MPRWA DEIR Review 3 Brine Disposal

download MPRWA DEIR Review 3 Brine Disposal

of 15

Transcript of MPRWA DEIR Review 3 Brine Disposal

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    1/37

    DRAFT

    Review of Brine Disposal System

    DEIR, Monterey Desal Project

    DRAFT Presentation to Monterey

    Peninsula Regional Water Authority

    23 June 2015

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    2/37

    DRAFT

    Outline

    Brine Disposal System Overview

    Critical Issues

    Near Field Approach

    Semi-Empirical Analysis Conservative assumptions

    Potential weaknesses

    Far Field Approach

    Conservative assumptions

    Potential weaknesses

    Results and Mitigation

    Conclusions

    Recommendations

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    3/37

    DRAFT

    Brine Disposal System

    3

    Monterey Regional Water Pollution Control Agency’s

    (MRWPCA) ocean outfall and diffuser (existing)

    Diffuser

    1,100 ft long 90 – 110 ft deep

    172 ports total

    130 ports open

    8 ft port spacing

     Alternating sides

    Horizontal discharge

    3.5 to 4 ft above

    sea floor Source: Appendix D2

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    4/37

    DRAFT

    Brine Disposal System

    4

    Buoyancy

    Wastewater floats

    High dilution

    Brine sinks

    Lower dilution

    Blend can do either

    wastewater

    brine

    Source: modified from Appendix D2

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    5/37

    DRAFT

    Discharge Composition

    5

    Source: Modified from Appendix D4

    eosyntec C

    consultants

    Tab

    le

    ode

    led fl

    ow

    scenari

      s

    fo r

    the

    PWSP

    RTP

    design capa city witho

    ut

    Desai B

     

    ne

    9  6 0 1

    2

    Desa i Brine wi

    th

    no

    seco

    n

    da

    ry efflue

    nt

    13 98 0 1

    3

    Desa

    i Brinewi

    th

    l

    ow seco

    nd

    ary

    e

    ffl

    uent

    2 13 98 0 1

    4 Desa i Brinewith highsecondary effluent b 19 68 13 98 0 1

    Table M ode led fl

    ow

    scenari  sfor the Vari

    ant pr

    oject

    D

    esa

    i B

    ri

    neonly

    99

    0 1

    2

    Desai Brine wi

    th

    high

    seco

    ndary effluent b

    19 68 8 99 0 1

    3

    D

    esa

    i B

    ri

    ne with

    GWR

    Concentra

    te

    and

    15 9 8 99 0 94° 0 1

    high secondary effluent

    4

    Desai Brine with GWR oncentrate and

    99

    0 94c

    0 1

    no

    seco

    ndary effluent

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    6/37

    DRAFT

    Terminology

    6

    Source: Abessi & Roberts (2014)

    Near Field Far Field

    Source: Jenkins and Wasyl (2009).

    Dominated by jets

    Short time and length

    scales

    Seconds to minutes

    Feet to tens of feet

    Dominated by ocean processes

    Long time and length scales

    Hours to days

    Hundreds of feet to miles

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    7/37DRAFT

    Critical Issues

    Near Field (mixing due to jet/plume velocity/buoyancy)

     Achieving targets at edge of “brine mixing zone” (defined as

    the lesser of the zone of initial dilution (ZID) and 100 m)

    Change in salinity < 2.0 ppt (SWRCB March 2015

    recommendation)

    Concentrations for numerous constituents as per 2012

    California Ocean Plan

    Edge of ZID governs (ZID within 100 m)

    Critical case is when plume sinks

    7

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    8/37DRAFT

    Critical Issues

    Far Field (mixing due to ambient ocean currents)

    Hypoxic: low dissolved oxygen concentration

    Density currents

    Pooling due to bathymetry

    8

    May 5, 2015 Draft Final Desalination

     Amendment to the Ocean Plan

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    9/37DRAFT

    Near Field Approach

    Rising positively-buoyant plume

    When volume of blended wastewater is large enough plume

    will rise

     Analyzed using Visual Plumes (VP)

