Moffett Restoration Advisory Board Hangar One Update July 14, 2011
-
Upload
steve-williams -
Category
Technology
-
view
2.759 -
download
0
description
Transcript of Moffett Restoration Advisory Board Hangar One Update July 14, 2011
![Page 1: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/1.jpg)
Former NAS Moffett Field
Hangar 1 Removal Action UpdateHangar 1 Removal Action UpdateHangar 1 Removal Action UpdateHangar 1 Removal Action Update
Bryce Bartelma, PGNavy BRAC PMO West
July 14, 2011RAB Meeting
1
![Page 2: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/2.jpg)
Presentation Overview
P j t Obj ti• Project Objective• Progress Update
Continued Monitoring Roof Redwood Siding & Continued Monitoring and Protection Measures
Historic Mitigation
Roof, Redwood, Siding & Window Removal
Washing & CM15 Coating Additional Removal Historic Mitigation
Scaffolding Installation
• Schedule
Additional Removal Action Activities
• Questions
2
![Page 3: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/3.jpg)
Project Objective
• Control release of PCBs from Hangar 1 in accordance with EE/CA (July 2008) and Action Memorandum (December 2008)(December 2008)Demolition of interior structuresRemoval of contaminated sidingRemoval of contaminated sidingApplication of weather-resistant coating to steel frame
3
![Page 4: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/4.jpg)
Continued Monitoring and Protection Measures
• No observed impacts to biological activityactivity
• Continued storm water and ground surface protectionp
• Navy and NASA air monitoring data demonstrates control of air emissions
4
![Page 5: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/5.jpg)
Historic Mitigation
M C B k t (8)Man Crane Baskets (8)
Corrugated Windows (up to 25)
5
g ( p )
![Page 6: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/6.jpg)
Hangar 1 Interactive CD
• Currently in final production with copies to be made available in the coming monthsavailable in the coming months
6
![Page 7: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/7.jpg)
NASA and SHPO Site WalkNASA and SHPO Site Walk
• June 7, 2011June 7, 2011• ~30 people to observe
progress and discuss re-use
7
![Page 8: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/8.jpg)
Scaffolding InstallationScaffolding Installation
8
![Page 9: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/9.jpg)
Mansard Panels, Redwood, Silver SidingMansard Panels, Redwood, Silver Sidingand Window Removaland Window Removal
• Mansard panels removed inMansard panels removed in Zone 1
• Initiated redwood removal at f ith il idi droof with silver siding and
windows to follow
9
![Page 10: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/10.jpg)
Washing & Coating Washing & Coating –– CarbomasticCarbomastic 1515
• ~98% complete with Zone 1 washing and coating• Initiated washing in Zone 2• Navy representatives Quality Assurance (QA) inspection
of coating from roof to floorof coating from roof to floor
10
![Page 11: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/11.jpg)
Washing & Coating Washing & Coating –– CarbomasticCarbomastic 1515
11
![Page 12: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/12.jpg)
Additional Removal Action Activities
• Clam Shell Door Mechanisms– NASA and SHPO requested cleaning, partial coating,
and wrapping for NASA’s future re-use
12
![Page 13: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/13.jpg)
Additional Removal Action Activities
• Permanent access to• Permanent access to Federal Aviation Administration (FAA)
i d f brequired roof beacon
13
![Page 14: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/14.jpg)
Additional Removal Action Activities
• Recognition Lunch for over 365 days and 70,000 man-hours without a recordablerecordable incident or injury!!
14
![Page 15: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/15.jpg)
ScheduleSchedule
• Fieldwork in zones 1 – 6 OngoingC l t fi ld k• Complete fieldwork, confirmation sampling and demobilize Spring 20122012
• Submit After Action Completion Report p pSummer 2012
15
![Page 16: Moffett Restoration Advisory Board Hangar One Update July 14, 2011](https://reader033.fdocuments.in/reader033/viewer/2022060109/5558b653d8b42aa52a8b4b73/html5/thumbnails/16.jpg)
Questions?
Point of Contact:
Scott Anderson, P.E.BRAC EnvironmentalBRAC Environmental
Coordinator(619) 532-0938( )
16