Modeling, Simulation, and Performance Analysis of Power Management Strategies for an Islanded Microg
-
Upload
shirley-wang -
Category
Documents
-
view
218 -
download
0
description
Transcript of Modeling, Simulation, and Performance Analysis of Power Management Strategies for an Islanded Microg
International Journal of Energy Science (IJES) Volume 3 Issue 6, December 2013 www.ijesci.org
doi: 10.14355/ijes.2013.0306.02
383
Modeling, Simulation, and Performance
Analysis of Power Management Strategies for
an Islanded Microgrid Faruk A. Bhuiyan*1, Amirnaser Yazdani2, Serguei L. Primak3
*1,3Electrical and Computer Engineering Dept., Western University, London, Ontario, Canada 2Electrical and Computer Engineering Dept., Ryerson University, Toronto, Ontario, Canada
*[email protected]; [email protected]; [email protected]
Abstract
Considering both real and reactive power, this paper
presents the modeling, simulation, and performances
analysis of various power management strategies (PMSs) for
the sizing of an enhanced renewable energy penetrated
islanded microgrid (IMG), which consists of an integrated
photovoltaic‐wind‐diesel‐battery system. The models of the
PMSs are illustrated by flowcharts which can be utilized to
determine optimal sizes of the IMG components. When the
IMG contains both a battery energy storage system (BESS)
and a diesel generator system (DGS), there are several ways
to meet the load demand. The various options of fulfilling
the load demand make the PMSs complex. The complexities
in PMSs have significant impact on the incurred costs
through the fuel usages rate of DGS and the deterioration
level of BESS. The PMSs are presented by considering
unknown component sizes of the IMG. The paper considers
the effect of reactive power on BESS charging. The
effectiveness of the modified PMSs is demonstrated through
simulation studies in the MATLAB/Simulink environment.
Then the performances of the PMSs are compared and the
cost‐varying areas are identified meticulously by utilizing
the simulation results.
Keywords
Battery; Dispatch; Microgrid; Photovoltaic; Power Management;
Wind
Introduction
Electrification of remote communities remains a challenge
in Canada and elsewhere due to the economical and
technical barriers. Most of the Canadian remote
communities have been supplied by diesel generator
systems (DGSs), while the rest have used low to
medium penetration wind/pv diesel systems (Arriaga
et al. 2012; Weis et al. 2008). Thus far, many studies
(Bernal−Agustin et al. 2009) of islanded microgrid
(IMG) have been performed and many systems are
installed with various configuration of components.
Among the installed systems, many projects have
failed due to improper design. The systems design can
be improved if optimization methods are applied
(Zhou et al. 2010). The sizing optimization of an IMG
can be performed by either analytical techniques or
chronological time‐series/probabilistic simulations.
Analytical techniques are difficult to implement due to
the large number of variables, non‐linearity in the
models, and complexity of the configurations. The
timeseries/probabilistic simulation techniques require
well‐defined power management strategies (PMSs)
and are computationally intensive. Power management
in an IMG can be performed by either controlling the
energy resources or/and load management
(Lujano−Rojas et al. 2012); the accommodation of load
management strategies during the design phase may
not be a good idea.
Barley et al. (1996) proposes a number of control
strategies for the operation and simulation of a
wind‐photovoltaic‐diesel‐battery system. Utilizing
load setpoint to start and stop the diesel engine, and
state of energy (SOE) setpoint to charge the battery
energy storage system (BESS), an optimization method
for the control strategies is proposed in Ashari et al.
(1999). Bagen et al. (2005) presents a simulation
technique for the operating strategies of stand‐alone
power systems by giving the priorities to the operation
of nonconventional generating units, conventional
generating units, and BESS in sequence. Dufo−López et
al. (2005) combines two of the operating strategies of
Barley et al. (1996) in a photovoltaic (PV) system with
energy storage and identified a critical load. Katiraei et
al. (2007) proposes an energy‐flow model for an
autonomous wind‐diesel system for the investigation
of the the daily and monthly performances. Various
PMSs for standalone hybrid power system integrated
with hydrogen energy storage are proposed in Ipsakis
www.ijesci.org International Journal of Energy Science (IJES) Volume 3 Issue 6, December 2013
384
et al. (2009). Zhou et al. (2011) proposes the
‘source‐following’ and ‘grid‐following’ dynamic
control approaches in order to enable exchange power
amongst the sources, and to manage energy of the
grid‐connected system. Considering real power only,
Vrettos et al. (2011) proposes three operating modes for
a small isolated high‐penetration renewable energy
system integrated with a BESS. Ohsawa et al. (1993)
has applied artificial neural network to the control
strategies of PV‐diesel power system, although few
researchers (Lin et al. 2011; Yasin et al. 2011) have
proposed intelligence‐based approaches for the
dynamic control of autonomous hybrid power
systems.
