Modification of Group Housing Project Trident Embassy Plot no. 5B, Sector 1, Greater...
Transcript of Modification of Group Housing Project Trident Embassy Plot no. 5B, Sector 1, Greater...
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 1
INTRODUCTION
M/s. Trident Infra Homes Pvt. Ltd. proposes modification of the Group Housing Project ‘Trident
Embassy’ which is located at Plot no. 5 B, Sector – 1, District Gautam Budh Nagar, Greater Noida,
U.P.
The company has vast experience in planning and construction of Residential & Commercial
projects.
The project was earlier granted Environment Clearance by SEIAA, U.P. vide letter no.
1574Parya/SEAC/1492/2012/DD (Sh) dated 07th
October 2013 for Plot area 30,480 sqm (7.531
acre) and Built-up area 1,66,785.104 sqm. A copy of the EC letter is enclosed as Annexure – I.
The project has undergone some revision in planning due to which the built-up area will reduce to
1,66,072.358 sqm. However, the plot area remains same.
Therefore, the application is being submitted for amendment in Environment Clearance as a result
of proposed modification of the project.
SITE LOCATION AND SURROUNDING
The project site is located at Plot no. 5 B, Sector – 1, Greater Noida, District Gautam Budh Nagar,
Uttar Pradesh.
The geographical co-ordinates of the project site are 28° 34' 15.98" N & 77° 26' 45.49" E.
Google earth image depicting 500 m & SoI Toposheet depicting 10 & 15 km around project site are
enclosed as Annexure - II (a) & (b) respectively.
CONNECTIVITY
The project site is well connected through Noida Greater Noida Link Road. Dadri and Pusta Road
are approx 4.09 km and 3.88 km away from project site towards South and South West direction,
respectively. NH 91 is approx. 6.62 km away from project site towards North East direction.
The nearest railway station is Ghaziabad Railway station, which is approx. 8.73 km away towards
North. Indira Gandhi International Airport is at a distance of approx. 32.29 km from the project site
towards West direction.
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 2
AREA STATEMENT
The total area of project site is 30,480.00 m2
(or 7.531 acre). The detailed area statement is provided
below in Table 1.
Table 1: Comparative Detailed Area Statement
S.
No.
Particulars Value as per
earlier EC
(m2)
Modification
(m2)
Total Area
(m2)
Percentage
1. Total Plot Area 30,480.000 100
2. Permissible Ground
Coverage (35%)
10,668.000
3. Proposed Ground
Coverage
5207.572 477.619 5685.191
18.652
4. Total Permissible FAR
Area including
purchasable FAR for
Residential (@ 2.75 +
0.75 = 3.5)
1,06,680.000
5. Permissible FAR Area
for Commercial (@1%
of permissible FAR for
Residential)
838.2
6. Permissible
Facility/Ancillary FAR
Area (@15% of total
permissible FAR for
Residential)
16,002
7. Total Proposed FAR
(@ 3.492)
Residential
Commercial
Connecting Bridge
Community
area/Club
1,05,728.303
1,04,410.211
838.092
Nil
480
1160.144
0.052
24.00
168*
1,06,432.499
1,05,570.355
838.144
24.00
648*
8. Basement Area 26,979.760 -1378.378 25,601.382
9. Podium Area 23,918.380 -3120.857 20,797.523
10. Stilt Area 608.678 2636.32 3244.998
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 3
11. Proposed
Facility/Ancillary FAR
Area (Club + Fire
Staircase + Lift lobby
+ Mumty + Machine
Room + Lift wells +
Cupboard + Guard
room + Overhead Tank
+ STP)
9549.983 445.973 9995.956
12. Total Built-up area (7
+ 8 + 9 + 10 + 11)
1,66,785.104 -712.746 1,66,072.358
13. Required Green area
(@50% of Open area)
12,636.214 -238.809 12,397.405
14. Open Area 25,272.428 - 477.619 24,794.809
Landscape Area
(52.51% of Open
Area)
Paved/road area
12,636.214
12,636.214
384.52
-862.139
13,020.734
11,774.075
42.71%
38.62%
15. No. of DUs 1307 -53 1254
16. No. of Towers 12 Nil 12
17. Maximum Building
Height (m)
69
(G+24)
16.05 85.05
(G+26)
*Counted in Facility FAR area
Table 1: Comparative Built-Up Area
S.
