MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th...

224
MODELLING LOSSES IN FLOOD ESTIMATION MAHBUB ILAHEE

Transcript of MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th...

Page 1: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

KODE

MODELLING LOSSES IN FLOOD ESTIMATION

MAHBUB ILAHEE

Page 2: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

MODELLING LOSSES IN FLOOD

ESTIMATION

School of Urban Development Queensland University of Technology

By

MAHBUB ILAHEE B.E (CIVIL)

MASTER OF TECHNOLOGY (CIVIL)

A THESIS SUBMITTED TO THE SCHOOL OF URBAN DEVELOPMENT QUEENSLAND UNIVERSITY OF TECHNOLOGY IN PARTIAL FULFILMENT OF THE REQUIRMENTS FOR THE DEGREE OF DOCTOR OF PHILOSOPHY

MARCH 2005

Page 3: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation iii

ACKNOWLEDGEMENT

The author wishes to express his appreciation and wholehearted sense of gratitude to

his principal supervisor Professor Rod Troutbeck, postgraduate research co-ordinator

Professor David Thambiratnam and associate supervisor Dr. Ashantha Goonetilleke

for their enthusiastic guidance, valuable suggestions, constructive criticisms, friendly

discussions and persistent supervision which were indispensable for the completion

of this research work

The author also wants to express his heartfelt thanks to Professor Mahen Mahendran,

Dr. Ataur Rahman, Dr. Walter Boughton, Erwin Wienmann and Peter Hill for their

valuable suggestion, advice, constant encouragement and meticulous efforts of this

research work.

Innumerable thanks are extended to Queensland University of Technology (QUT) for

providing a postgraduate research scholarship to conduct this research, Department

of Natural Resources and Mines (DNRM) and Bureau of Meteorology (BOM) for

providing data and material for the research, all the staff of School of Civil

Engineering for the facilities and assistance for the research.

The author gratefully acknowledges the continuing patience and vital sacrifices of his

beloved mother, father, wife and children and all the brothers and sisters whose love

and support were a constant source of encouragement and guidance to him.

Page 4: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation iv

KEYWORDS Losses, Rainfall and runoff modelling, Flood estimation, Initial losses, Continuing

losses, joint probability Approach, Design Event Approach, IL–CL model,

Pluviograph station, Stream gauging station, Daily rainfall station, Baseflow,

streamflow, Study catchments, Storm losses, Design floods, Rainfall-runoff, Runoff

routing

Page 5: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation v

ABSTRACT Flood estimation is often required in hydrologic design and has important economic

significance. For example, in Australia, the annual spending on infrastructure

requiring flood estimation is of the order of $650 million ARR (I.E. Aust., 1998).

Rainfall-based flood estimation techniques are most commonly adopted in practice.

These require several inputs to convert design rainfalls to design floods. Of all the

inputs, loss is an important one and defined as the amount of precipitation that does

not appear as direct runoff. The concept of loss includes moisture intercepted by

vegetation, infiltration into the soil, retention on the surface, evaporation and loss

through the streambed and banks. As these loss components are dependent on

topography, soils, vegetation and climate, the loss exhibits a high degree of temporal

and spatial variability during the rainfall event.

In design flood estimation, the simplified lumped conceptual loss models were used

because of their simplicity and ability to approximate catchment runoff behaviour. In

Australia, the most commonly adopted conceptual loss model is the initial loss-

continuing loss model. For a specific part of the catchment, the initial loss occurs

prior to the commencement of surface runoff, and can be considered to be composed

of the interception loss, depression storage and infiltration that occur before the soil

surface saturates. ARR (I. E. Aust., 1998) mentioned that the continuing loss is the

average rate of loss throughout the remainder of the storm.

At present, there is inadequate information on design losses in most parts of

Australia and this is one of the greatest weaknesses in Australian flood hydrology.

Currently recommended design losses are not compatible with design rainfall

information in Australian Rainfall and Runoff. Also design losses for observed

storms show a wide variability and it is always difficult to select an appropriate value

of loss from this wide range for a particular application. Despite the wide variability

of loss values, in the widely used Design Event Approach, a single value of initial

and continuing losses is adopted. Because of the non-linearity in the rainfall-runoff

process, this is likely to introduce a high degree of uncertainty and possible bias in

the resulting flood estimates. In contrast, the Joint Probability Approach can consider

probability-distributed losses in flood estimation.

Page 6: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation vi

In ARR (I. E. Aust., 1998) it is recommended to use a constant continuing loss value

in rainfall events. In this research it was observed that the continuing loss values in

the rainfall events were not constant, rather than it decays with the duration of the

rainfall event. The derived loss values from the 969 rainfall and streamflow events of

Queensland catchments would provide better flood estimation than the recommended

design loss values in ARR (I. E. Aust., 1998). In this research, both the initial and

continuing losses were computed using IL-CL loss model and a single median loss

value was used to estimate flood using Design Event Approach. Again both the

initial and continuing losses were considered to be random variables and their

probability distribution functions were determined. Hence, the research showed that

the probability distributed loss values can be used for Queensland catchments in near

future for better flood estimate.

The research hypothesis tested was whether the new loss value for Queensland

catchments provides significant improvement in design flood estimation. A total of

48 catchments, 82 pluviograph stations and 24 daily rainfall stations were selected

from all over Queensland to test the research hypothesis. The research improved the

recommended design loss values that will result in more precise design flood

estimates. This will ultimately save millions of dollars in the construction of

hydraulic infrastructures.

Page 7: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation vii

LIST OF PUBLICATIONS NATIONAL AND INTERNATIONAL CONFERENCE PAPERS 1. Ilahee, M. and Rahman, A. (2003).Investigation of continuing losses for design

flood estimation: A case study in Queensland. 28th Hydrology and Water Resources

Symposium, the Institution of Engineers, Australia, Wollongong NSW Australia,

10-13 November

2. Ilahee, M. and Rahman, A. (2003). Storm loss studies for the Bremer river

catchment in Australia. International Union of Geodesy and Geophysics (IUGG),

Sapporo, Japan (Only Abstract published), June 30 – July 11.

3. Ilahee, M., Rahman, A. and Boughton, W.C. (2002). New design losses in

Queensland. 27th Hydrology and Water Resources Symposium, the Institution of

Engineers, Australia, Melbourne, 20-23 May.

4. Ilahee, M., Rahman, A. and Boughton, W. C. (2001). Probability distributed initial

losses for flood estimation in Queensland. International Congress on Modelling and

Simulation, The Australian National University Canberra, 10-13 December.

5 Ilahee, M., Rahman, A. and Boughton, W. C. (2001). A new loss function for flood

estimation in Queensland. 6th Physical Infrastructure Centre Postgraduate

Conference, School of Civil Engineering, Queensland University of Technology, 19

June 2001, p. 87-96

6. Ilahee, M., Rahman, A. Assessment of design losses for flood estimation in

Queensland. Research Report, Physical Infrastructure Centre, School of Civil

Engineering, Queensland University of Technology, 2001, pp. 49.

7. Rahman, A., Ilahee, M. and Boughton, W. C. (2001). Improved fixed and

stochastic design losses for Queensland. 13th Queensland Hydrology Symposium, 6-

7 Nov, 2001, Brisbane.

Page 8: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation viii

TABLE OF CONTENTS

Acknowledgements iii

Keywords iv

Abstract v

List of Publications vii

Table of Contents viii

List of Tables xiv

List of Figures xvi

List of Symbols xix

Statement of Original Authorship xxii

1. INTRODUCTION 1-1 1.1 Background 1-1

1.2 Scope and Objectives 1-3

1.3 Research hypotheses 1-4

1.4 Justification for the study 1-5

1.5 Outline of the thesis 1-5

2. REVIEW OF DESIGN LOSSES IN FLOOD

ESTIMATION 2-1 2.1 General 2-1

2.2 Methods based on point infiltration equations 2-1 2.2.1 Horton equation 2-1

2.2.2 Green-Ampt model 2-2

2.2.3 Philip equation 2-4

2.2.4 Richards equation 2-5

2.2.5 Applications of the theoretical equations in flood estimation 2-7

2.3 Conceptual loss models 2-7

2.3.1 General 2-7

2.3.2 Spatially lumped loss models 2-8

Page 9: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation ix

2.3.3 Constant loss rate 2-8

2.3.4 Initial loss–Continuing loss (IL-CL) model 2-10

2.3.5 Proportional loss rate (PLR) model 2-12

2.3.6 SCS curve number method 2-13

2.4 Loss accounting in rainfall runoff models 2-15 2.4.1 Rainfall Runoff Routing using Burroughs (RORB) 2-15

2.4.2 Watershed Bounded Network Model (WBNM) 2-15

2.4.3 Urban Runoff and Basin System (URBS) 2-16

2.4.4 Australian Water Balance Model (AWBM) 2-17

2.4.5 Comments 2-18

2.5 Loss estimate for real-time flood forecasting 2-18 2.5.1 Loss models adopted in real-time flood forecasting 2-19

2.5.2 Initial loss-continuing loss and initial

loss-proportional loss models 2-20

2.5.3 Constant loss rate 2-20

2.5.4 Antecedent precipitation index (API) 2-20

2.5.5 Point infiltration equations 2-21

2.5.6 Comments 2-21

2.6 Currently recommended design loss values

in Australia 2-22 2.6.1 Past studies on losses 2-22

2.6.2 Losses recommended in ARR (I. E. Aust., 1998) 2-25

2.7 Summary 2-28

3. FLOOD ESTIMATION METHODS 3-1 3.1 General 3-1

3.2 Design Event Approach 3-1

3.3 Joint Probability Approach 3-4

3.4 Continuous Simulation 3-8

3.5 Selection of flood estimation method 3-9

3.6 Summary 3-9

Page 10: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation x

4. STUDY CATCHMENTS 4-1 4.1 General 4-1

4.2 Criteria to select study catchments 4-1

4.2.1 Catchment area 4-1

4.2.2 Regulation 4-2

4.2.3 Record length 4-2

4.2.4 Catchment boundary 4-3

4.3 Mapping catchment boundaries and the selected

pluviograph, daily rainfall and streamflow stations 4-4

4.4 Selected catchments 4-6

4.5 Summary 4-11

5. DATA ANALYSIS 5-1 5.1 General 5-1

5.2 List of stream gauge, pluviograph and daily

rainfall stations 5-1

5.3 Streamflow data 5-4

5.4 Pluviograph data 5-6

5.5 Daily Rainfall data 5-8

5.6 Formatting stream flow, rainfall and

pluviograph data 5-10

5.7 Process to estimate the weighting average rainfall of a

catchment for more than one pluviograph and daily

rainfall stations 5-11

5.8 Selection of rainfall and streamflow events 5-14

5.9 Summary 5-16

6. METHODOLOGY FOR LOSS COMPUTATION 6-1 6.1 General 6-1

Page 11: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation xi

6.2 Runoff generation mechanism 6-2

6.3 Method of initial loss computation 6-2

6.4 Method of continuing loss computation 6-4

6.5 Method of proportional loss computation 6-7

6.6 Method of volumetric runoff coefficient computation 6-7

6.7 Losses versus catchment size 6-8

6.8 FORTRAN program developed 6-9

6.9 Surface runoff threshold value 6-10

6.10 Reasons for the variability of calculated loss values 6-10

6.11 Summary 6-11

7. METHOD OF BASEFLOW SEPARATION 7-1 7.1 General 7-1

7.2 Review of baseflow separation process 7-1

7.3 Results 7-7

7.4 summary 7-14

8. RESULTS AND DISCUSSIONS 8-1 8.1 General 8-1

8.2 Fixed losses 8-1 8.2.1 Comparison was made between derived computed losses

and ARR (I. E. Aust., 1998) recommended losses 8-2

8.2.2 Interactions of losses with other variables 8-6

8.2.2.1 Different methods of computing continuing losses

and their comparison 8-6

8.2.2.2 Comparison of derived loss values with different

surface runoff threshold values 8-10

8.2.2.3 Variation of continuing losses with duration 8-14

8.3 Stochastic losses 8-18 8.3.1 Initial losses 8-18

Page 12: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation xii

8.3.2 Continuing losses 8-23

8.4 Regionalisation of derived loss values 8-24 8.4.1 General 8-24

8.4.2 Basis of Queensland recommended design

losses in ARR (I. E. Aust., 1998) 8-25

8.4.2.1 Recommended loss values in ARR (I. E. Aust., 1998) 8-25

8.4.2.2 Recommended median initial loss for eastern

Queensland 8-25

8.4.2.3 Recommended median continuing loss for eastern

Queensland 8-25

8.4.2.4 Recommended initial loss for eastern Queensland 8-26

8.4.3 Comments 8-26

8.5 Validation of results 8-27 8.5.1 Calibration of runoff routing model 8-27

8.5.2 Comparison of flood frequency curves with the observed

losses and the derived losses from this research 8-28

9. IMPLICATIONS AND IMPACTS OF THE

RESEARCH 9-1 9.1 General 9-1

9.2 Implications on model development 9-1

9.3 Socio – economic implication 9-3

10. CONCLUSIONS AND RECOMMENDATIONS 10-1 10.1 Introduction 10-1

10.2 Overview of this study 10-2

10.3 Conclusions 10-7

10.4 Suggestions for future research 10-10

REFERENCES R-1

APPENDIX A A-1

Page 13: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation xiii

APPENDIX B B-1

APPENDIX C C-1

APPENDIX D D-1

APPENDIX E E-1

APPENDIX F F-1

APPENDIX G G-1

APPENDIX H H-1

Page 14: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation xiv

LIST OF TABLES

Table 2.1 Summary of previous studies on losses 2-23

Table 2.2 Currently recommended Design Losses

(From ARR, 1987, 1998) 2-26

Table 4.1 Stream gauge station number, their location, catchment

area and streamflow record length of the study catchments 4-9

Table 5.1 List of the selected stream gauge, pluviograph and daily

rainfall stations 5-2

Table 7.1 Effects of changing α value on CL, PL (proportional loss)

and Volumetric runoff co-efficient 7-10

Table 7.2 Effects of changing value on CL, PL (proportional loss)

and Volumetric runoff coefficient 7-14

Table 8.1 Descriptive statistics of the computed IL and CL values

(N = number of events) 8-3

Table 8.2 Comparison of computed median initial and median

continuing loss values with ARR recommended

median loss values for eastern Queensland catchments 8-4

Table 8.3 Comparison of initial loss values from Queensland and

Victorian Catchments 8-5

Table 8.4 Comparison of computed median initial and median continuing

loss values with ARR (I. E.. Aust., 1998) recommended median

loss values for western Queensland catchments 8-6

Table 8.5 Descriptive statistics of the computed CL and CL1 values

(N = number of events) 8-9

Table 8.6 Comparison between computed CL and CL1 values for all the

selected catchments 8-10

Table 8.7 Comparison of computed IL, CL and CL1 values

with different surface runoff threshold values

(N = number of events) 8-11

Table 8.8 Comparison of loss values with different

threshold values 8-13

Page 15: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation xv

Table 8.9 Loss statistics for 15 Queensland catchments

(N = number of events, SD = standard deviation) 8-20

Table 8.10 Comparison at-site observed and generated ILs

data for the 15 catchments 8-23

Page 16: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation xvi

LIST OF FIGURES

Figure 2.1 Constant loss rate 2-9

Figure 2.2 Initial loss - continuing loss (IL-CL) 2-11

Figure 2.3 Proportional loss 2-12

Figure 2.4 Schematic diagram of AWBM model (Boughton 1993) 2-18

Figure 3.1 Schematic diagram of the Design Event Approach 3-3

Figure 3.2 Schematic diagram of the Joint Probability Approach

(Monte Carlo simulation technique, probability-distributed

components shaded) 3-7

Figure 4.1 Example of a single catchment with a stream gauging

station 119006A, pluviograph and daily rainfall stations 4-5

Figure 4.2 Distribution of the drainage divisions and the basins

in Queensland 4-7

Figure 4.3 Locations of the 48 study catchments in Queensland 4-8

Figure 4.4 Distribution of catchment areas of the study catchments

in Queensland 4-11

Figure 5.1 Histogram showing the distribution of streamflow

record lengths 5-4

Figure 5.2 Cumulative plot showing the range and median value of

streamflow data record lengths 5-5

Figure 5.3 Histogram showing the distribution of pluviograph record

lengths 5-7

Figure 5.4 Cumulative plot showing the range and median value of

Pluviograph data record lengths 5-8

Figure 5.5 Histogram showing the distribution of daily rainfall record

Lengths 5-9

Figure 5.6 Cumulative plot showing the range and the median value of

daily rainfall record lengths 5-10

Figure 5.7 Example of the grids ranging from 40×40 to 80×80 depending

on the catchment size 5-12

Figure 5.8 Rainfall events: complete storms and storm-cores 5-16

Figure 6.1 Initial loss – Continuing loss (IL-CL) model 6-3

Figure 7.1 Comparison of baseflow separation by two different models 7-5

Page 17: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation xvii

Figure 7.2 Example of comparison of baseflow recharge models in large

and small runoff events 7-6

Figure 7.3 Separation of streamflow components in a semi-log graph for

Event 1, when α=0.003, 0 .004, 0.005, 0.008 (Bremer River) 7-9

Figure 7.4 The baseflow separation with α = 0.004 for 3 events in the

Bremer River catchment 7-11

Figure 7.5 Baseflow separation of four events for Tenhill Creek

catchment. 7-12

Figure 7.6 Baseflow separation for the four events with α =0.0055

(Tenhill Creek) 7-13

Figure 8.1 Variation of continuing loss values with duration in all 48

selected Queensland catchments 8-15

Figure 8.2 Variation of continuing loss values with duration in 11

eastern Queensland catchments 8-16

Figure 8.3 Variation of continuing loss values with duration in 5

western Queensland catchments 8-16

Figure 8.4 Variation of continuing loss values with duration in 12

northern Queensland catchments 8-17

Figure 8.5 Locations of the 15 study catchments in Queensland 8-19

Figure 8.6 Histogram showing distribution of ILs

for catchment 143110 8-21

Figure 8.7 Histogram showing distribution of ILc for

catchment 143110 8-22

Figure 8.8 Distribution of observed CL values 8-24

Figure 8.9 Fitting the single non-linear storage model for

the Black River catchment (event 27/12/97) 8-28

Figure 8.10 Comparison of derived flood frequency curve with the

results of 48 selected catchments and ARR

for Burnett river 8-30

Figure 8.11 Comparison of derived flood frequency curve with

the results of 48 selected catchments and ARR

for Bluewater creek 8-31

Page 18: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation xviii

Figure 8.12 Comparison of derived flood frequency curve with

the results of 48 selected catchments and

ARR (I. E. Aust., 1998) for Black river. 8-32

Page 19: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation xix

LIST OF SYMBOLS

A = Constant (mm/h)

a = Filter parameter ( or factor).

α = The fraction of the surface runoff

a1 = Constant

a2 = Constant

a3 = Constant

B = Baseflow

BF = Baseflow (mm)

Bi = Rate of baseflow at any time

CL = Continuing loss

C1 = Rainfall (mm/h)

C2 = Rainfall (mm/h)

CL1 = Continuing loss occurred within the time t1

CWAR = Catchment weighting average rainfall

D = Rainfall duration

D1 = Daily rainfall station site1

Dc = Storm-core duration

fp = Infiltration capacity (mm/h)

fo = Initial infiltration capacity (mm/h)

fc = Final infiltration capacity (mm/h)

kf = Fitted quick response streamflow at the kth sampling instant:

=F Cumulative infiltration volume from beginning of the event (mm)

F1 = Areal reduction factor

F2 = Areal reduction factor

H0 = Null hypothesis

H1 = Alternative hypothesis

IL = Initial loss

ILs = Complete storm initial loss

ILc = Storm-core initial loss

Page 20: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation xx

2ID = 2 year ARI intensity for the selected storm duration D 2Id = 2 year ARI intensity for the sub-storm duration d

I = Rainfall intensity

k = Exponential decay constant

k = Runoff model calibration

=sK Saturated hydraulic conductivity (mm/h)

k = Hydraulic conductivity of soil

k = Storage delay coefficient (hour)

k = Constant

LL = Lower limit

m = Non-linearity parameter

m = Runoff model calibration

=M Initial soil moisture deficit (vol/vol)

N = Number of events

P = Catchment response model and parameters

P1 = Pluviograph station site 1

PL = Proportional loss

Q = Streamflow discharge (m3/s)

QF = Quickflow, assumed to be resulted from the rainfall event, expressed in mm

RFID = Average rainfall intensity during the entire storm duration

RFId = Average rainfall intensity during a sub-storm duration

R = Total rainfall of the event expressed in average depth of rainfall in mm

S = Sorptivity of soil (mm/h1/2)

S1= Storage capacity

S2 = Storage capacity

S3 = Storage capacity

S = Spatial pattern

S1 = Stream gauging station

SD = Standard deviation

SFT = Total streamflow (mm)

S = Storage (m3)

t = Time

Page 21: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation xxi

t2 = duration of infiltration (h)

t = Time elapsed between the start of the surface runoff and end of the rainfall event

t1 = Time elapsed between the start of the surface runoff and end of the surface

runoff (hour)

TP = Rainfall temporal pattern

Ui = Incremental value

UL = Upper limit

ky = Total streamflow

z = Space coordinate in vertical direction

=ψ Capillary suction at wetting front ( mm of water)

=θ Volumetric water content

=ψ Total metric potential

Page 22: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation xxii

The work contained in this thesis has not been previously submitted for a degree or

diploma in any other higher education institution. To the best of my knowledge and

belief, the thesis contains no material previously published or written by another

person except where due reference is made.

Signed: ________________________________________________________ Date: _________________________________________________________

Page 23: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 1-1

CHAPTER 1

INTRODUCTION

1.1 Background

Flood estimation is often required in hydrologic design and has important economic

significance. For example, in Australia, the annual spending on infrastructure

requiring flood estimation is of the order of $650 million (I. E. Aust., 1998). Design

flood estimation methods can be broadly classified into two groups: streamflow

based methods and rainfall based methods. Rainfall based flood estimation

techniques are most commonly adopted in practice. These require several parameters

to convert design rainfalls to design floods. Among the parameters of flood

estimation, loss is an important factor and is defined as the amount of precipitation

that does not appear as direct runoff. Loss includes all the factors involved in

reducing the runoff during a flood event. The concept of loss includes moisture

intercepted by vegetation (interception loss), infiltration into the soil (infiltration),

retention on the surface (depression storage), evaporation and loss through the

streambed and banks. As these components are dependent on topography, soils,

vegetation and climate, the losses exhibit a high degree of temporal and spatial

variability during a rainfall event. Most loss models do not directly account for

individual components such as interception, depression storage and transmission

losses directly.

In design flood estimation, simplified lumped conceptual loss models are commonly

used because of their simplicity and ability to approximate catchment runoff

behaviour. Secondly, the detailed parameters needed for calculating individual loss

components are generally not available. This is particularly true for design loss

which is probabilistic in nature and for which complicated theoretical models may

not be required. In Australia, the most commonly adopted conceptual loss model is

the initial loss-continuing loss model (I. E. Aust., 1998; Hill et al., 1996a,b; Rahman

et al., 2000). The initial loss occurs prior to the commencement of surface runoff,

and can be considered to be composed of the interception loss, depression storage

Page 24: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 1-2

and infiltration that occur before the soil surface is saturated. In design rainfall

events, the continuing loss is computed as the average rate of loss that occurs up to

the end of the rainfall event, after the initial loss is satisfied.

Losses are important inputs to rainfall runoff models. However, the paucity of

information on design losses constitutes one of the greatest weaknesses in Australian

flood design (Pilgrim and Robinson, 1988). The design loss values, which are

available for the initial loss and recommended in Australian Rainfall and Runoff (I.

E. Aust., 1998), exhibit a wide range, which makes it difficult to select an

appropriate value for a particular design application.

Many studies (such as Hill and Mein, 1996; Waugh, 1991) have found that the use of

the design losses recommended in ARR (I. E. Aust., 1987) with the design rainfalls

results in overestimation of design peak flows, when compared with a frequency

analysis of recorded peak flows. This indicates that, for many catchments, the design

losses recommended in ARR (I. E. Aust., 1987; I. E. Aust., 1998) are too low.

There are two inadequacies in the current recommended loss values in ARR (I. E.

Aust, 1998), most of which were derived from analysis of large flood events. The

selection of high runoff events for loss derivation is biased towards wet antecedent

conditions. That is, loss tends to be low. The second inadequacy is that storm losses

do not account for the nature of design rainfall information, which is the design

intensity-frequency-duration and design temporal patterns of rainfall. This design

rainfall information has been derived from a rainfall burst within longer storms, but

losses are derived from complete storms. Since antecedent rainfall will pre-wet the

catchment, losses derived for storms will tend to be too high for application to bursts.

It is recognised in ARR (I. E. Aust., 1998) that these two inadequacies have opposite

effects, and it is assumed by users of the current design loss values that they

compensate for each other.

Page 25: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 1-3

1.2 Scope and Objectives

The scope and objectives of the research work are described here.

The scope of the proposed research was:

• This research was restricted to the estimation of losses for rural catchments and

therefore urbanised catchments were not considered.

• The selected catchments size was small to medium, therefore large catchments

were not considered.

• The streamflow needed to represent ‘natural’ flow, with no large diversions or

flow regulated by reservoirs.

• All the catchments which were used in this research work were selected from

Queensland only.

• Baseline data such as rainfall, streamflow, catchment boundaries and catchment

areas were obtained from relevant Commonwealth and State government

agencies.

• Commercially available software was used for processing data.

The objectives of the proposed research were:

• To identify the impact of losses, its distribution and its functional form for design

flood estimates.

• To develop a loss function to be used in design flood estimation. The new loss

function would account for the probability-distributed nature of both initial and

continuing losses and their variation with rainfall duration.

• To regionalise the derived loss values for Queensland so that the loss distribution

can be derived for ungauged catchments in Queensland.

• To recommend new design loss values for Queensland, this will ultimately save

millions of dollars in the construction of hydraulic infrastructures.

Page 26: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 1-4

1.3 Research hypotheses It was hypothesised that a new loss function that considers continuing loss as a

probability-distributed variable and variation of the continuing loss with rainfall

duration would result in significant reduction of uncertainty and bias associated with

design flood estimates. The nature of the variation of continuing loss with rainfall

duration would be identified and incorporated in the new loss function. Thus,

continuing loss would be a function of rainfall duration as given by the following

equation:

)(DfCL = (4.1)

The hypotheses to be tested were:

(H0 = Null hypothesis, H1 = Alternative hypothesis)

(a) H0: The new loss value provides more accurate design flood estimates

over the method recommended in ARR (I. E. Aust., 1998).

H1: The new loss value does not offer any improvement over the

existing method.

(b) H0: The underlying probability distribution for initial loss is 4–parameter

Beta distribution.

H1: The underlying probability distribution for Initial loss is not 4-parameter

Beta distribution.

(c) H0: The initial loss of whole of Queensland can be described by a single

probability distribution.

H1: The initial loss of whole of Queensland can not be described by a

single probability distribution.

(d) H0: The continuing loss of whole of Queensland can be described by a

single probability distribution.

H1: The continuing loss of whole of Queensland cannot be described by

a single probability distribution.

Page 27: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 1-5

1.4 Justification for the study

Loss is a vital input to rainfall runoff models, but there is inadequate information

and design data on losses in Queensland catchments. There are two inadequacies

identified in the currently recommended design loss values as discussed in Section

1.1. These inadequacies result in over estimation of design floods. Ultimately the

overestimation of design floods leads to the construction of over design and

expensive hydraulic infrastructures. It is therefore important to estimate suitable

design losses, which would ultimately save millions of dollars in the construction of

hydraulic infrastructures. Another reason for this research work is, a single

representative design loss value (mean or median value) is used from a wide range of

recommended losses with the Design Event Approach, as recommended by ARR (I.

E. Aust., 1998). This is likely to introduce a high degree of uncertainty and possible

bias in the resulting flood. It is therefore important to formulate an improved loss

function that can lead to more accurate design flood estimates.

1.5 Outline of the thesis

The thesis contains ten chapters. Chapter 2 discussed the method of infiltration, loss

models, recommended losses for Queensland and the review of design losses in flood

estimation. Different flood estimation methods are covered in Chapter 3. Chapter 4

presented the criteria to select the study catchments. Chapter 5 discussed how

pluviograph, daily rainfall and streamflow data were collected, formatted and

analysed for this research. The adopted methodology to compute the initial loss and

continuing loss of a rainfall streamflow event is detailed in Chapter 6. Chapter 7

describes how baseflow separation was executed from the streamflow, which was

necessary to compute continuing losses. Chapter 8 provides the results of all the

investigation performed during the analysis and compares the derived design loss

values of this research with the recommended design losses for Queensland. The

implications and impacts of this research work are documented in Chapter 9. The

conclusions of this research and the recommendations for future research and

development are outlined in Chapter 10.

Page 28: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-1

CHAPTER 2

REVIEW OF DESIGN LOSSES IN FLOOD

ESTIMATION

2.1 General

Rainfall-based flood estimation techniques are most commonly adopted in practice.

These require several parameters such as rainfall duration, intensity, temporal pattern

and loss. Selection of an appropriate loss value is very important. A low loss value

results in over estimation of design floods. A high loss value results in under

estimation of design floods. Of all the parameters, loss is the most important factor

and is defined as the amount of precipitation that does not appear as direct runoff.

Loss includes all the factors involved in reducing runoff during a flood event.

Losses during rainfall events can be represented by several methods. There are

mathematical equations based on point infiltration to estimate losses. However, in

practice losses are frequently represented by conceptual models. This chapter

describes the point infiltration equations used in loss estimation, followed by a

discussion on conceptual loss models. It also covers how losses are accounted for in

rainfall runoff models. It also discusses how loss is estimated for real-time flood

forecasting and the most commonly adopted loss models in real-time flood

forecasting. Finally it describes the currently recommended design losses for various

regions in Australia.

2.2 Methods based on point infiltration equation 2.2.1 Horton equation

Horton (1940) suggested that the infiltration capacity is a decay process as the soil

voids become exhausted. He described the infiltration rate at any time from the start

of an adequate supply of rainfall by the equation 2.1:

Page 29: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-2

pf = cf + ktc eff −− )( 0 (2.1)

where

fp = Infiltration capacity (mm/h)

fo = Initial infiltration capacity (mm/h)

fc = Final infiltration capacity (mm/h)

t = Time

k = Exponential decay constant.

fo is the initial infiltration rate at time t = 0 depending on soil moisture content and

soil type. fc and k are dependent on soil type and vegetation. The limitation of this

equation is that it is only applicable for shallow ponded conditions. Parameters are

difficult to predict because they have no physical significance (Mein and Larson,

1971). This infiltration equation is generally suitable for small catchments but not for

larger catchments. This is because as fc and k are dependent on soil type and

vegetation, larger catchments tend to be heterogeneous and the soil type and

vegetation do not remain the same throughout the catchment.

2.2.2 Green–Ampt model

A number of theoretically based infiltration models have evolved over the years.

Many of these models are based on the work performed by Green-Ampt (1911). The

Green-Ampt (G-A) method of infiltration estimation is based on Darcy’s law. This

method is based on the following assumptions:

(a) The soil surface is covered by a pool of water whose depth can be neglected.

(b) There is a definable wetting front in the soil, which separates a uniformly wetted

infiltrated zone from a totally dry uninfiltrated zone.

(c) Once the soil is wet, the water content in the soil does not change.

(d) A negative pressure is present at the wetting front.

Page 30: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-3

The G-A infiltration equation is described as:

)1( FM

sp kf ψ+= (2.2)

where

=pf Infiltration capacity (mm/h)

=sk Saturated hydraulic conductivity (mm/h)

=M Initial soil moisture deficit (vol/vol)

=ψ Capillary suction at wetting front ( mm of water)

=F Cumulative infiltration volume from beginning of the event (mm).

Mein and Larson (1971) showed that the Green-Ampt (G-A) model could be adapted

for a constant intensity rainfall at the surface (rather than ponded conditions). Chu

(1978) extended the application to an unsteady rain condition by shifting the time

scale to account for the effect of cumulative infiltration before ponding time. Mein

(1980) showed that G-A model can also be used successfully with variable rainfall by

shifting the time scale to account for the effect of cumulative infiltration before

ponding time. Brakensiek (1970) extended the model to allow for multiple soil

layers. Bouwer (1969) and Onstad et al. (1973) suggested modifications in capillary

suctions. Skaggs and Khalil (1982) outlined estimation procedures for the parameters

in the G-A equation. Todd (1980) had done the verification of the assumptions in the

derivation of G-A equation. Moore et al. (1981) mentioned that ks should be modified

for the effect of air entrapment in the field and surface conditions. Van Mullem

(1991) applied the G-A model to 12 catchments and it was found that the G-A model

did not predict peak flows well. Rajendran and Mein (1986) accounted for spatial

variability of infiltration rates in a catchment by using a scaling factor applied to

saturated hydraulic conductivity. Although the approach used by Rajendran and

Mein (1986) takes into account the spatial variability of infiltration, it does not

consider the effect of rainfall excess flowing and rainfall infiltration from one

subarea to another subarea. Also Smith and Hebbert (1979) showed that relative

positions of ponding regions are important in determining the catchment infiltration

loss.

Page 31: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-4

Since sK is a multiplier of other terms in the G-A equation (Equation 2.2), the

prediction accuracy of the equation is most sensitive to the value of the sK

parameter. It is important to note that sK value varies with the soil texture of the

catchment. Nandakumar et al. (1994) noted that for sand, sK is 23.56cm/h and for

clay sK is 0.06 cm/h. It is difficult to predict a suitable sK value for the whole

catchment, as catchments are heterogeneous in nature. For loamy sand sK is 5.98cm/h

and for sandy loam sK is 2.18cm/h. Hence there is no average value which can be

applicable for the heterogeneous catchment. To find a suitable sK for the whole

catchment is one of the limitation for this G-A infiltration equation. The other

limitation of the equation is that soil infiltration cannot be uniform throughout the

catchment. For example where there is a crack, hole or tree root in the catchment, the

infiltration rate in one part of the catchment will be different than another part of the

catchment. Mein and Larson (1971) noted that the variables in this G-A infiltration

equation are all predictable. Bouwer (1966) assumed ψ to be the water entry value,

which was reported to be approximately half the air entry value. Philip (1957a)

considered ψ to be the height of capillary rise in the soil. Mein and Larson (1971)

noted that the variables in G-A infiltration equation have physical significance,

although determining ψ causes some difficulties.

2.2.3 Philip equation

Infiltration capacity depends on many factors such as soil type, its moisture content,

organic matter in it, vegetative cover and season. Of the soil characteristics affecting

infiltration, noncapillary porosity is perhaps the most important. Porosity determines

storage capacity and also affects resistance to flow. Thus, infiltration tends to

increase with porosity. For a homogeneous soil with a uniform initial moisture

content and ponded conditions at the surface, Philip (1957) developed a simple

formula for infiltration rate related to time:

22 AttSF += (2.3)

Page 32: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-5

where

F = Cumulative infiltration (mm)

t2 = Duration of infiltration (h)

S = Sorptivity of soil (mm/h1/2)

A = Constant (mm/h)

The monash rainfall-runoff model (Porter and McMahon, 1971) is based on the

Philip equation. Sharma and Seely (1979) used the Monte-Carlo Simulation method

to evaluate the effect of spatial variability of parameters S and A and they concluded

that an average infiltration curve based on average parameters would underpredict

rainfall excess. Maller and Sharma (1980) studied the effect of spatial variability of

the parameters S and A on ponding time using analytical methods. For log-normally

distributed parameters, the predicted ponding time was also found to have the log-

normal distribution. As the log-normal distribution is highly skewed and with a long

tailed there is a high probability that ponding of some areas of the catchment will

occur quite late. As a result, this will affect the catchment rainfall excess dependent

on location of such areas (Smith and Hebbert, 1979).

Unfortunately, computing the parameters of the Philip equation is difficult. Also the

parameter values are more commonly obtained by curve fitting (Mein and Larson,

1971). A further constraint is the assumption of ponded conditions at the surface,

thus an event with a high infiltration rate cannot be represented.

Nandakumar et al. (1994) noted that parameter values of the Philip equation are

related to the soil texture as they have physical meaning. They noted that several

varying interpretations of the parameter A values are found in Singh (1989), such as

the value of parameter A ranges from 1/3 sK to sK . The sK is the saturated hydraulic

conductivity.

2.2.4 Richards equation

Richards equation is a physically based mathematical model of flow in porous media.

It is derived by combining Darcy’s law and the continuity equation. This equation is

Page 33: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-6

used for the derivation of vertical unsaturated soil moisture flow. (e.g., Childs,

1969)

The one dimensional form of the Richards equation (e.g., Childs, 1969) is stated as

given below:

( ) ⎥⎦

⎤⎢⎣

⎡⎟⎠⎞

⎜⎝⎛ −∂∂

∂∂

=∂∂ 1

zk

ztψψθ (2.4)

where

=θ Volumetric water content

t = Time

z = Space coordinate in vertical direction

k = Hydraulic conductivity of soil

=ψ Total metric potential

Numerical solutions of Richards equation have been combined into many physically

based computer packages, which simulate individual hydrological processes. This

equation provides a commonly accepted basis for detailed studies of soil water

movement, but its solution is computationally complex. Similarly, simulating field

conditions for infiltration is highly complicated because of initial and boundary

conditions are not constant and soil characteristics vary with time and space.

Recently, more practical methods have been developed (Kool et al.,1985) which

have reduced computational limitations. A further development has been undertaken

by Campbell (1985) and Ross (1990a) on Richards equation. TOPOG is a

hydrological model developed by CSIRO Division of Water Resources (CSIRO,

1992). TOPOG is modeled by a mixed form of the Richards equation. The computer

package SWIM provides a numerical solution of the Richard’s equation for cases

involving infiltration, redistribution and evapotranspiration of soil water (Ross,

1990b). This equation is not suitable for general application as the numerical solution

is rather complex, and the required soil data are difficult to obtain (Mein and Larson,

1971).

Page 34: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-7

2.2.5 Applications of theoretical equations in flood estimation

The theoretical equations mentioned above are suitable for small catchments and

each theoretical equation has its own limitations. Horton’s equation is applicable for

shallow ponded conditions. In the Green-Ampt equation, assumption is made for

ponded conditions, a constant matric potential at the wetting front and uniform

moisture content which are hardly satisfied in the real situations. Philip’s equation is

based on homogeneous soil with a uniform initial moisture content and ponded

conditions at the surface. Again, these assumptions are hardly met in real conditions.

In Richards equation, input data (soil moisture characteristics) are not commonly

available and the solution methods are computationally demanding.

A pilot study was undertaken by the CRC for Catchment Hydrology on nine

catchments to evaluate if the application of a ‘theoretically correct’ loss model based

upon a point infiltration equation (Green-Ampt) provided superior results to the

simplified models at the catchment scale. Although the Green-Ampt equation was

able to be successfully applied to each catchment, the results were not on average

superior to those produced using the simplified lumped conceptual loss models (Hill

et al., 1998). Hence simplified lumped conceptual loss model was used in this

research work to estimate loss values.

2.3 Conceptual loss models 2.3.1 General

In hydrology, design flood estimation is a common problem. Estimates of design

flood can be made using frequency analysis of the streamflow data if adequate data is

available. Design floods are typically estimated from design storms either using the

Rational Method for peak flows or by using routing models in association with loss

models for flow hydrograph estimation. No physical process involved in runoff

generation is considered in the Rational Method for peak flow estimation. Design

peak runoff rate of a catchment is related to a storm of specified intensity using

runoff coefficients.

Page 35: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-8

A loss model is applied in rainfall routing models to convert gross rainfall to rainfall

excess. Rainfall excess is routed using an appropriate routing model to obtain the

flood hydrograph. Design flood hydrographs are needed where storage is significant

or where the duration of flooding is required. The purpose of design loss is to

achieve a flood with a given Annual Exceedance Probability (AEP) from a design

rainfall with the same AEP. Since actual losses vary from event to event, design loss

can be viewed as probabilistic or statistical estimates of the most likely value

(Nandakumar et al., 1994).

2.3.2 Spatially lumped loss models

The term “storm losses” include interception, depression storage and infiltration

losses, which have been conceptualised in simple forms. These types of

conceptualised models do not consider the spatial variability or the actual temporal

pattern of storm losses. Consideration of the model parameters are considered using

the total catchment response i.e. runoff. However, spatially lumped loss models are

widely used because of their simplicity and ability to approximate catchment runoff

behaviour.

Some of the most frequently used methods in ARR (I. E. Aust., 1998) for spatially

lumped losses include:

(i) Constant loss rate

(ii) Initial loss-continuing loss

(iii) Proportional loss rate

(iv) SCS curve number procedure.

2.3.3 Constant loss rate

Constant loss rate, where the rainfall excess is the residual left after a selected

constant rate of infiltration capacity is satisfied. In this method, a constant loss rate is

subtracted from the design storm as shown in Figure 2.1. ARR (I. E. Aust., 1998)

mentioned that for design case, use of constant loss rate would be more appropriate

for large storms from which significant runoff is likely to occur. Flavall and Belstead

Page 36: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-9

(1986) applied this model to an area in the Kimberly region of Western Australia

with large extents of bare rock and shallow sand cover and the constant loss rate

varied from 2.0 to 4.8mm/h for a range of average recurrence intervals (ARI). Flavall

and Belstead (1986) mentioned that they applied IL-CL loss model for most of the

catchments outside the south west region of Western Australia, but constant loss rate

was applied for the Kimberly region of Western Australia because of low losses and

high rates of runoff.

The constant loss rate is not suitable for storms which produce low rates of runoff.

Also the constant loss rate method does not allow initial loss during the rainfall

event. Hence in the constant loss rate method the matching of initial rise of the

observed hydrograph is difficult.

Nandakumar et al. (1994) noted that this model does not closely conceptualise the

actual infiltration process for many Australian catchments, it can be used in

catchments that produce high runoff from storms. In Queensland most of the

catchments showed high loss rates and can not produce high runoff from storms

unless the storm is very large. Hence the constant loss rate model is not suitable for

many of the Queensland catchments loss estimations.

Figure 2.1 Constant loss rate

halla
This figure is not available online. Please consult the hardcopy thesis available from the QUT Library
Page 37: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-10

2.3.4 Initial loss–Continuing loss (IL-CL) model

This model (Figure 2.2) has been widely used in Australia (I. E. Aust., 1998), due

both to its simplicity and to its generally better approximation of the temporal pattern

of storm losses than the constant loss rate approach. Initial loss is the loss that occurs

in the early part of the storm, prior to the commencement of surface runoff. Thus, it

can be considered to be composed of the interception loss, depression storage and

infiltration that occurs before the soil surface is saturated. Continuing loss is the

average rate of loss during the remaining period of the storm.

Cordery (1970a) found that initial loss (IL) is highly correlated with water content

present in the catchment prior to rainfall i.e. antecedent precipitation index (API),

and suggested that IL is an important factor in low rainfall areas, but can be

neglected in areas where mean annual rainfall is greater than 1270mm. Laurenson

and Pilgrim (1963) presented 150 continuing loss rate values for 24 catchments in

South Eastern Australia. The values varied markedly from catchment to catchment,

and were found to be significantly influenced by antecedent wetness and season. The

median values of continuing loss rate for the 24 catchments were between 0 to

5mm/h, with half of them equal to or less than 2.5mm/h.

Page 38: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-11

Figure 2.2 Initial loss-continuing loss (IL-CL)

Flavell and Belstead (1986) used the IL-CL model to obtain design losses for

catchments in Western Australia. They found that IL decreased with ARI in the

region where flooding tends to increase towards the end of winter as catchments

become wetter with the rarer events being associated with high antecedent wetness.

In the other regions, IL increased with ARI up to 10 years, and then decreased. A

minimum IL of 20mm was obtained with an ARI of 2 years for loamy soil areas, and

a maximum IL of 98mm was derived with ARI of 10 years for sandy soil catchments.

This indicates the broadness of the range of values of this parameter. For the same

data, CL varied from 3mm/h to 5mm/h.

Using the design rainfall given in ARR (I. E. Aust., 1987), Walsh et al. (1991)

estimated design IL values for 22 catchments in NSW. An average CL rate of 2.7

mm/h was used to obtain the IL for a range of ARIs. The derived IL values varied

from 15 to 50mm and were dependent on the degree of nonlinearity used in the flood

hydrograph model (RORB). The derived IL values also showed some degree of

dependency on design rainfall pattern.

halla
This figure is not available online. Please consult the hardcopy thesis available from the QUT Library
Page 39: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-12

Cordery and Pilgrim (1983) found no relationships between catchment characteristics

and median continuing loss rate. They concluded that the difficulty of obtaining

relationships between loss model parameters and catchment characteristics was due

to: (i) the probabilistic nature of the design losses, (ii) the inadequacy of the loss

models for conceptualising real catchment processes both, temporally and spatially.

