MS for Construction

33
Excavation of Unsuitable Material and Back Fill With Suitable Material EXCAVATION OF UNSUITABLE MATERIAL AND BACK FILL WITH SUITABLE MATERIAL OBJECTIVE To outline the work instruction by which the excavation of unsuitable material and backfill with suitable fill is carried out. REFERENCES MS ISO 9001 Clause 7.5.1 BS 1377 Method of test for soils for Civil Engineering purposes DEFINITIONS Unsuitable material shall include i) running silt, peat, logs, stumps, perishable or toxic material, slurry or mud, or ii) any material - Consisting of highly organic clay and silt. - Which is clay having a liquid limit exceeding 80% and / or a plasticity index exceeding 55%. - Which is susceptible to spontaneous ignition. - Which has a loss of weight greater than 2.5% on ignition. - Containing large amounts of roots, grass and other vegetable matter. iii) Suitable Material shall mean those materials other than the unsuitable materials defined above. MATERIALS All Suitable Material / Earth Fill must have record of Proctor Test and Engineer to verify the soil characteristic so as it will suit with the existing earth at the excavated area. HANDLING AND STORAGE OF MATERIALS Handling : - Transport for material shall be carried out by dump trucks or other suitable machinery. Storage : Suitable material / Earth fill must be protected and cover if not been use within 24 hours or as per environmental guideline. PLANT, MACHINERY AND EQUIPMENT Excavator, Lorries, Dozer, Compactor and Backpusher. PREPARATORY WORKS 1. Obtain relevant approved construction drawing from client / client’s representatives.

description

REFERENCES • MS ISO 9001 Clause 7.5.1• BS 1377 Method of test for soils for Civil Engineering purposes

Transcript of MS for Construction

  • Excavation of Unsuitable Material and Back Fill With Suitable Material

    EXCAVATION OF UNSUITABLE MATERIAL AND BACK FILL WITH SUITABLE

    MATERIAL

    OBJECTIVE

    To outline the work instruction by which the excavation of unsuitable material and backfill

    with suitable fill is carried out.

    REFERENCES

    MS ISO 9001 Clause 7.5.1

    BS 1377 Method of test for soils for Civil Engineering purposes

    DEFINITIONS

    Unsuitable material shall include

    i) running silt, peat, logs, stumps, perishable or toxic material, slurry or mud, or

    ii) any material

    - Consisting of highly organic clay and silt.

    - Which is clay having a liquid limit exceeding 80% and / or a plasticity index exceeding

    55%.

    - Which is susceptible to spontaneous ignition.

    - Which has a loss of weight greater than 2.5% on ignition.

    - Containing large amounts of roots, grass and other vegetable matter.

    iii) Suitable Material shall mean those materials other than the unsuitable materials defined

    above.

    MATERIALS

    All Suitable Material / Earth Fill must have record of Proctor Test and Engineer to verify the

    soil characteristic so as it will suit with the existing earth at the excavated area.

    HANDLING AND STORAGE OF MATERIALS

    Handling : - Transport for material shall be carried out by dump trucks or other suitable

    machinery.

    Storage : Suitable material / Earth fill must be protected and cover if not been use within 24

    hours or as per environmental guideline.

    PLANT, MACHINERY AND EQUIPMENT

    Excavator, Lorries, Dozer, Compactor and Backpusher.

    PREPARATORY WORKS

    1. Obtain relevant approved construction drawing from client / clients representatives.

  • 2. Set out the location and limits of work. 3. Carry out Soil Investigation to determine the depth of unsuitable material and submit

    the results to the client / clients representative for decision on depth of unsuitable

    material that needs to be replaced.

    4. Carry out survey to obtain original ground level and submit to client / clients representatives.

    5. Identify and obtain approval for disposal site.

    WORK METHODOLOGY

    1. Prepare access to the working area and plan for the lorry and plant movements. 2. Excavate the unsuitable material to the required depth as specified by the client /

    clients representative and dispose at approved disposal area.

    3. Transport, fill and spread suitable material in layers. The loose for each layer of fill shall be determined from the trial compaction.

    4. Repeat step 4 until the required level is achieved. Carry out necessary tests as per inspection & test plans :

    o Compaction Trials : The BS 1377 Compaction test (4.5 kg rammer method)

    shall be used in determining the moisture contest versus density relation of

    soil.

    o Degree of compaction : The whole of the embankment below the top 300mm

    of the subgrade shall be compacted to not less than 90% (for cohesive

    material) or 95% (for cohesionless material) of the maximum dry density

    determined in the BS 1377 Compaction test (4.5 kg rammer method)

    o Field Density Testing : Field density tests on each layer of compacted earth

    fill shall be carried out using sand replacement method in accordance with BS

    1377.

    o Moisture control : - Each layer of earth fill shall be processed as necessary to

    bring its moisture content to a uniform level throughout the material, suitable

    for compaction. The Optimum moisture content as determined by BS 1377

    compaction test (4.5 kg rammer method) shall be used as a guide in

    determining the proper moisture content at which each soil type shall be

    compacted.

    5. Submit request for inspection form for joint inspection and joint measurement with client / clients representative using Earthwork Inspection checklist.

    6. Request client / clients representative to sign on checklists and maintain all inspection / approval records as per Project Filing Index.

    7. Carry out computation and submit for claim.

  • Hydroseeding Mix and Method Of Application

    HYDROSEEDING MIX & METHOD OF APPLICATION

    (CAPACITY OF HYDROSEEDER 1, 000 liters)

    HYDROSEEDING MIX

    1. Pump water into hydroseeder to level. 2. Free gear and start engine. 3. Put in mulch (if paper mulch is used 15 to 20 kg dry weight is recommended) 4. Next add in 30 kg Soil Tackifier (R1187) 5. Put in 8 to 10 kg grass seeds. You may add millet if you wish for fast establishment of

    greens/ vegitation.

    6. Add one bag (40-50 kg) of Bio-Super 1 fertilizer with the mixture. 7. Finally top up with water.

    METHOD OF APPLICATION

    Before engaging the gear, the person who will do the spraying must hold tight the

    nozzle and have firm footing on stable ground as he will expect a strong back-kick the

    moment the slurry shoots out of the nozzle.

    Do not shoot the slurry directly to the soil surface. Instead, it should be done in the

    form of raindrops in a uniform pattern. Ensure even coverage of slurry on soil surface.

    One machine load with proper application can cover approximately 600 to 700 m2.

    Watering (also in the form of raindrops) on the hydroseeded area can start

    immediately the next day and must be continued daily in the initial stage to ensure

    speedy germination and growth. Light watering will not help much due to our hot

    climatic condition. Therefore, sufficient and proper watering must be done ensuring

    water seep into the soil yet avoiding overflow of water on the soil surface.

    NOTE: Hydroseeding shall never be applied during, before or immediately following

    rainfall. Avoid application in high winds. Machines and tools should be flushed and clean

    with water immediately after use. All moving parts should be oiled and greased regularly.

  • Method Statement For Anti Termite Work

    METHOD STATEMENT FOR ANTI TERMITE

    1. Scope of Work

    a) Main contractor shall notify pest control operator 24 hours in advance that anticipates concrete

    casting into the area to be treated.

    b) Before area treated, Main Contractor shall ensure that all loose timber, wood shaving, loose

    containing materials be removed from the said allocation area.

    c) Pest control operator shall applied Dynamite EC or Termigard 38.7EC (or any other applicable /

    approve with Termicide 38.7 EC) chemical onto entire ground floor slab area prior to concrete

    casting.

    d) The area surrounding all sides of the column stumps extending to 1 meter below the soil surfaces

    of to the top of pile cap.

    e) Pest control operator shall applied 2 meter all round the building prior to concrete of the apron

    area.