    Well accepted for rising (buoyant) plumes

    Used appropriate ambient salinity and temperature conditions

     Assumed zero ambient cross-flow (conservative assumption)

    Large dilution (≥ 68) at edge of ZID is achieved 

    Salinity and Ocean Plan objectives easily met

    9

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    10/37DRAFT

    Near Field Approach

    Sinking negatively-buoyant plume

    Considered two approaches:

    Visual Plumes (VP)

    VP is well-validated for rising plumes

    Less validation for sinking plumes (especially for horizontaldischarge)

    Compelling evidence that dilution from VP is substantially under-

    estimated for negatively-buoyant discharges (Palomar et al., 2012)

    CORMIX, CORJET, and JetLag also substantially underestimate

    Dilution results from VP were not used

    Semi-empirical analysis

    Based on analysis by Kikkert et al., (2007) and Fischer et al., (1979)

     Approach is reasonable …

    10

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    11/37DRAFT

    Semi-Empirical Analysis (Near Field)

    Plume trajectory based on

    analysis by Kikkert et al. (2007)

    Well validated by experiments

    Dilution based upon analysis

    for non-buoyant jet (Fischer et

    al., 1979) using plume length

    calculated along trajectory

    Fischer approach is reasonable due to flat trajectory

    [vertical distance (3.5 feet)

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    12/37DRAFT

    Semi-Empirical Analysis (Near Field)

    Conservative assumptions

    Dilution calculation assumed round jet, whereas jet is oval

    shaped

    Oval shape has higher area to volume ratio and will achieve

    more dilution than circular shape

     Assumed minimum height above sea-floor of 3.5 feet (only

    19 ports have height of 3.5 feet, most ports have height

    nearer to 4 feet)

    Larger height will allow for longer travel distance and moredilution

    12

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    13/37DRAFT

    Semi-Empirical Analysis (Near Field)

    Conservative assumptions

    The dilution at the impact point was used in the analysis.

    However, the near-field continues beyond the impact point

    (the flow and mixing are still dominated by jet processes)

    and additional dilution will occur within the near field (i.e.,the ZID is larger than assumed)

    “the increase in dilution

    from the impact point to

    the end of the near field

    is approximately 60%for nonmerged jets”

    (inclined jets,

     Abessi & Roberts, 2014)

    13

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    14/37DRAFT

    Semi-Empirical Analysis (Near Field)

    Potential Weaknesses

     Analysis used in DEIR to assess merging of jets is ad-hoc

    Volume of water entrained in 10 seconds was compared to

    volume of water available per port

    Merging of jets will reduce dilution

    Recommend replacing analysis in EIR with improved Port

    Spacing Analysis by Geosyntec (provided on Slide 16)

    Coanda effect is not addressed in DEIR

    Coanda effect is the tendency for a jet to deviate towards andattach to near surfaces (in this case the sea-floor)

    Coanda attachment would reduce dilution

    Recommend including new Coanda Analysis by Geosyntec in

    EIR (provided on Slide 17)

    14

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    15/37DRAFT

    Semi-Empirical Analysis (Near Field)

    Potential Weaknesses

    Existing ports are horizontal which is not optimal for

    negatively-buoyant discharges

    Consider retrofit with inclined ports if additional dilution is

    required

    15

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    16/37DRAFT

    Port Spacing Analysis

    Based on experiments Abessi & Roberts (2014)

    recommend the following to avoid merging of jets;

    s >~2.d.F

    where s = spacing, d = port diameter, and F = densimetric

    Froude number

    d = 1.86 inches (Appendix D2, Table 3)

    F ≈ 26 (Appendix D1, Table 5) 

    → s > ~ 8 ft

    Port spacing on diffuser is 16 ft (alternating sides)

    Jets will not merge

    Same conclusion as in DEIR, but this analysis is more robust

    16

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    17/37DRAFT

    Coanda Analysis

    Based on experiments Shao & Law (2011) recommend

    the following minimum clearance above the sea-floor to

    prevent Coanda attachment;

    z0 > 0.12 (π/4)0.25 d.F = 0.11 d.F

    where, d = port diameter, and F = densimetric Froudenumber

    d = 1.86 inches (Appendix D2, Table 3)