2.3.5 Proportional loss rate (PLR) model

For this model, loss is assumed to be a fixed proportion of storm rainfall (Fig 2.3). In

Australia, the approach is generally used in conjunction with an initial loss for rural

catchments. The model performs well on catchments where runoff is generated from

particular areas of the catchment, not from all over the catchment. Since loss is

proportional to the rainfall after surface runoff has commenced, the surface runoff is

also proportional to the rainfall (I. E. Aust., 1998).

02

468

101214

1618

1 2 3 4 5 6 7 8 9

Time (hour)

Rai

nfal

l and

loss

(mm

)

Loss

Rainfall excess

Figure 2.3 Proportional loss rate

Harvey (1982) found the PLR model, with an initial loss model, performed well in

South Western Australia. Flavell and Belstead (1986) used the PLR model to derive

design losses in forested catchments in Western Australia. PLR was related to the

Page 40: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-13

steamlength, the percentage of forest cleared and the mean annual rainfall. The

relationship for a given ARI was given in the form:

PLR = k 10 a 1 c pa 2 La 3 (2.5)

where

k, a1 , a 2

and a3 are constants, depending on the type of forest and soil.

L = Steam length (km),

C = The percentage of forest cleared

P = Mean annual rainfall (mm)

The statistical significance level of a1 , a 2

and a3was derived and it was found that

most of the fitted regression equations were significant at 5.0% level or a lower level

for the catchments considered.

Dyer et al. (1994) compared the performance on the initial loss–proportional loss and

initial loss–continuing loss models on 24 catchments and found that the initial loss-

proportional loss gave a better result between observed and calculated hydrographs

using the RORB model.

Although proportional loss model closely simulates the source area concept, it has

not been recommended in ARR (I.E. Aust, 1998), except for some regions of

Western Australia. There is virtually no guidance in ARR (I.E. Aust, 1998), as to

suitable values of proportional losses for design. It can be concluded that this model

needs further investigation for application in other parts of Australia, especially in

forested catchments where source area runoff generation is dominant.

2.3.6 SCS curve number method

The U.S. Soil Conservation Services (SCS) curve number procedure is widely used

for estimating stream flow volumes for small to medium sized watersheds in the

United States (U.S. Soil Conservation Services, 1985). It was originally developed to

Page 41: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-14

estimate runoff volume and peak discharge for the design of soil conservation works

and flood control projects, but later extended to estimate the complete hydrograph.

The procedure, which is empirical, aims to provide a consistent basis for estimating

the amount of runoff under varying land use and soil types. The primary input

parameter is a runoff curve number (CN) defined in terms of soil type, antecedent

moisture conditions, land use treatment and hydrological condition of the catchment.

The accuracy of the method for simulating the runoff volume is largely determined

by the selection of the appropriate curve number, and accurate estimation of

watershed antecedent moisture conditions (Boughton, 1989).

The CN value is determined from the watershed characteristics, using tables

contained in U.S. Soil Conservation Service (1985) or other texts. From this, the

depth of runoff from a given rainfall is determined. The CN method has been

extended to calculate rates of runoff. For this, the peak discharge is estimated using a

triangular approximation to the hydrograph, corresponding to a uniform rainfall

excess. For a complex storm, rainfall excess over different time intervals may be

computed separately and the resulting triangular hydrographs superimposed to obtain

the peak discharge.

The SCS curve number procedure has been adapted for application to a wide range of

catchments, such as urban and semi-arid areas. It has also been incorporated in a

number of computer programs to estimate runoff hydrographs for rural and urban

catchments.

Titmarsh et al. (1989) carried out extensive testing of the SCS method using data

from 140 catchments in two regions of Eastern Australia. They also found that the

probabilistic CN values were fairly weakly related to catchment characteristics, such

as percentage of area of the catchment cultivated, but with a much smaller range of

values than indicated by the US SCS recommendations. The relationship between CN

values estimated from catchment characteristics by the US procedure, and the

probabilistic values derived from Australian data, was found to be very poor.

Page 42: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-15

2.4 Loss accounting in rainfall runoff models

2.4.1 Rainfall Runoff Routing using Burroughs (RORB)

The Rainfall Runoff Routing using Burroughs (RORB) model (Laurenson and Mein,

1997) provides for estimating the outflow hydrograph from a catchment by

modelling the drainage network as a series of conceptual nonlinear storages. It allows

for the subdivision of the catchment based on catchment divides and drainage lines.

Each division is independent of rainfall inputs, allowing for spatial and temporal

variation of rainfall. As outlined by Mein et al. (1974), nonlinear conceptual storages

are used to route the rainfall excess along the reaches of the drainage network to the

catchment outlet.

ARR (I. E. Aust., 1998) recommends the RORB model for estimating outflow

hydrographs and uses IL-CL loss model. The IL is taken from the results of the

calibration of the model i.e. a representative value (either mean or median) from the

available values. Alternatively, the IL values recommended in ARR (I. E. Aust.,

1998) are used. The problem in selecting an appropriate value of IL or CL is that the

observed or recommended values in ARR (I. E. Aust., 1998) cover a wide range and

it is not easy to select the most appropriate value for a particular application. The use

of arbitrary value of loss is a major source of uncertainty in flood estimation by

RORB and similar models.

2.4.2 Watershed Bounded Network Model (WBNM)

Watershed Bounded Network Model (WBNM) is an event based nonlinear runoff

routing model for calculating a flood hydrograph from a rainfall hyetograph (Boyd et

al., 2001). The model structure is based on the geomorphology of the catchment and

its stream network, and model nonlinearity and lag parameter values are based on

measured catchment lag times. WBNM permits the user to specify a design rainfall

spectrum by accepting a range of standard ARIs and durations for analysis in a

particular run. The model also includes the storm temporal patterns for all Australian

rainfall zones, for ARIs from 1 to 100 years and burst durations from 10 minutes to

Page 43: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-16

72 hours. Once the rainfall hyetograph at each gauge has been read in or constructed,

the model calculates the hyetograph for each subcatchment using the temporal

pattern of the nearest gauge, and an average intensity at the gauge calculated from

surrounding gauges weighted according to the inverse of the squared distance from

the subcatchment.

In relation to loss values, WBNM has an advantage over other loss models because it

can handle five alternative loss models as listed below:

(i) Initial loss-continuing loss rate

(ii) Initial loss-loss rate varying in steps

(iii) Initial loss-runoff proportion

(iv) Horton continually time varying loss rate

(v) Green-Ampt time varying loss, with recovery after period of low rainfall

Once a rainfall loss model is selected, WBNM calculates the excess rainfall

hyetograph for each subcatchment. WBNM is not based on probability distributed

loss values but on a single loss value similar to RORB, though WBNM can

accommodate different loss values for different areas.

2.4.3 Urban Runoff and Basin System (URBS)

The Urban Runoff and Basin System (URBS) runoff routing model is based on a

network of subcatchments whose centroidal inflows are routed along a prescribed

routing path to generate runoff (Carroll, 1994). The catchment variables used by

URBS are, stream length, catchment area, channel slope, catchment slope, fraction

urbanised, fraction forested and channel roughness. This model requires that the

stream length is specified to define the extent of catchment routing, and that

catchment area is specified to determine excess rainfall. All other variables are

optionally included in the modelling process at the discretion of the user. There are

two runoff routing models; the basic model (RORB based) and the split model. The

split model separates the channel and catchment routing processes.

The URBS model uses four types of loss models; the first three are simplistic models

whose parameters can vary for each sub-catchment whilst the fourth model is based

Page 44: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-17

on losses calculated by a suitable water balance model such as the AWBM model

(Boughton, 1993). The first three loss models are;

(i) Initial loss - continuing Loss model (IL/CL)

(ii) Proportional Loss model (IL/PL) and

(iii) Manly-Philips Loss model.

2.4.4 Australian Water Balance Model (AWBM)

Boughton and Carroll (1993) have combined the AWBM (Boughton, 1993) with the

URBS runoff routing model (Carroll, 1992). AWBM is a partial area saturation

overland flow model, which allows modelling in hourly/daily steps for spatially and

temporally variable source areas of surface runoff. The partial area concept is

modelled by adopting different soil storage capacities over a catchment area, with

computation based on a conceptual soil moisture accounting procedure.

As shown in Figure 2.4, this model uses three capacities which allow for different

source areas of surface runoff. Surface runoff occurs when one or more of the stores

are filled and overflow occurs. A fixed proportion of the surface runoff is diverted

for recharge of baseflow storage with baseflow discharge at time step t being

proportional to that at time step t-1. These three storages S1, S2, S3 and baseflow

recharge are considered as losses in flood estimation. The rainfall excess from partial

areas of the catchment calculated from the calibrated AWBM model is routed by the

URBS model to calculate the flood hydrograph. Nandakumar et al. (1994) illustrated

the AWBM model as follows:

Page 45: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-18

Surface runoff =(1-BFI)*Excess

Baseflow recharge =BFI*Excess

Baseflow = (1-K)*BS

S1S2

S3

Excess

Rainfall Evaporation

BS

Figure 2.4 Schematic diagram of AWBM model (after Boughton 1993)

2.4.5 Comments

The AWBM rainfall runoff model and other runoff routing models discussed here use

a representative (single not probability distributed) value of losses in design flood

estimation. Most of these models use ARR (I. E. Aust., 1998) recommended loss

values, which has a wide range and it is generally difficult to select a single

representative value that will preserve the AEP of input rainfall depth in the final

flood output. In this research the loss values were estimated using actual rainfall and

streamflow data. No runoff routing model was used, as the surface runoff hydrograph

was derived from the streamflow data.

2.5 Loss estimate for real-time flood forecasting

The procedures followed in real-time forecasting are similar to the procedures used

in the design storm method of flood estimation. In real-time forecasting, the actual

(or forecasted) rainfall hyetograph over the catchment is combined with a model of

losses to determine the rainfall excess for input to a runoff routing model. The

Page 46: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-19

estimation of hydrographs in real-time may include a feedback component for the

correction of forecasts according to the discrepancies observed in earlier forecasts.

There are different types of models that can be used in real-time flood forecasting,

such as linear runoff routing models, non-linear runoff routing models and

conceptual models. Conceptual models make use of explicit soil moisture accounting

through allocation of water into various stores. However their use is limited in

practice due to complexity and computational effort, along with the problem of

estimating values for the large number of parameters involved.

There are some simple techniques which can be used for updating in real-time, such

as adjustment of volumetric runoff coefficient (Simpson et al., 1980). Adjustment of

mean areal precipitation (Peck et al., 1980) has also been proposed as an updating

techniques for hydrological forecasts. Some models adopt techniques to optimise

model parameters in successive forecasting time steps. Recursive techniques, such as

application of the Kalman filter to non-linear conceptual catchment models for

parameter estimation and model forecast updating, have gained prominence in the

last decade (Nandakumar, et. al., 1994).

One of the most common indices of soil moisture condition of a catchment is the

Antecedent Precipitation Index (API). Antecedent Mean Daily Flow shows a good

index of initial soil moisture conditions in humid areas, where streamflow is

continuous and baseflow discharge is estimated at the beginning of the storm. Loy et.

al. (1996) investigated regional loss model relationships for catchments in south-east

Queensland. Three types of loss model relationships were examined for estimating

initial loss. Antecedent Precipitation Index (API) and Antecedent Mean Daily Flow

(AMDF) were found to be best in overall performance for initial loss estimates.

2.5.1 Loss models adopted in real-time flood forecasting

The most commonly adopted loss models in real-time flood forecasting are the initial

loss-continuing loss, initial loss-proportional loss rate models, constant loss rate,

antecedent precipitation index and point infiltration models (Nandakumar, et. al.,

1994).

Page 47: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-20

2.5.2 Initial loss-continuing loss and initial loss-proportional loss models

Spatially lumped loss models for initial loss, combined either with continuing loss or

proportional loss rate, have achieved wide adoption in real-time flood forecasting,

mainly due to the simplicity and ease of application. Rainfall runoff models such as

RORB (Crapper, 1989; Avery, 1989), URBS (Malone, 1999), AWBM (Srikanthan et

al., 1997) which incorporate the initial loss-continuing loss and initial loss-

proportional loss models are used to forecast runoff hydrographs in real time.

2.5.3 Constant loss rate

Chander and Shanker (1984) adopted a simple unitgraph procedure for real-time

flood forecasting with on-line estimation of the constant loss rate and rainfall excess.

The first estimate of constant loss rate is calculated to match the computed flow at

the end of the first time step with the observed flow. In each subsequent step, the

constant loss rate is updated to match calculated and observed hydrographs with the

current best estimate of constant loss rate at any time step being used in determining

rainfall excess for forecasting the next step. Corradini et al. (1986) developed a semi

distributed adaptive model for real-time flood forecasting, based on Clark’s (1945)

procedure, using calibrated parameters for the catchment.

2.5.4 Antecedent precipitation index (API)

In Australia, the Bureau of Meteorology uses the API concept, in which a correlated

relationship of initial loss against an antecedent precipitation index is used in flood

forecasting procedures (I. E. Aust., 1998). The loss models incorporated in the

Melbourne’s flood warning system include fitted regression relationship between

API and mean catchment loss rate for various rainfall durations (Gieseman, 1986). In

applications, the above loss models are applied to routing models such as unit

hydrographs, or non-linear runoff routing models to derive the forecasted

hydrographs.

Page 48: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-21

2.5.5 Point infiltration equations

The Clark routing procedure loss model has several applications in Australia in real-

time flood forecasting (Corradini and Melone, 1986). The effective rainfall was

based on a time varying point rainfall infiltration model, representing pre-ponding

and post-ponding stages through the model parameters of rainfall intensity, saturated

hydraulic conductivity (ks), and sorptivity parameter (S). For infiltration rates less

than soil infiltration capacity, a temporal redistribution of rainfall was used.

Variability of infiltration in space was incorporated through spatial variability in the

rainfall pattern and using spatially “equivalent” values of Ks and S. On-line

correction of flow forecast was then carried out by updating the S parameter and a

runoff scaling factor.

A number of more simpler soil moisture accounting conceptual models, with smaller

numbers of model parameters, have been proposed. In these models, infiltration is

modelled according to the Horton equation. Forecast updating, using an auto-

regressive moving average process (ARMA model) is a fairly common technique with

this type of model. Examples of these types of conceptual models (Marivoet and

Vandewiele, 1980; Tucci and Clarke, 1980).

2.5.6 Comments

Loss models adopted for real-time flood forecasting have usually been simple

lumped models, such as initial loss combined with continuing or proportional loss

rates, constant loss rate and API relationships. In most cases, temporal variation in

losses is not considered, but alternatively some other system such as changing the

values of the parameters is used to match the observed hydrograph. The more

“advanced” conceptual models, which have gained prominence in flood forecasting,

include loss models which are capable of modelling temporal variations. However

the difficulties in parameter optimisation and in updating have continued to limit

their use.

Page 49: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-22

2.6 Currently recommended design loss values in Australia

2.6.1 Past studies on losses

Design Event Approach, Joint probability Approach and Continuing Simulations are

the common flood estimation methods. These methods of flood estimation are

discussed in Chapter 3. A selected list of major studies in relation to storm losses

such as theoretical losses, conceptual losses and losses used in flood estimation

methods are summarised in Table 2.1 under following topics:

(i) Theoretical losses

(ii) Conceptual losses

(iv) Losses used in Design Event Approach

(v) Losses used in Joint Probability Approach and

(vi) Losses used in Continuous Simulation.

Page 50: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-23

Table 2.1 Summary of previous studies on losses

Types of losses/Modelling Nature of losses Researchers

Theoretical losses These mainly account for

infiltration of water into the

ground at a point.

Horton(1940), Green and Ampt (1911), Philip (1957), Richard (1931),

Bauer(1974), Akan (1992), Walsh and Pilgrim (1993), Mein and

Larson (1971), Chu (1978), Van Mullem (1991), Aston and Dunin.

(1979), Chapman (1968), Sharma and Seely (1979), Maller and

Sharma (1980), Kool et al.(1985), Campbell (1985), Ross (1990a,b).

Conceptual losses These are probabilistic in nature

and have the ability to

approximate catchment runoff

behaviours.

Flavell and Belstead (1986), Laurenson and Pilgrim (1963), I. E. Aust.

(1987), Walsh et al. (1991), Cordery and Pilgrim (1983), Harvey

(1982), Dyer et al. (1994), Linsley et al. (1982), Cordery (1970a),

NERC, (1975), Kumar and Jain (1982), U.S. Soil Conservation

Service, (1985).Clark (1980), Moore(1985).

Design Event Approach

The design Event Approach

considers the probabilistic nature

of rainfall depth but ignores the

probabilistic behaviour of other

inputs/parameters including

losses. This method uses a

representative value (either mean

or median) from a large number

of observed values.

ARR (I.E. Aust., 1958, 1977, 1987,1998), Beran (1973), Ahern and

Weinmann (1982), Walsh et al. (1991), Hill and Mein (1996), Overney

et al. (1995) Russel et al. (1979), Viessman et al. (1989).

Page 51: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-24

Table 2.1 Summary of previous studies on losses continued

Joint Probability

Approach

Considers outcomes of events of all

possible combination of input values and,

if necessary, their correlation structure, to

estimate design floods. This method uses

probabilistic losses in flood estimation.

ARR (I.E. Aust., 1987), Ahern and Weinmann.(1982), Beran and

Sutcliffe (1972), Eagleson (1972), Hughes (1977), Goyen (1983),

Laurenson (1974), Rahman et al. (2000, 2001a, b). Haan (1977), Haan

and Schulze (1987), Weinmann et al. (1998).

Continuous

Simulation

These Models aim to represent the major

processes responsible for converting the

catchment rainfall inputs into flood

outputs. This method estimates losses

from a continuous water balance.

Bras et al.(1985), Bradley and potter (1992), Porter and McMahon

(1971), Crawford and Linsley (1966), Chapman (1968), Boughton and

Carroll (1993), Linsley and Crawford (1974), James and Robinson

(1986), Hubber et al. (1986), Linsley et al. (1988), Rahman et al.

(1998), Russell (1977), Lumb and James (1976), Ahern and

Weinmann (1982), Boughton,W.C (2001), James and Robinson

(1982).

Page 52: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-25

2.6.2 Losses recommended in ARR (I. E. Aust., 1998)

The recommended design values in ARR (I. E. Aust., 1998) for Queensland, NSW

and Victoria are shown in Table 2.2.

There is virtually no information on the initial loss–proportional loss model and the

recommended value of initial loss varies over a large range. It is important to note

that for a large portion of Victoria (North and West of Great Dividing Range), the

only recommendation for design loss is that it is “probably as for similar areas of

NSW”. It is found in many studies that the use of design losses with the design

rainfall recommendation in ARR (I. E. Aust., 1987) result in the overestimation of

design peak flows, when compared with a frequency analysis of recorded peak flows

(Hill and Mein, 1996; and Walsh et al., 1991). This indicates that, for many

catchments, the design losses recommended in ARR (I. E. Aust., 1987; I. E. Aust.,

1998) are too low.

There are two inadequacies in the current ARR (I. E. Aust., 1998) loss values, which

were derived from the analysis of large flood events. These are, the selection of high

runoff events for loss derivation is biased towards wet antecedent conditions (i.e.

losses tend to be too low) and storm losses do not account for the nature of design

rainfall information of ARR (I. E. Aust., 1998), which has been derived from rainfall

bursts within longer duration storms (i.e. losses tend to be too high). It is recognised

in ARR (I. E. Aust., 1998) that these two adequacies should have opposite effects.

However it is implicitly assumed by users of the current design loss values that they

fully compensate each other.

Waugh (1991) examined the effect of the first inadequacy. From a study of five

Western Australian catchments, he concluded that the selection of runoff events for

the estimation of design loss underestimates the design loss value, and can result in

over-estimation of the design flood magnitude by up to 20%. This is because many

sizable summer storms yielded little or no runoff, due to dry antecedent conditions,

and were not included in the analysis. Srikanthan and Kennedy (1991) examined the

effect of the second inadequacy. They examined the degree to which the rainfall

burst used to generate design temporal patterns was embedded within longer duration

Page 53: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-26

storms, and found that, for a given annual exceedance probability (AEP), antecedent

rainfall prior to storm bursts decreased with increasing storm duration. This is

because, as the duration of the bursts increases, more bursts represent complete

storms.

Table 2.2 Currently recommended Design Losses in ARR (I. E. Aust., 1998)

halla
This figure is not available online. Please consult the hardcopy thesis available from the QUT Library
Page 54: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-27

The critical duration of design rainfall for a catchment is that duration which gives

the largest design peak flow. It depends on catchment characteristics and on the

variation of the rainfall magnitude and temporal pattern with duration. It would be

reasonable to expect that the critical duration would increase with catchment size, as

the surface runoff will take longer duration to reach the outlet of the catchment but a

number of studies have found the critical duration does not depend on catchment

area. For example, in a study of 22 NSW catchments (ranging in areas from 25 to

6,560 km 2 ), Walsh et al. (1991) found that the critical duration was independent of

catchment size. Some investigators (Walsh et al., 1991; Hill and Mein, 1996) have

noted that, when the recommended design losses in ARR (I. E. Aust., 1987) are

applied to the design rainfall, the resulting critical duration is excessively long.

Hill and Mein (1996) mentioned the excessively long critical durations, when

applying the ARR (I. E. Aust., 1987) recommended loss values to 8 Victorian

catchments with catchment areas ranging from 32 to 153 km2. For all but one

catchment in temporal pattern Zone 1, the 36 hour temporal pattern was critical. In

addition, the 72 hour temporal pattern was found to be critical for one catchment in

Zone 2, which has a catchment area of only 60 km2. Hill and Mein (1996) also noted

that the excessively long critical durations are caused by:

(i) Temporal patterns which include sub-intervals with excessively heavy

rainfall, and which are not consistent with the estimated average recurrence

interval (ARI) of the complete pattern. This sub-interval with excessively

heavy rainfall can be alleviated by fully filtering the temporal patterns to

ensure that no sub-interval has an ARI which is greater than the ARI of the

complete storm.

(ii) Another reason which causes the excessively long critical duration is the use

of the same design value of initial loss for all durations. In order to be

consistent with the derivation of design rainfalls in ARR (I. E. Aust., 1987),

the design initial loss should increase with increasing duration.

Page 55: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-28

(iii) The time increment used in ARR (I. E. Aust., 1987) for the longer duration

temporal patterns is too long, and for the smaller catchments, it approaches

the response time of the catchment.

2.7 Summary

The point infiltration equations discussed in Section 2.2 of this chapter are suitable

for small catchments and each theoretical equation has its own limitations. It can be

stated that, theoretically based point infiltration models should be considered to

determine the infiltration capacity of different types of soil and soil topography.

Larger catchments tend to be heterogeneous and as a result do not have the same

infiltration capacity throughout the catchments. Hence, these approaches are not

particularly appropriate for design flood estimation for larger catchments. The IL-CL

loss model has been widely used in Australia (I. E. Aust., 1998), due both to its

simplicity and to its generally better approximation of the temporal pattern of storm

losses than the constant loss rate approach.

The AWBM rainfall runoff model and other runoff routing models discussed here use

a representative value of losses in design flood estimation. The design loss values

which were used in these models were usually from ARR (I.E. Aust., 1998)

recommended loss values, which have wide ranges and it is generally difficult to

select a value that will preserve the AEP of input rainfall depth in the final flood

output.

Loss models adopted for real-time flood forecasting are usually simple lumped loss

models. In these models the temporal variation of losses are not considered. There

are some advanced conceptual loss models for flood forecasting, which are capable

of modeling temporal variation but there is limitation in their use because of the

difficulties in parameter optimization and in updating.

The existing two inadequacies in ARR (I. E. Aust., 1998) loss values were derived

from analysis of large flood events. These are, the selection of high runoff events for

loss derivation is biased towards wet antecedent conditions (i.e. losses tend to be too

Page 56: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

2-29

low) and storm losses do not account for the nature of design rainfall information of

ARR (I. E. Aust., 1998), which has been derived from rainfall bursts within longer

duration storms (i.e. losses tend to be too high).

These inadequacies result in over estimation of design floods. Ultimately the

overestimation of design floods lead to the construction of over design and expensive

hydraulic structures. It is therefore important to estimate suitable design losses which

would ultimately save millions of dollars in construction of hydraulic structures.

Hence it is necessary to develop a new loss function to estimate floods. A suitable

flood estimation method among the existing methods should be selected to examine

the effect of losses in flood estimation. A detailed discussion is performed about the

selection of flood estimation method in the next chapter.

Page 57: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 3-1

CHAPTER 3

FLOOD ESTIMATING METHODS

3.1 General

Design flood estimation methods can be broadly classified into two groups: rainfall

based methods and streamflow based methods. Rainfall based methods can be

subdivided into event based methods and continuous simulation. Design Event

Approach is an example of event based methods. The currently recommended

method for design flood estimation in ARR (I. E. Aust., 1998) is based on Design

Event Approach in that a hypothetical design storm is defined as an input to a runoff

routing model. In recent years, significant developments have been made in the

application of more advanced techniques in flood estimation e.g. Joint Probability

Approach (Rahman et al., 2001a, b) and Continuous Simulation (Boughton, 2001).

This chapter describes about all three types of flood estimation methods.

3.2 Design Event Approach

ARR (I. E. 1998), Ahern and Weinmann (1982), Beran (1973) described the steps

involved with the Design Event Approach. The estimation of design flood of a

specified annual exceedance probability (AEP) by Design Event Approach can be

described in the following steps:

i. Select a number of design storm durations D1, D2, …and for each of these,

obtain a streamflow hydrograph following the steps given below.

ii. Obtain an average rainfall depth from the intensity-frequency-duration (IFD)

curve, given the design location, specified AEP and duration.

iii. Distribute the total rainfall within the duration to form the gross rainfall

hyetograph.

iv. Select loss parameters and compute rainfall excess hyetograph.

v. Formulate catchment response model.

Page 58: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 3-2

vi. Select catchment response parameters.

vii. Select design baseflow.

viii. Compute stream flow hydrograph.

ix. The rainfall duration giving maximum peak flood is taken as critical duration,

and the corresponding peak is taken as the design flood of the specified AEP.

The key assumption involved in this approach is that the representative design values

of the inputs/ parameters (such as duration, temporal pattern, loss shown in Figure

3.1) at different steps can be defined in such a way that they are ”AEP neutral” i.e.

they result in a flood output that has the same AEP as the rainfall input. The success

of this approach is crucially dependent on how well this assumption is satisfied.

There are no definite guidelines on how to select the appropriate values of the

inputs/parameters in the above steps that are likely to convert a rainfall depth of

particular AEP to the design flood of the same AEP. There are many methods to

determine an input value. Likewise, other inputs to the design such as critical storm

duration, spatial and temporal distributions of the design storm, and baseflow values

can also be determined by many methods, the choice of which is totally dependant on

various assumptions and preferences of the individual designer. As an example, a

designer may follow any of the many possible combinations of the inputs (as shown

in the Figure 3.1). The critical storm duration is an important factor in converting

rainfall input to a flood output of design AEP. Critical storm duration depends on

storm factors, loss factors, catchment characteristics. Selection of inappropriate

values for any of these factors will result in different critical durations and assuming

that the resulting flood has the same AEP as the input rainfall depth is not correct.

Due to non-linearity of the transformation in the rainfall-runoff process, it is

generally not possible to know a priori how a representative value for an input should

be selected to preserve the AEP (Rahman et al., 1998).

In summary, the current Design Event Approach considers the probabilistic nature of

rainfall depth but ignores the probabilistic behaviour of other inputs/parameters such

as rainfall duration, losses and temporal pattern. The assumption regarding the

probability of the flood output i.e. a particular AEP rainfall depth will produce a

flood of the same AEP is unreasonable in many cases. The arbitrary treatment of the

various flood producing variables, as done in the current Design Event Approach, is

Page 59: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 3-3

likely to lead to inconsistencies and significant bias in flood estimates for a given

AEP.

Figure 3.1 Schematic diagram of the Design Event Approach

Duration

Temporal pattern

Spatial pattern

Loss

Catchment response model and parameters

Baseflow Design flood AEP = ?

AEP = 1 in Y

D2 D4D3

T1 T2 T3

S1 S2 S3

L1 L2 L3

P1

B1 B2 B3

D1 D5 Total rainfall depth

T4 T5

S4 S5

L4 L5 Rainfall excess hyetograph

P2 P3

Surface hydrograph

F

Page 60: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 3-4

3.3 Joint Probability Approach

The Joint Probability Approach recognises that any design flood characteristics (e.g.

peak flow) could result from a variety of combinations of flood producing factors,

rather than from a single combination, as in the Design Event Approach (Eagleson,

1972, Beran, 1973, Laurenson, 1974, Russell et al., 1979). For example, the same

peak flood could result from a small storm on a saturated basin or a large storm on a

dry basin. Thus it is clear that the Joint Probability Approach, which considers the

outcomes of events with all possible combinations of input, values and if necessary

their correlation structure is most likely to lead to better estimates of design flows

(Rahman et al., 1998, Weinmann et al., 1998). The flood output, consequently, will

also have a probability distribution instead of a single value.

By using the same component models as the current Design Event Approach but

treating inputs and parameter values to the design as random variables, the Joint

Probability Approach obviously attempts to eliminate subjective criteria in

specifying input values.

Joint Probability Approach is theoretically superior to the Design Event Approach

and regarded as an attractive design method (I.E. Aust., 1998). The Joint Probability

Approach is based on the Theorem of Total Probability that can be expressed in three

dimensions by the following equation:

)(),|()( ,111

xkixki

t

x

m

k

n

iDCBPDCBAPAP ∩∩= ∑∑∑

===

(3.1)

In applying the Theorem of Total Probability to the calculation of flood probability,

the explanations of the terms involved in Equation (3.1) are as follows:

• P (A) is the unconditional probability of a flood (to be exceeded in any given

year);

• B, C, D are random variables to the design, for example temporal pattern, losses

and storm duration.

Page 61: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 3-5

The method of combining probability distributed inputs to form a probability

distributed output is known as the derived distribution approach. A derived

probability distribution can be solved in two ways:

1) Analytical methods

2) Approximate methods

It depends upon the analytical skills of the designer and the computer resources

available to select a method to compute derived probability distribution. In the

analytical methods the probability distribution of the dependent variable is found by

directly applying principles of probability. The cumulative density function of the

dependent variable should be determined. The analytical methods have been found to

be difficult to apply under practical situations mainly due to the mathematical

complexity involved and difficulties in parameter estimation.

In approximate methods a solution is obtained by substituting numerical values for

variables and parameters. For example, Rahman et al. (2001a, b) developed a Monte

Carlo simulation technique (a type of approximate method), as illustrated in Figure

3.2, to solve Equation (3.1). This technique is easy to apply and has been found to

provide more precise flood estimates than the Design Event Approach. The

approximate methods can be applied relatively easily. These methods are applied

when an analytical approach to the problem becomes difficult or impossible.

In recent applications of Joint Probability Approach, Rahman et al. (2001a, b) have

used initial loss-continuing loss model without investigating the appropriateness of

other loss functions. Also, they assumed continuing loss to be a constant throughout

the storm duration. This could be a tenuous assumption for long duration storms.

Also they ignored the random variability of continuing loss from storm to storm.

The steps involved in the Monte Carlo Simulation technique illustrated in Figure 3.2

are as follows:

• Draw a random value of duration from the rainfall duration (D).

Page 62: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 3-6

• Given the random value of duration, draw a random value of rainfall intensity

from the conditional distribution of rainfall intensity (I).

• Given the random value of duration draw a random temporal pattern from the

conditional distribution of temporal pattern (TP).

• Given the random value of duration draw a random value of initial loss from

the conditional distribution of initial loss (IL).

• Run the randomly selected variables through the runoff generation and runoff

routing models to simulate a flood hydrograph.

• Add the baseflow to the simulated flood hydrograph and note the flood peak,

repeat the above steps in the order of thousands.

• Use the simulated flood peaks to determine the derived flood frequency curve

in a distribution free manner using rank-order statistics.

Page 63: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 3-7

Rainfall events

Identify component distributions

Rainfall duration(D )

Rainfall intensity (I )

Rainfall temporal pattern (TP )

Losses(IL )

D I TP IL

Rainfall excesshyetograph

Route through runoff routing model

Runoff model calibration (m, k )

Baseflow analysis

Peak of simulatedstreamflow hydrograph

Construct derived flood frequency curve

Repeat in theorder of thousands

Figure 3.2 Schematic diagram of the Joint Probability Approach (Monte Carlo

simulation technique, probability-distributed components shaded)

Page 64: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 3-8

3.4 Continuous Simulation Continuous Simulation is the alternative to the Design Event Approach using

deterministic catchment models or rainfall-runoff process models (I.E. Aust., 1998).

Examples of this approach can be found in Crawford and Linsley (1966); Linsley and

Crawford (1974); Huber et al. (1986) and Linsley et al. (1988).

Continuous Simulation models aim to represent the major processes responsible for

converting the catchment rainfall inputs into flood outputs. They generate outflow

hydrographs over a long period of time from inputs of historical rainfall series,

potential evaporation and other climatological data. Time steps used in these models

are usually from one hour to one day, sometimes may be as short as 5 or 15 minutes,

and the simulation period is often up to hundreds of years. It is difficult to use the

continuous modelling for design flood estimation in rural catchments because of the

complexity involved in calibration of the model.

ARR (I.E. Aust., 1998) states that: “although Continuous Simulation models provide

probably the best means of estimating runoff sequences from rainfall, considerable

care and expertise are required to obtain useful results”.

The main problems with the Continuous simulation arise from the difficulties in

adequately modeling the soil moisture balance, synthesising long records of rainfall

and evaporation at the appropriate temporal and spatial resolution, and accounting

for correlations between inputs. There are also some other difficulties associated with

Continuous Simulation as described by Lumb and James (1976), Ahern and

Weinmann (1982), James and Robinson (1982), Institution of Engineers (1998):

• Loss of sharp events by the use of relatively long time steps.

• Time and effort are required in gathering the precipitation and other

climatologic data needed for simulation of a long continuous sequence

(Extensive data requirements).

• Management of large amount of time series output (data management).

Page 65: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 3-9

• Expertise is required to determine parameter values which best reproduce

historical hydrographs (model calibration effort).

3.5 Selection of flood estimation method

The main problems with the Continuous Simulation arise from the difficulties in

adequately modeling the soil moisture balance, synthesising long records of rainfall

and evaporation at the appropriate temporal and spatial resolution, and accounting

for correlations between inputs. Hence Design Event Approach and Joint Probability

Approach were used in this research for flood estimation and flood frequency

analysis.

3.6 Summary

The currently recommended method for design flood estimation in ARR (I. E. Aust.,

1998) is based on Design Event Approach in that a hypothetical design storm is

defined as an input to a runoff routing model. The key assumption involved in this

approach is that the representative design values of the inputs/ parameters (such as

duration, temporal pattern, loss shown in Figure 3.1) at different steps can be defined

in such a way that they are ”AEP neutral” i.e. they result in a flood output that has

the same AEP as the rainfall input. The success of this approach is crucially

dependent on how well this assumption is satisfied.

In recent years, significant developments have been made in the application of more

advanced techniques in flood estimation e.g. Joint Probability Approach (Rahman et

al., 2001a, b) and Continuous Simulation (Boughton, 2001). Thus it is clear that the

Joint Probability Approach, which considers the outcomes of events with all possible

combinations of input, values and if necessary their correlation structure is most

likely to lead to better estimates of design flows. Joint probability Approach is

theoretically superior to the Design Event Approach and regarded as an attractive

design method (I. E. Aust., 1998).

Page 66: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 3-10

Although the continuous modelling approach is conceptually sounder than event

based approaches, it is difficult to use the continuous modelling for design flood

estimation in rural catchments because of the complexity involved in calibration of

the model. The main problems with the Continuous Simulation arise from the

difficulties in adequately modeling the soil moisture balance, synthesising long

records of rainfall and evaporatioin at the appropriate temporal and spatial resolution,

and accounting for correlations between inputs. Hence Design Event Approach and

Joint Probability Approach were used in this research as the flood estimation

methods.

To estimate the design flood of a catchment using the Design Event Approach and

Joint Probability Approach some catchments are needed to be selected, which are

discussed in the next Chapter.

Page 67: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 4-1

CHAPTER 4

STUDY CATCHMENTS 4.1 General For the proposed study, selection of study catchments was an important step. This

chapter describes the process of how study catchments were selected. Firstly, the

criteria to select the study catchments are discussed. Then mapping catchment

boundaries and all selected stations are described. Then the discussions on selected

catchments are presented.

4.2 Criteria to select study catchments

This study was aimed at deriving new improved design losses for Queensland

catchments. Initially from the whole of Queensland gauging stations, 78 catchments

were selected from a book (DNRM, 2000) published by the Department of Natural

Resources and Mines. This initial selection was performed depending upon the

catchment area, regulation and record length of the catchment. But there were some

other important criteria which were to be considered to finalise the catchment

selection. These were the location of the pluviograph station, daily rainfall station,

streamflow station and the catchment boundary. All of these criteria are discussed in

this Chapter.

4.2.1 Catchment area

It was important to know whether the catchment is small or large in size. The loss

(IL-CL) model which was used in this research is only suitable for small to medium

size catchments, and not suitable to compute the loss values for the larger

catchments. The reason is that the process of computing loss values for larger

catchments is different from the process of computing loss values for smaller

catchments as described in section 6.7. The definition of initial loss (IL) computation

adopted in this research section 6.3 does not satisfy large catchments, hence the

proposed study was based on small to medium sized catchments. Australian Rainfall

Page 68: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 4-2

and Runoff (ARR) (I. E. Aust, 1998) suggests the catchment area with an upper limit

of 1000 km2 can be considered as a small to medium sized catchments, which was

taken as a guide to selecting the study catchments.

4.2.2 Regulation

To select the study catchments consideration was given to whether the study

catchments were regulated or unregulated. As major regulation affects the rainfall

runoff relationship significantly, gauging stations subject to major regulation (such as

dams, back water effect etc) were not included in this research. Also urbanisation

affects the catchment hydrology, so no urban catchment was selected. Only

unregulated rural catchments were selected for this research work.

4.2.3 Record length

The record length of the rainfall and streamflow data should be long so that more the

number of rainfall and streamflow events can be selected for the analysis of any

catchment. The highest record length of streamflow data is 48 years and the mean

and median value of streamflow record length are 30 and 31 years. Some streamflow

data with record lengths up to 11 years were also selected. Hence the recorded lower

limit of streamflow data was 11 years for this analysis. In this study, if the stream

gauging record length for any catchment is less than 11 years, the catchment was not

selected as a candidate catchment.

Considering the above criteria, a total of 48 catchments were selected from all over

the Queensland. Streamflow data were obtained from the Department of Natural

Resources and Mines (DNRM) Queensland. Topographic Maps of Australia

(1:100000) were consulted to investigate the nature of streamflow network and

nature of regulation in the selected catchments. Also the gauging authority was

consulted to know about any recent changes of regulation and land use in the

selected catchments. A total of 132 pluviograph stations and 338 daily rainfall

stations were selected from and near the selected catchments. The rainfall data were

obtained from the Bureau of Meteorology (BoM), Australia. The streamflow and

Page 69: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 4-3

rainfall data graded as ‘good quality’ by the data authorities were accepted and poor

quality data were not included in the study.

4.2.4 Catchment boundary

All the 78 catchment boundaries were collected from the Department of Natural

Resources and Mines in electronic forms. Mapinfo professional version 5.0 (mapping

software) was used to select the catchment boundary for the study catchment.

After mapping the catchment boundary, an electronic layer of stream gauging

stations were laid over the catchment boundary. The catchments whose location of

the stream gauging station in the map was found away from the catchment boundary,

that catchment was not selected as study catchment. Catchments were selected, when

there was one or more pluviograph station or daily rainfall stations within the

catchment boundary. To select a rainfall streamflow event to estimate loss values the

temporal pattern of the rainfall over the catchment is to be obtained. Catchments with

only one pluviograph station but no daily rainfall station within the catchment

boundary were selected as candidate catchments. As the catchments were small to

medium in size, it was assumed that the temporal pattern of the pluviograph data

were the representative temporal pattern of the whole catchment, provided the

pluviograph station was located well inside the catchment boundary. But catchments

with no pluviograph station inside or within 50 km of the catchment boundary were

not selected as study catchments, though there was daily rainfall station within or

near the catchment boundary. Again catchments having a pluviograph station close

to the boundary and with daily rainfall stations within the catchment boundary, were

selected as study catchments. Because, it was assumed that when the pluviograph

station and daily rainfall station are closely located, the temporal pattern of the daily

rainfall station and the pluviograph station were same. Hence the pluviograph data

can be used to proportion the daily rainfall data to obtain the representative temporal

pattern of rainfall within the catchment.

Page 70: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 4-4

4.3 Mapping catchment boundaries and the selected pluviograph,

daily rainfall and streamflow stations

Finally a total of 48 study catchments were selected out of 78 catchments. A

mapping computer software known as Mapinfo professional version 5.0 (Mapinfo,

1998) was used in this study to select the representative pluviograph stations and the

daily rainfall stations. In Mapinfo for each of catchments, the selected catchment

boundaries, pluviograph stations and the daily rainfall stations were laid in electronic

layers one above another. Pluviograph stations and the daily rainfall stations which

were representative of the respective catchments were selected from this electronic

diagram. A single catchment boundary and its stream gauging station with all its

pluviograph and daily rainfall stations are shown in Figure 4.1 as an example. The

Figure 4.1 also shows that all the three pluviograph stations are inside the catchment

boundary and a number of daily rainfall stations are also located inside the catchment

boundary.

Page 71: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 4-5

Figure 4.1 Example of the Major Creek catchment with a stream gauging station

119006A, pluviograph and daily rainfall stations

The symbols used in Figure 4.1 are illustrated below:

● Stream gauging station (119006A)

■ Pluviograph station

□ Daily rainfall station

33,166

33,171

33,173

119006A

33,074 33,151

33,159 33,171

33,173

33,226

33,166

33,171

33,173

119006A

33,074 33,151

33,159 33,171

33,173

33,226

33,166

33,171

33,173

119006A

33,074 33,151

33,159 33,171

33,173

33,226

33,166

33,171

33,173

119006A

33,074 33,151

33,159 33,171

33,173

33,226

Page 72: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 4-6

Each catchment had only one stream gauging station. Within the catchment boundary

there could be more than one pluviograph and daily rainfall stations. The gauging

station which has shown in Figure 4.1 is 119006A.

119 - Basin number

0 - Sub-basin number

06 - Station number

A - Site location code

4.4 Selected catchments

Of the selected 48 study catchments which were selected from the whole of

Queensland, most of these catchments were selected from the coastal areas because

of their long streamflow record. There were only a few catchments in western

Queensland having a reasonably long streamflow record. The selected catchments

were mainly unregulated and rural and have reasonably long rainfall and streamflow

records. In Queensland there are 5 drainage divisions and there are many basins in

each drainage division. The distribution of the drainage divisions and basins are

shown in Figure 4.2.

Page 73: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 4-7

Figure 4.2 Distribution of the drainage divisions and the basins in Queensland

Page 74: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 4-8

The distribution of the candidate catchments selected from all over the Queensland is shown

in Figure 4.3. The locations of the study catchments were identified by the electronic layer of

catchment boundaries with in the Queensland boundary using Mapinfo professional version

5.0.

Figure 4.3 Locations of the 48 study catchments in Queensland

Each study catchment is represented by a stream gauging station. A list of selected stream

gauging stations numbers, streamflow names, location of stream gauging stations, latitude and

longitude of stream gauging stations, catchment area and streamflow record length (start and

finish date) is shown in Table 4.1.

