MONALISA at ATF2 First installation report

34
Wed 15 Jul 2009 ATF2 weekly meeting Oxford MONALISA 1 MONALISA at ATF2 First installation report 15 July 09

description

MONALISA at ATF2 First installation report. 15 July 09. Overview. Installation progress ATF2 roof: Initial tests with wooden frame Initial test results ATF2 FF: Mounted at IP in Final Focus Vacuum test Force tests Tilt tests Magnet lateral movement tests. Good progress. - PowerPoint PPT Presentation

Transcript of MONALISA at ATF2 First installation report

Page 1: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

1

MONALISA at ATF2 First installation report

15 July 09

Page 2: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

2

Overview

• Installation progress– ATF2 roof: Initial tests with wooden frame

• Initial test results

– ATF2 FF: Mounted at IP in Final Focus• Vacuum test• Force tests• Tilt tests• Magnet lateral movement tests

Page 3: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

3

Good progress• We kept within our proposed schedule

– As set out in ATF2 meeting 17 Jun 09

• All items arrived at KEK 1st July 2009– Brought to ATF2 roof within 15 mins of arrival

• On ATF2 roof– System assembled and retested

• Brought to ATF2 Final focus tunnel – Reassembled at IP Thursday 9th July and

tested

Page 4: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

4

On the roof of the ATF2

Page 5: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

5

Preliminary tests

• Closed the vacuum system– Pumped out to 25 Pa– Limited by small leak (1 Pa/s)

• Due to lower angled tube• Will be fixed in future by

replacing lower angled tube• Vacuum sufficient for test

programme

• Reassembled wooden frame on ATF2 roof

• Benoit measured vibrations (see his talk)

Page 6: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

6

Schematic Layout of Pneumatics • Vacuum in end boxes connected through inner bellows• High pressure only connected to outer bellows chamber

Page 7: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

7

Recalibrated force sensors

• Retested force sensor – Applying loads using spring balance

• Force sensor rather noisy– Produces signals up to +/- 10 mV

• Readout with NI USB 6009 ADC (14 bit)– Sampled at 5kSa/s– Used LabVIEW to average 5000 readings

together

Page 8: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

8

Forces on frame during pumping

• Cycled bellow chamber pressures– Inner chamber 100 kPa to 25 Pa to 100 kPa– Outer chamber 100 kPa to 140 kPa to 100kPa

• Measured forces– Using recalibrated force sensor

• Independently calculated forces– Based on SMC pressure sensors

• One for each chamber

Page 9: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

9

Sensor readout during pumping

Page 10: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

10

Over-pressure regulation• Over-pressure regulator does not behave

as we would like

Control Signal /V

Overpressure / kPa

0

40

Vmax0

No response for over-pressure requests less than (50 mbar)

Page 11: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

11

Required over-pressure regulation• Would want a straight line relationship

even for very low over-pressure

Control Signal /V

Overpressure / kPa

0

40

Vmax0

Page 12: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

12

Into the ATF2 tunnel

Page 13: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

13

Tunnel preparation

Terunua-san installed pipe across the inside of the ATF2 final focus tunnel roof

Equipped with 2 hoists

Page 14: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

14

Mounting Shintake components• Plate mounted using M30 hooks

• End box mounted using hoist

Cables

Page 15: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

15

Mounting QD0 end box• Beeswax was placed on QD0 surface

– To ensure good vibration coupling to magnet

Page 16: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

16

End boxes mutually aligned

• Laser light projected along accelerator axis

• Shintake end box – (left-right adjustable)– Moved to match QD0

end box

Page 17: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

17

The DBS was hoisted into placeFull assembly completed well

within one day

Page 18: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

18

Tilt sensor• Tilt change on Shintake ~5+5 rad

– After MONALISA DBS installed at IP

Page 19: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

19

DBS pumped out: with rods in

• Reached 28 Pa with a different pump– vacuum integrity was unaltered

Page 20: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

20

Forces measured pumping down when mounted at ATF2 IP

Regulator cycle ~225 s

Page 21: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

21

(x,y,z) Physicists coordinates• In the following we’re using the physicists

coordinate frame

Y

X

Z

Page 22: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

22

Tracking QD0 motion in Z• Set MONALISA at operational pressure

– Pumped out vacuum vessel– Over-pressure in outer bellowed chamber

• Set up independent tracking of QD0– Used FARO to survey QD0 position changes– Keyence laser meter tracked QD0 mounted

on SD0 base plate

Page 23: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

23

KEYENCE tracking QD0 Z

Readout sensor in mV

10 V = 5 mm

1 mV = 0.5 m

Readout with ourADC/LabVIEW DAQ

QD0

Supported from SD0

KEYENCE

Page 24: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

24

FARO survey instrument

FARO

Retro

Page 25: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

25

Comparison of FARO & KEYENCE

Page 26: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

26

FARO compared with KEYENCE

Page 27: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

27

FARO tracking X and Z

Page 28: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

28

Tracking QD0 motion in Z

Page 29: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

29

Tracking QD0 motion in X

Page 30: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

30

Left-right QD0 mover tests

Page 31: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

31

Left-right QD0 mover tests

Page 32: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

32

Left-right QD0 mover tests

DBS spring constant is small enough to let QD0 move freely

Page 33: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

33

What to learn from this measurements?

• We are told that static tolerances for QD0:– 100μm in x,y,z

• Our measurements show that even with the current pressure control system we meet this tolerance.

• The low spring constant of the DBS allows the QD0 mover to move the magnet unhindered.

• Dynamic tolerances: vertical: 10 nm, (between Shintake and QD0) horizontal: 500 nm

along beam: 10 μm• The question about dynamic motion and impact on the

Shintake table will be answered in the next two talks.

Page 34: MONALISA at ATF2 First installation report

Wed 15 Jul 2009 ATF2 weekly meetingOxford MONALISA

34

Summary & Outlook

• MONALISA vacuum system worked well– Many thanks for the wonderful support we got!

• The next step is to do optics tests with the vacuum system in place to gain calibration constants.

• Our goal is to get first position measurements to the Shintake group late next spring.