Monthly Construction Progress Report: April 2019 Trampas ...

28
Monthly Construction Progress Report: April 2019 Trampas Canyon Dam and Reservoir Project No. C-1773 Page 1 of 28

Transcript of Monthly Construction Progress Report: April 2019 Trampas ...

Page 1: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 1 of 28

Page 2: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 2 of 28

CONTRACT SUMMARY

• The contract status through April 30, 2019 is provided below. It summarizes project cost details and time constraints.

Trampas Canyon Dam and Reservoir

PROJECT SUMMARY

• Notice to proceed was issued January 30, 2018.

• DSOD, AECOM, and GMU were onsite on March 27, 2019 to review damages resulting from rain events in preparation of resuming work. The intent of the meeting was to observe existing conditions and discuss necessary repairs in the bedrock and embankment slopes prior to starting embankment fill activities.

Embankment fill activities of the Main Dam did not progress this month due to weather impacts. East Saddle Dam embankment fill activities resumed this month to include downstream filter and drainage blanket as well as upstream and downstream shell placement. Import material quality remains to be consistent.

• Microtunneling activities continued with the MTBM recovery procedures by hand tunneling approximately 100 lineal feet and installing 79-inch casing.

• Emergency outlet structure concrete placement occurred April 10, 2019 for the walls and deck. Some defects in the concrete were observed and the Sub-Contractor is in the repair process.

• Perimeter fence installation continued throughout the month with approximately 1500 lineal feet installed to date.

30 4.4% 455 64.5% 250 35.5%

(1,103,729.00) -1.3% 30,419,919.75 37.5% 50,765,351.25 62.5%

12/6/2019

705 1/5/2020

C-1773 11/8/2017 1/30/2018 675

Approved Time Extension

(CD)

Revised Contract

Duration (CD) Revised Completion Date

Elapsed Contract Time

(CD)

Contract Time Remaining

(CD)

4 1,500,000.00 82,685,271.00 120 5/4/2020

Billed to Date ($) Amount Remaining ($)

# of Potential Issues

Potential Change Order

Amount ($) Total Exposure ($) Potential Delays (CD)

Potential Completion

Date

82,289,000.00 81,185,271.00

Original Contract Amount

($)

Change Orders to Date

($)

Revised Contract Amount

($)

Project No. Date of Award Notice to Proceed

Original Contract

Duration (CD) Original Completion Date

Page 3: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 3 of 28

Cost Tracking

• Three change orders have been added to the Project to date.

• Multiple cost impacts are being tracked on a force account/time and materials basis to help keep work progressing in a logical manner and assist in the mitigation of delays. Other potential cost changes are being evaluated by estimates that are being submitted by the Contractor or are forthcoming from the Contractor. The listing of multiple potential cost change items that the CM Team is tracking is contained in attached Appendix 1. Much of the CM effort on this project remains attributed to addressing and resolving potential delays and changes in project costs. Change Orders, both additive and deductive, will eventually be issued to capture the items listed in the Appendix 1 tabulation. The tabulation continues to be an evolving document.

• Several design revisions are occurring as the project progresses. These are also being tracked in the Appendix 1 tabulation. New design revisions for this month include:

o Revised grading plan for Spillway Structure Entrance to capture varied bedrock

elevations. This change was designated as Design Change Memorandum 6.21.

o There will be an upcoming design change regarding the I/O piping exiting the tunnel and turning up the I/O slope and structure. The AECOM design does not comply with AWWA recommendations and further evaluation and modification is anticipated.

Schedule Tracking

• The progress of construction is currently behind schedule by approximately two months due to differing site conditions related to bedrock locations at the East Saddle Dam and the Main Dam which was described in detail in prior reports.

• Contractor production and weather delays have also contributed to the overall schedule delay by an additional approximately two months.

• Critical path Embankment Fill operations have been suspended until April 2019 based on current weather patterns and the impacts weather has had on the project. Sukut formally requested this deferment on February 4, 2019 and the District accepted the proposal with conditions on February 26, 2019. This will potentially add an additional 2-3 months to the overall schedule. Embankment activities resumed on April 15, 2019.

• All other work activities have resumed progress.

o The project is currently projected to conclude at or before early July 2020 based on the most current Contractor CPM schedule update. This update takes into account weather delays and re-mobilization activities prior to resuming embankment fill activities.

Page 4: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 4 of 28

COST MONITORING

• Graphical cost analysis for General Contractor:

Page 5: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 5 of 28

Page 6: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 6 of 28

• Graphical cost analysis for principal consultants:

Current Month To Date Total Contract

118,000$ 2,054,685$ 3,039,065$

34,049$ 2,920,880$ 2,764,512$

57,783$ 1,207,479$ 1,257,666$

8,648$ 124,009$ 134,750$

7,550$ 66,742$ 110,058$

Leatherman Bioconsulting Inc.

Dudek & Associates Inc.

Work Billed By Month

Butier Engineering Inc.

URS/AECOM

GMU Geotechnical Inc.

$-

$1,000,000

$2,000,000

$3,000,000

$-

$500,000

$1,000,000

$1,500,000

$- $1,000,000 $2,000,000 $3,000,000 $4,000,000

$-

$50,000

$100,000

$150,000

$- $20,000 $40,000 $60,000 $80,000

Page 7: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 7 of 28

• Tabular cost listing for all project costs:

Project Costs by Vendor To Date

Vendor Balance

ARC-American Reprographics Co. $ 18,784.27

Archaeological Resource 13,261.60

AT&T 72,275.60

Best, Best & Krieger 17,558.51

Butier Engineering Inc. 2,054,685.43

Dams-State of CA Division of Safety 433,895.00

Department of Water Resources 31,604.00

Dudek & Associates Inc. 66,742.02

Eurofins Eaton Analytical Inc. 3,800.00

Glenn Lukos Associates 48,055.72

GMU Geotechnical Inc. 1,280,270.54

Huitt-Zollars Inc. -

Ibeam Construction Cameras 20,421.74

Joey Soto 4,999.05

Leatherman Bioconsulting Inc. 124,008.80

Murow CM 18,925.00

Northstar Surveys Inc. 6,385.00

Olaunu, LLC 15,000.00

Payroll & Burden 231,118.46

Power Plus 72,823.83

Psomas 220,425.64

San Diego Gas & Electric 297,226.00

San Diego Regional Quality Board 600.00

Sierra Analytical Labs 20,114.60

State Water Resources Control Board 61,746.00

Sukut Construction Inc. 31,744,882.44

SWRCB Accounting Office 7,177.00

Sycamore Valuation 2,500.00

URS/AECOM 2,920,879.55

Xylem Dewatering Solutions Inc. 152,688.53

$ 39,962,854.33

Page 8: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 8 of 28

PROJECT COMMUNICATION

• Fifty-four Weekly Construction Progress Meetings have been held since the Notice of Award was issued for November 8, 2017. Weekly Progress Meetings have resumed as of April 18th.

• Itemized action items and topics are usually summarized in the Progress Meeting Minutes; Specific items to note for this month include the following:

o Clean-up activities in preparation of resuming work at both East Saddle Dam and Main

Dam.

o Emergency Outlet Structure Concrete Wall Repair Procedures o Embankment activities started at East Saddle Dam on April 22nd.

SUBMITTALS

• 244 submittals have been received from Sukut Construction. 6 remain under review. REQUESTS FOR INFORMATION

• 203 requests for information (RFIs) have been received from Sukut Construction. 4 RFI remain open and await responses.

STORM WATER POLLUTION PREVENTION PLAN

• SWPPP monitoring conducted by Sukut personnel. REAP report received for all rain events, with permanent BMPs currently being installed. The project is current on all required SWPPP paperwork.

Page 9: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 9 of 28

APRIL ACCOMPLISHMENTS

• Dewatering Activities

o Ongoing dewatering at future Inlet/Outlet sump. This is also the receiving pit area for the Micro-tunneling.

• Embankment fill

o East Saddle Dam downstream shell and core embankment fill placement resumed this month

o Main Dam downstream embankment fill placement on hold as contractor is preparing to resume work.

• Perimeter fence installation continued and will continue for the next several months.

• Microtunnel Operations

o Hand tunneling efforts began, achieving approximately 100 linear feet towards the MTBM cutter head.

ANTICIPATED WORK FOR MAY 2019

• East Saddle Dam Embankment fill activities will continue.

• Main Dam Embankment fill activities to resume on or around May 1st.

• Double shift to begin, with dayshift focusing on placing filter chimney and choker materials, and night shift placing embankment fill and core.

• Emergency Outlet Structure wall repair to begin early May after DSOD and AECOM review repair plan. Anticipating forming deck by the middle of May and install downstream spool with weep ring.

• Perimeter fence installation will continue.

• Microtunnel operations anticipated to retrieve MTBM from receiving pit side by hand tunneling methods by the beginning of May.

• Continue Dewatering as needed.

Page 10: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 10 of 28

Laborer Blowing Loose Material from Bedrock

Meeting with Contractor, CM and Geologist to Review Plan for Work Resumption

Page 11: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 11 of 28

Laborers Cleaning Main Dam: Removal of Posi-Shell

East Saddle Dam Looking into Reservoir

Page 12: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 12 of 28

Main Dam: Removing Posi-Shell from Bedrock

Arch-Paleo Monitor Inspecting Native Excavation within Borrow Area

Page 13: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 13 of 28

Laborers Cleaning Silt from East Saddle Dam Filter Materials

Interior View of Microtunnel Recovery Operations

Page 14: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 14 of 28

Emergency Outlet Structure: Inspection of Forms and Rebar Prior to Concrete Placement

GMU Sampling Concrete for Emergency Outlet Structure Pour

Page 15: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 15 of 28

Inside View of Concrete Wall Placement at Emergency Outlet Structure

Emergency Outlet Structure: Concrete Placement

Page 16: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 16 of 28

Scrapers Hauling from Future Dam Control Building Site

Laborers Clean Bedrock at East Saddle Dam

Page 17: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 17 of 28

DSOD, AECOM & GMU Inspect East Saddle Dam

Inside View of Microtunnel Recovery Casing

Page 18: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 18 of 28

Sukut Compacting Embankment Fill at East Saddle Dam

Main Dam: Laborers Cleaning Posi-Shell and Removing Silt from Previous Storms

Page 19: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 19 of 28

Laborer Blowing Loose Material from Main Dam Bedrock

Microtunnel: MTBM Recovery View of Hand Tunneling Face

Page 20: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 20 of 28

Test Panel for Shotcrete Use at Inlet Outlet Piping

Arch-Paleo Monitor Inspecting Bench Cut at Borrow Areas

Page 21: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 21 of 28

Emergency Outlet Structure with Forms Removed

DSOD Inspection of Main Dam West Canyon

Page 22: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 22 of 28

Emergency Outlet Structure Formwork Removed for DSOD Review

Emergency Outlet Structure Formwork Removed for AECOM & SMWD Review

Page 23: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 23 of 28

Laborers Place Filter Materials at East Saddle Dam

Scraper Hauling Silt from Main Dam to Disposal for Cleanup after Rain Events

Page 24: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 24 of 28

Sukut Laborers Cleaning East Saddle Dam Bedrock

Laborers Place Chimney Material at East Saddle Dam

Page 25: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 25 of 28

Laborers Cleaning Loose Materials at East Saddle Dam

Sukut Laborers Sweeping Loose Materials at East Saddle Dam

Page 26: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 26 of 28

Microtunnel Receiving Pit During DSOD Site Tour

Main Dam: Scrapers Hauling in Embankment Fill

Page 27: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 27 of 28

APPENDIX 1

C-1773 Trampas Canyon Dam & Reservoir Issue and Cost Tracker

Page 28: Monthly Construction Progress Report: April 2019 Trampas ...

Monthly Construction Progress Report: April 2019

Trampas Canyon Dam and Reservoir Project No. C-1773

Page 28 of 28