Modeling of Switching Transients in Nysted Offshore …etd.dtu.dk/thesis/242550/thesis_iaa.pdf · 3...
Transcript of Modeling of Switching Transients in Nysted Offshore …etd.dtu.dk/thesis/242550/thesis_iaa.pdf · 3...
Iván Arana Aristi, s060768
Modeling of Switching
Transients in Nysted Offshore
Wind Farm and a Comparison
with Measurements
EMT Simulations with Power Factory and
PSCAD
Master of Science Thesis, June 2008
Iván Arana Aristi, s060768
Modeling of Switching
Transients in Nysted Offshore
Wind Farm and a Comparison
with Measurements
EMT Simulations with Power Factory and
PSCAD
Master of Science Thesis, June 2008
2
3
Modeling of Switching Transients in Nysted Offshore Wind Farm and a Comparison with Measurements, EMT Simulations in Power Factory and PSCAD
This report was drawn up by: Iván Arana Aristi Supervisor(s): Arne Hejde Nielsen Joachim Holbøll Ole Holmstrøm Poul Sørensen Troels Sørensen
DTU Elektro Centre for Electric Technology (CET) Technical University of Denmark Elektrovej Building 325 2800 Kgs. Lyngby Denmark www.elektro.dtu.dk/ Tel: (+45) 45 25 35 00 Fax: (+45) 45 88 61 11 E-mail: cet@ elektro.dtu.dk
Release date:
30 June 2008
Category:
1
Edition:
1st edition
Comments:
This report is part of the requirements to achieve the Master of Science in Wind Energy at the Technical University of Denmark.
This report represents 30 ECTS points.
Rights:
©Iván Arana, 2008
4
5
ABSTRACT
This report was prepared as part of the requirements to achieve the Master of Science in
Wind Energy with Electrical Engineering Specialization at the Technical University of
Denmark (DTU).
In the recent years there has been a particular interest in the collection grid of large
offshore wind farms. This is due to the expected increase in size, and investment, of
these wind power plants in the following years. However, the electrical conditions
present in the collection grid are not alike any other industrial application. The length of
MV cable is remarkable; as well as the number of switchgears and transformers. This
combination of components creates an electrical environment never assemble before.
In 2007 field measurements are done in Nysted Offshore Wind Farm, where three GPS
synchronized measuring systems have been built and used for simultaneous
measurement at three different locations in the wind farm. The measurement system and
the measurements performed were within the project entitled “Voltage conditions and
transient phenomena in medium voltage grids of modern wind farms”, funded by
Energinet.dk.
A comprehensive explanation of the modeling and transient phenomena, of some
electrical devices present in the collection grid of Nysted, was made; followed by a
simple case to compare the models -for some devices- in Power Factory and PSCAD.
Then, based on three measured switching events in the wind farm, three study cases
were created in both simulation programs. Here, the standard models of the electrical
devices were used to assemble the collection grid of Nysted and compare the results
from both simulations with the measurements.
After the digital models in both programs were evaluated, an assessment on the voltage
dip due to the sequential energization of different amount and combination of wind
turbine transformers was made. Finally, a comparison of both programs was created for
electromagnetic transient simulations; as well as guidelines to energize the collection
grid in large wind farms and a list of information required for switching transient
studies.
Kgs. Lyngby, 2008-06-30
6
7
ACKNOWLEDGEMENTS
This thesis work was conducted at DONG Energy. I would like to express my deepest
gratitude to my supervisor Troels Sørensen for providing me with the opportunity to
work in an excellent engineering environment and for all his time, guidance and
support.
I am grateful as well to Arne Hejde Nielsen, Joachim Holbøll, Poul Sørensen and Ole
Holmstrøm for their valuable discussions and supervision.
Special thanks goes to Mogens Henriksen and Asger Jensen, who believed in me since
the beginning.
I am extremely grateful as well with Saeed Rahimi for his help with the modeling part
and his constant guidance, suggestion and valuable input to this work.
I would like to acknowledge the other people who have helped and encouraged me. I
want to thank Braulio Barahona, Morten Lunow, Aleksander Derdowski, Daniel
Villarreal and particularly Ari Bronstein
To Javier, for being the best role model a son can have; to my sisters Lucia and Teresa,
and to my aunts Enriqueta and Silvia.
I also want to thank my friends in Denmark for being with me during these two years,
especially to Lucia, Cris, Mercè, Elie, Xavier, Leo, Andrzej, Bernt, Bing, Carlos, Iván
and Sonsoles. To my friends from Mexico: Ana, Mario, Juan Raul, Evelyn, Mariana,
Miguel, Jorge, Mauricio, Christian and Erick.
Last but not least, I am deeply indebted with Esperanza for her support and concern
during the entire period of my thesis.
9
TABLE OF CONTENTS
1 Preface.................................................................................................................... 23
1.1 Background ...................................................................................................... 24
1.2 Objectives ......................................................................................................... 24
1.3 Problem formulation ........................................................................................ 24
1.4 Method and limitations .................................................................................... 25
1.5 Work by others ................................................................................................. 27
1.6 Guide on how to read the report ....................................................................... 30
2 Switching transients .............................................................................................. 33
2.1 Switching transients studies ............................................................................. 33
2.2 Transient recovery voltage ............................................................................... 34
2.3 Inrush current calculations in transformers ...................................................... 35
3 Measurements at Nysted Offshore Wind Farm ................................................. 37
3.1 Nysted Offshore Wind Farm ............................................................................ 37
3.2 Measurements .................................................................................................. 38
3.3 Study cases ....................................................................................................... 41
3.3.1 Case 1. First closing of the line breaker for line A ................................... 41
3.3.2 Case 2. Second closing of the line breaker for line A............................... 45
3.3.3 Case 3. Closing of the breaker on wind turbine A9 .................................. 46
3.4 Analysis of voltage and current measurements ................................................ 49
3.4.1 Voltage dip standards................................................................................ 49
3.4.2 Rms calculations ....................................................................................... 50
3.4.3 Power calculations .................................................................................... 50
3.4.4 FFT in current ........................................................................................... 50
3.5 State of the NWP when the measurements were done ..................................... 53
3.6 Steady state for case 1 and case 2 .................................................................... 55
4 Electrical equipment in simulation programs .................................................... 57
4.1 Network ............................................................................................................ 57
4.2 Wave theory ..................................................................................................... 57
4.3 Switchgear ........................................................................................................ 60
4.3.1 Circuit breaker modeling .......................................................................... 61
4.3.2 Vacuum circuit breaker ............................................................................. 63
4.3.3 Vacuum circuit breaker modeling............................................................. 66
Table of contents
10
4.4 Transformers ..................................................................................................... 67
4.4.1 Simple transformer model ......................................................................... 68
4.4.2 Switching transient studies in transformers............................................... 69
4.4.3 Magnetic characteristic of the transformer ................................................ 71
4.4.4 Simple case simulation .............................................................................. 74
4.4.5 Further inrush current control.................................................................... 87
4.5 High voltage cables........................................................................................... 88
4.5.1 Cable modeling theory .............................................................................. 88
4.5.2 Cable modeling application ....................................................................... 88
4.5.3 Conductive materials ................................................................................. 89
4.5.4 Insulating materials ................................................................................... 90
4.5.5 Grounding .................................................................................................. 91
4.5.6 Sensitivity of transients ............................................................................. 91
4.5.7 Simple case in Power Factory ................................................................... 92
4.5.8 Simple case in PSCAD .............................................................................. 95
4.5.9 Comparison ............................................................................................... 97
4.6 Voltage source .................................................................................................. 98
4.7 Capacitors bank ................................................................................................ 99
4.8 Generator ........................................................................................................ 101
4.9 Summary ......................................................................................................... 103
5 System modeling .................................................................................................. 105
5.1 General procedure ........................................................................................... 105
5.2 Study case 1: Connection of Row A-I ............................................................ 108
5.2.1 Power Factory.......................................................................................... 108
5.2.2 PSCAD .................................................................................................... 114
5.2.3 Transient comparison .............................................................................. 116
5.2.4 Steady state comparison .......................................................................... 132
5.3 Study case 2: Connection of Row A-II ........................................................... 134
5.3.1 Power Factory and PSCAD ..................................................................... 134
5.3.2 Comparison ............................................................................................. 135
5.4 Study case 3: Switch A09 ............................................................................... 138
5.4.1 Power Factory.......................................................................................... 138
5.4.2 PSCAD .................................................................................................... 139
5.4.3 Wind turbine generator ............................................................................ 140
5.4.4 Comparison ............................................................................................. 141
5.5 Worst case switching- voltage ........................................................................ 156
5.6 Worst case switching -current ........................................................................ 156
5.7 Fit traveling time of the voltage wave ............................................................ 157
5.8 Summary ......................................................................................................... 161
Table of contents
11
6 Voltage dip at the PCC, due to the connection of different amount of
transformers at the same time ................................................................................... 163
6.1 Sequence energization .................................................................................... 164
6.2 Simulation in PF ............................................................................................. 166
6.3 Simulation in PSCAD .................................................................................... 169
6.4 Results ............................................................................................................ 172
7 Conclusions .......................................................................................................... 175
7.1 Results- simulation tools ................................................................................ 175
7.2 Results- required information ........................................................................ 176
7.3 Results- simultaneous energization of transformers ...................................... 176
7.4 Perspectives .................................................................................................... 177
7.5 Further work ................................................................................................... 177
A Non-simultaneous pole closing during three-phase transfromer energization in
Power Factory ............................................................................................................. 183
B Second study case plots ........................................................................................... 187
13
LIST OF FIGURES
Figure 1-1 Overview of case 1 and case 2 ...................................................................... 26
Figure 1-2 Overview of case 3 ........................................................................................ 27
Figure 1-3 Overview of sequential energization of transformers ................................... 27
Figure 1-4 Graphic overview of the project.................................................................... 32
Figure 2-1 Comparison of TRVs for cable systems and line-systems, adopted
from (Dufournet & Montillet, 2005) .................................................................... 34
Figure 3-1 Nysted Offshore Wind Farm ......................................................................... 37
Figure 3-2 Measurements locations, adopted from (Christensen, et al., 2007) .............. 38
Figure 3-3 Measurement at wind turbines, adopted from (Christensen, et al.,
2007) ...................................................................................................................... 39
Figure 3-4 Voltage waveforms for study cases. ............................................................. 39
Figure 3-5 Current waveforms for study cases ............................................................... 40
Figure 3-6 Case 1. Voltage 0-250 ms ............................................................................. 41
Figure 3-7 Case 1. Voltage 0-50 ms ............................................................................... 42
Figure 3-8 Case 1. Voltage 4,3-5 ms .............................................................................. 42
Figure 3-9 Case 1. Current 0-250 ms .............................................................................. 43
Figure 3-10 Case 1. Current 0-50 ms .............................................................................. 44
Figure 3-11 Case 1. Current 4,3-5 ms ............................................................................. 44
Figure 3-12 Case 2. Voltage 20-21 ms ........................................................................... 46
Figure 3-13 Case 2. Current 0-250 ms ............................................................................ 46
Figure 3-14 Case 3. Voltage 0-50 ms ............................................................................. 47
Figure 3-15 Case 3. Current 0-50 ms .............................................................................. 48
Figure 3-16 Case 3. Voltage and current 2,5-8 ms ......................................................... 48
Figure 3-17 Usual form of voltage change caused by motor starting, adopted
from (ENA, 1989.) ................................................................................................ 49
Figure 3-18 Case 1-A01. Current 0-500 ms ................................................................... 51
Figure 3-19 Case 1-A09. Current 0-500 ms ................................................................... 51
List of figures
14
Figure 3-20 Case 1-A01 and A09. FFT on current ......................................................... 52
Figure 3-21 Active power measurements, 10 min average ............................................. 53
Figure 3-22 Reactive power measurements, 10 min average .......................................... 54
Figure 4-1 Case 1. Voltage phase B 4,3-4,6 ms .............................................................. 60
Figure 4-2 Pre-strike effect in circuit breakers, adopted from (PSCAD User's
Guide, 2005) .......................................................................................................... 65
Figure 4-3 Transformer model used in (Popov, et al., 2001) .......................................... 68
Figure 4-4 Simple transformer equivalent ....................................................................... 68
Figure 4-5 Impedance magnitude and angle of a wind turbine transformer,
adopted from (Pedersen, et al., 2005) .................................................................... 70
Figure 4-6 A very detailed model adopted from (de Leon, et al., 1994) ......................... 71
Figure 4-7 Simple case-transformer. Power Factory system .......................................... 74
Figure 4-8 Simple case- transformer. Single phase a). Voltage, current and
flux. ........................................................................................................................ 75
Figure 4-9 Simple case- transformer. Single phase a). Voltage, current and
flux. 500 ms ........................................................................................................... 76
Figure 4-10 Current- flux characteristic of transformers in Power Factory .................... 77
Figure 4-11 Simple case- transformer. Single phase b). Voltage, current and
flux ......................................................................................................................... 77
Figure 4-12 Simple case- transformer. Single phase c). Voltage, current and
flux ......................................................................................................................... 78
Figure 4-13 Simple case- transformer. Single phase a), b), c), d) e) and f). Zero
crossing (top) and peak crossing (bottom). Voltage and flux ................................ 79
Figure 4-14 Simple case- transformer. Single phase, all. Voltage (top) and flux
(bottom).................................................................................................................. 80
Figure 4-15 Simple case- transformer. Three phase. Zero voltage switching ................. 81
Figure 4-16 Simple case- transformer. Three phase. Peak voltage switching. ............... 82
Figure 4-17 Simple case- transformer. Three phase. With residual flux.
Voltages ................................................................................................................. 83
Figure 4-18 Simple case- transformer. Three phase. With residual flux. Fluxes ............ 83
Figure 4-19 Simple case- transformer. Three phase. With residual flux. Current .......... 84
Figure 4-20 Residual flux and voltages. Left φd=0, φq=-1. Right φd=-1, φq=0 ............ 84
Figure 4-21 PSCAD transformer equivalence................................................................. 85
Figure 4-22 Simple case- transformer. PSCAD .............................................................. 86
Figure 4-23 Simple case-transformer. PSCAD. Results ................................................. 87
List of figures
15
Figure 4-24 Simple case- cable. Power Factory. Network ............................................. 92
Figure 4-25 Simple case- cable. Power Factory. Single core cables .............................. 93
Figure 4-26 Simple case- cable. Power Factory. Three phase cable .............................. 94
Figure 4-27 Simple case- cable. Power Factory. Cable system, basic data .................... 94
Figure 4-28 Simple case- cable. Power Factory. Cable system, EMT
simulations............................................................................................................. 95
Figure 4-29 Simple case- cable. PSCAD. Network ........................................................ 96
Figure 4-30 Simple case- cable. PSCAD. Cable configuration. ..................................... 96
Figure 4-31 Single case- Cable. Comparison ................................................................. 97
Figure 4-32 Capacitor bank .......................................................................................... 100
Figure 4-33 Capacitor bank impedance characteristic .................................................. 101
Figure 4-34 Simple case- Generator. Network ............................................................. 102
Figure 4-35 Simple case- Generator. Rotor speed ........................................................ 103
Figure 5-1 Simplified network for study case 1, 2 and 3 .............................................. 106
Figure 5-2 Case 1. Power Factory. HV network........................................................... 108
Figure 5-3 Case 1. Power Factory. MV network .......................................................... 109
Figure 5-4 Case 1. Power Factory. Sheath network ..................................................... 110
Figure 5-5 Case 1. Power Factory. A01........................................................................ 111
Figure 5-6 Case 1. Power Factory. Cable 50 mm ......................................................... 111
Figure 5-7 Case 1. Power Factory. Cable 50 cm .......................................................... 112
Figure 5-8 Case 1. Power Factory. Separation ............................................................. 112
Figure 5-9 Case 1. Power Factory. Phase voltage B ..................................................... 114
Figure 5-10 Case 1. PSCAD. HV network ................................................................... 115
Figure 5-11 Case 1. PSCAD. MV network .................................................................. 115
Figure 5-12 Case 1. PSCAD. A01 ................................................................................ 116
Figure 5-13 Case 1. Platform voltages (4,3-5,5 ms) ..................................................... 117
Figure 5-14 Case 1. Phase A voltage for each location (4,3-5,5 ms) ........................... 117
Figure 5-15 Case 1. Phase B voltage for each location (4,3-5,5 ms)............................ 118
Figure 5-16 Case 1. Phase C voltage for each location (4,3-5,5 ms)............................ 118
Figure 5-17 Case 1. Platform voltages (4-10 ms) ......................................................... 119
Figure 5-18 Case 1. Platform voltages (4-50 ms) ......................................................... 119
Figure 5-19 Case 1. Platform currents (4-5,5 ms) ........................................................ 120
Figure 5-20 Case 1. Platform currents (4-50 ms) ......................................................... 121
List of figures
16
Figure 5-21 Case 1. A01 currents (0-50 ms) ................................................................. 121
Figure 5-22 Case 1. A01 currents (0-500 ms) ............................................................... 122
Figure 5-23 Case 1. A01 currents FFT .......................................................................... 123
Figure 5-24 Case 1. A09 currents (0-50 ms) ................................................................. 123
Figure 5-25 Case 1. A09 currents (0-500 ms) ............................................................... 124
Figure 5-26 Case 1. A09 currents (4-6 ms) ................................................................... 124
Figure 5-27 Case 1. A09 current phase B (4-6 ms) ....................................................... 125
Figure 5-28 Case 1. Rms current at platform................................................................. 125
Figure 5-29 Case 1. Rms current at A01 and A09 ......................................................... 126
Figure 5-30 Case 1. Active power at platform .............................................................. 127
Figure 5-31 Case 1. Active power at A01 and A09 ...................................................... 128
Figure 5-32 Case 1. Reactive power at platform ........................................................... 128
Figure 5-33 Case 1. Reactive power at A01 and A09 ................................................... 129
Figure 5-34 Case 1. Rms voltage at platform ................................................................ 130
Figure 5-35 Case 1. Rms voltage from measurements .................................................. 131
Figure 5-36 Case 1. Rms voltage from Power Factory .................................................. 131
Figure 5-37 Case 1. Rms voltage from PSCAD ............................................................ 132
Figure 5-38 Case 1. Power Factory. Steady state .......................................................... 133
Figure 5-39 Case 2. Platform voltages (20-22 ms) ....................................................... 135
Figure 5-40 Case 2. Platform currents (20-70 ms) ........................................................ 136
Figure 5-41 Case 2. A01currents (10-70 ms) ................................................................ 136
Figure 5-42 Case 2. A09 currents (10-70 ms) ............................................................... 137
