May 12, 2016
CEU Honolulu
![Page 2: Monument Meeting Slide Presentation May 2016a (1)...Current Schedule • May‐June 2016: Finalize Work Plan • May‐August 2016: Assemble Gear/Equipment • August 13 2016: Charter](https://reader033.fdocuments.in/reader033/viewer/2022051915/6006f7daf4e991175b45aa24/html5/thumbnails/2.jpg)
Kure
Oahu
Kure Atoll Remediation Project Update
![Page 3: Monument Meeting Slide Presentation May 2016a (1)...Current Schedule • May‐June 2016: Finalize Work Plan • May‐August 2016: Assemble Gear/Equipment • August 13 2016: Charter](https://reader033.fdocuments.in/reader033/viewer/2022051915/6006f7daf4e991175b45aa24/html5/thumbnails/3.jpg)
Background
• 1991‐1992: USCG/USACE conducted sampling for PCBs
• 1993: Reburied 800 cubic yards of soils; 36 cyds removed off island
• 1993‐1994: Post remediation sampling/reporting
• 2008‐2012: SI/Alternative remediation testing
• 2012 – A Engineering Eval/Cost Analysis performed
• 2014 – Contract awarded for remediation.
• 2015 – Treatability study conducted.
• 2016 – Remedial Action
![Page 4: Monument Meeting Slide Presentation May 2016a (1)...Current Schedule • May‐June 2016: Finalize Work Plan • May‐August 2016: Assemble Gear/Equipment • August 13 2016: Charter](https://reader033.fdocuments.in/reader033/viewer/2022051915/6006f7daf4e991175b45aa24/html5/thumbnails/4.jpg)
Project Plan
• Remediate through reburial upto 900 cuyds of PCB soils
• Prepare the new burial site with AC and additives to enhance microbial breakdown
• Install piezometers /biota sampling
![Page 5: Monument Meeting Slide Presentation May 2016a (1)...Current Schedule • May‐June 2016: Finalize Work Plan • May‐August 2016: Assemble Gear/Equipment • August 13 2016: Charter](https://reader033.fdocuments.in/reader033/viewer/2022051915/6006f7daf4e991175b45aa24/html5/thumbnails/5.jpg)
Current Schedule
• May‐June 2016: Finalize Work Plan
• May‐August 2016: Assemble Gear/Equipment
• August 13 2016: Charter Vessel Kahana departs Honolulu for Midway Island
• August 17 2016: Kahana picks up field crew at Midway and proceeds to Kure Atoll
• August 19‐20 2016: Begin Field Effort on Green Island
• September 9 2016: End Field Effort‐crew returns to Midway