Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT OCTOBER, 2018 RAS OFFICERS’ INSTITUTE (CLUB HOUSE) (2, institutional Area, Near Dainik Bhaskar, Jaipur) Developers: M/S RAS Officers’ Institute 2, institutional Area, Near Dainik Bhaskar-Jaipur

Transcript of MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf ·...

Page 1: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

Prepared By

SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS)

MONTHLY PROGRESS REPORT

OCTOBER, 2018

RAS OFFICERS’ INSTITUTE (CLUB HOUSE)

(2, institutional Area, Near Dainik Bhaskar, Jaipur)

Developers: M/S RAS Officers’ Institute

2, institutional Area, Near Dainik Bhaskar-Jaipur

Page 2: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

Project Highlights

Total Built up Area: - 1, 20,000Sq.ft

Total Floor of Project: -2 Basement + 6 Floors

(Gym, Swimming pool, Banquet hall, Conference hall, Bar, Tennis& Squash)

Builders & Developers

M/S RAS Officers’ Institute,

Registered office at 2, institutional Area,

Near Dainik Bhaskar- Jaipur (Raj.)

Consultants & Management Team

Architectural Consultant Project Management Consultants

Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40, 4th Floor, Trinity Mall,

New Sanganer Road Sodala- Jaipur New Sanganer Road, Jaipur

Mr. Lokesh JoshiMob: 91-9680282624. Phone: 91-9314932438, 0141 5106606

Mr. Kulvinder Singh Mob: 91-9314480610

Structural Consultant MEP Consultant M/S SANRACHNA M/S Cube Consultant

S-41, AMBA BARI, JAIPUR A-8, Jamna Nagar Sodala- Jaipur

Mr. Sandeep Garg Mob: 91-9799496696 Mr. Sanjay Vajpayee Mob: 91-9214308430

Interior Designer Consultant M/S Sthapatya Architects A-58 Shanti path, Tilak Nagar, JAIPUR

Ms. Ritu Khandelwal Mob: 91-9829016773

Page 3: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

Contractor Agencies

Civil Contractor Electrical Work Contractor

M/S H. R. Gwala M/S Vijay Electric service

F9/465, Chitrakoot, Vaishali Nagar-Jaipur VivekVihar, New Sanganer Road, Sodala.

Mr. H.R. Gwala Mob: 91-9783940001 Mr. Shyam Vijay Mob: 91-9783300501

Plumbing Contractor Waterproofing Contractor M/S Gayatri Plumbing M/S NS Solutions

B-50, Jawahar Nagar, Jaipur 3/77, Agarwal Farm, Mansarovar, Jaipur

Mr. Jeet Ram Mob: 91-9829008082 Mr. Shrikant Dandia Mob: 91-9214529486

Fire Fighting Contractor False Ceiling Contractor

M/S Men At Work M/s Shakuntalam Interiors Pvt. Ltd.

S-3, CD 304, Dadudayal Residency, 100-A, Civil Lines, Ajmer Road, Jaipur

Dadudayal Nagar, Mansarover, Jaipur. Mr. Sandeep Tholiya Mob: 91-9829059622

Mr. Ravi Kumawat Mob: 91-9928084922

Heating, ventilation, and air conditioning (HVAC)

Daikin Air conditioning India Pvt. Ltd (Higher Side)

S-10-11-12, Second Floor, Geejgarh Tower, Hawa Sadak

Jaipur,302006

M/s K.P. Airtech (Lower Side)

Yashoda Nikunj,BB-51, Jai Ambey Nagar, Tonk Road,

Jaipur – 203018, Rajasthan.

Mr. K.K. Sharma Mob: 91-9829063283

Page 4: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

4 | P a g e

INDEX

S. No. Content Page. No.

(i) Executive Summary 5

(ii) Project View 5

(iii) Milestone Achieved: At Execution Level 6

(iv) Manpower & Material Status 6-8

(v) Proposed Schedule & Material Procurement Details 8-11

(vi) Drawing Status 12

(vii) Progress Photographs 13-17

(viii) Pending Decisions & Requirements 18

Distribution to:-

(i) RASO’I Members

(ii) Architect Design & Services (ADS)-Architectural Consultant

(iii) Sthapatya- Interior Designer

Page 5: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

5 | P a g e

EXECUTIVE SUMMARY

Terrace floor OHWT R/W & Slab shuttering,bar binding & casting 90% completed.