Various software tools (HOMER ; HYBRID2; iHOGA;
INSEL ; RETScreen ; TRANSYS ) are used for
simulation, optimization, and performance evaluation
of IMGs. Amongst them, HOMER (Hybrid
Optimization Model for Electric Renewable) has been
widely used for optimization studies, HYBRID2 is
popular for simulations, and HOGA (Hybrid
Optimization by Genetic Algorithms) is primarily used
for multi‐objective optimization.
However, the aforementioned software tools and
papers have not modeled PMSs for the objective of
determining the component sizes considering both real
and reactive powers of the load. This paper models the
PMSs in detail by utilizing flowcharts, where both real
and reactive powers of the load are considered.
Study System
Fig. 1 shows a schematic diagram of an IMG whose
main components are DGS, a wind power system
(WPS), a photovoltaic power system (PVS), an energy
storage system, a dump load, a primary load, and
power‐electronic converters. In this configuration, the
energy storage system is assumed to be a battery
energy storage system (BESS) connected to the power
system through a bi‐directional power‐electronic
converter. In turn, the PV power system comprises
multiple PV modules interface with the point of
common coupling (PCC) through a DC/AC converter.
Also, the BESS is composed of a bank of series‐/
parallelconnected batteries and a power‐electronic
converter. The WPS delivers power at unity power
factor to the PCC, represented as Pw. The delivered real
and reactive powers of the PVS are denoted
respectively by Ppv and Qpv. The real and reactive
powers delivered by the DGS are denoted by Pdi and
Qdi, respectively. The power delivered by the batteries
is referred to as the discharged power and denoted by
Pb. The real and reactive powers of the
power‐electronic converter of the BESS are denoted as
Pcon and Qcon, respectively; the typical high efficiency of
the power‐electronic converter implies that Pb and Pcon
are almost equal and are therefore used
interchangeably in this paper. The real and reactive
power components of the primary load are
represented by Pl and Ql, respectively. The dump load
is assumed to be a resistive load and represented as Pdl.
At any instant, stable operation of the IMG
corresponds to following power‐balance equations (1):
Pw(t) + Ppv(t) + Pdi(t) + Pcon(t) − Pl(t) − Pdl(t) = 0
Qdi(t) + Qpv(t) + Qcon(t) − Ql(t) = 0
(1)
FIG. 1 SCHEMATIC DIAGRAM OF AN ISLANDED MICROGRID
Reactive Power and Charging/Discharging of BESS
Figs. 2 (a) and (b) show that the primary load is
decoupled into real power, Pl, and reactive power, Ql.
Depending on the control strategy, the load reactive
power, Ql, can be supplied by the converters of the
PVS, BESS or DGS. To deliver the rated power of the
PVS into the PCC, the PVS converter rating, pvconS ,
must be the same as the rated power of the PVS, pvratP .
The power delivered by the PVS usually falls below pv
ratP in a year. Therefore, the PVS converter can be
utilized to supply reactive power of the load. If the
instantaneous real power of the PVS is Ppv(t), then the
PVS can deliver a reactive power of
2 2( ) ( )pv pv pvconQ S P where 2 2( ) ( )pv pv
conS P
(2)
International Journal of Energy Science (IJES) Volume 3 Issue 6, December 2013 www.ijesci.org
385
(a)
(b)
FIG. 2 REAL AND REACTIVE POWER PHASORS AT (a) EXCESS RENEWABLE
GENERATION, AND (b) SHORTAGE OF RENEWABLE GENERATION
Figs. 2(a) and (b) indicate that a part of the load
reactive power is supplied from PVS, as Qpv, while the
remaining load reactive power can be supplied from
the BESS converter and/or DGS. Fig. 2 further
illustrates that the real power supplying capacity of the
BESS converter decreases when the load reactive
power needs to be compensated. Thus, the BESS
converter real power, conavaP , is formulated as,
22( ) (max 0,( )pvcon con lava rat
lrem
P S Q Q
Q
(3)
where conratS is the rating of the BESS converter, and
lremQ is the remaining load reactive power demand; conratS needs to be higher than l
remQ when DGS does not
run. However, if DGS runs and delivers real power,
the load reactive power can be shared by the
converters and DGS,
(max 0,( ) )
(max 0,( ) )
conpvcon lrat
con dirat rat
lrem
dipvdi lrat
con dirat rat
lrem
SQ Q Q
S SQ
SQ Q Q
S SQ
(4)
where Qcon and Qdi are the reactive‐power output of the
BESS converter and DGS, respectively. In (4) diratS is the
rated power of DGS, and, lremQ should not be higher
than the aggregated value of conratS and di
ratS .
