Client : Saudi Arabian oil company
Contractor : Abdul Ali Al-Ajmi Company
Contract No. : 6600025881
Project : Site Preparation & Access roads; Shaybah NGL Recovery Project
1 Method Statement for Bituminous prime coat / Abdul Ali Al-Ajmi Co.
METHOD STATEMENT FOR BITUMINOUS PRIME COAT
Purpose
To detail the methods adopted with regard to application of Bituminous
Prime Coat on to the Aggregate Base Course layers, prior to laying of
asphaltic road construction layers.
Scope of work
i. Cleaning of surface to ABC layersii. Application of Bituminous Prime Coat
Reference Documents :
i. SAES-Q-006-Asphalt Concrete Paving.ii. Saudi Aramco Product Specifications
A-973 (Cutback Asphalt, MC-70)
A-974 (Cutback Asphalt, MC-250)
Inspection & Testing
i. Inspection & Testing of raw materials shall be done in accordance withSaudi Aramco Product Specifications A-973 (Cutback Asphalt, MC-70)
A-974 (Cutback Asphalt, MC-250), and application by site testing for
determination of spread rate.
ii. Prime coat shall be tested prior to applications and every 10,000 m.
-
8/13/2019 MS for Prime Coat
2/4
Client : Saudi Arabian oil company
Contractor : Abdul Ali Al-Ajmi Company
Contract No. : 6600025881
Project : Site Preparation & Access roads; Shaybah NGL Recovery Project
2 Method Statement for Bituminous prime coat / Abdul Ali Al-Ajmi Co.
Preparation
i. All materials shall be submitted to the SAPMTs Representative forapproval with supporting documentation, prior to them being used on
site. No material will be used on site prior to receiving the above-
mentioned approvals.
ii. Ensure that all the previous construction layers have been tested, andsubsequently approved, by the SAPMTs representative prior to the
application of any Bituminous Prime Coat.
iii. All surfaces to be primed shall be thoroughly cleaned from foreignmaterials by blowing compressed air or hand brushing, immediately
prior to the bituminous application, and in any case, not more than two
hours before.
iv. If the surface to receive the Bitumen Prime Coat is excessively dry, itshall be lightly dampen with water in advance of the application of
prime coat. If too much water is applied, and ponding occurs, then the
surface will be allowed to dry naturally before any bituminous
application will be done.
Method
i. All Bituminous Prime Coat material(MC-70) shall be applied bymeans of a purpose built mechanical spray tank distributor, or by
pressure hand spray. Application temperatures will be between 50 C
to 80 C and the rate of application will not be less than 0.65 litres/m
2
,and not more than 1.75 litres/m
2and will be checked regularly.At all
-
8/13/2019 MS for Prime Coat
3/4
Client : Saudi Arabian oil company
Contractor : Abdul Ali Al-Ajmi Company
Contract No. : 6600025881
Project : Site Preparation & Access roads; Shaybah NGL Recovery Project
3 Method Statement for Bituminous prime coat / Abdul Ali Al-Ajmi Co.
times, the temperature of the prime coat material shall be maintained
at least 10C below the flash point of the material
ii. Prior to the first application of the Bituminous Prime Coat on theproject, a rate of spray trial shall be done to determine the penetration,
and at each successive application, a test of the spray rate will be
undertaken to ensure that the distributor is correctly working and the
coverage rate is achieved.
iii. The prime coat shall be permitted to cure until the penetration intounderlying surface has been approved by Saudi Aramco
Representative, but at no time shall the curing period be less than 24
hours. Ponding will be avoided and shall be removed immediately if
occurring.
iv. Wherever there are adjacent items, such as concrete barriers, kerbstones, gutters, and the like, precautions shall be taken to prevent the
Bituminous Prime Coat from being sprayed on to them. Where
necessary, hand spraying of the Prime Coat will be done in localized
areas.
v. Bituminous primer will not be applied in adverse weather conditionssuch as sand storm and rain.
vi. Temporary barricades and warning signs shall be erected around areaof sprayed Bituminous Prime Coat to prevent any vehicle access on to
the newly primed surface. Any area where prime coat is disturbed
shall be repaired to the satisfaction of SAPMT's representative.
vii. Overlapping shall not be permitted at transverse joints and thick papershall be used to protect the previous application.
viii. The prime coat materials shall be applied to a width of 300 mmgreater on each side of the road than the specified width of thefinished surface
-
8/13/2019 MS for Prime Coat
4/4
Client : Saudi Arabian oil company
Contractor : Abdul Ali Al-Ajmi Company
Contract No. : 6600025881
Project : Site Preparation & Access roads; Shaybah NGL Recovery Project
4 Method Statement for Bituminous prime coat / Abdul Ali Al-Ajmi Co.
ix. Priming will not be permitted when surface is wet.x. After the cleaning operations, prior to the application of primer, a
joint inspection shall be conducted.
xi. A trial run shall be conducted prior to start the actual work.Equipment:
The following equipments are to be utilized for this purpose:
i. Air Compressorii. Bitumen Spray Tanker
Health & Safety:
All operations will be carried out in a safe working manner, and in each &
every case, the practices adopted shall be fully in accordance with Saudi
Aramco Construction Safety manual.