Page 75: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 4-9

Table 4.1 Stream gauge station number, their location , catchment area and streamflow record length of the study catchments Serial

Number Basin ID Streamflow name Location of stream

gauging station Lat. of stream

gauge Long. of

stream gaugeCatchment area (km2)

Start date of streamflow

Finish date of streamflow

1 102101A Pascoe River Fall Creek 12.87 142.97 635 1/10/1967 Continue 2 104001A Stewart River Telegraph Road 14.17 143.38 480 18/01/1970 " 3 105105A E. Normanby River Development Road 15.77 145.00 300 24/02/1969 " 4 107001B Endeavour River Flaggy 15.42 145.05 310 1/10/1967 " 5 107003A Anna River Beesbike 15.68 145.20 247 9/03/1990 " 6 112003A N. Johnston River Glen Allyn 17.37 145.65 173 1/10/1958 " 7 112101B S. Johnston River Upstream Central Meal 17.60 145.97 400 1/10/1974 " 8 114001A Murray River Upper Murray 18.10 145.80 155 26/05/1970 " 9 116008B Gowrie Creek Abergowrie 18.43 145.83 124 1/10/1953 "

10 116015A Blunder Creek Wooroora 17.73 145.43 127 20/10/1966 " 11 116017A Stone River Running Creek 18.77 145.95 157 30/06/1970 " 12 118003A Bohle River Hervey Range Road 19.32 146.70 143 1/04/1985 " 13 119006A Major Creek Damsite 19.67 147.02 468 4/05/1978 " 14 120014A Broughton River Oak Meadows 20.17 146.32 182 5/11/1970 13/04/1999 15 120216A Broken River Old Racecourse 21.18 148.43 78 1/06/1969 " 16 124002A St. Helens Creek Calen 20.90 148.75 129 7/02/1973 " 17 125005A Blacks Creek Whitefords 21.32 148.82 505 12/12/1973 " 18 130207A Sande Creek Clermont 22.78 147.57 409 21/01/1965 " 19 136108A Monal Creek Upper Monal 24.60 151.10 92 15/07/1962 " 20 137101A Gregory River Burrum Highway 25.08 152.23 454 10/02/1966 " 21 138110A Mary River Bellbird Creek 26.62 152.70 486 1/10/1959 " 22 141009A N. Maroochy River Eumundi 26.48 152.95 38 15/02/1982 " 23 143110A Bremer River Adams Bridge 27.82 152.50 125 30/09/1968 " 24 143212A Tenhill Creek Tenhill 27.55 152.38 447 18/03/1968 " 25 145003B Logan River Forest Home 28.20 152.77 175 1/10/1953 "

Page 76: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 4-10

Serial Number Basin ID Streamflow name

Location of stream gauging station

Lat. of stream gauge

Long. of stream gauge

Catchment area (km2)

Start date of streamflow

Finish date of streamflow

26 145010A Running Creek 5.8km Deickmans

Bridge 28.23 152.88 128 26/11/1965 " 27 145011A Teviot Brook Croftby 28.13 152.57 83 7/02/1966 " 28 146014A Back Creek Beechmont 28.12 153.18 7 5/06/1971 " 29 145101D Albert River Lumeah Number 2 28.05 153.03 169 1/10/1953 " 30 416410A Macintyre Brook Barongarook 28.43 151.45 465 15/06/1967 " 31 422321B Spring Creek Killarney 28.35 152.32 35 1/10/1972 " 32 422338A Canal Creek Leyburn 28.02 151.58 395 27/03/1972 " 33 422394A Cadamine River Elbow Vally 28.37 152.13 325 2/12/1972 " 34 913005A Paroo Creek Damsite 20.33 139.52 305 20/11/1968 1/10/1988 35 913009A Gorge Creek Flinders Highway 20.68 139.63 248 13/11/1970 Continue 36 915205A Malbon River Black Gorge 21.05 140.06 425 1/10/1970 1/10/1988 37 916002A Norman River Strathpark 19.53 143.25 285 1/10/1969 30/09/1988 38 916003A Moonlight Creek Alehvale 18.27 142.33 127 1/10/1969 10/04/1989 39 917005A Agate Creek Cave Creek Junction 18.93 143.47 228 1/07/1969 30/09/1988 40 917007A Percy River Ortana 19.15 143.48 445 2/09/1969 30/09/1988 41 917107A Elizabeth Creek Mount Surprise 18.13 144.30 585 23/07/1968 Continue 42 917114A Routh Creek Beef Road 18.28 143.70 81 11/12/1972 30/09/1988 43 919201A Palmer River Goldfields 16.10 144.77 530 11/12/1967 Continue 44 919205A North Palmer River 4.8 km 16.00 144.28 430 16/10/1973 30/09/1988 45 921001A Holroyd River Ebagoola 14.23 143.15 365 19/01/1970 17/05/1988 46 922101B Coen River Racecourse 13.95 143.17 166 10/11/1967 Continue 47 926002A Dulhunty River Dougs Pad 11.83 142.42 325 18/11/1970 " 48 926003A Bertie Creek Swordgrass Swamp 11.82 142.50 130 10/11/1972 "

Table 4.1 (Continued)

Page 77: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 4-11

The distribution of the selected catchment area is shown in Figure 4.4. The areas of

the catchment were ranging from 7 km2 – 645km2. The median and mean of the

catchment areas were respectively 248 km2 and 273 km2. Only 8.0% of the

catchments were greater than 500 km2 and 15.0% were smaller than 100 km2.

Figure 4.4 Distribution of catchment areas of the study catchments in Queensland.

4.5 Summary

Initially 78 catchments were selected on the basis of catchment size, regulation and

streamflow record length. But after plotting all these catchment boundaries,

pluviograph, rainfall and stream gauging stations in electronic forms in Mapinfo

professional version 5.0, only 48 catchments were selected for loss computation and

eventually to estimate the design flood.

592.0528.0

464.0400.0

336.0272.0

208.0144.0

80.016.0

Freq

uenc

y

12

10

8

6

4

2

0

592.0528.0

464.0400.0

336.0272.0

208.0144.0

80.016.0

Freq

uenc

y

12

10

8

6

4

2

0

592.0528.0

464.0400.0

336.0272.0

208.0144.0

80.016.0

Freq

uenc

y

12

10

8

6

4

2

0

592.0528.0

464.0400.0

336.0272.0

208.0144.0

80.016.0

Freq

uenc

y

12

10

8

6

4

2

0

592.0528.0

464.0400.0

336.0272.0

208.0144.0

80.016.0

Freq

uenc

y

12

10

8

6

4

2

0

592.0528.0

464.0400.0

336.0272.0

208.0144.0

80.016.0

Freq

uenc

y

12

10

8

6

4

2

0

592.0528.0

464.0400.0

336.0272.0

208.0144.0

80.016.0

Freq

uenc

y

12

10

8

6

4

2

0

592.0528.0

464.0400.0

336.0272.0

208.0144.0

80.016.0

Freq

uenc

y

12

10

8

6

4

2

0

Catchment area (km2)

Page 78: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 4-12

To select a rainfall streamflow event the temporal pattern of the rainfall over the

catchment is required. To estimate loss values the selection of rainfall streamflow

event was required. Catchments with only one pluviograph station but no daily

rainfall station within the catchment boundary were selected as candidate

catchments. As the catchments were small to medium in size, it was assumed that the

temporal pattern of the pluviograph data was the temporal pattern of the whole

catchment, provided the pluviograph station was located well inside the catchment

boundary.

Most of these catchments were selected from coastal areas because there were only a

few catchments in western Queensland having a reasonably long streamflow record.

The selected catchments were mainly unregulated, rural and with reasonably long

rainfall and streamflow records. Once the catchments were selected it was important

to compile and analyse the data to compute losses for design flood estimation. So

data compilation and analysis is discussed in the next chapter.

Page 79: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 5-1

CHAPTER 5

DATA ANALYSIS 5.1 General

All the streamflow data for this research were collected from the Department of

Natural Resources and Mines (DNRM, 2000) for this research. Pluviograph data and

daily rainfall data were collected from the Bureau of Meteorology (BOM). Only

good data were used in this research, as the quality and error of the data were

checked by the respective authority before the data was collected. This chapter

describes the collation and formatting of streamflow, pluviograph and daily rainfall

data. It also describes how to estimate the catchment average rainfall and finally how

to select the rainfall streamflow events.

Generally it is found that the srteamflow hydrograph tend to be high peaked when

there is little or no delay between the commencement of rainfall excess and the start

of rise of the streamflow hydrograph. Again the hydrograph tend to be broad crested

when a considerable delay will occur between the beginning of rainfall excess and

the start of surface runoff at the catchment.

5.2 List of stream gauge, pluviograph and daily rainfall stations

The list of the selected stream gauge stations, their location, streamflow record

lengths, selected pluviograph stations and daily rainfall stations is provided in Table

5.1. The Basin ID is the unique identifier of stream gauging stations used by the

Queensland Department of Natural resources and Mines (DNRM) for Queensland

catchments. Table 5.1 shows that for each catchment only one stream gauge station

was selected but 5 pluviograph stations and 5 daily rainfall stations were selected.

Table 5.1 shows the data range of all the selected 48 stream gauging stations. The

pluviograph and daily rainfall stations were selected on the basis of their locations

and the record length of data as shown in Figure 5.1.

Page 80: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

5-2

Table 5.1 List of the selected stream gauge, pluviograph and daily rainfall stations

SL BASIN ID NAME LOCATION LA.. LOG.AREA(Km2) ST. DATE FIN. DATE PluSta 1 PluSta 2 PluSta 3 Plusta 4 plusta 5 DaRaSta 1 DaRaSta2 DaRaSta3 DaRaSta4 DaRaSta5

1 102101A Pascoe River Fall Creek 12.87 142.97 635 1/10/1967 Continue 27006 27045 27042 27022 _ 27024 28008 28001 27064 27014

2 104001A Stewart River Telegraph Road 14.17 143.38 480 18/01/1970 " 27006 27045 27042 31017 _ 27005 27028 28017 27006 _

3 105105A East Normanby River Development Road 15.77 145.00 300 24/02/1969 " 31016 31017 31055 28004 _ 31112 31074 31009 31106 31003

4 107001B Endeavour River Flaggy 15.42 145.05 310 1/10/1967 " 31017 31016 28004 31055 _ 31129 31107 31030 31017 31137

5 107003A Anna River Beesbike 15.68 145.20 247 9/03/1990 " 31016 31017 31055 28004 _ 31112 31074 31007 31003 31106

6 112003A North Johnston River Glen Allyn 17.37 145.65 173 1/10/1958 " 31034 31053 32061 32021 31046 31038 31153 31050 31149 31163

7 112101B South Johnston River Upstream Central Meal 17.60 145.97 400 1/10/1974 " 32061 31053 31083 32021 32076 32161 32138 31186 31128

8 114001A Murray River Upper Murray 18.10 145.80 155 26/05/1970 " 32004 32042 31083 32052 32018 32109 32035 32144 32060 32006

9 116008B Gowrie Creek Abergowrie 18.43 145.83 124 1/10/1953 " 32052 32004 32086 32043 32042 32123 32153 32147 32050 32170

10 116015A Blunder Creek Wooroora 17.73 145.43 127 20/10/1966 " 31083 31053 31046 32018 32042 31078 31085 31142 31083 31018

11 116017A Stone River Running Creek 18.77 145.95 157 30/06/1970 " 32043 32064 32078 32086 32052 32039 32011 32186 32129 32043

12 118003A Bohle River Hervey Range Road 19.32 146.70 143 1/04/1985 " 32040 33171 33173 33166 32064 32134 32116 32127 32065 32120

13 119006A Major Creek Damsite 19.67 147.02 468 4/05/1978 " 33171 33173 33166 32040 33002 33171 33151 33159 33226 33173

14 120014A Broughton River Oak Meadows 20.17 146.32 182 5/11/1970 13/04/1999 34036 34002 34084 _ _ 34056 34037 34040 34036 34002

15 120216A Broken River Old Racecourse 21.18 148.43 78 1/06/1969 " 33172 33099 33191 33152 33021 33172 33197 33182 33108 33183

16 124002A St. Helens Creek Calen 20.90 148.75 129 7/02/1973 " 33191 33152 33172 33099 33021 33080 33191 33010 33109 33102

17 125005A Blacks Creek Whitefords 21.32 148.82 505 12/12/1973 " 33090 33172 33152 33191 33145 33090 33178 33182 33301 33172

18 130207A Sande Creek Clermont 22.78 147.57 409 21/01/1965 " 35010 35104 36047 35147 35098 35252 35011 35171 35158 35183

19 136108A Monal Creek Upper Monal 24.60 151.10 92 15/07/1962 " 39148 39104 39330 39089 39334 39129 39202 39119 39175 39292

20 137101A Gregory River Burrum Highway 25.08 152.23 454 10/02/1966 " 40624 39303 39128 40126 40451 39027 39159 39207 40624 39188

21 138110A Mary River Bellbird Creek 26.62 152.70 486 1/10/1959 " 40106 40386 40102 40062 40139 40051 40698 40018 40298 40118

22 141009A North Maroochy River Eumundi 26.48 152.95 38 15/02/1982 " 40059 40386 40106 40282 40496 40078 40059 40561 40053 40257

23 143110A Bremer River Adams Bridge 27.82 152.50 125 30/09/1968 " 40135 40004 40677 40082 41018 40400 40183 40675 40392 40447 Basin ID – Unique identifier of stream gauging stations used by Queensland Department of Natural resources and Mines (NRM) for Queensland catchments

Page 81: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

5-3

Table 5.1 List of the selected stream gauge, pluviograph and daily rainfall stations (continued)

SL BASIN ID NAME LOCATION LA.. LOG.AREA(Km2) ST. DATE FIN. DATE PluSta 1 PluSta 2 PluSta 3 Plusta 4 plusta 5 DaRaSta 1 DaRaSta2 DaRaSta3 DaRaSta4 DaRaSta5

24 143212A Tenhill Creek Tenhill 27.55 152.38 447 18/03/1968 " 40082 40270 40135 41018 40004 40570 40716 40114 40079 40835

25 145003B Logan River Forest Home 28.20 152.77 175 1/10/1953 " 40677 40676 40135 41056 40192 40597 40394 40832 40619 40012

26 145010A Running Creek 5.8km Deickmans Bridge 28.23 152.88 128 26/11/1965 " 40192 40676 40757 40677 40606 40363 40006 40653 40116 40362

27 145011A Teviot Brook Croftby 28.13 152.57 83 7/02/1966 " 40677 40135 41056 40676 41044 40490 40485 40030 40876 40267

28 145101D Albert River Lumeah Number 2 28.05 153.03 169 1/10/1953 " 40676 40192 40750 40197 40606 40413 40044 40866 40407 40182

29 146014A Back Creek Beechmont 28.12 153.18 7 5/06/1971 " 40192 40750 40606 40584 40197 40742 40015 40162 40173 40882

30 416410A Macintyre Brook Barongarook 28.43 151.45 465 15/06/1967 " 41457 41175 41060 41465 41413 41377 41014 41034 41447

31 422321B Spring Creek Killarney 28.35 152.32 35 1/10/1972 " 41056 41465 41044 40677 40135 41085 41134 41208 41165 41093

32 422338A Canal Creek Leyburn 28.02 151.58 395 27/03/1972 " 41060 41063 41457 41018 41044 41084 41118 41344 41315 41104

33 422394A Cadamine River Elbow Vally 28.37 152.13 325 2/12/1972 " 41056 41465 41044 40677 40135 41056 41463 41381 41186 41233

34 913005A Paroo Creek Damsite 20.33 139.52 305 20/11/1968 1/10/1988 29127 29130 29009 37010 29090 29109 29107 29118 29064 29128

35 913009A Gorge Creek Flinders Highway 20.68 139.63 248 13/11/1970 Continue 29127 29130 29009 37010 29090 29126 29130 29125 29127 29128

36 915205A Malbon River Black Gorge 21.05 140.06 425 1/10/1970 1/10/1988 29130 29127 29009 29090 37010 29133 29138 29161 29119 37110

37 916002A Norman River Strathpark 19.53 143.25 285 1/10/1969 30/09/1988 30122 30121 30082 30112 _ 30150 30019 30060 30056 30086

38 916003A Moonlight Creek Alehvale 18.27 142.33 127 1/10/1969 10/04/1989 29102 29101 29103 _ _ 29102 29103 29101 29096 29012

39 917005A Agate Creek Cave Creek Junction 18.93 143.47 228 1/07/1969 30/09/1988 30121 30122 30112 30082 30126 30122 30121 30104 30086 30060

40 917007A Percy River Ortana 19.15 143.48 445 2/09/1969 30/09/1988 30122 30121 30112 30082 30126 30104 30086 30060 30114 30019

41 917107A Elizabeth Creek Mount Surprise 18.13 144.30 585 23/07/1968 Continue 30036 30126 32018 31046 30120 30116 30154 30036 30126 31128

42 917114A Routh Creek Beef Road 18.28 143.70 81 11/12/1972 30/09/1988 30120 30036 30126 30112 _ 30111 30018 30103 30110 30013

43 919201A Palmer River Goldfields 16.10 144.77 530 11/12/1967 Continue 31055 28004 31016 31017 _ 28013 31114 31009 31110 31019

44 919205A North Palmer River 4.8 km 16.00 144.28 430 16/10/1973 30/09/1988 28004 31017 31016 31055 _ 28002 28021 28013 31110 31009

45 921001A Holroyd River Ebagoola 14.23 143.15 365 19/01/1970 17/05/1988 27006 28004 27045 27042 31017 27028 27005 28017 28014 27032

46 922101B Coen River Racecourse 13.95 143.17 166 10/11/1967 Continue 27006 27029 27042 _ _ 27005 27006 28017 27028 27049

47 926002A Dulhunty River Dougs Pad 11.83 142.42 325 18/11/1970 " 27042 27045 27022 _ _ 27050 27013 27030 27012 27015

48 926003A Bertie Creek Swordgrass Swamp 11.82 142.50 130 10/11/1972 " 27042 27045 27022 _ _ 27050 27013 27030 27012 27015

Page 82: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

5-4

To compute the weighting average rainfall easily this list was prepared. Because in

many investigations it was found that more than one pluviograph station or daily

rainfall station jointly represent the catchment average rainfall. Sometimes it was

found that there are only 3 or 4 pluviograph stations which are within or near the

candidate catchments, in that case only 3 or 4 pluviograph stations are illustrated in

this list instead of 5 pluviograph stations.

5.3 Streamflow data

In each of the selected study catchments, there was a stream gauging station at the

catchment outlet. A total of 48 stream gauging stations were selected for this

research work. The distribution of streamflow records for the selected 48 stream

gauging stations is shown in Figure 5.1. It also shows that the standard deviation and

the mean value of the stream flow data were 8.82 and 29.5 years respectively.

Record length of stream gauge (Year)

50.045.040.035.030.025.020.015.010.0

Freq

uenc

y

16

14

12

10

8

6

4

2

0

Std. Dev = 8.82 Mean = 29.5

N = 48.00

Figure 5.1 Histogram showing the distribution of streamflow record lengths

Page 83: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

5-5

A cumulative plot illustrating the number of stream gauging station and their stream

flow record length is shown in Figure 5.2. The horizontal line with in the cumulative

plot indicates the median value. The range of stream flow data varies from 11 years

to 48 years. In Figure 5.2 it is shown that the median value of the stream flow data

was 31 years.

All the range of streamflow data were put together and their data range at 10.0%,

25.0% and 90.0% are described. The following statistics were observed from the

streamflow data range.

• 10.0% of the range of streamflow stations has record length more than 39

years.

• 25.0% of the range of streamflow stations has record length more than 34

years.

• 90.0% of the range of streamflow stations has record length more than 17

years.

0

10

20

30

40

50

60

1 5 9 13 17 21 25 29 33 37 41 45

No of stream gauge stations

Stre

am g

auge

reco

rd le

ngth

(Yea

rs)

Median Value

Figure 5.2 Cumulative plot showing the range and median value of

streamflow data record lengths

Page 84: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

5-6

5.4 Pluviograph data

A total of 132 pluviograph stations were selected depending upon the location and

record length of data from the whole of Queensland. All these 132 pluviograph

stations were within or near the selected catchment boundaries. The procedure which

was adopted to select the representative pluviograph station of the selected

catchments is described below.

An electronic layer of 132 pluviograph stations was laid on an electronic layer of

selected Queensland catchment boundaries. This process was performed by MapInfo

(1998) GIS software. After selecting the representative pluviograph station for each

catchment it was found that a total of 82 pluviograph stations were needed to be used

in this research project. The distribution of these 82 pluviograph data record lengths

is shown in Figure 5.3 in the form of a histogram. Figure 5.3 shows the standard

deviation and the mean value of the pluviograph data were 11 and 19 years

respectively.

Page 85: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

5-7

Record length of pluviograph data (Year)

45.042.5

40.037.5

35.032.5

30.027.5

25.022.5

20.017.5

15.012.5

10.07.5

5.0

Freq

uenc

y

12

10

8

6

4

2

0

Std. Dev = 10.91 Mean = 19.3

N = 82.00

Figure 5.3 Histogram showing the distribution of pluviograph record lengths

A cumulative plot illustrating the number of pluviograph station and the pluviograph

data record length is shown in Figure 5.4. The range of the pluviograph data record

length varies from 4 years to 46 years. The horizontal line within the cumulative plot

of Figure 5.4 shows the median value of pluviograph data, which was 18 years.

All the range of pluviograph data were put together and their data range at 10.0%,

25.0% and 90.0% are described below:

• 10.0% of the range of pluviograph stations has record length more than 33

years.

• 50.0% of the range of pluviograph stations has record length more than 18

years.

• 90.0% of the range of pluviograph stations has record length more than 5

years.

Page 86: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

5-8

05

101520253035404550

1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81

No of pluviograph stations

Plu

viog

raph

reco

rd le

ngth

(Yea

rs)

Median value

Figure 5.4 Cumulative plot showing the range and median value of the

pluviograph data record lengths

5.5 Daily rainfall data

A total of 338 daily rainfall stations were selected depending upon the location and

record length of data from the whole of Queensland. An electronic layer of 338 daily

rainfall stations was laid on electronic layers of selected Queensland catchment

boundaries and selected pluviograph stations. This process was executed using

MapInfo professional version 5.0, GIS software. A total of 24 daily rainfall stations

were selected for this analysis. The daily rainfall stations data were needed to be

disintegrated by the temporal pattern of the nearest pluviograph station. The

distribution of the selected 24 daily rainfall data record lengths is shown in Figure

5.5 in the form of a histogram. All these selected 24 daily rainfall stations were

selected from within or near the 48 unregulated rural catchment boundaries. Figure

5.5 also shows that the standard deviation and the mean value of the daily rainfall

data were 28 and 41 years respectively.

Page 87: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

5-9

Record length of daily rainfall data (Year)

110.0100.0

90.080.0

70.060.0

50.040.0

30.020.0

10.0

Freq

uenc

y

7

6

5

4

3

2

1

0

Std. Dev = 28.30

Mean = 41.2

N = 24.00

Figure 5.5 Histogram showing the distribution of daily rainfall record lengths

A cumulative plot illustrating the number of daily rainfall stations and their daily

rainfall data record length is shown in Figure 5.6. The range of the daily rainfall data

record lengths varies from 7 years to 112 years. In Figure 5.6 it is shown that the

median value of the daily rainfall data was 30.5 years.

All the range of daily rainfall data were put together and their data range at 10.0%,

25.0% and 90.0% are described below:

• 10.0% of the range of daily rainfall stations has record length more than 82

years.

• 50.0% of the range of daily rainfall stations has record length more than 30

years.

• 90.0% of the range of daily rainfall stations has record length more than 9

years.

Page 88: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

5-10

0

20

40

60

80

100

120

1 2 3 4 5 6 7 8 9 101112131415161718192021222324

No of daily rainfall stations

Dai

ly ra

infa

ll re

cord

leng

th (Y

ears

)

Median value

Figure 5.6 Cumulative plot showing the range and the median value of daily

rainfall record lengths

5.6 Formatting stream flow, rainfall and pluviograph data

The stream flow data which was obtained from the Department of Natural Resources

and Mines (DNRM) had to be formatted for use in this research project. Special

purpose programs (FORTRAN PowerStation 4.0) were developed in this research to

format and analyse the voluminous streamflow and rainfall data efficiently and

rapidly and to provide the results in the required format. The stream flow data was

supplied in two stages, both the sets of streamflow data were formatted using two

specially developed computer programs for this study. Both the computer programs

SFFOR1 and SFFOR2 are illustrated in Appendix A and Appendix B.

The pluviograph data obtained from the Bureau of Meteorology (BOM) was

processed using the software called Hydsys Version 8.0 (Hydsys, 2002). The daily

rainfall data obtained from the Bureau of Meteorology and was needed to format this

data to use in this research project. The daily rainfall data was formatted using a

specially developed computer program (FORTRAN PowerStation 4.0)

RAINDATA3 illustrated in Appendix C. The daily rainfall data was used in places

where there was no pluviograph data which was representative to the catchment

Page 89: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

5-11

rainfall. The catchment weighting average rainfall (CWAR) was estimated for

catchments with more than one pluviograph or daily rainfall stations as was

discussed in section 5.7.

5.7 Process to estimate the weighting average rainfall of a catchment

for more than one pluviograph and daily rainfall stations

A computationally simpler approximation to the conventional procedure of Thiessen

polygons was used in this research. Depending on the size of the catchment, grids

ranging from 40×40 to 80×80 over the catchment, were used to divide the

catchments into small square elements. Example of the grid lines is shown in Figure

5.7. Each element located within the catchment boundary was assigned to the nearest

pluviograph or daily rainfall station. Only the stations having data for the particular

time period for which weighting factors are sought were considered. Weighting

factors were calculated by taking the proportion of elements assigned to each station.

Given the uncertainty about the true areal variation of rainfall over the catchment, the

errors associated with this approximation were considered negligible (Siriwardena,

L., & Weinmann, P. E., 1996).

Page 90: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

5-12

Figure 5.7 Example of the grids ranging from 40×40 to 80×80 depending on the

catchment size

S1 = Stream gauging station

D1 = Daily rainfall station site1

P1 = Pluviograph station site 1

The Figure 5.7 shows the example of a catchment with more than one pluviograph

and daily rainfall stations. For this type of catchments weighting average rainfall for

the catchment was estimated. To compute the weighting average rainfall, the daily

rainfall data was disintegrated by the temporal pattern of the nearest pluviograph data

1 1 2 3

4 5 6

7 8 9

* s1

*P2 1

*D1

1 2 3

*D2

4 5 6

* P1

7 8 9

* s1 *D3

Page 91: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation

5-13

as it was assumed that the temporal patterns of the daily rainfall data would be

similar to the temporal pattern of the nearest pluviograph data. The data of daily

rainfall stations D1 and D2 were disintegrated using temporal pattern of pluviograph

station P2, as P2 and is closer to D1 and D2 than any other pluviograph station.

Similarly the daily rainfall data of D3 was disintegrated using the temporal pattern of

pluviograph station P1, as P1 and is closer to D3 than any other pluviograph station as

shown in Figure 5.7.

As it is mentioned earlier that each small element located within the catchment

boundary was assigned to the nearest pluviograph or daily rainfall station. Figure 5.7

illustrated that, the small square elements of area 4, area 7, area 8 and most of the

small elements of area 5 were assigned to pluviograph station P1. Small elements of a

rea 1 and most of the small elements of area 2 were assigned to daily rainfall station

D1. Similarly the small square elements of area 6 and area 9 were assigned to daily

rainfall station D2 and the small square element of area 3 was assigned to pluviograph

station P2. CWAR was expressed in the form of equation 5.1:

CWAR = P1 * 0.50 + D1 * 0.25 + D2 * 0.125 + P2 * 0.125 (5.1)

Where

CWAR = Catchment weighting average rainfall

Page 92: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 5-14

5.8 Selection of rainfall and streamflow events

The streamflow, pluviograph and daily rainfall data for any specific catchment were

made concurrent to select the rainfall and streamflow events. The ARR (I. E. Aust.,

1998) losses are based on larger flood events as mentioned in Section 2.6.2. That is,

many heavy rainfall events that did not produce significant runoff due to higher

losses were not considered. This resulted in smaller recommended loss values. In

contrast, Hill et al. (1996a, b) and Rahman et al. (2001a) considered rainfall events

that have higher relative intensities irrespective of associated runoff in the

computation of losses. This approach is more logical and results in more appropriate

design loss values and was adopted in this study. In the approach of Rahman et al.

(2001a) partial series ‘complete storm’ events that have the potential to produce

significant runoff were selected. Figure 5.8 shows an example of a rainfall event

where the ‘complete storm’ is between the start of storm and end of gross storm.

A complete storm was defined by Rahman et al. (2001a) as follows:

• Step 1: A ‘gross’ storm is a period of rain starting and ending by a non-dry hour

(i.e. hourly rainfall > C1 mm/h), preceded and followed by at least six dry hours

(Figure 5.8), where C1 mm/h is a rainfall intensity.

• Step 2: ‘Insignificant rainfall’ periods at the beginning or at the end of a gross

storm, if any, are then cut off from the storm, the remaining part of the gross

storm being called the ‘net’ storm. [A period is defined as ‘having insignificant

rainfall’ if all individual hourly rainfalls ≤ C2 (mm/h), and average rainfall

intensity during the dry period ≤ C1 (mm/h)], where C2 mm/h is a rainfall

intensity.

• Step 3: The net storms, from now on simply referred to as complete storms, are

then evaluated in terms of their potential to produce significant storm runoff. This

is performed by assessing their rainfall magnitudes, i.e. by comparing their

average intensities with threshold intensities. A net storm is only selected for

further analysis if the average rainfall intensity during the entire storm duration

Page 93: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 5-15

(RFID) or during a sub-storm duration (RFId), satisfies one of the following two

conditions:

RFI F ID D≥ ×1 2

RFI F Id dmax ≥ ×2 2

where

2ID = 2 year ARI intensity for the selected storm duration D

2Id = Corresponding intensity for the sub-storm duration d

F1 = Areal reduction factors

F2 = Areal reduction factors

The values of 2ID and 2Id were estimated from the design rainfall data in ARR (I. E.

Aust., 1998). In the above event definition, the use of appropriate areal reduction

factors F1 and F2 allows the selection of only those events that have the potential to

produce significant storm runoff. The use of smaller values of F1 and F2 captures a

relatively larger number of events; appropriate values need to be selected such that

events of very small average intensity are not included. In ARR (I. E. Aust., 1998)

the areal reduction factor is typically 0.9 for this range of catchment sizes and storm

durations. But the recommendation of areal reduction factor value in ARR (I. E.

Aust., 1998) was estimated from the investigation performed for United States

catchments not for Australian catchments. In this study, the following parameters

which are the areal reduction factors and hourly rainfall values were considered same

like Rahman et al. (2000). Rahman et al. (2001b) used these parameter values F1 =

0.4, F2 = 0.5, C1 = 0.25 (mm/h), and C2 = 1.2 (mm/h) for flood frequency analysis of

Victorian catchments. This typically resulted in 3 to 6 rainfall events, on average,

being selected per year for a catchment.

Page 94: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 5-16

Figure 5.8 Rainfall events: complete storms and storm-cores

5.9 Summary

A total of 48 streamflow gauging stations were selected. A total of 82 pluviograph

stations and 24 daily rainfall stations were selected within and near the catchment

boundaries on the basis of location and record length of data range. The range of

stream flow data was 11 to 48 years. The pluviograph data range was from 4 to 48

years and similarly the daily rainfall data range was from 7 to 112 years.

The stream flow data was collected from the Department of Natural Resources and

Mines in two different stages and the data sets were compiled in two different

formats. Both the stream flow data sets were formatted using two different computer

programs SFFOR1 and SFFOR2 enclosed in Appendix A and Appendix B. Similarly

the pluviograph data received from the Bureau of Meteorology were extracted using

Hydsys version 8.0. The daily rainfall data supplied from Bureau of Meteorology

were formatted using computer program RAINDATA3 enclosed in Appendix C.

01234

56789

10

1 5 9 13 17 21 25 29 33 37 41 45

Time (h)

Rai

nfal

l int

ensi

ty (m

m/h

) Start of storm

Storm-core

End of net storm

End of gross storm

01234

56789

10

1 5 9 13 17 21 25 29 33 37 41 45

Time (h)

Rai

nfal

l int

ensi

ty (m

m/h

) Start of storm

Storm-core

End of net storm

End of gross storm

01234

56789

10

1 5 9 13 17 21 25 29 33 37 41 45

Time (h)

Rai

nfal

l int

ensi

ty (m

m/h

) Start of storm

Storm-core

End of net storm

End of gross storm

01234

56789

10

1 5 9 13 17 21 25 29 33 37 41 45

Time (h)

Rai

nfal

l int

ensi

ty (m

m/h

) Start of storm

Storm-core

End of net storm

End of gross storm

Complete storm

Page 95: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 5-17

The pluviograph data and the disintegrated daily rainfall data were not only used but

also the weighting average rainfall was used to obtain the representative rainfall of

the catchment. The streamflow, pluviograph and daily rainfall data were made

concurrent before selecting the rainfall streamflow event and were investigated as to

how streamflow varies with the variation of rainfall.

Page 96: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 6-1

CHAPTER 6

METHODOLOGY FOR LOSS COMPUTATION

6.1. General

Losses during rainfall events can be represented in several ways. There are

mathematical equations to estimate losses, however, in practice, losses are frequently

represented by conceptual models. These types of conceptualised models do not

consider the spatial variability or the actual temporal pattern of storm losses.

Consideration of the model parameters is obtained using the total catchment response

i.e. runoff. These, spatially lumped loss models are widely used because of their

simplicity and ability to approximate catchment runoff behaviour. Some of the most

frequently used methods for spatially lumped losses include (i) constant loss rate, (ii)

initial loss-continuing loss, (iii) proportional loss rate, (iv) antecedent precipitation

index and (v) SCS curve number procedure.

Initial loss and continuing loss are two parameters simplified from the loss concept to

represent the average situation of a storm over the catchment with time. This method

is widely used in Australian practice and hence adopted in this study. This Chapter

describes how loss values were computed in this research. It also describes how loss

values vary with the catchment size.

The initial loss value was computed for all the selected rainfall steamflow events. It

was observed that less than 1.0% of total selected events based on initial loss were

more than 200 mm. Similarly, it was observed that less than 1.5% of the total

selected events based on continuing loss were more than 20 mm/h. Hence a upper

limit of initial loss 200 mm and continuing loss 20 mm/h was imposed in this

research.

Page 97: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 6-2

6.2 Runoff generation mechanism

There are two types of runoff generating mechanisms reported in literature (I. E.

Aust., 1998). Runoff being produced by infiltration excess i.e. when the rainfall

intensity exceeds the infiltration capacity, the rainfall excess which occurs at the

ground surface produce storm runoff. The other runoff generating mechanisms is

runoff being produced by saturated overland flow i.e. when the surface horizon of the

part of a catchment becomes saturated as a result of either the build-up of a saturated

zone above a soil horizon of lower hydraulic conductivity, or due to the rise of a

shallow water table to the surface causing saturated overland flow. Further rain on

the saturated soil then converts 100% surface runoff whereas little or no runoff may

occur on areas where the surface is not saturated.

There is another type of runoff known as throughflow. The storm runoff that occurs

due to water that infiltrates into the soil and percolates rapidly, largely through macro

pores such as cracks, root holes, worm holes and animal holes, and then moves

laterally in a temporarily saturated zone above a layer of low hydraulic conductivity

is known as throughflow. It reaches the stream channel relatively quickly and differs

from other subsurface flow by the rapidity of its response and possibly by its

relatively large magnitude.

Use of a large storm from which runoff is likely to occur from the whole catchment

would be the most appropriate design case. Therefore the concept of runoff produced

by infiltration excess was adopted in this study.

6.3 Method of Initial loss computation

The rainfall which occurs prior to the commencement of surface runoff was

considered to be as initial loss (IL) is shown in Figure 6.1. The same procedure was

adopted in this research to compute the initial loss i.e. amount of rainfall saturated

the catchment before the surface runoff. The estimation of initial loss from observed

storms was a somewhat arbitrary and subjective procedure, mainly due to difficulties

in the determination of the beginning and end time of initial loss. In general, most

Page 98: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 6-3

hydrographs are characterised by an initial rise with a very mild gradient followed by

a steep rising limb. The end time for initial loss computation was considered as the

start of the steep rising limb, as shown in Figure 6.1.

Figure 6.1 Initial loss – Continuing loss (IL-CL) model

In computing initial loss, a surface runoff threshold value equal to 0.01 mm/h was

used, similar to Hill et al. (1996a). It was considered that surface runoff commences

when the surface runoff threshold was exceeded. The initial loss occurs in the

beginning of the storm, prior to the commencement of the surface runoff. Figure 6.1

shows the example of an initial loss-continuing loss (IL-CL) model. As IL-CL model

computes the loss values from rainfall and streamflow data. This model can not

identify the start of surface runoff of a catchment for any rainfall event. The hourly

streamflow data was observed and compared with the surface runoff threshold value

in volume. When the difference of streamflow volume exceeds the surface runoff

threshold value volume of rainfall, then the rainfall that occurred before the rise of

streamflow in a rainfall event was considered as the initial loss. Figure 6.1 shows a

12 hours rainfall event, out of this rainfall event the first 5 hours were considered as

initial loss as there was no rise of streamflow occurred.

02468

1012141618

1 2 3 4 5 6 7 8 9 10 11 12

Rainfall duration (h)

IL (m

m) a

nd C

L (m

m/h

)/ st

ream

flow

(m3/

s)

IL

Streamflowhydrograph

02468

1012141618

1 2 3 4 5 6 7 8 9 10 11 12

Rainfall duration (h)

IL (m

m) a

nd C

L (m

m/h

)/ st

ream

flow

(m3/

s)

IL

Streamflowhydrograph

CL

Page 99: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 6-4

Surface runoff threshold values equal to 0.02 mm/h and 0.005 mm/h was also used

for all the selected rainfall events in this research to compute the variation of loss

values with different threshold values. The results of the loss variations due to the

change of threshold values are discussed in chapter 8. A lower limit of 0.0mm and an

upper limit of 200.0mm were imposed for the initial loss computation and events

outside of this range were excluded from the analysis.

When the catchment was extremely saturated i.e. when the initial loss was very low,

it was observed that sometimes the initial loss values were lower than continuing loss

values. It was also observed in this analysis that in a few rainfall streamflow events,

the initial loss value was found lower than the continuing loss value not because the

catchment was extremely saturated but due to overlapping of two rainfall events

upon each other in one complete rainfall event. Events that overlapped each other in

one complete event were excluded in this analysis.

In the IL-CL model losses are estimated from observed rainfall and stream flow

events. The same procedure was adopted in this research work for the estimation of

losses. Also in the IL-CL model, they do not consider spatial variability or real

temporal pattern of losses. In this research work the spatial variability or real

temporal pattern of losses were not considered.

6.4 Method of continuing loss computation

In ARR (I. E. Aust., 1998) the continuing loss is defined as the loss that occurs at a

constant rate after the commencement of the surface runoff. The continuing loss in

ARR (I. E. Aust., 1998) is the average rate of loss that occurred during the remainder

of the storm. The procedure which was adopted in this analysis to compute the

continuing losses was the same as the procedure adopted in ARR (I. E. Aust., 1998)

i.e. the continuing loss is the rate of loss that occurred during the remainder of the

storm.

The rates of continuing loss are constant as recommended in ARR (I. E. Aust., 1998),

but the value could be decreasing with time depending upon the soil cover and

Page 100: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 6-5

duration of the storm. It was investigated in this analysis whether continuing loss rate

is constant in nature or continuing loss rate decays with the duration of the storm.

The continuing loss rate is a decaying function of duration, which is an assumption.

In this analysis initial loss and continuing loss model was used to compute the initial

loss and continuing loss values from the rainfall and streamflow events. In ARR (I.

E. Aust., 1988) the recommended design median initial loss ranging from 15.0 mm –

35.0mm and the recommended design median continuing loss 2.5 mm/h for eastern

catchments. Similarly for western Queensland catchments the recommended median

continuing loss is 1.4 mm/h. This shows that the recommended design initial loss

varies with the duration of the storm but the recommended design continuing loss

does not vary but remain constant throughout the duration of the storm.

Table 8.1 shows that the derived median continuing loss values for all the 48 selected

catchments are from 0.71mm/h – 5.8 mm/h. Hence it is observed that for Queensland

catchments the continuing loss varies with the duration of the storm rather than it

remains constant throughout the storm.

The rate of loss that occurred during the remainder of the storm after the initial loss

was satisfied was considered as continuing loss. In Figure 6.1 (section 6.3) the loss

that started from the 6th hour and continued up to the 12th hour was the continuing

loss. The continuing loss was computed and averaged over the time period for the

remainder of the storm at hourly timesteps.

In actual rainfall events the continuing loss continues until the end of surface runoff.

As this research was performed with the real pluviograph and daily rainfall data, it

was easy to compute the duration of surface runoff of the same rainfall event. In this

research continuing loss was also estimated up to the end of the surface runoff, to

investigate how much actual continuing loss values varied with the design

recommended Queensland continuing loss values. It was observed that usually the

surface runoff from a rainfall event continues even after the end of the storm.

Therefore the continuing loss which was averaged over the time period computed up

to the end of the storm always estimates higher loss value than the continuing loss

value which was averaged over the time period computed up to the end of surface

Page 101: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 6-6

runoff. In some of the rainfall streamflow events, the duration of the remainder of the

storm is longer than the duration of the surface runoff i.e. the rainfall continued even

after the end of the surface runoff. In these events when the rainfall was very low in

intensity and did not show any variation in the resulted streamflow, then the duration

of the remainder of the storm and the duration of the surface runoff for those same

rainfall streamflow events were considered equal. For these types of rainfall

streamflow events the continuing loss values computed were the same under both the

conditions. Some of the events from stream gauge stations 105015A, 107001B and

107003A were examples of these types of events.

The water balance equation from the start of a rainfall event and the end of a runoff

event may be expressed as:

R = IL + CL*t + QF (6.1)

where R = Total rainfall of the event expressed in average depth of rainfall in mm

over the catchment.

QF = Quickflow, assumed to be resulted from the rainfall event, expressed in mm.

t = Time elapsed between the start of the surface runoff and end of the rainfall event

(hours).

Since, QF is the total streamflow (SFT) minus baseflow (BF), equation (6.1) may be

written as:

R = IL + CL*t + SFT – BF (6.2)

Where both SFT and BF are expressed in mm.

As IL-CL model does not consider the temporal variability of losses. From equation

(6.1) CL may be expressed as:

CL = (R – IL – QF)/ t (6.3)

Page 102: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 6-7

To estimate QF in equation (6.3), separation of baseflow from total streamflow was

required, as discussed in chapter 7. A lower limit of 0.0mm/h and an upper limit of

20.0mm/h were imposed for the continuing loss computation and events outside of

this range were excluded from this analysis. As continuing loss value more than 20.0

mm/h, needs more detailed investigation.

6.5 Method of proportional loss computation

In ARR (I. E. Aust., 1998) the proportional loss is defined as an initial loss followed

by a loss consisting of a constant fraction of the rainfall in the remaining time period.

The proportional loss is assumed to be a constant fraction of the rainfall after the

commencement of surface runoff. The proportional loss was computed as:

Proportional loss = 1 – [(Vol2) / (rainstorm – Ilstorm)] (6.4)

Rainstorm = Total rainfall volume of the storm

Ilstorm = Volume of initial loss for the storm

Vol2 = Total surface runoff volume for the storm

To evaluate the loss values and investigate how the loss value varies with the

catchment, the proportional loss was also computed for each and every selected

rainfall and streamflow events. Then these computed proportional losses were

observed and compared with the continuing loss values of the same rainfall

streamflow events. The loss model which was used in this research analysis is the

initial loss-continuing loss model. Appendix E shows the results of all the

proportional losses of 48 selected catchments.

6.6 Method of volumetric runoff coefficient computation

The volumetric runoff coefficient was computed as the ratio of the volume of surface

runoff to the total volume of rainfall of the storm (Hill et al., 1996). The same

Page 103: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 6-8

equation was used in this research to compute the volumetric runoff coefficient. The

volumetric runoff coefficient was computed as:

Volumetric runoff coefficient = (Vol2) / (rainstorm) (6.5)

Vol2 = Total surface runoff volume for the storm

Rainstorm = Total rainfall volume of the storm

All the abbreviations were the same as mentioned in Section 6.5. In this research

work the volumetric runoff coefficient was also computed for all the selected rainfall

streamflow events of the catchments. Then these computed volumetric runoff

coefficients were observed and compared with the continuing loss as well as

proportional loss values. Appendix E shows the results of all the volumetric runoff

coefficient losses of 48 selected catchments.

The volumetric runoff co-efficient can not be rational since the runoff co-efficient

must vary with the both loss values and rainfall volume. For catchment where the

soil is more pervious the runoff co-efficient would be smaller. As the impervious

area increases the runoff co-efficient approaches unity. Again when the soil is

saturated even in the case of rural catchments, the runoff co-efficient value will also

be higher depends upon the degree of saturation of the catchment.

6.7 Losses versus catchment size

Catchment size influences storm runoff in a number of direct and indirect ways.

Various aspects of runoff such as total yield, flood peaks, direct storm runoff and

losses are usually affected by the catchment size accordingly.

The resulting streamflow hydrograph of a streamflow depends upon the size of the

catchment. When the catchment size is small to medium, the source area is close to

the rainfall gauging station. The streamflow hydrographs of these catchments tend to

be high peaked with little or no delay between the commencement of rainfall excess

and the start of rise of the streamflow hydrograph. For large catchments the source

Page 104: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 6-9

area is far away from the rainfall gauging station. Hence a considerable delay will

occur between the beginning of rainfall excess and the start of surface runoff at the

catchment outlet, hence the hydrographs tend to be broad crested. Laurenson and

Pilgrim (1963) mentioned that peak discharge is one of the factors affecting the loss

rate magnitude.

It was observed that for larger catchments there is lack of uniformity in catchment

characteristics than in smaller to medium sized catchments. Laurenson and Pilgrim

(1963) mentioned that catchment characteristic is a factor which affects the loss

value.

The rainfall events which are potential to produce significant surface runoff for large

catchments, the rainfall excess would not occur from all over the catchment at the

same time. The rainfall excess would occur only on some portion of the catchment.