Figure 5-43 Case 2. Rms voltage at platform ................................................................ 137
Figure 5-44 Simplified network for study case 3 .......................................................... 138
Figure 5-45 Case 3. Power Factory. MV network. ....................................................... 139
Figure 5-46 Case 3. PSCAD. Induction generator ........................................................ 140
Figure 5-47 Active power characteristic of induction generator ................................... 141
Figure 5-48 Reactive power characteristic of induction generator ............................... 141
Figure 5-49 Case 3. Phase A voltage for each location (2-6 ms) .................................. 142
Figure 5-50 Case 3. Phase B voltage for each location (2-6 ms) .................................. 143
Figure 5-51 Case 3. Phase C voltage for each location (2-6 ms) .................................. 143
Figure 5-52 Case 3. A01 voltages (2-6 ms)................................................................... 144
Figure 5-53 Case 3. A01 currents (0-400 ms) ............................................................... 144
List of figures
17
Figure 5-54 Case 3. A01 currents (300-400 ms) .......................................................... 145
Figure 5-55 Case 3. A09 currents (0-400 ms) .............................................................. 145
Figure 5-56 Case 3. A09 currents (0-50 ms) ................................................................ 146
Figure 5-57 Case 3. A09 currents (2-7 ms) .................................................................. 146
Figure 5-58 Case 3. Phase B currents in A09 (2-7 ms) ................................................ 147
Figure 5-59 Case 3. Rms currents at platform .............................................................. 147
Figure 5-60 Case 3. Rms currents at A01 and A09 ....................................................... 148
Figure 5-61 Case 3. Active power at platform.............................................................. 149
Figure 5-62 Case 3. Active power at A01 and A09 ...................................................... 149
Figure 5-63 Case 3. Influence of generators inertia in active power at platform ......... 151
Figure 5-64 Case 3. Reactive power at platform .......................................................... 153
Figure 5-65 Case 3. Reactive power at A01 and A09 .................................................. 153
Figure 5-66 Case 3. Rms voltage at platform................................................................ 154
Figure 5-67 Case 3. Rms voltage from measurements.................................................. 154
Figure 5-68 Case 3. Rms voltage from Power Factory ................................................. 155
Figure 5-69 Case 3. Rms voltage from PSCAD............................................................ 155
Figure 5-70 Worst case switching at peak voltage ....................................................... 156
Figure 5-71 Worst case switching at zero voltage ........................................................ 157
Figure 5-72 Fit traveling time of voltage wave. Power Factory. Relative
permittivity. ......................................................................................................... 158
Figure 5-73 Fit traveling time of voltage wave. Power Factory. Frequency. ............... 158
Figure 5-74 Fit travelling time of voltage wave. Comparison ...................................... 160
Figure 6-1 Overview of sequential energization of transformers ................................. 163
Figure 6-2 Sequencial energization. Power Factory. Saturation exponent. .................. 164
Figure 6-3 Sequence energization. Power Factory. Vzero A01-A09 ........................... 166
Figure 6-4 Sequence energization. Power Factory. Vzero ........................................... 167
Figure 6-5 Sequence energization. Power Factory. Vpeak ........................................... 167
Figure 6-6 Sequence energization. Power Factory. Row B .......................................... 168
Figure 6-7 Sequence energization. Power Factory. Residual flux ................................ 168
Figure 6-8 Sequence energization. Power Factory. Reduced grid ................................ 169
Figure 6-9 Sequence energization. PSCAD. Vzero ...................................................... 170
Figure 6-10 Sequence energization. PSCAD. Vpeak ................................................... 170
Figure 6-11 Sequence energization. PSCAD. Vzero. Rms each cycle ......................... 171
List of figures
18
Figure 6-12 Sequence energization. PSCAD. Vpeak. Rms each cycle ......................... 171
Figure 7-1 Non-simultaneous pole closing with 0,02 ms apart ..................................... 184
Figure 7-2 Non-simultaneous pole closing with 2 ms apart .......................................... 184
Figure 7-3 Non-simultaneous pole closing with 3,33 ms apart ..................................... 185
Figure 7-4 Non-simultaneous pole closing with 5 ms apart .......................................... 185
Figure 7-5 Non-simultaneous pole closing with 6,66 ms apart ..................................... 186
Figure 7-6 Case 2. Phase A voltage for each location (20-22 ms) ................................ 187
Figure 7-7 Case 2. Phase B voltage for each location (20-22 ms) ................................ 187
Figure 7-8 Case 2. Phase C voltage for each location (20-22 ms) ................................ 188
Figure 7-9 Case 2. Phase A voltage for each location (20-20,5 ms) ............................. 188
Figure 7-10 Case 2. Platform voltages (20-30 ms) ....................................................... 189
Figure 7-11 Case 2. Platform voltages (10-60 ms) ....................................................... 189
Figure 7-12 Case 2. Platform currents (20-22 ms) ........................................................ 190
Figure 7-13 Case 2. A01currents (0-500 ms) ................................................................ 190
Figure 7-14 Case 2. A09 currents (0-500 ms) ............................................................... 191
Figure 7-15 Case 2. A09 currents (20-21,5 ms) ............................................................ 191
Figure 7-16 Case 2. A09 current phase A (20-21,5 ms)................................................ 192
Figure 7-17 Case 2. A09 current phase B (20-21,5 ms) ................................................ 192
Figure 7-18 Case 2. Platform current (400-500 ms) ..................................................... 193
Figure 7-19 Case 2. Rms currents at platform ............................................................... 193
Figure 7-20 Case 2. Rms currents at A01 and A09 ....................................................... 194
Figure 7-21 Case 2. Active power at platform .............................................................. 194
Figure 7-22 Case 2. Active power at A01 and A09 ...................................................... 195
Figure 7-23 Case 2. Reactive power at platform ........................................................... 195
Figure 7-24 Case 2. Reactive power at A01 and A09 ................................................... 196
Figure 7-25 Case 2. Rms voltage from measurements .................................................. 196
Figure 7-26 Case 2. Rms voltage from Power Factory .................................................. 197
Figure 7-27 Case 2. Rms voltage from PSCAD ............................................................ 197
19
LIST OF TABLES
Table 3-1 Harmonic current ratio ................................................................................... 52
Table 3-2 Steady state (0,5 s) for case 1 and case 2 ....................................................... 56
Table 4-1 Modeling guidelines adopted from (CIGRE, 1998) ....................................... 63
Table 4-2 Accepted values for equation (4.10)............................................................... 67
Table 4-3 Color nomenclature. Three phase, without residual flux. .............................. 81
Table 4-4 Color nomenclature. Three phase, with residual flux .................................... 82
Table 4-5 Material properties in cables .......................................................................... 89
Table 4-6 XLPE relative permittivity ............................................................................. 90
Table 4-7 Simple case- cable. Information ..................................................................... 92
Table 5-1 Input information and models in both simulation tools ............................... 107
Table 5-1 Case 1. Power Factory. Cable 50 mm .......................................................... 111
Table 5-2 Case 1. Power Factory. Cable 50 cm............................................................ 112
Table 5-3 Case 1. Power Factory. Pre-strike times....................................................... 113
Table 5-4 Case 1. Active and reactive power during the first cycle. ............................ 129
Table 5-5 Steady state values (at 25 cycles) for current and voltages .......................... 134
Table 5-6 Steady state values (at 25 cycles) for real and reactive power ..................... 134
Table 5-7 Reactive power comparison in MVAr .......................................................... 152
Table 6-1 Times for sequencial energization in seconds .............................................. 165
Table 6-2 Sequence energization results ...................................................................... 172
Table 7-2 Color nomenclature for appendix A ............................................................. 183
Table 7-3 Non-simultaneous simulation cases ............................................................. 183
21
LIST OF SYMBOLS
Symbol Unit Definition
C F Capacitance
G S Conductance
L H Inductance
R Ω Resistance
φd p.u. Residual flux in d-axis
φd p.u. Residual flux in q-axis
22
LIST OF ABBREVIATIONS
Abbreviation Meaning
CB Circuit breaker
CIGRE International Council on Large Electric Systems
DAQ Data acquisition
emt Electromagnetic transient
EMTP The Electromagnetic Transients Program
FFT Fast Fourier Transform
HF High frequency
HV High voltage
IEC International Electrotechnical Commission
IEEE Institute of Electrical and Electronics Engineers,
LV Low voltage
MV Medium voltage
NOWF Nysted Offshore Wind Farm
p.u. Per unit
PCC Point of common coupling
Power Factory Power Factory/DIgSILENT
PSCAD PSCAD/HVDC
rms Root mean square
TOV Transient Overvoltage
TRV Transient recovery voltage
UK United Kingdom
VCB Vacuum circuit breaker
WT Wind turbine
WTs Wind turbines
23
1 PREFACE
The offshore wind power in the UK is expected to increase largely in the following
years. In his first environmental policy speech in November 2007, Prime Minster
Gordon Brown announced that the present British reduction target for CO2 emissions
might have to be raised by 2050. This legislative objective promotes the increase of
renewable energy in the UK, and since wind energy is the most technically mature and
cost-effective of the new energies, it is predicted that the amount of wind power will
increase rapidly during the coming years.
So far there have been two calls for bids to develop UK offshore wind sites, known as
Round 1 and Round 2. The first phase‟s successful applicants were announced in 2001,
with leases awarded for 18 sites at 13 locations. In this pilot phase the sites were limited
to a maximum of 30 turbines. In 2003 the final results of Round 2 were announced, with
the right to develop 15 sites totaling 5,4-7,2 GW awarded to 10 companies or consortia.
Round 2 sites are larger than Round 1 sites and will utilize more powerful machines, at
greater distance from shore, with no maximum limit of turbines. Some of the sites are as
big as 1 GW.
The 90 MW Burbo Bank park of DONG Energy was connected last October. DONG
Energy will also build and operate the two offshore wind parks Walney Island with 151
MW and Gunfleet Sands with 173 MW off the British coast by 2010.
According to the British Engineering Recommendations P28, the voltage fluctuation at
the point of connection with the grid may be required to be as low as 3% during the
energization of a motor; and since the energization of a transformer is similar to the
direct-on-line starting of induction motors, this recommendation automatically applies
to the transformers.
For the thesis, site measurements of three switching operations in Nysted Offshore
Wind Farm were used to implement a digital model of the collection grid in Power
Factory and PSCAD. Then, the results from the switching operations in both programs
were compared to the measurements with acceptable agreement.
Finally, once the models have been verified, different combinations of transformers
were switched-in at different times, and the voltage drop at the point of common
coupling was compared. In general, the results from Power Factory regarding two
Preface
24
energizing sequences were contradictory, since a large voltage dip was present ever
though the inrush current had not increase dramatically.
Finally, a comparison of both programs was created for electromagnetic transient
simulations; as well as guidelines to energize the collection grid in large wind farms and
a list of information required for switching transient studies.
1.1 Background
The collection grid of large offshore wind farms are especially vulnerable to switching
operation, due to the electrical environment assemble in the sea. And since the wind
power plants are expected to increase in size and investment, the industry is particularly
interested in the prediction of possible risks to protect their wind farms.
The problem with switching transient studies is that the information needed for almost
every electrical device is very detailed, and the manufacturers are unwilling to provide
this information to the system designer.
On the other hand, there are grid requirements that the wind power plant has to comply
in order to connect with the network. This grid codes are defined by the Transmission
System Operator of each country, and some of them are not updated to regulate
correctly the operation of large wind power plants.
1.2 Objectives
The main aim of this thesis was to simulate three switching events in two simulation
programs and compare the results with measurements. Once the models were validated,
an assessment on the voltage dip due to the sequential energization of different amount
of wind turbine transformers was prepared, in order to create general guidelines to
energize the collection grid in large wind farms.
Another important goal of this thesis was to compare Power Factory and PSCAD for
electromagnetic transient simulations. In addition to this, it was also fundamental to
catalog the critical component data required for switching transient studies.
1.3 Problem formulation
The offshore wind farms are expected to increase in size and power; so far, there have
been successful applications in Denmark and the UK. However, the best way for
protection and risk assessment, is the accurate prediction of possible occurrences. On
this basis the project answers the following questions:
Are there major differences in the results from electromagnetic transients in
Power Factory and PSCAD?
How good can the simulation programs predict the transient behavior in cables
during energization?
Preface
25
What information is needed to simulate the possible events in the switchgear?
How accurate are the models for transformers, and what other information
would be relevant to obtain from the manufacturer for transient studies?
How good does the voltage dip, caused by the energization of a transformer, is
simulated in Power Factory and PSCAD?
1.4 Method and limitations
In order to create the digital network of Nysted Offshore Wind Farm, the available
information from each component had to be found and compare. This was a
complicated task since this wind power plant was installed in the year 2003, and some
changes were done from the first draft of the wind farm to the actual installation.
Then, based on the measurements log, relevant switching operations were selected as
the study cases to be simulated and compared between the two programs. Once the
events were selected, the state of the system was deduced from the available
measurements and the experience of the operator.
Afterwards, the standard models in Power Factory and PSCAD for the electrical devices
connected in the study cases were compared in both programs. Subsequently, three
study cases were simulated and compared in Power Factory and PSCAD. Just then, with
acceptable correspondence between the results from both digital systems and the
measurements, the voltage dip was assessed.
Since the results from the simulations were compared with measurements, it was
assumed from the beginning that the measurements were correct. As the comparison
from the third study case showed, the uncertainties of the measurement system are less
than 2%.
The measurement data and the results from the simulations were analyzed and
compared in MATLAB; here predefined subroutines and commands were used for the
analysis, but in general all the necessary code was created.
One very important value not available from the datasheets was the open circuit
characteristic of the transformer; however after several simulations using estimated
values, a saturated reactance was found to give similar results as the measurements. At
this stage it was also assumed that all transformers in the simulations had the same
characteristics. This was a reasonable assumption since no additional information was
available.
As explained further in the document, the pre-strike phenomenon in the vacuum circuit
breaker was not simulated, since there was no information about the breaker and the
time for the project was limited.
Preface
26
The residual flux in the transformer model in PSCAD was not used, since the scenario
for sequence energization of transformers with residual flux is not a realistic situation in
Nysted Offshore Wind Farm.
All the models used in Power Factory and PSCAD are standard models without
additional control parameters, or dynamic properties beside the transient phenomenon
simulated.
Every time a problem occurred in both simulation programs, the support team from each
program helped as much as they could, and the results presented here are the final
outcome after many preliminary simulations. However, one of the main objectives of
the project was to compare Power Factory and PSCAD for electromagnetic transient
studies, and some limitations were noticed for both simulation tool.
In general three systems were created from scratch in each program. The model for the
first and second study case is shown in Figure 1-1. The third study case is shown in
Figure 1-2, and the Figure 1-3 presents the network for the sequencial energization. In
these three figures the equipment in red color are the energized devices and the
equipment in black color are the non-energized devices prior to the switching event.
Additional discussion on each study case and modeling procedure was done further in
the report.
Figure 1-1 Overview of case 1 and case 2
Preface
27
Figure 1-2 Overview of case 3
Figure 1-3 Overview of sequential energization of transformers
1.5 Work by others
Switching transient studies in large offshore wind farms using PSCAD have been done
before in (Liljestrand, Sannino, Breder, & Thorburn, 2008), while in (R. King, 2008) the
simulation program used is EMTP-RV. In both papers the pre-strike during cable
energization, within the breaker is modeled. Sørensen, in (Sørensen, et al., 2007),
models the cable energization in Power Factory corresponding to the first case study of
this thesis. Abdulahovic, in (Abdulahovic & Thiringer, 2007) simulated, the
energization of a wind park radial (in the current project the radials in the wind farms
Preface
28
were referred to as rows). In this paper, the comparison between simulations and
measurements of the energization of a MV cable with several wind turbines is done,
with reasonable agreement between simulations and measurements.
Liljestrand concluded that the electrical stress on transformers during transients depends
on the wave propagation in the collection grid and their location in the system. King
focused on the voltage reflections and cable charging currents.
Sørensen conluded that there are some limitations in Power Factory when modeling
cables for switching transients studies. This paper is highly practical, with little
emphasis on theory, but it is the starting point for this project. In the paper, the authors
initially simulated with the basic equipment models; a lumped () parameter model for
the cables, a switch for the circuit breaker and a T-equivalent for the transformers.
Then, the frequency for fitting the distributed line parameter model with constant
parameters was calculated. Afterwords, an FFT on the simulated current with the
lumped model is made to identify the resonant frequency (1959 Hz).
Once the model is updated, the switching event is repeated. In the simulation results
they found a problem with the appearance of a voltage on phases that were not
connected yet.
Finally, they included a HV-ground capacitance in the transformer model to obtain the
current peaks that have been seeing on the measurements when the voltage waves arrive
at each transformer. At this stage they estimate a capacitance value and conclude that
the current peaks are very sensitive to this parameter.
The current project is important because no work has been done to compare the
behavior of standard models of electrical devices in offshore wind farms in both Power
Factory and PSCAD. Neither simulations nor measurements had been compared for
these very large wind farms when high quality measurements have been available.
Some work regarding the voltage dip due to sequential energization of different number
of transformers in wind farms has been carried out before in (Ma & Cadmore, 2006),
(Smith, 2005) and (Abdulahovic & Thiringer, 2007). In (Rioual & Sow, 2008) a study
of symathetic interaction during transformer‟s energization in wind farms was realized.
Ma investigated possible solutions to the fulfillment of the UK recommendations for
voltage dips in (Ma & Cadmore, 2006). Here, two types of transformers were compared
in two different sites (2x10 turbines and 1x17 turbines):
The standard design transformer with 7,35 p.u. peak current and 1,6 s to damped
the current.
The special design transformer with 4,04 p.u. peak current and 1 s to damped the
current.
Preface
29
For the study, site measurements were done to implement a realistic model in PSCAD.
Once the model in PSCAD has been verified, different amount of transformers are
switched in at the same time, and the voltage drop is compared at 0 ms and 30 ms.
The study results show that:
1. The higher the inrush current magnitude, the higher the voltage dips.
2. Voltage dips decrease when the number of transformers energized
simultaneously is reduced.
3. The energization inrush current is more rapidly damped when there are no
initially energized transformers than with formerly energized transformers.
4. The slow decay of the inrush current with initially energized transformers
prolongs the voltage dip.
5. The voltage dip increases if the voltage of one phase is around zero, when the
system is energized and the three phases are energized non-simultaneously.
Smith investigated the transient inrush current and system voltage drop during the
energization of wind turbine transformers, based on PSCAD simulations, in (Smith,
2005). Here, a generally accepted “worst case” scenario for transformer energization is
presented, where residual flux might be expected upon a random energization (-80%
one phase, +80% second phase and third phase zero).
The author compares two wind farms, one with 15 wind turbines (WTs) connected via a
33 kV and the second with 52 WTs at 33 kV divided in collection rows of nine WTs,
with two parallel step-up transformers to the 132 kV grid.
From the simulations it was found that in order to fulfill the P28 requirements at the
point of common coupling (PCC), fewer transformers could be energized
simultaneously at the smaller capacity wind farm with a 33 kV grid connection.
On the 52 WTs study case, a sympathetic inrush current assessment is made. Here nine
WT transformers are energized simultaneously with only one incoming transformer in
service, while the rest of the wind turbine transformers are on-line; this way achieving
the strongest sympathetic interaction between transformers. The event is made at zero
degrees switching angle and 0,8 pu residual flux. A “sympathetic magnetizing current”
in the on-line transformer around 12 cycles after switching is achieved.
Abdulahovic compared measurements and simulation results from PSCAD during the
energization of a wind park radial in (Abdulahovic & Thiringer, 2007). Here, the master
library components from PSCAD are used for the simulations. The authors divided the
transient event into the phenomena cable energization, followed by the transformer
magnetization. The measurements also show that the voltage rises slightly due to the
reactive power generated by the cable capacitance, at steady state.
Rioual and Sow used EMTP as a simulation tool in (Rioual & Sow, 2008), where the
phenomena of sympathetic interactions between transformers is present. Here, several
transformer are energized simultaneously, then the voltage dip and overvoltage are
calculated.
Preface
30
In the case where five transformers are energized sequentially, with a time delay of 4
seconds between each other, they concluded that due to sympathetic interaction, one of
the transformers is stressed five times during the total energizing procedure. They also
showed that the same transformer experience four times an offset in flux, which causes
high inrush sympathetic-currents. Another important contribution of this sequential
energization simulation is that the voltage dip increases as the energizing sequence
progresses.
Regarding the transformer energization, the current thesis is important because there are
three measurement cases used to compare the transformer characteristics and
realistically approximate and assess the voltage dip.
A very detailed modeling in PSCAD and experimental verification was done in (Daniel
& Gebre, 2008) for transformers and cables commonly used in offshore wind farms.
Here a comprenhensive explanation of the transient phenomena in VCBs, cables and
transformers was made.
For the cables, it was explained that the model that should be used in PSCAD for
switching transients is the “Frequency dependant (phase) model”. A step voltage on
different cables was measured to compare the simulations, obtaining a good agreement.
It was found that additional stray component need to be included in the models, in order
to obtain better results. It was also found that there is faster damping in the cables than
estimated in the simulation.