Consequently, the effective real power of the BESS
converter ( )conavaP and the DGS max( )diP decrease as
2 2
2 2max
( ) ( )
( ) ( )
con con conava rat
di con dirat
P S Q
P S Q
(5)
The rate of charge of BESS, ( )bavaP , depends on state of
energy (SOE), Eb(t), and the rated charging power,
maxbP , is
maxmax
( )min ,max(0,
Δ
b bb b
avaE E t
P Pt
(6)
If bavaP in (6) is larger than con
avaP , then the charging of
the BESS needs to be lowered to conavaP ; otherwise, the
BESS can be charged by bavaP . Fig. 2 (a) shows surplus
power, Psur, at higher renewable power generation. The
actual charging of the BESS, equation (7), is the lowest
of the three values bavaP , con
avaP and Psur.
min( , , )b con bsur ava avaP P P P (7)
If the surplus power Psur is higher than the absolute
value of Pb, then the remaining power must be
dumped. Fig. 2 (b) illustrates the real and reactive
powers of DGS and BESS converter. When DGS and
BESS converter run, the load reactive power is shared
by DGS and BESS as described by (4). During the BESS
discharge, the available discharging power from BESS
can be formulated as
minmax
( )min ,max(0, )
Δ
b bb b
avaE t E
P Pt
(8)
Since the BESS discharges through its converter, the
maximum discharge power of the BESS is determined
by the real power that flows through the converter. If
the net load, Pde f, needs to be delivered by the BESS,
then the BESS discharge power is
min( , , )b con bava ava defP P P P (9)
Depending on the PMS, Pde f may need to be supplied
by both the BESS and the DGS. Otherwise, power
shortage will occur. In Fig. 2 (b), the negative Psur
means positive Pde f .
The SOE in the BESS can be expressed as
( Δ ) ( )(1 ) ( )Δb b b bE t t E t P t t (10)
where is the self discharge coefficient, b is the
efficiency during charging and discharging, and Δt is
www.ijesci.org International Journal of Energy Science (IJES) Volume 3 Issue 6, December 2013
386
the time step.
Power Management Strategies and Their Flowcharts
Two distinct types of control in an IMG are (i) dynamic
control, which deals with the frequency and
magnitude of the voltage, and (ii) PMS, which controls
the energy resources of an IMG. This paper deals with
four different PMSs, which are described in the
following subsections.
Power Management Strategy‐A (PMS‐A)
Fig. 3 illustrates the algorithm of the PMS‐A, utilizing
the renewable resources first for the real load power
demand. The load reactive‐power demand is
compensated from converters (PVS and BESS) and
DGS. The real power limit of the BESS converter ( conavaP )
and that of the DGS ( maxdiP ) are then calculated
(explained earlier). If the renewable resources cannot
meet the net real load i.e., Pde f > 0, then the BESS is
employed to compensate the demand (at ( 2b
defP P ));
otherwise, the DGS shall start. The “power shortage”
in Fig. 3 indicates that the resource sizes do not meet
the load demand. The BESS enters into charging mode
if the aggregated delivered power from the renewable
resources exceeds the primary load demand (Psur > 0).
The actual charging power (Pb) depends on the
capacity and power rating of the batteries, and the real
power handling capability of the BESS converter. If the
surplus power cannot be absorbed by the BESS (i.e.
1b
surP P ), the rest is burnt in the dump load. The
PMS‐A does not allow DGS to charge the BESS. The
exception is when the DGS operates at a low load with
a non‐zero minimum setpoint ( mindiP ) setting. When the
net load demand falls below the minimum setpoint of
the DGS, the DGS then runs at its minimum operating
point. The extra generation from the DGS is then used
to charge the BESS. Otherwise it can be dumped. The
PMS‐A is a modified form of load following strategy.
FIG. 3 FLOWCHART OF PMS‐A
International Journal of Energy Science (IJES) Volume 3 Issue 6, December 2013 www.ijesci.org
387
Power Management Strategy‐B (PMS‐B)
The PMS‐B allows the DGS for charging the BESS.
Fig.4 illustrates a flowchart for the PMS‐B. First the
aggregate renewable power is compared with load real
power. The real powers from the converter of BESS
and the DGS are then calculated upon supplying load
reactive power (described earlier). If the surplus
generation, i.e. Psur > 0 is higher than Pb, then the BESS
enter the charging mode at its maximum rate and the
rest is burnt to the dump load; otherwise at Psur < Pb,
the DGS runs for a while to charge the BESS at a
maximum rate. At min( )b bE t E of the BESS and/or at
‘on’ status (k = 1) of DGS, if aggregate surplus
generation from the renewable resources is lower than
Pb, then the DGS starts/continues operation for
charging the BESS. The DGS is commended to stop
when SOE in the BESS reaches at bsocE . If Pde f > 0, and
( )b bsocE t E in BESS, and the DGS is off (k = 0), the net
real load (Pde f) is supplied by the BESS; if fails, the DGS
starts to compensate the remaining net load. When
DGS is already in ‘on’ status (k = 1) and SOE of the
BESS stays above minimum ( min( )b bE t E ) and below
bsocE , the DGS continues its operation for charging
BESS at its maximum rate. The energy at BESS may fall
at/below minimum level ( min( )b bE t E ) with DGS ‘off’
status. In such a situation, the DGS goes into operation
mode for charging BESS. As soon as the SOE of the
BESS reaches at bsocE , the DGS stops for charging the
BESS. The bsocE is considered a lavel which is lower than
maxbE . The Fig. 4 represents all possible scenarios under
unknown sizes. The “power shortage” of Fig. 4 is true
if the reserve and renewable resources cannot meet the
primary load demand. The PMS‐B is a modified form
of SOC setpoint dispatch strategy.