This ‘partial area runoff’ can more probably occur in larger catchments because of

the variation of catchment soil conditions, soil moisture content or variation in

rainfall. Care should therefore be exercised in using these values in determining a

design loss rate, especially if the type and condition of soil and soil cover vary

appreciably over the catchment.

From the above discussion it is evident that loss computation for large catchments is

different from small to medium sized catchments. For that reason only small to

medium sized catchments were used in this research to derive the loss values for

design flood estimation.

6.8 FORTRAN program development

To compute losses (continuing loss, proportional loss and volumetric runoff

coefficient) the volume of runoff resulting from the rainfall streamflow event needs

to be estimated. The streamflow data recorded, consists of runoff resulting from

rainfall event and baseflow. A computer program was developed to separate the total

streamflow hydrograph into baseflow and surface runoff, which is illustrated in

Appendix D. The output of this specially developed computer program was checked

Page 105: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 6-10

with the readily available software packages. Then the computed program was used

to compute losses for 48 selected catchments. The program first computed initial loss

then computed continuing loss, proportional loss and volumetric runoff coefficient

using the definitions mentioned in sections 6.3, 6.4 and 6.5.

6.9 Surface runoff threshold value

Initially a surface runoff threshold value equal to 0.01 mm/h was used in computing

all these losses. The surface runoff commenced when the surface runoff threshold

value was exceeded. From this analysis it was observed that with the variation of the

threshold value the loss value also varied. To observe how much loss value varied

with the change of threshold value two more surface runoff threshold values were

used in this research (Table 8.6). There was nothing called most suitable threshold

value for loss computation of different size of catchments. The two other surface

runoff threshold values which were used in this research work were 0.02mm/h and

0.005mm/h respectively. The analysis of how the loss value varied with the change

of the threshold value is discussed in chapter 8.

6.10 Reasons for the variability of calculated loss values

From this investigation it was observed that there are few reasons which affected the

variability in calculated loss values from event to event. These reasons are discussed

below:

• Catchment condition is a factor which affects the loss values from event to

event. For example from the same rainfall event a saturated catchment will

produce larger floods than the dry catchment.

• In a rainfall event, when the rainfall intensity is not uniform throughout the

catchment. A partial area runoff occurs which is another reason for the

variability in calculated loss values from event to event.

Page 106: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 6-11

• The variability of calculated loss values from event to event also occurs with

the variation of the surface runoff threshold value.

6.11 SUMMARY

Initial loss and continuing loss are two parameters simplified from the loss concept to

represent the condition of storm over the catchment with time. The initial loss-

continuing loss method is widely used in Australian practice and hence adopted in

this study. The most appropriate design case would usually involve the use of a large

storm from which runoff is likely to occur from the whole catchment. Therefore the

concept of runoff produced by infiltration excess was adopted in this study.

In ARR (I. E. Aust., 1998) the continuing loss rate is assumed to be constant during

the remainder of the storm. The procedure to derive the continuing loss values, which

was adopted in this research were the same as the procedure adopted in ARR (I. E.

Aust., 1998). In the IL-CL model losses are estimated from observed rainfall and

stream flow events. The same procedure was adopted in this research work for the

estimation of losses. Also in the IL-CL model, they do not consider spatial variability

or real temporal pattern of losses. In this research work the spatial variability or real

temporal pattern of losses were not considered. The proportional loss and the

volumetric runoff coefficient are computed in this analysis using the equations 6.4

and 6.5. Appendix E shows the results of all the initial losses, continuing losses,

proportional losses and volumetric runoff coefficient losses of 48 selected

catchments.

The resulting streamflow hydrograph depends upon the size of the catchment. When

the catchment size is small to medium, the source area is close to the rainfall gauging

station. The streamflow hydrographs of these catchments tend to be high peaked with

little or no delay between the commencement of rainfall excess and the start of rise

of the streamflow hydrograph. For large catchments the streamflow hydrographs tend

to be broad crested. Also the rainfall excess that occurs only on some portion, not the

entire of the catchment, that is, ‘partial area runoff’ situations can occur in larger

Page 107: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 6-12

catchment. For that reason only small to medium sized catchments were used in this

research to derive the loss values for design flood estimation.

The streamflow data recorded, consists of runoff resulting from rainfall event and

baseflow. A computer program was developed to separate the total streamflow

hydrograph into baseflow and surface runoff. Three different surface runoff threshold

values were used in this research to examine the effect of loss values with the

variation of threshold values. There is nothing called most suitable threshold value

for loss computation of different size of catchments.

Page 108: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-1

CHAPTER 7

METHOD OF BASEFLOW SEPARATION

7.1 General

The streamflow data measures total flow, which consists of surface runoff (rainfall

excess), interflow or throughflow and baseflow. In this analysis surface runoff was

considered to be the water that enters the stream primarily by way of overland flow

across the ground surface. Baseflow which is groundwater flow included other

components such as interflow or throughflow. It was required to separate the total

streamflow into surface runoff and baseflow to compute the storm losses. This

Chapter describes various methods of baseflow separation and the method that was

selected for this research work.

7.2 Review of baseflow separation process

There have been a number of studies performed regarding the separation of

streamflow on the basis of physical properties, chemical properties or travel time of

the streamflow in order to determine the proportions of the surface runoff and

baseflow at a given time. O’Loughlin et al. (1982), Hill (1993), Nathan and

McMahon (1990) separated the flow components not according to physical sources

of runoff but on the basis of travel times. Separation of surface runoff from baseflow

has been important for methods of real time and design flood estimation. For

example Dickinson et al. (1967) and Hall (1971) have reviewed the streamflow

separation problem from the viewpoint of flood analysis. Also separation of

streamflow is needed for the purpose of synthesising the hydrological behaviour of

catchments in rainfall runoff models. For example Boughton (1987) and Lyne and

Hollick (1979) illustrate the use of streamflow partitioning as a basis for rainfall

runoff modelling.

Page 109: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-2

Shirmohammadi et al. (1984) used rainfall data in conjunction with streamflow data

to determine periods of surface runoff. Their method involved making prior

assumptions about a threshold amount of rainfall was needed to initiate surface

runoff and also assumptions were made about the duration of surface runoff.

Pilgrim et al (1979) and Kobayashi (1986) studied the use of specific electrical

conductance of stream waters as a means of estimating the proportion of different

flow components. Kobayashi (1985) also used stream temperatures for partitioning

flows in an area where snowmelt formed a major part of the flow. Hino and Hasebe

(1985) used isotopes of oxygen as a means of separation. Boughton (1988)

mentioned that the data used in these studies are not readily available for routine

partitioning of streamflow, which is the limitation for practical application of these

methods.

Nathan and McMahon (1990) compared two baseflow separation techniques, one

based on a digital filter and the other on a simple smoothing and separation

technique. They noted that compared to the smoothed minima technique, the digital

filter method is better suited to low baseflow conditions.

Lyne (1979) separated streamflow into quick and slow response components using a

recursive digital filter. Also O’Loughlin et al. (1982), Chapman (1987), Nathan and

McMahon (1990) and Hill (1993) have used a similar method for baseflow

separation. The filter is of the simple form:

kf = 1. −kfa +

21 a+ ( ky - )1−ky (7.1)

where,

kf = Fitted quick response at the kth sampling instant

ky = Total streamflow;

a = Filter parameter ( or factor).

Page 110: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-3

Boughton (1988) mentioned that the recursive digital filter method (Equation 7.1)

uses only a single parameter (usually in the range of 0.75 to 0.90). Hill et al. (1996)

mentioned that two restrictions are placed on the digital filter: the separated slow

flow is never to be negative and nor it is greater than the original streamflow. The

other mathematical filtering methods used in Australia for partitioning streamflow

are more complex and use several parameters.

Bethlahmy (1971) used a method for baseflow separation using only streamflow

data. In that method, the rate of baseflow at any time (Bi) is made equal to the sum of

the baseflow rate at the previous time (Bi-1) and an incremental value (Ui).

Bi = Bi-1 + Ui (7.2)

Boughton (1988) mentioned that the rationale behind the calculations of the

incremental values (Ui) is not clear and the applicability of this method to Australian

catchments seems dubious.

In this research analysis two simple models of computer separation of baseflow and

surface runoff were compared in Figure 7.1. Both the models allow for user

identification of the point on a hydrograph at which the separation of flow

components was most clear. Figure 7.1 shows a streamflow hydrograph, where point

A and point B indicate the start and end of surface runoff hydrograph. Two models to

separate the baseflow from the streamflow are assumed by joining these two points

either by a straight line (Model 1) or by a smooth curve (Model 2). The methods of

baseflow separation from streamflow hydrograph were performed in using hourly

streamflow data. These methods use manual identification of one or more points that

mark the end of surface runoff. They differ in the assumption of how baseflow

discharge increases with the surface runoff.

Model 1 which was tested is based on the following operational assumptions:

• The maximum increase in baseflow discharge in one time step is limited to a

preset value,

Page 111: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-4

• Surface runoff commences when the total streamflow exceeds the baseflow

of the previous day by the preset maximum increase in baseflow discharge;

the new baseflow is made equal to the previous baseflow plus the preset

constant value; surface runoff is the difference between the total flow and the

baseflow,

• Surface runoff ends when the total streamflow does not exceed the baseflow

of the previous day by the preset maximum increase in baseflow discharge,

Model 2 allows for the increase in baseflow discharge to vary depending on the rate

of increase in total flow. The operation of the model is based on the following

assumptions:

• Baseflow increases whenever there is an increase in the rate of total flow,

• The rate of increase in baseflow is calculated as a fraction of the difference

between the total flow and the rate of baseflow on the previous day; the

difference between the total flow and the new baseflow is surface runoff,

• Surface runoff ends when the total flow is less than the baseflow of the

previous day

Model 1 used a constant rate of baseflow increase at each time step i.e. the increase

in baseflow and hence the rate of recharge of baseflow storage was time dependent.

In Model 2 the increase in rate of baseflow by a fraction of the surface runoff i.e.

baseflow increase and hence baseflow recharge was dependent on runoff volume.

Page 112: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-5

0

5

10

15

20

25

30

35

40

45

0 5 10 15 20 25Days

Dai

ly d

isch

arge

- M

L

Model 2

Model 1

A

B

Figure 7.1 Comparison of baseflow separation by two different models

Boughton (1988) has shown that both models give similar results in simulating big

runoff events. The main difference between these two models is that Model 1

estimates more surface runoff and less baseflow than Model 2 for the big events.

Also Model 1 estimates less surface runoff and more baseflow than Model 2 for

small runoff events. Model 2 estimates some surface runoff at every rise in the

hydrograph while Model 1 treats many small rises in the hydrograph as increases in

baseflow shown in Figure 7.2.

In general, the results obtained from Model 1 are more sensitive to change in the

value of the constant than the results of Model 2 to change in the value of the surface

runoff fraction (Boughton, 1988).

Page 113: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-6

Figure 7.2 Example of comparison of baseflow separation models in large and small

runoff Events (Boughton, 1988)

Dickson et al. (1967) illustrated some different ideas about the pattern of increase of

baseflow during periods of surface runoff. Regarding the numerous small rises in the

streamflow hydrograph, he mentioned that because of the rain falling directly on to

flowing water it should be partitioned as surface runoff in the manner of Model 2.

Dickson et al. (1967) also mentioned that the partition of surface runoff should be in

the manner as shown in of Model 2. It seems unlikely that baseflow discharge would

rise and fall as quickly as is calculated by Model 1 in these small rises in the

hydrograph.

Lyne and Hollick (1979) in Western Australia; and Bethlahmy (1971) in Idaho, USA

used the rate of increase of the baseflow proportional to the rate of surface runoff as

in Model 2. Also it seems highly unlikely that baseflow discharge would rise and fall

as quickly as is calculated by Model 1 in these small rises in the hydrograph.

For these reasons in this study Model 2 was selected as a method for baseflow

separation, i.e. the rate of increase of baseflow depends on the fraction of the surface

runoff (α ). The rate of baseflow at any time step is i (BFi) may be expressed as

halla
This figure is not available online. Please consult the hardcopy thesis available from the QUT Library
Page 114: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-7

equal to the baseflow in the previous timestep i-1(BFi-1) plus α times the difference

of total streamflow at step i (SFi) and baseflow at step i-1 (BFi-1).

The Equation, which was used to separate the baseflow from the total streamflow in

this research, is of the form:

BFi = BFi-1+ α (SFi - BFi-1) (7.3)

where

α = The fraction of the surface runoff

BFi = The rate of baseflow at any time step i

BFi-1 = The rate of baseflow in the previous timestep i-1

SFi = Total streamflow at timestep i

7.3 Results For the baseflow separation of rainfall streamflow events of 48 selected catchments it

was necessary to determine an acceptable baseflow separation co-efficient (α). In

this analysis the baseflow separation co-efficient was selected by trial and error

method. Also the sensitivity analysis of the α value was performed using 3 to 4

rainfall streamflow events.

The method of baseflow separation in this study was based on hourly streamflow and

rainfall data. The baseflow separation method Model 2 was applied to all the selected

48 study catchments to determine the value of α for each catchment and finally to

compute their baseflow and continuing loss values. The α value was not attached

with the relative streamflow event size, but it was a fraction of the surface runoff.

The example of the methods used to select the α value for different catchments are

discussed in this Chapter. Two catchments were selected randomly from Queensland

as an example to show how α values were estimated for this research with different

methods. These catchments were the Bremer River (143110A, catchment area 130 sq

km2) and the Tenhill Creek (143212A, catchment area 447 sq km2).

Page 115: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-8

Four streamflow events were selected for each catchment. An appropriate value of α

needed to be selected that allows acceptable separation of baseflow for all the events

of the Bremer River and Tenhill Creek catchments. In this research a semi-

logarithmic plot of the recession curve method was applied (I. E. Aust., 1998) to find

the end of surface runoff. In normal scale plot a change from quickflow to baseflow

in a streamflow hydrograph can not be identified. Hence streamflow hydrographs

were plotted on a semi-logarithmic graph (discharge to logarithmic scale, time to

linear scale), as the recession curves on semi-logarithmic graph approximated as

straight line segments. The baseflow separation line which starts from the rising limb

of the streamflow hydrograph (point A in Figure 7.1) and finishes at the start of the

recession curve (point B in Figure 7.1), was considered as the acceptable baseflow

separation line. For the Bremer River catchment a streamflow event (Event 1) was

selected and four different values of α were used to determine a suitable α value,

which would be used for the baseflow separation. In Figure 7.3 it is shown that when

α = 0.005 and α = 0.008 the baseflow separation curve joined above the start of the

straight line segment of the streamflow hydrograph. Hence any of these two values

of α did not provide acceptable baseflow separation. Again, in Figure 7.3 when α =

0.003 the baseflow separation curve joined below the start of the straight line

segment of the streamflow hydrograph. Hence α = 0.003 did not provide acceptable

baseflow separation. The results shown in Figure 7.3 indicate that a value of α =

0.004 provided acceptable baseflow separation for Event 1.

-4

-3

-2

-1

0

1

2

0 50 100 150

Time step

LogQ

α = 0.003

Page 116: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-9

-4

-3

-2

-1

0

1

2

0 50 100 150

Time stepLo

gQ

α = 0.004

-4

-3

-2

-1

0

1

2

0 50 100 150

Time step

LogQ

α = 0.005

-4

-3

-2

-1

0

1

2

0 50 100 150

Time step

LogQ

α = 0.008

Figure 7.3 Separation of streamflow components in a semi-log graph for Event 1,

when α = 0.003, 0 .004, 0.005, 0.008 (Bremer River)

Page 117: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-10

It was worth examining how sensitive the derived loss values were on the selection

of α values. In ARR (I. E. Aust., 1998) it is mentioned that the maximum baseflow

discharge is well below 10.0% of the maximum discharge. Table 7.1 shows that for

Event 1 of the Bremer River catchment when α = 0.004, CL = 1.16, if α was

increased by 25.0%, the value of CL varied by 1.11%, if α was decreased by 25.0%,

the value of CL varied by 1.38%. A variation of 100.0% in the value of α resulted in

only 4.0% variation in CL. This showed that a small error in selecting appropriate

value of α would not affect the value of CL significantly. For Event 1 in the Bremer

River catchment, it appeared that an α = 0.004 was acceptable.

Table 7.1 Effects of changing α value on CL, PL (proportional loss) and Volumetric runoff co-efficient Catchment ID = 143110A Catchment name = Bremer River

Event No α CL % differ. PL % differ. Vol.r.c % differ.

Event 1 0.003 1.147 1.380 0.624 1.270 0.112 2.750

0.004 1.163 0.632 0.109

0.005 1.176 1.118 0.641 1.424 0.107 1.835

0.008 1.211 4.127 0.659 4.272 0.101 7.339

Event 2 0.003 0.010 71.430 0.007 72.000 0.381 1.870

0.004 0.035 0.025 0.374

0.005 0.057 62.857 0.041 64.000 0.368 1.604

0.008 0.114 225.714 0.082 228.000 0.352 5.882

Event 3 0.003 0.179 17.510 0.118 15.710 0.614 3.020

0.004 0.217 0.140 0.596

0.005 0.251 15.668 0.163 16.429 0.581 2.517

0.008 0.344 58.525 0.223 59.286 0.539 9.564

Event 4 0.003 0.915 1.290 0.639 1.240 0.144 2.860

0.004 0.927 0.647 0.140

0.005 0.938 1.187 0.655 1.236 0.137 2.143

0.008 0.967 3.092 0.675 4.328 0.129 7.857

It was then examined whether the best value selected for Event 1 (α = 0.004), gives

an acceptable baseflow separation for other events of the same catchment. Three

more events were selected from the Bremer river catchment and α = 0.004 was used

for all three events to investigate the acceptable baseflow separation. Figure 7.4

Page 118: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-11

shows that the value of α = 0.004 indeed provided acceptable baseflow separation for

the other 3 events of the same catchment.

Thus, it appeared that for the Bremer River catchment a value of α = 0.004 was used

for baseflow separation for all streamflow events.

-0.5

0

0.5

1

1.5

2

0 20 40 60 80

Time step

Log

Q

-3

-2

-1

0

1

2

3

0 50 100 150

Time step

Log

Q

Event 2 Event 3

-3.5-3

-2.5-2

-1.5-1

-0.50

0.51

1.52

0 50 100 150

Time step

Log

Q

Event 4

Figure 7.4 The baseflow separation with α = 0.004 for 3 events in the Bremer

River catchment.

For the catchments where a single α value did not provide the acceptable baseflow

separation, another method was used to select an appropriate α value for the

acceptable baseflow separation. ARR (I. E. Aust., 1998) recommends that the

median value is to be used, where a single value is to be selected from a range of

values. For Events 1, 2, 3 and 4 in the Tenhill Creek catchment, a value of α equals

Page 119: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-12

to 0.010, 0.003, 0.008 and 0.002 respectively provided acceptable separation of

baseflow, as shown in Figure 7.5. It was observed that the selected α value for each

event showed a wide variation and none of these values provided acceptable

separation for all four events.

0

0.5

1

1.5

2

0 50 100 150Time step

Log

Q

0

0.5

1

1.5

2

2.5

3

0 50 100 150 200Time step

Log

Q

Event 1 when α = 0.010 Event 2 when α = 0.003

-2

-1

0

1

2

3

0 20 40 60 80

Time step

LogQ

-1-0.5

00.5

11.5

22.5

3

0 50 100 150 200

Time step

Log

Q

Event 3 when α = 0.008 Event 4 when α = 0.002

Figure 7.5 Baseflow separation of four events for Tenhill Creek catchment.

It was then examined whether the median of these four values (0.0055) provided

acceptable separation for all four events. In Figure 7.6, Event 1 showed that the

separation curve between baseflow and surface runoff joined the streamflow

hydrograph in the middle of the recession curve. In Event 2, the baseflow separation

curve joined the streamflow hydrograph at the start of the recession curve. In Event

4, the baseflow separation curve joined the streamflow hydrograph before the start of

the recession curve. Figure 7.6 shows that baseflow separation with α = 0.0055

which was the median value provided a reasonable baseflow separation for all four

events for the Tenhill Creek catchment.

Page 120: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-13

0

0.5

1

1.5

2

0 50 100 150Time step

Log

Q

0

0.5

1

1.5

2

2.5

3

0 50 100 150 200Time step

Log

Q

Event 1 Event 2

-2

-1

0

1

2

3

0 20 40 60 80

Time step

LogQ

0

50

100

150

200

250

300

350

30 40 50 60 70

Time step

Q

Event 3(log scale) Event 3 (natural scale)

-1-0.5

00.5

11.5

22.5

3

0 50 100 150 200

Time step

Log

Q

0

50

100

150

200

250

300

350

400

0 50 100 150 200

Time step

Q

Event 4(log scale) Event 4 (natural scale) Figure 7.6 Baseflow separation for the four events with α =0.0055 (Tenhill Creek) The value α (0.0055 was rounded to 0.005) was varied to observe how CL value was

affected. Table 7.2 shows that for Event 1 in the Tenhill Creek catchment when α =

0.005, CL = 1.71, if α was increased by 20%, the value of CL varied by 2.78%, if α

was decreased by 20%, the value of CL varied by 1.46%. Thus a variation of 60% in

the value of α resulted in only 4.8% variation in the CL value. For the Event 2 and

Page 121: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-14

Event 3, the variation in α value by about 50% caused about 13% and 2% variation

in CL value. However for Event 4, the CL was more sensitive to the change of α

value. In general it was found that a smaller error in selecting appropriate value of α

did not affect the value of CL significantly for the Tenhill Creek catchment. A single

flood event with total rainfall, flood hydrograph and baseflow separation is shown in

Appendix H.

Table 7.2 Effects of changing value on CL, PL (proportional loss) and Volumetric

runoff coefficient

Catchment ID = 143212A Catchment name = Tenhill Creek

Event No α CL % differ. PL % differ. Vol.r.c % differ.

Event 1 0.004 1.689 1.460 0.757 1.560 0.091 4.600

0.005 1.714 0.769 0.087

0.006 1.736 2.783 0.779 2.906 0.083 8.791

0.008 1.771 4.855 0.795 5.020 0.077 15.385

Event 2 0.004 1.475 4.283 0.503 4.373 0.334 4.702

0.005 1.541 0.526 0.319

0.006 1.593 8.000 0.543 7.952 0.307 8.084

0.008 1.671 13.288 0.57 13.320 0.289 13.473

Event 3 0.004 2.063 0.578 0.694 0.857 0.111 1.835

0.005 2.075 0.700 0.109

0.006 2.087 1.163 0.703 1.297 0.108 2.703

0.008 2.111 2.327 0.711 2.450 0.105 5.405

Event 4 0.004 0.17 24.107 0.111 24.490 0.508 4.312

0.005 0.224 0.147 0.487

0.006 0.27 58.824 0.177 59.459 0.47 7.480

0.008 0.346 103.529 0.226 103.604 0.442 12.992

7.4 Summary

The recursive digital filter method used by many of the researchers for the baseflow

separation, uses only a single parameter (usually in the range of 0.75 to 0.90). Two

restrictions are placed on the digital filter: the separated slow flow is never to be

Page 122: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 7-15

negative and nor it is greater than the original streamflow. The other mathematical

filtering methods used in Australia for partitioning streamflow are more complex and

use several parameters.

Bethlahmy (1971) used a method for baseflow separation using only streamflow

data. In that method, the rate of baseflow at any time (Bi) is made equal to the sum of

the baseflow rate at the previous time (Bi-1) and an incremental value (Ui). Boughton

(1988) mentioned that the rationale behind the calculations of the incremental values

(Ui) is not clear and the applicability of this method to Australian catchments seems

dubious.

Two simple models of computer separation of baseflow and surface runoff were

compared in this study. Both the models allow for user identification of point on a

hydrograph at which the separation of flow components was most clear. The method

of baseflow separation from streamflow was performed in using hourly streamflow

data. The two models of baseflow separation were compared to select a suitable

baseflow separation method for this research work. The baseflow separation method

Model 2 was selected for this analysis and was applied to all the selected 48 study

catchments to determine the α value for each catchment and finally to compute their

continuing losses, proportional losses and volumetric runoff coefficients. The results

of only two catchments are discussed in this Chapter as an example.

The following conclusions were drawn from the study:

• An acceptable baseflow separation coefficient (α) was selected for the

catchments by trial and error and also their sensitivity analysis was performed

using 3 to 4 rainfall streamflow events.

• The continuing loss was not very sensible to the selection of α value in the

baseflow separation. It was found that a change in α value by about 50% made

less than about 10% variation in the value of continuing loss. The results of the

loss values derived from this research are discussed in the next chapter.

Page 123: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-1

CHAPTER 8

RESULTS AND DISCUSSIONS 8.1 General

The design loss values which were derived from this research are presented and

discussed in this chapter. A total of 969 rainfall and streamflow events were

identified for the 48 unregulated rural catchments as shown in Table 8.1. A lower

limit of 0.0mm and an upper limit of 200.0mm were imposed for the initial loss

computation i.e. rainfall streamflow events which estimated initial loss values

outside of this range (0.0mm-200.0mm) were excluded from this analysis. Similarly

a lower limit of 0.0mm/h and an upper limit of 20.0mm/h were imposed for

continuing loss i.e. rainfall streamflow events which estimated continuing loss values

outside of this range (0.0mm/h–20.0mm/h) were excluded from this analysis. Less

than 1.0% of total events based on initial loss and less than 1.5% of total events

based on continuing loss were excluded as the range of the loss values were

considered. This chapter describes the fixed losses used in design flood estimation,

followed by a discussion on stochastic losses. It also covers regionalization of losses.

Finally the validation of results is described in this chapter.

8.2 Fixed losses

The losses where only a single loss value for a catchment either the median or mean

value was used are described as fixed losses in this analysis. The derived storm

losses were compared with ARR (I. E. Aust., 1998) recommended loss values and

the interaction of these derived losses were observed with other loss variables such as

how continuing loss should be estimated, surface runoff threshold values and

durations of the storm. This section compares the derived loss values obtained from

the 48 selected catchments with ARR (I. E. Aust., 1998) recommended losses and

also discusses about how the derived loss values vary with the change of loss

variables.

Page 124: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-2

ARR (I. E. Aust., 1998) is a design guide for flood estimation. The design loss values

are recommended in ARR (I. E. Aust., 1998), which is used by the designers for

design flood estimation. In ARR (I. E. Aust., 1998) there is no recommended

proportional loss and volumetric runoff co-efficient values. Hence the results of the

derived proportional loss and volumetric runoff co-efficient were not compared.

8.2.1 Comparison was made between derived computed losses and ARR (I. E.

Aust., 1998) recommended losses

The descriptive statistics of all the selected 969 rainfall streamflow events of IL and

CL values are shown in Table 8.1. Out of all the 48 selected catchments in Table 8.1,

the catchments which have the streamflow towards the east of Queensland were

considered as eastern catchments. A total of 25 catchments were considered as

eastern catchments. For the eastern catchments the IL values range was 0.0mm –

189.37mm and the CL values range was 0.01mm/h – 18.31mm/h and the median IL

values range was from 4.84mm – 71.77mm and the median CL values range was

from 0.71mm/h – 4.74mm/h respectively. The derived IL values from the study

catchments were much higher than the recommended IL values in ARR (Table 3.6,

Book Two, P.48, I. E. Aust., 1998 for eastern Queensland). The median IL values

from the selected 627 rainfall events of eastern catchments showed a range of

4.84mm – 71.77mm (average range of the median value: 37.98 mm) was compared

with the median IL values in ARR (I. E. Aust., 1998) for eastern catchments, which

was 15.0mm – 35.0mm (average of the range of median value: 25 mm). The details

of all the results of 969 rainfall streamflow events of 48 selected Queensland

catchments with a threshold value 0.01mm/h are presented in Appendix E.

Page 125: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-3

Table 8.1 Descriptive statistics of the computed IL and CL values (N = number of events)

Catchment ID Name Area (km2) N Storm initial losses (IL ), mm Storm continuing losses (CL ) mm/hRange Median Range Median

102101 Pascoe River 635 93 0.2 - 174.88 37.61 0.05 - 13.67 1.91104001 Stewart River 480 7 3.89 - 78.3 42.17 0.9 - 6.59 1.42105105 E. Norman. R. 300 3 10.92 - 18.39 11.92 0.92 - 1.43 1.3107001 Endeavour R. 310 3 16.35 - 114.03 71.77 0.57 - 3.07 0.71107003 Anna River 247 3 12.24 - 36.46 14 0.94 - 2.63 1.49112003 N. Johnston R. 173 15 3.3 - 108.55 34.04 0.3 - 7.79 2.69112101 S. Johnston R. 400 3 31.52 - 112.72 41.66 2.68 - 4.48 3.34114001 Murray River 155 23 1.6 - 159.22 65.75 0.05 - 8.44 4.74116008 Gowrie River 124 61 0.29 - 155.01 21.74 0.01 - 10.29 2.63116015 Blunder Creek 127 48 1.92 - 189.37 70.53 0.07 - 11.3 1.46116017 Stone River 157 55 0.26 - 161.71 33.23 0.09 - 14.52 2.54118003 Bohle River 143 24 0.11 - 93.2 28.8 0.66 - 7.63 2.26119006 Major Creek 468 4 10.27 - 79.87 35.35 0.33 - 1.20 1.15120014 Broughton R. 182 19 2.0 - 71.0 18.42 0.16 - 8.39 2.06120216 Broken River 78 11 29.35 - 123.37 64.26 0.56 - 9.11 1.7124002 St. Helens Ck. 129 11 11.56 - 154.62 53.71 0.33 - 6.04 1.62125005 Blacks Creek 505 35 0.8 - 144.39 57.63 0.22 - 15.39 3.15130207 Sande Creek 409 14 3.84 - 97.04 27.74 0.18 - 8.99 2.68136108 Monal Creek 92 12 2.71 - 48.2 13.08 0.18 - 9.12 1.21137101 Gregory River 454 8 3.57 - 123.05 29.81 0.12 - 5.74 2.235138110 Mary River 486 23 0.6 - 126.09 29.95 0.1 - 4.01 1.02141009 N. Maroochy R. 38 22 1.52 - 113.26 42.27 0.16 - 3.71 0.89143110 Bremer River 125 37 0.24 - 116.98 39.04 0.02 - 12.55 1.17143212 Tenhill Creek 447 24 6.86 - 125.46 43.48 0.01 - 7.58 1.16145003 Logan River 175 42 0.2 - 99.01 30.82 0.07 - 18.31 1.46145010 Running Creek 128 20 0.0 - 80.57 31.86 0.01 - 10.17 1.18145011 Teviot Brook 83 37 1.5 - 91.9 29.7 0.01 - 6.99 1145101 Albert River 169 35 0.59 - 165.84 43.46 0.1 - 6.95 1.52146014 Back Creek 7 10 0.0 - 49.55 4.84 0.52 - 2.92 1.87416410 Macintyre Brk. 465 28 0.05 - 93.34 28.73 0.15 - 15.06 1.77422321 Spring Creek 35 6 0.24 - 40.41 4.29 0.05 - 1.76 0.73422338 Canal Creek 395 27 0.07 - 116.41 24.24 0.13 - 6.84 1.58422394 Cadamine R. 325 21 8.99 - 89.35 40.51 0.08 - 3.2 0.92913005 Paroo Creek 305 6 1.06 - 25.64 9.31 0.64 - 5.58 2.38913009 Gorge Creek 248 9 0.03 - 46.23 6.2 0.17 - 5.39 1.06915205 Malbon River 425 5 9.17 - 59.79 34.21 0.56 - 14.61 3.95916002 Norman River 285 9 0.66 - 102.63 16.61 0.54 - 5.63 3.2916003 Moonlight Ck. 127 7 0.51 - 60.58 28.93 0.45 - 10.4 2.4917005 Agate Creek 228 19 0.14 - 34.67 13.9 0.23 - 7.12 2.83917007 Percy River 445 8 0.11 - 24.85 24.49 0.04 - 5.02 1.92917107 Elizabeth Ck. 585 8 2.74 - 42.09 27.25 0.25 - 4.03 2.04917114 Routh Creek 81 7 6.57 - 61.03 29.55 0.67 - 4.06 1.44919201 Palmer River 530 5 1.82 - 55.86 38.31 0.08 - 8.62 2.2919205 N. Palmer R. 430 7 0.8 - 46.19 14.51 0.3 - 10.95 5.8921001 Holroyd River 365 16 1.91 - 90.31 39.29 0.26 - 16.04 1.19922101 Coen River 166 59 0.26 - 81.89 24.52 0.08 - 9.45 2.16926002 Dulhunty River 325 12 0.0 - 16.29 3.39 0.03 - 5.91 1.6926003 Bertie Creek 130 8 0.0 - 5.03 0.7 0.18 - 6.85 1.64Average 20 0.0 - 189.37 0.7 - 71.77 0.01 - 18.31 0.71 - 5.8

Page 126: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-4

In this research the median initial loss values of all the selected 48 catchments were

computed as shown in Table 8.1. ARR (I. E. Aust., 1998) presented only the range of

median initial loss values, not all median initial loss values for the catchments. Hence

the average of the range of median loss values was compared in this research, not the

median value of the median initial losses of Queensland catchments. Table 8.2 shows

that the derived median IL which was computed from the 25 selected eastern

catchments was 52.0% higher than the ARR (I. E. Aust., 1998) recommended

median initial loss value. The use of smaller initial losses recommended in ARR (I.

E. Aust., 1998) is likely to result in significant overestimation of design floods. The

computed median CL value for the 25 eastern catchments was 1.52 mm/h, which was

compared with ARR (I. E. Aust., 1998) recommended eastern catchments median CL

value (2.5 mm/h). From Table 8.2 it is observed that the computed median CL value

for eastern catchments was 39.2% less than that of ARR (I. E. Aust., 1998)

recommended median continuing loss value. The low continuing loss values for

Queensland catchments was not because of the high initial loss values for the

catchments, but due to longer storm durations and less significant rainfall intensities.

In ARR (I. E. Aust., 1998) the median initial loss is shown by the upper and lower

limit, but the median continuing loss is illustrated by a fixed value. The derived

single median continuing loss value from this study was compared with ARR (I. E.

Aust., 1998) recommended single median continuing loss value.

Table 8.2 Comparison of computed median initial and median continuing loss values

with ARR (I. E. Aust., 1998) recommended median loss values for eastern

Queensland catchments

Typesof losses

Medianlosses

Average of the range of median losses

% Variation for loss values

Computed IL value 4.84 mm - 71.77 mm 37.98 mm 52.0

ARR (I. E. Aust., 1998) recommended IL value 15.0 mm - 35.0 mm 25.00 mm

Computed CL value 1.52 mm/h -39.2

ARR (I. E. Aust., 1998) recommended CL value 2.50 mm/h

Page 127: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-5

The derived initial loss values obtained from this research work was compared to the

computed initial loss values for Victorian catchments (Rahman et al., 2000). It was

observed that the losses in Queensland exhibit a much greater variability, as shown

in Table 8.3. The lower limit of initial loss for both the Queensland and Victorian

catchments are 0.0mm. The upper limit of initial loss and median initial loss values

for Queensland catchments are respectively 32.43% and 29.39% greater than that of

Victorian catchments. The possible reason for higher loss values and greater

variability in Queensland as compared to Victoria may be due to higher evaporation

rate in Queensland and variation in soil characteristics and yearly rainfall.

Table 8.3 Comparison of initial loss values between Queensland and Victorian

catchments

Initial loss Queensland (mm) Victoria (mm)Variation

(% higher for Qld)

Lower limit 0.00 0.00

Upper limit 189.37 143.00 32.43

Median 29.76 23.00 29.39 In ARR (I. E. Aust., 1998) the whole Queensland catchments is divided into eastern

and western catchments. In this research there were 5 catchments, which were

considered as the western catchments. Other catchments were considered as northern

catchments, though in ARR (I. E. Aust., 1998) there are no loss values recommended

for northern catchments. Table 8.4 shows that the average of the derived median IL

which was computed from the 5 selected western catchments was 44.8mm and the

ARR (I. E. Aust., 1998) recommended median initial loss value is 0.0mm. The use of

smaller initial losses recommended in ARR (I. E. Aust., 1998) is likely to result in

significant overestimation of design floods. The computed median CL value for the 5

western catchments was 1.58 mm/h, which was compared with ARR (I. E. Aust.,

1998) recommended western catchments median CL value (1.4 mm/h). Table 8.4

shows that the computed median CL value for western catchments was 12.86%

higher than that of ARR (I. E. Aust., 1998) recommended median continuing loss

value. For the Western catchments the IL value range was from 0.07mm –

Page 128: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-6

116.41mm, but in ARR (I. E. Aust., 1998) the IL value range is from 0.0mm-

80.0mm. The reason of computed IL and CL values of this research were well

different from recommended loss values, because in ARR (I. E. Aust., 1998) the

recommended CL values used were derived from a very few Queensland catchments

and also recommended IL values used were derived using the NSW catchments (not

Queensland catchments). The detail of this existing recommended loss values in

ARR (I. E. Aust., 1998) is discussed in section 8.4.2.

Table 8.4 Comparison of computed median initial and median continuing loss values

with ARR (I. E. Aust., 1998) recommended median loss values for

western Queensland catchments

Typesof losses Loss range

Medianlosses

Average of the rangeof median losses

% Variation for loss values

Computed IL value 0.07 mm - 116.41 mm 4.29 mm - 40.51 mm 44.8 mmARR (I. E. Aust., 1998) recommended IL value 0.0 mm - 80.0 mm 0.0mm 0.0 mm

Computed CL value 1.58 mm/h 12.86ARR (I. E. Aust., 1998) recommended CL value 1.4 mm/h

8.2.2 Interactions of losses with other variables

8.2.2.1 Different methods of computing continuing losses and their comparison

In ARR (I. E. Aust., 1998) it is mentioned that after satisfying the IL, the CL in a

rainfall event occurs until the end of the storm. In other words the recommended

value for the continuing loss is computed up to the end of the remainder of the storm.

The assumption of the estimation of continuing loss in ARR (I. E. Aust., 1998) is

discussed in equation 6.3 (Chapter 6). This assumption is applicable where the

design storm is used to compute the design loss values.

This assumption is not accurate for actual rainfall events, because in actual rainfall

events continuing loss occur up to the end of the surface runoff. In this research

actual rainfall and actual streamflow data were used to compute the loss values.

Page 129: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-7

Hence it was possible to compute the duration of surface runoff from the surface

runoff hydrograph. The continuing loss occurred up to the end of surface runoff was

computed by the equation 8.1 and was compared with the computed CL values (CL

values up to the end of the storm) of this research work. As IL-CL model does not

consider the temporal variability of losses, to compute continuing loss the following

equation 8.1 was adopted in this research.

CL1 = (R – IL – QF)/ t1 (8.1)

Where,

R = Total rainfall of the event expressed in average depth of the rainfall over the

catchment in mm

IL = Initial loss in mm

QF = Quickflow, total streamflow minus baseflow in mm

CL1 = Continuing loss occurred within the time t1 (h)

t1 = Time elapsed between the start of the surface runoff and end of the surface

runoff (hour)

All the derived CL and CL1 values obtained from this research are shown in Table

8.5. Also some important statistics of the derived CL and CL1 values from the study

catchments are summarized in Table 8.5. The range of CL and CL1 values were

found 0.01mm/h – 18.31mm/h and 0.0mm/h – 10.40mm/h respectively and the

median values for CL and CL1 were 1.67mm/h and 1.49mm/h respectively.

In most of the rainfall events the surface runoff continues even after the end of the

storm. A few events in some catchments like stream gauging station numbers

116015A, 124002A, 141009A, 146014A, 422321B and 913009A the duration (t) is

greater than the duration (t1). It means that the surface runoff was ceased prior to the

completion of the rainfall event. This usually happens when there is a long duration

rainfall event with a very little rainfall intensity at the end of the storm. For those

rainfall events the derived median CL value was found less than the derived median

CL1 value.

Page 130: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-8

A few events in 6 catchments out of 48 selected catchments (which is 12.5%), it was

observed that continuing loss does not continue upto the end of the storm as the

surface runoff was ceased prior to the completion of the rainfall event. Again most of

the events of 4 catchments out of 48 selected catchments (which is 8.33 %), it was

observed that these events do not satisfy the requirements of IL – CL model to

compute the losses as the surface runoff started after the end of the rainfall event.

Hence continuing loss does not occur upto the end of the storm.

In this research design continuing loss rate (CL) and actual continuing loss rate (CL1)

both were computed from observed rainfall event. The continuing loss rate CL1 can

be used as recommended continuing loss rate for real time flood estimation.

Page 131: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-9

Table 8.5 Descriptive statistics of the computed CL and CL1 values (N = number of events) Catchment Name Area (km2) N Storm continuing losses (CL ) mm/h Storm continuing losses (CL 1 )mm/h

Range Median Range Median102101 Pascoe River 635 93 0.05 - 13.67 1.91 0.06 - 9.15 1.68104001 Stewart River 480 7 0.9 - 6.59 1.42 0.45 - 3.76 1.07105105 E. Norman. R. 300 3 0.92 - 1.43 1.3 0.92 - 1.43 1.3107001 Endeavour R. 310 3 0.57 - 3.07 0.71 0.57 - 3.07 0.71107003 Anna River 247 3 0.94 - 2.63 1.49 0.94 - 2.63 1.49112003 N. Johnston R. 173 15 0.3 - 7.79 2.69 0.1 - 7.79 2.33112101 S. Johnston R. 400 3 2.68 - 4.48 3.34 2.49 - 3.20 2.63114001 Murray River 155 23 0.05 - 8.44 4.74 0.04 - 7.3 3.81116008 Gowrie River 124 61 0.01 - 10.29 2.63 0.01 - 9.33 2.41116015 Blunder Creek 127 48 0.07 - 11.3 1.46 0.05 - 8.24 1.58116017 Stone River 157 55 0.09 - 14.52 2.54 0.08 - 7.3 2.14118003 Bohle River 143 24 0.66 - 7.63 2.26 0.66 - 4.16 2.08119006 Major Creek 468 4 0.33 - 1.20 1.15 0.21 - 1.06 0.64120014 Broughton R. 182 19 0.16 - 8.39 2.06 0.04 - 7.52 1.5120216 Broken River 78 11 0.56 - 9.11 1.7 0.26 - 9.11 1.49124002 St. Helens Ck. 129 11 0.33 - 6.04 1.62 0.23 - 6.02 2.32125005 Blacks Creek 505 35 0.22 - 15.39 3.15 0.16 - 13.7 3.08130207 Sande Creek 409 14 0.18 - 8.99 2.68 0.02 - 6.36 1.95136108 Monal Creek 92 12 0.18 - 9.12 1.21 0.03 - 7.82 0.85137101 Gregory River 454 8 0.12 - 28.74 2.56 0.12 - 3.59 1.84138110 Mary River 486 23 0.1 - 4.01 1.02 0.07 - 3.72 0.83141009 N. Maroochy R. 38 22 0.16 - 3.71 0.89 0.16 - 2.43 0.94143110 Bremer River 125 37 0.02 - 12.55 1.17 0.01 - 3.81 0.44143212 Tenhill Creek 447 24 0.01 - 7.58 1.16 0.01 - 7.58 0.75145003 Logan River 175 42 0.07 - 18.31 1.46 0.01 - 5.18 0.43145010 Running Creek 128 20 0.01 - 10.17 1.18 0.0 - 6.73 0.63145011 Teviot Brook 83 37 0.01 - 6.99 1 0.01 - 3.93 0.8145101 Albert River 169 35 0.1 - 6.95 1.52 0.06 - 6.3 0.99146014 Back Creek 7 10 0.52 - 2.92 1.87 0.3 - 2.92 2.16416410 Macintyre Brk. 465 28 0.15 - 15.06 1.77 0.09 - 8.03 1.22422321 Spring Creek 35 6 0.05 - 1.76 0.73 0.02 - 1.76 0.78422338 Canal Creek 395 27 0.13 - 6.84 1.58 0.07 - 5 57 0.81422394 Cadamine R. 325 21 0.08 - 3.2 0.92 0.04 - 1.93 0.52913005 Paroo Creek 305 6 0.64 - 5.58 2.38 0.43 - 3.28 1.72913009 Gorge Creek 248 9 0.17 - 5.39 1.06 0.16 - 2.53 1.42915205 Malbon River 425 5 0.56 - 14.61 3.95 0.36 - 3.76 1.93916002 Norman River 285 9 0.54 - 5.63 3.2 0.25 - 4.03 2.18916003 Moonlight Ck. 127 7 0.45 - 10.4 2.4 0.3 - 10.4 2.32917005 Agate Creek 228 19 0.23 - 7.12 2.83 0.23 - 4.9 2.05917007 Percy River 445 8 0.04 - 5.02 1.92 0.03 - 4.96 1.81917107 Elizabeth Ck. 585 8 0.25 - 4.03 2.04 0.25 - 2.93 1.42917114 Routh Creek 81 7 0.67 - 4.06 1.44 0.21 - 3.69 0.94919201 Palmer River 530 5 0.08 - 8.62 2.2 0.08 - 7.2 2.16919205 N. Palmer R. 430 7 0.3 - 10.95 5.8 0.19 - 4.38 3.4921001 Holroyd River 365 16 0.26 - 16.04 1.19 0.21 - 6.42 1.11922101 Coen River 166 59 0.08 - 9.45 2.16 0.03 - 7.46 1.58926002 Dulhunty River 325 12 0.03 - 5.91 1.6 0.01 - 5.6 0.71926003 Bertie Creek 130 8 0.18 - 6.85 1.64 0.18 - 2.69 1.18Average 20 0.01 - 18.31 1.67 0.0 - 10.40 1.49

Page 132: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-9

For some catchments only 3-5 rainfall streamflow events were selected to compute

loss values (Basin ID no: 112101b, 137101a, 119006a and 915205a), as in those

catchments most of the events do not satisfy the requirements of IL-CL model to

compute the losses. For example, rainfall events where there was no surface runoff

occurred throughout the duration of the storm, such rainfall events were not

considered for the analysis. When the duration of the storm continues even after the

completion of the surface runoff and the rainfall that occurs after the completion of

the surface runoff did not show any impact in the streamflow, then to compute

continuing losses the duration of the remainder of the storm (t) and the duration up to

the end of the surface runoff (t1) were considered equal.