    F ≈ 26 (Appendix D1, Table 5)

    → z0 > ~ 0.5 ft

    Ports are 3.5 ft above sea-floor

    Coanda attachment will not occur

    Include this analysis in EIR

    17

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    18/37DRAFT

    Far Field Approach

    Uses regional ocean model (ROM) to extract time-series

    of horizontal velocities (u and v) at diffuser location

    Examines different seasonal patterns

    Oceanic, Davidson, Upwelling

     Assumes the velocity field (u,v) is spatially homogeneous

    Generally conservative assumption

    Neglects local variations in bathymetry

    Bathymetry in vicinity of brine plume is generally flat (no

    depressions or ridges) and sloping to sea

    Brine plume does not extend to Monterey Canyon

    Diffuser structure may act as a ridge to trap brine locally

    Solves 2-D advection-diffusion

    18

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    19/37DRAFT

    Far Field Approach

    Conservative assumptions

    Neglects vertical mixing

    Mixing and dilution underestimated away from the diffuser

    Stability was examined via computing Richardson number

    Uses low-end lateral diffusion coefficient

    1.37 m2/s (versus 2 m2/s measured by Ledwell et al., (1998))

    Neglects wave action

    Waves provide additional mixing

    Neglects gravity current

    Gravity current would tend to move brine away from diffuser

    more quickly (down-slope)

    19

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    20/37DRAFT

    Far Field Potential Weaknesses

    Present analysis is “dated”

    Modern approach would use full 3D model including density

    effects and spatially varying velocity field

    However, present analysis is generally conservative

    3D model will likely result in additional dilution

    Neglects gravity currents

    Unlikely to affect conclusions, since bathymetry is generally

    flat in vicinity of diffuser

    Brine plume does not reach Monterey Canyon

    20

     Appendix D1, page 8

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    21/37DRAFT

    Far Field Potential Weaknesses

    Brine particles are only tracked for 48 hours

    Simulation period is 90 days

    What happens to particle after 48 hours?

    If particle simply disappears then will the extent of the plume be

    underestimated?

    Unlikely to affect conclusions, since exceedances are

    governed by near field

    21

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    22/37

    DRAFT

    Far Field Potential Weaknesses

    Local trapping of brine by diffuser structure was not fully

    addressed

    Trapping is minimized by aligning diffuser structure with

    slope (perpendicular to shore)

    Recommend adding discussion of this issue consideringcurrent directions (from ROM) with respect to diffuser

    alignment and tidal reversals

    Potential for hypoxia was not addressed Recommend including Hypoxia Analysis by Geosyntec in

    EIR (provided on Slides 23-25)

    22

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    23/37

    DRAFT

    Hypoxia Analysis

    Potential for hypoxia can be addressed using simple

    mass balance approach;

    Estimate oxygen demand from sediments

    Estimate oxygen supplied by brine plume (including entrained

    flow)

    23

    Sediment oxygen demand

    Entrainment of dissolved oxygen

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    24/37

    DRAFT

    Hypoxia Analysis

    Sediment oxygen demand (SOD) in Monterey Bay

    5.0 to 13.5 mmol/m2/day (Berelson et al., 2003)

    0.16 to 0.43 g/m2/day

     Areal extent of plume

    ~3,000 ft x 1,500 ft = 4,500,000 ft2

    ~420,000 m2

    Mass flux consumed;

    70 to 180 kg/day

    24

    Figure 4.3-5

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    25/37

    DRAFT

    Hypoxia Analysis

    Brine flow rate = 13.98 MGD

    Dilution > 15

    Entrained flow > 15 x 13.98 = 210 MGD = 9.2 m3/s

     Ambient dissolved oxygen concentration > 7 mg/L lower limit of Ocean Plan

    Mass flux supplied;

    > 5,600 kg/day

    Oxygen supplied by entrained flow > 30 times greater

    than oxygen consumed by sediments

    Hypoxia unlikely

    25

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    26/37

    DRAFT

    Results and Monitoring

    Results of analyses indicate some exceedances of

    Ocean Plan criteria at edge of ZID are possible for

    certain constituents;

    Copper, Ammonia, Chlordane, DDT, PCBs, TCDD

    Equivalents, Toxaphene

    Depends upon Project versus Variant and on flow blends

    Monitoring program may indicate no exceedances

    Many conservative assumptions in analysis

    Drawing source water through sand/sediments will likely

    remove some PCBs

    Will this cause a build up of PCBs in sediments?

    26

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    27/37

    DRAFT

    Mitigation Measures

    Proposed Mitigation Measure 4.3-4

     Additional pre-treatment of source water

    Treatment of discharge

    Temporary storage and release of brine

    3 million gallon brine storage basin

    Store 5 to 8 hours of flow

    Can pulsing achieve necessary dilutions?

    Recommend conducting additional near-field analysis to

    demonstrate (if necessary)

    Consider retrofit of diffuser to add inclined ports

    60o – 65o is optimal for negatively-buoyant

    Need to also consider buoyant cases (trade-off)

    27

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    28/37

    DRAFT

    Brine Disposal System - Conclusions

    Brine disposal governed by near field

    Concentrations at ZID

    DEIR used two methodologies for near field Visual Plumes for rising discharges

    Semi-empirical analyses for sinking discharges

    Trajectory for sinking plume from Kikkert et al., (2007)

    Dilution for sinking plume estimated using method for non-

    buoyant jet (Fischer et al., 1979)

    28

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    29/37

    DRAFT

    Brine Disposal System - Conclusions

    Near field analyses make reasonable and conservative

    assumptions

    Round jets (instead of oval)

    Minimum height of port above sea-floor of 3.5 feet ZID defined as jet impact point and not end of near field

    29

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    30/37

    DRAFT

    Brine Disposal System - Conclusions

    Near field analysis of merging jets was ad-hoc New analysis by Geosyntec indicates jets will not merge

    Near field analysis of Coanda attachment was not

    included

     Analysis by Geosyntec indicates Coanda attachment will not

    occur

    Near field analysis was not performed to demonstrate

    extent of increased dilution due to pulsing

    Mitigation measure 4.3-4

    30

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    31/37

    DRAFT

    Brine Disposal System - Conclusions

    Far field analyses makes conservative assumptions

    No vertical mixing of brine

    Low-end estimate for horizontal diffusivity

    Neglects wave action

    No density current*

    Far field method is “dated”

    3D simulations including density currents could be used 3D simulations would likely result in more dilution

    Flat bathymetry in the vicinity of the diffuser and conservative

    assumptions

    31

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    32/37

    DRAFT

    Brine Disposal System - Conclusions

    Potential for hypoxia not discussed

     Analysis by Geosyntec indicates hypoxia is unlikely

    Brine trapping by diffuser structure not analyzed Minimized by aligning diffuser structure with slope

    (perpendicular to shore)

    Brine particles are only tracked for 48 hours

    What happens to particle after 48 hours?

    32

    Brine Disposal System

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    33/37

    DRAFT

    Brine Disposal System -

    Recommendations

    Include the following analyses provided by Geosyntec

    Port merging

    Coanda effect

    Hypoxia

     Address/discuss potential for build up of PCBs in

    sediments surrounding intakes

    Conduct additional near field analysis to estimate

    additional dilution achievable by pulsing brine discharge

    Consider retrofit of diffuser ports with inclined angles to

    achieve more dilution if necessary

    33

    Brine Disposal System

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    34/37

    DRAFT

    Brine Disposal System -

    Recommendations

     Add discussion of potential for diffuser structure to trap

    brine

    Consider current directions (from ROM) and bathymetry

    slope with respect to diffuser alignment and tidal reversals

    Consider using 3D far field model

    Will likely result in additional dilution

    Will better address potential for brine trapping by diffuser

    structure

     Add discussion of the effect of only tracking brine

    particles for 48 hours

    34

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    35/37

    DRAFT

    Recommended Minor Edits

    35

    Issue Descr ipt ion Page Comments / RecommendationsIncorrect

    interpretation

    of SWRCB

    2012a

    SWRCB 2012a states that increase

    in salinity should be limited to < 5%

    of background, corresponding to 1.7

    ppt in California waters. The DEIR

    then rounds this to 2.0 ppt, but this

    is an incorrect interpretation of the

    2012 document (i.e., it should be 1.7

    ppt).

    4.3-27 The phrase, “(rounded to 2.0 ppt)” should be

    removed from the EIR. Note that SWRCB 2015

    refers directly to 2.0 ppt (it does not refer to 5% or

    1.7 ppt). That is, 2.0 ppt is the correct target per

    SWRCB 2015, but not per SCWRCB 2012a.

    Different

    number of

    ports

    The correct number of open ports

    (130) is first mentioned in Section

    4.3. This is late in the report to

    mention the change (from 120) and

    surprises the reader.

    4.3-72 The incorrect number of ports should be mentioned

    earlier in the EIR, including in the Executive

    Summary. It should also be re-iterated that using

    130 instead of 120 provides additional dilution (as

    demonstrated in Addendum to Appendix D4).

    Misleading

    statement

    overstates theextent of the

    plume

    The DEIR states, “where the plume

    extended from near the Monterey

    Submarine Canyon rim to the centerof the southern half of Monterey

    Bay”. This statement overstates the

    extent of the plume, and is perhaps

    mistakenly based on the inset figure.

    4.3-88 Revise wording to better indicate that the plume

    extent is several miles from the Monterey Submarine

    Canyon rim.

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    36/37

    DRAFT

    Recommended Minor Edits

    36

    Issue Descr ipt ion Page Comments / RecommendationsUnnecessary

    footnote in

    table

    See Comments / Recommendations Table

    4.3-11

    Footnote ‘a’ should be removed and the column

    header changed from “Average Dilution” to

    “Centerline Dilution”.

    Equation for

    centerline

    dilution not

    provided

    Equation (7) presented in Appendix

    D2 is for average dilution, whereas

    calculations provide centerline

    dilution (which is ~1.4 times lower

    (Fischer et al., 1979)).

     App D2,

    pages 10

    and C-13

    EIR should be modified to include the relation

    between average and centerline dilution.

     Apparent

    discrepancy in

    port and

    duckbill size

    4 inch duckbill valves are specified,

    but the port size is given as 2 inch.

     App D2 This discrepancy should be corrected or explained.

  • 8/21/2019 MPRWA DEIR Review 3 Brine Disposal

    37/37

    References

    1.  Abessi & Roberts (2014), Multiport Diffusers for Dense Discharges, J. Hydraul. Eng. 04014032-1.

    2. Berelson, McManus, Coale, Johnson, Burdige, Kilgore, Colodner, Chavez, Kuleda, Boucher

    (2003), A time series of benthic flux measurements from Monterey Bay, CA, Continental Shelf

    Research 23 (2003) 457-481. 

    3. Fischer, List, Koh, Imberger, Brooks (1979), “Mixing in Inland and Coastal Waters”, Academic

    Press 

    4. Jenkins & Wasyl (2009), Current Analysis for Receiving Water of the Santa Cruz SeawaterDesalination Project, submitted to City of Santa Cruz, 49 pp + app.

    5. Kikkert, Davidson, Nokes (2007), Inclined Negatively Buoyant Discharges, J. Hydraul. Eng.

    2007.133:545-554. 

    6. Ledwell, Watson, Law, Law, (1998), Mixing of a tracer in the pycnocline, Journal of Geophysical

    Research, 103(C10), 21499-21529. 

    7. Palomar, Lara, Losada (2012), Near field brine discharge modeling part 2: Validation of

    commercial tools, Desalination 290 (2012) 28-42. 

    8. Shao & Law (2011), Boundary impingement and attachment of horizontal offset dense jets,

    Journal of Hydro-environment Research 5 (2011) 15-24.