Regarding the VCB several simulations were done based on (Kondala & Gajjar, 2006)
but no comparison with measurements was made.
The work on the transformer modeling was very extensive; it achived agreement
between measurements, calculations and simulations of the transformer impedance
characteristic.
1.6 Guide on how to read the report
The project is divided in six main sections;
2) Switching transient
3) Network and measurements description
4) Electrical equipment explanation and comparison
5) System modeling
6) Voltage dip due to transformer energization sequence
7) Conclusions
The second section pre1sents some important definitions regarding the switching
transient studies. Here relevant information from current research and industrial
applications was gathered.
Preface
31
The collection grid at Nysted Offshore Wind Farm (NOWF) and the state of the system
under the measurement campaign is presented on the third section. Here the
measurements and study cases were explained and compared.
The electrical equipment in the collection grid of NOWF is presented and explained in
the fourth section. The main phenomena occurring during transient conditions and the
simulation methods used to represent switchgear, medium voltage cables, transformers,
induction generators and capacitor banks in Power Factory and PSCAD are explained.
Then, a comparison between Power Factory and PSCAD was made for some
component, with a simple case simulation.
After the model of each electrical device is understood and compared between Power
Factory and PSCAD, the collection grid of NOWF was created. In the fifth section, the
procedure to create the network in Power Factory and PSCAD is explained step by step.
Also in this section, the comparisons for each study case are presented between the
measurements and the simulation results from both Power Factory and PSCAD.
Once the simulations were done with the available information, additional models were
created to compare worst-case scenarios for both voltage and current switching to
previous study cases. In the last model the velocity of the travelling voltage wave was
“fitted” to the measurements.
In the sixth section the voltage dip when different number of transformers are being
energized simultaneously was simulated in Power Factory and PSCAD. Here, the
maximum number of transformers energized simultaneously while complying with the
UK grid code requirements was calculated.
The last section presents the conclusions of the overall project. Here, a comparison
between simulation softwares was made. In this section, a summary of the available and
necessary information to realize switching transients was presented. At last,
recommendations regarding the simultaneous energizing of different amount of
transformers were stated, as well as possible solutions.
Figure 1-4 shows graphically the overall project contents. The five main electrical
devices that compose the collection grid are shown, as well as the voltage source that
accounts for the connection to the transmission grid.
The colored rings represent layers of analysis for each device, where the first ring
encloses the theory and simulation basis, the second and third rings represent the Power
Factory and PSCAD simple-case simulations, the fourth ring corresponds to the
network simulation and comparison with measurements. The last ring contains the
voltage dip simulation due to transformer energization.
Preface
32
Figure 1-4 Graphic overview of the project
Switching transients
33
2 SWITCHING TRANSIENTS
Switching transients are caused by the operation of breakers and switches in a power
system. The switching operations are divided in two main categories: energization
phenomena and de-energization of the system elements.
Due to the complexity of the mathematical representation of the equipment involved,
digital simulation using electromagnetic transient (emt) simulation programs has a
major importance in the study of switching transients. Results from such studies are
useful for:
Overvoltage calculation
Insulation coordination
Transient recovery voltage (TRV) across circuit breakers
Transient mitigation devices
Inrush current calculations in transformers
Switching during normal operation, as well as during faults and outages, are the most
important switching conditions to consider, in a insulation coordination study for the
collection grid in an offshore wind farm.
Damaging switching operations depend to a large extent on the behavior of the
switching devices. Therefore, after a study, the system designer should verify with the
manufacturers that the electrical devices can withstand the calculated stress. At this
stage, the amplitude as well as the maximum rate-of-rise of the voltage are essential
parameters.
In the collection grid of offshore wind farms, the combination of vacuum circuit
breakers, cables, and transformers causes high-voltage high-frequency transients that
are suspected of contributing to the transformer failure in Middelgrunden (Larsen,
Sørensen, Christiansen, Naef, & Vølund, 2005) and Horns Rev (Sweet, 2004).
2.1 Switching transients studies
There are some modeling requirements that switchgear devices should comprise for
switching transients studies (Rashidi, et al., 2003):
Protection delay or clearing times
Maximum fundamental frequency switching voltage
Maximum capacitive switching capabilities
Switching transients
34
Reclosing sequence and whether they will be used
Rated TRV and maximum rate of rise of TRV
Mechanical closing time and variation in pole closing time. This is important if
point-in-wave closing is to be investigated
In practice, due to the secrecy of product development, there is no way of directly
comparing vacuum circuit breakers between manufacturers, except for the transient
recovery voltage (TRV).
2.2 Transient recovery voltage
According to the IEEE, the recovery voltage is the voltage that appears across the
terminals of a pole of a circuit breaker after interruption. This voltage can be considered
in two successive time intervals: one during which a transient voltage exists (TRV),
followed by a second during which a power frequency voltage alone exists (IEEE
Application Guide for Transient Recovery Voltage for AC High-Voltage Circuit
Breakers). There is ongoing work for the harmonization of TRVs in IEEE and IEC
Standards for AC high-voltage circuit breakers rated less than 100 kV.
In order to cover all types of networks in the range of rated voltage higher than 1 kV
and less than 100 kV the revision of the IEC 62271-100 has defined two types of
systems (Dufournet & Montillet, 2005): Cable systems and line systems. Both systems
have a TRV during a breaking of terminal fault at 100% of short-circuit breaking
current that does not exceed the two-parameters enveloped in the standard. Figure 2-1
shows the comparison of the TRVs for cable-systems and line-systems based on IEC
62271-100. It can be seen that the rise of recovery voltage (RRRV) for line-systems is
approximately twice the value for cable systems.
Figure 2-1 Comparison of TRVs for cable systems and line-systems, adopted from
(Dufournet & Montillet, 2005)
Switching transients
35
According to (Kondala Rao & Gajjar, 2006), it is posible for a generic model of VCB to
simulate current chopping, re-ignitions, virtual current choping and pre-strikes if certain
values are known. Some of the most important values are:
Rate of Rise of Restriking Voltage
Rate of Rise of Dielectric Strength
However, in reality it‟s impossible to obtain any of these values from the manufacturer.
Most of the time, circuit breakers are considered as ideal breakers for switching
transient studies focusing mainly on low voltage phenomena. The closing time of the
poles is normally simplified to simultaneous closing, where in reality the non-
simultaneous phenomenon is possible. To widen the switching transient studies,
variation on point-in-wave could be included.
2.3 Inrush current calculations in transformers
Transformer energization is a common occurrence in any electric power system. Most
of the time, energization results in the transformer needing a large inrush current, which
eventually decreases to a small magnetizing current. The length of time the transformer
demands the inrush current depends on the impedance of the system, including the
transformer characteristics.
The inrush current could cause a temporary voltage drop due to the impedance of the
system between the source and the energized transformer. If the short circuit MVA
available at the transformer bus is low, the resulting voltage drop can be significant.
Short duration voltage drops that are caused by faults or large inrush currents are called
voltage dips (IEC) or sags (IEEE).
The magnitude of the inrush current is a statistical variable depending on where on the
sinusoidal voltage curve the circuit breaker connects the transformer to the source. The
highest inrush current occurs when the circuit breaker connects the transformer, when
the voltage passes through zero.
Modern transformers tend to have higher inrush currents compared to transformers built
40 years ago. The reason for this is that modern low-loss core steel allows higher flux
densities in the core without unacceptable high core temperature as consequence.
In offshore wind farms, the system designer is more concered about the losses in the
transformer, due to its high costs, than in the transient phenomena. However, grid
requirements in the UK limit the voltage dip to 3% when an induction machine is
started, and this requirement is simply applied to transformer energization (ENA, 1989).
No standard update has been made for wind turbine transformer energizing or park
transformer energizing.
Switching transients
36
In practice, a study to assess the voltage dip due to transformer energization or inrush
current ratings would take into account point-in-wave switching, as well as different
levels (low/high) of residual flux in the transformer core.
In the last section of the project, some recommendations are included regarding the
available and required information to realize switching transient studies in offshore
wind farms.
37
3 MEASUREMENTS AT NYSTED OFFSHORE WIND FARM
Once the switching transients studies had been define, the measurements done in the
collection grid at Nysted Offshore Wind Farm (NOWF) are presented in this section.
The state of the system under the measurement campaign is presented as well. Here the
measurements and study cases are explained and compared.
3.1 Nysted Offshore Wind Farm
The wind farm is installed in the year 2003 and it‟s operated by DONG Energy who
owns 80% of the farm, while E.ON owns 20%. It consists of 72 wind turbines (WTs)
with a rated power of 2.3 MW. The turbines are arranged in a parallelogram, formed by
eight rows with nine WTs each. Figure 3-1 shows the arrangement. The WTs are
delivered by former Bonus, now Siemens Wind Power.
Figure 3-1 Nysted Offshore Wind Farm
The WTs are connected in “rows” of 36 kV submarine cables. Each row is then
connected to the platform by one “root” cable. The park transformer (180/90/90 MVA,
132/33/33 kV) is in the central position. Each feeder is connected by a VCB, followed
by the root cable. There are eight rows, from A to H, where A, B, C and D are
connected to one MV winding, and E, F, G, and H to the other MV winding.
The submarine cable is connected on the bottom of each WT where the armor and the
shield of the cables are grounded. Then the transformer (2,5 MVA, 33/0.69 kV) is
connected via switch disconnector-fuse on the MV. On the LV side of each transformer
Measurements at Nysted Offshore Wind Farm
38
only the capacitor bank to compensate the induction generator and a small load were
included in some of the simulations.
The WTs are interconnected with 36 kV cables of 505 m of length. Furthermore, the
HV grid (132 kV), sea cable (10.5 km) and land cable (18.3 km) were included in the
models.
During the entire document, the base voltage and current for per unit calculation was the
rms and not the emt magnitude, since the emt uses the amplitude of the waveform.
The voltage at the three measurement locations is the same (33 kV), while the base
current depends on the location. For the platform the nominal current of the cables was
used (420 A) as base current, while for the measurements in A01 and A09 the nominal
current of the transformer was used (43 A).
3.2 Measurements
A novel GPS synchronized measuring system for MV equipment to document high
frequency transients, was developed and installed in NOWF, Denmark (Christensen, et
al., 2007). Three voltages and three current were sampled at 2.5 MHz, in three different
locations in the network simultaneously and synchronized via GPS. The measuring
points can be seen Figure 3-2 and were located at:
The transformer platform after the circuit breaker from radial A
The wind turbine A01, the first turbine of the radial A
The wind turbine A09, the last turbine of the radial A
Figure 3-2 Measurements locations, adopted from (Christensen, et al., 2007)
Several switching transients were generated and recorded, but only the opening and
closing of the line breaker for radial A and the load breaking switch in turbine A09 were
covered in this work. In WTs A01 and A09, the measuring equipment was placed
between the MV switchgear and the transformer, as showed in Figure 3-3.
Measurements at Nysted Offshore Wind Farm
39
Figure 3-3 Measurement at wind turbines, adopted from (Christensen, et al., 2007)
The measurements to be replicated in Power Factory and PSCAD as study cases are
shown in the next subsection. The two first cases where the row A was energized (7 km
of cables and nine wind turbine transformers (WTT)) and then the third case where only
the last WTT (A09) of row A was energized, with seven other wind turbines under
production in the same row. The voltage for the three cases is shown in Figure 3-4.
Figure 3-4 Voltage waveforms for study cases.
In this figure, the top plot is the voltage at the platform during the initial 50 ms of the
recording of the first study case. The plot in the middle is the voltage at the platform
during the initial 50 ms of the recording of the second study case. The bottom plot is the
Measurements at Nysted Offshore Wind Farm
40
voltage at the wind turbine A09 during the initial 50 ms of the recording for the third
study case.
It can be seen in the second study case, that the voltage reaches 2 p.u. and has higher
oscillations after the switching occurred. In theory the system should be the same, only
the point-in-wave has changed. In the second case the voltage of phase A (Va) is closer
to the peak voltage than in the first study case.
In the third study case, it can be seen that the time between pole closing is larger than in
the first two cases. This is because in each WT, the breaker before the transformer is not
a vacuum- circuit breaker (VCB) but an air-blast breaker.
In the bottom plot of Figure 3-4 it can be seen as well some oscillation on the voltage
phase A (Va) when phase C and B has been connected. This oscillation could be caused
by the delta connection in the primary side of the wind turbine transformer. Since the
transformer is a three-phase core-type transformer; where the vector sum of the flux
should be zero at any time. Hence, in phase A some voltage might be induced.
The inrush currents for each study case are presented in Figure 3-5. Here the top plot is
the current at the platform during the initial 250 ms of the recording from the first study
case. The plot in the middle, is the current at the platform during the initial 250 ms of
the recording from the second study case. The bottom plot, is the current at the wind
turbine A09 during the initial 50 ms of the recording for the third study case.
Figure 3-5 Current waveforms for study cases
The current in the second and third case presents a flat top. This is due to measurement
errors. It‟s important to remember that 1 p.u. in the platform represents 420 A, while 1
p.u. in A09 is only 43 A.
Measurements at Nysted Offshore Wind Farm
41
Before the inrush current starts to flow, some current energize the MV cable. Deeper
analysis was done for each study case further in the thesis. At this stage it is important
to notice how the point-in-wave is very important for the inrush current. This can be
seen in the first and second case, since they are essentially the same system, but for the
initial cycles the current peaks are higher in the second study case.
From Figure 3-4 can be seen the difference in the switching angle for each study case.
In the first case the switching occurred before the voltage of phase B (green) reached a
negative peak value. In the second case the switching occurred after the voltage of
phase A (blue) reached a negative peak value. Finally, in the third case the switching
occurred almost when the voltage of phase C (red) reached a negative peak value
In the first two cases “half-wave-current” appears when the switching occurs, this are
due to the appearance of electric arcs in the switchgear. While the current spikes in A01
and A09 are caused by stray capacitances in the transformers.
3.3 Study cases
Once the study cases have been mentioned, the following subsection presents each
study case in detail.
3.3.1 Case 1. First closing of the line breaker for line A
The voltage measured in the three locations (platform, A01, A09) from 0 s to 0.25 s are
shown in Figure 3-6. Here it can be seen that, there are some transient overvoltages
(TOVs) at the beginning of the waveform. These are caused by reflections in the cables
that attenuates during the first milliseconds.
Figure 3-6 Case 1. Voltage 0-250 ms
Measurements at Nysted Offshore Wind Farm
42
If a zoom is made for the first 50 ms it can be seen that the transient due to the cable
energizing and reflections disappears in less than 50 ms after the closing (Figure 3-7).
Figure 3-7 Case 1. Voltage 0-50 ms
If the voltage is visualized only from 4.3 ms to 5 ms the traveling wave can be analyzed.
In Figure 3-8 it can be seen how the voltage travels from the platform to the last wind
turbine (A09) in 45 μs and 45 μs later returns to the platform almost doubling the
voltage. It can be also seen that there is no simultaneous-pole-closing in the circuit
breaker on the platform.
Figure 3-8 Case 1. Voltage 4,3-5 ms
Measurements at Nysted Offshore Wind Farm
43
If the cable between the platform and the last wind turbine is 7 km, and it takes 45 μs to
the voltage wave to arrive, the velocity of the wave would be 157 km/s, 52% of the
speed of light (300 km/s) (Sørensen, et al., 2007). The same phenomena can be seen in
phase A and phase C.
From the voltage shape of phase B on A09, a doubling of the voltage can be recognized.
This occurred when an open-circuited line is energized, and the magnetic energy
associated with the current disappears when the current is brought to zero at the open
circuit. It reapers as electric energy, which manifest itself in the voltage increase
(Greenwood, 1991).
The current measured in the three locations from 0 s to 0.25 s is showed in Figure 3-9.
Here can be clearly seen two phenomena occurring: the cable energizing at the
beginning, followed by transformer energizing.
Figure 3-9 Case 1. Current 0-250 ms
If a zoom is made for the first 50 ms, it can be seen that the transient due to the cable
energizing disappears in less than 10 ms (Figure 3-10).
In Figure 3-10 a flat region on the phase C of the current on A01 can be seen. The value
present here is 2.858 pu (125 A), this is a measurement error due to the specified input
range in the data acquisition (DAQ) software, since the Rogowski-coil sensor used has a
peak current of 600 A (Christensen, et al., 2007).
Measurements at Nysted Offshore Wind Farm
44
Figure 3-10 Case 1. Current 0-50 ms
Figure 3-11 Case 1. Current 4,3-5 ms
If the currents are visualized only from 4.3 ms to 5 ms (Figure 3-11), it‟s possible to see
current spikes with a value lower than 1 p.u., for less than 1 ms in A01 and A09, when
the voltage waves (Figure 3-8) arrive to each transformer. This is due to the charging of
capacitances in the MV transformer in the WTs. This phenomena has been reproduced
by (R. King, 2008) and (Sørensen, et al., 2007). This can be explain simply by the
instantaneous current caracteristc of the capacitor:
dv
i Cdt
(3.1)
Measurements at Nysted Offshore Wind Farm
45
where C is the stray capacitances of the WT transformers, that are being charged by the
dv/dt of the waves arriving at each transformer.
It can be also seen in Figure 3-11 that the current in the platform have “half-waves”
presumably caused by pre-strikes in the VCB as reported by (Liljestrand, Sannino,
Breder, & Thorburn, 2008). When the breaker closes to energize the cable on row A, the
circuit is almost closed before the contacts mechanically touch. Then, the system
voltage acts across the diminished pole gap, creating an increased dielectric stress
between the contacts, which can result on breakdown before the circuit mechanically
closes.
3.3.2 Case 2. Second closing of the line breaker for line A
This second case was not presented as thoughtfully as the first case, since is basically
the same event. The voltage on the three measurement location are shown in Figure
3-12 for the first millisecond after the closing. It can be seen that the voltage at the
platform and at the wind turbine A09 surpasses 2 pu several times. This is because the
closing in the VCB took place closer to the negative peak voltage of phase A. Then
when it reached the last wind turbine, the voltage increased further on, as explained
before.
It‟s important to notice that the energization of an individual phase does not affect the
voltage of the other phases. This is due to the shielding of each individual conductor
within the cable. Howerver, in reality there are some capacitances between phases due
to the close geometrical arrangement of the cable. These capacitances are responsible
for the small variations and decrease in voltage of phase C on the platform just before it
gets energized.
The current on the three measurement location for the first 250 ms is shown in Figure
3-13. The flat peak in two phases is noticeable in the three locations, and its explanation
is the same measurement error as explained before.
There is a higher inrush current in the second study case compared to the first one. This
is due to the point-in-wave in which the switching happened.
In Figure 3-13 and Figure 3-9, an oscillating current can be seen in A01. This current is
caused by a capacitor bank still connected on the LV side of the wind turbine
transformer. Analysis on the current waveforms for both cases, and an explanation of
the state of the system during the measurements was discussed in the following section.
However, it is very clear that the current in A01is different between the first and second
study cases.
Measurements at Nysted Offshore Wind Farm
46
Figure 3-12 Case 2. Voltage 20-21 ms
Figure 3-13 Case 2. Current 0-250 ms
3.3.3 Case 3. Closing of the breaker on wind turbine A9
The voltage at the three measurement locations, for the first 50 ms of the third study
case are shown in Figure 3-14. It is important to mention that no significant drop in the
platform voltage is noticeable, for this a half-cycle rms calculation were performed
further in the document.
Measurements at Nysted Offshore Wind Farm
47
The current for the first 50 ms is shown in Figure 3-15. Some currents are present in the
platform and in A01. It was shown later in the document that seven of the nine WTs of
row A (all except the ones with measurement equipment) were under production. Here
it‟s only important to notice that no significant change occurs on A01 after the switch in
A09 was closed.
Figure 3-14 Case 3. Voltage 0-50 ms
The voltage and current in the WT A09 are presented in Figure 3-16. It can be seen that
the switch closes the phases not simultaneously. Between closing of phase C and B
there are 200 μs, and between phase B and A there are 2 ms.