No.
Description Value as
per earlier
EC (m2)
Modification
(m2)
Total Area
(m2)
1. Total Proposed FAR (@
3.492 )
Residential
Commercial
Connecting Bridge
Community area/Club
1,05,728.303
1,04,410.211
838.092
Nil
480
704.196
1160.144
0.052
24.00
168*
1,06,432.499
1,05,570.355
838.144
24.00
648*
2. Basement Area 26,979.760 -1378.378 25,601.382
3. Podium Area 23,918.380 -3120.857 20,797.523
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 4
4. Stilt Area 608.678 2636.32 3244.998
5. Permissible
Facility/Ancillary FAR
Area (Club + Fire
Staircase + Lift lobby +
Mumty + Machine
Room + Lift wells +
Cupboard + Guard room
+ Overhead Tank + STP)
9549.983 445.973 9995.956
Total Built-up area 1,66,785.104 -712.746 1,66,072.358
*Counted in Facility FAR area
POPULATION DENSITY
The total population of project after proposed modification will be 6849 persons. The detailed
comparative population break-up is given below in Table 3 and population break-up (post
modification) is given in Table 4:
Table 3: Comparative Population Break-up
S. No. Description Value as per
earlier EC
Modification Population
1 Residents
(@4.5/DU)
5881 -238 5643
2 Staff
(Maintenance +
Commercial)
395 -13 382
3 Visitors 848 -24 824
Total
Population
7124 -275 6849
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 5
Table 2: Population Break up (Post Modification)
PROJECT COST
The total estimated cost of the project (post modification) is approx. INR 320 Crore including cost
land as well as development.
WATER REQUIREMENT AND SUPPLY SYSTEM
The total water requirement for the project (post modification) will be approx. 554 KLD out of
which domestic water demand is 497 KLD. The fresh water requirement will be 353 KLD.
However, one time fresh water demand for the project will be 554 KLD. The water will be supplied
by Local Authority. The comparative water calculation is given below in Table 5.
Table 3: Comparative Water Calculation
S. No.
Description
Value as per
earlier EC
(KLD)
Modification
(KLD) Quantity
(KLD)
1. Total water demand 551 3 554
2. Domestic water 531 -34 497
3. Fresh water 372 -24 348
4. Waste water 457 -30 427
5. STP Capacity 550 -35 515
S. No. Description DU PPU Population
1. Residents 1254 4.5 5643
2.
Staff
(Maintenance +
Commercial)
382
3. Visitors 824
Grand Total Population 6849
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 6
Table 6: Calculation for Daily Water Demand (Post Modification)
S. No.
Description Occupancy
Rate of Water
Demand
(lpcd)
Water Requirement
(KLD)
A. Domestic Water
Residents 5643 86 485
Staff (Maintenance +
Commercial) 382 30 12
Visitors 824 15 12
Total Domestic Water 497 KLD
B. Horticulture (13,020.734 m2) 3 l/sqm 39
C. DG Cooling* (2 x 1010 + 2 x
625) 0.9 l/kva/hr 18
Grand Total (A+B+C) 554 KLD
*Considering 6 hrs operation/day for DG sets
Table 7: Waste Water Calculation (Post Modification)
Domestic Water Requirement 497 KLD
Fresh (70% of domestic) 348 KLD
Flushing (30% of domestic) 149 KLD
Waste Water Generated
(80% fresh + 100% flushing) 278 + 149 = 427 KLD
The water balance diagram of project (post modification) during rainy and non-rainy season are
shown below in figure 1 & 2:
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 7
Figure 1: Water Balance Diagram (Non-rainy season)
FRESH WATER
(348 KLD)
(70% of Domestic water)
WASTE WATER
GENERATED
(427 KLD)
STP CAPACITY 515 KLD
HORTICULTURE
(39 KLD)
@ 80%
FLUSHING
(149 KLD)
(30% of Domestic water)
@ 100%
39 KLD
CSTP
(178 KLD)
149 KLD
DG COOLING
(18 KLD)
18 KLD
Treated effluent Waste water
@90%
384 KLD
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 8
Figure 2: Water Balance Diagram (Rainy season)
Wastewater Generation & Treatment
It is expected that the project (post modification) will generate approx. 427 KLD of wastewater.
