An Overview and Best Practices
ASHRAE Spring Conference 2020
Daniel Hosko, PE, LEED AP O+M, CEM, QCxP
Aero Building Solutions
Monitoring-Based Commissioning (MBCx)
![Page 2: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/2.jpg)
• MBCx/Analytics Overview
• MBCx Setup/Timeline
• Common Hurdles
• Examples
• Q+A
Outline/Agenda
![Page 3: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/3.jpg)
MBCx/Analytics Overview
• Using software to acquire and analyze HVAC performance data on a continuous basis
• How is this different than the BAS front end?
• MBCx is a process
• Alarms vs Analytics
![Page 4: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/4.jpg)
MBCx/Analytics Overview
![Page 5: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/5.jpg)
• Design• Confirms the performance criteria of the initial
design
• Owner – “We aren’t saving the energy we thought we would!”
• Verification that design worked (or where it didn’t)
• Small step towards data driven designs
MBCx/Analytics Overview
![Page 6: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/6.jpg)
• Building Operations• Reactive vs Predictive Repairs
• Identify and address issues before they become costly failures
• Increased transparency into the building system performance
MBCx/Analytics Overview
![Page 7: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/7.jpg)
• Measurement and Verification• Issues with M&V
• “I don’t have enough data”
• “I don’t have the right data”
• Lengthy and cumbersome process
• Focuses on energy efficiency and struggles on maintenance opportunities
• High initial investment in time, money, and effort to implement tools and technology
• Use MBCx to Support M&V
• Little to no sub metering required
• Continuously tracking and trending much easier
MBCx/Analytics Overview
![Page 8: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/8.jpg)
• Energy Efficiency• More in depth than retro-commissioning (RCx)
MBCx/Analytics Overview
![Page 9: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/9.jpg)
MBCx Setup/Timeline
![Page 10: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/10.jpg)
MBCx Setup/Timeline
![Page 11: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/11.jpg)
MBCx Setup/Timeline
CLOUD
![Page 12: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/12.jpg)
• BAS System is Open Protocol BACnet
• Example Compatible Systems• Trane Tracer Summit
• Niagara AX
• Niagara N4
• Trane – SC (BACnet) (Trane’s newest)
• Siemens (BACnet)
• Johnson Controls (Metasys with NAE and NCI building level controllers)
• Johnson Controls (BACnet)
• Automated Logic
• Alerton BACtalk
• Delta Controls – ORCA
• Reliable – Third generation MACH-system or later
• Others
• CSV Files/Trends
MBCx Setup/Timeline
![Page 13: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/13.jpg)
• Work with IT Department on security and MBCx device setup/communication
• Deploy MBCx software/device on site
• Onsite investigation and information gathering
• Build and customize analytics
• Deliver findings and recommendations
• Refine analytics
• Repeat
MBCx Setup/Timeline
![Page 14: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/14.jpg)
• BAS control system is not BACnet (proprietary)
• BAS control system is a local network
• Equipment missing from network
• IT issues/coordination
• Network speed and quality issues
• Data security concerns
• Network device ID conflicts/naming issues
• Inconsistent point names
Common Hurdles
![Page 15: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/15.jpg)
• Corrective Measures• Terminal Units reheating at a CFM above the reheat
setpoint
• Airflow stations out of calibration
• Improper economizer operation
• Control valves are leaking and heating/cooling when valve is commanded 100% closed
• Minimum airflow fraction is out of calibration
• Excessive cycling
• Improvement Measures• Temperature and pressure reset sequences
• Identify critical zones and use to tune sequences and setpoints
• Demand control ventilation
Examples
![Page 16: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/16.jpg)
Examples
![Page 17: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/17.jpg)
Examples
![Page 18: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/18.jpg)
Examples
0
100
200
300
400
500
600
700
800
0 200 400 600 800 1000 1200 1400 1600
Po
we
r
Tons
Chiller Load Profiles
Chiller 1 Chiller 2 Chiller 3 Chiller 4
![Page 19: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/19.jpg)
Examples
![Page 20: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/20.jpg)
Examples
0
10
20
30
40
50
60
70
80
90
100
Pre-Heat Temperature Setpoint
CLG-O PH-O
![Page 21: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/21.jpg)
Examples
![Page 22: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/22.jpg)
Examples
0
10
20
30
40
50
60
70
80
90
100
60
65
70
75
80
85
90
95
100
105
110
HW
Val
ve %
Tem
pe
ratu
re
Date
VAV HW Valve Signal Reversed
DAT ZN-T ZNT-SP HTG-O
![Page 23: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/23.jpg)
Examples
0
100
200
300
400
500
600
Air
flo
w (
CFM
)
Date
VAV Box Airflows
CLG-MAXFLOW HTGOCC-MINFLOW SA-F
![Page 24: Monitoring-Based Commissioning (MBCx) · Monitoring-Based Commissioning (MBCx) • MBCx/Analytics Overview • MBCx Setup/Timeline • Common Hurdles • Examples • Q+A Outline/Agenda.](https://reader035.fdocuments.in/reader035/viewer/2022071405/60fa0d12dbfc584e684ff498/html5/thumbnails/24.jpg)
Daniel Hosko, PE, LEED AP O+M, CEM, QCxP
Aero Building Solutions
Questions?