There are some high frequency oscillations in the voltage after each phase closes, this
could be due to an arc on the breaker. When each phase is energized there are sudden
current raises, that cannot be explain easily by the charging capacitance in the
transformers, since they reach more than 1 p.u. and in the previous cases the current
spikes hardly reach 0,5 p.u.
Measurements at Nysted Offshore Wind Farm
48
Figure 3-15 Case 3. Current 0-50 ms
After phase B has close, there is some voltage oscillation on phase A until it is
connected. This could be due to the coupling between phases in the HV side of the
transformer, since it is a delta connected three-phase core-type transformer.
Figure 3-16 Case 3. Voltage and current 2,5-8 ms
Once the measurements have been presented and analyzed, the required calculation for
its comparison with the results from the simulation in Power Factory and PSCAD, were
explained in the next subsection.
Measurements at Nysted Offshore Wind Farm
49
3.4 Analysis of voltage and current measurements
3.4.1 Voltage dip standards
Voltage dips are defined as a short-duration reduction in rms voltage (Bollen, 1999).
These phenomanas are produced by short-duration increase in current elsewhere in the
system, e.g. transformer energizing. International organizations like the IEEE, IEC and
CIGRE have been working in the stardarization of the voltage dip, however there is still
some work to be done (Bollen, et al., 2006).
The IEC 62000-4-30 distinguishes between single-channel and multi- channel
measurements. For multi-channel measurements the worst channel is taken for further
analysis when calculating single event indices. Thus for every half-cycle update of rms
voltage, the lowest of the values from the different channels should be used.
For the present report the half-cycle rms voltage was used to compare the voltage dip on
each study case, and further in the report to calculate the voltage dip due to
simultaneous energization of different amount of transformers.
Since one of the practical objectives of the theses is to assess the voltage dip due to
sequential energization of different amount of transformers in order to comply with the
UK requirements, the voltage change limitation based on this standard is presented here.
The following information was taken from (ENA, 1989.).
Figure 3-17 Usual form of voltage change caused by motor starting, adopted from
(ENA, 1989.)
In the UK the general limit on the allowable magnitude on voltage drop, caused by
motor starting, has been the accepted practice to control the risk of low voltages. The
Figure 3-17 shows the typical voltage of a motor with direct starting. Here is assumed
that the magnetizing inrush current last for 30 ms. In this case the recommended limit
for the voltage magnitude variation is DV .
Measurements at Nysted Offshore Wind Farm
50
3.4.2 Rms calculations
The formula to calculate the rms value of the voltage (3.2) and current (3.3)are:
2 2 2
1 2 1 ½½
½
Nrms
u u uU
N
(3.2)
2 2 2
1 2 1 Nrms
u u uI
N
(3.3)
Where the N is the number of samples per cycle. For the half-cycle rms voltage the first
value is obtained over the sample (1,½N), the next over the sample (½N+1,N), etc. For
the rms current the first value is obtained over the sample (1,N), the next over the
sample (N+1,2N), etc.
3.4.3 Power calculations
Another important parameters to compare the measurements and the results from the
simulations are the instantaneous real power (3.4) and instantaneous reactive power
(3.5):
, , , , , ,
1
1( )
N
A k A k B k B k C k C k
k
P v i v i v iN
(3.4)
, , , , , , , , ,
1
1(( ) ( ) ( ) )
N
B k C k A k C k A k B k A k B k C k
k
Q v v i v v i v v iN
(3.5)
Where k is the sample number. For the first and second study cases only one
measurements file was used since each file covers half a second. For the third study case
two consecutives measurements files were used, since each file cover only 200 ms.
Thus for the first and second study cases 1,25×106 samples, corresponding to 25 cycles
were analyzed for 18 signals. While only 1,00×106 samples, corresponding to 20 cycles
were analyzed for the third study case.
Nevertheless the instantaneous powers were not directly compared on the study cases.
The active and reactive powers were calculated with the average of each instantaneous
power every cycle. This method was found to be insufficient to calculate the active and
reactive power in a system with high harmonic contents, however this situation was
only present in A01.
3.4.4 FFT in current
The current in each phase measured at A01 during the first study case is shown in
Figure 3-18, while the current measured at A09 is shown in Figure 3-19.
Measurements at Nysted Offshore Wind Farm
51
Figure 3-18 Case 1-A01. Current 0-500 ms
It can be seen from this two figures that the equipment connected on the LV side of the
transformers is not the same in A01 and A09, assuming that the transformers are. To
discard possibilities on the equipment connected on the LV side of the transformer an
FFT analysis was done.
Figure 3-19 Case 1-A09. Current 0-500 ms
Measurements at Nysted Offshore Wind Farm
52
The results of this two FFT analysis are shown in Figure 3-20. It can be seen that there
are significant differences around 210 Hz between A01 and A09.
Figure 3-20 Case 1-A01 and A09. FFT on current
It was found from the FFT that apparently there is not the same equipment connected at
A01 and A09. The harmonic current/fundamental current ratio is presented in
Table 3-1. The forth harmonic on phase B in A01 presents the highest ratio with 1,16.
Table 3-1 Harmonic current ratio
I(100)/I(50) I(150)/I(50) I(200)/I(50) I(250)/I(50)
Case 1
A1
Ia 0,87 0,34 0,79 0,04
Ib 1,05 0,42 1,16 0,37
Ic 0,83 0,48 0,35 0,12
A9
Ia 0,61 0,32 0,24 0,18
Ib 0,90 0,10 0,66 0,40
Ic 0,59 0,32 0,24 0,19
It‟s not possible to realize the FFT analysis on other study cases since the current
waveforms are incomplete.
The main loads connected on the LV side of each WTT consist of yawing motors,
hydraulic pumps, cooling fans, lubrication equipment, heating elements and control
system. While there are other devices with high priority that are directly supplied from
the transformer like the hoist, control cabinets and cooling fans in the transformer.
Large loads were not included in any simulation since they are not part of the main
project objective. However it was found in the datasheets of the wind turbines that there
is a permanent load directly connected to the LV side of the transformer, of 0,37 kW
that was included in the simulations.
On the other hand, the capacitor banks that compensate for the reactive power
consumption of the asynchronous generator under production were included further on
in the report, while they were found to be relevant for the simulation.
Measurements at Nysted Offshore Wind Farm
53
3.5 State of the NWP when the measurements were done
The measurements of the opening and closing of row A on NOWF were done the 8 of
march 2007 between 16:50 and 17:00. The Figure 3-21 and Figure 3-22 present the 10
minutes average of the permanent measuring equipment in the turbines A01 to A09.
The measurements files used for the first two study cases, had a time stamp on the file‟s
name so the user can be sure of the time of the switching event. However for the third
case the files‟ name had been edited before and no record or log of the measurement
was kept. This brought problems for the last study case, since from the beginning of the
project it was assumed that the wind turbines without measurement equipment of row A
were not under production. Later on the project changes were made and simulations
with the generators were done.
Ac tive P ower
-
500
1.000
1.500
2.000
2.500
15:00 15:10 15:20 15:30 15:40 15:50 16:00 16:10 16:20 16:30 16:40 16:50 17:00 17:10 17:20 17:30 17:40 17:50
P [
kW
]
A1
A2
A3
A4
A5
A6
A7
A8
A9
Figure 3-21 Active power measurements, 10 min average
From the Figure 3-21it can be seen that between 16:50 and 17:20 the wind turbines
were almost under no production. While A09 and A01 does not start production at all
after this period. While the rest of the turbines returned to almost full production.
Measurements at Nysted Offshore Wind Farm
54
R eac tive P ower
-
50
100
150
200
250
300
15:00 15:10 15:20 15:30 15:40 15:50 16:00 16:10 16:20 16:30 16:40 16:50 17:00 17:10 17:20 17:30 17:40 17:50
Q [
kV
Ar]
A1
A2
A3
A4
A5
A6
A7
A8
A9
Figure 3-22 Reactive power measurements, 10 min average
The reactive power on each WT is shown in Figure 3-22. It is important to notice that
during the field test the turbine A01 kept injecting between 150 and 200 kVAr to the
grid. This shows that the capacitor bank in A01 remained connected.
The generators on NOWF are asynchronous machines with a capacitor bank to
compensate for the reactive power consumption during production. Hence, by knowing
the terminal voltage of the generator and the production, the slip can be calculated.
Once the slip is computed, the reactive power consumption can be estimated. Then, by
adding the measured reactive power at the LV side of the WTT and the calculated
reactive power consumption of the generator, the amount of reactive power from the
capacitor can be calculated.
It results that before the opening of the platform breaker 1260 kVAr were delivered by
each capacitor bank. This value could be used to calculate the resonance frequency of
the system during the first opening of the radial A. But due to time limitations this
analysis had to be left out of the scope of the theses
In order to fully understand the state of the system after closing the breaker in the
platform and energize row A (case 1 and case 2), the following subsection presents the
expected values for currents, voltage, real and reactive power for the mentioned cases.
Measurements at Nysted Offshore Wind Farm
55
3.6 Steady state for case 1 and case 2
The Table 3-2 presents the main characteristics of each wind turbine transformer under
normal conditions, as well as the comparison with a small low voltage load.
Once the nominal values are known, the current at the LV side of the transformer can be
calculated, for a small LV load as:
3 3 LLS I V (3.6)
Then, the equivalent current at the primary side of the transformer can be calculated as:
P P S SI V I V (3.7)
Then, the equivalent copper losses (3.8) and leakage reactive power (3.9) consumption
of the transformer, with lower current can be computed as:
2
1 1
2
2 2
P I R
P I R (3.8)
2
1 1
2
2 2
Q I X
Q I X (3.9)
Then the result can be multiplied by the total amount of transformers, obtaining the
steady state value that should be theoretically measured and simulated at the platform.
However, the reactive power production in the cables has to be included as well. For
this with the specific capacitance per length (3.10), the length of the MV cable (3.11),
frequency and voltage, the reactive power (3.12) can be calculated as:
1
2CX
fC
(3.10)
CC
XX
l
(3.11)
2
LL
C
VQ
X (3.12)
From Table 3-2 can be seen that the real and reactive power consumtion in the cables is
almost insignificant. Howerver, at steady state the cables would produce nearly 0,5
MVAr, where the iron losses in each transfromer acount for all the active power
consumtion in row A.
Once the measurements and the system have been explained, as well as the study cases;
the theory behind the electrical components that will be used for the simulations of the
study cases in Power Factory and PSCAD can be done.
Measurements at Nysted Offshore Wind Farm
56
Table 3-2 Steady state (0,5 s) for case 1 and case 2
Steady state power balance for row A P [kW] Q [kVAr]
Tra
nsfo
rme
rs
Three phase transformer characteristics
Nominal three phase apparent power [MVA] 2,50
Primary side nominal rms phase-phase voltage [kV] 33,00
Secondary side nominal rms phase-phase voltage [kV] 0,69
Positive sequence short circuit voltage [%] 8,30 206,43
No load losses (iron losses) [kW] 5,50
Nominal operation losses (copper losses) [kW] 21,00
High voltage side nominal current [A] 43,74
Low voltage side nominal current [A] 2.091,85
Three phase transformer under operation
Low voltage load [kW] 0,37
Low voltage side current [A] 0,31
High voltage side current [A] 0,10
Iron losses [kW] 5,50
Copper losses [kW] 0,00
Leakage reactance [kVAr] 0,00
Total power consumption 5,87 0,00
Total power consumption of nine transformers 52,83 0,00
Cab
les
Power consumed in cable sections
Current at high voltage side of each transformers [A] 0,10
Section Amount of current
Root A 0,92 0,00 0,00
A1-A2 0,82 0,00 0,00
A2-A3 0,72 0,00 0,00
A3-A4 0,62 0,00 0,00
A4-A5 0,51 0,00 0,00
A5-A6 0,41 0,00 0,00
A6-A7 0,31 0,00 0,00
A7-A8 0,21 0,00 0,00
A8-A9 0,10 0,00 0,00
Addition of power consumption in row A 0,00 0,00
Reactive power generated from the cable’s capacitance
Capacitance per phase [μF/km] 0.199
Cable length [km] 7,061
Nominal frequency [Hz] 50
Line to line voltage [kV] 33
Total power consumption in row A 0,00 -483,14
Overall total 52,83 -483,14
Steady state current at platform in feeder A [A] 8,50
57
4 ELECTRICAL EQUIPMENT IN SIMULATION PROGRAMS
In this section the network characteristics will be presented, as well as information
regarding wave theory. Then, the six main electric components used in the Power
Factory and PSCAD were explained and compared. This are:
Circuit Breaker
Transformer
Cables
Grid (Voltage source)
Capacitor bank
Generator
The theory behind each device and its application in offshore wind farms is presented.
Then, the explanation regarding the standard models in Power Factory and PSCAD, as
well as a simple case for comparison is presented for each device.
4.1 Network
In an offshore wind park, the turbines are connected in radials by MV cables, with
feeders coming from the wind park transformer to each radial. This property of the
collection network has an influence on the TOVs caused by the CB operations. The
large number of cables and transformers gives rise to reflections in the system. The
reflection points will cause different stress on the insulation of the equipment depending
on its location (Liljestrand, et al., 2008).
In cable systems the CB operation are the main source of TOVs, since the surge
impedance has direct impact on the time derivate of the TOVs and the surge impedance
of cables is low compared to overhead lines (OHL): the lower the surge impedance, the
higher the time derivate of the TOVs. The time constant for the voltage across a load
when hit by a step voltage, depends as:
loadsurgeCZ (4.1)
where the Zsurge is the surge impedance and Cload is the capacitance of the load.
4.2 Wave theory
The electrical devices are usually analyzed as lumped or concentrated models with
constant R, L and C parameters. In reality these parameters are actually distributed in
any circuit or piece of equipment. This way of modeling the electrical devices, has the
unique characteristic to support travelling waves of current and voltage. The
Electrical equipment in simulation programs
58
transmission line theory is well explain in [Greenwood A. 1991], and the reader is
invited to review this source, only the main information is included here.
The current and voltage waves travel along a lossless circuit at a velocity of:
LC
v1
(4.2)
With a approximation of the inductance
ln( / )L d r
(4.3)
And a approximation of a capacitance
ln( / )
Cd r
(4.4)
The velocity of the wave can be rewritten as
1
v
(4.5)
From equation (4.5) can be seen that the wave velocity is independent of the line
geometry, it is only dependant on the conductor relative permeability (μ) and the
insulation relative permittivity (ε).
The ratio of the amplitude of the voltage and current waves on a transmission line has
the dimension of impedance and is called characteristic impedance Z0 of the line, and
can be calculated as:
C
LZ 0 (4.6)
And it can be seen that unlike the wave velocity, v, the characteristic impedance
depends upon the line geometry. A typical value or characteristic impedance for OHL is
400 Ω, while for cables is between 30-80 Ω because the closer spacing makes C larger
and L smaller. The capacitance is further increased by the permittivity of the cable
dielectric.
When the cables are analyzed as transmission lines, some of the following items might
not be taken into account (Sluis, 2001):
Skin-effect for high frequencies
Losses in the dielectric medium between the conductors
Leakage current across string insulators
The influence of ground resistance
However, when a voltage or current wave travels along a cable with losses, the
attenuation caused by the properties of the transmission line, would decrease the
amplitude of the wave. This attenuation in the voltage wave was visible on the
measurements from the first and second study cases, which both of the simulation
programs were able to replicate.
Electrical equipment in simulation programs
59
When a wave arrives at a discontinuity in a line, where Z0 changes, some adjustments
occur in the wave, so the proportionality (Z0) is not to be violated. This adjustment takes
the form of the initiation of two new wave pair. The reflected voltage wave and its
companion current travel back in the line superimposed on the incident wave. The
refracted wave penetrates beyond the discontinuity. The amplitude of the reflected and
the refracted waves are such that the voltage to current proportionalities are preserved
for each, as demanded by Z0 of the line on which they are traveling; current and voltage
at the line discontinuity are themselves continuous, and the energy is conserved.
The magnitude of the reflected voltage wave at a junction point with characteristic
impedance ZA and ZB on the incident side and refractive side, respectively, can be
calculated as:
112 VVZZ
ZZV
AB
AB
(4.7)
the refracted voltage wave can be calculated by
113
2VV
ZZ
ZV
AB
B
(4.8)
Where V1 is the incident wave, V2 is the reflected wave and V3 is the refracted wave. ρ
and α are called reflected and refracted coefficient, respectively.
The Figure 4-1 shows the first milliseconds of the measurements of the first study case.
Here, the voltage of phase B is presented on the three measurement locations where the
voltage at the platform is shown in blue, the voltage at A01 in green and the voltage at
A09 in red. In the lower part of the figure, the color nomenclature is the same, but the y
axis is not voltage as in the upper part, here the distance between measurement locations
is shown.
The lower figure presents the position of the voltage wave in grey color. At T1 the
phase B is energized on the platform. At T2 the voltage arrives to A01 and at T3 the
voltage reaches A09.
It is possible to see the doubling of the voltage at T3, since the transformer would be
seen as an open circuit. Then once it has reach the end of the line the wave bounces
back to the platform, arriving to A01 at T4 and to the platform at T5. Here it‟s important
to notice that the voltage at the platform increases again, since the park transformer and
other feeders are connected at this point.
At T5 two gray lines leave the platform in direction to A09. The dark gray line
represents the position of the voltage wave if the velocity of the voltage had not
decreased. The light gray line is the position of the voltage at decreased velocity. From
this simple numerical equivalencies can be seem that the velocity of the wave diminish
after the first reflection period. The wave velocity reduction could be explained by the
change in relative permittivity due to frequency variations. Additional discussion on the
transient phenomena in cables and its simulation was done further in the report.
The orange lines represent the reflections each time the voltage reaches a wind turbine
between A01 and A09. From (4.8) can be seen that each time the voltage wave reaches
a transformer (high impedance) between the platform and A09, a small amount was
Electrical equipment in simulation programs
60
reflected back. Similar reflections appear as small variations in A01 (green voltage)
between T2 and T3, due to the change from copper core cables to aluminum core cables
at A02.
Figure 4-1 Case 1. Voltage phase B 4,3-4,6 ms
4.3 Switchgear
In an offshore wind farms like Nysted, the collection grid is relatively active, and not
passive as in a distribution network. Hence the switchgear plays a critical part in
controlling what is taking place. In general the switchgear is used to (Steward, 2004):
Isolate faulty equipment
Divide the network into sections for repair purposes
Electrical equipment in simulation programs
61
Reconfigure the network in order to restore the power production
Control other equipment
All switchgear must be capable of either closing or opening an electrical circuit. This
includes the switching device, associated control, measuring, protection and regulating
equipment.
The difference between a CB and a switch is that the CB can detect and interrupt a
short-circuit fault current, whereas a switch can do neither.
Any CB should meet thermal interruption requirements, interrupt at natural current zero
and withstand dielectric stresses caused during interruptions. Depending on the
extinguishing medium used, the CBs are classified as oil, air, air-blast, vacuum and SF6
CBs.
For this project only two types of the switching element from the collection grid of
NOWF were taken into account; a vacuum circuit breaker (VCB) as the breaking
element for each collection radial in the platform and a switch disconnector fuse on the
MV side of each WTT.
Due to time constrains during the project only a theoretical review of the switching
phenomena in CBs and the modeling of gas insulated CBs and VCBs was made. In the
simulations, the models used were the simplest with an ideal breaking action that is
independent of the arc, while the breakers were represented as ideal switch that opened
when the tripping signal was given.
4.3.1 Circuit breaker modeling
The following information about switching transient studies for gas insulated CBs, was
taken from the IEEE PES Task Force on Data for Modeling System Transients
“Parameter determination for Modeling System Transients-Part VI: Circuit breakers”.
For switching transients studies the switch is usually modeled as an ideal conductor
(zero impedance) when closed, and an open circuit (infinite impedance) when open.
