  • 7/29/2019 MS 1005 R2 Surveying Work

    1/7

    Employer:

    Supervision Committee for the Expansion ofAbu Dhabi International Airport (SCADIA)

    Contractor

    Project Manager / Engineer:

    Project No.: 1008Document Category:

    Method Statement Agreement No.: NRTW-1008-CN

    Project Title:

    Expansion of Abu Dhabi International AirportNew 2K Runway Main Runway Works

    Procedure No.:

    1008-OAJ-MS-1005

    Procedure Title:

    Surveying WorkRevision No: 2

    Page: 1 of 7

    Method Statement for Surveying Work

    REVISION HISTORY

    Rev.

    No.Date

    CONTRACTOR-OAJ JVRevision History ENGINEER

    Status of

    ApprovalPrepared Reviewed Approved

    2 16/07/2006AN ZH RR Para 2.1

    Para 8.1 to 8.6

    1 04/07/2006EAH/IF ZH RR Para 3.2, 8.1

    Para 9.2, 9.4, 9.5

    0 22/06/2006 EAH/IF ZH RBR First Submissionfollowing award ofContract

  • 7/29/2019 MS 1005 R2 Surveying Work

    2/7

    Employer:

    Supervision Committee for the Expansion ofAbu Dhabi International Airport (SCADIA)

    Contractor

    Project Manager / Engineer:

    Project No.: 1008Document Category:

    Method Statement Agreement No.: NRTW-1008-CN

    Project Title:

    Expansion of Abu Dhabi International AirportNew 2K Runway Main Runway Works

    Procedure No.:

    1008-OAJ-MS-1005

    Procedure Title:

    Surveying WorkRevision No: 2

    Page: 2 of 7

    CONTENTS

    1.0 Scope of Work

    2.0 Definitions

    3.0 References

    4.0 Subcontractors

    5.0 Materials

    6.0 Plant & Equipment

    7.0 Safety

    8.0 Prior Activities

    9.0 Procedure

    10.0 Responsibilities

    11.0 Attachments

    1. Scope:

  • 7/29/2019 MS 1005 R2 Surveying Work

    3/7

    Employer:

    Supervision Committee for the Expansion ofAbu Dhabi International Airport (SCADIA)

    Contractor

    Project Manager / Engineer:

    Project No.: 1008Document Category:

    Method Statement Agreement No.: NRTW-1008-CN

    Project Title:

    Expansion of Abu Dhabi International AirportNew 2K Runway Main Runway Works

    Procedure No.:

    1008-OAJ-MS-1005

    Procedure Title:

    Surveying WorkRevision No: 2

    Page: 3 of 7

    1.1 This Method Statement covers the various steps in Site Survey Works.

    2. Definitions:

    2.1 MS: STM Method Statement : Surveying Work

    2.2 ITR Inspection and Test Request

    2.3 PPS Particular Project Specification

    2.4 GPS General Project Specification

    2.5 UG Underground

    2.6 TPS Technical Project Specification

    3. References:

    3.1 GPS Section100, Clause 100.6 Surveying instruments.

    3.2 GPS Section102: Clause 102.20Surface Levels

    3.2 GPS Section200: Clause 200.1 Particular Earthworks Requirement.

    4. Subcontractors:

    N/A

    5. Products:

  • 7/29/2019 MS 1005 R2 Surveying Work

    4/7

    Employer:

    Supervision Committee for the Expansion ofAbu Dhabi International Airport (SCADIA)

    Contractor

    Project Manager / Engineer:

    Project No.: 1008Document Category:

    Method Statement Agreement No.: NRTW-1008-CN

    Project Title:

    Expansion of Abu Dhabi International AirportNew 2K Runway Main Runway Works

    Procedure No.:

    1008-OAJ-MS-1005

    Procedure Title:

    Surveying WorkRevision No: 2

    Page: 4 of 7

    5.1 None (No Permanent Materials)

    6. Tools & Equipments:

    6.1 Survey Equipment Total Station, Theodolite

    6.2 Tripods

    6.3 Ranging Poles, Ranging Rods

    6.4 Measuring tapes, spirit levels, plumb lines

    7. Safety

    7.1 TPS Section : Site Safety and Security

    7.2 CSM Construction Safety Manual

    7.3 Safety Hazards and Precautions

    a. Traffic :- Set out warning signs, plastic glass range flagging and/or barricades asnecessary.

    b. Electrical Lines :- Use only wood or fiber glass range poles or rods when working nearelectrical lines.

    c. Surveyors & chainmen to wear reflective jackets.

    d. All instruments, tripods, carrying cases, surveying tools, will be fitted with stripes ofhighly reflective adhesive tape.