    2. Chemical Preparation and Application

    Pest control operator shall mixed the solution at site in the present of Site Supervisor/ Consultant

    according to 1:40 as manufacturers specification proposed rate and to apply the mixed solution

    onto the indicated allocation area by 4-5 liter to 1m2.

    Before soil treatment will be carried out, the ground water table will be checked. Excavation of trial

    holes of more than 0.5 meters deep measured from the level of the soil to be treated will be done.

    As required by Environmental Department, no treatment is to be carried out if the ground water

    table is 0.5m of less below of soil to be treated.

    This chemical preparation shall be carried out within a kerb area under a roof with no outlet to the

    lake, open drains or public sewer. The waste water containing the chemical shall not be discarded

    into the lake, septic tank or open drain.

    3. Time of Application

    a) Link concrete shall be laid immediately after chemical has been applied on the hardcore as to

    avoid exposure to weather.

    b) Application of chemical Dynamite EC or Termigard 38.7EC (or any other applicable / approve with

    Termicide 38.7 EC) should spray on hard surfaces of hardcore or sand blinding prior to concrete

    casting.

    c) After completion of applying chemical, PVC sheet have to provide to cover up treated area as to

    avoid exposure to sun heated and rain wash in case occurred of concreting

  • d) Immediately after the soil treatment is completed, the treated soil shall be securely covered with

    black polyethylene sheet. The layer of lean concrete shall be cast on top of the sheet

    e) After completion of applying chemical pest control operator will let the site supervisor/

    Consultant to sign and certify on the job street provided by pest control operator.

    4. Allocation Equipment

    Pest control operator must provide full range equipment for the job (Mask, Eye protector, Latex

    Glove, etc).

    5. Temporary Drainage

    The provision of temporary drainage will be provided of adequate capacity around the whole area to

    be treated within an outlet to a sump.

    6. Sampling

    The examination/ quality control sampling (please refer to chemical manufacturers material safety

    data sheet, material identification report)

    7. Storage

    Pest control operator shall arrange owned transportation and delivery, storage of material at site is

    not necessary.

    SUBMITTAL OF MATERIAL

    a) Sample of material to be used is ready for submission

    b) Material for test shall be done at site at any time

    MATERIAL

    a) Dynamite EC or Termigard 38.7EC (or any other applicable / approve with Termicide 38.7 EC)

    chemical must be applied uniformly over the area to be treated at the rate of 4.5 liters to 1m2 or

    according to manufacturers specification

    b) The area to be chemically treated byDynamite EC or Termigard 38.7EC (or any other applicable /

    approve with Termicide 38.7 EC) onto 2 meters all round building perimeter prior concreting of the

    apron area.

    PEST CONTROL OPERATOR

    a) Anti Termite Contractor is the operator and XXX Agencies (M) Sdn. Bhd. is the chemical (Dynamite

    EC or Termigard 38.7EC (or any other applicable / approve with Termicide 38.7 EC) importer and

    supplier.

  • b) Pest control operator (company) is not necessary to register with CIDB (Please refer to CIDB) but

    our technicians are trained by CIDB and obtained recognized operators cards issued by CIDB

    (attached).

    c) Poison permit is issued not by Environmental Department but the ministry of agriculture control

    the issuing poison permit (please refer to Environmental Department Guideline). The poison permit

    issued by the ministry of agricultural is attached for your perusal.

    WARRANTY

    a) Actual warranty is issued by Anti Termite Contractor immediately upon P.R. request subject to

    payment fully settled by the main contractor. The warranty period is 2 years from CPC.

    b) The treated subterranean termite be found affected the treated building within warranty period

    Anti Termite Contractor undertakes to control by whatever method the company should deem fit

    free of charge.

    METHOD OF APPLYING ANTI TERMITE SOIL TREATMENT (4 Stage)

    a) Spraying of surfaces of pile cap and ground beam trenches.

    b) Spraying of surfaces below the floor-slab area after laying of hardcore and prior to the final

    concreting stage.

    c) Spraying of surfaces below apron/ Terraces and area within 2 meters perimeter beyond the edge

    of external building wall unless adjoining structures render this impossible.

    d) Power spray at any soil surfaces or areas through which termite infestation is likely to occur and

    as directed by the S.O.

    METHOD OF APPLYING ANTI TERMITE SOIL TREATMENT (2 Stage)

    a) Spraying of surfaces below the floor-slab area after laying of hardcore and prior to the final

    concreting stage.

    b) Spraying of surfaces below apron/ Terraces and area within 2 meters perimeter beyond the edge

    of external building wall unless adjoining structure render this impossible.

    c) Power spray at any soil surface of areas through which termite infestation is likely to occur and as

    directed by the S.O.

    EC - EMULSIFIABLE CONCENTRATE

  • Method Statement For Dynamic Load Test And Pile Driving Analysis Test

    METHOD STATEMENT FOR DYNAMIC LOAD TEST AND PILE

    DRIVING ANALYSIS TEST

    DYNAMIC PILE TESTING EQUIPMENT Dynamic pile testing and instrumentation will be performed using the PDA/CAPWAP system on the

    tested pile.

    Measurements of the force and velocity waves induced in the pile during pile testing are collected by

    force and acceleration transducers, which are fixed near the pile head.

    TEST PROCEDURE Dynamic pile testing can be conducted on bored piles by means of a heavy impact at the pile head.

    The impact is often provided by a suitable drop weight and the response is measured in terms of

    force and acceleration close to the pile head.

    For testing, the pile may require some excavation prior to the field-testing. The exposed length of

    pile have to be at least 1.5 diameters of the pile or 1.0m whichever is greater above the penetration

    level for pile instrumentation.

    The pile head will be protected for the impact by means of steel casing, which is used to build up the

    pile.

    A guide frame will be positioned onto the pile. The frame is used to guide the drop weight under the

    fall.

    A steel plate of about 50mm is placed on top of the pile head so as to protect the pile head from

    damage under the hammer fall.

    3 nos. of 6mm diameter holes are drilled on two opposite sides of the pile for attachment of gauges

    at 1.5 diameters below the pile top. Two pairs of force transducer and accelerometer are bolted

    onto the pile using wall plugs.

    During testing, the transducers will be connected to the Pile Driving Analyzer and its associated

    storage computer equipment via a main 19-wire cable (up to 50m long).

  • The client will supply and operate the piling hammer to induce a driving force onto the pile. The drop

    weight is positioned and drop onto the pile under controlled height. Dynamic measurement of force

    and velocity will be collected by gauges attached to the pile. This data will be processed by the PDA

    to give immediate visual and permanent record onsite.

    Each blow monitored by the PDA will be displayed on the built-in LCD screen/ oscilloscope in the

    form of force and velocity traces for immediate data quality control and computation. The PDA will

    also provide onsite results such as: -

    a. Mobilized static load capacity based on the CASE method

    b. Pile Integrity location and extent of damage

    c. Pile Stresses maximum compression forces at pile top/ toe

    d. Hammer Performance maximum energy transferred to the pile

    The transducers and accelerometers will be dismantled at the end of the testing. PDA data will be

    transferred and stored in a disk for subsequent report and analysis.

    The above procedure will be repeated for the next pile test.

    A survey of the pile top is taken before and after the testing to obtain the permanent set per blow.

    The client is also to provide the bore log information and pile construction record for the test pile.