There are a variety of options of closing time provided by commercial transient
programs, ranging from one-shot deterministic closing to multi-shot statistical or
systematic closing.
In normal operation a CB is in closed position, and some current is usually flowing
though the closed contacts. The CB opens its contacts when a tripping signal is sent to
it. The separation of the contacts causes the generation of an electric arc. There are
several levels of model complexity available in transient analysis applications (CIGRE,
1998):
1. The simplest model considers an ideal breaking action that is completely
independent of the arc. The breaker is represented as an ideal switch that opens
Electrical equipment in simulation programs
62
at the first current-zero crossing after the tripping signal is given. The model
may include a current margin parameter for approximate modeling of possible
current chopping. Such models are applicable in studies where the interaction
between the breaker arc and the surrounding network can be neglected. It can be
used to obtain the voltage across the breaker; this voltage is to be compared with
a prespecified TRV withstand capability for the breaker.
2. A more elaborate model considers the arc as a time-varying resistance or
conductance. The time variation is determined ahead of the time based on the
breaker characteristics and perhaps upon knowledge of the initial interrupting
current. This model can represent the effect of the arc on the system, but requires
advanced knowledge of the effect of the system on the arc. Arc parameters are
not always easy to obtain and the model still requires the use of precomputed
TRV curves to deliver the adequacy of the breaker.
3. The most advanced models represent breakers as a dynamically varying
resistances, whose value depends on the past history of voltage and currents in
the arc itself. This model can represent both the effect of the arc in the system
and the effect of the system in the arc. No precomputed TRV curves are
required. Most of these models rely on the first-order differential equation. This
type of model is generally developed to determine arc quenching capabilities.
Most models can be used to study the thermal period, some can be used to
determine arc re-ignitions due to insufficient voltage withstand capabilities of
the dielectric between breaker contacts. Their most important application cases
are short-line-faults (SLF) interruption and switching of small inductive
currents. They are exclusively applied to gas CBs.
Several models can be used to represent a CB in closing operation.
The simplest model assumes that the breaker behaves as an ideal switch whose
impedance passes instantaneously from an infinite value, when open, to a zero
value at the closing time. The performance can be represented at any part of the
power cycle. A closing operation can produce TOV whose maximum peaks
depends on several factors; for instance, the network representation of the source
side of the breaker, or the charge trapped on transmission lines in a reclosing
operation. One of the factors that has more influence on the maximum peak is
the instant of closing, which can be different for every pole of the three-phase
breaker.
Most transient programs allow users to analyze the influence of this factor and
obtain a statistical distribution of the switching overvoltages, usually provided in
the form of a cumulative distribution function. Two types of switches can be
represented.
o The closing time of the switch is systematically varied from a minimum to a
maximum instant in equal increments of time; this type is known as
systematic switch.
o The closing time is randomly varied according to either a normal or a
uniform distribution; this type is known as statistical switch. Data required
Electrical equipment in simulation programs
63
to represent these switches are the mean closing time, the standard deviation
and the number of switching operations.
The breaker model assumes that there is a closing time from the moment at
which the contacts starts to close to the moment that they finally make. The
withstand voltage decreases as the separation distance between contacts
decrease; an arc will strike before the contacts have completely closed if the
voltage across them exceeds the withstand voltage of the dielectric medium.
To summarize the modeling guidelines for CBs the next table from the same paper was
used.
Table 4-1 Modeling guidelines adopted from (CIGRE, 1998)
4.3.2 Vacuum circuit breaker
The vacuum breaker is, at least in principle, the simplest of all the breakers designs
from the mechanical construction with only a fixed and movable contact located in a
vacuum vessel. When the contacts are separated, the arc is supported by ionized metal
vapour derived from the contacts instead of by ionized gas as in other interrupters, and
at current zero collapse of ionization and vapour condensation is very fast, ensuring
interruption virtually independent of the rate of rise of re-striking voltage (Flurscheim,
1982).
Vacuum is used as an extinguishing medium for MV CBs. VCB are capable of
interrupting currents with a very high di/dt, typically in the range of 150-1000 A/μs
(Wong, Snider, & Lo, 2003).
The current interruption is performed by cooling the arc plasma so that the electric arc,
which is formed between the breaker contacts after contact separation, disappears. At
short circuit current zero, the instantaneous energy input to the arc is minimal, enabling
Electrical equipment in simulation programs
64
the arc to extinguish. Immediately after the extinction of the arc, the power network
reacts with a TRV that stresses the gap.
The arc that occurs in the vacuum interrupter is very different from the arcs in other
CBs. The “vacuum arc” is a contradiction in terms, since an arc, by definition contains
positive ions; however, a vacuum arc is an arc where the vapour to produce positive
ions is generated from electrodes by the arcing process itself. The physical processes in
the VCB are rather complex, but for simulation purposes some simplifications can be
made.
For the VCB different breaker models exists and they all take into account arc thermal
instabilities. However there is no universal precise arc model. The generic model of
VCB incorporates stochastic properties of different phenomena that take place in the
breaker opening process. The different properties that are generally considered are
(Wong, Snider, & Lo, 2003):
Random nature of the arcing time
Current chopping ability
The characteristic recovery dielectric strength between contacts when opening
The quenching capabilities of the high frequency current at zero crossing
Below the four main causes of overvoltage in VCB are presented, based on (Kondala &
Gajjar, 2006):
Current chopping
Voltage escalation due to multiple pre-ignitions
Virtual current chopping
Pre-strikes
Only the pre-strike phenomenon was explained since it is the only incident that was
measured in the study cases, being highly relevant during the energization of radial in a
wind farm. The pre-strike phenomenon during opening of a VCB is mentioned below.
4.3.2.1 Pre-strike
Traditional methods of representing the CB for energizing phenomena in transients‟
studies are to assume that the contacts can close on any part of the cycle. In reality,
there is a closing time between when the contacts start to close and when they finally
make. Somewhere in between, an arc may strike across the contacts as they close
(Rashidi, et al., 2003), this is known as “pre-strike”. The pre-strike effect in closing CBs
with finite closing time is shown in Figure 4-2.
Electrical equipment in simulation programs
65
Figure 4-2 Pre-strike effect in circuit breakers, adopted from (PSCAD User's Guide,
2005)
The vertical axis in Figure 4-2 is a measure of the withstand voltage across the CB
contacts. In the open position the withstand voltage of the CB will be a per unit value of
the rated voltage. The time varying value of the voltage across the contacts is depicted
as an absolute function of the alternating voltage across the contacts. As the contact
close, the withstand voltage reduces as the separation distance between the contacts
reduces. When the voltage across the contacts exceeds the reduced withstand voltage of
the insulating medium between them, and pre-strike occurs. As a result of the pre-strike,
there will be a greater tendency for effective closing to occur with rising or maximum
voltage across the contacts (PSCAD User's Guide, 2005).
4.3.2.2 Opening
In studying interrupting operations of a VCB the entire process can be divided into a
few stages (Kosmac & Zunko, 1995):
The contact starts to separate and the electric arc begins to burn. As is well-
known, the voltage/current characteristic of a VCB in a very wide current range
is almost constant, and the arc voltage drop for Cu/Cr contacts is approximately
20 V.
The current decreases and approaches zero value. At one specific point, a very
fast decrease occurs (chopping current). The slop di/dt can be 108A/s or even
higher. For load currents between 45 and 170 A the following empirical
expression based on measurements can be used to estimate the chopping current
[Weber, F.U., 1988]
Nch ZcbIai log1 (4.9)
in which ich is chopping current, I1 rms load current, a, b, c, contact dependant
constants and ZN the impedance of the network.
Electrical equipment in simulation programs
66
For operating condition not matching the current range some assumptions can be
made.
In the case of high and/or fault current, the chopping current is essentially
zero because of the high ionization of the space between contacts and
thermal electron emission from the cathode which assures a long mean-
free path for electrons and ions.
When low current are interrupted it can be expected instability of the arc
and higher value of the chopping current and the di/dt.
The voltage on the load side terminal of the breaker may- after the current is
chopped due to a high di/dt value and conversion of magnetic into electric
energy- reach very high values. The potential difference between the contacts
can be higher that the dielectric strength of the space between contacts, and re-
ignition of the arc may occur. But dielectric strength improves with time, and
after certain period a full dielectric strength is reached. Sometimes contact start
to separate just before zero current. In such cases –due to small contact gap- the
voltage needed for re-ignition is relatively small. If the TRV is sufficiently high
and fast, re-ignition occurs. The number of re-ignitions and HF zero current
passing are random. The quenching capabilities of the HF current passing are
random. The quenching capability of the HF current depends on the current
slope and is different for different rms values [Czarnecki, L 1984]. When
inductive current is interrupted, multiple re-ignition, voltage escalation and
virtual current chopping can be observed. Post-zero current may be presented
even after contacts are separated, and it is load-current dependant.
4.3.3 Vacuum circuit breaker modeling
When realizing a switching transient study, the component involved should be modeled
as accurately as possible. However is very complicated to obtain an accurate model of
the VCB when all the phenomena mentioned above should be included.
As mentioned before only a theoretical approach was made regarding the VCB
modeling. Nevertheles, how to model the dielectric strength in a VCB is shown below.
4.3.3.1 Dielectric strength
During the closing of a VCB, is assumed that no current was flowing though the breaker
previous the closing. Thus, the relevant breakdown voltage under the influence of the
TRV is equivalent to the cold gap breakdown voltage. The frequency of this voltage is
in kHz range. The linear dependency of the dielectric strength and contact distance is
assumed as (Helmer, et al., 1996):
BttATVRU open )(lim (4.10)
Where topen is the moment of contact opening, A is the rate of rise of dielectric strength,
B the breaker TRV just before current zero and TRVlim is the maximum dielectric
strength that the breaker can withstand (IEEE Std. C37.011, 1994):
3
2lim magppaf EkkTVR (4.11)
Electrical equipment in simulation programs
67
Where kaf is the amplitude factor (1,4), kpp is the first pole to clear factor (1,5) and Emag
is the breaker rated voltage.
The calculated value of the dielectric strength is incorporated by considering the normal
distribution with a standard deviation of 15%, since breakdown phenomena is statistical
in nature. Some accepted values for equation (4.10) are shown in Table 4-2 based on
(Gliiikowslti, et al., 1997).
Table 4-2 Accepted values for equation (4.10)
A [V/ms] B[kV]
High 17 3,4
Medium 13 0,69
Low 4,7 0,69
As a practical matter in PSCAD simulations, is important to notice that the breakers
have a close resistance of 0,1 Ω, as standard value. This was found to be one possible
source of discrepancy between the results from Power Factory and PSCAD in the study
cases 1, 2 and 3.
Once the transient phenomena presented in the first and second study cases within the
switchgear device has been explained and understood, the next electrical device should
be explained. In this case the following equipment is the transformer.
4.4 Transformers
In offshore wind farms the step-up transformers in each wind turbine have great
exposure to electrical transients. Hence this subsection is dedicated to the theory behind
the emt modeling of transformers for switching transient studies.
There is a large amount of literature about the behavior of transformers when subjected
to surges and transient conditions, thus a comprehensive survey is presented next.
A complete model for a transformer would require that every turn be represented and
that all mutual couplings, inductive and capacitive, with every other turn be included. In
practice such a model is unnecessary, and a simplified model would be sufficient. The
model chosen will depend on the purpose of the simulation.
For example, if the time for the simulation needed is only microseconds, no significant
current can penetrate the winding properly because of its inductance. Currents would
flow as displacement currents in the capacitive of the windings. Thus, to obtain the
initial voltage distribution the model required would comprise capacitive elements only
(Greenwood, 1991).
On the other hand, when the model is used for other studies, e.g. to calculate the
transient overvoltage caused by vacuum circuit breaker re-ignitions, a simple capacitive
model would not be sufficient.
Electrical equipment in simulation programs
68
When the transformer is switched in no-load, the transformer model should represent
the influence of the transformer winding and the transformer core. Since the VCB re-
ignitions contain oscillations with different frequencies, the transformer behavior is also
different because of the variable impedance of the transformer winding and the
frequency dependant losses (Popov, et al., 2001).
Figure 4-3 Transformer model used in (Popov, et al., 2001)
4.4.1 Simple transformer model
The transformer model shown in Figure 4-4 is a simplification used in practical
engineering applications, where the secondary winding is referred to the primary. Here
the losses that occur in real transformers have to be accounted for. R1 X1 R’2 X’2
Xm Rfe
Figure 4-4 Simple transformer equivalent
The major items to be considered in the construction of such a model are (Chapman,
2003):
Copper losses are resistive heating losses in the primary and secondary windings
of the transformer. (R1 and R`2)
Eddy current losses are resistive heating losses in the core of the transformer.
They are proportional to the square of the voltage applied to the transformer
(Rfe).
Hysteresis losses are associated with the rearrangement of magnetic domains in
the core during each half-cycle. They are complex, nonlinear function of the
voltage applied to the transformer (Rfe).
Leakage flux that escape the core and pass through only one of the transformer
windings are leakage fluxes. These escaped fluxes produce a self-inductance in
the primary and secondary coils, and the effects of this inductance must me
accounted for (X1 and X`2).
Electrical equipment in simulation programs
69
The magnetization current of the core is proportional (unsaturated region only)
to the voltage applied to the core and lagging the applied voltage by 90°, so it
can be modeled as a reactance (Xm)
The main component in a transformer model for switching in open circuit is the
magnetizing branch and the capacitance to ground of the winding. This capacitance can
be assumed as distributed uniformly over the length of the winding; hence a total
capacitance referred to a terminal can be calculated (Greenwood, 1991).
Capacitances between terminals and between windings can be required for simulations
of some low-frequency transients; in addition, their effect can be important in excitation
tests (Martinez, et al., 2005). Transformer windings and bushing capacitances can be of
critical importance for slow transient phenomena such as ferroresonance and other
resonance situations. In addition their value increases with transformer size. The
manufacturer can state capacitances for their product, although they can also be
estimated from construction details or from typical values listed in the literature.
4.4.2 Switching transient studies in transformers
During switching operations in the radial of an offshore wind farm, the wind turbine
transformers are subjected to high-voltage and high-frequency waves. During the
connection of a transformer, the insulation of the coils connected to the line terminals
might be subjected to a voltage concentration, however the severity of the stress
situation depends on the point-in-wave on which the switching takes place.
As explained in the previous subsection the closing and opening events in a CB are
extremely hard to predict. However it is important to remember that the electric arc in
CB is highly possible. Arcing in the breaker contacts produces trains of high frequency
waves, which impinge upon the transformer windings and represents a real problem to
the insulators (JH- Franklin, et al., 1983). If an intermittent arcing takes place the
situation may worsen, additional information is presented in subsection 4.4.2.2.
In offshore wind farms a careful design of the system is important since maintenance is
highly expensive, hence the use suitable protective devices is imperative.
4.4.2.1 Detailed transformer model for surges
For switching surge transient studies it is better to use a reduced order representation
with less detail compared to the very detailed transformer model needed for the
insulation studies. Usually a lumped parameter coupled-winding model with sufficient
number of R-L-C elements, gives the appropriate impedance characteristics at the
terminal within the frequency range of interest. The nonlinear characteristic of the core
should usually be included, although the frequency characteristics of the core are often
ignored. This may be an oversimplification as the eddy current effect prevents the flux
from entering the core steel at high frequencies thereby making the transformer appear
Electrical equipment in simulation programs
70
to be air-cored. This effect begins to be significant even at frequencies in the order of 3-
5 kHz (A.M. Gole, 1997).
For switching surges studies, the following approaches may be used (A.M. Gole, 1997):
The model may be directly be developed from the transformer characteristic e.g.
nameplate information or measurements. The standard EMTP models fall into
this category.
A model synthesized from measured impedance versus frequency response of
the transformer. An example of this is shown in Figure 4-5.
A very detailed model obtained from the transformer geometry and material
characteristic may be developed. The model is the reduced to one that is usable
in the time domain solution. An example of this approximation is shown in
Figure 4-6.
When possible, the following techniques can be used to validate the model (Martinez, et
al., 2005):
A frequency response obtained by simulation can be compared within the desire
bandwidth with the actual characteristic if available. This should be done for all
possible open and short circuit conditions on the windings.
Determining the fundamental frequency response in the form of open and short
circuit impedances is a standard check. The turns ratio or induced winding
voltages at fundamental frequency are of interest.
Comparison with factory test if available also validates the model if terminal
capacitances measurements are available a comparison between measurements
and computed response is useful
Figure 4-5 Impedance magnitude and angle of a wind turbine transformer, adopted from
(Pedersen, et al., 2005)
Electrical equipment in simulation programs
71
Figure 4-6 A very detailed model adopted from (de Leon, et al., 1994)
4.4.2.2 Transformer-breaker interaction
Occasionally, when a transformer is switched into or out of a system, the transient
voltage produced at the terminals of the transformer may contain high frequency
oscillatory components. This oscillatory voltage is the result of the system configuration
and the breaker characteristics. When this voltage has a frequency component near one
of the natural frequencies of the transformer, and is of sufficient magnitude and
duration, damage to the internal insulation structure of the transformer may result.
In the IEEE there is an ongoing standard project PC57.142 “A Guide To Describe The
Occurrence And Mitigation Of Switching Transients Induced By Transformer-Breaker
Interaction”.
Because the reduced amount of time for the project, no high frequency phenomenon in
the transformer was modeled.
4.4.3 Magnetic characteristic of the transformer
Transformer saturation is an important component of many low-frequency EMT
phenomena (Martinez, et al., 2005). In general, it needs to be modeled in transient
conditions with high flux. Many simulation programs are concerned with the details of
the transformer saturation curve. For most phenomena, the critical transformer
saturation parameters are the slope (air-core inductance) and the zero-current intercept
of the saturation curve. The location of the saturation representation in the transformer
model topology is also important
Saturation can be incorporated into a power transformer model using test
data/manufacturer‟s curves or estimating the key parameters from design details, core
material and transformer geometry. However, joints in the core structure can play a
significant role that is not reflected in the material data. Relationships needed to obtain a
Electrical equipment in simulation programs
72
saturation characteristic from transformer geometry (cross-section of core, magnetic
path length, number of turns) and standard values of core permeability are provided in
textbooks.
The saturation characteristic can be modeled by a piecewise linear inductance with two
slopes, since increasing the number of slopes does not significantly improve accuracy.
Except for very specific applications, a very accurate model is not required. A non-
linear iron core model of a three-phase, three-limb power transformer based on the
current-dependant characteristics of flux linkage in presented in (Dolinar, et al., 2006),
by three independent controlled voltage sources while secondary windings are opened.
The method used is relatively complex; however, it is possible to perform an accurate
numerical analysis of the saturation in the core.
4.4.3.1 Inrush current of the transformers during energization
The following information was taken from the ABB Transformer manual.
The magnitude of the inrush current is a statistical variable depending on where on the
sinusoidal voltage curve the circuit breaker connects the transformer to the source. The
highest inrush current occurs when the circuit breaker connects the transformer when
the voltage passes through zero.
On the other hand, when the circuit breaker disconnects the transformer from the
voltage source, some residual flux is trapped in the core, unless the disconnection takes
place exactly when the flux passes zero. Hence, the residual flux is also a statistical
variable. The residual flux will be at its maximum if the disconnection happens when
the flux has its maximum. The polarity of the residual flux may be positive or negative,
depending on the voltage before the disconnection, since the flux is the integral of the
voltage.
When a transformer with zero residual flux, is switched on when the instantaneous
value of the applied voltage is close to zero, which requires that the instantaneous value
of the flux in the magnetizing branch must be at peak value or lag by 90° to satisfy the
steady state equilibrium. Since the flux cannot instantly rise to peak value, it starts from
zero and reaches 1 pu after ¼ cycle and continues to increase until it becomes
approximately 2 pu ½ cycle after the switching. This phenomenon is commonly referred
to as the flux doubling-effect. However if there is any remnant flux present prior to
switching, and its polarity is in the same direction of the flux build-up after switching,
the maximum value can even exceed 2 pu (Nagpal, Martinich, Moshref, Morison, &
Kundur, 2006). The statistical probability that the absolute worst case will occur is not
high.