    8. Prior Activities:

  • 7/29/2019 MS 1005 R2 Surveying Work

    5/7

    Employer:

    Supervision Committee for the Expansion ofAbu Dhabi International Airport (SCADIA)

    Contractor

    Project Manager / Engineer:

    Project No.: 1008Document Category:

    Method Statement Agreement No.: NRTW-1008-CN

    Project Title:

    Expansion of Abu Dhabi International AirportNew 2K Runway Main Runway Works

    Procedure No.:

    1008-OAJ-MS-1005

    Procedure Title:

    Surveying WorkRevision No: 2

    Page: 5 of 7

    8.1 Establishing the control point consists of scouting existing reference points on sitewhich are already referenced to existing control points defined and indicated by theEngineer

    8.2 The control points will be protected by concrete surround and by warning tape tosecure the perimeter.

    8.3 Regular monthly checks on the control points will be carried out as part of the QAprocedures.

    8.4 Location of bench marks are checked jointly with the Consultant surveyors and levelsin the drawings are verified accordingly.

    8.5 Review and submit to the Consultant the calibration records for survey instruments tobe used in the work

    9. Procedure:

    9.1 Before proceeding with survey works all survey equipments to be used will becalibrated and the calibration certificates will be submitted to the Consultant.

    Note: This activity is a Hold Point.

    9.2 For ease of reference in daily activities temporary bench marks are established andprotected on site. A duly signed layout drawing showing the location and co-ordinates,will be submitted to the Engineer for future records.

    9.3 At the beginning, setting out of lines will be carried out to check all possibleobstructions prior to commencement of construction.Ground levels are also recorded and records will be jointly signed with the Consultantfor future reference.

    Note: Those G.L. records shall form the basis for Contracts Measurements.

    9.4 The setting out for the Main Secondary Turning points will becarried out by OAJ JVsurveyors then it will be checked by the Engineers Surveyors. A traverse drawingshowing the actual location and coordinates of the T.Ps (where applicable), as well asthe offsets from permanent services will be produced and duly signed by both parties.

    Note: This traverse drawing will be the reference for all future setting out activities.

    9.5 Shop Drawings will then be prepared and submitted to the Engineer for agreementand approval.

    Note: The Shop drawings will be the basis for all the construction activities. Anyamendments must be recorded and monitored. Care should be taken to only usethe latest revision during execution.

  • 7/29/2019 MS 1005 R2 Surveying Work

    6/7

    Employer:

    Supervision Committee for the Expansion ofAbu Dhabi International Airport (SCADIA)

    Contractor

    Project Manager / Engineer:

    Project No.: 1008Document Category:

    Method Statement Agreement No.: NRTW-1008-CN

    Project Title:

    Expansion of Abu Dhabi International AirportNew 2K Runway Main Runway Works

    Procedure No.:

    1008-OAJ-MS-1005

    Procedure Title:

    Surveying WorkRevision No: 2

    Page: 6 of 7

    9.6 For every particular item of work such as pipeline excavation, laying, leveling, manholelocation setting out, invert level, stubs level, cover leveletc. survey checking out is amust to eliminate any possible discrepancy.

    9.7 Surveying during the execution will be carried out by qualified surveyors along with

    experienced chainmen.

    9.8 Latest versions of survey instruments are used such as Total Station, DigitalTheodolite and highly accurate level instruments.In addition to the various accessories such as Ranging Rods, Measuring Tapes,Ranging Poles, Tripodsetc. all survey equipment will be calibrated as mentioned insection 9.1 above.

    9.9 In the cases of pipelines and associated structure every step will be checked.

    9.10 Surveying records will be kept up to date as they will form the basis for payment,measurements sheets and as-built records of the works done on site.

    9.11 Any changes will have to be shown on the final drawings.

    10. Responsibilities:

    10.1 It is the Project Managers duty to ensure that all necessary safety and protectiveequipment are provided along with properly trained and qualified personnel.

    10.2 It is the Site Supervisors duty to organize the work in safe manner and to ensure thatsafety and protective equipment are being properly utilized.

    He must also assure the method statement procedure is followed and must observe

    any hold-points and notify the Consultants for inspection.

    10.3 It is the workers duty to properly wear the protective equipment provided and obey allsafety rules. They must also perform the work as described in the method statementprocedure.

    10.4 The Contract Manager will coordinate with Safety Engineer and ensure that thenecessary resources to implement the approved method statement have beenallocated to the task.

    10.5 The Site Engineer will ensure that the site preparation activities are conductedaccording to the approved method statement.

    10.7 The Material Engineer will ensure that the materials being used are in accordance tothe project specifications and the approved method statement.

  • 7/29/2019 MS 1005 R2 Surveying Work

    7/7

    Employer:

    Supervision Committee for the Expansion ofAbu Dhabi International Airport (SCADIA)

    Contractor

    Project Manager / Engineer:

    Project No.: 1008Document Category:

    Method Statement Agreement No.: NRTW-1008-CN

    Project Title:

    Expansion of Abu Dhabi International AirportNew 2K Runway Main Runway Works

    Procedure No.:

    1008-OAJ-MS-1005

    Procedure Title:

    Surveying WorkRevision No: 2

    Page: 7 of 7

    11. Attachments:

    NONE