    DATA ASSESSMENT AND CAPWAP ANALYSIS The pile top force and velocity signals recorded in the field will be processed and a representative

    blow will be selected for further analysis using the CAPWAP suite of computer software.

    CAPWAP analysis involves applying the measured pile top force/ velocity time record as a boundary

    condition to a wave equation model of the pile comprising of continuous segments.

    The soil model is continuously adjusted in an iterative procedure until the computed pile top force

    time record is in close agreement to the measured pile top force time record. When good agreement

    is obtained between measured and computed pile top data, the soil resistance parameters are

    assumed to provide the best accurate model of the actual soil behavior.

    A typical presentation of the CAPWAP results will be as follows: -

    1. CAPWAP model a match curve of computed pile top force to the measured pile top force time record

    2. Total computed soil capacity sum of Skin Friction and Toe Bearing 3. Computing Load against Settlement curve

  • REPORTING Initial results are normally available within 24 hours or two working days of the completion of each

    test. These shall include the following: -

    a) the assumed damping factor

    b) the assumed wavespeed

    c) the maximum force applied to the pile head

    d) the maximum pile head velocity

    e) the maximum energy imparted to the pile

    f) the maximum tension force experience by the pile

    g) the field estimated static resistance

    h) the maximum driving stresses

    A full report shall be submitted within 10 days of the completion of the testing. This report shall

    include the follwing: -

    a) report all information given in preliminary report

    b) information of pile size and working load

    c) date of pile installation

    d) date of test

    e) pile identification and location

    f) length of pile below existing surface

    g) total pile length, including projection above existing surface at time of testing

    h) length of pile from instrumentation position to pile toe

    i) hammer type

    j) best estimated static capacity

    k) pile integrity

    l) force/ velocity versus time trace

    m) computed load versus settlement

    QUALITY ASSURANCE Quality control is the single most important element in a successful dynamic test. Every stage in

    setting up and operation of the testing is subject to thorough quality assurance checking procedures.

    The equipment has many inbuilt checking routines and signals warning display.

    Quality assurance procedures are also followed in data processing and CAPWAP analysis. Check

    reviews and re-analysis will be carried out prior to final reporting.

  • The international acceptance of PDA/CAPWAP system and the proposal to use Geotechnical

    engineers trained and experienced in the application of the system are the key issues in providing

    the necessary quality assurance.

    Method Statement For Pile Load Test By Kentledge Method

    METHOD STATEMENT FOR PILE LOAD TEST BY KENTLEDGE METHOD 1.0 INTRODUCTION

    Vertical Compression pile load test is usually carried out to ensure the structural and Geotechnical

    soundness of pile and also to predict settlement of other piles. The common procedure is to increase

    the load in stages until the proposed working load is reached and then to unload and reduce the

    load in stage and to leave the load off until the rise or rebound substantially leases.

    A variety of test procedures and method have been developed for carrying pile load, amongst the

    most common procedure for pile load test is by using Kentledge method where a static load is apply

    direction to the pile with the required surplus.

    2.0 KENTLEDGE SET-UP

    The Standard Kentledge set-up is as shown in Figure 1. The full support system consists of the Test

    Beam and Kentledge RC Blocks.

    3.0 TEST BEAM

    The arrangement of test beams and secondary beams are placed as shown in Figure 1. Secondary

    beam shall place it evenly spaced and main beam should be in line with the center of test pile.

    4.0 MEASURING MOVEMENT OF PILE LOAD

  • Movement of pile head shall be measured with a leveling instrument and scale rules which were

    already securely fixed to the pile cap. Scale rules shall secure on top of the pile head on diagonally

    opposite direction.

    Two other scale rules shall be fixed as independent Bench Marks on a permanent structure, and the

    distance for these two Bench Marks shall be located at a distance of 5 times the pile diameter from

    one another.

    5.0 EQUIPMENT FOR APPLYING LOAD

    A 1,000 ton capacity hydraulic jack will be used for the test. The jack shall be arranged in conjunction

    with the reaction system to deliver axial load to the test pile. The complete systems shall be capable

    of transferring the maximum load required for the test.

    6.0 PROTECTION OF TESTING EQUIPMENT

    Construction equipment and site personnel who are involved in the testing process shall be more

    cautious to the testing and to prevent unnecessary disturbances to the testing devices. Also

    sufficient protection to the testing equipment (e.g. away from rain and direct under hot sunlight) is

    compulsory.

    7.0 RECORDS

    Records shall be kept properly throughout the testing period and signed by all necessary parties.

    8.0 PILE TESTING

    The pile shall be tested to the maximum test loads applied in the numbers of cycles as below: -

    ITEM WORKING LOAD (kN) MAX. TEST LOAD NO. OF CYCLES

    Spun Piles 2, 700 5, 400 2

    2Bored Piles 2, 400 4, 800 2

    8.1 Test Loading Cycles

    Each increment of load shall be maintained until the rate of settlement does not exceed 0.05 mm in

    30 minutes.

  • The following procedure shall be carried out.

    LOAD (0/0) MAINTAIN OR HOLDING TIME

    1ST Cycle

    0 2 hours

    25 2 hours

    50 2 hours

    75 24 hours

    100 1 hour

    75 1 hour

    50 1 hour

    25 1 hour

    0 1 hour

    2nd Cycle

    0 2 hours

    25 2 hours

    50 2 hours

    75 2 hours

    100 2 hours

    125 2 hours

    150 2 hours

    175 2 hours

    200 24 hours

    175 1 hour

    150 1 hour

    125 1 hour

    100 1 hour

    75 1 hour

    50 1 hour

    25 1 hour

    0 1 hour

  • ACCEPTANCE CRITERIA Following the completion of load test, the engineer shall make an evaluation of the results. The

    acceptance or rejection of piles tested shall be based on the criteria in the specification.

    Method Statement For Interior Painting

    METHOD STATEMENT FOR INTERIOR PAINTING

    1.1 DESCRIPTION

    Work of this section shall conform to the requirements of the Contract Documents.

    1.2 QUALITY ASSURANCE

    Execute this work by a firm who has adequate plant, equipment and skilled workers to

    perform its expeditiously and is known to have been responsible for installation similar to

    that specified during the immediate past five (5) years.

    1.3 WORK INCLUDED

    This work shall include supply and installation of paintings works for the building interior.

    1.4 SUBMITTALS

    1. No portion of the work requiring submission of shop drawing, product datum, or sample shall be commenced until the submittal has been reviewed and approved by

    the Consultant Architect, Interior Consultant and P.R. Such portions of the work shall

    be in accordance with reviewed and approved submittals.

    2. Samples shall fully represent the material to be installed in color, texture and finish range

    3. Submit three (3) copies of manufacturers maintenance instructions, including written data on physical characteristics, durability and information on the paint properties to

    P.R. and Employer.

  • 1.5 DELIVERY HANDLING AND STORAGE

    1. Delivery materials to project site in original factory wrappings and in containers clearly labeled with identification of approved manufacturer, brand name, fire-hazard

    classification, lot number and quality or grade.

    2. Follow approved manufacturers recommendations for special delivery, storage and handling of materials.

    1.6 WARRANTY

    1. Submit a written warranty executed by the contractor and approved installer agreeing to repair or replace materials and painting works, which fails in workmanship within

    the specified warranty period, which is five (5) years from the date of substantial

    completion.

    2.0 MATERIALS - GENERAL

    1. Paints generally for the works shall be ICI (Imperial Chemical Industries) paints or approved equivalent and each type used have to be the best quality produced within

    each specific range.

    2. All materials used in the preparation of surfaces for painting and all undercoats shall be those recommended by the approved manufacturer of the finish coat for that

    specific finish.

    2.1 COLORS

    1. Colors will be selected from the BS Standard range of colors and/or approved equivalent standards or shall be specially mixed or milled as necessary by the

    approved manufacturer. No additional payments will be apportioned for colors that

    have to be specially milled. Provide and keep on site, BS or other approved equivalent

    standards color chips of selected colors. Colors without sample chips will be rejected.

    2.2 STORAGE

    1. All materials for painting shall be delivered to site in the original sealed containers supplied by the approved manufacturers and shall be carefully stored to minimize

    exposure to high temperatures in accordance with approved manufacturers

    instructions.

    2.3 WORKMANSHIP

    1. Commencement of Works: o Interior decoration shall not commence before the work of all trades has been

    substantially completed and the areas concerned have been thoroughly cleaned

    out. Clean condition shall be maintained during interior decoration.

    2. Conditions of Base: o No paint shall be applied to surfaces structurally or superficially damp and all

    surfaces shall be free from condensation, dust and nay extraneous matter

    before application.

    3. Protection: o Before commencing work to adjoining areas which not to be painted or which

    may have been previously painted, these adjoining areas shall be adequately

  • protected. Any material, which is marked, stained or mechanically damaged,

    shall be cleaned off and made good to the approval of the Consultant

    Architect, Interior Consultant and P.R. If in their opinion cleaning and making

    good is impractical, these materials should be completely redecorated to their

    satisfaction at no cost to the employer.

    4. Removal of Ironmongery: o With the exception of butt hinges, all ironmongery and etc. wood or steel shall

    be removed before the application of the finish to the body of the work and

    after completion shall be replaced, reinstalled, eased, adjusted and oiled.

    5. Inspection and Approval o Prior to painting, all surfaces to be painted shall be inspected and approved by

    the Consultant Architect, Interior Consultant and P.R.

    o Each coat of paint, both externally and internally, shall be similarly inspected

    and approved before proceeding with the next coat.

    6. Preparation and Finish of Plastered Surfaces o Surfaces for painting and polyurethane coating shall be clean and dry. Any

    efflorescence shall be removed by first wiping with a dry coarse cloth and then

    with a damp cloth. The surface shall be applied until efflorescence has ceased.

    All new plastered surfaces for polyurethane coating shall be cured for a

    minimum of 28 days.

    o The surfaces shall be cleaned to remove dust, plaster splashes, oil grease and

    all foreign matters.

    o Cracks and other imperfections shall be cut out and make good with suitable

    fillers. Such patching works shall be allowed to dry out thoroughly before

    painting or polyurethane coating.

    7. Preparation and Finish of Internal surfaces o After surfaces have been inspected and approved by the Consultant Architect,

    Interior Consultant and P.R. apply one coat plaster sealer and two coats of

    approval Polyvinyl Acetate Emulsion Paint on the internal plastered walls.

    The duration for drying time between the first and second coat must not be

    less than four hours.

    8. Preparation and Finish of Gypsum Plasterboard/ Fibrous Plasterboard o Brush off all loose particles and apply one coat of plaster sealer and two

    finishing coats of approved ICI emulsion paint or approved equal.

    9. Preparation and Finish of Mild Steel Surface o All metalwork before fixing shall be thoroughly cleaned down to remove all

    dirt grease, scale and rust by wire-brushing, scraping or other means. The

    surfaces are to be rubbed down

    o Paint one coat of Dulux Grey-Green Chromate Metal Primer F500-388, two

    coats of Micaceous Iron Oxide and two finishing coats of Dulux Gloss Finish

    A365 Line or approved equivalent.

    10. Preparation of Unprimed Joinery o Well sand the surface to bring it to a smooth finish suitable for a high quality

    finish. Apply knotting to all permissible knots, gum veins sand resin streaks.

    Apply one coat primer and allow to dry for not less than six hours and stop all

    holes, shakes and splits with hard stopping.

    o Filler shall be used where the grain is open. After stopping and filling, allow

    priming to dry for not less than eighteen hours. Any shop primed joinery

    which does not receive the final coat within eight weeks shall be considered

    unprimed for the purpose of preparation.

    11. Preparation of Shop Primed Joinery o Inspect for imperfect knotting and damaged or inadequate priming, make good

    and touch up as necessary. Stop all holes, shakes and silts with hand stopping.

    Where the grain is sufficiently open fillers shall be used.

    12. Preparation of Joinery for Clear Finish o Well sand the surface to bring to a smooth finish suitable for a high quality

    finish. Stop up any defects with plastic wood of approved manufacture tinted

    to match color of timber or stain.

  • 2.4 TESTING

    All materials for paint and film finishes shall be subject to test including but not limited to the

    followings:-

    1. Fading and color fastness 2. Bending and scratching resistances 3. Oxidation, weathering and accelerated weathering 4. Resistance to mould, fungus and algae 5. Application and self-leveling properties 6. Pigment content and fineness of grind 7. Chemical analysis (Particularly anti-corrosive paints) 8. Samples for testing shall be supplied without charge. The cost of testing shall be

    borne by the Contractor.

    2.5 DRYING TIME

    1. Allow as minimum as possible the drying time recommended by the approved manufacturers of the material used.

    Method Statement For External Painting

    METHOD STATEMENT FOR EXTERNAL PAINTING

    1.1 GENERAL INSTRUCTION

    1. All work shall conform to BS 6150; BS 1336, BS 245; MS 125: 1985 Enamel Paints; MS

    134: 1989 Emulsion Paints, Exterior; MS 903: 1987 Emulsion Paints, Exterior; and

    approved manufacturers specific recommendations.

  • 1.2 RELATED WORK SPECIFIED ELSEWHERE

    1. Unit Masonry Section 04200 2. Metals Division 5 3. Woods and Plastic Division 6 4. Doors and Windows Division 8 5. Gypsum Board Section 09250 6. Textured Coatings Section 09835 7. Mechanical Division 14 8. Electrical Division 15

    1.3 WORK INCLUDED

    1. Provided all materials, labor and equipment required to complete the painting works, together with ancillary work herein described and implied to the full intent of the

    drawings and schedules.

    2. Make thorough examination of drawings, details and schedules, determine the intent, extent, materials, and types of surfaces, locations and be fully cognizant of

    requirements.

    3. Examine the specifications and drawings for the work of other Section regarding the provisions for prime and finish coats. Paint or finish all materials installed throughout

    the project which are required to be painted, and which are left unfinished or

    unpainted by other Sections.

    4. For areas indicated as unfinished in the Room Finish Schedules, painting is not required, except for doors and frames, railings, miscellaneous metal work, insulation

    on mechanical pipes and equipment, pipes and fittings, electrical mounting boards,

    and all gypsum board surface. In tenant areas, prime paint gypsum board only.

    5. Provide finishes free of defects in materials and workmanship affecting appearance and performance. Defects shall include, but not be limited to improper cleaning and

    preparation of surface, entrapped dust and dirt alligatoring, blisters, peeling, drips,

    runs, uneven coverage, misses, poor cutting in, improper use or application of

    materials.

    6. All paints shall be factory tinted to required colors and thoroughly mixed before application.

    7. Comply with toxic trace limitations stipulated by the authorities having jurisdiction. 8. Frame spread rating finishes shall conform to the local building code.

    1.4 SUBMITTALS:

    1. Colors

    Paint colors will be selected by the Consultant Architects and P.R. form approved

    manufacturers full color range, including light and dark tones. Consultant Architect and P.R.

    will furnish Schedule showing where the various colors, gross value and sheen of the finishes

    occur. The Consultant Architect and P.R. shall have complete freedom in choice of colors in

    compiling Color Schedule and will not necessarily select colors from standard color charts of

    approved manufacturer whose products have been approved for use.

    2. Samples

    Submit samples of various finishes to the Consultant Architects and P.R. at least thirty (30)

    days before materials are required. Submit samples in triplicate on 300mm x 300m material

    of the same type as that on which the coating is to be applied, where possible. Identify each

    sample as to job, finish, color name, number, sheen and gloss values, date and name of

    contractor.

  • 3. List of Materials

    Submit name of paint manufacturer proposed for the work and complete list of materials

    intended for use on work prepared by paint manufacturer to the Consultant Architect and P.R.

    at least sixty (60) day before materials area required. Indicate approved manufacturers

    official certification that materials listed thereon is the top quality made by the company.

    Materials delivered to the work shall conform to the accepted list.

    1.5 DELIVERY, HANDLING AND STORAGE PROTECTION

    1. Delivery material to site in sealed original containers with labels intact and store in space as directed. Keep stored materials covered at all times. The presence of any

    unauthorized materials or containers for such on the site shall be sufficient cause of

    rejection of all paint materials on the site at the time.

    2. Exercise extreme caution in the storage of materials to prevent fire or create fire hazards. Thinners and solvents shall be stored in approved metal safety containers in

    accordance with governing fire and safety regulations.

    3. In areas of storage, protect floor and wall surfaces from paint drips and splatters. Protect floors with sheets of clean plywood or metal panels where mixing and strictly

    enforce this requirement. Provide and maintain CO fire extinguishers of minimum

    9kg capacity accessible in storage mixing areas.

    4. Leave storage areas clean and free from evidence of occupancy when these are required for intended use.

    5. Keep waste rags in metal drums containing water and remove from building at end of each working shift.

    1.6 ENVIRONMENTAL CONDITIONS

    1. All areas shall be clean and dust free before painting is commenced. 2. Use sufficient clean drop cloths and protective covering s for full protection of floors,

    furnishings and work not being painted. Protect mechanical, electrical and special

    equipment and all other soiling during painting process. Mask adjoining work

    adjacent to work being painted or carefully cut-in-Without overlaps. Clean surfaces

    soiled by spillage of paint and paint spatters. If cleaning operations damages the

    surface, repair or replace damage work without cost to the Employer.

    3. On exterior work, do not paint during or immediately following rain. 4. Be responsible for damage to the work of this section until the building is complete

    and accepted by the Employer. In cases of damage, surfaces shall be cleaned and

    repainted to Architects satisfaction.

    5. Leave areas clean and free from evidence of occupancy upon completion of painting. 6. Do not paint surfaces exposed to direct sun or where condensation has or will form

    due to the presence of high humidity and lack of proper ventilation.

    2.0 MATERIALS

    1. Paint and Finishing Materials: Undiluted, highest grade, first line quality of the approved manufacturer, correctly labeled, bearing the brand and makers name, type

    of paint, color and code number.

    2. Undercoater, Sealer and Primer: Made for the purpose by the approved manufacturer of finishing materials being used.

    3. Primer: Drying time 4 hours maximum, high hiding pigments; sealer low odor, alkyd or latex to suit substrate.

    4. Paint: Aikyd and vinyl Tape, low odor, quick drying, high hiding and low solvent content.

    5. Shellac shall be pure white gum dissolved in pure grain alcohol.

  • 6. Flame spread ratings of interior finishes shall conform to the Malaysian Building Code.

    7. Brushes, Rollers and Application Equipment: The best of their respective kinds, clean and suitable for the work.

    3.0 MIXING

    1. Ensure that paint has not settled, caked or thickened in the container, is readily dispersed with a paddle to a smooth consistency and has excellent application

    properties.

    2. Use all reducing and tinting materials as recommended by the approved manufacturer for the particular material reduced or tinted.

    3. Mix materials thoroughly before application.

    4.0 INSPECTION

    1. Examination: Examine the work upon which the work of this Section depends prior to the application. If surfaces cannot be put in proper condition by customary cleaning,

    sanding and puttying, report such defects in writing.

    2. Acceptance: Failure to report defects will constitute acceptance or surfaces. Refinish the faulty work at no expense to the Employer.

    3. Moisture Content: Do not paint surface while moisture content as tested by moisture meter exceeds the following:

    1. Wood surface 15% 2. Masonry and concrete surfaces 10% 3. Interior plaster and gypsum board 12% 4. Concrete Floors 10%

    4. Lighting Level: Do not apply finishes or undertake surface preparation unless illumination characteristics are acceptable for production of first class job.

    5.0 PREPARATION

    1. Dust: Clean floors, adjacent surfaces and surfaces to be painted before work is commenced.

    2. Defects: Ensure that surfaces to be finished are clean, free from machine, tool or standing marks, dust, grease, soil or other extraneous matter and all defects or sanding

    marks which could be detrimental to an acceptable finish.

    3. Alkaline Surface: Neutralize highly alkaline surfaces with a neutralizing wash of 4% solution of Zinc Suphate. Substitute 4% solutions of Tetrapotassium Pyrophosphate

    for surfaces to receive latex paints. Brush off residue before painting.

    4. Mildew: Scrub mildewed surfaces with a solution of Trisodium Phosphate, bleach with a solution of 1 part Sodium Hypochlorite to 3 parts water and rinse with clear

    water.

    5. Mask and cover surrounding surfaces, coordinate and remove ironmongery, electric plates and accessories as required to keep paint from adjacent surfaces. Mask labels

    and specification plates occurring on equipment to be painted. Properly mask all

    sprinkler heads and fire detectors wherever they occur in surfaces to be painted.

    Remove tape when paint is dry and clean. Do not clean hardware with solvent that

    will remove permanent lacquer finish. Reinstall after completion.

    6.0 APPLICATION

    1. Approved Manufacturers Instructions: Apply materials in accordance with the directions and instructions of the approved manufacturer of the materials. DO not use

    adulterants.

  • 2. Workmanship: Execute the work in accordance with the recognized highest standards of workmanship of the industry and to meet requirements of the specification. Work

    shall be executed by approved workers specially trained and having a provincial

    tradesman qualification certificate of proficiency. Have an approved full time senior

    qualified representative at the site to direct the work.

    3. Painting shall be four-coat work throughout. Priming coat shall be color toned lighter than undercoat, undercoat lighter than the first finish coat: final coat shall be approved

    color. Apply on additional finish coat to surfaces scheduled to receive deep, dark or

    accent colors called for on the Schedules and for graphics.

    1. Each coat shall be inspected by the Consultant Architect and P.R. Recoating occurs without Consultant Architect and P.R. inspection, it shall be considered

    as not having been done and shall be re-coated.

    4. Paint shall be applied by means of brushes, except for wall and ceiling surfaces on which the paint shall be applied by lambs wood rollers. Varnish shall be brushed.

    5. Spray painting will not be permitted unless specifically approved for certain areas. If approval is granted for spraying, the equipment shall be airless type. Consultant

    Architect and P.R. may at any time prohibit use of spray painting for such reasons

    during application as carelessness, poor masking or protective measures, drifting paint

    fog, disturbance to other trades or failure to obtain a dense, even, opaque finish. All

    motors, fans, and mechanical ventilation system equipment shall be shut off during

    spray painting.

    6. Appearance: Apply materials evenly, uniform in thickness, color, texture and gloss under adequate illumination.

    1. Finishes shall be free of defects in materials and workmanship affecting appearance and performance visible from a distance of 2m defects shall

    include, but not be limited to improper cleaning and preparation of surfaces,

    entrapped dust and dirt, alligatoring, blisters, peeling, drips, runs, uneven

    coverage, misses, poor cutting in, improper use of application of materials.

    Apply coats of the proper consistency as received from the container.

    7. Sand: Semi-gloss, medium and high gloss shall be sanded lightly between coats. 8. Dryness: Each coat applied shall be thoroughly dry before the next coat is applied.

    Follow approved manufacturers directions for drying time.

    9. Doors: 1. DO NOT paint stainless steel or bronze door butts. 2. Paint steel door butts in the following manner: Paint the trim half of each butt

    2 coats to match the color of the door trim: and paint the door half of each butt

    2 coats to match the color of the finish of the door. Paint the pivot portion to

    match the trim.

    3. Exterior doors shall have tops, bottoms and side edges finished the same as the exterior faces of these doors.

    4. 4. Do not paint over label on steel doors and frames, and other identification labels.

    10. Ledges: Finish projecting ledges, both above and below sight lines as specified for surrounding surfaces.

    11. Mechanical and Electrical Items 1. Removable grilles, gratings, louvers and access panels for convectors and

    ventilating system and perimeter heating enclosures shall be removed and

    painted separately, if not factory finished. Reinstall when dry.

    2. Where the back of the unit, wall or insulation are visible through grilles or louvers, paint such surfaces. Visible portions of ducts behind grilles shall be

    painted matte black.

    3. Paint access doors and frames to match the surface in, which they occur. 4. In Compartment Room, walls shall be painted, floor sealed with concrete

    sealer, all thermally insulated pipes shall be painted. Equipment will not be

    painted: Mask and cover equipment and floor. Equipment will not be painted.

    All gas piping will be painted.

    5. Use heat resistant epoxy paint on pipes and surfaces where operating surface temperature exceeds 65 degrees C.

    6. Coordinate the painting of pipes, ducts and covering with Mechanical Contractor to ensure that he does not install pipe color banding, flow arrows

  • and pipe identification until the painting of the pipes, coverings and ducts has

    been done.

    7. Remove and reinstall electrical outlet covers. 12. Metal

    1. Paint all interior and exterior exposed metal work, including those in areas which are shown as unfinished on the room Finish Schedules, with two coats

    of paint over the prime coat. Include, without being limited to, all structural

    steel, mechanical and electrical equipment, ductwork and piping.

    2. The exceptions to paragraph 3.3.12.1 shall be stainless steel and aluminium. 3. Ferrous Metals: Remove all rust and mili scale using power wire brushing.

    Remove weld flux and wash with water to remove alkali contaminants.

    4. Shop Coated Steel or Iron: Remove oil or grease contaminants by solvent washing. Touch up abraded areas with rust inhibiting primer similar to that

    used for shop coating.

    5. Galvanized Steel: Wash thoroughly with mineral spirits and wipe entirely clean using sufficient number of clean cloths. Touch up damage areas with

    organic zinc rich primer.

    13. Wood 1. Mounting Boards: Paint both sides and edges of plywood mounting for

    electrical and telephone equipment with fire regardant paint before

    installation.

    14. Concrete and Masonry 1. Ensure that surfaces are clean, free from contamination. Scrap of mortar nibs

    of cement spatter. Remove from oil by washing with xylol or Trisodium

    Phosphate Solution. Remove efflorescence by dry brushing or washing with a

    diluted solution of Muriatic Acid 1 part commercial Muriatic acid to 20 parts

    water by volume followed by complete rinsing with clean water. Remove

    mildew by the application of 1 part Sodium Hypochlorite to 3 part water. If

    dirt is also in evidence, add kg Trisodium Phosphate to 4L of the above

    solutions.

    15. Concrete and Masonry 1. Inspect to ensure properly filled and finished surface. Fill small nicks or holes

    with patching compound and sand smooth.

    2. Cut out scratches, cracks and abrasions in wall surface as required and fill with non-shrink patching compound and sand smooth.

    16. Doors, Frame and Walls to Water Storage 1. Prepare surface and apply primer in accordance with approved manufacturers

    instructions

    2. Apply finish by airless or conventional spray. 17. Patching

    1. Do all retouching to ensure that the work is handed over to the Owner in perfect condition, free of runs, spatter, rust, watermarks, scratches, blemishes

    or other disfiguration.

    2. After fully decorating retouching and finishing a room or area, notify the Consultant Architect and P.R. After inspection and acceptance, post sign

    DECORATING COMPLETE NO ADMITTANCE WITHOUT

    PREMISSION

    3. Repaint the entire plane of areas showing defects of incomplete coverage. Patching will not be permitted.

    7.0 FIELD QUALITY CONTROL

    1. Arrange a site meeting between the Consultant Architect and P.R. with the approved paint manufacturers representative prior to the commencement of the painting

    operations to discuss the painting and finishing procedures to be used and to analyze

    the surface conditions in order that alternative recommendations may be made to the

    Employer and P.R. should adverse conditions exist. Discuss the following items.

    1. Environmental conditions for each area 2. Maximum moisture readings or surfaces and type of reading meter to be used.

  • 3. Remedy of defects in surfaces 4. Paint thickness measurements and acceptable tolerances

    2. Arrange with the approved paint manufacturers to visit the site at weekly intervals or more often if requested, during the surface preparation and painting operations to

    ensure that the proper surface preparation has been completed, the specified paint

    products are being used, the proper number of coats are being applied and the agreed

    finishing procedures are being used. Arrange for the approved paint manufacturer to

    regularly submit written reports to Consultant Architect and P.R.

    3. An area located in the building will be designated for site tests. 1. Apply samples of finishes in the testing area. Apply the samples with the

    correct material, number of coat, color, texture, and degree of gloss required.

    Refinish it if required, until acceptance of the Consultant Architect and P.R. is

    obtained.

    2. Leave test areas undisturbed until completion of the work. Approved work in the test area shall serve as a standard for similar work throughout the project.

    3. Work, which does not match the approved sample finishes, shall be corrected and refinished at no expense to the Employer.

    8.0 EXTERIOR FINISHES

    1. Steel: 1 coat exterior metal alkyd primer, 1 coat alkyd undercoat, 2 coats exterior alkyd enamel gloss

    9.0 INTERIOR FINISHES

    1. Concrete: 4 coat interior latex primer-sealer alkali resistant (walls and ceiling) coat tinted alkyd undercoat (column and beams). 2 coats interior alkyd semi-gloss or

    eggshell enamel

    2. Concrete Block: 1 coat interior latex primer-sealer alkali resistant, 1 coat tinted alkyd undercoat, 2 coats interior alkyd semi-gloss or eggshell

    3. Steel-Primer: Touch up damage areas of primer coat with primer, 1 coat alkyd enamel undercoat, 2 coats interior alkyd enamel semi-gloss or eggshell.

    4. Concrete Floor (Refer to Room Finish Schedule for Locations): 2 coats polyurethane floor paint

    5. Gypsum Board: 1 coat acrylic primer, 1 coat tinted alkyd undercoat, 2 coats interior alkyd enamel of selected gloss.

    6. Surface visible through Grilles, Registers, etc: 2 coats alkyd enamel flat back 7. Wood-Paint Finish (Mounting Boards): 1 coat fire retardant undercoated, 2 coats fire

    retardant, paint both sides before installation.

    8. Water-Storage (Door Frames and Walls): 1 coat primer, coatings, 2 coats finish-Amercoat Coatings or approved equal.

    9. Wood Carvings: 3 coats of polyurethane lacquer.

    10.0 WARRANTY

    1. Submit a written executed by the contractor agreeing to provide finishes free of defects in material and workmanship affecting appearance and performance (as per

    paragraph 1.3 Work Included). Within the specified warranty period which is five (5)

    years from the date of substantial completion.

    11.0 CLEANING

    1. Promptly as the work proceeds and on completion of work, remove all paint spilled, splashed or spattered. During the progress of the work, keep the premises free from

    any unnecessary accumulation of tools, equipment, surplus materials and debris. At

  • the conclusion of the work, leave the premise neat and clean to the satisfaction of the

    Consultant Architect and P.R.

    Method Statement For Remedial Of Honeycomb At Structure Member

    METHOD STATEMENT FOR REMEDIAL OF HONEYCOMB AT STRUCTURE MEMBER

    Case A: Superficial Honeycomb

    1. To identify the affected area 2. Removed all the loose particles surrounding the affected area and make sure it was free

    from dust, grease and oil. 3. Estimated the quantity of non-shrink grout and water to be used, gradually add the grout

    into the water and mix it by using spatula or slow speed drill to the consistency required (refer to the mixing ratio guide for water: grout ratio)

    4. Trowel able of stiff consistency mix is adopted to apply onto the affected area by using the steel trowel and leveled it to flush with the original structure member

    5. Repeat item 1 to 4 for any new affected area

  • Case B: More Severe Honeycomb (Cavity)

    1. To identify the affected area

    2. Removed all the loose particles surrounding the affected area and make sure it was free

    from dust, grease and oil.

    3. Prepare and install the formwork for the grouting work around the defective area and leave

    about 25mm gap to pour the non-shrink grout.

    4. Estimate the quantity of non-shrink grout and water to be used, gradually add the grout into

    the water and mix it by using spatula or slow speed drill to the consistency required (refer to

    the mixing ratio guide for water: grout ratio)

    5. Pour the mix with non-shrink grout at high workability by using gravity flow

    6. Remove formwork after 24 hours and patch the 25mm gap with stiff mix non-shrink grout.

    7. Repeat item 1 to 4 for any new affected area

    Materials

    1. Sika Grout-215

    2. 5 Star Grout

  • Method Statement - Bored Cast-In-Place Piles

    OBJECTIVE

    1. To outline the instruction by which the piling works for bored cast-in-place piles are carried out.

    MATERIALS

    1. Concrete grade 30 2. Reinforcement as specified

    PLANT, MACHINERY AND EQUIPMEN

    1. Rotary auger, Tremie attached with hopper, Hydraulic ram or Jaw.

    PREPARATORY WORKS

    1. Obtain approved construction drawings from the client / clients representatives. 2. Setting out shall be carried out from reference lines and points shown in the drawings.

    Immediately before installation of the pile, the pile position shall be marked with

    suitable identifiable pins or markers. The maximum permitted deviation of the

    finished pile from the center point shown on the setting out drawing shall be 75mm in

    any direction. The permitted deviation of the finished pile from the vertical is 1 in 75.

    WORK METHODOLOGY

    1. Boring through soil shall be by rotary auger only. Boring through rock shall be by use of approved rock

    drilling equipment. Boring shall be carried out to depths instructed by the S.O

    Standard penetration tests shall be carried out in pile borings to the requirements of

    test 19 BS 1377;1975.

    2. During the process of boring a pile through weak strata, drilling fluid materials bentonite shall be used to maintain the stability of the bore. The level of drilling fluid

    in the excavation shall be maintained so that internal fluid pressure exceeds the

    external ground water pressure.

    3. A permanent casing will be installed up to a stable stratum (SPT value=50). Then continue boring operation to founding level. Rock tools or chiselling shall be used for

    boring through rock where auger can not be used.

    4. If the soil below casing toe level is still found unstable then extend length of permanent casing by welding and push the casing further down to a stable stratum.

    5. On completion of boring and where inspection of a dry pile bore indicates the necessity, loose, disturbed or softened soil shall be removed from the bore.

    6. Each pile boring shall be inspected prior to the placing of concrete in it and cage then placed. Steel reinforcement shall be provided for the whole length of piles and shall

    be fixed in the form of a cage with lateral ties.

    7. Cast concrete to the required level. If the bore hole is dry, concrete will be discharged through a hopper with a short guide trunk. If the bore hole is filled with water,

    concreting will be done through a tremie pipe with an attached hopper. The pipe shall

    rest on the base of the boring at the commencement of the concrete pouring and it

    shall at all times penetrate into the concrete which has previously been poured. The

    concrete mix shall be such that a continuous compacted concrete shaft is formed. For

    piles with permanent casing, vibrators may be used when required, poke or immersion

    type vibrators shall only be used from the bottom of pile upwards.

    8. Drawings as specified for recording as built location of works shall be prepared and approved by S.O.

    http://methodofconstruction.blogspot.com/2011/07/method-statement-bored-cast-in-place.html

  • 9. Comprehensive records of all strata penetrate or bored shall be kept together with boring samples. The record shall include the following information: -

    a) Contract section

    b) Reduced level of pile position

    c) Pile reference number

    d) Nominal diameter of the bore hole

    e) Length of the bore hole

    f) Nominal diameter of the under ream

    g) Standing ground water level

    h) Date bored

    i) Date completed

    j) Depth from working level to pile toe

    k) Depth from working level to specified cut off level

    l) Length of temporary casing used

    m) Length of permanent casing used

    n) Soil samples taken and in-situ tests carried out inclusive of the interpretation and description

    of soils

    o) Length and details of reinforcement cage used

    p) Concrete mix used

    i) Water cement ratio

    ii) Slumps

    q) Concrete test cube results

    r) Volume of concrete supplied to pile

    s) Time spent in overcoming obstruction, delays and other interruption to the sequence of the

    works

    t) Weather report

  • Method Statement - Non Suspended Slab

    Method Statement For Construction Of Non Suspended Slab STAGE 1

    1. Casting the ground beam 25mm lower from original depth 2. Leveling and well-compacted sub-grade and crusher run

    STAGE 2

    1. Placing damp proof polythene sheet and followed by B.R.C. layer 2. Casting the ground slab to required level as specified in the construction drawing

    STAGE 3

    1. Leveling the slab with gradient to fall as specified in the construction drawing 2. Applying floor hardener finisher

    http://methodofconstruction.blogspot.com/2011/07/method-statement-non-suspended-slab.htmlhttp://3.bp.blogspot.com/-PGoQwlra2aA/Ti5AgwInhWI/AAAAAAAAACY/LrOpotDswsg/s1600/Stage+1+copyright.JPGhttp://2.bp.blogspot.com/--i4M_y_pZGs/Ti5Ahfz3IYI/AAAAAAAAACc/nuFG6mrFekM/s1600/stage+2+copyright.JPG

  • STAGE 4

    1. Forming a groove line by diamond cutter at both end of ground beam

    *The illustration and information is for guidance only. Please refer to your engineer or consultant

    for further advise.

    Posted by mny at 11:40 AM 0 comments

    Email ThisBlogThis!Share to TwitterShare to FacebookShare to Pinterest

    Labels: Non Suspended Slab

    Tuesday, June 14, 2011

    Method Statement For Pile Driving

    SCOPE

    This procedure refers only to the installation of the piles indicated. It does not include bored piles and

    jacked-in piles.

