Movement 2

26
8/24/04 Paul A. Jensen Operations Research Models and Methods Copyright 2004 - All rights reserved Material Movement The movement of material through the production facility is a waste because material movement does not add value to the product.

description

Movement 2

Transcript of Movement 2

Page 1: Movement 2

8/24/04

Paul A. JensenOperations Research Models and Methods

Copyright 2004 - All rights reserved

Material Movement

The movement of material through the production facility is a waste because

material movement does not add value to the product.

Page 2: Movement 2

2

The amount of movement depends on: the set of products manufactured, the sequence of operations (process) identified for

each product, the assignment of machines to the operations of the

processes, and the layout of the machines in the manufacturing

facility.

Here we assume that the first two are fixed and we concentrate on the latter two.

Page 3: Movement 2

3

The several generic types of layout

M1 M2

M3

M5

M4

M7

M6

Offices

The Job shop

M1

M2

M3

M5

M4

M7

M6

Offices

The assembly line or flow shop

Offices

M3

M2

M1

M4

M7M1

M5

M6M2

M7

M2

M3

M4

M6

Group technology

Page 4: Movement 2

4

Example Orders for products arrive as Poisson processes. Processing begins when an order arrives. Operations are performed in a numerical sequence. There are no losses in the operations.

Operation Times (hours/unit)

PRODUCTS

Operation A B C D E F G H I J K L

1 Mould 0.1 0.1 0.2 0.2 0.3 0.1 0.4 0.6 0.7 0.4 0.1 0.1

2 De-fraze 0.3 0.5 0.2 0.1 0.2

3 Barrel Polish 0.3 0.6 0.2 0.2

4 Test 0.4 0.1 0.3

5 Machine 0.4 0.2 0.2 0.3 0.4

6 Paint 0.2 0.2 0.2 0.2 0.2 0.2 0.6

7 Sub-assemble 0.1 0.3 0.2 0.3 0.1 0.1

8 Chemical Test 0.2

9 Dimensional insp. 0.1 0.3 0.1 0.2 0.5 0.4 0.2 0.2

10 Final insp. 0.4 0.4 0.2 0.3 0.3 0.2 0.2 0.4 0.1 0.2 0.3 0.3

Weekly Demand 100 200 50 300 80 40 120 200 250 100 120 180

Page 5: Movement 2

5

Machine information Each operation requires a unique machine. All machines operate 40 hours per week. Assume operation times have an exponential

probability distribution. Provide enough machines so that all

workstations are to have no more than 80% utilization.

Page 6: Movement 2

6

Space and Economic Information

WIP requires 0.4 sq. m. floor space per unit. Provide sufficient space at each station to

accommodate WIP 90% of the time. Transportation cost is $0.10/unit-meter Use a plant with length twice as great as width. The cost of the plant is $20 per week per square

meter.

Operation 1 2 3 4 5 6 7 8 9 10

Machine Size (sq.m.) 2 3 4 5 4 3 2 3 4 1

Machine cost ($/week) 50 30 40 30 100 80 60 20 70 40

Value Added ($) 10 1 2 1 3 1 2 2 1 1

Page 7: Movement 2

7

Design a plant that uses a job shop (or functional) layout

M1M2

M3

M5

M4

M7

M6

Offices

Page 8: Movement 2

8

Step 1: Queuing Analysis Do a Queuing Analysis for each

machine type

Machine 1 2 3 4 5 6 7 8 9 10

Arrival Rate

Service Rate

Number of Mach.

Spaces for WIP

Page 9: Movement 2

9

Queuing Analysis

Machine 1 2 3 4 5 6 7 8 9 10

Arrival Rate 1740 850 520 440 540 1270 760 200 1120 1740

Service Rate 129 158 125 114 129 156 197 200 187 142

Number of Mach. 17 7 6 5 6 11 5 2 8 16

Spaces for WIP 4 5 3 6 3 3 6 1 4 3

Page 10: Movement 2

10

Step 2: Space Analysis Find the space requirements of each

machine type. Find the space required for WIP.

Machine 1 2 3 4 5 6 7 8 9 10

Number

Space

Space for WIP

Total Space

Page 11: Movement 2

11

Space analysis

Machine 1 2 3 4 5 6 7 8 9 10

Number 17 7 6 5 6 11 5 2 8 16

Space for Mach. 34 21 24 25 24 33 10 6 32 16

Space for WIP 2 2 2 3 2 2 3 1 2 2

Total Space 36 23 26 28 26 35 13 7 34 18

Space for Plant 246 Sq. M.