FIG. 4 FLOWCHART OF PMS‐B AND PMS‐C
www.ijesci.org International Journal of Energy Science (IJES) Volume 3 Issue 6, December 2013
388
FIG. 5 FLOWCHART OF PMS‐D
Power Management Strategy‐C (PMS‐C)
When the DGS is utilized for charging the BESS at
maxbE instead of b
socE , then the PMS‐B becomes PMS‐C. It
is a modified form of the cycle charge strategy. The
strategy may need the DGS to continue at its operation
mode for a longer period than that of PMS‐B.
According to PMS‐B and PMS‐C, the DGS runs either
at full power or at a rate not exceeding the aggregate of
BESS charging power and net load demand. The
flowchart for the PMS‐C is given in Fig. 4 where both
real and reactive power balances are depicted. The
PMS‐C also indicates that the dumping of power,
generated from the DGS, is required. Fig. 4 illustrates
that “power shortage” may occur under various
conditions, especially with improper sizes of
components in IMG. Fig. 4 illustrates the DGS ‘on’/‘off’
status by a flag variable ‘k’.
Power Management Strategy‐D (PMS‐D)
Utilizing the per unit energy cost curve of DGS (Barley
et al. 1996), the calculation steps of critical load Pd and
cycle charge load Pc are shown in the end of this
subsection. The Pd is the intersecting point of direct
diesel cost and BESS deterioration cost. It is more
economical to use the batteries when net load stays
below Pd; otherwise the operation of DGS is more
economical. Fig. 5 illustrates the PMS‐D which utilizes
the critical load, Pd, upon fulfilling load reactive power
demand. The PMS‐D is the modified form of the frugal
discharge strategy. Fig. 5 illustrates that when the net
load Pdef is above Pd, the DGS provides power to the
load at its fullest capacity; otherwise, the BESS delivers
the remaining load power. Alternatively, if the net
load, Pdef, falls below Pd, the BESS discharges power at
its extent. Power failure may occurs if both the DGS
and the BESS cannot meet the net load demand, which
may occur due to inappropriate component sizes.
Subsection‐1 shows the procedure for deriving Pd and
Pc.
1) Determination of Critical and Cycle Charge Load: The
International Journal of Energy Science (IJES) Volume 3 Issue 6, December 2013 www.ijesci.org
389
per unit costs of energy for the DGS includes capital,
operation, maintenance, and replenishment. Capital
costs depend on the rating of the DGS. The running
costs depend on operation and maintenance costs. The
operation cost is mainly the fuel costs, which including
fuel, transportation, and inventory holding cost. The
fuel consumption of the DGS is not linear. The fuel
consumption can be assumed as a quadratic function
with a cost at no‐load operation. Thus, the fuel
consumption (L/h) of DGS for Pdi, can be expressed as
(Zhu 2009).
21 2 3( )di di di di
c ratF g P g P g P (11)
Where 1g , 2g , and 3g are fuel consumption
coefficients in L/kW2h, L/kWh, and L/kWh, respectively.
Here diratS is the same as di
ratP taken at unity power
factor. The fuel consumption cost in $/kWh for DGS can
thus be expressed as
1 2 3( )di
di di ratf fdi
PC g P g g C
P (12)
where Cf is in $/L and includes fuel, transportation and
inventory holding cost.
Maintenance cost of the DGS varies at the level of
produced power and number of start‐stop. The per
kWh hourly maintenance cost, dimhC , is given as
didi mmh di
rat
CC
P (13)
Where dimC is the maintenance cost for di
ratP capacity of
DGS.
The hourly running cost of the DGS for per kWh diesel
generated energy is the sum of the fuel consumption
cost (operation cost) and the hourly maintenance cost
expressed as
1 2 3( )di di diom f mh
diratdi
PC g P g g C C
P (14)
where diomC is the hourly operation and
maintenance/running cost. The capital cost of the BESS
depends on size. The BESS wear cost is treated as the
cost of delivered energy from BESS and the
maintenance cost. The BESS wear cost is expressed as
bb bcw mhb
eqc rat
CC C
DOD E (15)
where bwC , b
cC , DODeqc, bratE , and b
mhC are wear cost,
capital cost, equivalent depth of discharge, kWh rating
of BESS, and hourly maintenance cost of BESS
respectively. Number of cycle to failure (Ncf) for the
BESS can be expressed as (Drouilhet et al. 1997).
1
0
( 1)u DODce
cf uN e
NDOD
(16)
where Nce, u1, and u0 are parameters for the equation.
The DOD is the depth of discharge for the BESS. Based
on battery manufacturer life cycle data, (16) can be best
fitted for a specific BESS. As an example,
manufacturer’s life cycle data for NiCd cell is best
fitted, which provides the parameter values u0=1.67,
u1=‐0.52, and Nce = 2055. Once the best fitted values are
fixed, then the equivalent depth of discharge can be
calculated as
1
1( ) ( )
M
eqc n ncfn
DOD N DODM
(17)
where M is the total number of observation point to
figure out the values of Ncf for different DOD utilizing
(16). This DODeqc is required for (15). For charging the
BESS, DGS can be used to run in excess to the net‐load
and thus requires extra generating costs. If the round
trip efficiency of the BESS and the charger is R , then
the cost of cycle charge can be written as
dii fdi
cR
F cC
(18)
The sum of battery wear costs and cycle charge costs
can be written as
dii fe di b b
c c w wR
F cC C C C
(19)
where diiF is the extra fuel required to charge the BESS.
The DGS optimum stopping set‐point occurs when the
BESS wear costs and DGS running costs becomes equal.
Thus, the equation (14) and (15) can be equalized to
calculate the roots of Pdi, which is expressed as
2 22 1 32
1 1
( ) 4
2 2
di b dib diw ratf mh fw f mh
df f
g c C C g g c PC g c CP
g c g c
(20)
From (14) and (19) the cycle charge load is expressed as Pc
and can be calculated by (21)
2 22 1 32
1 1
( ) 4
2 2
di e die dic ratf mh fc f mh
cf f
g c C C g g c PC g c CP
g c g c
(21)
Simulation Results
To demonstrate the performances of the PMSs, several
case studies are conducted in the MATLAB/Simulink
environment by utilizing the values of Table I. The
www.ijesci.org International Journal of Energy Science (IJES) Volume 3 Issue 6, December 2013
390
values of Table II are used on (20) to determine the
critical load, Pd, and thus to simulate PMS‐D. The bwC of
(20) is determined using (15) and (17). The hourly
average time series wind speed data, for a Canadian
site, is obtained from Weather Canada; and hourly
average time series solar irradiation data, based on
latitude and longitude, is produced by using HOMER
package. The wind power and PV power are produced
by employing (Bhuiyan et al. 2010) and (Lee et al. 2008),
respectively. To generate Fig. 6, probabilistic treatment
is included on the time series data at 15 minutes
interval. For other figures, year around hourly average
time‐series data is used. In Fig. 1, the Pb is positive for
delivered power of the BESS; however, in all figures
except Fig. 6, the BESS power is represented by −Pb.
The real and reactive load power components are
calculated utilizing IEEE RTS load model (IEEE RTS
1979) and a time series of load power factor (Saha et al.
2010).
TABLE I SIMULATION PARAMETERS
Simulation Parameters Values
WPS rating 600 kW
PV power rating 150 kW
Diesel generator rating 320 kVA
Inverter rating 640 kVA
BESS capacity rating 7.2 MWh
BESS power rating 450 kW
Base power 300 kW
Base power factor 0.9
Base BESS discharge time 1 hr
Base BESS capacity 300 kWh
Efficiency of PV system ( pv ) 15%
Cut‐in wind speed 3.5 m/s
Rated wind speed 12 m/s
Cut‐out wind speed 23 m/s
Period under observation 8760 hrs
BESS minimum level Emin 40%
BESS SOC level Esoc 60%
Initial BESS SOC 80% of rated
Self discharge of battery 0.2% per hour
Efficiency of inverter (discharging) 95%
Efficiency of rectifier (charging) 95%
TABLE II CRITICAL LOAD, Pd, DETERMINATION PARAMETERS
FOR PMS‐D
Parameter Value Comments
1g 0.00012 L/kW2h equation (11)
2g ‐0.011 L/kWh equation (11)
3g 0.16 L/kWh equation (11)
diratP 300 kW equation (11)
Fuel price, fc 1 $/L equation (12)
dimhC 0.11 $/h for 1 kWh equation (13)
/b bc ratc E 400 $/kWh equation (15)
bmhC 0.05 $/h for 1 kWh equation (15)
eqcDOD 1100 cycles equation (17)
Impact of Converter Reactive Power on BESS
Charging
This case demonstrates the impact of converter
reactive power on the BESS charging for the PMS‐A of
the IMG which is considered composed of without
PVS. The rating of the BESS converter is taken 0.5 p.u..
As Fig.6 (a) shows, Pw remains above 1 p.u., which is
more than the primary load demand. Therefore, DGS
does not require to run, and thus Pdi and Qdi in Fig. 6 (a)
are zero from 1520th hour to 1525th hour. Fig. 6 (b)
indicates that the SOE of BESS has not reached to the
maximum level until 1525th hour. Thus, the excess
wind power is stored in the BESS. At 1520.25th hour,
the reactive power demand is 0.5 p.u., which is
supplied by the BESS converter, as shown in Fig. 6 (a).
Although there is excess wind power, and BESS has
the capacity remaining for charging, the actual BESS
charging power (Pb) is zero due to the lower size
converter.
FIG. 6 IMPACT OF CONVERTER REACTIVE POWER ON BESS CHARGING
Simulation Results for PMS‐A
Fig. 7 illustrates the effectiveness of the PMS‐A by the
real power, reactive power and SOE of the BESS. From
2171th hour to 2192th hour, the aggregate renewable
International Journal of Energy Science (IJES) Volume 3 Issue 6, December 2013 www.ijesci.org
391
power is sufficient for primary load as shown in Fig.
7(a); thus, the BESS is in charging mode. As Fig. 7(a)
shows, the aggregate renewable power is low for
primary load from 2238th hour to 2285th hour. Thus,
the shortage is compensated by the BESS; if fails, the
DGS runs e.g. 2286th hour to 2378th hour. The
operation from 2114th hour to 2170th hour in Fig. 7(b)
indicates that the SOE of BESS stays at minimum. Fig.
7(a) further demonstrates that short‐term start/stop of
DGS (e.g. 2325th hour) may occur depending on wind
and PV resource output. The Pdl of Fig. 7(a) indicates
that the excess renewable power is dumped when
BESS and converter cannot accommodate. As Fig. 7(c)
shows, the load reactive power is mostly delivered by
the PVS converter and then the rest is supplied by the
BESS converter and/or DGS.
FIG. 7 POWER AND ENERGY OF IMG COMPONENTS FOR PMS‐A
Simulation Results for PMS‐B
Fig. 8 demonstrates the capability of PMS‐B by the SOE
of the BESS, the real and reactive powers of the IMG
components, presented from 3300th hour to 3475th
hour. Fig. 8 (a) shows that the delivered wind power is
low for many hours, between 3300th hour and 3475th
hour. The BESS does not have enough SOE for
discharging as shown in Fig. 8 (b). Therefore, the DGS
operates for load real power and for charging the BESS
(e.g. 3305th hour to 3316th hour). Once the SOE of
BESS reaches at bsocE , then the DGS stops. The BESS can
deliver the part of net load until the SOE of BESS stays
above minbE , and thus Fig. 8(b) illustrates that the DGS
starts again when the SOE of BESS touches at minbE .
Thus, the DGS mostly runs with heavy load,
subsequently its short‐period start/stop decreases. Fig.
8(c) demonstrates further that the reactive power is
supplied mostly by the PVS converter; after that the
BESS delivers the remaining reactive power and at the
end the DGS helps.
FIG. 8 POWER AND ENERGY OF IMG COMPONENTS FOR PMS‐B
Simulation Results for PMS‐C
Fig. 9 illustrates the productiveness of the PMS‐C by
the real power, reactive power and SOE of the BESS.
From 3395th hour to 3410th hour in Fig. 9 (b) indicates
that the DGS operates for charging the BESS up to the
maximum level. As Fig. 9(a) shows, the DGS operates
almost at full load for charging the BESS and for
fulfilling the net load demand. By observing Figs. 8
and 9, it can be stated that the operating periods of
DGS in this strategy are longer than those of PMS‐B.
As the SOE of BESS goes at maximum level by the
DGS operation, Fig. 9(a) illustrates that the dumping
power has increased (e.g. from 3350 th hour to 3367th
hour). Thus, the renewable energy penetration for the
primary load is expected to decrease.
FIG. 9 POWER AND ENERGY OF IMG COMPONENTS FOR PMS‐C
Simulation Results for PMS‐D
Fig. 10 demonstrates the performance of PMS‐D by the
simulation results, presented from 2105th hour to
2110th hour. As Fig. 10(a) shows, the DGS operates
www.ijesci.org International Journal of Energy Science (IJES) Volume 3 Issue 6, December 2013
392
when net load exceeds Pd; otherwise the BESS delivers
the net load, e.g. 2111th hour to 2117th hour. Thus, the
operation of the DGS and the BESS is complementary
for the net load demand unless any constraints work.
Therefore, the DGS operation contains frequent
start/stop, and it can be inferred that this causes higher
maintenance costs for DGS. Fig. 10(b) demonstrates
that the SOE decrease rate in BESS is lower compared
to that in other strategies. The slow decreasing rate of
SOE in the BESS may enhance the life cycles of the
batteries. Fig. 10 indicates that the charging rate of the
BESS is much higher than that of the discharging rate.
FIG. 10 POWER AND ENERGY OF IMG COMPONENTS FOR PMS‐D
SOEs of BESS for the PMSs
Figs. 11 (a), (b) and (c) respectively illustrate the SOEs
of the BESS for the PMS‐A, PMS‐C, and PMS‐D. As Fig.
11(a) shows, the SOE of BESS for PMS‐A remains low
from 2900th hour to 5500th hour due to seasonal
variations of wind speed. The magnified plot in Fig.
11(a) demonstrates that the SOE of BESS has decreased
significantly below minimum level due to
self‐discharge of the BESS. The situation becomes
worse when the BESS reaches at minimum level along
with low renewable power generation (e.g. 1376th hour
to 1475th hour). Thus, the PMS‐B and PMS‐C utilize
the DGS for charging BESS; Fig. 11(b) shows that the
SOE of BESS does not reach below minimum level. Fig.