In the case of consecutive rainfall events, separated by a short time interval, if the

surface runoff generated by an individual event could not be distinguished explicitly

and hence these types of events were excluded from the analysis. Events where

surface runoff started after the end of the rainfall event were not considered in this

research work, as this kind of rainfall events do not satisfy the requirements of IL-

CL model.

To examine the variation of continuing loss due to difference of time t and t1 a

research was performed on the results of all the selected 969 rainfall events shown in

Table 8.6. The computed median CL value for time t which is 1.67 mm/h is 12.1%

higher than the computed median CL1 value for time t1 which is 1.49 mm/h. Table

8.6 also shows that by comparing the range of derived CL and CL1 values and by

taking the average of the range of both the loss values, CL value is 76.15% higher

than the CL1 value. The 25 catchments from Table 8.5, which is the eastern

Queensland catchments showed that the derived median CL value was 1.52mm/h and

the derived median CL1 value was 1.49mm/h. This result indicates that although the

initial losses for the study catchments were relatively higher than the ARR (I. E.

Aust., 1998) recommended initial losses (Table 8.2), but the derived CL and CL1

values were relatively smaller than the ARR (I. E. Aust., 1998) recommended

continuing losses. This indicates that once the catchments surface get saturated or

near saturated, the subsequent loss rate decreases. This is likely to produce relatively

greater volume of runoff particularly, at the latter part of the rainfall event.

Page 133: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-10

Table 8.6 Comparison between computed CL and CL1 values for all the selected

catchments

Typesof losses

Continuing loss range (mm/h)

Average of the range of continuing loss value (mm/h)

Variation(% higher for CL loss values)

Median continuingloss (mm/h)

Variation(% higher for CL loss values)

Computed CL 0.01 - 18.31 9.16 76.15 1.67 12.1

Computed CL 1 0.0 - 10.40 5.2 1.49

8.2.2.2 Comparison of derived loss values with different surface runoff

threshold values

The surface runoff threshold value is the minimum amount of water required above

the catchment to start the surface runoff. It is usually found that for a specific rainfall

event if the surface runoff threshold value increases, the initial loss also increases.

Hence it is important to select a more appropriate surface runoff threshold value to

compute the storm losses. In this research the surface runoff threshold value was

used as 0.01mm/h. To examine how storm loss values vary with the change of

surface runoff threshold values in loss computation, three different surface runoff

threshold values were used in this research work. These threshold values were

0.005mm/h, 0.01mm/h and 0.02mm/h respectively. Table 8.7 shows the change of

loss values of median IL, CL and CL1 with the change of surface runoff threshold

values.

Page 134: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-11

Table 8.7 Comparison of computed IL, CL and CL1 values with different surface runoff threshold values Catchment Name Area (km2) Events Surface runoff threshold = 0.005 mm/h Surface runoff threshold = 0.01mm/h Surface runoff threshold = 0.02 mm/h

No median IL median CL median CL 1 median IL median CL median CL 1 median IL median CL median CL 1

102101 Pascoe River 635 93 30.75 1.83 2.415 37.61 1.91 1.68 39.29 1.78 2.15104001 Stewart River 480 7 38.52 1.64 1.435 42.17 1.42 1.07 42.17 1.42 0.86105105 E. Norman. R. 300 3 11.92 1.3 1.3 11.92 1.3 1.3 11.92 1.3 1.3107001 Endeavour R. 310 3 71.77 0.71 5.21 71.77 0.71 0.71 53.68 0.705 5.28107003 Anna River 247 3 14 1.49 1.49 14 1.49 1.49 72 1.49 1.49112003 N. Johnston R. 173 15 22.19 3.005 2.47 34.04 2.69 2.33 47.275 3.325 2.635112101 S. Johnston R. 400 3 21.93 2.76 2.47 41.66 3.34 2.63 49.72 3.7 2.9114001 Murray River 155 23 38.14 2.91 3.32 65.75 4.74 3.81 64.805 2.445 3.46116008 Gowrie River 124 61 14.405 2.56 2.37 21.74 2.63 2.41 24.54 2.61 2.46116015 Blunder Creek 127 48 61.46 1.36 1.7 70.53 1.455 1.58 68.815 1.63 1.89116017 Stone River 157 55 31.21 2.49 2.4 33.23 2.54 2.14 32.51 2.63 2.37118003 Bohle River 143 24 27.685 2.355 1.925 28.8 2.255 2.08 37.71 2.17 1.86119006 Major Creek 468 4 35.345 1.18 1.03 35.345 1.145 0.64 47.865 0.995 0.525120014 Broughton R. 182 19 15.67 1.78 1.5 18.42 2.06 1.5 19.83 1.925 1.53120216 Broken River 78 11 40.4 1.08 0.93 64.26 1.7 1.49 52.33 2.015 1.655124002 St. Helens Ck. 129 11 47.11 2.525 2.15 53.71 1.62 2.32 57.895 2.485 3.31125005 Blacks Creek 505 35 36.7 3.08 2.78 57.63 3.15 3.08 48.2 3 3.92130207 Sande Creek 409 14 22.815 2.61 1.79 27.74 2.675 1.945 33.97 2.56 1.99136108 Monal Creek 92 12 11.31 1.21 0.85 13.075 1.205 0.85 25.66 1.2 0.85137101 Gregory River 454 8 31.22 2.235 1.575 29.805 2.56 1.84 37.51 2.45 1.04138110 Mary River 486 23 31.29 1.335 0.945 29.95 1.02 0.83 36.62 1.13 0.85141009 N. Maroochy R. 38 22 14.155 1.035 0.93 42.27 0.89 0.935 42.45 0.71 0.9143110 Bremer River 125 37 35.82 1.19 0.5 39.04 1.17 0.44 37.885 1.18 0.545143212 Tenhill Creek 447 24 39.19 1.26 1.14 43.475 1.155 0.75 42.21 1.23 0.73145003 Logan River 175 42 25.46 1.81 0.46 30.815 1.455 0.425 30.535 1.28 0.425145010 Running Creek 128 20 31.72 1.18 0.52 31.86 1.18 0.63 31.735 1.115 0.645145011 Teviot Brook 83 37 27.07 1.32 0.86 29.695 1 0.8 30.22 1.245 0.82145101 Albert River 169 35 36.89 1.5 0.86 43.46 1.515 0.99 43.46 1.41 1.03146014 Back Creek 7 10 4.84 1.56 2.16 4.84 1.87 2.16 4.84 1.64 2.6416410 Macintyre Brk. 465 28 28.73 1.49 1.125 28.73 1.765 1.22 28.91 1.55 1.19422321 Spring Creek 35 6 4.29 0.53 0.78 4.29 0.73 0.78 35.01 0.54 0.92422338 Canal Creek 395 27 26.955 1.345 0.88 24.24 1.58 0.81 25.73 1.5 0.83422394 Cadamine R. 325 21 38.83 0.74 0.52 40.51 0.92 0.52 33.67 0.9 0.52913005 Paroo Creek 305 6 4.455 2.295 1.205 1.84 2.38 1.715 2.23 1.51 1.19913009 Gorge Creek 248 9 11.155 1.075 0.615 6.2 1.06 1.42 9.49 1.31 0.65915205 Malbon River 425 5 34.21 1.24 1.24 46.69 3.945 1.925 15.65 2.33 1.33916002 Norman River 285 9 16.61 2.99 1.65 16.61 3.2 2.18 16.315 3.285 1.98916003 Moonlight Ck. 127 7 24.695 3.85 2.465 28.93 2.4 2.32 32.525 1.555 0.655917005 Agate Creek 228 19 14.205 3.06 1.995 13.9 2.83 2.05 18.36 3.03 1.995917007 Percy River 445 8 20.38 2.2 1.81 24.49 1.92 1.81 26.04 1.94 1.81917107 Elizabeth Ck. 585 8 23.47 2.14 1.24 27.25 2.035 1.415 31.55 1.92 1.43917114 Routh Creek 81 7 26.04 3.83 1.08 29.55 1.44 0.94 33.86 1.3 0.64919201 Palmer River 530 5 31.29 2.305 2.16 38.31 2.2 2.16 45.69 2.16 1.185919205 N. Palmer R. 430 7 14.51 6.97 3.4 14.51 5.8 3.4 11.685 7.15 3.83921001 Holroyd River 365 16 42.01 1.28 1.06 39.29 1.185 1.11 46.885 1.13 0.625922101 Coen River 166 59 14.78 2.23 1.62 24.52 2.16 1.58 25.175 2.185 1.475926002 Dulhunty River 325 12 0.72 1.59 0.7 1.64 1.6 0.705 4.145 2.3 1.95926003 Bertie Creek 130 8 0.31 1.44 1.71 0.7 1.635 1.175 4.58 2.3 2.3Average 20 26.5 1.62 1.46 29.75 1.67 1.49 33.77 1.64 1.38

Page 135: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-12

Table 8.8 shows the comparison of median loss values with different threshold

values. Table 8.8 also shows that, when the threshold value was 0.005mm/h the

median initial loss was 26.5mm. When the threshold value for surface runoff of all

the selected events was increased to 0.01mm/h, the median initial loss was 29.75mm

i.e. the median initial loss values increased 12.3%. When the threshold value was

increased to 0.02mm/h from 0.005mm/h, the median initial loss was 33.77mm i.e.

the median initial loss values increased 27.4%. The median CL value was 1.62mm/h,

when the surface runoff threshold value was 0.005mm/h. By increasing the threshold

value from 0.005mm/h to 0.01mm/h, the median CL value was 1.67mm/h i.e. the

median continuing loss increased 3.1%. Again by increasing the threshold value from

0.005mm/h to 0.02mm/h, the median CL value was increased to 1.64mm/h i.e. the

median continuing loss increased 1.2%. Similarly the median CL1 value was

1.46mm/h, when the surface runoff threshold value was 0.005mm/h. By increasing

the threshold value from 0.005mm/h to 0.01mm/h, the median CL1 value was

1.49mm/h i.e. the CL1 value was increased to 2.1%. Again by increasing the

threshold value from 0.005mm/h to 0.02mm/h, the median CL1 value was decreased

to 1.38mm/h i.e. the CL1 value was decreased to 5.5%.

Care should be taken before the selection of the threshold value, as the threshold

value depends on the rainfall input and the size of the catchment. For larger

catchments the smaller threshold value would compute more accurate loss values.

This is because for larger catchments a small increase in threshold value would

convert a big volume of surface runoff into initial loss. For Victorian catchments Hill

et al., (1996a) used a surface runoff threshold value of 0.01mm/h.

From this result it is observed that the proper selection of a threshold value is

important for the computation of storm loss values. The result also indicates that the

median initial loss of a rainfall event is quite sensitive to the selection of a surface

runoff threshold value. Again, the derived median CL and CL1 values were not very

sensitive to the selection of a surface runoff threshold value.

Page 136: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-13

Table 8.8 Comparison of loss values with different threshold values

Loss valuesThreshold

values (mm/h)Medianvalues

% variationof losses for different

threshold values

0.005 26.5

IL (mm) 0.01 29.75 12.3

0.02 33.77 27.4

0.005 1.62

CL (mm/h) 0.01 1.67 3.1

0.02 1.64 1.2

0.005 1.46

CL 1 (mm/h) 0.01 1.49 2.1

0.02 1.38 -5.5

Page 137: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-14

8.2.2.3 Variation of continuing losses with duration

In ARR (I. E. Aust., 1998) the continuing loss is assumed to occur up to the end of

the rainfall event. To compare the effect of duration on continuing losses equation

6.3 was used:

CL = (R – IL – QF)/ t

Where,

R = Total rainfall of the event expressed in average depth of rainfall in mm over the

catchment.

IL = Initial loss in mm

QF = Quickflow, assumed to result from the rainfall event, expressed in mm.

t = Time elapsed between the start of the surface runoff and end of the rainfall event

(hour)

To examine the effect of duration on continuing loss an analysis was performed on

all the selected 969 rainfall events of this research using threshold value 0.01mm/h.

In ARR (I. E. Aust., 1998) it is recommended that for any rainfall event, the

continuing loss is a constant after satisfying the required initial loss. To examine how

continuing loss varies with the duration, the continuing losses of all the selected 969

rainfall events were plotted against their duration (duration between the end of initial

loss and the end of the rainfall event) of all the events as shown in Figure 8.1. The

continuing loss for each catchment was examined against their durations of the

remainder of the storm. It was observed that the continuing loss decays with duration

i.e. it was not a single fixed value as recommended in ARR (I. E. Aust., 1998). The

result of the continuing loss values for each catchment is shown in Appendix F. The

catchments with more than 12 rainfall events were considered for this investigation.

In Queensland the loss value varies with the location of the catchments. To examine

the effect of duration in loss values for different regions of Queensland, the

Queensland catchments were divided into two categories to compute storm losses

such as eastern catchments and western catchments. The initial losses in western

catchments are sometimes higher because the catchments are dryer than the eastern

Page 138: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-15

catchments. An investigation was executed to examine the effect of duration on

continuing losses for different locations of Queensland catchments. Out of all

selected 48 Queensland catchments 11 eastern catchments, 5 western catchments and

12 northern Queensland catchments were selected to examine the effect of duration

on continuing loss values.

y = -0.5454Ln(h) + 4.0791

0

5

10

15

20

25

30

0.1 1 10 100 1000Duration (h)

CL

(mm

/h)

Figure 8.1 Variation of continuing loss values with duration in all 48 selected

Queensland catchments

To examine how continuing loss varies with duration, the continuing loss and the

duration of 270 rainfall events of 11 eastern Queensland catchments were plotted as

shown in Figure 8.2. It shows that, the continuing loss is not constant with storm

duration but rather it decays with the duration. The equation of the decaying curve is

shown in Figure 8.2.

Page 139: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-16

y = -0.5873Ln(h) + 3.4464

0

5

10

15

20

25

30

35

1 10 100 1000Duration (h)

CL

(mm

/h)

Figure 8.2 Variation of continuing loss values with duration in 11 eastern

Queensland catchments.

In Figure 8.3 the continuing losses of 96 rainfall events of 5 western catchments in

Queensland are plotted against their respective durations to examine the effect of

duration on continuing losses. Figure 8.3 shows that the continuing loss is not

constant in respect of duration, but it decays with respect to duration of the rainfall

event. The equation of the decaying curve is also shown in Figure 8.3.

y = -0.5893Ln(h) + 3.6065

0

2

4

6

8

10

12

14

16

1 10 100 1000Duration (h)

CL

(mm

/h)

Figure 8.3 Variation of continuing loss values with duration in 5 western Queensland

catchments.

Page 140: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-17

In Figure 8.4 the continuing losses of 340 rainfall events of 12 northern catchments

of Queensland are plotted against their respective durations to examine the effect of

duration on continuing losses. Figure 8.4 shows that the continuing loss is not

constant in respect of duration, but that it decays with respect to duration of the

rainfall event. The equation of the decaying curve is shown in Figure 8.4.

y = -0.8883Ln(h) + 5.7003

0

2

4

6

8

10

12

14

16

1 10 100 1000Duration (h)

CL

(mm

/h)

Figure 8.4 Variation of continuing loss values with duration in 12 northern

Queensland catchments.

ARR (I. E. Aust., 1998) recommended that continuing loss rate is constant

throughout the duration of the storm. The derived continuing loss values of this

research were plotted in the diagram against their durations as shown in Figures 8.1,

8.2, 8.3 and 8.4. Also the result of the continuing loss against their duration for

individual catchments is shown in Appendix F. All these diagrams show that the

derived continuing loss value decreases with the increase in the duration of the

rainfall event i.e. CL value was not a fixed single value for a catchment as

recommended in ARR (I. E. Aust., 1998) but it decays with the increase in the

duration of the storm. Hence it was observed that the continuing loss of the

Queensland catchments can be described as probability distributed losses.

Page 141: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-18

8.3 Stochastic losses

8.3.1 Initial losses

Fixed losses are discussed in Section 8.2. Stochastic or probability distributed losses

is discussed in this section. In Queensland there is no data available on probability

distributed losses. It was investigated whether a theoretical distribution can be used

to describe the initial loss distributions. To undertake the analysis of probability

distributed losses, a total of 15 catchments ranging from 83 km2 to 486 km2 (average:

254 km2) were selected along the coastal region of Queensland as there were very

few western catchments that have long streamflow records to compute storm losses.

Out of these 15 catchments, 12 catchments were previously selected to compute the

fixed losses and 3 new catchments were randomly selected for this analysis. The

selected catchments were unregulated and rural and have reasonably long rainfall and

streamflow records. The locations of the 15 study catchments are shown in Figure

8.5.

Page 142: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-19

Figure 8.5 Locations of the 15 study catchments in Queensland

A total of 388 complete storm rainfall events were selected that have the potential to

produce significant surface runoff. For each complete storm, a storm-core was

identified, defined as the most intense rainfall burst within a complete storm.

The available IFD information in ARR (I. E. Aust., 1998) is not based on complete

storm but on periods of intense rainfall within complete storm, called burst. If this

existing information is to be used with the proposed new approach, it is more useful

to undertake the design rainfall analysis in terms of the storm bursts. However as the

duration of the bursts in the ARR (I. E. Aust., 1998) analysis was predetermined

rather than random, it is necessary to consider a new storm burst definition that will

produce randomly distributed storm burst durations. These newly defined storm

bursts are referred to as storm-cores, same as mentioned in Rahman et al. (1998).

The computed complete storm initial loss (ILs) and storm-core initial loss (ILc) values

of the selected catchments are shown in Table 8.9. Considering all the 388 rainfall

events, the mean ILs and ILc values were respectively 34.7mm and 29.4mm, that is

Page 143: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-20

mean ILc value is 18.0% smaller than mean ILs value. The median values of ILs and

ILc are respectively 28.7mm and 27.3mm. The standard deviations were 28.0mm and

19.8mm respectively, which were relatively high showing a high degree of

variability in computed loss values. Also the loss values show a positive skewness

with an average value of over 0.7. This shows that the losses in Queensland, in

general are much higher and having greater variability. Given the degree of

variability and wide range of ILs and ILc values for Queensland catchments, it

appears to be unreasonable to adopt a single representative value (either mean or

median) of losses for flood estimation, as adopted with the Design Event Approach.

Table 8.9 Loss statistics for 15 Queensland catchments (N = number of events, SD =

standard deviation)

Station ID N Complete storm loss (ILs ) Storm-core loss (ILc )

Range Mean Median SD Skew Range Mean Median SD Skew

117002 21 4.59-152.32 45.63 41.14 37.33 1.24 0.0-87.58 31.62 34.42 26.39 0.29

117003 14 0.11-154.01 43.24 30.77 46.02 1.37 0.0-154.01 41.86 38.98 35.23 0.96

120014 19 2.0-71.41 24.86 18.42 21.15 1.24 0.0-71.41 22.55 15.42 19.63 1.27

136112 12 0.47-88.31 31.38 23.57 28.51 0.92 0.0-84.68 30.46 22.87 16.88 0.39

138110 22 0.6-95.19 38.15 29.95 32.12 1.4 0.0-95.19 31.64 32.05 21.11 0.29

143110 37 0.24-116.98 42.23 39.04 28.73 0.81 0.0-109.75 17.81 38.35 22.01 0.96

145003 42 0.2-99.01 33.97 30.82 24.44 0.71 0.0-98.72 33.31 29.76 17.3 1.38

145011 37 1.5-91.90 30.48 29.7 21.19 0.98 0.0-91.90 28.74 27.15 18.22 0.81

145101 35 0.59-165.84 53.04 43.46 46.78 0.97 0.58-156.39 45.08 39.24 29.44 1.4

416410 34 0.31-93.34 35.77 28.73 26.61 0.69 2.215-88.38 33.93 28.14 16.33 1.07

422338 26 0.07-116.41 35.28 25.73 31 1.35 17.16-94.45 34.71 25.49 16.06 1.2

422394 21 8.99-89.35 47.3 40.51 26.62 0.38 8.99-85.56 34.88 32.13 16.27 1.21

913009 6 0.03-31.86 12.99 7.57 14.44 0.74 3.24-31.86 9.8 5.36 11.35 0.06

916002 8 0.66-46.37 20.48 16.32 15.93 0.47 0.0-43.18 20.24 15.09 13.8 -0.75

922101 53 0.26-97.81 25.6 24.86 19.82 0.58 0.0-83.41 24.9 24.66 17.51 0.14

Average 26 0.03-165.84 34.69 28.72 28.05 0.92 0.0-156.39 29.44 27.27 19.84 0.71

The individual histogram of ILs and ILc values of all the 15 catchments were

examined (examples are shown in Figures 8.6 and 8.7), and it is hypothesised that a

four-parameter Beta distribution can be used to describe the initial loss distributions

for Queensland catchments. The individual histogram of ILs and ILc values of most of

the 15 catchments are shown in Appendix G. A four-parameter Beta distribution is

Page 144: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-21

fitted to individual site’s ILs data using observed values of lower limit (LL), upper

limit (UL), mean and standard deviation of ILs data. The fitting of a theoretical

distribution to ILs data is considered only because ILc value was estimated from

simple relationship between ILs and ILc. The ILc was estimated from ILs following

the approach of Rahman et al. (2000) shown in equation 8.2.

ILc = ILs [0.5 + 0.25log10 (Dc)] (8.2)

Where

ILs = Complete storm initial loss

ILc = Storm-core initial loss

Dc = Storm-core duration

This relation gave ILc = ILs at Dc = 100 hour, and ILc = 0.50 × ILs at Dc =1 hour.

Figure 8.6 Histogram showing the distribution of ILs for catchment 143110.

01020304050607080

0 -20 21 -40 41 -60 61 -80 81 -100101 -120Initial loss (mm)

Freq

uenc

y

01020304050607080

0 -20 21 -40 41 -60 61 -80 81 -100101 -120Initial loss (mm)

Freq

uenc

y

01020304050607080

0 -20 21 -40 41 -60 61 -80 81 -100101 -120Initial loss (mm)

Freq

uenc

y

01020304050607080

0 -20 21 -40 41 -60 61 -80 81 -100101 -120Initial loss (mm)

Freq

uenc

y

Page 145: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-22

Figure 8.7 Histogram showing the distribution of ILc for catchment 143110.

For each catchment, a total of 10,000 values of ILs were generated from the fitted

four-parameter Beta distribution. The statistics of the observed and generated ILs data

were compared in Table 8.10, which shows that the generated data preserves the

statistics of the observed loss value very well with respect to mean value (variation is

in the range 0.17-3.9% with an average of 1.83%) but for Gorge Creek (Catchment

ID 913009) the variation in mean value was 30.3% on the basis of generated data,

which needs some more investigation. Table 8.10 also shows that the generated data

preserves the statistics of the observed loss value very well with respect to the

standard deviation (variation in the range 0-1.62% with an average of 0.23%). The

lower limits of both the generated and observed data varies in the range of 0.0-

2.73mm (which is close to 0.0mm) with an exception of two values 4.59mm for

Black River and 8.99mm for Cadamine River. In the case of the upper limit of both

the generated and observed data the variation is in the range of 0.0-0.80% with an

average of 0.19%. Table 8.10 shows that the lower limit and upper limit of the

generated data preserves the statistics of the observed loss value very well.

From the above analysis it was found that the initial losses in Queensland can be

approximated by a four-parameter Beta distribution. The generated initial losses from

the fitted Beta distribution preserve the lower limit, upper limit, mean and standard

0102030405060708090

0 - 20 21 - 40 41 - 60 61 - 80 81 - 100 101 - 120

Initial loss (mm)

Freq

uenc

y

0102030405060708090

0 - 20 21 - 40 41 - 60 61 - 80 81 - 100 101 - 120

Initial loss (mm)

Freq

uenc

y

Page 146: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-23

deviation of the observed losses very well of the observed ILs data. Thus, four-

parameter Beta distribution can be used to approximate ILs distributions in the

selected 15 catchments. The generated ILs data from the fitted Beta distribution can

be used to obtain derived flood frequency curves in the Queensland catchments using

Joint Probability Approach (Monte Carlo Simulation) (Rahman et al., 2001a,b).

Table 8.10 Comparison at-site observed and generated ILs data for the 15 catchments Catchment ID Name of the stream Area (km2 ) LL(mm) UL(mm) Mean(mm) SD(mm)

117002 Black River 256 Observed 4.59 152.32 45.63 37.33Generated 4.00 152.09 44.73 37.30

117003 Bluewater Creek 86 Observed 0.11 154.01 43.24 46.02Generated 0.00 154.00 42.80 45.90

120014 Broughton River 182 Observed 2.73 73.53 24.86 21.15Generated 2.00 73.52 24.02 21.14

136112 Burnett River 370 Observed 0.47 88.31 31.38 28.51Generated 0.00 88.30 31.00 28.49

138110 Mary River 486 Observed 0.60 126.09 38.15 32.12Generated 0.01 125.90 37.80 32.12

143110 Bremer River 125 Observed 0.24 116.98 42.23 28.73Generated 0.01 116.04 41.80 28.63

145003 Logan River 175 Observed 0.20 99.01 33.97 24.44Generated 0.01 98.72 32.70 24.40

145011 Teviot Brook 83 Observed 1.50 91.90 30.48 21.19Generated 1.01 91.31 29.75 21.14

145101 Albert River 169 Observed 0.59 165.84 53.04 46.78Generated 0.00 165.81 52.66 46.76

416410 Macintyre Brook 465 Observed 0.31 93.34 35.77 26.61Generated 0.00 93.30 34.70 26.57

422338 Canal Creek 395 Observed 0.07 116.41 35.28 31.00Generated 0.00 116.00 34.70 30.97

422394 Cadamine River 325 Observed 8.99 89.35 47.30 26.62Generated 8.00 89.35 47.08 26.66

913009 Gorge Creek 248 Observed 0.03 31.86 12.99 14.44Generated 0.00 31.86 18.64 14.21

916002 Norman River 285 Observed 0.66 46.37 20.48 15.93Generated 0.00 46.40 20.10 15.93

922101 Coen River 166 Observed 0.26 81.89 25.60 19.82Generated 0.00 81.60 24.80 19.80

8.3.2 Continuing losses

It was investigated whether a theoretical distribution can be used to describe the

continuing loss distributions for the Queensland catchments. To examine the

probability distribution of the CL values, a total of 20 events from Bremer River

(Catchment ID: 143110), 9 events from Tenhill Creek (Catchment ID: 143212) and

27 events from Logan River (Catchment ID: 145003) were selected and a histogram

was plotted for all the 56 events as shown in Figure 8.8. The plot shows that CL

distribution can be approximated by an exponential distribution. Stochastic CL

Page 147: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-24

values can be generated from the fitted distribution, which can be used to obtain

derived flood frequency curves using a Joint Probability Approach. The impact of

stochastic CL values on design flood estimates is left to the future research efforts.

Figure 8.8 Distribution of observed CL values

8.4 Regionalisation of derived loss values

8.4.1 General

ARR (I. E. Aust., 1998) provided the best possible information for design flood

estimation. Previous editions were published in 1987, 1977 and 1958. ARR (I. E.

Aust., 1998) published the recommended loss values for the different states of

Australia. Table 8.2 and Table 8.4 compared between the existing recommended loss

values in ARR (I. E. Aust., 1998) and the computed loss values from this research.

The basis of Queensland existing recommended design losses in ARR (I. E. Aust.,

1998) is discussed in this section.

CL (mm/h)

6.515.514.513.512.511.51.51

Freq

uenc

y40

30

20

10

0

Std. Dev = 1.46 Mean = 1.40N = 56.00

CL (mm/h)

6.515.514.513.512.511.51.51

Freq

uenc

y40

30

20

10

0

Std. Dev = 1.46 Mean = 1.40N = 56.00

Page 148: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-25

8.4.2 Basis of Queensland existing recommended design losses in ARR (I. E. Aust.,

1998)

8.4.2.1 Recommended loss values in ARR (I. E. Aust., 1998)

The recommended design loss value in ARR (I. E. Aust., 1998) for Queensland is

divided into eastern Queensland and western Queensland. For western Queensland

the recommended loss values are considered as same as the Northern Territory; this

must be an assumption as there is no reference to this comment in ARR (I. E. Aust.,

1998). It means that no investigation was performed on western Queensland

catchments to compute the recommended loss values. For eastern Queensland the

three different recommended loss values like initial loss, median initial loss and

median continuing loss were selected from three single papers published by different

Authors (I. E. Aust., 1998), which are discussed below:

8.4.2.2 Recommended median initial loss for eastern Queensland

The recommended median initial loss in ARR (I. E. Aust., 1998) is 15.0-35.0mm has

been selected on the results of the research publication of Cordery (1970b). In this

paper a total of fourteen catchments were selected and their median initial loss values

were computed. These computed loss values are considered as a recommended

median initial loss values for Queensland. It is important to note that all of these

fourteen selected catchments are situated on or east of the Great Dividing Range in

New South Wales. None of them is situated within the boundary of Queensland. The

range of the median initial loss values for these fourteen catchments is from 0.91

inches (2.31 cm) to 1.72 inches (4.37 cm). The areas of these catchments are ranging

from 0.024 sq miles (.06 km2) to 97 sq miles (251.23 km2).

8.4.2.3 Recommended median continuing loss for eastern Queensland

In ARR (I. E. Aust., 1998) for eastern Queensland catchments, the recommended

median continuing loss 2.5 mm/h has been selected on the basis of the research

publication of Cordery and Pilgrim (1983). The Queensland Water Resources

Commission provided 37 values for six basins from Queensland. All of them were

Page 149: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-26

small to medium size catchments except the Boyan river catchment, which has an

area of 4105 km2. The other five catchment areas ranged from 350 km2 to 545 km2.

In term of land cover three of the catchments have dense forest, two have medium

forest and the Boyan River catchment has scattered forest. The mean loss rates for

these six catchments range from 0.8-10.0mm/h. The median continuing loss rates for

six catchments were in the range of 0.9-8.0mm/h. From this range, a loss value of

2.5mm/h has been used as the recommended median continuing loss rate in ARR (I.

E. Aust., 1998).

8.4.2.4 Recommended initial loss for eastern Queensland

The recommended initial loss value 0.0-140.0mm in ARR (I. E. Aust., 1998) was

selected on the basis of the research publication of Queensland Water Resources

Commission (1982). A total of four catchments were selected to compute the initial

loss for eastern Queensland. The areas of these catchments range from 340 km2 to

1375 km2. No initial loss values were published in this paper, and it is noted in ARR

(I. E. Aust., 1998) that, the initial loss values were obtained through private

communication.

8.4.3 Comments

In this research analysis, 48 catchments were selected from the whole of Queensland

to compute the loss values. Out of these 48 catchments the IL and CL values of 25

eastern catchments and 5 western catchments were computed. The range of the

median initial loss values of this research analysis can be used as recommended

median initial loss for eastern Queensland catchments as well as western catchments

to obtain more accurate design flood estimation. Also the median continuing loss

value of this research analysis would provide more accurate flood estimation than the

recommended median continuing loss value in ARR (I. E. Aust., 1998). Out of 48

selected catchments a total of 18 catchments were selected from the northern

Queensland. These loss values could be used as the recommended loss values for

different parts of Queensland catchments to obtain more accurate flood estimation

for Queensland.

Page 150: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-27

8.5 Validation of results

8.5.1 Calibration of runoff routing model

A catchment response model is needed to convert the rainfall excess hyetograph

produced by the loss model into surface runoff hydrograph. The proposed modelling

frame work was intended for application with a non-linear, semi-distributed runoff

routing model like RORB (Laurenson and Mein, 1997), as the runoff and streamflow

routing processes are generally non-linear and spatially variable. However for this

research a simpler conceptual runoff routing model (with a single non-linear storage

concentrated at the catchment outlet) was adopted to reduce computational effort.

This model can account for catchment non-linearity but not for the distributed nature

of catchment storage. For medium size catchment up to 500 km2, this model provides

an indication of what could be achieved with a semi-distributed model such as

RORB. For the adopted runoff routing model, the storage discharge relationship was

in the form shown in equation 8.3:

S = k Q m (8.3)

Where

S = Storage (m3)

k = Storage delay coefficient (hour)

Q = Streamflow discharge (m3/s)

m = Non-linearity parameter

The objective of this model calibration was to determine a value of k that results in

satisfactory fit for a range of recorded rainfall and runoff events at the catchment

outlet. In ARR (I. E. Aust., 1998) it is mentioned that the value of m is virtually

always less than one. Rahman et al. (2001b) used m = 0.8 for Victorian catchments.

Weeks and Stewart (1978) derived the m value for Queensland catchments and it was

found that the average m value for Queensland catchments was 0.73. As this research

was performed with Queensland catchments, hence m = 0.73 was used in this

analysis. The storage delay coefficient k was estimated in this analysis separately for

Page 151: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-28

each flood, then a global k value was selected for all events (e.g. a median or a mean

value) giving appropriate weight to the values from individual events depending on

data quality, purpose of modeling. The example of the quality of fit of the observed

and computed streamflow is shown in Figure 8.9. In Figure 8.9 event 27/12/97 for

the Black River is illustrated as an example. The difference in peak of the

hydrograph was 0.007% and the difference in volume of the hydrograph was 0.21%

of the observed hydrograph.

0

5

10

15

20

25

1 3 5 7 9 11 13 15 17 19 21 23Time (h)

Surf

ace

runo

ff (m

3/s)

ObservedComputed

Figure 8.9 Fitting the single non-linear storage model for the Black River catchment (event 27/12/97)

8.5.2 Comparison of flood frequency curves with the observed losses and the

derived losses from this research

Three catchments Burnett River, Bluewater Creek and Black River catchments were

selected randomly from Queensland for the validation of the storm loss results

obtained from this analysis. Three different k values were computed for three

different catchments as mentioned in section 8.5.1. Their catchment sizes were

370km2, 86km2, 256km2 respectively. A Joint Probability Approach flood estimation

Page 152: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-29

method was used to construct the flood frequency curves. To obtain the flood

frequency curves of these catchments, a set of values of duration, intensity, temporal

pattern and initial loss was generated to define the rainfall excess hyetograph, which

then routed through the calibrated runoff routing model to produce a corresponding

streamflow hydrograph. From this generated data the simulation of streamflow

hydrographs was drawn. The CL value was used as a constant value rather than

probability distributed value for the flood frequency curves. The peak of each of the

simulated hydrograph was used to construct a derived flood frequency curve. The

resulting observed flood frequency curves (partial series) for Burnett River,

Bluewater Creek and Black River catchments are compared in Figures 8.10, 8.11 and

8.12 respectively with the derived IL and CL loss values of the 48 catchments of this

research (following the empirical distribution approach using Cunnane’s plotting

position formula). This comparison of flood frequency analysis was performed by

using a FORTRAN program (Rahman, 1999). It is hypothesised that a four-

parameter Beta distribution can be used to describe the initial loss distributions for

Queensland catchments. A four-parameter Beta distribution is fitted to individual

site’s ILs data using observed values of lower limit (LL), upper limit (UL), mean and

standard deviation of ILs data (discussed in section 8.3). All parameters in the

observed and derived flood frequency curves were kept the same except the four

parameters of initial loss (upper limit, lower limit, mean and standard deviation) and

the median continuing loss for Burnett River and Black River.

To compare the flood frequency curves FORTRAN program (Rahman, 1999) needs

the four parameters of initial loss values (upper limit, lower limit, mean and standard

deviation), but ARR (I. E. Aust., 1998) did not illustrate the four parameters of the

recommended initial loss values. Hence for Bluewater Creek the comparison of the

flood frequency curves were performed between the observed floods, floods for CL

value of the ARR (I. E. Aust., 1998) and derived floods for the CL value of 48

catchments. The horizontal segment of these curves represents simulated events with

zero runoff.

Page 153: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-30

0

500

1000

1500

2000

2500

3000

3500

4000

0.1 1 10 100 1000 10000ARI (years)

Q (m

3 /s)

Observed floods

Derived floods with IL and CLof 48 catchments

Figure 8.10 Comparison of derived flood frequency curve with the losses of 48

selected catchments and ARR (I. E. Aust., 1998) for Burnett River.

In Figure 8.10 the comparison of the flood frequency curves was performed between

the observed floods of Burnett River and derived floods with the IL and CL loss

results of the 48 selected Queensland catchments. For both the flood frequency

curves, the generated data for the duration, temporal pattern and the intensity were

kept at same value for all the flood results. Only the IL and CL were changed, where

the IL values were probability distributed and the CL value was median loss value.

The result shows that the flood frequency curve from the derived loss values of 48

catchments fitted well with the flood frequency curve of Burnett River up to the

range of 900 years ARI.

In Figure 8.11 the comparison of the flood frequency curves was performed between

the observed floods of Bluewater Creek, computed floods with CL value of ARR (I.

E. Aust., 1998) derived floods with CL loss results of the 48 selected Queensland

catchments. For all the flood frequency curves, the generated data for the duration,

temporal pattern, intensity and IL were kept at same value for all the flood results.

Only the CL values were changed, where the CL values were the median loss values

Page 154: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-31

0100200300400500600700800900

1000

0.1 1 10 100 1000 10000ARI(years)

Q(m

3 /s)

Observed floods

Floods of CL loss of ARR

Derived flood of CL loss of 48catchments

Figure 8.11 Comparison of derived flood frequency curve with the losses of 48

selected catchments and ARR (I. E. Aust., 1998) for Bluewater Creek.

The probability distributed initial loss values were used for the Joint Probability

Approach flood estimation method, to construct the flood frequency curves. As ARR

(I. E. Aust., 1998) did not illustrate the probability distributed initial loss values,

hence comparison of the flood frequency curves in Figure 8.11 was performed using

only the median CL values for Bluewater Creek, the 48 catchments and ARR (I. E.

Aust., 1998). However, the difference between the flood frequency curves was not

remarkably high for Bluewater Creek.

In Figure 8.12 the comparison of the flood frequency curves was performed between

the observed floods of Black River and derived floods with the IL and CL loss results

of the 48 selected Queensland catchments. For both the flood frequency curves, the

generated data for the duration, temporal pattern and the intensity were kept same

value for all the flood results. Only the IL and CL values were changed, where the IL

values were probability distributed and the CL value was median loss value. The

result shows that the flood frequency curve from the derived loss values of 48

catchments fitted well with the flood frequency curve of Black River up to the range

of 1100 years ARI.

Page 155: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 8-32

0

1000

2000

3000

4000

5000

0.1 1 10 100 1000 10000ARI (years)

Q(m

3 /s)

Observed floods

Derived floods with IL and CL of 48catchments

Figure 8.12 Comparison of derived flood frequency curve with the results of 48

selected catchments and ARR (I. E. Aust., 1998) for Black River.

The results show that the derived flood frequency curves of all the three catchments

compare quite well with the derived loss values of this research analysis. From the

above findings it can be mentioned that the derived IL and CL loss values of this

research analysis, which were computed from the 48 selected catchments of the

entire of Queensland, can be used as the new recommended loss values for all the

Queensland catchments.

From this analysis it was found that the design flood peak did not change upto the

range of 350 years of ARI for Burnett River. For Bluewater Creek the design flood

peak remained unchanged upyo 65 years of ARI. Similarly for Black River the

design flood peak remain unchanged upto 460 years of ARI. Hence this analysis also

showed that the loss estimate from the rainfall does not change the probability of the

design flood peak for shorter range of ARI.

Page 156: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 9-1

CHAPTER 9

IMPLICATIONS AND IMPACTS OF THE RESEARCH

9.1. General

The implications and impacts from the outcome of this research work are discussed

in this chapter. These are categorised into two sections as follows:

1) Implications on model development

2) Socio-economic implications

9.2 Implications on model development

To compute the design IL and CL values, it is important to select a surface runoff

threshold value. ARR (I. E. Aust., 1998) recommends the IL-CL model to compute

design losses, but there is no surface runoff threshold given in ARR (I. E. Aust.,

1998) to use as a recommended threshold value. Hill et al., (1996a) used a surface

runoff threshold value to compute losses for Victorian catchments, which was

0.01mm/h. An investigation was performed on the 48 selected Queensland

catchments to select a suitable surface runoff threshold value that can be used as a

recommended threshold value for Queensland catchments. The surface runoff

threshold values used in this research were 0.005mm/h, 0.01mm/h and 0.02mm/h.

The result of the analysis showed that there is nothing called most suitable threshold

value which can be used as a recommended surface runoff threshold value for all

Queensland catchments. It depends, upon the catchment characteristics and the size

of the catchment. The result indicated that the median initial loss of a rainfall event is

quite sensitive to the selection of a surface runoff threshold value. However the

median continuing loss is not very sensitive to the selection of a surface runoff

threshold value. Some important information from this analysis was drawn.

Page 157: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 9-2

Information on surface runoff threshold value that will assist the designer to choose

the more accurate surface runoff threshold value are discussed below:

• For a candidate rainfall streamflow event the initial loss value increases by

increasing the surface runoff threshold value.

• The threshold value depends on the rainfall input and the size of the

catchment.

• For larger catchments the threshold value should be smaller, otherwise in loss

estimation a small increase in threshold value will convert a huge volume of

surface runoff into initial loss.

In ARR (I. E. Aust., 1998) it is mentioned that the continuing loss in a rainfall event

occurs for the remaining time period (t, discussed in section 8.2.2) of the storm, this

assumption is used for design storm. It is not possible to compute the duration of the

surface runoff from the design storm. In case of actual rainfall events this assumption

is not true, because the continuing loss of a rainfall event occurs until the end of the

surface runoff (t1, discussed in section 8.2.2). In this research analysis continuing loss

was computed using the pluviograph and streamflow data. It was possible to compute

the duration of the surface runoff for Queensland catchments. Continuing loss based

on both t and t1 were computed in this analysis. It was found that the median CL of

48 selected catchments based on t is 12.0% higher than the median CL1 (CL1

discussed in section 8.2.2) of the same 48 selected catchments based on t1. These

continuing loss values which were computed up to the end of the surface runoff are

more reliable than the ARR (I. E. Aust., 1998) recommended loss values. The

observed continuing loss value in this research analysis based on t1 would provide

better design flood estimation. Hence the computed continuing loss values which

were considered up to the end of the surface runoff can be used as recommended

continuing loss values for the future real time flood estimation.

ARR (I. E. Aust., 1998) recommended that continuing loss occurs at a constant rate

throughout the duration of the storm. An investigation was performed to examine

Page 158: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 9-3

whether continuing loss occurs at a constant rate for all storm durations or continuing

loss decays with duration of separate storm. Appendix F and Figures 8.1, 8.2, 8.3 and

8.4 shows that the continuing loss decreases with the duration of the rainfall event for

a catchment and for a region. From the Figures 8.1, 8.2, 8.3, 8.4 and Appendix F, it

can be noted that the fixed continuing loss values for Queensland catchments

recommended in ARR (I. E. Aust., 1998) is not acceptable. Hence continuing loss

function for Queensland catchments would provide probability distributed continuing

loss values, which will ultimately provide better design flood estimates.

9.3 Socio-economic implication

Rainfall runoff models are used to estimate design floods. These models require

several inputs such as rainfall duration, intensity, loss. Selection of an appropriate

loss value is very important for design flood estimation. A low loss value results in

over estimation of design floods (means large structures and higher capital cost). A

high loss value gives underestimation of design floods (means higher flood risk and

damage). Design of hydraulic structures that are subject to floods cost an average

$650 million per year in Australia (I. E. Aust., 1998). Since loss is an important input

for design flood estimation, an appropriate recommended loss value can save

millions of dollars per year in the design and construction of hydraulic structures

each year in Australia.

The steps followed in real time flood forecasting are similar to those used in the

design storm method of flood estimation. However, in real time forecasting, the

actual rainfall hyetograph over the catchment is combined with a model of losses to

determine the rainfall excess for input to a runoff-routing model. An investigation

was performed in this analysis, how conceptual loss models can provide more

accurate loss values by their more accurate loss functions. This improved conceptual

loss function can be used to provide better real time flood forecasting in the near

future. A more accurate flood forecasting will provide better socio-economic support

for the society.