Page 12: Movement 2

12

Step 3: Flow Analysis Construct the from-to chart for weekly

flowsMachine 1 2 3 4 5 6 7 8 9 10

1

2

3

4

5

6

7

8

9

10

Page 13: Movement 2

13

Step 4: Construct a Layout Use a plant dimension of 12x24 with

area 288 sq. m.1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

1

2

3

4

5

6

7

8

9

10

11

12

Page 14: Movement 2

14

Step 5: Economic Analysis Plant cost: Machine cost: Transportation Cost Cost of WIP Total Cost:

How will these costs change with larger lot sizes?

Page 15: Movement 2

15

Design a plant that uses a flow shop layout We assume that each product visits each station but

receives no processing at some stations. What do you think changes with respect to the

functional layout?

M1

M2

M3

M5

M4

M7

M6

Offices

Page 16: Movement 2

16

Queuing and space analyses

Machine 1 2 3 4 5 6 7 8 9 10

Arrival Rate

Service Rate

Number of Mach.

Spaces for WIP

Machine 1 2 3 4 5 6 7 8 9 10

Number

Space

Space for WIP

Total Space

Queuing analysis

Space analysis

Page 17: Movement 2

17

Flow Analysis Construct the from-to chart for weekly

flowsMachine 1 2 3 4 5 6 7 8 9 10

1

2

3

4

5

6

7

8

9

10

Page 18: Movement 2

18

Economic analysis Plant cost: Machine cost: Cost of WIP at machines: Cost of WIP in material movement: Total Cost:

Page 19: Movement 2

19

Design a plant that uses a separate line for each product Let moulding and final inspection be

separate departments What will be different in this type of

layout?

Page 20: Movement 2

20

Queuing and space analyses for each product

Product A

Machine 1 2 3 4 5 6 7 8 9 10

Arrival Rate

Service Rate

Number of Mach.

Spaces for WIP

Total Space

Product B

Machine 1 2 3 4 5 6 7 8 9 10

Arrival Rate

Service Rate

Number of Mach.

Spaces for WIP

Total Space

Page 21: Movement 2

21

Economic Analysis Plant cost: Cost of WIP at machines: Cost of WIP in material movement: Total Cost:

How does this cost relate to the cost of a functional layout?

Page 22: Movement 2

22

Design a plant that uses group technology Let moulding and final inspection be separate departments

Offices

M3

M2

M1

M4

M7M1

M5

M6M2

M7

M2

M3

M4

M6

Page 23: Movement 2

23

Grouped operations and families of products

PRODUCTS GROUP

Operation A B C D E F G H I J K L 1 2 3

1 Mould 0.1 0.1 0.2 0.2 0.3 0.1 0.4 0.6 0.7 0.4 0.1 0.1 x x x

2 De-fraze 0.3 0.5 0.2 0.1 0.2 x

3 Barrel Polish 0.3 0.6 0.2 0.2 x

4 Test 0.4 0.1 0.3 x

5 Machine 0.4 0.2 0.2 0.3 0.4 x x

6 Paint 0.2 0.2 0.2 0.2 0.2 0.2 0.6 x x x

7 Sub-assemble 0.1 0.3 0.2 0.3 0.1 0.1 x x

8 Chemical Test 0.2 x

9 Dimensional insp. 0.1 0.3 0.1 0.2 0.5 0.4 0.2 0.2 x x

10 Final insp. 0.4 0.4 0.2 0.3 0.3 0.2 0.2 0.4 0.1 0.2 0.3 0.3 x x x

Weekly Demand 100 200 50 300 80 40 120 200 250 100 120 180

Family 1 x x x x

Family 2 x x x x

Family 3 x x x x

Page 24: Movement 2

24

Queuing and space analysis for each family

Family 1

Machine 1-2 1-6 1-8 1-9

Arrival Rate

Service Rate

Number of Mach.

Spaces for WIP

Total Space

Family 2

Machine 2-5 2-6 2-7

Arrival Rate

Service Rate

Number of Mach.

Spaces for WIP

Total Space

Family 3

Machine 3-3 3-4 3-5 3-6 3-7 3-9

Arrival Rate

Service Rate

Number of Mach.

Spaces for WIP

Total Space

Page 25: Movement 2

25

Flow AnalysisMachine 1 1-2 1-6 1-8 1-9 2-5 2-6 2-7 3-3 3-4 3-5 3-6 3-7 3-9 10

1

1-2

1-6

1-8

1-9

2-5

2-6

2-7

3-3

3-4

3-5

3-6

3-7

3-9

10

Page 26: Movement 2

26

Economic Analysis Plant cost: Cost of WIP at machines: Cost of WIP in material movement: Total Cost: