Monitoring Report of the Scheme Construction of Bus Girage in Gdc Daggar Buner
-
Upload
engr-amir-jamal-qureshi -
Category
Documents
-
view
218 -
download
0
Transcript of Monitoring Report of the Scheme Construction of Bus Girage in Gdc Daggar Buner
-
7/25/2019 Monitoring Report of the Scheme Construction of Bus Girage in Gdc Daggar Buner
1/2
SUBJECT: - MONITORING REPORT OF THE SCHEME CONSTRUCTION OF EXAMINATION HALL,
ADMIN: BLOCK, ADDATIONAL CLASS ROOMS AND BUS GIRAGES IN GOVT: COLLEGS IN
KHYBER PAKHTUNKHWA ADP NO: 66!""#6$
SUB HEAD: CONSTRUCTION OF BUS GIRAGE IN GDC DAGGAR BUNER
S/No Analysis and recommendation Replies
1 In the desk review it was notice that the work order for the sub
scheme has been issued on 01/02/201 havin!
No"2#$%/&"'R()R with date for completion was framed upto
0/0*/201 from its commencement date i"e" 0*/02/201+ butin the monthly pro!ress report of the e,ecutin! department the
date of completion is sent upto 0/0*/201-" .pon inuiry
from the relevant staff of the & (epartment+ they were
unable to 3ustify that why the sub scheme was under e,ecution
phase and no action was taken by the department to restrict the
contractor so as to achieve his tar!et within the permissible
limit.It is recommended that the e,ecutin! a!ency must
3ustify that why such slackness had been observed in the
completion time period and no action has been taken on
such time overrun"
4he scheme is in pro!ress and the tar!et date of completion is
0/*/201- as per A(5 20161-" Allocation for compact
scheme for 78 920161-: is Rs; 22"00 9 thick which has been
erroneously shown in the photo!raph as ramp thickness" i!ht
breaka!e of the ed!e of ramp at manhole has been rectified+ and
steel !ratin! will be installed over the manholes"
D 4wistin! and bul!in! was observed in the R column
of the !ara!e havin! a -> offset at the lower section
while a $"$> offset at the upper section as shown in
photo!raph+ makin! the section to have a reduced load
takin! capacity and the with e,posure to failure"
4he increase in offset of the column at upper section was
due to over6concretin! as a result of shutterin! problem and
same has been rectified at site"
-
7/25/2019 Monitoring Report of the Scheme Construction of Bus Girage in Gdc Daggar Buner
2/2
)E)4ID) )NBIN))R S@ (IDISI'NA '77I)R S@ )NBIN))R
& (IDISI'N @N)R & (IDISI'N @N)R & (IDISI'N @N)R