UGWT Excavation work in completed.

UGWT Raft & R/W casting completed.

Fourth & fifth floor brick masonry work in 95% completed.

Fourth Floor Plastering work completed & Fifth Floor Plastering work in progress.

First & Second floor low-voltage wall conducting work in progress.

Ground & first floor electrical ceiling conducting work 90% completed as per Drawings.

HVAC copper piping work in progress at ground floor & first floor ducting work in progress.

Fire Staircase fifth floor LVL. BB, Shuttring & Casting Completed.

Plumbing work in progress at fourth floor.LVL.

West , North & South Side Boundary Wall in progress.

PROJECT VIEW as on 31st

OCTOBER 2018

Page 6: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

6 | P a g e

MILESTONES ACHIEVED

(i) At Execution Level:-

(i) Terrace floor OHWT concreting (casting) completed.

(ii) Casting of terrace floor columns concreting (casting) completed.

(iii) West & South side Boundary wall Stone masonry work started.

(iv) Fifth Floor Plastering work 70% Completed.

(v) HVAC copper piping work 80% Completed as per Drawings.

(vi) Electrical Wall conducting work Completed at Third floor.

(vii) UGWT Excavation work Competed.

(viii) UGWT R/W work Competed.

(ii) At Decision Level:-

MANPOWER DEPLOYED AT SITE STATUS

Total Manpower Deployed at Site by different Agencies / Vendors

Manpower Details Till 31st

October‘18

S. No. Name of Contractor Work Skilled Unskilled Total

1.0 H.R. Gwala Civil Work 60 290 350

1.1 SK Burman/ (H.R. Gwala) Shuttering 90 150 240

1.2 Govind/(H.R. Gwala) Bar Binding 80 120 200

1.3 Ashok/ (H.R. Gwala) Brick Work 220 240 460

1.4 Bharosi/ (H.R. Gwala) Plaster Work 248 270 518

2.0 Vijay Electrical Service Electrical 105 100 205

3.0 Gayatri Plumbing Plumbing 55 100 155

4.0 NS Solutions Waterproofing 0 0 0

5.0 Man At Work Fire Fighting 50 130 180

6.0 WhiteWash White Wash 20 40 60

7.0 K.P. Airtech HVAC 70 90 160

Total 998 1530 2528

Page 7: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

7 | P a g e

MATERIAL STATUS

A. Steel Received & Consumed Details in October‘18

Diameter of Bar Received Till

Date (MT)

Received in

October ’18

(MT)

Consumed in

October ’18

(MT)

Total

Consumed

till Date

(MT)

Balance at

Site as on

31.10.18 (MT)

8mm 85.68

- 2.00 84.68 1.00

10mm 210.02

3.057 2.05 206.02 4.00

12mm 107.16

8.393 7.73 102.16 5.00

16mm 55.09

- - 55.09 0.00

20mm 73.59

- 4.00 73.59 1.50

25mm 179.52

- 0.50 177.02 2.50

32mm 132.21

- - 132.21 0.00

Total (MT) 843.30

- 16.28 830.77 14.00

B. Cement Consumed & Received Details in month of October ’18

Location Received

Till Date

(Bags)

Received in

October ’18

(Bags)

Consumed

Till Date

(Bags)

Consumed in

October’18

(Bags)

Balance at

Site as on

31.10.18

(Bags)

Remarks

At Site 35357 1900 35257 2080 100

At RMC

Plant

5792-

372=5420

0 5420 0 0 372 Bags Amount

adjusted in Vendor’s

Bill

Total (Bags) 40777 1900 40677 2080 100

Aggregate Consumed & Received Details in month of October ’18

(i) 10mm Aggregate

Location Received

Till Date

(C.Ft)

Received in

October’18

(C.Ft)

Consumed

Till Date

(C.Ft)

Consumed in

October ’18

(C.Ft)

Balance at Site

as on 31.10.18

(C.Ft)

Remarks

At Site 49059 1520 48559 1120 500

At RMC

Plant

11506 - 12271 - 0 Excess 765 C.ft Amount

adjusted in Vendor’s Bill

Total (C.Ft) 60565 1520 60830 1120 500

(i) 20mm Aggregate

Location Received

Till Date

(C.Ft)

Received in

October’18

(C.Ft)

Consumed

Till Date

(C.Ft)

Consumed in

October ’18

(C.Ft)

Balance at Site

as on 31.10.18

(C.Ft)

Remarks

At Site 82090 4560 81290 4660 800

At RMC

Plant

17911 - 18130 - 0 Excess 219 C.ft Amount

adjusted in Vendor’s Bill

Total (C.Ft) 100001 4560 99420 4660 800

Page 8: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

8 | P a g e

Sand Consumed & Received Details in month of October ’18

Location Received

Till Date

(C.Ft)

Received in

October’18

(C.Ft)

Consumed

Till Date

(C.Ft)

Consumed in

October ’18

(C.Ft)

Balance at Site

as on 31.10.18

(C.Ft)

Remarks

At Site 101373 5221 100773 5869 600

M.Sand

(Site)

37175 9357 36675 3800 500

At RMC

Plant

18112 - 18100 - 0 12 C.ft Amount adjusted

in Vendor’s Bill

Total (C.Ft) 156660 14578 155548 9669 1100

C. Bricks Consumed & Received Details in month of October ’18

Location Received

Till Date

(Nos.)

Received in

October’18

(Nos.)

Consumed Till

Date (Nos.)

Consumed in

October ’18

(Nos.)

Balance at Site

as on 31.10.18

(Nos.)

At Site 424000 43000 404000 27000 20000

Total (Nos.) 424000 43000 404000 27000 20000

D. AAC Block Consumed & Received Details in month of October ’18

Location Received

Till Date

(Nos.)

Received in

October’18

(Nos.)

Consumed Till

Date (Nos.)

Consumed in

October ’18

(Nos.)

Balance at Site

as on 31.10.18

(Nos.)

At Site 7182 960 6582 1160 600

Total (Nos.) 7182 960 6582 1160 600

PROPOSED SCHEDULES FOR THE MONTH OF NOVEMBER ‘18

Following activities are planned for the Month of November ‘18

(i) Completion of O.H. Water Tank shuttering, bar binding & casting work.

(ii) Completion of Fire Staircase Mummty Slab bar binding, shuttering & Casting work.

(iii) Completion of Fifth Floor brick work.

(iv) Earth filling in surrounding areas of building.

(v) Lower Basement & Ground Floor Plumbing Drainage & Toilets Internal Piping Works.

(vi) U.G. Water tank shuttering, bar binding & concreting (casting) work.

(vii) Ground Floor Electrical Wiring, Modular Box Fixing & Ceiling Conducting Works.

(viii) Ground Floor Fire Alarm wiring work. (Fire Fighting).

(ix) First Floor HVAC Duct making, Installation & copper Piping of ground floor.

(x) South & East Side Boundary wall foundation & brick work.

(xi) Fifth Floor & Staircase Plastering Work.

(xii) Lower & Upper Basement VDC (Trimix) flooring work.

(xiii) Ground Floor False Ceiling Frame Fixing Work.

Page 9: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

9 | P a g e

STEEL & CEMENT REQUIREMENT FOR THE MONTH OF NOVEMBER ‘18

A. Steel Requirement Detail for the Month of November‘18

S. No. Location of Use Dia. Of Bars # Required

Quantity (MT)

Available at

Site (MT)

Net Required

Quantity (MT)

1.

Terrace Floor Beam for

Truss Structure

8mm 1.00 1.00 -

10mm 0.00 4.00 -

12mm 0.00 5.00 -

16mm 2.00 0.00 2.00

20mm 2.00 1.50 0.5

25mm 3.00 2.50 0.5

32mm - 0.00 -

Total Qty Required (MT) 8.0 MT 14.0 MT 3.0 MT

A. Cement Requirement Detail for the Month of November‘18

(i) Cement (PPC) At site

S. No. Description of Work Qty. Unit Coefficient Quantity Reqd. (Bags)

1 PCC & RCC Work

(i) UGWT R/W & Slab Casting 110 Cum 7.08 779

(ii) Terrace Floor Water Tanks Top Slab

& Column 80 Cum 7.08 566

(iii) VDC Flooring

(Upper & Lower Basement) 150 Cum 7.08 1062

(iv) Plaster Work 4020 Sqmtr 0.11 442

(v) Boundary Wall Masonry Work 250 cum 0.84 210

Total Required Bags of Cement for the Month of November‘18 3059

Total Available Bags of Cement at Site 100

Net Required Bags of Cement for the Month of November‘18 2959

Say 3500

Page 10: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

10 | P a g e

A. Aggregate Requirement Detail for the Month of November‘18

(i) 10mm Aggregate

S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)

(i) UGWT R/W & Slab Casting 110 Cum 11.515 1266

(ii) Terrace Floor Water Tanks Top

Slab & Column 80 Cum

11.515 921

(iii) VDC Flooring

(Upper & Lower Basement) 150 Cum

11.515 1727

Total Required Qty of 10mm Aggregates for the Month of November’18 3914

Total Available Qty of 10mm Aggregate at Site 500

Net Required Qty of 10mm Aggregate for the Month of November‘18 3414

Say 4000

(ii) 20mm Aggregate

S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)

(i) UGWT R/W & Slab Casting 110 Cum 16.8 1848

(ii) Terrace Floor Water Tanks Top

Slab & Column 80 Cum

16.8

1344

(iii) VDC Flooring

(Upper & Lower Basement) 150 Cum

16.8 2520

Total Required Qty of 20mm Aggregates for the Month of November’18 5712

Total Available Qty of 20mm Aggregate at Site 800

Net Required Qty of 20mm Aggregate for the Month of November’18 4912

Say 5000

A. Sand Requirement Detail for the Month of November’18

(i) Sand

S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)

(i) UGWT R/W & Slab Casting 110 Cum 17.30 1903

(ii) Terrace Floor Water Tanks Top

Slab & Column 80 Cum

17.30 1384

(iii) VDC Flooring

(Upper & Lower Basement) 150 Cum

17.30 2595

(iv) Plaster Work 4020 Sqmtr 0.50 2010

(v) Boundary Wall Masonry Work 250 cum 14.82 3705

Total Required Qty of Sand for the Month of November’18 11597

Total Available Qty of Sand at Site 1100

Net Required Qty of Sand for the Month of November’18 10497

Say 10500

Page 11: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

11 | P a g e

A. Bricks Requirement Detail for the Month of November’18

S.No Description of Work Unit Qty Reqd.

(i) Terrace Floor Brickwork. Nos. 15000

(ii) Boundary Wall Brickwork.(front Side & North Side) Nos. 20000

Total Required Qty. of Bricks for the Month of November’18 35000

Total Available Qty of Bricks at Site 20000

Net Required Qty of Bricks for the Month of November’18 15000

Say 15000

B. AAC Block (9”)Requirement Detail for the Month of November’18

S.No Description of Work Unit Qty Reqd.

(i) Terrace Floor Brick work. Nos. 1000

Total Required Qty. of Bricks for the Month of November’18 1000

Total Available Qty of Bricks at Site -

Net Required Qty of Bricks for the Month of November’18 400

Say 400

C. Weekly Material Procurement Schedule month of November ‘18

WEEKLY MATERIAL REQUIREMENT SCHEDULE FOR THE MONTH OF NOVEMBER‘18

S.

NO.

MATERIAL

DESCRIPTION 1st WEEK 2nd WEEK 3rd WEEK 4th WEEK

TOTAL

QUANTITY

Remarks

(if any)

1 Steel - - - 3.0 3.0 MT

2 Cement(PPC) 1500 600 600 800 3500 Bags

3 10mm Aggregate 2000 1400 600 - 4000 C.Ft

4 20mm Aggregate 2000 1500 800 700 5000C.Ft

5 Sand 4000 3000 1000 2500 10500C.Ft

6 Italian Marble - - - 1200 12000 Sqft

7 Bricks - - 15000 - 15000 Nos.

8 AAC Block - - - 400 400 Nos.

Page 12: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

12 | P a g e

DRAWING STATUS

Status of Drawings in the Month of October‘18

Following is the status of drawings in month of August from Architect Design & Services (ADS) by PMC

Engineer and issued to concerning Contractors at site.

S.No Date of

Received Drawing Title Drawing No.

Rev.

No. Remark

1 06.10.2018 Window Details First Floor 176/RASC/FFW/10 - Received

2 06.10.2018 Window Details Third Floor 176/RASC/TFW/12 - Received

3 06.10.2018 Window Details Fourth Floor 176/RASC/FFW/13 - Received

4 06.10.2018 Window Details Fifth Floor 176/RASC/FFW/14 - Received

5 06.10.2018 Fourth Floor Drainage Layout - - Received

6 06.10.2018 Fourth Floor Internal Plumbing Layout - - Received

7 06.10.2018 West Side Boundary Wall Section 176/RASC/GFP/BW Received

8 22.10.2018 Fire Staircase Roof & Beam Detail - Received

9 22.10.2018 Working Plan Terrace Floor 176/RASC/TP/15 Received

10 22.10.2018 Working Plan Ground Floor 176/RASC/GFP/09 Received

11 22.10.2018 Puddle Flange Details UGWT - Received

12 30.10.2018 Fourth Floor Internal Plumbing Layout - 03 Received

13 30.10.2018 Building Electrical Distribution - Received

14 30.10.2018 G.R.C. Jalli Detail 176/RASC/FFP/10 Received

15 30.10.2018 Truss Plan & Section - Received

16 30.10.2018 Trench Covering Jalli Detail 176/RASC/GFP/BWS/09 Received

17 30.10.2018 Lower Basement Drainage Plan - 01 Received

18 30.10.2018 S/E & N/E Corner Boundary 176/RASC/GFP/09 Received

List of Drawings Required in November ’18

Following Drawings are required at site in the Month of November’18

S. No. Drawing Title Date of Requirement

on OR Before

1 Terrace Floor Column & Covering Details with Sections. ASAP

2 STP & Rain water harvesting Pit Details With Sections. ASAP

3 Electrical Working & SLD & Plumbing SLD. ASAP

4 Ground Floor Flooring Detail with Section & Sectional Details.. ASAP

5 Outer Development Details with Sections including All MEP Services. ASAP

6 Fire Staircase Railing Details. ASAP

7 Main Gate MS Section Details & Guard Rooms Shuttering & Reinforcement Details.

ASAP

8 Porch Detail Section & Sectional Details. ASAP

9 Revised MEP Coordinated Plan upto first floor. ASAP

10 False Ceiling Plans (Second to Fifth Floor) with Section & Sectional Details.

ASAP

Page 13: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

13 | P a g e

PROGRESS PHOTOGRAPHS

Site View 31th

October ’18

Site Meeting With Architect & MEP Consultant (20.10.2018)

Page 14: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

14 | P a g e

Project Review Meeting at Site (24.10.2018)

Site Meeting for Finalization of Electrical Accessories

Page 15: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

15 | P a g e

False Ceiling Work in Progress at Ground Floor

Boundary Wall Brick Masonry Work (North & East Side)

Page 16: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

16 | P a g e

Project Views (Front Side)

(Back Side View)

Page 17: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

17 | P a g e

HVAC Work (Copper piping & Ducting) In Progress at Ground & First Floor

Electrical & Plumbing Work In Progress at First & Third Floor

Page 18: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I October-2018.pdf · Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40,

RAS Officers Institute (Club House) Monthly Progress Report October ‘18

18 | P a g e

MAJOR PENDING DECISIONS & REQUIREMENTS AT SITE

Some other decisions pending at site are as follows:-

(i) STP Vendor to be finalized.

(ii) Swimming pool Waterproofing & Tile fixing Vendor to be finalized.

(iii) Terrace floor M.S. work Vendor to be finalized.

(iv) Flooring Contractor to be finalized.

(v) Exterior Stone Cladding Contractor to be finalized.

(vi) Elevation Structural Glazing Contractor to be finalized.

Signature Signature

Mr. Vipin Pachlangia Mr. Kulvinder Singh

(Project Head) (PMC Head)

Mobile: 91-9929312666 Mobile: 91-9314480610