Monitoring and reporting project status Chapter 10, pages 317-342

23
CSSE 372 20.Oct.2008 Monitoring and reporting project status Chapter 10, pages 317-342

description

Monitoring and reporting project status Chapter 10, pages 317-342. CSSE 372 20.Oct.2008. Outline. Control vs. risk Other kinds of reporting EV. Why do we need to monitor progress?. 70% of projects are: Over budget Behind schedule - PowerPoint PPT Presentation

Transcript of Monitoring and reporting project status Chapter 10, pages 317-342

Page 1: Monitoring and reporting project status Chapter 10, pages 317-342

CSSE 37220.Oct.2008

Monitoring and reporting project status

Chapter 10, pages 317-342

Page 2: Monitoring and reporting project status Chapter 10, pages 317-342

OutlineControl vs. riskOther kinds of reportingEV

Page 3: Monitoring and reporting project status Chapter 10, pages 317-342

Why do we need to monitor progress?70% of projects are:

• Over budget• Behind schedule

52% of all projects finish at 189% of their initial budget

• Average of 16% of SW projects are on-time and budget

Source: The Standish Group

Page 4: Monitoring and reporting project status Chapter 10, pages 317-342

How and What to Update?Determine a set period of time and day of weekReport actual work accomplished during this periodReport start and finish datesReport days of duration accomplished and remainingReport resource effortReport percent complete

Page 5: Monitoring and reporting project status Chapter 10, pages 317-342

Types of progress reportingCurrent period reportsCumulative reportsException reportsStoplight reportsVariance reports

NumericalGraphical

Page 6: Monitoring and reporting project status Chapter 10, pages 317-342

Milestone trend charts

Page 7: Monitoring and reporting project status Chapter 10, pages 317-342

EVAEarned Value Analysis (EVA) is:

an industry standard way to:measure a project’s progress,forecast its completion date and final cost, andprovide schedule and budget variances along the way.

Page 8: Monitoring and reporting project status Chapter 10, pages 317-342

Baseline vs. actual cost curve

Page 9: Monitoring and reporting project status Chapter 10, pages 317-342

Let’s talk termsBCWS - Budgeted Cost of Work ScheduledACWP - Actual Cost of Work PerformedBCWP - Budgeted Cost of Work Performed

Page 10: Monitoring and reporting project status Chapter 10, pages 317-342

Variance (EV – PV)Positive

Indicates ahead of schedule or less cost than plannedMay not always be good

NegativeIndicates behind schedule or more cost than plannedMay not always be bad

Page 11: Monitoring and reporting project status Chapter 10, pages 317-342

Full story

http://evm.nasa.gov/images/key_data.gif

Page 12: Monitoring and reporting project status Chapter 10, pages 317-342

Performance indicesSchedule Performance Index

SPI = BCWP/ BCWSCost Performance Index

CPI = BCWP/ ACWP

Page 13: Monitoring and reporting project status Chapter 10, pages 317-342
Page 14: Monitoring and reporting project status Chapter 10, pages 317-342

Let’s do an example…PROJECT STATUS: Make 1000 widgets over 50 days (20 per day)

INPUT: Total Expected Output = 1000

INPUT: Budgeted Unit Cost = $.50

Total Project Budget is 1000 x $.50 = $500.

http://www.earnedvalueanalysis.com/index.cfm?nextpage=example

Page 15: Monitoring and reporting project status Chapter 10, pages 317-342

EV InputBCWS: How much did we expect to pay for the work

that was scheduled?

Total Project Days = 10 Unit Production Per Day = 20 widgets/day Budgeted Unit Cost = $.50/widget BCWS = 10 days x

20 widgets/day x $.50/widget budget = $100

Page 16: Monitoring and reporting project status Chapter 10, pages 317-342

EV InputBCWP: How much did we expect to pay for the work

that was actually done?

Actual Current Output = 150

Budgeted Unit Cost = $.50/widget

BCWP = 150 widgets x $.50/widget budgeted = $75

Page 17: Monitoring and reporting project status Chapter 10, pages 317-342

EV InputACWP: What was the actual cost of the work that was

completed?

Actual Current Output = 150 Actual Unit Cost = $.60/widget

ACWP = 150 widgets x $.60/widget actual = $90

Page 18: Monitoring and reporting project status Chapter 10, pages 317-342

EV AnalysisSV: Schedule Variance = BCWP – BCWS

The Question: Are we ahead or behind production schedule?

SV = BCWP – BCWS = $75 - $100 = -$25

Page 19: Monitoring and reporting project status Chapter 10, pages 317-342

EV AnalysisSPI: Schedule Performance Index = BCWP/BCWS

The Question: How far ahead or behind schedule are we?

SPI = BCWP/BCWS = 75/100 = 0.75 (LT 1, so behind schedule)

Page 20: Monitoring and reporting project status Chapter 10, pages 317-342

EV AnalysisCV: Cost Variance is measured as follows:

If BCWP > ACWP, the project is UNDER budget! If BCWP < ACWP, the project is OVER budget!

The Question: Are we on or off budget?

CV = BCWP - ACWP = $75 - $90

= -$15 (negative means over budget)

Page 21: Monitoring and reporting project status Chapter 10, pages 317-342

EV AnalysisCPI: Cost Performance Index

The Question: How far on or off budget are we?

CPI = BCWP / ACWP = 75/90 = 0.8333 (less than 1 means over budget)

Page 22: Monitoring and reporting project status Chapter 10, pages 317-342

Project forecastEAC: Estimate at Completion

Method 1: BCWP at a point + Estimates to completion. Method 2: The ratio of BAC / CPI. Method 3: (Wilkens) [(BAC - BCWP)/CPI] + ACWP

The Question: At the rate going, how much will all of this cost?

This is a SIMPLIFIED estimate of EAC      EAC = BAC / CPI = $500 / 0.8333 = $600

Page 23: Monitoring and reporting project status Chapter 10, pages 317-342

Questions?