11(b) further shows the SOE of BESS reaches
frequently at maximum level. The SOE of the BESS for
PMS‐B is excluded as it is very similar to PMS‐C. It can
be inferred that the SOE of BESS in PMS‐B would not
frequently reach the maximum level like PMS‐C. The
SOE of BESS for PMS‐D, (shown in Fig. 11(c)),
illustrates that the rate of discharge from BESS is lower,
as the BESS only discharges for low net load. Figs. 11
(a) and (c) show that the SOEs and self discharges of
BESS are similar both in PMS‐A and in PMS‐D.
FIG. 11 SOE OF BESS FOR (a) PMS-A, (b) PMS-C, AND (c) PMS-D
Reactive Power Management in IMG without PVS
The reactive powers of the IMG, which is constituted
without PVS for the PMS‐A, PMS‐B, PMS‐C and
PMS‐D are shown in Figs. 12 (a), (b), (c) and (d),
respectively. All of the sub‐figures of Fig. 12 illustrate
that the Qpv is zero. Thus, the BESS converter mostly
delivers the reactive power (Qcon), when the DGS does
not require to share. Fig. 12 (a) demonstrates that the
reactive power demand at around 2121th hour is 0.45
p.u., which is shared by both the BESS converter and
the DGS; where the Fig. 12 (b) (c) and (d) indicate that
the reactive powers are delivered only from the BESSs.
FIG. 12 REACTIVE POWER MANAGEMENT IN IMG OF NO PVS
Comparison of PMSs
All of the aforementioned studies are represented for
few hours of total simulation which is for the clarity of
the figures. Table III compares the performances of the
strategies based on a year around (8760 hrs) simulation.
As Table III shows, the SOE of BESS stays at minimum
level for 3898 hours, 156 hours, 72 hours, and 1143
hours, respectively, for PMS‐A, PMS‐B, PMS‐C, and
International Journal of Energy Science (IJES) Volume 3 Issue 6, December 2013 www.ijesci.org
393
PMS‐D. The number of hours, the SOE of the BESS at
minimum level, is significantly lower for PMS‐B and
PMS‐C compare to others. The number of hours, the
SOE stays above the 97% of its maximum level, is the
highest for the PMS‐C compare to the others’.
Consequently, the renewable energy penetration is the
lowest and thus the dumping power is the highest for
the PMS‐C. Although the DGS is used for charging the
BESS in PMS‐B and PMS‐C, the number of DGS
operating hours are lower in the strategies due to near
full load operation. Alternately, the DGS operates
longer hours with variable load in PMS‐A and PMS‐D.
Moreover, the self discharges in PMS‐A and PMS‐D
are higher (presented earlier). The low operating hours
of the DGS indicate low maintenance and operating
costs needed for the DGS.
TABLE III PERFORMANCES COMPARISON OF PMSs
Items PMS‐A PMS‐B PMS‐C PMS‐D
SOE at min. 3898 hrs 156 hrs 72 hrs 1143 hrs
SOE above 97%
of max. 1559 hrs 1824 hrs 2506 hrs 1864 hrs
DGS operation 3671 hrs 1763 hrs 1678 hrs 3614 hrs
Renew. Energy
penetration 69.15% 66.83% 62.62% 66.55%
Dumping
energy (kWh) 1183 1375.2 1620.3 1414.5
BESS self disch. high low low high
DGS operation variable rated rated variable
BESS expected
life‐cycle low moderate moderate low
Expected
maint. cost high low low high
Conclusions
The paper has modeled few PMSs and it has compared
the performances of them. The paper has also
presented the insight complexities in the model of the
PMSs. Moreover, the impact of converter reactive
power on BESS charging is incorporated in the study.
The performance analysis, based on case studies and
long term simulation, indicates that the PMS‐B is
comparatively better PMS than that of the others. The
study further illustrates the situation and impact of
BESS self‐discharge, SOE condition of BESS at
maximum and minimum level, hours of DGS
operation and frequent start/stop of DGS. Thus, the
analysis has figured out few sensitive parameters,
which need to be taken into account during system
design and feasibility study. In this study the necessity
of sizing optimization for the IMG is focused, so that,
the optimal sizes and the optimal power management
strategy can be determined effectively by utilizing the
flowcharts of the PMSs.
ACKNOWLEDGEMENT
The first author would like to thank Ministry of
Training, Colleges, and Universities, Ontario, and
Natural Sciences and Engineering Research Council
(NSERC), Canada, for awarding Ontario Graduate
Scholarship (OGS) and Canada Graduate Scholarship
(Doctoral), respectively.
REFERENCES
Arriaga M., Canizares C. A., and Kazerani M. “Re‐newable
energy alternatives for remote communities in northern
ontario, Canada.”IEEE Trans. on Sust. Energy 4(3); (2013):
661−70.