Page 159: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 9-4

An accurate flood estimate is an important requirement for flood insurance. The

flood insurance is related to the anticipated flood damage or flood risk. The factors

which govern the flood risk are the magnitude, frequency and duration of the flood.

To estimate an accurate flood magnitude a suitable loss model is necessary. In this

research analysis an investigation was conducted on, how the existing IL-CL model

can compute better loss values by improving their loss functions. The outcome of

this research illustrated that an existing loss model by using an improved loss

function would provide more accurate flood estimation which would ultimately

reduce the flood insurance premium. Also the derived loss values from this research

would provide better flood estimation and ultimately would reduce the premium of

the insurance company.

Page 160: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 10-1

CHAPTER 10

CONCLUSIONS AND RECOMMENDATIONS

10.1 Introduction At present, there is inadequate information on design losses in most parts of

Australia including Queensland and this is one of the greatest weaknesses in

Australian flood hydrology. Currently recommended design losses in Queensland are

not compatible with design rainfall information in Australian Rainfall and Runoff

(ARR). These recommended losses in ARR are biased towards wet antecedent

conditions and are generally too low. Also design losses for observed storms show a

wide variability and it is always difficult to select a representative value of loss from

this wide range for a particular application. Despite the wide variability of loss

values, in the commonly used Design Event Approach, a single value of initial and

continuing losses is adopted. Because of the non-linearity in the rainfall-runoff

process, this is likely to introduce a high degree of uncertainty and possible bias in

the resulting flood estimates. In contrast, the Joint Probability Approach can consider

probability-distributed losses in flood estimation. For Queensland, no data on

probability-distributed losses are yet available.

This research examines the currently recommended design initial and continuing loss

data for flood estimation in Queensland. A total of 48 catchments from Queensland

ranging from 7 km2 to 635 km2 are selected. From these 48 catchments 969 rainfall

events that have the potential to produce significant runoff are selected and their

initial and continuing losses are computed from the observed pluviograph and

streamflow data. The observed initial losses are much greater than the currently

recommended values in the ARR (I. E. Aust., 1998) for eastern Queensland. The

observed median initial loss for all over Queensland is found to be 44.0% greater

than the ARR (I. E. Aust., 1998) recommended initial loss value. This finding has

important economic significance.

Page 161: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 10-2

The initial losses in eastern Queensland show a greater variability than that of

Victoria. The upper limit and median of initial losses in Queensland are 32.0% and

34.0% greater than those of Victoria.

It has also been found that a four-parameter Beta distribution can be used to

approximate the initial loss distributions in Eastern Queensland. Probability-

distributed initial losses and continuing losses were specified in 15 and 3 Queensland

catchments, and it is found that the probability distributed initial and continuing

losses can be used with the Joint Probability Approach to determine derived flood

frequency curves.

10.2 Overview of this study

The investigation involved in modelling losses in flood estimation is summarised in

the following steps:

10.2.1. Methods adopted for estimation of flood:

In ARR (I. E. Aust., 1998) the currently recommended method for design flood

estimation is based on Design Event Approach. The key assumption involved in this

approach is that the result in a flood output that has the same AEP as the rainfall

input. The success of this approach is crucially dependent on how well this

assumption is satisfied.

Significant developments have been made in the application of more advanced

techniques in flood estimation e.g. Joint Probability Approach (Rahman et al., 2001a,

b) and Continuous Simulation (Boughton, 2000). Thus it is clear that the Joint

Probability Approach, which considers the outcomes of events with all possible

combinations of input, values and if necessary their correlation structure is most

likely to lead to better estimates of design flows. Joint probability Approach is

theoretically superior to the Design Event Approach and regarded as an attractive

design method (I.E. Aust., 1998).

Page 162: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 10-3

It is difficult to use the continuous modelling for design flood estimation in rural

catchments because of the complexity involved in calibration of the model. The main

problems with the Continuous simulation arise from the difficulties in adequately

modeling the soil moisture balance, synthesising long records of rainfall and

evaporation at the appropriate temporal and spatial resolution, and accounting for

correlations between inputs. Hence Design Event Approach and Joint probability

were used in this research as the flood estimation methods.

10.2.2. Selection of study catchments to compute losses:

A total of 48 catchments were selected from the entire Queensland to compute loss

values. The electronic version of all the 48 catchment boundaries was collected from

the Department of Natural Resources and Mines. All the selected catchments were

small to medium size catchments, not large catchments. Since major regulation

affects the rainfall runoff relationship significantly, gauging stations subject to major

regulation (such as dams, back water effect etc) were not included in this research.

The selected catchments were mainly unregulated and rural and have reasonably long

rainfall and streamflow records.

Each catchment was represented by a stream gauging station, which was located at

the outlet of the catchment. The stream gauging record length for any catchment was

less than 11 years, that catchment was not selected as a candidate catchment. A total

of 82 pluviograph stations and 24 daily rainfall stations were used to compute the

loss values for all the selected catchments. If there is no pluviograph station inside

the catchment or within 50 km of the catchment boundary then this type of

catchment was not selected as study catchment. Some of the study catchments have

more than one pluviograph and daily rainfall stations inside the catchment boundary.

Most of these catchments were selected from coastal areas because there are only a

few catchments in western Queensland having reasonably long streamflow record.

The areas of the catchment were ranging from 7 km2 – 645km2. The median and

mean of the catchment areas were respectively 248 km2 and 273 km2. Only 8% of the

catchments were greater than 500 km2 and 15% were smaller than 100 km2.

Page 163: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 10-4

10.2.3. Procedure adopted to compile and analyse the data:

A total of 48 streamflow gauging stations were selected for this research work. A

total of 82 pluviograph stations and 24 daily rainfall stations were selected for this

research. The range of stream flow data is 11 years to 48 years. The range of the

pluviograph record lengths is 4 years to 48 years. The range of the daily rainfall data

record lengths is 7 years to 112 years.

The list of the selected stream gauge stations, their location, streamflow record

lengths, selected pluviograph stations and daily rainfall stations was developed. The

Basin ID is the unique identifier of stream gauging stations used by Queensland

Department of Natural resources and Mines (DNRM) for Queensland catchments.

For each catchment only one stream gauge station was selected but 5 pluviograph

stations and 5 daily rainfall stations were selected.

In some instances more than one pluviograph and daily rainfall stations were used to

obtain the representative rainfall of catchments. In that cases the weighted average

rainfall was used to obtain the representative rainfall of the catchment, rather than

using a single pluviograph data or the disintegrated daily rainfall data. All the three

stream flow, pluviograph and rainfall data were made concurrent before selecting the

rainfall and streamflow event, as to understand how streamflow varies with the

variation of rainfall.

10.2.4. Storm loss computation in this research:

Initial loss and continuing loss are two parameters simplified from the loss concept to

represent the average situation of storm over the catchment with time. This method is

widely used in Australian practice and hence adopted in this study. The most

appropriate design case would usually involve the use of a large storm from which

runoff was likely to occur from the whole catchment. Therefore the concept of runoff

produced by infiltration excess was adopted in this study.

The procedure which was adopted in this analysis to compute the continuing losses

was the same as the procedure adopted in ARR (I. E. Aust., 1998). The capacity rates

Page 164: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 10-5

of continuing loss is constant as assumed in ARR (I. E. Aust., 1998), it also could be

decreasing with the duration of the storm. In this analysis the loss values were

computed from rainfall and streamflow data. The proportional loss and the

volumetric runoff coefficient are computed in this analysis using the equations 6.4

and 6.5.

The rainfall excess and storm runoff that occur only on some portion of the

catchment, is called ‘partial area storm’ situations can more probably happen in

larger catchment and does not satisfy the criteria of IL-CL model for loss

computation. For that reason the loss model which was used for this research

analysis was suitable for small to medium sized catchments but not suitable for large

catchments. For large catchments the source area is far away from the rainfall

gauging station. Hence a considerable delay will occur between the beginning of

rainfall excess and the start of surface runoff at the catchment outlet, hence the

hydrographs tend to be broad crested.

Three different surface runoff threshold values were used in this research to examine

the effect of loss values with the change of threshold values. There was nothing

called most suitable surface runoff threshold value for the loss computation of

different catchments.

A computer program was developed by the author using FORTRAN PowerStation

4.0 to compute the initial loss, continuing loss, proportional loss and volumetric

runoff coefficient from all the selected events of 48 selected catchments is illustrated

in Appendix D.

10.2.5. Procedure adopted to separate the baseflow from streamflow:

The various methods of baseflow separation were reviewed to select an appropriate

method of baseflow for the study catchments. The two models of baseflow separation

were compared to select a suitable baseflow separation method for this research

work. The baseflow separation method Model 2 given in section 7.2 was selected for

this analysis and was applied to all the selected 48 study catchments to determine the

α value for each catchment and finally to compute their continuing losses. It was

Page 165: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 10-6

found that an acceptable baseflow separation coefficient α was selected for a

catchment by trial and error and sensitivity analysis, using 3 to 4 streamflow events

of that catchment. The rate of baseflow at any time was computed from the total

streamflow by using the α value in Equation 7.3.

The continuing loss is not very sensible with the change of α value. It was found that

a change in α by about 50% made less than 10% variation in the value of continuing

loss. For the remaining study catchments an acceptable baseflow separation

coefficient α was selected for each catchment to estimate baseflow separation from

streamflow hydrograph and ultimately to compute the continuing loss values from a

rainfall event.

10.2.6. Outcome of the research work:

Comparison was made between the computed median initial and median continuing

loss values with ARR (I. E. Aust., 1998) recommended median loss values. The

computed median IL of all over Queensland (Eastern and western catchments) is

44.0% higher than the ARR (I. E. Aust., 1998) recommended median initial loss

value. The computed median CL value is 33.0% less than that of ARR (I. E. Aust.,

1998) recommended median continuing loss value. The use of smaller initial losses,

according to ARR (I. E. Aust., 1998) recommendation, is likely to result in

significant overestimation of design floods.

It was found that the ARR (I. E. Aust., 1998) recommended median CL value which

is 2.5 mm/h is 49.7% higher than the computed median CL value for time t which is

1.67 mm/h. The computed median CL value for time t which is 1.67 mm/h is 12.1%

higher than the computed median CL1 value for time t1 which is 1.49 mm/h. This

result indicates that although the initial losses for the study catchments are relatively

higher than the ARR (I. E. Aust., 1998) recommended initial losses (Table 8.2), but

the CL and CL1 values are relatively smaller, which indicates that once the

catchments surface get saturated or near saturated, the subsequent loss rate decreases.

This is likely to produce relatively greater volume of runoff particularly, at the latter

part of the rainfall event.

Page 166: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 10-7

To select a surface runoff threshold value two things should be considered, the

rainfall input and size of the catchment. If the catchment size is big then the

threshold value should be small, because a small increase in threshold value would

result in a high initial loss. An assumption is made in ARR (I. E. Aust., 1998) that for

a rainfall event, the continuing loss occurs at a constant rate during the remainder of

the storm. An analysis was executed in this research to investigate the assumption in

ARR (I. E. Aust., 1998). This research illustrated that the assumption of ARR (I. E.

Aust., 1998) is not correct as Figures 8.1, 8.2, 8.3 and 8.4 shows that the continuing

loss decreases throughout the duration of the storm.

It was observed from the analysis of 15 catchments that the initial losses in

Queensland can be approximated by a four-parameter Beta distribution and from the

analysis of 3 catchments it is found that the CL distribution can be approximated by

an exponential distribution. Stochastic IL and CL values can be generated from the

fitted distribution, which can be used to obtain derived flood frequency curves using

a Joint Probability Approach. The computed IL and CL value which was derived

from the 48 selected catchments of the whole of Queensland can be used as the

recommended IL and CL values for all other ungauged Queensland catchments. To

examine the flood frequency analysis, three catchments were randomly selected and

their derived flood frequency curves were compared with the observed flood

frequency curves, where the computed IL and CL values of 48 catchments were used.

The result shows that the flood frequency curve fits quite well with each other. Only

in the case of Bluewater creek for greater ARI, the range from 17 to 470 years the

flood magnitudes increase by about 0.0-20.0%.

10.3 Conclusions

This research analysis examined how to improve the design initial and continuing

loss data for flood estimation in Queensland. The finding has important significance

for design flood estimation. The following conclusions can be drawn from the

analysis:

Page 167: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 10-8

• The average of the median IL for eastern catchments was 52.0% higher than the

ARR (I. E. Aust., 1998) recommended median initial loss value. The average of

the median CL value for eastern catchments is 39.2% less than that of ARR (I. E.

Aust., 1998) recommended median continuing loss value. The use of smaller

initial losses, according to ARR (I. E. Aust., 1998) recommendation, is likely to

result in significant overestimation of design floods.

• The computed median initial loss and continuing loss rate values obtained from

this research analysis can be used as the recommended design loss values for

Queensland catchments to obtain more accurate flood estimation for Queensland.

• The average of the median IL which was computed from the western catchments

was 44.8mm and the ARR (I. E. Aust., 1998) recommended median initial loss

value for western catchments is 0.0mm. It was observed that the computed

median CL value for western catchments was 12.86% higher than that of ARR (I.

E. Aust., 1998) recommended median continuing loss value

• To examine the effect of surface runoff threshold value on storm loss, an analysis

was performed on the 48 selected Queensland catchments. The result indicated

that the median initial loss of a rainfall event is quite sensitive to the selection of

a surface runoff threshold value i.e. if the threshold value increases 100.0% the

median initial loss increases in the range of 12.0-15.0%. But the median

continuing loss for both the cases CL and CL1 is not very sensitive to the

selection of a surface runoff threshold value.

• The continuing loss is not very sensitive to the selection of α value in the

baseflow separation. It was found that a change in α by about 50.0% makes less

than 10% variation in the value of continuing loss.

• The initial loss for Queensland catchments can be approximated by a four-

parameter Beta distribution. The generated initial loss preserves the statistics very

well with respect to the lower limit, upper limit, mean and standard deviation of

the observed losses. The lower limits of both the generated and observed data

Page 168: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 10-9

varies in the range of 0.0-2.73mm (which is close to 0.0mm) with an exception of

two values 4.59mm for Black River and 8.99mm for Cadamine River. For upper

limit the range of variation of generated and observed data is 0.0-0.80%, for

mean the variation is in the range of 0.17-3.9% and for standard deviation the

variation is 0-1.62%.

• In ARR (I. E. Aust., 1998) it is mentioned that the continuing loss in a rainfall

event occurs till the remaining time period (t, discussed in section 8.2.2) of the

storm. But this assumption is applied for design storm, in actual rainfall event the

continuing loss occurs till the end of the surface runoff (t1, discussed in section

8.2.2). Continuing loss based on both t and t1 were computed in this analysis. It

was found that the median CL of 48 selected catchments based on t is 12.0%

higher than the median CL1 (CL1 discussed in section 8.2.2) of the same 48

selected catchments based on t1. Also by taking the average of the range of both

the continuing loss values CL and CL1, it was found that the CL value was

76.15% higher than the CL1 values.

• It is recommended in ARR (I. E. Aust., 1998) that the continuing loss that occurs

for a rainfall event is at a constant rate during the remainder of the storm. But this

recommendation is not correct as Appendix F and Figures 8.1, 8.2, 8.3 and 8.4

show that the continuing loss decreases throughout the duration of the storm i.e.

it was not a single fixed value during the remainder of the storm. Hence the

continuing loss for the Queensland catchments were probability distributed

losses.

• The CL distribution can be approximated by an exponential distribution.

Stochastic CL values can be generated from the fitted distribution. This finding is

being confirmed with a larger data set. However a large data set is required to

derive stochastic continuing losses for application with Joint Probability

Approach.

Page 169: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation 10-10

10.4 Suggestions for future research

Based on the findings of this study, following research tasks are identified as being

worth further research. These are:

• Derive probability-distributed initial and continuing losses for all the selected 48

catchments that can be used with the recently developed Joint Probability

Approach to flood estimation to obtain more accurate design flood estimates.

• Formulate a more realistic loss function that considers a fixed initial loss at the

beginning followed by continuing loss as a decaying function with respect to

rainfall duration. This loss function will be more suited to long duration storms

particularly on large catchments.

• This study did not address the issue of losses for extreme events. A detailed

investigation can be done on the rainfall events which have an initial loss of more

than 200 mm and a continuing loss of more than 20 mm/h.

• Regionalisation of the stochastic losses for use in ungauged catchments.

Page 170: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation R-1

REFERENCES Ahern, P. A., & Weinmann, P. E. (1982). Considerations for design flood estimation using catchment modelling. Hydrol. and Water Resour. Symp., Melbourne, I.E. Aust., 44 - 48. Akan, A. O. (1992). Horton infiltration equation revisited. Journal of Irrigation and Drainage Engineering, 118(5), 828-830. Aston, A. R., & Dunin, F. X. (1979). Coupled infiltration and surface runoff on a 5 ha experimental catchment, Krawaree, NSW. Aust. Jour. Soil Res., 17, 53-64. Avery, D. R. (1986). Master of engineering science project report. School of Civil Engineering, The University of New South Wales. Avery, D. R. (1989). Application of RORB model to a flood warning system in the tweed valey, New South Wales. Hydrol. and Water Resour. Symp., I.E. Aust., 89/19, 90-94. Bates, B. C., Sumner, N. R., & Boyd, M. J. (1993). Non- linearity of flood runoff: what can be gleaned from calibrated runoff routing models? Civil Eng. Trans., I. E. Aust., CE35(2), 151-164. Bauer, S. W. (1974). A modified Horton equation for infiltration during intermittent rainfall. Hydrology Science Bulletin, 19(2), 219-225. Beaver, R. D., Hartman, J. P., & Wanielista, M. P. (1977). Infiltration and stormwater retention/ detention ponds.: Florida Technical University, Orland, FL. Bethlahmy, N. (1971). Hydrograph analysis: a computerised separation technique. Roneod report, USDA forest services, Intermountain Forest and Range Experiment Station, Moscow, Idaho, 14 pp. Beran, M. A. (1973). Estimation of design floods and the problem of equating the probability of Rainfall and Runoff. Paper presented at the Symposium on the Design of Water Resources Projects with Inadequate Data., Madrid, Spain. Beran, M. A., & Sutcliffe, J. V. (1972). An index of flood producing rainfall based on rainfall and soil moisture deficit. Jour. Hydrol., 17, 229-236. Betts, H. (1999). Floodplain planning - risk management from a local government perspective. Hydrol. And Water Resource. Symp. I.E. Aust. Nat. Conf. Brisbane, 99(25), 679 - 684. Boughton, W. C. (1987). Hydrograph analysis as a basis for water balance modelling. The institution of Engineers, Australia, Civil Engineering Transactions, Vol. CE 29, no.1, pp. 28-33.

Page 171: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation R-2

Boughton, W. C. (1988). Partitioning streamflow by computer. Civil Engineering Transcation, Institution of Engineers Australia, pp. 285-291. Boughton, W. C. (1989). A review of the USDA SCS curve number method. Aust. Jour. Soil Reaser, Soil and Water Management and Conservation, Vol. 27, pp 511-523. Boughton, W. C. (1993). A hydrographed-based model for estimating the water yield of ungauged catchments. Hydrol. Water Resour. Symp., I.E. Aust., 317-324. Boughton, W. C., & Carrol, D. G. (1993). A simple combined water balance/ flood hydrograph model. Hydrol. and Water Resour. Symp., 93/14, 299-304. Boughton, W. C., Srikanthan, S., & Weinmann, E. (2000). Benchmarking a new design flood estimation system. Hydrol. and Water Resour. Symp., 570-575. Boughton, W. C. (2001). Continuous Simulation model for flood estimation, User Manual Computer Version. Bouwer, H. (1966). Rapid field measurement of air-entry value and hydraulic conductivity of soil as significant parameters in flow system analysis. Water Resour. Resear. 2(4), 729-738 Bouwer, H. (1969). Planning and interpreting soil permeability measurements. Jour. Irrig. Drain. Engg,, 95(1R3), 391-402. Boyd, M. J., Bates, B. C., Pilgrim, D. H., & Cordery, I. (1987). WBNM a general runoff routing model computer programs and user guide (Water Research Lab. 170): The University of New South Wales. Boyd, M. J., Rigby, E., & Vandrie, R. (2001). WBNM2001 version 3.00 runoff routing model for floods on natural, urban and part urban catchments.: University of Wollongong. Bradley, A. A., & Potter, K. W. (1992). Flood frequency analysis of simulated flows. Water. Resour. Res., 28(9), 2375-2385. Brakensiek, D. L. (1970). Infiltration of water into non-uniform soil, discussion. Jour. Irrig. Drain. Div., American Society of Civil Engineers. New York, NY. Bras, R. L., Gaboury, D. R., Grossman, D. S., & Vicens, G. L. (1985). Spatially varying rainfall and flood risk analysis. J. Hydraul. Eng. ASCE, 111(5), 754-773. Broadbridge, P., & White, I. (1988). Constant rate rainfall infiltration: A versatile nonlinear model 1. Analytic solution. Water Resour. Res., 24, 145 -154. Bureau of Meteorology (1963). Report on development of a flood forecasting system for the Lower Macleay River Valley, NEW. Cadavid, L. J., Obeysekera, T., & Shen, H. W. (1991). Flood Frequency Derivation from Kinematic Wave. Jour. Hydraul. Eng. ASCE, 117(4), 489-510.

Page 172: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation R-3

Campbell, G. S. (1985). Soil Physics with BASIC. Elsevier, New York, 73-97. Carroll, D. G. (1991). Flood warning and monitoring in the Brisbane City area using event based radio telemetry systems. Unpublished MEngSc Thesis, QUT. Carroll, D. G. (1992). URBS, The urbanised catchment runoff model, Brisbane City Council. Carrol, D. G. (1994). The BCC catchment runoff routing model manual, version 3.3.: Brisbane City Council, Australia. Chander, S., & Shanker, H. (1984). Unit hydrograph based forecast model. Hydrol. Scien. Jour., 29(3), 279-291. Chapman, T. G. (1968). Catchment parameters for a deterministic rainfall-runoff model. Melbourne: In 'Land Evaluation', ed. G.A. Stewart, McMillan. Chapman, T. G. (1987). Unitgraph identification using only streamflow data. Civil Engineering Transaction, Institution of Engineers Australia, Vol. CE29, pp 187-191. Chapman, T. G. (1999). A comparison of algorithms for streamflow recession and baseflow separation, Hydrol. Process. 13, 701-714. Childs, E. C., (1969). An introduction to the physical basis of soil and water phenomena, John Wiley, New york, 210-212. Chu, S. T. (1978). Infiltration during a unsteady rain. Water Resour. Res., 14(3), 461-466. Clark, C. O. (1945). Storage and unit hydrograph. ASCE Trans., 110(1419-1446). Clark, R. D. S. (1980). Rainfall stream flow analysis to investigate spatial and temporal variability of rainfall excess generation. Jour. Hydrol., 47, 91-101. Cordery, I. (1968). Improved techniques in flood estimation. Intern. Assn. Hydrol. Sc., 140, 187 -195. Cordery, I. (1968). Initial loss for design flood estimation and flood forecasting. Flood Symposium, Sydney Division I.E. Aust and University of New South Wales, Sydney,. Cordery, I. (1970a). Antecedent wetness for design flood estimation. Civil Engineering Transactions, Institute of Engineers, Australia,, 12(2), 181 - 185. Cordery, I. (1970b). Initial loss for flood estimation and forecasting. Amer. Soc. Civil Engrs, Jour. Hydraulics Div (HY12), 96, 2447--2466.

Page 173: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation R-4

Cordery, I., &Webb, S.N. (1974). Flood estimation in Eastern New South wales – a design method, Civil Engg. Trans., Institution of Engineers, Australia., Vol CE 16, pp 87 – 93. Cordery, I., & Pilgrim, D. H. (1983). On the lack of dependence of losses from flood runoff on soil and cover characteristics. IAHS, 140, 187 - 195. Cordery, I., Pilgrim, D. H., & Doran, D.G. (1983) Some hydrological characteristics of arid western New South Wales . Hydrol. And Water Resour. Symp., Institution of Engineers, Australia, Natl. Confer. Publ. no. 86/13, pp 203 – 208. Corradini, C., Melone, F., & Ubertini, L. (1986). A semi-distributed adaptive model for real-time flood forecasting. Water Resour. Bull., 22(6), 1031-1038. Corraini, C., & Melone, F. (1986). An adaptive model for on-line flood predictions using a piecewise uniformity framework. Jour. Hydrol., 88, 365-382. Crapper, G. C. A. (1989). Development of areal-time reservoir routing flood warning procedure using the RORB model. Hydrol. and Water Resour. Symp. I.E. Aust, 89/19, 86-89. Crawford, N. H., & Linsley, R. K. (1966). Digital simulation in Hydrology: Stanford Watershed model IV, Technical Report 39. California: Stanford University. CSIRO, (1992). TOPOG user guide, version 4.0. CSIRO Division of Water Resources. Canberra. Dickinson, W.T., Holland, M.E., Smith, G.L. (1967). An experimental rainfall-runoff facility, Hydrology Paper no. 25, Colorado State University, 78 pp. DNRM, (2000). Department of Natural Resources and Mines. An index for stream gauging stations in Queensland. Dyer, B. G., Nathan, R. J., McMahon, T. A., & O'Neill, I. C. (1994). Development of regional prediction equations for the RORB runoff routing model.: CRC Report : 94/1. CRC for Catchment Hydrology, Monash University, Australia. Eagleson, P. S. (1972). Dynamics of flood frequency. Water Resour. Res., 8(4), 878-898. Flavell, D. J., & Belstead, B. S. (1986). Losses for design flood estimation in Western Australia. Hydrol. Water Resour. Symp., I. E. Aust., 86(13), 203 - 208. Gieseman, M. (1986). Melbourne's flood warning system. Flood warning in Australia. Centre for Resources and Environmental Studies, Canberra, 153-174. Goyen, A. G. (1983). A model to statistically derive design rainfall losses. Hydrol. and Water Resour. Symp. Hobart, 220-225.

Page 174: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation R-5

Green, W. H., & Ampt, C. A. (1911). Studies on soil physics; flow of air and water through soils. Jour.. Agricul. Sci., 4, 1-24. Hann, C. T. (1977). Statistical methods in Hydrology. Iowa State: The Iowa State University Press. Haan, C. T., & Schulze, R. E. (1987). Return period flow prediction with uncertain parameters. ASCE Trans., 30(3), 665-669. Hall, A.J. (1971). Baseflow recessions and the baseflow hydrograph separation problem . Hydrology Papers , The Institution of Engineers, Australia, pp. 159-170 Harvey, R. A. (1982). Estimation of the probable maximum flood - Western Australia. Proc. of the Workshop on spillway Design, Department of National Development and Energy. AWRC Conference series, 6, 157-176. Hill, P.I. (1993). Extreme flood estimation for the Onkaparinga River catchment, M. Eng. Science Thesis, Department of Civil and Environmental Engineering, University of Adelaide Hill, P. I., & Mein, R. G. (1996). Incompatibilities between storm temporal patterns and losses for design flood estimation. Hydrol. and Water Resour. Symp., Hobart, I.E. Aust., 2, 445 - 451. Hill, P. I., Maheepala, U. K., Mein, R. G., (1996). Empirical analysis of data to derive losses: methodology, programs and results, working document, CRC Report 96/5.CRC for Catchment Hydrology, Monash University, Australia. Hill, P. I., Mein, R. G., & Weinmann, P. E. (1996a). Testing of improved inputs for design flood estimation in South-Eastern Australia. CRC Report 96/6, CRC for Catchment Hydrology , Monash University, Australia. Hill, P. I., Maheepala, U. K., Mein, R. G., & Weinmann, P. E. (1996b). Empirical analysis of data to derive losses for design flood estimation in South-Eastern Australia.: CRC Report 96/5.CRC for Catchment Hydrology, Monash University, Australia. Hill, P. I., Mein, R. G., & Weinmann, P. E. (1997). Development and testing of new design losses For South-Eastern Australia. Hydrol. and Water Resour. Symp., I.E.Aust. Auckland:, 71 – 76. Hill, P. I., Mein, R. G., Siriwardena. (1998). How much rainfall becomes runoff? loss modelling for flood estimation. CRC Report 98/5, CRC for catchment hydrology, Monash University, Australia. Hino, M., Hasebe, M. (1985) Separation of a storm hydrograph into a runoff component by both filter separation AR method and environmental isotope tracers. Jour. of Hydrol., Vol. 85, pp. 251-264.

Page 175: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation R-6

Hoang, T. M. T., Rahman, A., Weinmann, P. E., Laurenson, E. M., & Nathan, R. J. (1999). Joint Probability description of design rainfalls. Hydrol. and Water Resour. Symp., Brisbane, I.E. Aust., 99(25), 379 - 384. Horton, R. E. (1940). An approach toward a physical interpretation of infiltration capacity. Proc. Soil. Sci. Soc., 5, 399 - 417. Hromadka, T. V. (1996a). Rainfall – Runoff probabilistic simulation program :1 synthetic data generation. Environmental Software, Elsevier Science Ltd, Great Britain, 11(4), 235 - 242. Hromadka, T. V. (1996b). A Rainfall - Runoff probabilistic simulation program :2 Synthetic data generation. Environmental Software, Elsevier Science Ltd, Great Britain, 11(4), 243 - 249. Hubber, W. C., Heaney, J. P., Nix, S. J., Dickenson, R. E., & Polman, D. J. (1982). Storm water management model user's manual.: Department of Environmental Engineering Sciences, University of Florida. Florida. Hubber, W. C., Cunningham, B. A., & Cavendor, K. A. (1986). Continuous SWMM modelling for selection of design events. Comparison of urban drainage models with real catchment data (C. Maksimocic & M. Radojkovic Ed. ). Yugoslavia: DubrovniK. Hughes, W. C. (1977). Peak discharge frequency from rainfall information. Jour. Hydraul. Div. ASCE, 103(1), 39-50. Hydsys (2002). Hydsys version 8.0, pluviograph data extraction software for PC, Hydsys Pty Ltd. Institution of Engineers Australia. (1958). Australian Rainfall and Runoff, Institution of Engineers, Australia. Institution of Engineers Australia. (1977). Australian Rainfall and Runoff, Institution of Engineers Australia. Institution of Engineers Australia. (1987). Australian Rainfall and Runoff, Institution of Engineers Australia. Institution of Engineers Australia. (1998). Australian Rainfall and Runoff, Vol, 1and 2, Institution of Engineers Australia. Institution of Engineers. Australia. (2001). Australian rainfall and Runoff, Institution of Engineers Australia. James, W., & Robinson, M. A. (1982). Continuous Models Essential for Detention Design. Engineering Foundation Conference, Amer. Soc. of Civil Eng., 163-175.

Page 176: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation R-7

James, W., & Robinson, M. A. (1986). Continuous deterministic urban runoff modelling. Comparison of urban drainage models with real catchment data (C. Maksimovic & M. Radojkovic Ed. ). Yugoslavia: Dubrovnik. Knee, R. (1986). Derived loss parameters in the A.C.T. First report. Hydrol. And Water Resour. Unit, Department of Territories, H.W.R. no. 86/15, September. Kobayashi, D. (1985). Separation of the snowmelt hydrograph by stream temperatures. Jour. of Hydrol., Vol.76, pp 155-162. Kobayashi, D. (1986). Separation of a snowmelt hydrograph by stream conductance. Jour. of Hydrol., Vol.84, pp 157-164. Kool, J. B., Parker, J. C., & Genuchten, M. T. (1985). Determining soil hydraulic properties from one-step outflow experiments by parameter estimation: 1. Theory of numerical studies. Soil Scien. Soc. Amer. Jour.., 49, 1348-1353. Kumar, S., & Jain, S. (1982). Application of SCS infiltration model. Water Resour. Bull., 18(3), 503-507. Laurenson, E., M., & Pilgrim, D., H. (1963). Loss rates of Australian catchments and their significance. I.E Aust., 35(1-2), 9 - 24. Laurenson, E. M. (1974). Modelling for stochastic-deterministic hydrologic systems. Water Resour. Res., 10/5, 955-961. Laurenson, E. M., & Mein, R. G. (1997). RORB version 4 runoff routing program user manual, Monash University, Australia. Linsley, R., & Crawford, N. (1974). Continuous simulation models in Hydrology. Geophysical Research Letters, 1(1), 59-62. Linsley, R. K., Kohler, M. A., & Paulhus, J. L. (1982). Hydrology for engineers. McGraw-Hill Co. ( Vol. 3). New York. Linsley, R. K., Kohler, M. A., & Paulhus, J. L. H. (1988). Hydrology for Engineers.: McGraw-Hill Book Company. Loy, A., Ayre, R. A., & Ruffini, J. L. (1996). Regional loss model relationships for catchments in South East Queensland. Hydrol. Water Resour. Symp. I.E. Aust. Hobart, 133-140. Lumb, A. M., & James, L. D. (1976). Runoff files for flood hydrograph simulation. Jour. Hydraul. Div. ASCE, 1515-1531. Lyne, V.D., (1979). Recursive modelling of sluggish and time varying streamflow responses, M. Eng., Science Thesis, Department of Civil Engineering, University of Western Australia.

Page 177: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation R-8

Lyne, V.D., and Hollick, M. (1979). Stochastic time variable rainfall runoff modelling. The Institution of Engineers, Australia, Hydrology and Water Resources Symposium, Perth, pp. 89-92 Maller, R. A., & Sharma, M. L. (1980). Time of ponding and areal infiltration from spatially varying parameters. Hydrol. Water Resour. Symp., I. E. Aust., 80(9), 162 - 165. Malone, T. (1999). Using URBS for real time flood modelling. Water 99 Joint Congress, Brisbane, 603-608. Manly, R. E. (1974). Catchment Models for River Management. Unpublished MSc Thesis, University of Birmingham. Mapinfo (1998). Mapinfo prefessional version 5.0, GIS software, Mapinfo corporation. Marivoet, J. L., & Vandewiele, G. L. (1980). A real-time rainfall runoff model. In Hydrological Forecasting. IAHS, 129, 409-418. Mein, R. (1999). Overview of the Flood Hydrology Program of the CRC for Catchment Hydrology. Hydrol. And Water Resour. Symp. I.E. Aust. Brisbane, 99(25), 173 - 177. Mein, R. G. (1980). Recent development in modelling of infiltration: Extension of the Green - Ampt model. Hydrol. Water Resour. Symp., I. E. Aust., 80(9), 23 -28. Mein, R. G., & Larson, C. L. (1971). Modelling infiltration during a steady rain. Water Resour. Res., 9(2), 384 - 394. Mein, R. G., Laurenson, E.M., & McMahon, T.A. (1974). “Simple nonlinear method for flood estimation. J. Hyd. Div. ASCE, Vol 100, No. HY11, pp 1507 – 1518. Moore, I. D., Larson, C. L., Slack, D. C., Wilson, B. N., & Idike, F. (1981). Modelling infiltration: A measurable parameter approach. Jour. Agri. Engg. Res., 25, 21-32. Moore, R. J. (1985). The probability-distributed principle and runoff production at point and basin scales. Hydrol. Scien., 30, 273-297. Nandakumar, N., Mein, R. G., & Siriwardena, L. (1994). Loss modelling for flood estimation - A Review. CRC Report 94/4, CRC for Catchment Hydrology, Monash University, Australia. Nathan, R. J. and McMahon, T.A.(1990), Evaluation of automated techniques for

baseflow and recession analysis, Water Resour. Res., 26 (7), 1465 – 1473. Natural Environment Research Council. (1975). Flood studies report. Hydrological Studies, London, 1.

Page 178: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation R-9

O'Loughlin, E.M., Cheny, N.P., Burns, J., (1982) The bushranger experiment; Hydrological response of a eucalypt catchment to fire. The First National Symposium of Forest Hydrology, Melbourne, I.E. Aust. Nat. Conf, Pub. No. 82/6, pp 132-138 O'Loughlin, G. (1988). The ILSAX Program for urban stormwater drainage design and analysis (Users Manual for microcomputer version V2.0): Sydney University of Technology. Onstad, C. A., Olson, T. C., & Stone, L. R. (1973). An infiltration model tested with monolith moisture measurements. Soil Science, 116(1), 13-17. Overney O. et al. (1995). Estimating expected flood values with Monte-Carlo Methods. Paper presented at the Bernier Conference, Paris. Pearse, M. A. (1997). A Joint Probability Approach to estimating the frequency of extreme precipitation for flood estimation. (PhD Thesis ): Monash University. Peck , E. L., Johnson, E. R., Krouse, K. M., & Carroll, T. R. (1980). Hydrological update techniques used by the US National Weather Service. Hydrological Forecasting, IAHS, 129, 419-424. Philip, J. R. (1957). The theory of infiltration, 1: The infiltration equation and its solution. Soil. Science, 77(2), 153 - 157. Philip, J. R. (1957a). The theory of infiltration, 4, sorptivity and algebraic infiltration equations, Soil. Science, 84(3), 257 – 264 Pilgrim, D., Huff, D., Steels, T (1979). Use of specific conductance and contact time relations for separating flow components in storm runoff. Water. Resour. Resear., Vol. 15, no.2, pp. 329-339 Pilgrim, D. H., & Robinson, D. K. (1988). Flood estimation in Australia - progress to the present possibilities for the future. Civil Eng. Trans., I.E. Aust., CE30(4), 187 - 206. Porter, J. W., & McMahon, T. A. (1971). A model for the simulation of stream flow data from climatic records. Jour. Hydrol., 13, 297-324. Queensland Water Resources Commission (1982). Private communication, W.D. Weeks, 17 December, 1982. Rahman, A. (1999). FORTRAN routines for determining derived flood frequency curve by Monte Carlo Simulation, Working Document. CRC for Catchment Hydrology, Monash University, Australia. Rahman, A., Hoang, T., Weinmann, P., & Laurenson, E. M. (1998). Joint Probability Approaches to design flood estimation. CRC Report 98/8, CRC for Catchment Hydrology, Monash University, Australia.

Page 179: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation R-10

Rahman, A., Weinmann, P. E., & Mein, R. G. (2000). The probabilistic nature of initial losses and its impacts on design flood estimates. Hydro. and Water Resour. Symp., Perth, I. E. Aust., 1, 71 -75. Rahman, A., Weinmann, P. E., Hoang, T., Laurenson, E., M, & Nathan, R. J. (2001a). Monte Carlo Simulation of flood frequency curves from rainfall. CRC Report 01/4. CRC for Catchment Hydrology, Monash University, Australia. Rahman, A., Weinmann, P. E., Hoang, T., Laurenson, E., M, & Nathan, R. J. (2001b). Monte Carlo Simulation of flood frequency curves from rainfall. Jour. Hydrol. Rajendran, R., & Mein, R. G. (1986). Determination of rainfall excess on spatially variable catchments. Jour. Hydraul., 83(1/2), 67 - 89. Renard, K. G., (1977) past, present and future water resources research in arid and semi-arid areas of the south western United States. Institution of Engineers, Australia, National conference, Pub., 77/5: 1 – 29. Richards, L. A. (1931). Capillary conduction through porous medium. physics, 1, 313-318. Ross, P. J. (1990a). Feeicient numerical methods for infiltration using Richards equation. Water Resour. Res., 26(2), 279-290. Ross, P. J. (1990b). SWIM - a simulation model for soil water infiltration and movement, . Queensland: CSIRO Divisions of Soils. Russell, S. O. (1977). A new method for computing design flows for urban drainage. Hydrol. Sym. Edmonton, Canada, 11, 188-197. Russel, S. O., Kenning, B. F. I., & Sunnell, G. J. (1979). Estimating design flows for urban drainage. Jour. Hydrau. Div., 105, 43-52. Sharma, M. L., Gander, G. A., & Hunt, C. G. (1980). Spatial variability of infiltration in a watershed. Jour. Hydrol., 45, 101 - 122. Sharma, M. L., & Seely, E. (1979). Spatial variability and its effect on areal infiltration. Hydrol. and Water Resour. Symp. I.E. Aust., 79(10), 69 - 73. Shirmohammadi, A., Knisel, W.G., and Sheridan, J.M. (1984) An approximate method for partitioning daily streamflow data. Jour. of Hydrol.Vol. 74, pp. 335-354. Simpson, R. J., Wood, T. R., & Hamlin, M. J. (1980). Simple self-correcting models for forecasting flow on small basins in real-time. Hydrological Forecasting, IAHS, 129, 433-443. Singh, V.P. (1989). Hydrological systems watershed modelling. (Prentice-Hall Inc. : New Jersey)

Page 180: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation R-11

Siriwardena, L., & Weinmann, P. E. (1996). Derivation of areal reduction factors for design rainfalls in Victoria. CRC Report 96/4, CRC for Catchment Hydrology , Monash University, Australia, 96(4), 60. Skaggs, R. W., & Khaleel, R. (1982). Infiltration in hydrologic modelling of small watershed. C.T. Haan, Amer. Soc. of Agricul. Eng., St. Joseph, MI, 121-166. Smith, R. E., & Hebbert, H. B. (1979). A Monte-Carlo analysis of the hydrologic effects of spatial variability of infiltration. Water Resour. Res., 15(2), 419-428. Srikanthan, R., & Kennedy, M. R. (1991). Rainfall antecedent to storm burst from which temporal patterns were derived for Australian Rainfall and Runoff. Hydro. and Water Resour. Symp., Perth, I. E. Aust., 19, 280 - 282. Srikanthan, R., Sooriyakumaran, P., & Elliott, J. F. (1997). Comparison of four real-time flood forecasting models. Hydrol. Water Resour. Symp. Auckland, 185-190. Terstriep, M. L., & Stall, J. B. (1974). The Illinios urban area simulator, ILLUDAS ( 58). Urbana: Illinios State Water Survey. Titmarsh, G. W., Pilgrim, D. H., Cordery, I., & Hoesein, A. A. (1989). An examination of design flood estimation using the US Soil Conservation Services Method. Hydrol.and Water Resour. Symp., 89/19, 241-247. Todd, D. K. (1980). Ground water hydrology, Wiley. New York. Tucci, C. M. E., & Clarke, R. T. (1980). Adaptive forecasting with a conceptual rainfall-runoff model. Hydrological Forecasting, IAHS, 129, 445-454. U.S. Soil Conservation Services. (1985). National Engineering Handbook, Section 4, Hydrology. Washington, D.C.: U.S. Department of Agriculture. Van Mullem, J. A. (1991). Runoff and peak discharges using Green-Ampt infiltration model. Jour. Hydraul. Engg., 117(3), 354-370. Viessman, W. J., Lewis, G. L., & Knapp, J. W. (1989). Introduction to Hydrology.: Harper Collins Publisher. Walsh, M. A., & Pilgrim, D. H. (1993). Re-assessment of some design parameters for flood estimation in New South Wales. Hydro. Water Resour symp., I.E. Aust., 93(14), 251-256. Walsh, M. A., Pilgrim, D. H., & Cordery, I. (1991). Initial losses for design flood estimation in New South Wales. Hydro. and Water Resour. Symp, Perth, I.E Aust., 19, 283 - 288. Waugh, A. S. (1991). Design losses in flood estimation. Hydrol. Water Resour. Symp., I.E. Aust., 12, 629 - 630.

Page 181: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Modelling losses in flood estimation R-12

Weinmann, E., Rahman, A., Hoang, T., Laurenson, E. M., & Nathan, R. J. (1998). A new modelling framework for design flood estimation. International Conference on Hydraulics in Civil Engineering, Adelaide, Australia, 393-398. Weinmann, P. E., Rahman, A., Hoang, T. M. T., Laurenson, E. M., & Nathan, R. J. (2000). Monte Carlo Simulation of flood frequency curves from rainfall - the way ahead. Hydrol. and water Resour. Symp., I. E. Aust., Perth, 1, 564-569. Weeks, W.D., Stewart, B.J. (1978). Linear and nonlinear runoff routing for ungauged catchments, Hydrology Symposium, I.E. Aust., National Conference Publication78/9, pp 124-128.