When the voltage changes direction, the current will decrease. But in the next cycle the
current will increase again. The curse of events will continue with gradually decreasing
Electrical equipment in simulation programs
73
the peak value of the current. The influence of the original residual flux will also
gradually disappear. The number of cycles before steady-state is reached varies from
less than 10 cycles for small transformers up to several minutes for larger transformers.
A characteristic of the inrush current is that it contains a second harmonic component
because of asymmetrical half-cycles. Inrush currents tend to be higher on modern
transformers compared to transformers build 40 years ago. The reason is that modern
low loss core steel allows higher flux densities in the core without unacceptable high
core temperature as consequence.
4.4.3.2 Voltage dip due to transformer energization
Transformer energization is a common occurrence in the electric power system. Most of
the times energization results in the transformer needing large inrush current, which
eventually decreases to a small magnetizing current. The time the transformer demands
the inrush current depends on the resistance and reactance of the equipment, including
the transformer magnetizing reactance.
The inrush current could cause a temporary voltage drop due to the impedance of the
system between the source and the energized transformer. If the short circuit MVA
available at the transformer bus is low, the resulting voltage drop can be significant.
Typically a voltage sag or dip is a decrease in the system voltage to between 0.1 pu and
0.9 pu at the power frequency lasting from half cycle to one minute (Nagpal, Martinich,
Moshref, Morison, & Kundur, 2006).
A simple back-of-the-envelope method can be used to obtain an indication of the
maximum inrush current and the expected voltage sag due to it from the equivalent
circuit (Nagpal, Martinich, Moshref, Morison, & Kundur, 2006).The following equation
uses the source reactance (X) and assumes that the transformer iron core behaves like an
air core at saturation, with a value of two times the short circuit impedance. Being the
short circuit impedance the sum of the primary (Xp) and the secondary leakage
reactance of the transformer (Xt). The inrush current cannot exceed:
tp
MAXinrushXXXZ
VI
2
1_
(4.12)
Thus, the maximum voltage sag can be estimated as
_
2sag MAX
p t
XV
X X X
(4.13)
And since the primary side can be assumed as half of the transformer reactance
t
MAXsagXX
XV
5,2_
(4.14)
During the energization of a single wind turbine transformer in Nysted, taking into
account the reactance for the collection cable, reactances in the park transformer,
reactances from the sea cable, land cable and the grid; the maximum voltage sag is
calculated to be 6%. However further in the report this value was found to be extremely
Electrical equipment in simulation programs
74
high in comparison with the actual measurements and the sequential energization results
from the simulation programs.
In the paper where this equation was used, the maximum voltage sag calculated with the
back-of-the-envelope method and the maximum voltage sag simulated were very close
when switching the three phases simultaneously at the zero crossing of one phase.
4.4.4 Simple case simulation
In order to compare the low frequency transformer model for energization from Power
Factory and PSCAD a simple case simulation was done.
First a comprehensible explanation of the residual flux and its influence on the inrush
current based on (JH- Franklin, et al., 1983) was done for single phase transfromers in
Power Factory. Then several simulations were done changing the residual flux and the
pole closing time between phases in Power Facotry.
Then, a brief comparisson between available standard models of transformers in
PSCAD was done. Finally a comparisson between the energization of the same
transfromer in both simulation programs was done, achieaveing similar results in both
cases.
4.4.4.1 Power Factory- single phase transformer
In order to simulate the switching of a single phase transformer in Power Factory the 5
limb transformer should be used with YN/YN connection, since the fluxes in all three
branches must add to zero in a 3 limb core delta-winding transformer.
The Figure 4-7 shows the simple case model for the simulations in Power Factory. The
AC voltage source connected to a bus feeding the high voltage side of the transformer,
while on the low voltage side of the transformer is connected to the LV bus with no load
or generation.
Figure 4-7 Simple case-transformer. Power Factory system
Electrical equipment in simulation programs
75
For single phase transformers there are six limiting conditions to consider for the
switching in a transformer;
a) At zero voltage with no residual flux
b) At zero voltage with residual flux with same polarity
c) At zero voltage with residual flux with opposite polarity
d) At peak voltage with no residual flux
e) At peak voltage with residual flux with same polarity
f) At peak voltage with residual flux with opposite polarity
Each of these conditions are explained and simulated below.
a) At zero voltage- no residual magnetism
Under normal conditions the magnetic flux in the core, being 90° out of phase with the
voltage, reaches its peak value when the voltage passes though zero. Due to the phase
displacement it is necessary for the flux to vary from a maximum in one direction to a
maximum in the opposite direction in order to produce on half cycle the required back
e.m.f in the primary winding, so that the total flux is embraced during the half cycle
corresponding to twice the maximum flux density.
At the instant of switching in, there being no residual magnetism in the core the flux
must start form zero, and to maintain the first half cycle of the voltage wave it must
reach a value corresponding approximately to twice the normal magnetic flux density.
35.0028.0021.0014.007.000-0.000 [ms]
8.00
6.00
4.00
2.00
0.00
-2.00
2-Winding Transformer: Phase Voltage C/HV-Side in p.u.
2-Winding Transformer: Phase Current C/HV-Side in p.u.
2-Winding Transformer: Magnetizing Flux C in p.u.
VfluxI
Date: 4/7/2008
Annex: /7
DIg
SIL
EN
T
Figure 4-8 Simple case- transformer. Single phase a). Voltage, current and flux.
The voltage (red), current (green) and flux density (blue) waves for the previous
condition are shown in Figure 4-8 and Figure 4-9. The maximum value of the flux
density, vary gradually from nearly approaching twice the peak in one direction only,
down to a normal peak value located symmetrically on each side of the zero axis as can
be seen in Figure 4-9.
As the magnitude of the no-load current is dependent upon the flux density, it follows
that the current waves also will initiate unsymmetrical, and that they will gradually
Electrical equipment in simulation programs
76
settle down to a steady state conditions. However, in the case of the flux density the
transient value cannot exceed twice the normal, where the transient current reaches a
value very many times the normal no-load current and can exceed the full-load current.
The reason for this high inrush current is to be found in the characteristic shape of the
B/H curve of transformer steel core, which is shown in Figure 4-10 as flux/current in
p.u. From this figure it can be see that the for a small increase in the flux (0,9 to 1,3
p.u.) the current would largely increase in comparison with the current under steady
state conditions.
In Figure 4-10 is shown the two slope representation of the core saturation in blue,
while the polynomial representation with a saturation exponent of 13 and 7, green and
red respectively, are shown as well. This are two standard ways to represent the variable
reactance in the transformer in Power Factory, but care should be taken when choosing
a polynomial representation, because some problems might arise as it will be explained
in the next section.
500.0400.0300.0200.0100.00-0.000 [ms]
6.00
4.00
2.00
0.00
-2.00
2-Winding Transformer: Phase Voltage C/HV-Side in p.u.
2-Winding Transformer: Phase Current C/HV-Side in p.u.
2-Winding Transformer: Magnetizing Flux C in p.u.
VfluxI
Date: 4/7/2008
Annex: /7
DIg
SIL
EN
T
Figure 4-9 Simple case- transformer. Single phase a). Voltage, current and flux. 500 ms
Electrical equipment in simulation programs
77
0.50000.40000.30000.20000.10000.0000 [p.u.]
2.0000
1.6000
1.2000
0.8000
0.4000
0.0000
[p.u.]
2-Winding Transformer: Phase Current C/HV-Side in p.u./Magnetizing Flux C in p.u.
2-Winding Transformer: Phase Current C/HV-Side in p.u./Magnetizing Flux C in p.u.
2-Winding Transformer: Phase Current C/HV-Side in p.u./Magnetizing Flux C in p.u.
Tw o-slopes
7
13
Flux I
Date: 6/13/2008
Annex: /5
DIg
SIL
EN
T
Figure 4-10 Current- flux characteristic of transformers in Power Factory
b) At zero voltage-maximum residual magnetism having the same polarity to that to
which the flux would normally attain under equivalent normal voltage
conditions
If there is residual magnetism in the core at the instant of switching in and the residual
magnetism possesses the same polarity to that which the varying flux would normally
have, the phenomena described under (a) will be accentuated. This is, instead of the flux
wave starting at zero it will start at a value corresponding to the polarity and magnitude
of the residual magnetism in the core, and in the first cycle the flux will reach a
maximum higher than outlined in (a) by the amount of the residual flux. The theoretical
limit is three times the normal maximum flux density.
34.9227.9320.9513.976.9840.000 [ms]
8.00
6.00
4.00
2.00
0.00
-2.00
2-Winding Transformer: Phase Voltage C/HV-Side in p.u.
2-Winding Transformer: Phase Current C/HV-Side in p.u.
2-Winding Transformer: Magnetizing Flux C in p.u.
VfluxI
Date: 4/7/2008
Annex: /6
DIg
SIL
EN
T
Figure 4-11 Simple case- transformer. Single phase b). Voltage, current and flux
Electrical equipment in simulation programs
78
The Figure 4-11 illustrates the resulting transient flux/time distribution, while the inrush
current and voltage are showed as well. In this case the maximum value of the current
will be much higher and will take longer time to reach steady state conditions that in (a).
c) At zero voltage- maximum residual magnetism having a opposite polarity to
that to which the flux would normally attain under equivalent normal voltage
conditions
The converse of (b), where the residual magnetism has the opposite polarity as that
which is changing flux would normally attain, results in a diminution of the initial
maximum values of the flux, and consequently of the inrush current as can be seen in
Figure 4-12.
34.9227.9320.9513.976.9840.000 [ms]
8.00
6.00
4.00
2.00
0.00
-2.00
2-Winding Transformer: Phase Voltage C/HV-Side in p.u.
2-Winding Transformer: Phase Current C/HV-Side in p.u.
2-Winding Transformer: Magnetizing Flux C in p.u.
VfluxI
Date: 4/7/2008
Annex: /6
DIg
SIL
EN
T
Figure 4-12 Simple case- transformer. Single phase c). Voltage, current and flux
d) At maximum voltage- no residual magnetism
In this case at the instant of switching in, the flux should be zero, due to its 90° phase
displacement from the voltage, and with no residual magnetism in the core, the desired
conditions are obtain which produce the normal steady state time distribution of the
flux. That is, at the instant of switching in the flux start from zero, rises to normal
maximum in one direction, falls to zero, rises to normal maximum in the opposite
direction and again to zero, the wave being symmetrically disposed about the zero axis.
The no-load current, therefore, pursues its normal cause and does not exceed the
magnitude of the normal no-load current.
e) At maximum voltage-maximum residual magnetism having a polarity opposite to
that to which the flux would normally attain under equivalent normal voltage
conditions
This is the converse of the foregoing case, and the initial flux waves will again by
unsymmetrical disposed about the zero axis. For the same value of the residual
magnetism the total maximum flux would be the same as in case (e), but both flux and
current waves would initially be disposed on the opposite side of the zero axis.
Electrical equipment in simulation programs
79
f) At maximum voltage- maximum residual magnetism having a the same polarity
to that to which the flux would normally attain under equivalent normal voltage
conditions
In this case the residual magnetism introduces the transient component, so that the
initial flux waves are unsymmetrical disposed about the zero axis, high initial maximum
flux values are attained, and in the case where residual magnetism has the same value as
corresponds to the normal maximum flux density the inrush current will have a value
corresponding approximately to twice the normal maximum flux.
The voltage and flux for the six previous cases is shown in Figure 4-13. In the upper
plot the switching occurs when the voltage is zero, where the plot below presents the
fluxes when the switching occurs on the peak voltage.
40.0030.0020.0010.000.00 [ms]
3.75
2.50
1.25
0.00
-1.25
-2.50
Vc Opposite (e)
Zero (d)
Same (f)
40.0030.0020.0010.000.00 [ms]
3.75
2.50
1.25
0.00
-1.25
-2.50
Vc Same (b)
Zero (a)
Opposite (c)
Vflux(single)
Date: 4/7/2008
Annex: /6
DIg
SIL
EN
T
Figure 4-13 Simple case- transformer. Single phase a), b), c), d) e) and f). Zero crossing
(top) and peak crossing (bottom). Voltage and flux
The Figure 4-14 shows the fluxes (top) and currents (bottom) for all cases are compared
before. It can be clearly seen that the maximum current would happen during the
condition (b), where the switch closes on zero voltage and the transformer had resudial
flux on the same direction.
Electrical equipment in simulation programs
80
40.0030.0020.0010.000.00 [ms]
3.75
2.50
1.25
0.00
-1.25
-2.50
b
a
c
e
d
f
40.0030.0020.0010.000.00 [ms]
7.50
5.00
2.50
0.00
-2.50
-5.00
b
a
ce
d
f
Ivs
Date: 4/7/2008
Annex: /9
DIg
SIL
EN
T
Figure 4-14 Simple case- transformer. Single phase, all. Voltage (top) and flux (bottom)
4.4.4.2 Power Factory-three phase transformer
For three-phase transformers the previous operating principles are applicable, as long as
the normal magnetic relationships between different phases are considered, and each
phase is treated in combination with the remaining ones.
Normally the flux waves are simplified to sinusoidal functions in order to present the
phenomenon as clearly as possible, but the actual shape of flux and current waves will
be determined by the connections of the transformer windings and the type of magnetic
circuit.
A further simulation was done using a 3 limb delta winding transformer as the wind
turbine transformers in the collection grid of Nysted offshore wind farm.
First a comparison between switching when one of the phases was zero and peak
voltage was made. Then the residual flux during a zero voltage switching was varied in
the dq axis to obtain a worst case scenario. After these simultaneous pole closing, a non-
simultaneous pole energization of the transformer was done. Here, the switching was
made using the “worst case” (voltage on one of the phases was zero and the residual
flux on the other two was 0,8 with same polarity to that to which the flux would
normally attain under normal voltage conditions) for different times between pole
closing.
First a switching-in the transformer, was simulated, when one phase voltage was zero
(red) and then it was compared with a switching-in when the same phase voltage had
peak value. Figure 4-15 presents the voltages, fluxes and currents for the first case in
this comparison, where Figure 4-16 shows the results when he switching occurred on
peak voltage. The color nomenclature is shown in Table 4-3.
Electrical equipment in simulation programs
81
Form these two figures it can be seen that the highest current appears when the
switching happened in zero voltage crossing, with respect to the red phase, hence the
worst switching case is under the zero voltage crossing for any phase.
Table 4-3 Color nomenclature. Three phase, without residual flux.
Position Color Value
Top Blue Voltage phase A Green Voltage phase B Red Voltage phase C
Middle Light blue Magnetizing flux phase A Dark green Magnetizing flux phase B Pink Magnetizing flux phase C
Bottom Blue Current phase A Green Current phase B Red Current phase C
35.0028.0021.0014.007.0000.000 [ms]
3.000
1.800
0.600
-0.600
-1.800
-3.000
2-Winding Transformer: Phase Voltage A/HV-Side in p.u.
2-Winding Transformer: Phase Voltage B/HV-Side in p.u.
2-Winding Transformer: Phase Voltage C/HV-Side in p.u.
35.0028.0021.0014.007.0000.000 [ms]
3.000
1.800
0.600
-0.600
-1.800
-3.000
2-Winding Transformer: Magnetizing Flux A in p.u.
2-Winding Transformer: Magnetizing Flux B in p.u.
2-Winding Transformer: Magnetizing Flux C in p.u.
35.0028.0021.0014.007.0000.000 [ms]
4.000
2.400
0.800
-0.800
-2.400
-4.000
2-Winding Transformer: Phase Current A/HV-Side in p.u.
2-Winding Transformer: Phase Current B/HV-Side in p.u.
2-Winding Transformer: Phase Current C/HV-Side in p.u.
VI_2
Date: 6/19/2008
Annex: /10
Figure 4-15 Simple case- transformer. Three phase. Zero voltage switching
Electrical equipment in simulation programs
82
35.0028.0021.0014.007.0000.000 [ms]
3.00
2.00
1.00
0.00
-1.00
-2.00
-3.00
2-Winding Transformer: Magnetizing Flux A in p.u.
2-Winding Transformer: Magnetizing Flux B in p.u.
2-Winding Transformer: Magnetizing Flux C in p.u.
35.0028.0021.0014.007.0000.000 [ms]
3.00
2.00
1.00
0.00
-1.00
-2.00
-3.00
2-Winding Transformer: Phase Voltage A/HV-Side in p.u.
2-Winding Transformer: Phase Voltage B/HV-Side in p.u.
2-Winding Transformer: Phase Voltage C/HV-Side in p.u.
35.0028.0021.0014.007.0000.000 [ms]
4.000
2.400
0.800
-0.800
-2.400
-4.000
2-Winding Transformer: Phase Current A/HV-Side in p.u.
2-Winding Transformer: Phase Current B/HV-Side in p.u.
2-Winding Transformer: Phase Current C/HV-Side in p.u.
VI_1
Date: 6/19/2008
Annex: /9
Figure 4-16 Simple case- transformer. Three phase. Peak voltage switching.
Then, once the worst case switching is found, simulations with residual flux were done,
but only for this situation. Here, four cases were developed since the residual flux in
Power Factory can be only defined on d-q axis, and not independently on each phase.
These four cases are:
φd=0 and φq=1 (top-left)
φd=1 and φq=0 (top-right)
φd=0 and φq=-1 (bottom-left)
φd=-1 and φq=0 (bottom-right)
The voltages and fluxes for these cases are shown in Figure 4-17 and Figure 4-18,
respectively. Where the currents are presented in Figure 4-19. The color nomenclature is
shown in Table 4-4.
Table 4-4 Color nomenclature. Three phase, with residual flux
Left/right
Color Value
Voltages
Figure 4-17 Top/Bottom
Blue Voltage phase A
Green Voltage phase B
Red Voltage phase C
Flux
Figure 4-18 Top/Bottom
Light blue Magnetizing flux phase A
Dark green Magnetizing flux phase B
Pink Magnetizing flux phase C
Currents
Figure 4-19 Top/Bottom
Current phase A Current phase A
Current phase B Current phase B
Current phase C Current phase C
Electrical equipment in simulation programs
83
35.0028.0021.0014.007.0000.000 [ms]
3.000
1.800
0.600
-0.600
-1.800
-3.000
35.0028.0021.0014.007.0000.000 [ms]
3.000
1.800
0.600
-0.600
-1.800
-3.00035.0028.0021.0014.007.0000.000 [ms]
3.000
1.800
0.600
-0.600
-1.800
-3.000
35.0028.0021.0014.007.0000.000 [ms]
3.000
1.800
0.600
-0.600
-1.800
-3.000
Vvs(1)
Date: 6/19/2008
Annex: /6
Figure 4-17 Simple case- transformer. Three phase. With residual flux. Voltages
35.0028.0021.0014.007.0000.000 [ms]
3.000
1.800
0.600
-0.600
-1.800
-3.000
35.0028.0021.0014.007.0000.000 [ms]
3.000
1.800
0.600
-0.600
-1.800
-3.00035.0028.0021.0014.007.0000.000 [ms]
3.000
1.800
0.600
-0.600
-1.800
-3.000
35.0028.0021.0014.007.0000.000 [ms]
3.000
1.800
0.600
-0.600
-1.800
-3.000
psi vs
Date: 6/19/2008
Annex: /7
Figure 4-18 Simple case- transformer. Three phase. With residual flux. Fluxes
Electrical equipment in simulation programs
84
35.0028.0021.0014.007.0000.000 [ms]
6.000
3.600
1.200
-1.200
-3.600
-6.000
35.0028.0021.0014.007.0000.000 [ms]
6.000
3.600
1.200
-1.200
-3.600
-6.00035.0028.0021.0014.007.0000.000 [ms]
6.000
3.600
1.200
-1.200
-3.600
-6.000
35.0028.0021.0014.007.0000.000 [ms]
6.000
3.600
1.200
-1.200
-3.600
-6.000
I vs
Date: 4/5/2008
Annex: /7
DIg
SIL
EN
T
Figure 4-19 Simple case- transformer. Three phase. With residual flux. Current
It can be seen from Figure 4-19 that the highest currents are presented when φd=0, φq=-
1 (bottom-left) and when φd=-1, φq=0 (bottom-right). This can be explained from
Figure 4-18 (bottom-left) where the its noticeable that the magnetizing flux of phase B
(dark green), starts in 1 p.u.; where the magnetizing flux of phase C and A starts in 0,5
p.u. In Figure 4-18 (bottom-right) it can be seen that the magnetizing flux of phase B,
starts in 0 p.u.; where the magnetizing flux of phase C and A starts in 0,8 p.u. and -0,8
p.u., respectively. These two cases are shown graphically in Figure 4-20 where the same
color nomenclature for voltages and fluxes was used.