Ashari M., Nayar C. V. “An optimum dispatch strategy
using set points for a photovoltaic (PV)‐diesel‐battey
hybrid power system.” Solar Energy 66(1); (1999): 1−9.
Bagen, Billinton R. “Evaluation of different operating
strategies in small stand‐alone power systems.” IEEE
Trans. Energy Convers 20(3); (2005): 654−60.
Barley C. D., Winn C. B., “Optimal dispatch strategy in
remote hybrid power systems.” Solar Energy 58(4‐6);
(1996): 165−79.
Bernal‐Agustin J. L, Dufo‐Lot’pez R. “Simulation and
optimization of stand‐alone hybrid renewable energy
systems.” Renew and Sust Energy Rev. 13(8); (2009) :
2111−18.
Bhuiyan F. A., Yazdani A. “Reliability assessment of a
wind‐power system with integrated energy storage.” IET
Renew Power Generation 4(3); (2010); 211−20.
Drouilhet S., Johnson B. L., Drouilhet S. and Johnson L.: “A
battery life prediction method for hybrid power
applications.” National Renewable Energy Labora‐tory,
US Dept. Energy, Chicago, IL 1997; Contract
DE‐AC36‐83CH10093.
Dufo−López R., Bernal‐Agustín J. L. “Design and control
strategies of PV‐Diesel systems using genetic
algorithms.” Solar Energy 79(1); (2005): 33−46.
Ipsakis D., Voutetakis S., Seferlis P., Stergiopoulos F., and
Elmasides C. “Power management strategies for a
stand‐alone power system using renewable energy
sources and hydrogen storage.” International Journal of
Hydrogen Energy 34(16); (2009): 7081−95.
www.ijesci.org International Journal of Energy Science (IJES) Volume 3 Issue 6, December 2013
394
Katiraei F., Abbey C. “Diesel plant sizing and perfor‐mance
analysis of a remote wind‐diesel microgrid.” IEEE PES
Gener Meeting 2007; p. 1−8.
Lee D. J., Wang L. “Small−signal stability analysis of an
autonomous hybrid renewable energy power
generation/energy storage system part I: time‐domain
simulations.” IEEE Trans. Energy Convers 23(1); (2008):
311−20.
Lin W. M., Hong C. M., and Chen C. H. “Neural‐network
‐based MPPT control of a stand‐alone hybrid power
generation system.” IEEE Trans. Power Elec‐tronics
26(12); (2011): 3571−81.
Lujano‐Rojas J. M., Monteiro C., Dufo‐López R., and
Bernal‐Agustin J. L. “Optimum load management
strategy for wind/diesel/battery hybrid power systems.”
Renewable Energy44 (2012): 288−95.
Ohsawa Y., Emura S., and Arai K. “Optimal operation of
photovoltaic/diesel power generation system by neural
network.” Proc. of the second international forum on
application of neural networks to power system (1993); p.
99−103.
Saha T. K., Kastha D. “Design optimization and dynamic
performance analysis of a stand‐alone hybrid wind‐diesel
electrical power generation system.” IEEE Trans. Energy
Convers 25(4); (2010): 1209−17.
Subcommittee P. M. “IEEE reliability test system.” IEEE
Trans. on Power Appar. and Syst. PAS‐98(6); (1979):
2047−54.
Vrettos E. I., Papathanassiou S. A. “Operating policy and
optimal sizing of a high penetration RES‐BESS system for
small isolated grids.” IEEE Trans. Energy Convers 26(3);
(2011): 744−56.
Weis T. M., Ilinca A. “The utility of energy storage to
improve the economics of wind−diesel power plants in
Canada.” Renewable Energy 33(7); (2008): 1544−57.
Yasin A., Napoli G., Ferraro M, Testa A., and Antonucci V.
“Fuzzy logic based management of a stand‐alone hybrid
generator.” Clean Electric Power Confer, Italy (2011); p.
690−6.
Zhou W., Lou C., Lu L., and Yang H. “Current status of
research on optimum sizing of stand‐alone hybrid˝
solarUwind power generation systems.” Applied Energy
87(2); (2010): 380−9.
Zhou T., François B. “Energy management and power
control of a hybrid active wind generator for distributed
power generation and grid integration.” IEEE Trans.
Indus. Electronics 58(1); (2011): 95−104.
Zhu, J.: Optimization of power system operation, Wiley‐IEEE
Press, 2009.
HOMER:ʺhttp://www.nrel/gov/HOMER.“
HYBRID2:ʺhttp://www.ceere.org/rerl/projects/software/hybri
d2/.“
iHOGA:ʺhttp://www.unizar.es/rdufo/hoga‐eng. htm.“
INSEL:ʺhttp://www.insel.eu.“
RETScreen:ʺhttp://www.retscreen.net/.“
TRANSYS:ʺhttp://www.trnsys.com/.“
Available at:“http://climate.weatheroffice.gc.ca/ʺ. ac‐cessed
Nov. 2012.