Once the tank has been cleaned and inspected, conduct sterilization to ensure the tank is capable

    of providing fresh potable water for human consumption.

    The sterilization of water storage tanks shall be undertaken by a licensed water service plumber.

    After cleaning, potable water is fed into the cleaned tank up to overflow level. Sterilizing chemical

    in solution form containing chlorine shall be gradually added while the tank is being filled to ensure

    thorough mixing. Safety procedure for the handling of such chemical must be observed at all

    times. Introduction of the sterilizing chemical into the tank in powder form is not allowed.

    The chemical concentration for sterilization of the tank shall be 50 mg/litre of free chlorine (i.e. 50

    ppm of free chlorine). Ordinary bleaching powder in solution form or sodium form or sodium

    hypochlorite solution may be used with equivalent concentration.

    While the water in the tank is being sterilized, all outlet pipes from the tank must be closed tight

    and no water shall be allowed to flow into these pipes as the water under sterilization may not be

    safe for human consumption.

    The sterilized water shall be kept in the tank for at least 24 hours. The water in the tank is then

    drained off completely through the wash out pipe and the tank refilled with potable water through

    the inlet pipe. It must be ensured that all outlet pipes are closed tight before re-filling the tank with

    potable water.

    Main and distribution pipes must also be sterilized while the tank is being soaked using the same

    concentration. Open the discharge valve and fill the pipe with chemical solution. Pipe must be filled

    until the remotest fitting. Once sterilized, drain the pipe and flush with potable water.

    Water samples shall then be taken from the tank sampling tap for bacteriological and chemical

    analyses at an accredited laboratory.

    Water samples shall be taken by a licensed water service plumber and should be sealed and

    marked by CLIENT or its representative and escorted to the accredited laboratory. Alternatively,

    the water samples may be taken by personnel from the accredited laboratory and sealed and

    marked by CLIENT or its representative. Water samples with broken seals shall be rejected.

    1

  • METHOD STATEMENT FOR FRP TANK INSTALLATION WORKS

    Prepared by: KIM TECHNOLOGY & SYSTEMS ENGINEERING PTE LTD Page 6 Revision: 01 Date: 08 October 2014

    The tank and the water shall only be put into use after satisfactory test reports are obtained from

    the accredited laboratory. All down feed and distributing pipes from the tank shall be thoroughly

    flushed until clean before water from the tank is put into use.

    If the test reports from the accredited laboratory are unsatisfactory, sterilization shall have to be

    carried out again.

    After cleaning and sterilization have been completed, a final joint inspection with the CLIENT or its

    representative to check on the condition of the water tank shall be carried out to ensure that all

    remedial works have been carried out and all tank openings (such as air vents, overflow and

    warning pipes, etc) have been properly screened to prevent birds, insects and other possible

    contaminants from entering the water tank.

    Upon completion of cleaning and sterilization work, the licensed water service plumber shall notify

    the authority on prescribed forms of the completion work accompanied with the laboratory water

    sample test reports within the time period stipulated by the Authority.

    4. HEALTH & SAFETY MEASURES

    SWMS for all activities to be established and it must be briefed to all workers who are involved in

    the task

    All necessary control measures should be taken as mentioned in the SWMS

    Workers must complete the minimum Work At Height foundation course by Authorized Training

    Provider accredited by MOM

    Workmen shall wear all appropriate safety Personnel Protective Equipment such as safety helmet,

    long sleeves, safety shoes, goggles, safety gloves etc. wherever required.

    Other than basic PPE, workers to wear full body harness when working at height.

    Sufficient lighting shall be provided at dark areas.

    Wind speed and direction to be considered when assembling the FRP panels at building roof tops.

    PTW shall be prepared and approved prior to start work.