Figure 4-20 Residual flux and voltages. Left φd=0, φq=-1. Right φd=-1, φq=0
Electrical equipment in simulation programs
85
The problem with the residual flux defined in dq-axis is that there is no independence
between phases. The technical documentation of Power Factory is no very extensive in
this topic, where only few example cases refer to this phenomenon.
For the sequential transformer energization with residual flux in section 6, the case with
φd=-1, φq=0 was used since the inrush current is higher in this case, and is similar to the
“worst case” in (Smith, 2005).
Additional simulations were done with non-simultaneous closing of the breaker, with
and without residual flux, since in (Ma, et al., 2006) the authors mentioned that this
closing condition could lead to higher inrsh currents. But they don‟t mention the time
between each pole. Hence ten cases were done for five different closing times, with and
without residual flux as Table 7-2 in page 183 states.
It can be seen from Figure 7-1 to Figure 7-5 that the non-simultaneous closing does not
seems to worsen the inrush current. However additional work could be done in other
simulation programs where residual flux for each phase can be specified.
4.4.4.3 PSCAD-Single phase transformer
In PSCAD there are several single-phase and three-phase transformer models. In
general a three-phase transformer model can be made out of single phase transformer
models as Figure 4-21 shows of YD transformer.
Figure 4-21 PSCAD transformer equivalence
The transformer models in PSCAD are devided based on the classical approach and the
unified magnetic equivalent circuit (UMEC) approach.
The UMEC transformer models are based primarily on core geometry. Unlike the
classical transformer model, magnetic coupling between windings of different phases, in
addition to coupling between windings of the same phase, are taken into account
(PSCAD User's Guide, 2005).
For the current project the trasformers used are based on the clasical aproach. However
no simulations were done for the single-phase transformer.
Electrical equipment in simulation programs
86
4.4.4.4 PSCAD-three phase transformer
In this subsection the zero-voltage simultaneous pole energization of a transformer with
no residual flux was simulated in PSCAD (same event as Figure 4-15 in Power
Factory), in order to compare the same transformer model in both simulation programs.
The network used in this subsection is shown in Figure 4-22. Here the connection to the
grid is simulated as a voltage source, then a breaker is connected between the
transformer and the grid. On the low voltage side of the transformer a small load was
connected to avoid numerical problems.
It‟s important to notice that the grounding on the secondary side of the transformer is
simply connected with a “wire” device, as recommended in (PSCAD User's Guide,
2005).
In Figure 4-22 is possible to locate the voltage measurements on both sides of the
breaker and the current measurements in the primary side of the transformer.
The closing signals for the breaker are send individually for each phase, with a “Time
breaker logic” component used to control single and three phase breakers, to a signal
(BRKA, BRKB and BRKC) used to transfer data signals to the breaker.
Figure 4-22 Simple case- transformer. PSCAD
The results from the voltage and current measurements are send to an output channel,
that are further visualized in a graph, this measurements are shown in Figure 4-23.
Electrical equipment in simulation programs
87
Figure 4-23 Simple case-transformer. PSCAD. Results
The instantaneous voltage and currents are shown here with the color nomenclature as
stated on the upper side of each graph. If the current in Figure 4-23 is compared with
Figure 4-15 is possible to see the same shape and magnitude for the current. This proves
that both models match each other, regarding the saturated and un-saturated reactances
during energization.
In PSCAD the transformer model has an “inrush decay time constant” parameter that
gives the possibility to force a fast decay of the inrush current by artificially introducing
damping in the circuit. However this value was set to 0 for all the simulations, and the
inrush would be damped solely by the network.
4.4.5 Further inrush current control
There are possible solutions to reduce the residual magnetism in power transformers,
some of them are:
1. Switch off the load of the transformers before the primary circuit is opened
2. De-magnetization. Gradually reducing the applied voltage before switching the
transformer out of circuit. As the voltage decreases, the flux in the transformer
core also decreases.
3. De-energization. The transformer breaker can be controlled to achieve define
and repeatable remanent flux. Subsequent energization can be then matched
with known residual flux to minimize inrush current (ABB Controlled
Switching 2006-09).
On the other hand there are possible solutions to reduce the inrush current in power
transformers (Nagpal, Martinich, Moshref, Morison, & Kundur, 2006):
Electrical equipment in simulation programs
88
1. Include pre-insertion reactors, this adds impedance to the switched circuit and
thereby reduces the inrush. This is an expensive solution because an additional
substation is needed (Ma & Cadmore, 2006).
2. Transformers energized by segregated point-in-wave closing method requires
that the circuit breaker poles be switched at optimal instants to reduce or
eliminate inrush currents [Brunke, J.H., et al 2001]
Additional work should be done regarding a risk and economical analysis of the benefits
of reducing the residual flux, and inrush current in large offshore wind farms, since
maybe due to grid concerns or protection, specialized equipment would pay off.
4.5 High voltage cables
The cables used in the collection grid in Nysted Wind Farm are solid dielectric cables
with cross-linked polyethylene (XLPE) insulation. The XLPE cables have several
advantages over High-Pressure Fluid-Filled (HPFF) pipe-type cables that makes them
ideal for the use in offshore wind farms [Tziouvaras, D.A., 2006]:
Lower capacitance, resulting in lower steady-state charging current
Higher load-carrying capability
Lower losses
Lower maintenance cost because there is no dielectric fluid
No environmental risk due to insulating oil fluid leak
Immediate re-energization capabilities on system restoration
4.5.1 Cable modeling theory
Cables can be divided into two broad categories, shielded and unshielded. The effect of
the shield is to confine the electric field between itself and the conductor. Since the
current almost always returns through the conductor of the other phases, the magnetic
shield is not confined in the same way, it is nevertheless affected by the presence of the
shield and armoring because of eddy current induced within.
For low frequency transients the dominant attribute of the cable is the capacitance. The
cable can be therefore modeled as a capacitor in parallel with the load. For fast
transients, a distributed model is required. Because the conductors are in close
proximity it is necessary to consider the line and ground modes. Also when shields or
armor are grounded at one end only, a mode is added between this shield or armor and
the external ground plane.
In XLPE cables the skin effect, dielectric and semi-conductive layer losses are
responsible for a attenuation on the steep-fronted transient (Dick, et al., 1988).
4.5.2 Cable modeling application
According to the IEEE PES Task Force on insulated cable modeling (Gustavsen, et al.,
2005), there are several EMT programs that can accurately represent the frequency
dependence of the cables. These models require the same information: the series
impedance matrix Z and the shunt admittance matrix Y.
Electrical equipment in simulation programs
89
However other parameters are hard to obtain for cables system because the small
geometrical distance makes the parameters highly sensitive to errors. Furthermore, there
is no simple method to represent features like wire screens, semiconductive screens,
armor or lossy insulation materials.
The basic equations to represent insulated cables have the following form:
)()()(
)()()(
CjGY
LjRZ
(4.15)
where R is the series resistance, L the series inductance, G the shunt conductance and C
the shunt capacitance per unit length of the cable system. These quantities are (n x n)
matrices, being n the number of parallel conductors of the cable system. Both Z and Y
being frequency dependant quantities.
The series impedance Z and the shunt admittance Y are calculated automatically by the
cable constants routines within the program, using cable geometry and material
properties as input parameters. In general, the user must input:
Geometry
o Location of each conductor (x-y coordinates)
o Inner an outer radii of each conductor
o Burial depth of the cable system
Material properties
o Resistivity and relative permeability of all conductors
o Resistivity and relative permeability of the surrounding medium
o Relative permittivity of each insulating material
The calculation of Z and Y from the geometry and the material properties follows
similar procedure for all cable constant routines. However there are still challenges on
the impedance calculation, based on computing surface impedance and transfer
impedance of cylindrical metallic shields, as well as self and mutual ground
impedances. The standard routines in PSCAD include the skin effect but neglect the
proximity effect on the cable. However the losses due to these effects are small at
nominal frequency.
4.5.3 Conductive materials
Table 4-5 Material properties in cables
Resistivity Copper Aluminum Lead Steel
[m] 1,72E-8 2.83E-8 22E-8 18E-8
Stranded conductors are to be modeled as solid conductors, with an increased resistivity
to take into account the fill factor of the conductor, in order to achieve the correct
resistance. The corrected resistivity should be calculated as:
c
c
A
r2
'
(4.16)
Where, rc is the conductor radio and Ac the conductor area given from the manufacturer
for each phase. In the simulations of the next section, the corrected resistivity increased
Electrical equipment in simulation programs
90
about 7% due to the modification of equation (4.16) in the MV cables at Nysted
offshore wind farm.
In the same document it is mentioned that the resistivity of the surrounding ground
depends strongly on the soil characteristics, where a recommended value of 1 m for
wet soil.
The submarine cables in Nysted have a magnetic steel armor, consisting of a number of
round wires enclosing the three-phase cable; hence, the cable can be modeled using
“pipe-type” representation. Here, the permeability depends on the wire diameter, the
laying angle and the intensity of the circumferential magnetic field. This variation on
the permittivity arises problems with the calculation of the zero-sequence impedance of
the pipe-type cables, while zero-sequence impedance varies with the effective
permeability of the steel pipe, and the permeability of the steel pipe varies with the
magnitude of the zero-sequence current (Tziouvaras, 2006). However neither PSCAD
nor Power Factory supports armored three-phase cables.
4.5.4 Insulating materials
Table 4-6 XLPE relative permittivity
Relative permittivity XLPE
2,3
Most extruded insulations, are practically lossless up to 1 MHz. The losses are
associated with complex, frequency-dependant permittivity
'/'')(tan
)('')(')(
rr
rrr j
(4.17),(4.18)
where the tan is the insulation loss factor. This value should be set to zero, while non
of the available routines allows to enter a frequency-dependant loss factor and a
constant value would lead to inaccuracies.
As stated above, the main insulator of each conductor lays between to semiconductive
screens, unfortunately in the EMT programs it‟s not possible to specify these layers.
Therefore, a correction should be made in order to allow the insulation to extend
between the core and the sheath conductor, with the capacitance of the cable unchanged.
This can be done by
0
12
2
)/ln(
rrCr (4.19)
where the C is the cable capacitance, r1 the conductor radius, r2 the outer radius of the
insulation plus both semiconductive screens. In the simulations of the next section, the
corrected relative permittivity increased about about 10% due to the modification of
equation (4.19) in the MV cables at Nysted offshore wind farm.
Electrical equipment in simulation programs
91
4.5.5 Grounding
In submarine cables, the armor is usually thick for mechanical strength, thus preventing
any high- frequency flux to penetrate the armor, so no voltage drop will develop here.
However the armor and the sheath are grounded at both cable ends in the collection
grid. In reality, the outer metal wire armor is in contact with the soil, since it is only
covered with impregnated insulator.
With this connection, during transients, very small induced voltages would appear in the
sheath compared with voltages in the conductors. However the sheath and armor were
included in the studies when possible.
4.5.6 Sensitivity of transients
High-frequency cable transients propagate as decoupled coaxial waves between core
and sheaths, so the transient behavior of the cable is sensitive to the modeling of the
core, main insulation, semiconductors, and sheath. The sensitivity of coaxial waves can
be summarized as follows (Gustavsen, et al., 2005):
Increasing the core resistivity increases the attenuation and slightly decreases
propagation velocity
Increasing the sheath resistivity (or decreasing the sheath thickness) increases
attenuation
Increasing the insulation permittivity increases the cable capacitance. This
decreases the velocity of the surge impedance
With a fixed insulation thickness, adding semiconductive screens increases the
inductance of the core-sheath loop without changing the capacitance. This
decreases the velocity and increases the surge impedance
Since the sheath conductors are normally grounded at both ends, the potential along this
conductor is low compared to that of the core conductor, even in transient conditions.
As a result, the simulated transient on phase conductors are insensitive to the specific
properties of insulating materials external to the sheath.
Once the transient phenomena in cables and its modeling have been presented, the
simple study cases to compare Power Factory and PSCAD are explained.
For each simulation program four cases based in (Gustavsen, et al., 2005) has been done
with a fixed step value of 1 μs (145 kV, 5 km cable). The information for all the cases is
presented in Table 4-7. The different cases are:
3 mm lead sheath, 1 mm semiconductor on both side of the insulation
1 mm lead sheath, 1 mm semiconductor on both side of the insulation
0,211 mm copper sheath, 0 mm semiconductor on both side of the insulation
0,211 mm copper sheath, 3 mm semiconductor on both side of the insulation
Electrical equipment in simulation programs
92
Table 4-7 Simple case- cable. Information
Case Radius Resistivity Relative
permittivity
Outer radius Relative
permeability
Units [m] [Ω*m] [m]
1 Core 0,02 1,72E-08 1
Insulation 1 2,671 0,035 1
Sheath 2,20E-07 0,038 1
Insulation 2 2,3 0,043 1
2 Core 0,02 1,72E-08 1
Insulation 1 2,671 0,035 1
Sheath 2,20E-07 0,036 1
Insulation 2 2,3 0,041 1
3 Core 0,02 1,72E-08 1
Insulation 1 2,3 0,035 1
Sheath 1,72E-08 0,035211 1
Insulation 2 2,3 0,040211 1
4 Core 0,02 1,72E-08 1
Insulation 1 3,897 0,035 1
Sheath 1,72E-08 0,035211 1
Insulation 2 2,3 0,040211 1
4.5.7 Simple case in Power Factory
A step voltage on one of the phases of a cable has been modeled in Power Factory, as
the example in (Gustavsen, et al., 2005). The network for this simple case is shown in
Figure 4-24. Where the individual voltage sources for each phase are connected at
Terminal A. Here the conductor for the cable system is connected on one side, where
the other side of the cable is connected to Terminal B. The sheath conductor for the
cable system is connected between Terminal Sh A and Terminal Sh B.
Phase C
Phase B
Phase A
0.0000..
AC Voltag..
Sheath
0.0000..0.0000..0.0000..
0.0000..0.0000..0.0000..
Conducto
r
0.0000..0.0000..0.0000..
0.0000..0.0000..0.0000..
Terminal B0.0000.0000.000
Terminal A0.0000.0000.000
Terminal Sh B0.0000.0000.000
Terminal Sh A0.0000.0000.000
DIg
SIL
EN
T
Figure 4-24 Simple case- cable. Power Factory. Network
Electrical equipment in simulation programs
93
Once the sheath and the conductor network have been done, a cable system has to be
created, where the coupling between the sheath and the phases can be included. This
coupling can be seen in Figure 4-27.
Once the coupling has been created a single core cable element has to be added in the
Data Manager, since the cables are not standard components in Power Factory and they
are still under development.
The information needed for each single core cable (Table 4-7) must be set in the cable
type as Figure 4-25 presents. Then the geometrical position of each single core cable
has to be added in the cable definition, as Figure 4-26 shows.
Figure 4-25 Simple case- cable. Power Factory. Single core cables
Electrical equipment in simulation programs
94
Figure 4-26 Simple case- cable. Power Factory. Three phase cable
Figure 4-27 Simple case- cable. Power Factory. Cable system, basic data
Then, the cable system should be define as a distributed parameter, where the frequency
for parameter approximation (a frequency value representative of the range of frequency
expected for the study) should be used (Figure 4-28) (DigSILENT Technical
references). This cable system fixes this frequency during the entire simulation period,
which in the following section was proven to be give wrong results in the steady state of
the study cases 1 and 2.
Electrical equipment in simulation programs
95
Figure 4-28 Simple case- cable. Power Factory. Cable system, EMT simulations
4.5.8 Simple case in PSCAD
In this subsection the procedure to create the same study system for a cable, in PSCAD
as previously explained in Power Factory is shown.
First the cable interfaces for both sides of the cable has to be done, then the cable
configuration has to be added. It is important to notice that the cable interfaces and the
cable configuration has to have the same name (Cable1 in this case) in order for
PSACAD to understand that these are three parts of the same cable system. Then the
sheaths on each cable interface (S1) has to be grounded with a very low resistance to
avoid numerical problems.
Since the study case require that only one of the phases experience a step voltage, the
remaining phases on the same side of the cables had to be grounded, where in the other
side of the cable all phases were connected to a large resistance to emulate an open
circuit.
Electrical equipment in simulation programs
96
Figure 4-29 Simple case- cable. PSCAD. Network
Figure 4-30 Simple case- cable. PSCAD. Cable configuration.
In the cable configuration (Figure 4-30) the control constrains to solve the cable
behavior under transient condition, has to be define based on the recommendations of
the User‟s manual. Then coaxial cable constants for each single core cable are to be
define. Some of the information needed here is the position of each cable with respect to
each other and the soil, the thicknesses and electrical parameters of the cable conductors
and insulators, etc.
Electrical equipment in simulation programs
97
4.5.9 Comparison
The four cases, on each simulation program were done and the results were exported to
MATLAB in order to compare them. Figure 4-31 shows on the top the first two cases in
Power Factory (Va1PF, Va2PF) and PSCAD (Va1PSCAD, Va2PSCAD). Where the
lower part shows the last two cases in Power Factory (Va3 PF, Va4 PF) and PSCAD
(Va3PSCAD, Va4PSCAD).
Figure 4-31 Single case- Cable. Comparison
At first sight is noticeable that the response in Power Factory and PSCAD are very
different, however the main problem in Power Factory is that the voltage source is not
capable to realize step changes, and work independently with each phase. The
simulations were repeated in Power Factory several times with measurements files for
step voltages, capacitances between the conductor and sheath, etc.. However the
response never fit the results from PSCAD, or the figures on the paper from Gustavsen.
Nevertheless, some conclussions can be made from this comparisson, based on the cable
sensitivity under transeint conditions (subsection 4.5.6 in page 91):
In both simulation programs, an increase in the sheath resistivity (or decreasing
the sheath thickness) an increase in the attenuation is presented.
In both simulation program, an increase in the insulation permittivity increased
the cable capacitance, and this decreased the velocity of the voltage wave.
Electrical equipment in simulation programs
98
The rounding during first microseconds of the overvoltage, is not present in the
results from Power Factory. This phenomena is caused by the skin effect
representation in the core (frequency dependant).
Emphasis should be made in this comparison, since the results from Power Factory and
PSCAD are very different. The results presented in (Gustavsen, et al., 2005), are made
on EMTP-RV, where PSCAD is the graphical user interface of the simulation engine
EMTDC. Although the comparison was based on the simulation results from Gustavsen,
no measurements were done in the thesis on a cable.
However at Chalmers University of Technology, similar measurements on a real system
were reported in (Daniel & Gebre, 2008). Here, the authors initially charged a cable at
800 V and discharged through a COM-gap, to create a very steep fronted voltage.
Then the measurements were emulated using PSCAD with good agreement between
measured and simulated values. The frequency of oscillation and propagation delay in
the cable matched the measurements, although higher damping is observed in the real
system.