Page 182: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

APPENDIX A program sffor1 c ****************************************************** c This program is written by Mr.Mahbub Ilahee to format c the stream flow data received from Department of c Natural resources. So that this stream flow data can be c be used as a input file for loss computation in Design c Flood Estimation. Date 01/02/2002 c c ****************************************************** double precision x(500000),y(50000),qual(500000),sf(500000) integer jd(500000),jm(500000),jyr(500000),jh(500000) integer jq(500000) character*50 fn1,fn2 write (*,*)'Enter filename containing unformatted flow data' read(*,*)fn1 open(3, file=fn1,status='unknown') write (*,*)'Enter output filename containing formatted flow data' read(*,*)fn2 open(7, file=fn2,status='unknown') open(5,file='floint.out',status='unknown') i=1 5 read(3,*,end=10)x(i),y(i),qual(i) c write(*,*)x(i) c write(*,*)y(i) c write(*,*)qual(i) c write(*,555)x(i),y(i),qual(i) write(5,555)x(i),y(i),qual(i) i=i+1 goto 5 10 continue rewind(5) i=1 11 read(5,560,end=15)jd(i),jm(i),jyr(i),jh(i),sf(i),jq(i)

Modelling losses in flood estimation A-1

Page 183: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

c write(*,*)jq(i) c write(*,*)jm(i) c pause write(7,655)jyr(i),jm(i),jd(i),jh(i),sf(i),jq(i) i=i+1 goto 11 15 continue 555 Format(1x,f14.1,2x,f11.3,10x,f5.1) 560 Format(1x,i2,i2,i4,i2,6x,f9.3,5x,i3) 655 Format(14x,i4,i2,i2,i2,4x,f12.3,i4) close(3) close(5) close(7) stop end

Modelling losses in flood estimation A-2

Page 184: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

APPENDIX B program sffor2 c ****************************************************** c This program is written by Mr.Mahbub Ilahee to format c the stream flow data received from Department of c Natural resources. So that this formatted stream flow data c can be be used as a input file for loss computation in Design c Flood Estimation. Date 01/03/2002 c c ****************************************************** double precision x(500000),y(50000),qual(500000),sf(500000) integer jd(500000),jm(500000),jyr(500000),jh(500000) integer jq(500000) character*50 fn1,fn2, fn(50000) write (*,*)'Enter filename containing unformatted flow data' read(*,*)fn1 open(3, file=fn1,status='unknown') write (*,*)'Enter output filename containing formatted flow data' read(*,*)fn2 open(7, file=fn2,status='unknown') open(5,file='floint.out',status='unknown') i=1 5 read(3,*,end=10)x(i),y(i),fn(i),qual(i) c write(*,*)x(i) c write(*,*)y(i) c write(*,*)qual(i) c write(*,555)x(i),y(i),qual(i) write(5,555)x(i),y(i),qual(i) i=i+1 goto 5 10 continue rewind(5) i=1

Modelling losses in flood estimation B-1

Page 185: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

11 read(5,560,end=15)jd(i),jm(i),jyr(i),jh(i),sf(i),jq(i) c write(*,*)jq(i) c write(*,*)jm(i) c pause write(7,655)jyr(i),jm(i),jd(i),jh(i),sf(i),jq(i) i=i+1 goto 11 15 continue 555 Format(1x,f14.1,2x,f11.3,10x,f5.1) 560 Format(1x,i2,i2,i4,i2,6x,f9.3,12x,i3) 655 Format(14x,i4,i2,i2,i2,4x,f12.3,i4) close(3) close(5) close(7) stop end

Modelling losses in flood estimation B-2

Page 186: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

APPENDIX C program RAINDATA3 c ***************************************************** c Changing the rainfall data from horizontal form c to vertical form.This program is written by Mr.Mahbub c ilahee on 30/03/2002 c ***************************************************** integer m,n,jsn,jy,jm,jd,jh,jav,d1 real x(5000),Tr,c character*15 fn1,fn2 write (*,*)'Enetr input file:' read(*,*)fn1 Write(*,*)'Enetr output file' read(*,*)fn2 open(5, file=fn1, status='unknown') open(6, file=fn2, status='unknown') c write(6,*)'Daily Rainfall data' c write(6,*)'STN NO, YY, MM,DD,RAINFALL(mm)' c write(6,*) Do m=1,85 Do n=1,12 read(5,60,end=10)jsn,jy,jm,jd,jh,Tr,jav,(x(i),i=1,31) c write(*,100) jsn,jy,jm,jd,jh,Tr,jav,(x(i),i=1,31) c pause c write(*,*)'Daily Rainfall data' c write(*,*) if(jm .eq.4 .or. jm .eq. 6 .or. jm .eq. 9 .or. jm .eq. 11)then do i=1,30 write (6,200)jsn,jy,jm,i,x(i) enddo endif if(jm .eq.1 .or. jm .eq. 3 .or. jm .eq. 5 .or. jm .eq. 7 +.or. jm .eq. 8 .or. jm .eq. 10 .or. jm .eq. 12 )then

Modelling losses in flood estimation C-1

Page 187: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

do i=1,31 write (6,200)jsn,jy,jm,i,x(i) enddo endif c=MOD(jy,4) if (c .eq. 0) then d1=29 endif if (c .ne. 0) then d1=28 endif if (jm .eq. 2) then do i=1,d1 write (6,200)jsn,jy,jm,i,x(i) enddo endif c write(*,*)'STN NO, YY, MM, RAINFALL(mm)',jsn,jy,jm, c + (x(i), i=1,31) enddo enddo 10 write(*,*)'no data' close(5) close(6) 60 format(7x,i6,1x,i4,1x,i2,1x,i1,1x,i1,2x,f5.1,1x,i2, + 3x,f4.1,30(8x,f5.1)) 200 format(i6,x,i4,x,i2,x,i2,x,f5.1) c100 format(I6,4x,I4,2x,I2, 31(3x,/f5.1)) stop end

Modelling losses in flood estimation C-2

Page 188: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

APPENDIX D

program Icloss c A program to compute continuing loss, proportional loss c and volumetric runoff coefficient c written by Mahbub Ilahee at QUT 28/05/03 character*50 file2,file3,file5 integer iyr(300),im(300),id(300),ih(300) real x(300),y(300),u(300),v(300),z(300) real xsum,il,xsum1,A,PL,ROC,CL,CL1 real sf(300),hrf(300),w1 write(*,*)'Enter inputfile contains streamflow and pluvio data' read(*,*)file2 open(2,file=file2,status='old') write(*,*)'Put the value of fraction of baseflow' read(*,*)w1 write(*,*)'put the value of area, (A)' read(*,*)A Write(*,*)'Enter output filename containing baseflow data:' read(*,*)file3 open(3,file=file3,status='unknown') Write(*,*)'Enter output file contains IL,CL,CL1,PL,ROC,d1,d2' read(*,*)file5 open(5,file=file5,status='unknown') write (5,202)'yr','m','d','h','il(mm)','CL(mm/h)','PL','ROC', + 'j-1','j1-1','CL1(mm/h)','thresholdvalue=.01' write (3,201)'yr','m','d','h','sf','hrf','x','y', + 'z','u','v' c x(i)=the difference between the consecutive two c streamflow values c y(i)= x*fraction of the surface runoff (a) c z(i)=y(i)+y(i-1)(one timestep before) c u(i)= sf(i) if u(i)<0, otherwise u(i)=z(i) c v(i)=sf(i)-u(i)(surface runoff) c xsum = total rainfall c il = initial loss c reading streamflow and pluvio data xsum=0 il=0 xsum1=0

Modelling losses in flood estimation D-1

Page 189: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

i=1 k=1 30 read (2,*,end=21)iyr(i),im(i),id(i),ih(i),sf(i),hrf(i) if(hrf(i) .eq. -99.000)then n=i-1 write (3,*)'no of line=',n go to 21 else continue endif if(hrf(i) .eq. -1111.000)then n=i-1 c write (3,*)'no of line=',n c write(3,*) 'endfil' endfil=-1111.000 go to 21 else continue endif x(i)= (sf(i)-z(i-1)) y(i)=(sf(i)-z(i-1))*w1 z(i)=(z(i-1)+(sf(i)-z(i-1))*w1) if(y(i) .lt. 0)then u(i)=sf(i) else u(i)=z(i) endif v(i)=(sf(i)-u(i)) if (z(i-1) .gt. sf(i))then x(i)=0 y(i)=0 endif if (k .gt. 3)then go to 28 else if(sf(i)-sf(i-1) .lt. (0.00277*A)) then c if (sf(i) .lt. (.00277*A))then x(i)=0 y(i)=0 z(i)=sf(i) u(i)=sf(i) v(i)=0 else

Modelling losses in flood estimation D-2

Page 190: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

k=i if (i .eq. 1)then v(i)=0 x(i)=0 else continue endif c write(*,*)'start of surface runoff from line no =',k endif endif 28 xsum=xsum+hrf(i) write(3,100) iyr(i),im(i),id(i),ih(i),sf(i),hrf(i) +,x(i),y(i),z(i),u(i),v(i) i=i+1 go to 30 21 continue c q(i)=LOG10(ABS(sf(i))) c bf(i)=LOG10(ABS(u(i))) i=1 33 if (sf(i+1)-sf(i) .lt. (0.00277*A)) then v(i+1)=0 i=i+1 go to 33 else 34 if( v(i+1) .gt. 0 .or. v(i+2) .gt. 0 .or. v(i+3) .gt. 0 +.or. v(i+4) .gt. 0 .or. v(i+5) .gt. 0 + .or. v(i+6) .gt. 0) then xsum1=xsum1+v(i+1) i=i+1 go to 34 else xsum1=xsum1+v(i+1) endif endif i=1 45 if (sf(i+1)-sf(i) .lt. (0.00277*A))then i=i+1 go to 45 else j=1 55 if (hrf(i+1) .eq. -99.000)then hrf(i)=j else if(hrf(i+1) .gt. 0 .or. hrf(i+2) .gt. 0 .or. hrf(i+3) .gt. 0 +.or. hrf(i+4) .gt. 0 .or. hrf(i+5) .gt. 0 + .or. hrf(i+6) .gt. 0) then hrf(i+1)=j

Modelling losses in flood estimation D-3

Page 191: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

j=j+1 i=i+1 go to 55 else hrf(i+1)=j c continue endif endif endif i=1 11 if (sf(i+1)-sf(i) .lt. (0.00277*A))then i=i+1 go to 11 else j1=1 12 if (hrf(i+1) .eq. -99.000)then hrf(i)=j1 else if(v(i+1) .gt. 0 .or. v(i+2) .gt. 0 .or. v(i+3) .gt. 0 +.or. v(i+4) .gt. 0 .or. v(i+5) .gt. 0 + .or. v(i+6) .gt. 0) then v(i+1)=j1 j1=j1+1 i=i+1 go to 12 else v(i+1)=j1 c continue endif endif endif i=1 50 if (sf(i+1)-sf(i) .lt. (0.00277*A))then if (hrf(i+1) .eq. -99.)then il=il+hrf(i) go to 52 else il=il+hrf(i) i=i+1 go to 50 endif else il=il+hrf(i) endif c if there is no surface runoff then to calculate only Total c rainfall and initial loss

Modelling losses in flood estimation D-4

Page 192: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

52 if (PL .lt. 0)then PL=0 else if (CL .lt. 0)then CL=0 else if (CL1 .lt. 0)then CL1=0 else continue endif endif endif if(xsum .eq. il .or. xsum .eq. 0 .or. (j-1) .eq. 0 + .or. (j1-1) .eq. 0)then write(3,*)'Total rainfall =',xsum c Total volume of rainfall = xsum*1000*A write(3,*)'initial loss =',il c Total volume of il = il*1000*A PL=0.0 CL=0.0 CL1=0.0 write(3,*)'continuing loss =',CL write(3,*)'proportional loss =',PL write(3,*)'Contining loos upto surface runoff =',CL1 c write (5,203)iyr(i),im(i),id(i),ih(i),il,CL,PL,ROC,(j-1),(j1-1), c + CL1 go to 97 else continue endif CL= ((xsum*1000*A)-(il*1000*A)-(xsum1*60*60))/(A*1000* (j-1)) PL= 1-(xsum1*60*60)/(xsum*1000*A-il*1000*A) ROC= xsum1*60*60/(xsum*1000*A) CL1=((xsum*1000*A)-(il*1000*A)-(xsum1*60*60))/(A*1000* (j1-1)) if (PL .lt. 0 .or. CL .lt. 0 .or. CL1 .lt. 0)then c write (5,203)iyr(i),im(i),id(i),ih(i),il,CL,PL,ROC,(j-1),(j1-1), c + CL1 go to 97 endif write(3,*)'Total rainfall is =',xsum c Total volume of rainfall = xsum*1000*A write(3,*)'Initial loss=',il

Modelling losses in flood estimation D-5

Page 193: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

c Total volume of il = il*1000*A write(3,*)'Surface runoff=',xsum1*60*60 c Total volume of surface runoff = xsum1*60*60 m3 write(3,*)'remainder of the rain rr=',j-1 write(3,*)'Continuing loss CL=',CL write(3,*)'surface runoff finished after =',j1-1 write(3,*)'Continuing loss CL1=',CL1 write(3,*)'Proportional loss PL=',PL write(3,*)'Volumetric r.c. =',ROC c pause go to 137 97 if(endfil .eq. -1111.000)then go to 200 else xsum=0 xsum1=0 il=0 i=i+2 i=1 k=1 go to 30 endif 137 write (5,203)iyr(i),im(i),id(i),ih(i),il,CL,PL,ROC,(j-1),(j1-1), + CL1 go to 97 200 continue close(2) close(3) close(5) 100 format(i4,i3,i3,i3,2f8.3,5f8.3) 201 format(a4,3a3,2a8,5a8) 202 format(a4,a3,a3,a3,a8,a8,a8,a8,a6,a6,a10,a20) 203 format(i4,3i3,4f8.2,2i6,f8.2) stop end

Modelling losses in flood estimation D-6

Page 194: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

APPENDIX E PL = Proportional lossVRC = Volumetric runoff coefficient

Year month date hour IL(mm) CL(mm/h) PL VRC1968 2 6 6 84.47 0.08 0.46 0.09 PASCOE RIVER1970 3 28 12 75.26 0.39 0.87 0.021970 11 27 7 169.64 0.49 0.86 0.011971 4 2 9 114.15 3.12 0.96 0.011971 4 21 12 98.46 10.63 0.86 0.021972 4 12 18 84.63 3.45 0.77 0.171973 2 25 17 84.78 2.53 0.88 0.051973 3 13 2 24.35 0.84 0.83 0.111973 3 17 20 33.9 1.62 0.58 0.31973 3 20 23 1.27 5.22 0.7 0.31974 2 15 14 14.51 2.25 0.48 0.361975 2 11 18 10.71 12.85 0.9 0.091975 4 3 9 25.63 13.67 0.59 0.261975 4 4 15 38.34 2.83 0.7 0.231975 4 7 15 1.53 2.56 0.71 0.291975 12 21 17 37.61 0.4 0.97 01976 1 2 16 37.54 1.65 0.61 0.031976 1 5 1 4.54 2.01 0.9 0.091976 1 18 15 30.65 1.24 0.14 0.21976 2 18 6 28.69 0.87 0.46 0.291976 2 19 18 2.73 0.81 0.2 0.761976 4 8 16 0.63 8.35 0.81 0.191976 4 9 9 19.37 3.81 0.58 0.341976 4 10 9 8.14 1.43 0.24 0.611977 1 25 22 60.67 1.91 0.94 0.031977 3 15 19 38.34 0.37 0.17 0.321977 4 7 3 63.22 2.74 0.91 0.041977 4 13 20 50.83 8.95 0.97 0.031977 5 15 23 60.01 0.05 0.91 0.021978 2 20 14 50.33 1.86 0.84 0.11978 3 11 16 79.54 4.25 0.87 0.041978 4 1 15 48.51 1.67 0.94 0.041978 4 5 19 5.8 6.77 0.8 0.181978 4 7 2 86.84 0.5 0.37 0.181978 5 5 8 112.62 0.08 0.65 0.021979 1 7 16 28.8 2.72 0.91 0.071979 1 9 22 48.13 1.61 0.55 0.361979 2 17 8 64.63 0.47 0.88 0.021980 2 14 14 0.83 1.53 0.97 0.031980 3 15 1 11.88 8.73 0.85 0.131980 3 16 9 8.44 1.18 0.77 0.21980 3 20 14 50.79 0.08 0.08 0.241981 1 26 10 0.2 2.8 0.84 0.161981 3 4 15 1.1 7.46 0.89 0.11981 3 31 7 96.3 0.67 0.91 0.021982 1 10 20 43.86 1.4 0.97 0.011982 2 3 2 66.56 2.44 0.47 0.391982 3 20 14 3.29 3.71 0.71 0.281983 5 5 9 112.62 0.23 0.87 0.021984 2 11 19 44.15 0.95 0.9 0.021984 2 15 0 22.95 1.11 0.84 0.121984 2 23 16 30.85 1 0.31 0.261984 2 24 15 1.14 3.88 0.83 0.171984 3 2 15 23.59 4 0.8 0.121984 3 27 21 29.12 2.6 0.78 0.131985 3 20 23 17.87 3.15 0.91 0.061986 1 8 17 96.43 0.6 0.99 01986 1 14 8 52.89 4.03 0.94 0.011986 1 26 15 80.72 2.14 0.63 0.011986 3 20 3 94.02 0.11 0.9 0.01

Modelling losses in flood estimation E-1

Page 195: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1987 1 31 18 63.25 0.58 0.84 0.011988 3 9 4 62.02 5.56 0.95 0.041988 12 26 20 22.47 1.67 0.93 0.041989 4 6 16 14.22 2.91 0.86 0.111989 4 21 0 50.57 1.95 0.73 0.11990 1 23 9 174.88 0.52 0.31 0.11990 3 3 10 6.78 12.48 0.95 0.041990 5 3 0 49.12 0.05 0.15 0.191992 1 10 19 39 0.51 0.26 0.451992 3 2 0 52.05 1.71 0.41 0.041992 4 6 5 18.52 3.56 0.96 0.031992 12 22 0 36.77 2.41 0.89 0.11993 1 24 6 68.45 2.82 0.8 0.141994 1 30 6 123.24 0.59 0.9 0.011994 2 17 21 19.17 7.12 0.83 0.131994 2 23 20 39.29 1.15 0.64 0.211995 2 24 22 58.87 6.95 0.98 0.011995 3 16 21 12.83 7.73 0.96 0.031996 1 16 19 3.4 1.37 0.45 0.511996 2 14 14 24.88 3.33 0.8 0.151996 2 15 17 16.57 7.69 0.56 0.41996 3 10 11 6.06 2.37 0.69 0.311996 4 5 10 14.32 1.2 0.54 0.351997 2 14 1 0.64 1.18 0.94 0.051997 2 21 22 5.81 6.38 0.93 0.071997 2 23 1 0.86 0.14 0.09 0.91998 1 17 20 74.93 0.19 0.64 0.021998 2 2 8 71.63 0.17 0.83 01998 3 14 7 71.99 0.66 0.99 0.011998 3 19 3 118.49 0.67 0.37 0.091998 3 20 15 37.13 5.27 0.83 0.121999 11 25 16 87.77 8.29 1 02000 3 2 18 2.39 5.62 0.72 0.271971 4 10 20 78.3 5.88 0.59 0.2 STEWART RIVER1972 4 13 20 73.71 0.94 0.22 0.461973 2 22 18 3.89 6.59 0.96 0.031973 3 5 20 66.46 1.22 0.25 0.31973 3 8 13 13.23 1.42 0.42 0.481973 3 23 0 34.87 2.06 0.57 0.31973 11 21 20 42.17 0.9 0.24 0.271997 2 1 16 10.92 0.92 0.99 0.01 EAST NORMAN RIVER1997 3 3 17 18.39 1.43 0.95 0.041997 4 30 15 11.92 1.3 1 01998 3 17 21 16.35 3.07 0.94 0.06 ENDEAVOUR RIVER1998 12 31 15 114.03 0.57 0.9 0.021999 2 1 18 71.77 0.71 0.95 0.031997 2 1 21 12.24 0.94 1 0 ANNA RIVER1997 3 3 16 14 1.49 0.97 0.021997 3 21 23 36.46 2.63 0.9 0.091964 10 12 12 12.6 3.1 0.98 0.02 NORTH JOHNSTON RIVER1971 2 16 18 36.15 2.64 0.92 0.061972 1 8 5 108.55 1.7 0.98 0.011972 3 17 16 83.31 1.91 0.76 0.121973 2 9 16 63.49 0.3 0.59 0.081973 3 4 0 26.92 6.07 0.88 0.111973 12 12 8 36.21 2.69 0.6 0.271974 1 2 17 10.73 6.62 0.58 0.341974 2 10 14 21.75 2.15 0.66 0.241974 3 5 21 34.04 7.79 0.76 0.211974 3 22 4 26.08 5.08 0.79 0.171974 3 24 14 3.3 2.72 0.52 0.451974 3 27 23 11.52 7.29 0.77 0.21975 2 19 23 55.93 0.44 0.09 0.141975 3 6 2 59.66 1.65 0.85 0.071982 1 29 0 41.66 4.48 0.86 0.09 SOUTH JOHNSTON RIVER

Modelling losses in flood estimation E-2

Page 196: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1985 1 16 4 112.72 3.34 0.77 0.111985 2 13 19 31.52 2.68 0.88 0.111973 5 4 22 38.15 8.14 0.74 0.19 MURRAY RIVER1973 12 9 17 70.95 4.83 0.95 0.041975 1 15 23 51.45 5.66 0.95 0.041975 1 31 0 110.27 2.92 0.98 0.011975 2 8 22 38.51 5.71 0.88 0.071976 12 19 23 95.42 6.77 0.99 0.011977 1 31 3 42.94 8.44 0.84 0.131977 5 15 20 159.22 1.67 0.71 0.021978 1 31 5 104.1 0.92 0.86 0.031978 4 8 4 72.39 5.53 0.96 0.031979 1 25 9 18.85 5.14 0.9 0.091979 2 12 22 130.63 3.84 0.95 0.021979 12 29 1 69.94 2.52 1 01980 1 5 1 79.22 3.16 0.99 0.011984 2 8 22 97.19 4.74 0.88 0.081985 2 25 19 1.6 7.92 0.97 0.031988 12 27 20 18.02 2.23 0.88 0.111989 3 20 23 71.75 0.06 0.04 0.551992 2 25 13 25.08 7.93 0.93 0.061995 11 21 21 35.6 0.05 0.66 0.011997 3 3 14 2.07 5.13 0.62 0.371997 3 6 11 63.86 2.54 0.79 0.11998 12 30 18 65.75 0.16 0.88 01973 3 4 15 8.19 4.53 0.8 0.19 GOWRIE CREEK1973 12 9 8 14.86 2.63 0.9 0.091974 1 19 6 6.35 2.37 0.8 0.191974 2 3 21 0.5 2.69 0.21 0.791974 2 15 8 15.2 0.6 0.23 0.681974 3 3 1 73.6 1.99 0.64 0.181975 1 16 8 87.82 1.96 0.31 0.271975 12 11 3 0.94 1.76 0.4 0.591975 12 27 3 13.95 4.61 0.73 0.261976 2 6 22 4.97 6.07 0.83 0.161976 3 11 22 4.08 4.75 0.85 0.141976 4 10 8 2.6 2.89 0.72 0.271977 1 31 8 42.08 4.35 0.44 0.421977 2 5 21 7.65 2.5 0.55 0.441977 4 9 8 2.1 1.71 0.53 0.471978 2 27 9 1.03 4.17 0.42 0.571979 1 25 8 32.5 4.02 0.57 0.371979 2 1 16 7.71 1.6 0.29 0.651979 3 10 2 8.86 3.25 0.74 0.251979 12 29 2 66.29 2.22 0.79 0.131980 1 4 4 2.98 6.22 0.92 0.081980 3 18 6 67.35 2.18 0.34 0.451981 2 24 13 0.68 0.3 0.14 0.861981 5 20 0 7.26 1.83 0.62 0.351981 11 29 13 1.54 4.79 0.3 0.671982 1 28 8 104.23 2.92 0.75 0.11982 3 17 2 71.21 1.32 0.72 0.21982 4 14 18 40.7 1.76 0.38 0.491983 3 6 7 122.03 3.79 0.8 0.091983 3 8 6 47.11 8.82 0.86 0.131983 4 26 20 34.04 1.42 0.8 0.141985 2 5 11 21.74 2.61 0.95 0.041985 2 15 8 94.74 1.82 0.83 0.071985 3 24 17 24.62 1.56 0.62 0.251985 4 21 1 40.97 3.99 0.98 0.021987 3 26 11 107.46 1.62 0.29 0.091988 12 12 23 18.54 2.89 0.76 0.211988 12 28 22 6.78 3.97 0.7 0.291989 4 5 18 53.31 6.33 0.91 0.081989 11 22 12 6.44 3.04 0.5 0.47

Modelling losses in flood estimation E-3

Page 197: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1991 1 31 1 28.69 1.33 0.51 0.411991 2 11 1 0.3 3.08 0.19 0.811991 2 16 12 10.41 0.25 0.03 0.941992 12 19 18 83.24 2.32 0.98 0.011993 1 17 0 76.82 1.33 0.79 0.081993 1 30 7 155.01 1.41 0.64 0.051995 2 28 18 0.33 3.24 0.88 0.111996 1 7 5 54 0.41 0.95 0.011997 3 3 16 4.32 6.33 0.68 0.311997 12 29 14 45.71 4.22 0.73 0.181998 1 12 18 0.29 0.57 0.19 0.811998 1 26 19 46.88 3.7 0.53 0.181998 2 26 9 24.64 2.18 0.93 0.051998 12 10 19 29.17 9.81 0.99 0.011999 1 19 23 24.54 8.24 0.91 0.071999 2 11 10 105.59 2.7 0.42 0.481999 2 27 10 115.19 3.03 0.88 0.061999 11 18 22 0.81 10.29 0.78 0.222000 3 10 1 73.93 0.01 0 0.262000 3 16 13 3.71 2.5 0.63 0.372000 4 24 16 2.64 2.05 0.74 0.261968 2 12 15 15.56 0.11 0.06 0.75 BLUNDER CREEK1968 3 28 12 115.84 0.42 0.74 0.031969 2 19 12 71.87 2.66 0.69 0.211969 3 23 12 87.5 0.74 0.82 0.11970 4 19 1 78.25 0.68 0.84 0.041971 2 16 9 48.48 2 0.83 0.121971 3 10 22 116.25 1.34 0.81 0.11971 3 16 18 68.74 11.3 0.9 0.061971 3 30 9 50.87 1.87 0.74 0.21971 4 10 3 33.72 1.5 0.84 0.151972 3 17 15 13.26 3.78 0.78 0.21972 3 27 3 69.26 0.23 0.26 0.121972 5 5 12 68.54 1.75 0.91 0.051973 2 10 13 20.07 8.77 0.99 01973 2 21 9 35.06 0.07 0.44 0.041973 3 4 7 128.08 1.41 0.81 0.131973 4 6 6 73.34 0.59 0.87 0.061973 4 13 3 107.22 1.25 0.51 0.31973 12 10 14 124.7 1.73 0.83 0.121974 1 30 14 24.81 1.41 0.69 0.221974 2 5 16 1.92 3.26 0.61 0.381974 2 10 10 35.18 2.52 0.69 0.21974 3 17 4 90.83 1.37 0.65 0.231975 2 8 23 75.78 5.1 0.77 0.091975 3 6 9 18.16 1.29 0.41 0.541975 7 30 17 157.61 0.63 0.99 01975 9 8 6 68.66 0.81 0.96 0.021976 2 16 13 38.16 1.9 0.51 0.291976 2 24 16 49.43 1.57 0.64 0.211976 11 19 17 42.36 9.38 0.97 0.011977 1 31 14 137.98 2.67 0.85 0.021977 4 6 18 121.68 4.49 0.87 0.041977 4 13 14 159 0.5 0.72 0.051979 1 2 5 189.37 8.09 0.83 0.141979 1 11 6 60.96 1.91 0.67 0.241979 1 26 2 71.8 1.28 0.74 0.011979 1 29 1 17.78 2.21 0.83 0.141979 2 22 1 113.72 0.26 0.17 0.341979 3 5 17 19.7 6.9 0.98 0.011979 3 6 18 44.31 0.55 0.69 0.031979 7 17 10 62.51 0.74 0.81 0.011981 1 7 16 99.27 2.03 0.91 0.071981 2 6 17 34.27 1.25 0.73 0.111981 7 20 17 107.15 0.26 0.96 0.01

Modelling losses in flood estimation E-4

Page 198: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1981 9 15 7 78.28 0.66 0.85 0.031982 3 18 10 84.05 0.82 0.94 0.041982 4 1 15 90.19 1.63 0.82 0.121982 4 14 14 93.68 1.56 0.8 0.141973 2 6 3 51.09 1.99 0.89 0.04 STONE RIVER 1973 3 4 20 11.59 3.55 0.61 0.361973 12 12 10 114.68 0.54 0.93 0.021974 1 3 12 2.72 13.79 0.92 0.081974 3 2 23 23.77 1.89 0.83 0.141975 1 31 19 33.31 9.2 0.95 0.031975 3 29 10 31.21 4.49 0.92 0.051976 1 14 15 43.37 2.51 0.88 0.041977 1 31 0 18.32 3.9 0.89 0.091977 2 4 14 19.3 2.25 0.49 0.371977 3 3 22 7.73 3.53 0.72 0.271977 4 5 0 71.86 5.69 0.87 0.011977 5 15 3 42.84 2.64 0.74 0.181977 12 30 9 68.05 0.18 0.34 0.031978 2 27 18 80.33 4.34 0.87 0.081978 4 4 21 44.93 4.98 0.8 0.091979 2 1 16 0.26 6.34 0.95 0.051980 1 4 14 24.27 2.44 0.93 0.051980 3 18 13 53.62 6.88 0.87 0.081981 1 9 16 90.36 1.93 0.95 0.021981 2 3 16 1.61 0.39 0.17 0.811981 2 10 14 16.92 0.15 0.03 0.821981 2 24 10 11.86 1.65 0.74 0.231981 5 20 21 67.64 0.87 0.3 0.31982 2 21 10 0.51 3.41 0.97 0.021986 1 22 7 48 2.6 0.54 0.31986 2 27 22 1.14 2.89 0.64 0.351988 2 13 21 50.61 0.59 0.98 01989 3 6 3 62.01 0.78 0.87 0.011989 3 12 1 56.48 2.42 0.93 0.041989 3 20 23 71.36 2.61 0.65 0.21989 4 5 21 9.79 1.26 0.53 0.441990 3 20 19 85.39 2.03 0.67 0.191990 4 9 4 32.51 1 0.48 0.341990 4 17 13 23.22 2.8 0.63 0.321990 6 5 15 43.46 1.22 0.6 0.231991 2 1 2 7.03 0.09 0.03 0.911991 2 18 21 11.36 2.75 0.95 0.051992 2 26 18 31.89 4.79 0.84 0.141993 1 29 19 46.06 2.31 0.84 0.111994 2 21 2 30.25 14.52 0.97 0.031996 3 4 16 122.99 0.79 0.99 01997 3 22 18 13.29 4.12 0.53 0.451997 12 29 16 58.44 1.46 0.82 0.051998 1 8 11 19.19 6.1 0.77 0.221998 5 14 17 51.28 2.32 0.9 0.061998 11 24 18 33.23 3.39 0.29 0.291999 1 5 20 24.13 4.51 0.93 0.061999 11 4 6 9.72 2.9 0.99 0.011999 11 20 8 61.39 1.17 0.9 0.021999 11 27 1 69.98 1.95 0.84 0.081999 12 26 16 61.31 1.29 0.61 0.12000 2 6 0 22.04 5.28 0.86 0.132000 3 16 20 15.74 6.04 0.75 0.242000 4 3 12 46.03 2.54 0.7 0.181986 1 22 5 42.35 3.25 0.9 0.07 BOHLE RIVER1987 1 17 14 28.25 0.66 0.88 0.011987 12 25 16 27.12 0.7 0.96 01988 2 28 1 37.71 1.46 0.89 0.071988 12 10 3 0.2 4.17 0.42 0.581988 12 11 19 0.63 7.63 0.48 0.51

Modelling losses in flood estimation E-5

Page 199: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1988 12 27 21 0.7 3.35 0.53 0.471989 2 3 20 41.14 2.64 0.34 0.371989 3 20 18 17.53 2.76 0.7 0.261989 12 15 18 29.16 2.1 0.88 0.091990 3 21 19 38.58 4.54 0.64 0.191990 4 18 9 46.43 4.32 0.56 0.271990 6 5 14 31.99 2.37 0.78 0.151990 12 30 13 0.11 2.05 0.27 0.721991 2 2 16 10.59 1.2 0.3 0.671991 2 16 0 10.69 1.19 0.36 0.61991 2 18 22 46.01 2.34 0.24 0.631992 2 28 20 1.47 1.75 0.14 0.851994 1 30 23 28.44 1.99 0.68 0.261995 2 9 17 18.55 3.23 0.6 0.331996 1 6 7 93.2 2.17 0.68 0.21997 12 22 4 61.88 5.09 0.82 0.131998 2 25 9 34.41 1.44 0.96 0.031999 2 27 17 39.57 1.64 0.43 0.371981 1 16 1 10.27 1.16 0.7 0.27 MAJOR CREEK 1981 1 20 3 15.45 1.2 0.49 0.441981 2 22 22 55.24 1.13 0.72 0.021981 5 21 2 79.87 0.33 0.17 0.191974 1 1 21 21.47 2.07 0.98 0.01 BROUGHTON RIVER1974 1 13 19 11.44 1.63 0.77 0.151974 1 14 14 8.81 2.09 0.72 0.221974 1 15 17 3.86 2.06 0.81 0.181974 4 26 2 23.9 5.17 0.6 0.211975 1 10 10 15.42 0.48 0.08 0.391975 1 12 16 2 2.16 0.65 0.331975 10 23 14 36.49 1.14 0.99 01975 11 8 23 21.24 2.7 0.7 0.111977 5 15 13 3.52 3.26 0.88 0.111978 1 31 13 71 0.29 0.48 01979 2 1 18 14.1 8.39 0.96 0.031980 2 24 16 18.42 2.92 0.97 0.021980 2 29 17 32.44 1.41 0.94 0.011980 3 3 21 12.76 1.86 0.88 0.091980 3 5 15 10.57 2.48 0.92 0.051980 4 23 21 36.11 0.16 0.73 0.011981 4 9 2 58.28 1.54 0.98 01981 5 21 2 67.27 1.35 0.88 0.021993 1 11 6 123.37 2.38 0.95 0.02 BROKEN RIVER1993 2 15 17 99.8 1.08 0.8 0.071994 2 1 17 85.73 0.86 0.37 0.221994 3 4 0 40.4 0.67 0.87 0.041998 8 28 21 82.79 9.11 0.65 0.291999 1 14 14 31.87 0.56 0.42 0.121999 2 10 19 69.1 0.74 0.78 0.071999 2 14 15 32.4 1.7 0.71 0.231999 12 25 17 39.44 2.71 0.84 0.132000 4 2 6 64.26 4.37 0.55 0.362000 5 3 7 29.35 2.78 0.87 0.111973 12 18 6 53.71 4.72 0.62 0.34 ST. HELENS CREEK1974 1 1 3 28.17 0.7 0.22 0.691974 1 17 11 11.56 3.43 0.68 0.311974 11 15 22 113.48 1.51 0.93 0.021975 1 14 23 14.21 6.04 0.71 0.281975 3 5 15 66.52 4.38 0.8 0.151975 9 10 5 154.62 0.47 0.82 01975 12 10 11 122.32 3.98 0.64 0.271976 1 28 18 46.75 1.62 0.59 0.31976 5 14 16 113.87 1.21 0.97 0.011977 1 19 22 18.54 0.33 0.18 0.551970 1 18 14 99.56 13.11 0.9 0.08 BLACKS CREEK1970 2 4 15 70.42 1.84 0.9 0.06

Modelling losses in flood estimation E-6

Page 200: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1971 2 20 16 68.73 8.49 0.89 0.071971 3 6 18 64.66 2.95 0.86 0.091971 12 24 3 143.57 4.78 0.87 0.071972 1 1 22 29.86 12.33 0.99 01972 1 8 4 7.2 2.43 0.79 0.191973 12 18 14 8.35 4.02 0.94 0.061974 1 3 0 53.63 3.65 0.99 0.011974 1 5 16 0.8 2.7 0.95 0.051974 1 14 9 4.78 3.55 0.96 0.041974 1 17 17 2.27 13.54 0.93 0.071974 1 29 17 38.29 3.75 0.95 0.031974 2 16 18 20.7 2.49 0.99 0.011974 2 28 16 32.45 3.15 0.87 0.121975 12 10 20 138.58 4.67 0.97 0.021975 12 22 1 110.46 0.46 0.44 0.051976 2 6 5 42.99 1.34 0.97 0.021976 3 3 19 36.79 0.82 0.5 0.091976 3 4 22 8.07 5.42 0.62 0.361977 2 1 0 76.99 4.11 0.88 0.071977 3 7 17 11.29 4.56 0.93 0.061978 1 30 20 144.39 3.94 0.96 0.031979 1 26 8 57.63 3.08 0.98 0.021979 2 13 5 36.7 4.37 0.85 0.111979 3 8 19 81.3 1.71 0.97 0.021980 1 6 10 62.29 15.39 0.98 0.021980 2 10 14 117.95 1.65 0.86 0.021981 1 19 23 66.13 2.23 0.91 0.051981 5 21 3 77.85 5.05 0.97 0.011983 3 5 22 125.2 0.22 0.98 01983 5 20 5 39.7 1.75 0.95 0.041983 11 17 3 70.6 0.23 0.97 01984 1 14 23 40.07 1.73 0.96 0.031985 3 12 15 80.14 2.19 0.96 0.031972 5 10 23 31.85 0.56 0.47 0.11 SANDE CREEK1973 1 14 0 46.72 0.18 0.18 0.021973 12 19 12 19.65 8.97 0.89 0.11974 1 8 21 3.84 3.64 0.87 0.111974 12 28 16 26.46 4.67 0.96 0.031975 1 2 14 13.52 2.51 0.82 0.161975 2 25 9 23 2.66 0.82 0.131975 3 18 15 29.67 2.71 0.39 0.331975 12 21 14 39.53 2.46 0.87 0.091976 2 2 15 12.78 1.57 0.35 0.51976 10 31 20 6.12 8.99 0.75 0.211977 2 24 23 29.02 3.41 0.93 0.031978 1 31 16 97.04 2.69 0.7 0.21979 3 10 17 85.67 1.56 0.92 0.031967 6 21 14 48.2 0.24 0.92 0.01 MONAL CREEK1968 1 13 10 3.25 1.21 0.93 0.071969 12 7 18 26.15 0.85 0.88 01970 12 9 9 3.03 9.12 1 01971 1 22 18 2.71 6.35 0.86 0.131971 1 30 8 46.28 0.45 0.24 0.361971 2 3 16 10.79 2.57 0.27 0.531971 2 4 15 7.56 1.2 0.13 0.681971 2 7 19 15.36 1.27 0.34 0.491971 2 8 18 4.34 1.24 0.41 0.511971 2 21 11 25.66 1.03 0.65 0.261971 11 29 16 39.24 0.18 0.76 01973 7 8 9 40.58 4.6 0.86 0.1 GREGORY RIVER1973 12 20 14 123.05 5.27 0.83 0.051974 1 26 20 33.42 1.1 0.33 0.571974 11 24 22 50.94 0.12 0.96 01976 1 19 8 19.81 2.48 0.63 0.291976 2 22 5 26.19 1.86 0.59 0.27

Modelling losses in flood estimation E-7

Page 201: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1976 3 5 7 3.57 2.64 0.54 0.441977 11 18 15 26.07 28.74 0.98 0.011967 1 28 21 37.51 1.02 0.38 0.44 MARY RIVER1967 6 26 6 15.13 0.42 0.15 0.681968 1 9 0 126.09 1.68 0.38 0.521971 2 18 6 57.86 0.67 0.19 0.651971 11 29 7 72.09 0.53 0.99 01971 12 27 17 112.21 0.77 0.56 0.151972 1 25 19 24.86 3.06 0.76 0.061972 2 18 23 16.88 0.48 0.21 0.61972 4 2 5 1.13 1.12 0.13 0.871972 11 11 14 35.73 2.62 0.41 0.281973 2 11 23 52.36 3.72 0.49 0.121973 2 23 17 32.33 2.01 0.53 0.151973 7 4 10 0.6 1.63 0.39 0.611974 1 12 12 8.41 0.89 0.77 0.21974 1 24 12 49.04 3.3 0.61 0.351974 3 9 8 23.66 0.81 0.42 0.451974 11 18 9 52.51 0.84 0.51 0.31976 2 11 18 21.42 4.01 0.32 0.531976 5 22 9 2.74 0.27 0.14 0.831978 3 31 22 21.56 2.1 0.88 0.081978 11 10 16 29.95 0.1 0.42 0.071981 2 14 23 56.45 0.63 0.24 0.51981 5 21 16 27 2.21 0.69 0.211983 6 21 9 1.98 0.24 0.04 0.95 NORTH MAROOCHY RIVER1983 11 21 4 57.23 0.62 0.29 0.451986 11 30 0 17.82 1.02 0.44 0.481987 10 16 15 68.8 3.71 0.68 0.161987 12 1 3 58.14 0.52 0.19 0.381988 4 4 19 13.47 2.37 0.71 0.271988 7 2 17 20.57 0.76 0.32 0.621989 2 22 3 21.71 2.24 0.44 0.31989 3 30 16 104.36 2.4 0.4 0.51989 8 18 9 1.52 1.59 0.44 0.551997 3 5 14 52.16 1.08 0.27 0.611997 5 1 8 113.26 0.23 0.94 0.021997 10 8 2 42.56 0.27 0.74 0.021997 10 20 0 42.87 1.27 0.9 0.041997 12 28 21 65.08 0.16 0.84 0.031998 1 28 14 93.32 0.42 0.44 0.241998 12 31 15 35.76 0.61 0.85 0.111999 2 7 11 14.13 1.11 0.33 0.651999 2 28 10 61.94 1.1 0.47 0.411999 3 18 7 18.23 0.43 0.69 0.271999 5 9 14 41.98 2.8 0.76 0.191999 5 18 19 14.52 0.7 0.46 0.51969 8 27 1 62.4 0.93 0.64 0.15 BREMER RIVER1970 12 7 3 62.29 1.83 0.57 0.251971 1 31 1 23.18 1.39 0.41 0.541971 2 3 11 0.24 2.63 0.6 0.41972 10 19 0 39.13 12.55 0.97 0.021972 10 28 1 25.75 0.2 0.13 0.611973 2 17 12 10.65 0.85 0.61 0.311974 1 9 23 25.99 0.74 0.47 0.351974 11 19 15 14.14 2.47 0.72 0.211975 2 24 22 116.98 1.81 0.71 0.091975 10 20 3 72.35 1.06 0.61 0.081975 12 19 20 45.31 0.32 0.27 0.521976 1 20 12 28.23 0.19 0.11 0.581977 5 10 22 35.82 1.95 0.39 0.181979 11 24 17 4.95 2.36 0.28 0.611980 2 5 21 49.01 0.09 0.25 0.051980 5 9 12 111 0.05 0.13 0.041981 2 7 6 70.38 1.43 0.4 0.33

Modelling losses in flood estimation E-8

Page 202: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1983 1 3 6 42.8 1.33 0.75 0.031983 5 1 2 23.2 1 0.45 0.461983 5 27 11 23.25 0.63 0.14 0.681983 6 18 15 28.17 1.17 0.48 0.211983 6 21 11 15.39 0.65 0.27 0.611983 11 27 19 0.4 1.25 0.6 0.41984 7 26 16 30.89 0.69 0.32 0.41984 11 5 13 9.95 2.86 0.52 0.351986 11 30 23 66.75 0.02 0.18 01987 1 27 20 39.16 3.69 0.82 0.091987 10 16 15 74.28 1.19 0.42 0.161987 12 1 15 23.92 0.88 0.26 0.391988 2 14 16 82.74 0.41 0.73 01989 4 2 10 85.89 2.48 0.61 0.181989 5 16 16 39.04 0.34 0.31 0.291989 12 5 13 55.23 2.79 0.95 0.011990 1 15 20 44.14 0.47 0.35 0.091990 2 3 4 55.01 3.88 0.99 01990 2 6 20 24.46 9.44 0.88 0.041969 1 1 21 99.85 0.09 0.93 0 TENHILL CREEK1971 2 7 15 21.1 0.19 0.74 0.011971 11 28 21 34.95 1.49 1 01976 2 10 17 58.28 1.27 0.48 0.281976 10 31 21 44.38 0.89 0.74 0.061979 6 21 8 89.19 0.64 0.7 0.041981 2 7 7 104.39 2.12 0.71 0.11981 12 3 14 20.16 1.26 0.87 0.051982 1 21 3 51.84 0.37 0.45 0.041982 2 24 17 75.96 0.48 0.9 01983 5 3 1 81.99 1.7 0.52 0.051983 5 27 18 29.6 2.68 0.84 0.091983 6 21 22 6.86 3.9 0.86 0.131985 1 23 18 28.33 1.49 0.98 0.011988 4 5 11 14.55 0.83 0.7 0.241988 7 5 8 27.51 0.07 0.05 0.541990 5 22 21 58.44 0.64 0.74 0.051990 5 28 0 42.57 1.44 0.88 0.011991 12 12 11 125.46 0.02 0.04 0.051992 2 9 21 15.41 7.58 0.94 0.061995 11 20 8 42.21 2.51 0.97 0.011996 1 10 5 53.69 0.09 0.25 0.021999 2 9 3 97.67 1.34 0.89 0.031999 3 3 17 35.68 0.01 0.1 0.011978 3 21 15 0.2 2.91 0.51 0.49 LOGAN RIVER1978 4 2 9 5.79 0.1 0.03 0.781978 12 29 16 7.51 2.73 0.35 0.521979 3 4 13 47.99 0.73 0.97 0.011979 6 20 20 62.74 1.12 0.51 0.231979 11 20 18 16.46 6.24 0.94 0.041979 12 15 22 13.98 2.46 0.36 0.481981 2 5 23 13.98 2.73 0.89 0.11981 11 2 22 10.9 0.84 0.45 0.431982 2 24 23 83.07 0.53 0.32 0.081983 3 20 23 43.64 3.08 0.91 0.041983 5 1 9 32.41 0.79 0.29 0.561983 7 29 4 34.02 1.18 0.76 0.091983 10 15 20 0.65 9.63 0.82 0.181983 11 21 6 35.52 0.57 0.37 0.131985 4 3 16 38.99 0.41 0.69 0.021986 10 1 16 47.49 3.09 0.92 0.031987 12 1 20 64.7 3.62 0.74 0.051988 4 5 7 6.5 0.15 0.09 0.821988 7 4 21 32.28 1.13 0.28 0.571989 3 26 3 22.89 0.6 0.7 0.191989 4 1 14 25.12 0.7 0.27 0.58