The wastewater will be treated in onsite STP of 515 KLD capacity. The treated effluent will be
reused for flushing, horticulture & DG cooling. Surplus will be discharged to CSTP of Greater
Noida Authority.
SEWAGE TREATMENT PLANT
SAFF TECHNOLOGY
Sewerage System
An external sewage network shall collect the sewage from all units, and flow by gravity to the
proposed sewage treatment plant.
FRESH WATER
(348 KLD)
(70% of Domestic water)
WASTE WATER
GENERATED
(427 KLD)
STP CAPACITY 515 KLD
@ 80%
FLUSHING
(149 KLD)
(30% of Domestic water)
@ 100%
CSTP
(217 KLD)
149 KLD
DG COOLING
(18 KLD)
18 KLD
Treated effluent Waste water
@90%
384 KLD
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 9
Following are the benefits of providing the Sewage Treatment Plant in the present circumstances:
Reduced net daily water requirements, source for Horticultural purposes by utilization of the
treated waste water. This shall consequently lead to a lower withdrawal from the
underground aquifer water sources.
Reduced dependence on the public utilities for water supply and sewerage systems.
Sludge generated from the Sewage Treatment Plant shall be rich in organic content and an
excellent fertilizer for horticultural purposes.
a. Waste Water Details
(a) Daily load : 427 KLD
(b) Duration of flow to STP : 24 hours
(c) Temperature : Maximum 32oC
(d) pH : 7-8.5
(e) Colour : Mild
(f) T.S.S. (mg/l) : 200-450 mg/l
(g) BOD5 (mg/l) : 250-400 mg/l
(h) COD (mg/l) : 600-800 mg/l
b. Final discharge characteristics
(a) pH : 6.5 to 8.5
(b) B.O.D. : <10 mg/l
(c) C.O.D. : <30 mg/l
(d) Total Suspended Solids : <50 mg/l
Treatment technology is based on the Submerged Aerobic Fixed film reactor. The main advantages
of SAFF technology is that having the combination of the fixed film technologies and fine bubble
diffused aeration techniques. With the higher surface area of bio media, higher organic loading
rates are enabled, thus reducing the overall size required of the aeration tank.
Raw sewage will be collected under gravity into the sump after allowing to pass through the bar
screen. The bar screen, by removing coarse solids from the sewage help in protecting the raw
sewage pump. The raw sewage sump, through temporarily holding the incoming sewage facilitates
both pumping of sewage through the STP and dampening the flow variation in the received sewage.
The sewage collected in equalization tank is pumped and passed through the Aeration tank. From
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 10
the aeration tank, the raw sewage goes to a settling tank (Clarifier) to allow gravity separation of
the mixed liquor suspended solids from the treated wastewater. Settled MLSS are then recycled to
the aeration tank. Excess sludge from the system is drained out. The excess sludge will be
dewatered and used as manure for green belt development. The effluent coming after treatment will
be passed through the flocculation cum settling tank to capacity. Treated effluent coming out from
the tank will be passed through softening plant followed with disinfection.
Figure 3: STP Design
Sewer System
The alignment and slope of the sewer line will follow the road network, drains or natural ground
surface and will be connected to the trunk sewers. The discharge point will be a treatment plant, a
pumping station, a water course or an intercepting sewer. Pumping stations would be provided at
places where the natural slope of the terrain is insufficient to permit gravity flow or the cost of
excavation is uneconomical to do the same.