    TYPE OF PILE

    600mm Diameter Spun Pile

    Working Load = xxxT

    http://methodofconstruction.blogspot.com/2011/07/method-statement-non-suspended-slab.htmlhttp://methodofconstruction.blogspot.com/2011/07/method-statement-non-suspended-slab.html#comment-formhttp://www.blogger.com/share-post.g?blogID=2403940435481005403&postID=4153289390472075624&target=emailhttp://www.blogger.com/share-post.g?blogID=2403940435481005403&postID=4153289390472075624&target=emailhttp://www.blogger.com/share-post.g?blogID=2403940435481005403&postID=4153289390472075624&target=twitterhttp://www.blogger.com/share-post.g?blogID=2403940435481005403&postID=4153289390472075624&target=twitterhttp://www.blogger.com/share-post.g?blogID=2403940435481005403&postID=4153289390472075624&target=pinteresthttp://methodofconstruction.blogspot.com/search/label/Non%20Suspended%20Slabhttp://methodofconstruction.blogspot.com/2011/06/method-statement-for-pile-driving.htmlhttp://2.bp.blogspot.com/-9RRtwd7Aw-c/Ti5AiJAprPI/AAAAAAAAACg/b3bceX8B-H8/s1600/stage+3+copyright.JPGhttp://1.bp.blogspot.com/-pTeOIg134tA/Ti5AgTC4v0I/AAAAAAAAACU/dlmNdb8txZI/s1600/stage+4+copyright.JPGhttp://www.blogger.com/email-post.g?blogID=2403940435481005403&postID=4153289390472075624

  • EQUIPMENT

    The following types of Hydraulic shall be used:

    600mm Diameter - 9 Ton Hydraulic Hammer

    PILE SET CALCULATION

    For this calculation, Hiley Formula will be used to compute the estimated SET for each type of pile:

    Hiley formula :

    SET = Awh / fL x (W+Pe2) / (W+P) C/2

    Hammer Efficiency A

    Mass of Hammer W

    Drop of Hammer h

    Safety Factor f

    Pile Working Load L

    Total Mass P

    Coefficient of Restitution e

    Temporary Compression C

    Summary of Sets is to be attached. Set Calculation detailed with respect to hammer, drop and

    estimated penetration need to be provided.

    The actual SET values will be recomputed at site based on the variable parameters of actual pile

    length installed and the actual temporary compression recorded.

    SITE PREPARATION

    Piling platform will be leveled prior to piling activities

    SETTING OUT

    Boundary survey shall be carried upon possession of site based on the pre-computation plan available.

    Setting out plan shall be submitted for checking and approval.

  • HANDLING, PITCHING, DRIVING AND EXTENSION

    All handling and lifting will be at the designed lifting points and support points.

    Boundary survey shall be carried upon possession of site based on the pre-computation plan

    available. Setting out plan shall be submitted for checking and approval.

    During pitching and driving, the vertically of the pile will be continuously monitored and plumbed

    to ensure the pile is centrally in line with the pile axis to receive the hammer to prevent pile whip,

    twist or rotation.

    Each pile shall be clearly marked with red ink at 300mm intervals along its length to enable the

    driving blows to be recorded at every 300mm depth of pile penetration.

    The pile will be extended by butt-welding the steel plates on the pile heads. On completion of

    welding, the slag will be chipped off and wire brushed to receive red-oxide paint.

    Each pile shall be driven continuously until the specified set and / or depth has been reached. A

    detail record of the driving resistance over the full length of each pile should be kept.

  • Method Statement - Concreting Work

    CONCRETING WORK

    OBJECTIVE

    Method on how the concreting works are carried out

    MATERIALS

    Ready mixed concrete

    PLANT, MACHINERY AND EQUIPMENT

    Tower crane / Mobile Crane, Concrete Pumps, Concreting Buckets, Vibrators, Wheelbarrows, etc.

    as applicable

    PREPARATORY WORKS

    1. Request for design mix based on the concrete grades specified on structural drawings from the

    Ready Mixed Concrete Supplier(s).

    2. Submit the proposed design mix to client / clients representative for approval.

    3. Submit request for inspection of structural members with client / clients representative prior to

    concreting works using Structural Work (Reinforcement / Concrete) Inspection Checklist and

    Inspection and Test Plan.

    4. Carry out receiving inspection of ready mixed concrete as per Material Receiving Inspection

    Checklist.

    5. File completed Material Receiving Inspection Checklist as per Project Filing Index.

    WORK METHODOLOGY

    1. Take concrete cube samples for quantity specified in the contract document.

    2. Mark the location of pour for concrete received on the delivery docket and checklist as reference

    and identification.

    3. Provide adequate equipment, machinery and manpower to carry out the concreting works.

    4. Place concrete on designated locations using concrete pumps and / or crane assisted concrete

    buckets.

    5. Start concreting from a fresh location or a predetermined construction joint and continue

    uninterrupted up to the next predetermined construction joint or to completion.

    6. If concreting is to commence from a construction joint, roughen the joint before placing the

    concrete when wire mesh is not available.

    7. Place concrete from the lowest point to the final concrete level in one operation in horizontal

    layers.

    8. Compact concrete by mechanical vibrators. Ensure that concrete is worked into the corners of

    the structural members.

    9. After the concrete has set, carry out curing works by applying curing compound.

    http://methodofconstruction.blogspot.com/2011/06/method-statement-concreting-work_10.html

  • Method Statement - Placing Formwork

    PLACING FORMWORK

    OBJECTIVE

    The method statement for placing of formwork

    MATERIALS

    Steel Form, Timber, Plywood, nails, scaffolding, frame / accessories

    PLANT, MACHINERY AND EQUIPMENT

    Crane, Lorry and Backhoe

    PREPARATORY WORKS

    1. Obtain relevant approved construction drawings from client / clients representatives.

    2. Set out the locations, centre lines and levels for formwork along with reference lines.

    3. Prepare necessary formwork panels to the required dimensions and sizes.

    4. Coat formwork surface evenly and thinly with release agent like form oil etc.

    WORK METHODOLOGY

    1. Erect the formwork by providing sufficient props and struts including necessary bracing.

    2. Use scaffolding and staging arrangements, where necessary.

    3. Seal gaps in formwork to avoid leakage of grout.

    4. Ensure checking for the required shape and dimensions as per drawings.

    5. Submit Request for Inspection Form for joint inspection with client / clients representative

    using Structural Work (Reinforcement / Concrete) Inspection Checklist.

    6. On completion of joint inspection, request client/clients representative to sign on the checklist

    and file as per Project Filing Index.

    Method Statement - Excavation And Backfill

    EXCAVATION AND BACKFILL

    The method statement by which the excavation and backfill with suitable fill is carried out.

    PLANT, MACHINERY AND EQUIPMENT

    -Excavator, Dump Truck, Dozer, Compactor and Back pusher.

    http://methodofconstruction.blogspot.com/2011/06/method-statement-placing-formwork_10.htmlhttp://methodofconstruction.blogspot.com/2011/06/method-statement-excavation-and_10.html

  • PREPARATORY WORKS

    1. Obtain relevant approved construction drawing from client / clients representatives.

    2. Set out the location and limits of work.

    3. Carry out survey to obtain original ground level, excavation level and final backfilled level.

    WORK METHODOLOGY

    1. Prepare access to the working area and plan for the dump truck and plant movements.

    2. Excavate to the required depth as indicated on construction drawing and dispose off at dump site.

    3. Transport, fill and spread suitable material and compact as required.

    4. Repeat step 3 until the required level is achieved.

    5. Submit Request for Inspection Form for joint inspection using General Earthworks Excavation And

    Backfill Inspection Check-list.

    6. On completion of joint inspection, request client / clients representative to sign on the checklist

    and file as per Project Filling Index