Modelling losses in flood estimation E-9

Page 203: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1989 5 15 23 1.48 0.42 0.19 0.791989 11 9 20 72.79 3.95 0.56 0.071989 11 11 23 26.33 1.77 0.77 0.031989 12 5 1 11.83 0.97 0.3 0.571990 1 15 20 38.56 0.19 0.22 0.11990 2 7 21 9.8 3.56 0.93 0.051991 1 26 19 29.35 1.38 0.74 0.151991 2 7 1 69.39 18.31 0.36 0.511991 2 7 16 8.29 6.66 0.43 0.551991 2 8 17 22.67 0.07 0.13 0.131991 12 12 3 77.55 4.14 0.61 0.251995 1 20 22 54.75 0.38 0.46 0.041995 2 17 19 25.46 5 0.93 0.041995 3 9 19 40.62 0.35 0.82 01996 7 28 4 44.57 1.06 0.63 0.011996 8 30 18 49.56 0.8 0.7 0.041996 12 7 17 27.39 2.35 0.88 0.071997 2 14 19 99.01 1.81 0.44 0.311997 12 23 22 52.51 2.76 0.27 0.121998 1 30 13 17.89 2.29 0.97 0.031978 1 28 16 34.29 3.36 1 0 RUNNING CREEK1978 3 21 16 0.76 3.75 0.45 0.551978 11 5 22 43.86 0.15 0.27 0.051978 12 26 22 38.19 1.53 0.84 0.051979 3 4 20 49.31 0.09 0.76 0.011979 6 21 2 80.57 0.32 0.64 0.041979 11 20 21 37.22 8.1 0.95 0.011979 12 24 18 39.51 1.91 0.87 0.031980 12 31 18 36.57 0.41 0.81 0.041981 2 6 18 33.43 2.2 0.82 0.131981 4 4 19 34.15 5.44 0.98 0.011982 1 20 16 22.81 0.88 0.43 0.331983 5 1 16 34.72 1.88 0.6 0.311983 6 21 13 16.55 1.22 0.36 0.541983 11 16 3 46.63 0.17 0.63 0.021984 3 3 19 47.2 1.83 0.99 01984 4 8 14 14.33 10.17 0.42 0.511989 1 6 23 1.78 0.01 0.16 0.191989 12 24 19 0 0.03 0.66 0.341995 3 1 21 0.64 0.08 0.62 0.141978 3 21 19 29.41 2.99 0.77 0.13 TEVIOT BROOK1978 4 2 9 5.79 1.74 0.45 0.441978 12 29 16 7.51 6.42 0.82 0.141979 6 20 15 45.49 1.8 0.75 0.161979 11 19 19 32.62 0.18 0.64 01979 11 20 20 26.62 6.99 0.9 0.031979 12 15 20 13.73 4.62 0.99 0.011980 2 5 20 51.27 0.09 0.16 0.051980 5 28 16 34.18 0.71 0.28 0.131981 2 7 13 91.9 1.18 0.5 0.121981 4 4 17 25.81 2.1 0.89 0.051981 11 2 14 3.55 0.63 0.4 0.561982 12 31 21 31.72 0.7 0.94 01983 5 1 6 25.28 0.69 0.25 0.621983 10 15 23 65.99 3.39 0.79 0.041987 1 2 17 1.5 3.73 0.85 0.141987 1 27 22 31.86 0.8 0.69 0.061987 3 3 6 53.58 0.71 0.82 0.021988 4 3 18 26.46 1.01 0.15 0.631988 4 5 5 6.46 1.32 0.98 0.021988 7 4 21 32.28 0.47 0.12 0.71989 3 26 7 33.9 0.01 0.02 0.421989 4 1 16 29.98 0.14 0.07 0.661989 10 27 5 40 0.81 0.99 01990 2 7 21 9.8 3.59 0.94 0.04

Modelling losses in flood estimation E-10

Page 204: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1990 4 20 11 5.42 0.75 0.3 0.621990 12 21 20 31.75 0.22 0.97 01991 2 7 16 8.29 5.89 0.43 0.551991 12 12 1 61.21 2.92 0.42 0.411991 12 31 21 31.87 0.05 0.35 01995 2 17 20 41.64 0.29 0.2 0.11995 12 5 23 27.04 0.98 0.66 0.031995 12 23 15 35.93 0.54 0.69 0.041997 2 14 18 81.43 2.32 0.57 0.261998 1 30 5 14.7 1.24 0.65 0.291999 1 9 19 27.13 2.41 0.72 0.121999 3 3 12 4.77 3.15 0.47 0.451973 2 14 12 11.27 0.93 0.76 0.17 ALBERT RIVER1973 7 6 15 55.76 2.59 0.7 0.241974 1 24 23 137.95 6.95 0.7 0.251974 3 10 14 43.46 0.99 0.57 0.31974 4 21 19 10.17 0.39 0.87 0.041975 1 8 14 14.06 1.48 0.44 0.491975 2 24 21 110.27 0.61 0.07 0.511976 2 10 23 3.13 0.26 0.11 0.861976 2 27 23 30.46 2.15 0.96 0.011977 3 2 13 0.59 0.62 0.99 0.011978 12 23 13 5.69 2.39 0.98 0.021978 12 26 4 51.48 0.69 0.27 0.351981 2 4 18 11.08 2.57 0.59 0.381981 2 6 23 36.89 2.99 0.95 0.031981 5 21 8 165.84 0.4 0.34 0.111981 11 3 12 16.11 2.08 0.89 0.041981 12 3 18 25.84 1.3 0.61 0.321982 1 19 0 6.63 2.17 0.95 0.041982 3 15 13 1.77 0.69 0.44 0.261982 12 13 22 56.6 0.34 0.19 0.151983 5 27 13 131.03 0.18 0.11 0.271983 6 21 16 35 1.14 0.47 0.331989 5 27 2 93.63 1.67 0.93 0.031990 3 27 20 51.67 2.6 0.58 0.311990 4 4 19 12.84 0.56 0.28 0.461990 5 22 9 35.1 1.07 0.51 0.281990 5 27 12 94.19 1.21 0.83 0.041990 6 7 4 165.02 4.36 0.83 0.071991 12 12 11 70.31 2.47 0.88 0.051992 3 16 12 58.75 0.17 0.73 0.021994 3 1 5 75.07 0.12 0.6 0.061995 11 20 20 81.15 0.19 0.3 0.211996 1 3 16 88.91 0.1 0.67 0.011997 5 5 11 59.23 0.36 0.92 01997 5 17 0 9.32 0.49 0.49 0.241978 3 17 3 12.44 2.83 0.84 0.15 BACK CREEK1978 12 26 21 3.6 0.74 0.71 0.21979 12 16 2 0 0.52 0.86 0.141980 5 6 19 8.13 2.45 0.58 0.411981 11 2 12 12.49 2.53 0.93 0.061982 10 10 13 0 2.92 0.98 0.021987 3 5 6 49.55 2.82 0.78 0.141989 4 3 14 0.42 2.39 0.56 0.431991 11 30 18 0 1.64 0.99 0.011995 2 14 18 6.08 1.62 0.78 0.21970 10 24 16 28.02 1.48 0.85 0.05 MACINTYRE BROOK1970 12 9 9 0.31 3.11 0.84 0.161974 10 30 22 25.1 0.55 0.97 0.011974 11 1 19 2.7 1.55 0.78 0.211974 11 18 23 28.91 1.98 0.76 0.121975 2 24 14 88.38 1.55 0.78 0.021975 3 17 17 0.79 2.26 0.87 0.131975 12 23 13 93.34 5.52 0.82 0.03

Modelling losses in flood estimation E-11

Page 205: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1976 2 10 10 90.65 2.51 0.57 0.221978 9 6 21 54.99 0.69 0.86 0.031982 12 2 21 17.87 10.14 0.96 0.031983 5 1 10 31.52 1.4 0.61 0.291984 2 17 19 2.54 5.29 0.92 0.071984 4 8 16 88.11 1.5 0.46 0.071987 1 27 16 28.55 4.39 0.82 0.131988 4 3 16 19.11 2.36 0.67 0.211988 4 11 4 22.97 0.18 0.1 0.391989 3 26 11 47.25 1.09 0.78 0.121990 4 20 16 29.55 3.4 0.63 0.221991 2 7 20 35.65 0.59 0.72 0.111994 2 19 23 59.13 0.68 0.83 01995 2 17 19 7.55 3.91 0.97 0.021995 2 18 17 16.24 15.06 0.81 0.171995 10 26 4 5.28 4.57 0.98 0.021995 11 19 22 44.05 0.93 0.67 0.151996 1 9 0 47.18 0.15 0.21 0.221996 1 22 4 28.46 0.34 0.53 0.231996 5 2 12 83.54 2.8 0.7 0.131997 12 15 2 40.41 0.05 0.52 0.01 SPRING CREEK1998 7 24 21 0.5 1.76 0.99 0.011998 11 23 13 0.24 0.95 0.94 0.061999 1 28 14 5.94 0.33 0.94 0.051999 6 27 13 2.64 0.53 0.93 0.061999 11 6 22 16.06 0.93 0.99 0.011970 12 9 9 0.31 2.24 0.73 0.27 CANAL CREEK1972 10 28 13 0.07 3.56 0.94 0.061973 11 22 2 30.7 3.76 0.88 0.011974 11 1 18 3.05 1.64 0.73 0.251974 11 18 23 19.28 2.57 0.76 0.161975 2 24 14 104.29 2.56 0.81 0.021975 3 17 17 0.97 2.73 0.85 0.141975 12 23 13 116.41 6.84 0.81 0.031976 2 10 9 50.01 1.3 0.31 0.451978 4 2 11 46.26 0.39 0.92 01978 9 6 21 53.63 0.51 0.72 0.061982 12 2 21 14.03 6.12 0.92 0.051983 5 1 10 36.15 0.67 0.31 0.491983 5 27 15 12.54 1.32 0.39 0.451983 6 21 16 27.66 0.6 0.47 0.311984 4 8 16 85.01 0.18 0.07 0.11984 9 4 21 13.93 1.67 0.78 0.091987 1 27 16 9.24 0.37 0.21 0.551988 4 3 15 12.55 1.91 0.51 0.371988 4 11 4 26.66 1.1 0.29 0.41989 3 26 11 51.72 0.36 0.41 0.231989 12 22 3 27.25 0.13 0.19 0.281990 4 20 16 24.24 1.58 0.31 0.431990 5 22 14 22.72 0.85 0.51 0.251995 2 17 19 8.56 3.33 0.96 0.031996 1 9 0 17.71 0.29 0.32 0.391996 5 2 12 77.66 2.38 0.58 0.191978 11 5 23 30.98 0.36 0.94 0 CADAMINE RIVER1979 6 21 7 75.83 0.33 0.55 0.041980 2 5 19 39.38 0.56 0.99 01980 5 9 11 89.35 0.08 0.17 0.081981 12 3 10 8.99 3.2 0.87 0.091983 5 1 13 61.09 2.27 0.87 0.081983 5 27 16 20.58 0.51 0.46 0.371986 12 25 9 40.51 0.74 1 01987 5 15 11 20.84 1.17 0.79 0.141987 12 1 14 79.12 2.73 0.74 0.081988 4 1 3 85.87 1.27 0.8 0.121989 11 17 21 12.69 2.49 0.69 0.2

Modelling losses in flood estimation E-12

Page 206: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1990 4 5 10 54.14 0.5 0.68 0.051990 4 20 21 44.63 0.92 0.65 0.061991 12 31 5 24.47 0.45 0.86 01995 11 20 17 85.14 0.46 0.76 0.021996 12 12 3 30.94 1.42 0.92 0.011997 11 3 17 38.83 0.14 0.28 0.031998 1 30 22 41.23 1.02 0.94 0.021998 7 28 8 23.04 2.02 0.95 0.011999 3 3 6 85.74 2.57 0.71 0.091974 1 19 16 1.45 2.8 0.83 0.17 PAROO CREEK1974 1 21 11 1.06 1.96 0.87 0.131974 2 3 14 25.64 0.64 0.63 0.131974 2 15 18 24.08 3.9 0.59 0.181974 2 16 22 2.23 1.51 0.81 0.181975 12 13 20 1.38 5.58 0.98 0.021971 3 3 4 46.23 1.06 0.6 0.28 GORGE CREEK1971 3 17 18 9.49 0.72 0.27 0.521971 4 12 7 30.31 0.69 0.55 0.231972 3 7 5 5.65 1.31 0.32 0.571973 3 27 19 6.2 1.46 0.97 0.031973 12 16 17 0.03 5.39 0.84 0.161974 1 31 15 0.62 2.01 0.55 0.451975 1 1 15 31.86 0.17 0.79 0.021975 2 14 12 4.51 0.73 0.93 0.061971 4 12 18 59.79 0.56 0.76 0.03 MALBON RIVER1972 3 6 5 21.58 7.05 0.81 0.141973 11 25 21 59.17 0.84 0.71 0.041973 12 16 20 34.21 14.61 0.96 0.021973 12 20 22 3.63 3.09 0.85 0.13 NORMAN RIVER1974 1 1 19 0.66 2.18 0.82 0.181974 1 3 20 16.61 4.36 0.83 0.121974 1 6 1 102.63 3.85 0.98 0.011974 1 30 18 43.18 3.46 0.93 0.041974 12 29 12 16.02 5.63 0.88 0.111975 1 16 19 14.46 3.2 0.6 0.31975 12 28 20 28.41 2.02 0.92 0.031977 2 3 14 37.69 0.54 0.56 0.061973 11 26 15 16.37 8.71 1 0 MOONLIGHT RIVER1973 12 25 21 33.83 0.45 0.29 0.151973 12 26 19 2.27 6.79 0.58 0.411974 1 2 9 36.62 2.4 0.64 0.081974 1 24 18 60.58 1.34 0.55 0.231974 3 9 1 20.46 0.62 0.16 0.551974 12 31 2 28.93 10.4 0.99 0.011973 11 11 23 31.22 1.77 0.8 0.03 AGATE CREEK1973 12 20 22 3.63 3.23 0.89 0.11973 12 25 13 3.29 3.71 0.95 0.051973 12 29 20 1.46 7.12 0.95 0.051974 1 2 0 6.37 2.65 0.81 0.161974 1 3 16 1.54 3.95 0.84 0.161974 1 15 18 0.93 2.83 0.77 0.221974 1 29 20 19.53 2 0.85 0.131974 2 2 17 32.28 0.23 0.94 01974 2 6 16 0.14 1.41 0.35 0.651974 2 15 20 6.11 1.04 0.54 0.391974 3 4 22 34.67 0.93 0.31 0.281974 12 29 6 2.8 4.68 0.89 0.111975 1 16 16 2.94 4.03 0.81 0.181975 2 23 0 5.54 2.89 0.9 0.081975 10 23 15 18.36 3.96 0.93 0.051975 12 19 17 14.12 1.09 0.99 0.011976 1 6 22 5.31 5.63 0.93 0.061977 1 20 2 10.7 2.23 0.9 0.081973 12 20 22 6.02 5.02 0.96 0.04 PERCY RIVER1974 1 3 17 1.32 3.04 0.9 0.09

Modelling losses in flood estimation E-13

Page 207: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1974 1 5 23 3.27 4.96 0.93 0.061974 1 17 22 4.26 3.13 0.86 0.131974 1 29 15 24.85 1.01 0.39 0.51974 3 9 23 9.4 3.19 0.94 0.041975 1 14 23 10.72 1.27 0.8 0.161977 2 3 10 0.11 0.04 0.36 0.581973 11 24 22 37.14 0.25 1 0 ELIZABETH CREEK1974 1 3 16 13.9 4.03 0.97 0.031974 1 17 17 26.68 1.77 0.79 0.181974 1 20 17 42.09 1.92 0.8 0.171974 1 29 17 24.49 1.45 0.81 0.111974 2 22 15 12.23 2.15 0.65 0.231974 3 4 16 2.74 3.88 0.89 0.111975 12 26 16 16.22 2.17 0.98 0.011974 1 29 14 29.55 1.09 0.79 0.03 ROUTH RIVER1974 2 6 21 26.04 4.06 0.51 0.321974 3 20 22 6.57 3.96 0.85 0.131974 12 30 0 36.21 0.67 0.13 0.261975 1 14 22 7.9 3.83 0.77 0.191977 3 1 20 51.77 1.44 0.62 0.021978 12 13 23 35.19 1.16 0.89 0.051969 12 7 19 38.31 4.08 0.78 0.03 PALMER RIVER1972 1 7 22 55.86 1.79 0.91 0.051972 2 4 14 1.82 5.6 0.99 0.011972 2 15 23 53.07 0.08 0.09 0.081975 3 20 22 31.29 8.62 0.92 0.031974 1 23 9 5.19 5.8 0.83 0.16 NORTH PALMER RIVER 1974 1 30 19 25.28 2.57 0.82 0.071974 2 13 16 2.26 7.48 0.78 0.211974 2 15 19 14.51 10.95 0.91 0.071975 3 2 17 0.8 7.51 0.99 0.011975 3 31 21 46.19 0.3 0.85 0.011975 12 24 22 44.94 3.99 0.86 0.011970 12 31 0 87.05 0.26 0.92 0.01 HOLROYD RIVER1972 4 13 6 17.43 1.28 0.42 0.511973 2 8 16 62.04 7.92 0.97 0.011973 2 22 22 24.16 16.04 0.94 0.051973 2 24 23 42.01 1.09 0.71 0.021973 3 3 17 6.04 1.32 0.55 0.411973 3 5 14 1.91 7.01 0.65 0.341973 3 23 3 40.98 0.74 0.46 0.241973 11 21 20 63.13 2.31 0.41 0.21973 12 12 12 69.02 0.92 0.97 01973 12 25 1 3.03 1.06 0.76 0.231974 3 14 19 80.16 0.84 0.15 0.261975 10 22 4 90.31 1.48 0.8 0.011976 3 27 23 37.6 0.75 0.79 0.121977 2 11 16 22.3 0.92 0.23 0.541977 3 6 16 31.43 1.48 0.73 0.211971 2 26 12 13.13 6.91 0.95 0.04 COEN RIVER1971 3 12 17 6.97 2.17 0.49 0.451972 4 12 19 29.41 1.31 0.32 0.61973 3 3 22 11.78 1.19 0.35 0.561973 3 8 14 30.94 1.63 0.3 0.521973 3 22 14 0.41 3.59 0.68 0.321974 1 8 14 24.52 2.2 0.62 0.161974 2 26 13 3.53 5.11 0.86 0.131974 3 19 12 27.82 2.2 0.88 0.061974 3 24 16 36.38 1.59 0.54 0.111974 3 29 18 6.64 1.78 0.92 0.071975 2 6 18 45.12 1.51 0.35 0.431975 2 19 22 39.11 2.92 1 01975 10 22 5 35.62 3.07 0.7 0.031975 12 13 15 23.47 9.45 0.94 0.031975 12 19 17 49.63 0.2 0.3 0.02

Modelling losses in flood estimation E-14

Page 208: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Year month date hour IL(mm) CL(mm/h) PL VRC1976 2 18 10 14.93 1.96 0.44 0.461977 3 14 19 43 4.46 0.89 0.021978 2 18 19 0.26 9.11 0.8 0.21979 1 10 6 31.57 2.16 0.4 0.541979 3 23 3 10.3 3.29 0.34 0.541980 2 15 0 51.24 1.37 0.84 0.11981 1 23 13 0.27 2.62 0.76 0.241981 1 26 12 0.74 4.08 0.99 0.011981 2 25 13 13.84 2.66 0.68 0.271982 2 25 16 44.06 2.8 0.3 0.271982 3 31 18 36.13 0.55 0.14 0.381984 2 15 12 45.71 1.12 0.86 0.081984 2 23 13 1.77 4.16 0.46 0.531984 3 27 20 0.3 4.53 0.6 0.391985 2 17 23 3.19 2.7 0.41 0.561985 3 8 1 42.43 1.75 0.64 0.081985 3 31 22 25.93 1.55 0.63 0.291986 1 24 21 21.77 3.4 0.53 0.281986 2 8 18 62.85 0.62 0.21 0.151987 1 31 17 37.55 0.6 0.99 01987 2 2 21 21.38 1.95 0.81 0.141988 3 9 1 24.86 1.42 0.56 0.331988 12 13 13 25.25 3.76 0.92 0.061989 2 8 20 0.73 1.46 0.72 0.271991 2 14 19 7.52 1.18 0.96 0.041991 2 23 5 52.4 0.81 0.47 0.31992 1 11 8 26.45 2.96 0.92 0.051992 2 26 19 49.77 0.29 0.29 0.11992 12 21 19 15.53 2.42 0.85 0.141992 12 30 17 3.21 3.22 0.19 0.781993 1 23 23 15.62 0.96 0.48 0.461995 3 17 1 30.76 3.98 0.81 0.091996 3 3 14 14.78 4.07 0.48 0.411996 3 7 8 3.66 1.38 0.91 0.091996 3 10 9 0.82 1.43 0.51 0.491996 10 10 2 81.89 3.63 0.74 0.131996 12 24 23 9.07 3.13 0.89 0.11997 1 19 17 19.59 1.41 0.88 0.091997 3 4 13 14.26 2.53 0.86 0.121998 11 20 19 55.64 0.22 0.54 0.011999 1 1 19 63.04 0.08 0.31 0.011999 1 8 4 47.2 0.57 0.8 0.041999 1 29 21 31.59 0.3 0.15 0.21975 3 8 11 7.8 0.03 0.07 0.05 DULHUNTY RIVER1975 3 23 12 0.11 1.16 0.64 0.361976 1 16 12 4.67 5.91 0.96 0.041976 4 10 1 4.8 2.32 0.4 0.571979 1 10 20 0.32 1.83 0.37 0.631979 4 9 2 16.29 1.72 0.63 0.311980 1 7 14 0 0.53 0.51 0.491982 4 2 20 2.97 0.85 0.78 0.171984 2 10 13 0.72 1.48 0.88 0.091984 2 25 10 2.56 2.02 0.86 0.131986 1 15 14 0 3.54 0.77 0.231990 3 20 16 0.42 0.45 0.64 0.31975 3 6 21 0.2 0.18 0.95 0.04 BERTIE CREEK1975 3 8 9 0 2.27 0.83 0.171975 3 23 12 0.11 1.11 0.61 0.381976 1 16 13 4.67 6.85 0.95 0.041979 4 9 0 1.2 1.43 0.48 0.521983 5 20 20 5.03 1.33 0.98 0.021984 2 25 12 4.01 2.69 0.98 0.021986 1 15 10 0 1.84 0.93 0.07

Modelling losses in flood estimation E-15

Page 209: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

APPENDIX F

Gow rie River

0

2

4

6

8

10

12

1 10 100 1000Duration (h)

CL

(mm

/h)

Blunder Creek

0

2

4

6

8

10

12

1 10 100 1000Duration (h)

CL

(mm

/h)

Stone River

02468

10121416

1 10 100

Bohle River

0123456789

1 10 100Duration (h)

CL

(mm

/h

Duration (h)

CL

(mm

/h)

)

Broughton River

0

2

4

6

8

10

1 10 100Duration (h)

CL

(mm

/h)

Blacks Creek

0

5

10

15

20

1 10 100 1000Duration (h)

CL

(mm

/h)

Sande Creek

0

2

4

6

8

10

1 10Durat ion (h)

100

Monal Creek

0

2

4

6

8

10

1 10 100Duration (h)

CL

(mm

/h)

Modelling losses in flood estimation F-1

Page 210: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Mary River

00.5

11.5

22.5

33.5

44.5

1 10 100 1000Duration (h)

CL

(mm

/h)

North Maroochy River

0

1

2

3

4

1 10 100 1000Duration (h)

CL

(mm

/h)

Bremer River

0

2

4

6

8

10

1 10 100Duration (h)

CL

(mm

/h)

Tenhill Creek

0

0.5

1

1.5

2

2.5

3

1 10Duration (h)

CL

(mm

/h100

)

Logan River

0

5

10

15

20

1 10 1Duration (h)

CL

(mm

/h

00

Running Creek

0

2

4

6

8

10

12

1 10 100Duration (h)

CL

(mm

/h))

Teviot Brook

0

1

2

3

4

5

6

7

8

1 10Duration (h)

CL

(mm

/h

100

)

Albert River

00.5

11.5

22.5

33.5

44.5

5

1 10 100

Duration (h)

CL

(mm

/h)

Macintyre Brook

0

2

4

6

8

10

12

14

16

1 10

Duration (h)

CL

(mm

/h)

100

Canal Creek

0

1

2

3

4

5

6

7

8

1 10 100Duration (h)

CL

(mm

/h)

Modelling losses in flood estimation F-2

Page 211: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Cadamine River

00.5

11.5

22.5

33.5

1 10 100Duration (h)

CL

(mm

/h)

Agate Creek

0

2

4

6

8

1 10Duration (h)

CL

(mm

/h)

100

Holroyd River

02468

1012141618

1 10 100

Coen River

0

2

4

6

8

10

1 10 100 1000Duration (h)C

L (m

m/h

)Duration (h)

CL

(mm

/h)

Dulhunty River

0

1

2

3

4

5

6

7

1 10Duration (h)

CL

(mm

/h

100

)

Bertie Creek

0

2

4

6

8

1 10 100Duration (h)

CL

(mm

/h)

Modelling losses in flood estimation F-3

Page 212: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

APPENDIX G

Initial loss (mm) (ILs f or catchment ID 117003)

200.5181.5

162.5143.5

124.5105.5

86.567.5

48.529.5

10.5

Fre

quen

cy

10

8

6

4

2

0

initial loss (mm) (ILc for 117003)

160.0140.0120.0100.080.060.040.020.00.0

Freq

uenc

y

12

10

8

6

4

2

0

Modelling losses in flood estimation G-1

Page 213: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Initial loss (mm) (ILs for catchment ID120014)

68.059.150.241.232.323.314.45.5

Freq

uenc

y

8

6

4

2

0

Initial loss (mm) (ILc for catchment ID 120014)

68.059.150.241.232.323.314.45.5

Freq

uenc

y

8

6

4

2

0

Modelling losses in flood estimation G-2

Page 214: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Initial loss (mm) (ILs for catchment ID 145003)

83.558.132.77.3

Freq

uenc

y

30

20

10

0

Initial loss (mm) (ILc for catchment ID 145003)

87.367.046.726.46.1

Freq

uenc

y

30

20

10

0

Modelling losses in flood estimation G-3

Page 215: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Initial loss (mm) (ILs for catchment ID 138110)

90.676.863.049.235.521.77.9

Freq

uenc

y

14

12

10

8

6

4

2

0

Initial loss (mm) (ILc for catchment ID 138110)

91.579.467.355.343.231.219.17.0

Freq

uenc

y

16

14

12

10

8

6

4

2

0

Modelling losses in flood estimation G-4

Page 216: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Initial loss (mm) (ILs for catchment ID 145011)

86.072.959.846.733.720.67.5

Freq

uenc

y

40

30

20

10

0

Initial loss (mm) (ILc for catchment ID 145011)

86.875.363.952.541.029.618.26.7

Freq

uenc

y

50

40

30

20

10

0

Modelling losses in flood estimation G-5

Page 217: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Initial loss (mm) (ILs for catchment ID 416410)

87.978.869.660.551.342.233.023.914.75.6

Freq

uenc

y

50

40

30

20

10

0

Initial loss (mm) ( ILc for catchment ID 416410)

87.978.869.660.551.342.233.023.914.75.6

Freq

uenc

y

50

40

30

20

10

0

Modelling losses in flood estimation G-6

Page 218: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Initial loss (mm) ( ILs for catchment ID 422338)

100.076.753.430.16.8

Freq

uenc

y

40

30

20

10

0

Initial loss (mm) (ILc f or catchment ID 422338)

92.783.073.463.754.144.434.825.115.55.8

Freq

uenc

y

40

30

20

10

0

Modelling losses in flood estimation G-7

Page 219: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Initial loss (mm) (ILs f or catchment ID 422394)

87.978.869.660.551.342.233.023.914.75.6

Fre

quen

cy

40

30

20

10

0

Initial loss (mm) ( ILc f or catchment ID 422394)

83.274.565.957.248.639.931.322.614.05.3

Fre

quen

cy

40

30

20

10

0

Modelling losses in flood estimation G-8

Page 220: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Initial loss (mm) (ILs f or catchment ID 922101)

64.413.7

Fre

quen

cy

60

50

40

30

20

10

0

Initial loss (mm) (ILc f or catchment ID 922101)

76.755.133.411.8

Freq

uenc

y

50

40

30

20

10

0

Modelling losses in flood estimation G-9

Page 221: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

APPENDIX H

α = 0.0080.008

Y M D Timestep Streamflow Rainfall Difference1 x1=(diff1*f1) BF=(Storm.+X1) Baseflow Netflow LogQ LogBF1990 5 22 1 0 1.5 0.12 0 0 1.5 1.5 0 0.176091 0.1760911990 5 22 2 1 1.5 0.11 0 0 1.5 1.5 0 0.176091 0.1760911990 5 22 3 2 1.5 0.12 0 0 1.5 1.5 0 0.176091 0.1760911990 5 22 4 3 1.5 0.1 0 0 1.5 1.5 0 0.176091 0.1760911990 5 22 5 4 1.5 0.08 0 0 1.5 1.5 0 0.176091 0.1760911990 5 22 6 5 1.5 0.16 0 0 1.5 1.5 0 0.176091 0.1760911990 5 22 7 6 1.4 0.56 0 0 1.4 1.4 0 0.146128 0.1461281990 5 22 8 7 1.4 2.54 0 0 1.4 1.4 0 0.146128 0.1461281990 5 22 9 8 1.4 1.59 0 0 1.4 1.4 0 0.146128 0.1461281990 5 22 10 9 1.4 0.39 0 0 1.4 1.4 0 0.146128 0.1461281990 5 22 11 10 1.4 0.39 0 0 1.4 1.4 0 0.146128 0.1461281990 5 22 12 11 1.3 0 0 0 1.3 1.3 0 0.113943 0.1139431990 5 22 13 12 1.2 3.48 0 0 1.3 1.3 -0.1 0.079181 0.1139431990 5 22 14 13 1.2 3.57 0 0 1.2 1.2 0 0.079181 0.0791811990 5 22 15 14 1.3 2.76 0 0 1.3 1.3 0 0.113943 0.1139431990 5 22 16 15 1.3 3.23 0 0 1.3 1.3 0 0.113943 0.1139431990 5 22 17 16 1.4 3.36 0 0 1.4 1.4 0 0.146128 0.1461281990 5 22 18 17 1.4 4.28 0 0 1.4 1.4 0 0.146128 0.1461281990 5 22 19 18 1.5 3.28 0 0 1.5 1.5 0 0.176091 0.176091

0

10

20

30

40

50

60

0 50 100 150Time step

Q

-0.5

0

0.5

1

1.5

2

0 50 100 150

Time step

Log

Q

Modelling losses in flood estimation H-1

Page 222: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Y M D Timestep Streamflow Rainfall Difference1 x1=(diff1*f1) BF=(Storm.+X1) Baseflow Netflow LogQ LogBF1990 5 22 20 19 1.6 5.6 0 0 1.6 1.6 0 0.20412 0.204121990 5 22 21 20 2.1 8.93 0 0 2.1 2.1 0 0.322219 0.3222191990 5 22 22 21 3.1 13.79 1 0.008 2.108 2.108 0.992 0.491362 0.3238711990 5 22 23 22 4.9 10.92 2.792 0.022336 2.130336 2.130336 2.769664 0.690196 0.3284481990 5 22 24 23 6.5 0.39 4.369664 0.03495731 2.165293312 2.165293312 4.334706688 0.812913 0.3355171990 5 23 25 0 6.8 0.19 4.634706688 0.03707765 2.202370966 2.202370966 4.597629034 0.832509 0.342891990 5 23 26 1 12.2 0.2 9.997629034 0.07998103 2.282351998 2.282351998 9.917648002 1.08636 0.3583831990 5 23 27 2 31.2 0.17 28.917648 0.23134118 2.513693182 2.513693182 28.68630682 1.494155 0.4003121990 5 23 28 3 36.5 0.31 33.98630682 0.27189045 2.785583636 2.785583636 33.71441636 1.562293 0.4449161990 5 23 29 4 35.3 0.2 32.51441636 0.26011533 3.045698967 3.045698967 32.25430103 1.547775 0.4836871990 5 23 30 5 35.2 0 32.15430103 0.25723441 3.302933376 3.302933376 31.89706662 1.546543 0.51891990 5 23 31 6 48.7 0.2 45.39706662 0.36317653 3.666109909 3.666109909 45.03389009 1.687529 0.5642051990 5 23 32 7 51.7 0.19 48.03389009 0.38427112 4.050381029 4.050381029 47.64961897 1.713491 0.6074961990 5 23 33 8 48.8 0.19 44.74961897 0.35799695 4.408377981 4.408377981 44.39162202 1.68842 0.6442791990 5 23 34 9 44.4 0 39.99162202 0.31993298 4.728310957 4.728310957 39.67168904 1.647383 0.6747061990 5 23 35 10 40 0 35.27168904 0.28217351 5.01048447 5.01048447 34.98951553 1.60206 0.699881990 5 23 36 11 36.1 0 31.08951553 0.24871612 5.259200594 5.259200594 30.84079941 1.557507 0.720921990 5 23 37 12 32.8 0 27.54079941 0.2203264 5.479526989 5.479526989 27.32047301 1.515874 0.7387431990 5 23 38 13 30.1 0 24.62047301 0.19696378 5.676490773 5.676490773 24.42350923 1.478566 0.754081990 5 23 39 14 28.1 0 22.42350923 0.17938807 5.855878847 5.855878847 22.24412115 1.448706 0.7675921990 5 23 40 15 26.2 0 20.34412115 0.16275297 6.018631816 6.018631816 20.18136818 1.418301 0.7794981990 5 23 41 16 24.2 0 18.18136818 0.14545095 6.164082762 6.164082762 18.03591724 1.383815 0.7898681990 5 23 42 17 22.5 0 16.33591724 0.13068734 6.2947701 6.2947701 16.2052299 1.352183 0.798981990 5 23 43 18 21.2 0 14.9052299 0.11924184 6.414011939 6.414011939 14.78598806 1.326336 0.807131990 5 23 44 19 20.1 0 13.68598806 0.1094879 6.523499843 6.523499843 13.57650016 1.303196 0.8144811990 5 23 45 20 18.9 0.6 12.37650016 0.099012 6.622511844 6.622511844 12.27748816 1.276462 0.8210231990 5 23 46 21 17.8 0.5 11.17748816 0.08941991 6.71193175 6.71193175 11.08806825 1.25042 0.8268481990 5 23 47 22 16.9 0.51 10.18806825 0.08150455 6.793436296 6.793436296 10.1065637 1.227887 0.832091990 5 23 48 23 16 0.1 9.206563704 0.07365251 6.867088805 6.867088805 9.132911195 1.20412 0.8367731990 5 24 49 0 15.2 0.1 8.332911195 0.06666329 6.933752095 6.933752095 8.266247905 1.181844 0.8409681990 5 24 50 1 14.5 0.2 7.566247905 0.06052998 6.994282078 6.994282078 7.505717922 1.161368 0.8447431990 5 24 51 2 14 0.03 7.005717922 0.05604574 7.050327822 7.050327822 6.949672178 1.146128 0.8482091990 5 24 52 3 13.4 0.07 6.349672178 0.05079738 7.101125199 7.101125199 6.298874801 1.127105 0.8513271990 5 24 53 4 12.8 0.01 5.698874801 0.045591 7.146716197 7.146716197 5.653283803 1.10721 0.8541071990 5 24 54 5 12.3 0.1 5.153283803 0.04122627 7.187942468 7.187942468 5.112057532 1.089905 0.856605

Modelling losses in flood estimation H-2

Page 223: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Y M D Timestep Streamflow Rainfall Difference1 x1=(diff1*f1) BF=(Storm.+X1) Baseflow Netflow LogQ LogBF1990 5 24 55 6 11.7 0 4.512057532 0.03609646 7.224038928 7.224038928 4.475961072 1.068186 0.858781990 5 24 56 7 11.1 0 3.875961072 0.03100769 7.255046617 7.255046617 3.844953383 1.045323 0.860641990 5 24 57 8 10.6 0 3.344953383 0.02675963 7.281806244 7.281806244 3.318193756 1.025306 0.8622391990 5 24 58 9 10 0 2.718193756 0.02174555 7.303551794 7.303551794 2.696448206 1 0.8635341990 5 24 59 10 9.7 0 2.396448206 0.01917159 7.322723379 7.322723379 2.377276621 0.986772 0.8646731990 5 24 60 11 9.3 0 1.977276621 0.01581821 7.338541592 7.338541592 1.961458408 0.968483 0.865611990 5 24 61 12 8.9 0 1.561458408 0.01249167 7.35103326 7.35103326 1.54896674 0.94939 0.8663481990 5 24 62 13 8.7 0 1.34896674 0.01079173 7.361824994 7.361824994 1.338175006 0.939519 0.8669851990 5 24 63 14 8.5 0 1.138175006 0.0091054 7.370930394 7.370930394 1.129069606 0.929419 0.8675221990 5 24 64 15 8.4 0 1.029069606 0.00823256 7.37916295 7.37916295 1.02083705 0.924279 0.8680071990 5 24 65 16 8.2 0 0.82083705 0.0065667 7.385729647 7.385729647 0.814270353 0.913814 0.8683931990 5 24 66 17 8 0 0.614270353 0.00491416 7.39064381 7.39064381 0.60935619 0.90309 0.8686821990 5 24 67 18 7.9 0 0.50935619 0.00407485 7.394718659 7.394718659 0.505281341 0.897627 0.8689221990 5 24 68 19 7.7 0 0.305281341 0.00244225 7.39716091 7.39716091 0.30283909 0.886491 0.8690651990 5 24 69 20 7.6 0 0.20283909 0.00162271 7.398783623 7.398783623 0.201216377 0.880814 0.869161990 5 24 70 21 7.5 0 0.101216377 0.00080973 7.399593354 7.399593354 0.100406646 0.875061 0.8692081990 5 24 71 22 7.4 0 0.000406646 3.2532E-06 7.399596607 7.399596607 0.000403393 0.869232 0.8692081990 5 24 72 23 7.2 0 -0.199596607 -0.0015968 7.397999834 7.2 0 0.857332 0.8573321990 5 25 73 0 7.1 0 -0.297999834 -0.002384 7.395615835 7.1 0 0.851258 0.8512581990 5 25 74 1 7 0 -0.395615835 -0.0031649 7.392450909 7 0 0.845098 0.8450981990 5 25 75 2 6.9 0 -0.492450909 -0.0039396 7.388511301 6.9 0 0.838849 0.8388491990 5 25 76 3 6.8 0 -0.588511301 -0.0047081 7.383803211 6.8 0 0.832509 0.8325091990 5 25 77 4 6.7 0 -0.683803211 -0.0054704 7.378332785 6.7 0 0.826075 0.8260751990 5 25 78 5 6.6 0 -0.778332785 -0.0062267 7.372106123 6.6 0 0.819544 0.8195441990 5 25 79 6 6.5 0 -0.872106123 -0.0069768 7.365129274 6.5 0 0.812913 0.8129131990 5 25 80 7 6.4 0 -0.965129274 -0.007721 7.35740824 6.4 0 0.80618 0.806181990 5 25 81 8 6.3 0 -1.05740824 -0.0084593 7.348948974 6.3 0 0.799341 0.7993411990 5 25 82 9 6.2 0 -1.148948974 -0.0091916 7.339757382 6.2 0 0.792392 0.7923921990 5 25 83 10 6.1 0 -1.239757382 -0.0099181 7.329839323 6.1 0 0.78533 0.785331990 5 25 84 11 6.1 0 -1.229839323 -0.0098387 7.320000608 6.1 0 0.78533 0.785331990 5 25 85 12 6 0 -1.320000608 -0.01056 7.309440604 6 0 0.778151 0.7781511990 5 25 86 13 5.9 0 -1.409440604 -0.0112755 7.298165079 5.9 0 0.770852 0.7708521990 5 25 87 14 5.8 0 -1.498165079 -0.0119853 7.286179758 5.8 0 0.763428 0.7634281990 5 25 88 15 5.7 0 -1.586179758 -0.0126894 7.27349032 5.7 0 0.755875 0.7558751990 5 25 89 16 5.6 0 -1.67349032 -0.0133879 7.260102397 5.6 0 0.748188 0.748188

Modelling losses in flood estimation H-3

Page 224: MODELLING LOSSES IN FLOOD ESTIMATION · flood estimation: A case study in Queensland. 28th Hydrology and Water Resources Symposium, the Institution of Engineers, Australia, Wollongong

Y M D Timestep Streamflow Rainfall Difference1 x1=(diff1*f1) BF=(Storm.+X1) Baseflow Netflow LogQ LogBF

1990 5 25 90 17 5.6 0 -1.660102397 -0.0132808 7.246821578 5.6 0 0.748188 0.7481881990 5 25 91 18 5.5 0 -1.746821578 -0.0139746 7.232847006 5.5 0 0.740363 0.7403631990 5 25 92 19 5.4 0 -1.832847006 -0.0146628 7.21818423 5.4 0 0.732394 0.7323941990 5 25 93 20 5.3 0 -1.91818423 -0.0153455 7.202838756 5.3 0 0.724276 0.7242761990 5 25 94 21 5.2 0 -2.002838756 -0.0160227 7.186816046 5.2 0 0.716003 0.7160031990 5 25 95 22 5.1 0 -2.086816046 -0.0166945 7.170121517 5.1 0 0.70757 0.707571990 5 25 96 23 5 0 -2.170121517 -0.017361 7.152760545 5 0 0.69897 0.698971990 5 26 97 0 5 0 -2.152760545 -0.0172221 7.135538461 5 0 0.69897 0.698971990 5 26 98 1 4.9 0 -2.235538461 -0.0178843 7.117654153 4.9 0 0.690196 0.6901961990 5 26 99 2 4.8 0 -2.317654153 -0.0185412 7.09911292 4.8 0 0.681241 0.6812411990 5 26 100 3 4.7 0 -2.39911292 -0.0191929 7.079920017 4.7 0 0.672098 0.6720981990 5 26 101 4 4.7 0 -2.379920017 -0.0190394 7.060880656 4.7 0 0.672098 0.6720981990 5 26 102 5 4.7 0 -2.360880656 -0.018887 7.041993611 4.7 0 0.672098 0.6720981990 5 26 103 6 4.6 0 -2.441993611 -0.0195359 7.022457662 4.6 0 0.662758 0.6627581990 5 26 104 7 4.6 0 -2.422457662 -0.0193797 7.003078001 4.6 0 0.662758 0.6627581990 5 26 105 8 4.5 0 -2.503078001 -0.0200246 6.983053377 4.5 0 0.653213 0.6532131990 5 26 106 9 4.4 0 -2.583053377 -0.0206644 6.96238895 4.4 0 0.643453 0.6434531990 5 26 107 10 4.4 0 -2.56238895 -0.0204991 6.941889838 4.4 0 0.643453 0.6434531990 5 26 108 11 4.3 0 -2.641889838 -0.0211351 6.92075472 4.3 0 0.633468 0.6334681990 5 26 109 12 4.2 0 -2.72075472 -0.021766 6.898988682 4.2 0 0.623249 0.6232491990 5 26 110 13 4.2 0 -2.698988682 -0.0215919 6.877396772 4.2 0 0.623249 0.6232491990 5 26 111 14 4.2 0 -2.677396772 -0.0214192 6.855977598 4.2 0 0.623249 0.6232491990 5 26 112 15 4.2 0 -2.655977598 -0.0212478 6.834729778 4.2 0 0.623249 0.6232491990 5 26 113 16 4.1 0 -2.734729778 -0.0218778 6.812851939 4.1 0 0.612784 0.6127841990 5 26 114 17 4.1 0 -2.712851939 -0.0217028 6.791149124 4.1 0 0.612784 0.6127841990 5 26 115 18 4 0 -2.791149124 -0.0223292 6.768819931 4 0 0.60206 0.60206

Modelling losses in flood estimation H-4