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 11
RAIN WATER HARVESTING
The storm water collection system for the premises shall be self-sufficient to avoid any
collection/stagnation and flooding of water. The amount of storm water run-off depends upon many
factors such as intensity and duration of precipitation, characteristics of the tributary area and the
time required for such flow to reach the drains. The drains shall be located near the carriage way
along either side of the roads. Taking the advantage of road camber, the rainfall run off from roads
shall flow towards the drains. Storm water from various plots/shall be connected to adjacent drain
by a pipe through catch basins. Therefore, it is proposed to provide 4 RWH pits at selected
locations, which will catch the entire run-off from site.
1) Since the existing topography is congenial to surface disposal, a network of storm water
pipe drains is planned adjacent to roads. All building roof water will be brought down
through rain water pipes.
2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at regular
intervals for rain water harvesting and ground water recharging.
3) For basement parking, the rainwater from ramps will be collected in the basement storm
water storage tank. This water will be pumped out to the nearest external storm water drain.
4) Peak Hourly rainfall of 40 mm/hr shall be considered for designing the storm water drainage
system.
Rain water harvesting has been catered to and designed as per the guideline of CGWA. Peak hourly
rainfall has been considered as 45 mm/hr. The recharge pit of 3 m diameter and 4 m depth is
constructed for recharging the water. Inside the recharge pit, a recharge bore is constructed having
250-300 mm diameter with 160 mm PVC slotted pipe up to a layer where sandy aquifer/ deeper
aquifer permeable layer exist. The bottom of the recharge structure will be kept 5 m above this
level. At the bottom of the recharge well, a filter media is provided to avoid choking of the recharge
bore. Design specifications of the rain water harvesting plan are as follows:
Catchments/roofs would be accessible for regular cleaning.
The roof will have smooth, hard and dense surface which is less likely to be damaged
allowing release of material into the water. Roof painting has been avoided since most
paints contain toxic substances and may peel off.
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 12
All gutter ends will be fitted with a wire mesh screen and a first flush device would be
installed. Most of the debris carried by the water from the rooftop like leaves, plastic bags
and paper pieces will get arrested by the mesh at the terrace outlet and to prevent
contamination by ensuring that the runoff from the first 10-20 minutes of rainfall is flushed
off.
No sewage or wastewater would be admitted into the system.
No wastewater from areas likely to have oil, grease, or other pollutants has been connected
to the system.
Calculations for storm water load -
Roof-top area = Ground Coverage = 5685.191 m2
Green Area = 13,020.734 m2
Paved Area = Total Plot Area – (Roof-top Area + Green Area)
= 30,480.00 – (5685.191 + 13,020.734)
= 11,774.075 m2
Run-off from green and paved area:
Green Area = 13,020.734 × 0.045 × 0.1
= 58 m3/hr
Paved Area = 11,774.075 × 0.045 × 0.75
= 397 m3/hr
Total Run-off from green and paved area = 397 + 58 = 455 m3/hr
Taking 15 minutes retention time, total volume of storm water = 455/4
= 114 m3
Taking the effective dia and depth of a Recharge pit 3 m and 4 m respectively, Volume of a single
Recharge pit = π r2h = 3.14 × 1.5 × 1.5 × 4 = 28 m
3
Hence no. of pits required = 114 / 28 = 5.083 Pits = 4 pits
4 Rain Water Harvesting pits are proposed for artificial ground water recharge.
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 13
Figure 4: Rain Water Harvesting Pit Design
Run-off from roof top:
Monthly rain water harvesting potential of roof-top area = Roof-top area × Maxm
monthly
rainfall (m) × runoff coefficient
= 5685.191 × 0.10 × 0.9
= 512 m3
Considering storage facility for 2 days run-off = 512/15
= 34 m3
Volume of a tank (3 × 2 × 4 m) = 24 m3
Hence no. of tanks required = 34/24 = 1.4
2 tanks are proposed for harvesting run-off from rooftop area.
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 14
PARKING FACILITIES
Adequate provision will be made for parking within the project site. Parking details are provided
below:
PARKING REQUIRED:
As per MoEFCC norms = 1 ECS/ 100 m2 Proposed FAR area
= 1,05,570.355/100
= 1056 ECS
Total parking required as per MoEFCC norms = 1056 ECS
As per bye-laws = 1 ECS/80 m2 of Permissible FAR
= 106680/80
= 1334 ECS
Total Parking required as per bye-laws = 1334 ECS
PARKING PROPOSED:
Area proposed for Stilt parking = 3244.998 m2
Area proposed for 1 ECS of Stilt parking = 30 m²
Parking proposed for Stilt parking = 108 ECS
Area proposed for Podium Parking = 15301.572 m2
Area proposed for 1 ECS of Podium Parking = 30 m²
Parking proposed for Podium Parking = 510 ECS
Area proposed for Basement Parking = 21986.571 m2
Area proposed for 1 ECS of Basement Parking = 30 m²
Parking proposed for Basement Parking = 732 ECS
TOTAL PARKING PROPOSED = 108 + 510 + 732 = 1350 ECS
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 15
POWER REQUIREMENT
The power requirement shall be met from Noida Power Company Limited. The total power
requirement for the project post modification will be 5137 KVA.
Details of D.G Set
There is provision of 4 no. of DG sets of total 3270 KVA (2 X 1010 + 2 X 625) capacity for power
back up in the project. The DG sets will be equipped with acoustic enclosure to minimize noise
generation and adequate stack height for proper dispersion.
SOLID WASTE GENERATION
Solid waste would be generated both during the construction as well as operation phase. The solid
waste during the construction phase comprise of excavated materials, used bags, bricks, concrete,
MS rods, tiles, wood etc. The following steps are proposed to be followed for the management solid
waste:
Construction yards have been provided for storage of construction material within project
site.
The excavated material such as topsoil and stones are being reused for construction.
Excavated top soil is being reused for landscaping development.
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 16
Solid Waste
Construction
Waste Food Waste
Construction waste,
Broken Bricks,
Waste Plaster
Empty Cement
Bags
Used in re-filling,
raising site level
For Road making purpose
Excavated Soil
Top soil conserved for landscaping,
balance & re-filling
As per MSW Rules, 2016
Figure 5: Solid Waste Management Scheme (Construction Phase)
During the operation phase, waste will comprise of domestic as well as horticultural waste. The
solid waste generated from the project shall be approx. 3085 kg per day (@ 0.50 kg per capita per
day for residents @ 0.15 kg per capita per day for visitor, @ 0.25 kg per capita per day for staff and
landscape waste @ 0.2 kg/acre/day).
Following arrangements will be made at the site in accordance to Municipal Solid Waste
(Management and Handling) Rules, 2016.
Table 8: Calculation for Solid Waste Generation from Project (Operation Phase)
S.
No. Category Occupancy
Per Capita Waste
Generation
(kg/day)
Waste generated
(kg/day)
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 17
1. Residents 5643 0.5 2821.5
2. Staff 382 0.25 95.5
3. Visitors 824 0.15 124
4. Landscape waste 3.21 acre @ 0.2 kg/acre/day 1
5. STP sludge 43
TOTAL SOLID WASTE 3085 kg/day
Collection and Segregation of waste
1. A door to door collection system will be provided for collection of domestic waste from
household units.
2. Local vendor will be hired to provide separate colored bins for dry recyclable and Bio-
degradable waste.
3. Adequate number of colored bins (Green, Blue, and Dark Grey bins separate for Bio-
degradable and Non Bio-degradable) are proposed to be provided at the strategic
location within the complex.
4. Litter bin will also be provided in open areas like parks, etc.
Treatment of waste
Bio-Degradable waste
1. Bio-degradable waste will be subjected to composting through Organic Waste Converter to
form manure for use in gardening/horticulture.
2. STP sludge is proposed to be used as manure.
3. Horticultural waste is proposed to be composted and used for gardening purpose.
Recyclable waste
1. Grass Recycling – The cropped grass will be spread on the green area. It will act as manure
after decomposition.
2. Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclers.
Non-Recyclable waste
Non-Recyclable waste will be disposed through a local approved agency. The solid waste
management scheme for Operation Phase is depicted in the figure below:
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 18
Figure 6: Solid Waste Management Scheme (Operation Phase)
Organic Waste Converter
A waste converter is a machine used for the treatment and recycling of solid and liquid refuse
material. A converter is a self-contained system capable of performing the following functions:
pasteurization of organic waste; sterilization of pathogenic or biohazard waste; grinding and
pulverization of refuse into unrecognizable output; trash compaction; dehydration.
Benefits of organic waste converter:
1. Large quantity of solid waste is converted to manure in a very short period
2. Manure can be used as compost for gardening
3. Machine requires less space and the efficiency is high
4. Manpower and maintenance is very less
5. This is one of the latest techniques of managing biodegradable solid waste.
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 19
Operation cost of OWC:
Organic Waste Converter - 300 (Dim. 3m × 4m) is proposed to be used for composting waste
120kg/batch or 3000 kg/day & it requires electricity of about 13.5 HP.
No. of batches /day = 3000/20 = 150
No. of batches to convert 1697 kg/day = 1697/20 = 85
Monthly per capita Operation Cost of OWC:
The operating cost of OWC-300 = 90,000 INR/month
Cost/day = 90,000/30
= 3000/- (i.e. 30 batch/day = 3000/-)
1 batch/day cost = 3000/30
= 100 INR
Cost for 85 batch/day = 85 × 100/-
= 8500/-
Monthly operating cost = 30 × 8500
= 2,55,000/-
Total residential population of the project = 5643
Operating cost of OWC-300 = 2,55,000 INR/month
Monthly per capita cost
= Monthly operating cost/Total Residential population of the project (i.e. 5643)
= 2,55,000/5643
= INR 45/month
GREEN AREA
The total green area measures 13,020.734 m2 (41 % of plot area) which includes area under
greenbelt plantation, avenue plantation and parks.
Evergreen tall and ornamental trees have been proposed to be planted. List of the plantation is given
below in Table 9.
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 20
Table 9: Proposed Plantation List
DETAILS OF CONSTRUCTION MATERIAL
1. Coarse sand
2. Fine sand
3. Stone aggregate
4. Stone for masonry work
5. Cement
6. Reinforcement steel
7. Pipe scaffolding (cup lock system)
8. Bricks
S. No. Scientific Name Local Name
1 Cassia fistula Amaltas
2 Delonix regia Gulmohar
3 Buhinia purpurea Koenar
4 Bauhinia variegata Kachnar
5 Peltophorum ferrugineum Copperpod
6 Jacaranda ferrugineum Jacaranda
7 Lagerstroe flosreginae Banaba
8 Grevillea robusta Silver Oak
9 Callistemon lanceolatus Bottle brush
10 Anthocephatus cadamba Kadamb
11 Polyalthia longifolia False Ashok
12 Putranjiva roxburghii Putranjiva
13 Sterculia alata Cola nut
14 Melia azadirachta Bainkan
15 Tamarindus indica Imli
Modification of Group Housing Project ‘Trident Embassy’
Plot no. 5B, Sector – 1,
Greater Noida, U.P. PFR
M/s Trident Infra Homes Pvt. Ltd 21
9. CLC fly ash blocks
10. Crazy (white marble) in grey cement
11. P.V.C. conduit
12. MDS, MCBs
13. PVC overhead water tanks
14. 2 1/2'’ thick red colour paver tiles
15. PPR (ISI marked)
16. PVC waste water lines
17. S.W. sewer line up to main sewer
18. UPVC is being used as the Sewer pipe material
19. PVC rain water down take
20. Stainless steel sink in kitchen
21. Joinery hardware- ISI marked
LIST OF MACHINERY USED DURING CONSTRUCTION
(i) Dumper
(ii) Concrete mixer with hopper
(iii) Excavator
(iv) Concrete Batching Plant
(v) Cranes
(vi) Road roller
(vii) Bulldozer
(viii) RMC Plant
(ix) Tower Cranes
(x) Hoist
(xi) Labor Lifts
(xii) Pile Boring Machines
(xiii) Concrete pressure pumps
(xiv) Mobile transit mixer