The results from Daniel & Gebre are important because they show that PSCAD results
can be trusted for a step voltage variation in a cable. On the other hand, the outcome of
the simulations done in the current thesis, reveal that the model in Power Factory for a
step voltage in a cable is inaccurate. However this conclusion cannot be extrapolated to
a real system, where other equipment is connected on both ends of a cable (study cases
in Nysted Offshore wind farm).
It was shown in the next section that Power Factory and PSCAD results, from a
switching event on a real system, are not as accurate as an insulation coordination study
would require.
Additional comments regarding the cable behavior under transient conditions in Power
Factory and PSCAD was done further in the report.
4.6 Voltage source
In the next section the study cases 1, 2, and 3, where simulation results in Power
Factory and PSCAD were compared with actual measurements, the grid connection at
132 kV was modeled as a voltage source with a series impedance that accounts for the
short circuit capacity and damping of the grid. These are important values for the
simulation since the “strength” of the system is simplified in this two values.
As stated in the section 2, 3 and subsection 4.5 the voltage source has key importance in
the switching transient studies. In section 2 and 3 was mentioned the importance of the
point-in-wave where the switching takes place since the overvoltages, reflections and
inrush currents are highly dependent in this parameter. In subsection 4.5 was shown
how the representation of independent voltage sources for each phase can result in
Electrical equipment in simulation programs
99
better simulation results. In section 6 one of the study cases to compare simulation
results has a decreased grid capacity, which has an influence on the voltage dip due to a
sequencial energization of a number of transformers.
In this subsection a comparison between voltage sources in Power Factory and PSCAD
was done, as well as a procedure to include accurately a voltage source for switching
transients.
First of all Power Factory has one very flexible AC voltage source, with many options
of control, while PSCAD Master Library includes three equivalent Thévenin voltage
source types. Each of these possesses distinctive features, so the system designer
should be aware of the differences.
In the three study cases and sequential energization of transformers, the Three-Phase
Voltage Source Model 3 was used. In this model it‟s possible to specify the positive
sequence and zero sequence source impedance. Here the source impedance is modeled
as aseries RL impedance. The difference with the other models in PSCAD is that this
source must be controlled externally, where the rms voltage and the phase angle are
inputs to the model, however these values can be constants.
Once the voltage source has been chosen for each simulation program, the magnitude
and phase of the voltage should be calculated based on the measurements. Here it‟s
important to notice that in both programs the phase angle is based on the moment when
the simulation begins, hence is recommended to start the simulation at time zero or with
variations every 20 ms.
From the measurements is possible to calculate the phase of the voltage, however care
should be taken, since there is a phase shift in the park transformer, and the initial angle
is defined differently in both programs.
Another important aspect of the switching transient studies is that the system should be
stable before the switching begins. In the case of the voltage source in PSCAD is
recommended that the voltage increase for 60 ms until the switching operations begins.
This is done by setting the “Voltage input time constant” to 0,06 s. This way the voltage
ramps up to 1 p.u. in three cycles to reduce start-up transients.
No simple case to compare the voltage sources in Power Factory and PSCAD was done.
However additional comment were realized further in the report.
4.7 Capacitors bank
The capacitor bank located on the low voltage side of the transformer on each wind
turbine, is in charge of compensate for the reactive consumption of the asynchronous
machine under generation.
In the first and second study cases there was a capacitor connected in A01, while in the
third study case additional capacitors were connected in A02, A03, A04, A05, A06, A07
and A08 since the generators in this wind turbines were under production.
Electrical equipment in simulation programs
100
It is a common use in the capacitor banks to include a reactor before the capacitors in
order to protect the banks, in this situation the reactor is indirectly defined by the degree
of inductance in the capacitor bank. This degree represents the ratio between the
inductive and capacitive reactance of the equipment. Hence if the reactive power
generation is known (Figure 3-22), as well as the nominal frequency and voltage on the
low voltage side of the transformer the reactance and capacitance can be calculated for
each case.
In Power Factory the capacitor banks in each wind turbines can be simply defined as a
Filter ABC-„D‟ with the rated reactive power and the degree in the bank. However in
PSCAD, the capacitance and inductance of the bank has to be calculated, as stated
before.
The capacitor bank in A01 with a rated capacity of 180 kVAr, and 5,6 % is presented in
Power Factory (left) and PSCAD (right) in Figure 4-32.
Figure 4-32 Capacitor bank
If the impedance characteristic of the bank is plotted (Figure 4-33) for different values
of inductance, is possible to see that if a wrong value of inductance is used, the
resonance frequency of the capacitor bank would change.
Is possible to see from Figure 4-33, that the resonance frequency for a value of 4,71E-4
H is around 210 Hz, similar to the resonance frequency achieved in the current at A01
(Figure 3-20-left). Hence, a capacitor bank is connected at A01. However, in the
PSCAD model of the filter, a value of 4,71E-5 H was used by mistake, as Figure 4-32
shows.
Electrical equipment in simulation programs
101
Figure 4-33 Capacitor bank impedance characteristic
Once the capacitor bank model was explained, the next electrical device left to explain
is the induction generator.
4.8 Generator
In the third study case, it was found after the active and reactive power calculation in
the measurements that seven of the nine wind turbines of row A were under production.
Thus in order to simulate this case as close to reality as possible, the generators were
included, nevertheless this was not part of the initial scope of the project.
The induction machine is relatively easy to define and use in Power Factory, where the
equivalent circuit should be defined, the nominal power, the operating condition
(motor/generator), the inertia, nominal frequency and number of poles pair.
In PSCAD the procedure is a little more complicated. First the model is set for a double
cage induction machine; here corrections had to be made to the equivalent model since
the equivalent model used in Power Factory is a single-cage machine. In reality the
double squirrel-cage induction machines are used to obtain high value of starting
resistance and low value of resistance at full load (Kundur, 1994). On page 294 of this
same book, the procedure to achieve an equivalent circuit for an induction machine with
double-cage rotor is presented. In this case the available information is on a single-cage
machine, and the required equivalent circuit for PSCAD should be calculated for certain
slip (under production).
Once the equivalent circuit is complete, the model is partially complete, since the
control has to be implemented. Here the machine has to be started in speed control
mode and then switched over to torque control after the initial transients of the machine
Electrical equipment in simulation programs
102
are over. The time to switch to torque control varies depending on the machine. This
change to torque control is important because in the wind turbines if there is a voltage
dip e.g. caused by a transformer energization, the machine would accelerate and
oscillate for several cycles, since it can be assume that the wind speed remains constant.
The equivalent circuit in Power Factory (left) and PSCAD (right) is shown in Figure
4-34. The simple study case here is to start the induction machine as a generator, then at
2 s one breaker would disconnect the machine for 10 ms. Here the machine would
accelerate since there is no electric torque to control it, then it would oscillate for
several cycles depending on the damping in the system and the inertia of the generators.
Figure 4-34 Simple case- Generator. Network
In Figure 4-35 the speed of the generators on both models are presented. The left side
plot of this figure is the results from Power Factory, while the plot in the right is the
calculated speed from PSCAD. Both simulations show the same behavior regarding the
oscillations. However the initial speed is not the same, this could be due to the fact that
the control of the machine in Power Factory is torque control for the entire simulation,
while for the PSCAD model the initial control speed set the velocity to 1.01 p.u.
Another difference is that the decreased speed after the re-connection of the machine is
lower in Power Factory than in PSCAD. Other important difference is that the system
seems to have larger damping in Power Factory than in PSCAD. Both of these
variations could be due to the different generator representation in the programs.
However, these disparities for the third study case are not really important.
Electrical equipment in simulation programs
103
Figure 4-35 Simple case- Generator. Rotor speed
Now that the main electrical devices in the collection grid of Nysted offshore wind farm
had been explained and compared between simulation programs, the computation of the
three main study cases was done in the next section.
4.9 Summary
In this section the electrical equipment needed to emulate the measurements of the three
study cases in Power Factory and PSCAD were explained. The theory behind the
modeling of a breaker was clarified. The transformer transient conditions were
explained based on theory and examples in Power Factory. Then, a satisfactory
comparison between the transformer model in Power Factory and PSCAD for
energizing studies was done.
The transient phenomena occurring in the cable during energization was presented, as
well as the guidelines for cable modeling. When a comparison was made between the
cable models in Power Factory and PSCAD, a clear difference was present due to the
simulated voltage source in Power Factory. After that, the voltage source models in
Power Factory and PSCAD were mentioned and compared.
The capacitor bank connected in the low voltage side of the transformer, which
compensates for the reactive power consumption of the induction generator under
production, was explained and compared in both simulation programs.
Finally the induction machine model in Power Factory and PSCAD, were compared
achieving similar results in a simple study case.
105
5 SYSTEM MODELING
5.1 General procedure
First of all, the information regarding the wind farm was gathered. Some of the
available information was:
The gird impedance and voltage level.
The sequence impedance and capacitance of the cables between the point of
connection with the transmission grid and the high voltage side of the park
transformer.
The impedance, rated power and voltage level of the three winding park
transformer.
The sequence impedance and capacitance of the submarine cables of the
collection grid.
The length of the cables between wind turbines and between the first wind
turbine of each row and the transformer platform.
The construction layers of the three phase cables, with its dimensions and
properties.
The short circuit voltage of the wind turbine transformers, the copper and iron
losses and the no-load current.
To account for the transformer energization the magnetizing reactances and knee
flux are required.
The high frequency capacitances between the HV windings to ground, LV
winding to ground and LV to HV windings.
The permanent LV load on each wind turbine.
The capacitors bank that compensates for the reactive power consumption of the
induction generator in each wind turbine.
The induction generator electrical representation.
Once all the available information was gathered the next step is to find the event to
simulate. In this project only three cases from many measured events were relevant. It
was decided that two “Energization of Row A” and one “Switch A09” were to be
simulated. On the first two cases the breaker on the platform that connects the row A is
closed, here the cable is energized follow by all the transformers in the row. In the last
case only the transformer in the wind turbine A09 was energized, and in theory, the rest
of the wind turbines were not under production, but as it was later demonstrated that
seven of the remaining turbines were almost at full production.
Once it was decided which events to simulate, the next step is to approach the
measurements files. Since they were made at 2.5 MHz and there are three voltages and
System modeling
106
three currents at three locations, the problem becomes quite large. The files for the first
two cases are divided each half second with a time stamp on the file‟s name, and one
file for each location. In these six files the data was unscaled 16-bit data from the DAQ,
so it had to be converted to kV and kA. For the third case the file‟s length is only 0,2 s
instead of 0,5 s from the two first cases. These measurements files are already scaled
and not conversion had to be made.
Once the files are located the time of the switching events had to be found. Since there
are samples every 400 ns the switching time for each phase is very precise. Another
important thing to calculate at this stage is the phase of the voltage, since it is very
important for switching studies. If the phase of the voltage is not the right one, the
reflection on the cable and the inrush current on the transformers would be different.
Just as a reminder the Figure 5-1 shows the simplified network of the study cases 1, 2
and 3. The three measurement locations can be located in blue color, while the “live”
equipment is shown in red, and the equipment without voltage in black.
Figure 5-1 Simplified network for study case 1, 2 and 3
The digital system of NOWF was created in both simulation tools, based on the
experience gained in the previous section. However, it‟s important to mention the
differences between both systems. The Table 5-1 shows a comparison of some of the
System modeling
107
models used for the transient simulations in both programs, as well as important
parameters for emt studies:
Table 5-1 Input information and models in both simulation tools
Equipment Attributes Power Factory PSCAD
Available Used Available Used
Circuit
breaker Detailed model No No Yes No
Tra
nsfo
rme
r
Models
2-winding
transformer
type
2-winding
transformer
type
Classical and
UMEC model Classical
Residual flux Yes Yes Yes No
High frequency
capacitances Yes Yes Yes Yes
Inrush decay
time constant No No Yes No
Cable 3 phase cable
with armor No No No No
Voltage
source Models
AC voltage
source
AC voltage
source
Voltage
source model
1, 2 and 3
Voltage
source model
3
Capacitor
bank Models Yes Yes No Yes
Induction
generator Models
Asynchronous
machine
Asynchronous
machine
Double- cage
induction
machine
Double- cage
induction
machine
Due to time limitations, the detailed circuit breaker model available in PSCAD was not
used to emulate the measured pre-strikes. However, there is no standard model in Power
Factory for this phenomenon.
The transformer models used in PSCAD was the classic model, since no detailed
information of the transformer was available besides the main electrical characteristics.
The residual flux of the transformer in Power Factory was used in the next section;
however there was no need for it in the study cases. Where the residual flux in PSCAD
was not used due to time constrains. The inrush decay time constant of the transformers
in PSCAD could be set to decrease the time to reach steady state after energization,
nevertheless there is no equivalent variable in Power Factory.
On the modeling of submarine cables, none of the simulation tools have the possibility
to model three-phase armored cables. Although, due to the grounding of the system, the
transients propagate as decoupled coaxial waves between core and sheath; and the
specific properties of the cable external to the conductor-insulation-sheath system have
no influence on the transient behavior of the cable.
The voltage source, capacitor bank and induction generator were simulated in Power
Factory and PSCAD as stated on the previous section, where no major difference were
expected.
System modeling
108
5.2 Study case 1: Connection of Row A-I
Assuming that the previous steps had been fulfilled the modeling of the network can
start. The modeling of the first case “Row A energization” was explained below. The
procedure for the second case is relatively the same, only the switching time is different.
However is important to model the second case because this time difference caused
higher transient overvoltages and higher inrush currents.
The procedure to create the model in Power Factory will be presented first and then the
procedure for PSCAD, afterwards the comparison between the measured and simulated
results was done.
5.2.1 Power Factory
The first thing to define in the network are the terminals or busbars, where the cables,
transformers, voltage sources, loads, capacitor banks and generators were connected. To
simplify things, and avoid confusion, the network was created based on the geometrical
arrangement of the network as Figure 3-1 shows.
Here the connection to the grid is in the top center part of the network, followed by the
HV cables to connect the park transformer. This part is shown in Figure 5-1.
LV load(8)
LV load(7)
LV load(6)
LV load(5)
LV load(4)
LV load(3)
LV load(2)
LV load(1)
LV load
Sea cableSea cable
A8-A9A8-A9
A7-A8(1)A7-A8(1)
A6-A7A6-A7
A5-A6A5-A6
A4-A5A4-A5
A3
-A4
A3
-A4
132 kV network
V~
A2-A3A2-A3
A1-A2A1-A2
Shunt/Filter
Lin
eL
ine
A8(1)A8(1)
A7(1)A7(1)
A6A6
A5A5
A4(1)A4(1)
A3(1)A3(1)
A2(1)A2(1)
A1(1)A1(1)
A9(2)A9(2)
H1
-H9
H1
-H9
G1
-G9
G1
-G9
F1-F
9F
1-F
9
E1
-E9
E1
-E9
DDCCBB
Ro
otH
Ro
otH
Ro
otG
Ro
otG
Ro
otF
Ro
otF
Ro
otE
Ro
otE
Ro
otD
Ro
otD
Ro
otC
Ro
otC
Ro
otB
Ro
otB
Ro
otA
Ro
otA
132/33/33 Transformer132/33/33 Transformer132/33/33 Transformer
Platform/Sea
Raadsand/B1
Radsted/Shore
H9G9F9E9
D9C9B9
A9(..A9
H1G1F1E1
D1C1B1
Platform Term 2/EFGH
A8
A7
A6(1)
A5(1)
A4
A3
A2
A1
Platform Term 1/ABCD
DIg
SIL
EN
T
Figure 5-2 Case 1. Power Factory. HV network.
Then on each winding of the transformer, four feeders are created with a MV submarine
cable to the first turbine of each row. Then, only the row A is further defined since the
measurements and the switching operations take place here only. The MV collection
grid of Nysted offshore wind farms created in Power Facotry is shown in Figure 5-3.
System modeling
109
LV load(8)
LV load(7)
LV load(6)
LV load(5)
LV load(4)
LV load(3)
LV load(2)
LV load(1)
LV load
Sea cableSea cable
A8-A9A8-A9
A7-A8(1)A7-A8(1)
A6-A7A6-A7
A5-A6A5-A6
A4-A5A4-A5
A3
-A4
A3
-A4
132 kV network
V~
A2-A3A2-A3
A1-A2A1-A2
Shunt/Filter
Lin
eL
ine
A8(1)A8(1)
A7(1)A7(1)
A6A6
A5A5
A4(1)A4(1)
A3(1)A3(1)
A2(1)A2(1)
A1(1)A1(1)
A9(2)A9(2)
H1
-H9
H1
-H9
G1
-G9
G1
-G9
F1-F
9F
1-F
9
E1
-E9
E1
-E9
DDCCBB
Ro
otH
Ro
otH
Ro
otG
Ro
otG
Ro
otF
Ro
otF
Ro
otE
Ro
otE
Ro
otD
Ro
otD
Ro
otC
Ro
otC
Ro
otB
Ro
otB
Ro
otA
Ro
otA
132/33/33 Transformer132/33/33 Transformer132/33/33 Transformer
Platform/Sea
Raadsand/B1
Radsted/Shore
H9G9F9E9
D9C9B9
A9(..A9
H1G1F1E1
D1C1B1
Platform Term 2/EFGH
A8
A7
A6(1)
A5(1)
A4
A3
A2
A1
Platform Term 1/ABCD
DIg
SIL
EN
T
Figure 5-3 Case 1. Power Factory. MV network
In order to create the coupling between the conductors and the sheath, a sheath network
had to be created as Figure 5-4 presents. Here the grounding in the platform and in each
wind turbine had to be created with an AC voltage sources as the Technical References
explains. At this stage the user has to be very careful since the length of the conductor
and the sheath has to be the same in order for the cable system to work.
The name of each of the cables and sheath has to be define in a clear way since the
“connection” in the cable system is done in the Data Manager and not graphically, and
its complicated when 23 cables and 23 sheaths has to be connected in 23 cable systems.
System modeling
110
Sh_A
8-A
9S
h_A
8-A
9
AC Gnd(..
AC Gnd
Ac Gnd B1-B9
Ac Gnd A0-A1(..
Ac Gnd A0-A1(..
Ac Gnd A0-A1(..
Ac Gnd A0-A1(..
Ac Gnd A0-A1(..Ac Gnd D1-D9Ac Gnd C1-C9
Ac Gnd H9
Ac Gnd H1
Ac Gnd G9
Ac Gnd G1
Ac Gnd F9
Ac Gnd F1
Ac Gnd E9
Ac Gnd E1
Ac Gnd A0-A1(..
Ac Gnd A0-A1(..
Ac Gnd A1-A9
Ac Gnd A0-A1Ac Gnd D0-D1Ac Gnd C0-C1Ac Gnd B0-B1
Sh H
1-H
9S
h H
1-H
9
Sh G
1-G
9S
h G
1-G
9
Sh F
1-F9
Sh F
1-F9
Sh E
1-E
9S
h E
1-E
9
Sh_R
_H
Sh_R
_H
Sh_R
_G
Sh_R
_G
Sh_R
_F
Sh_R
_F
SH
_R
_ES
H_R
_E
Sh_D
Sh_D
Sh_C
Sh_C
Sh_B
Sh_B
Sh_R
_D
Sh_R
_D
Sh_R
_C
Sh_R
_C
Sh_R
_B
Sh_R
_B
Sh_A
7-A
8S
h_A
7-A
8
Sh_A
6-A
7S
h_A
6-A
7S
h_A
5-A
6S
h_A
5-A
6S
h_A
4-A
5S
h_A
4-A
5S
h_A
3-A
4S
h_A
3-A
4
Sh_A
2-A
3S
h_A
2-A
3S
h_A
1-A
2S
h_A
1-A
2
Sh_R
_A
Sh_R
_A
Station D1/Sheath D1Station C1/Sheath C1Station B1/Sheath B1
Station B9/Sheath B9
Station A1(5)/Sheath A6
Station A1(4)/Sheath A5
Station A1(3)/Sheath A4
Station A1(2)/Sheath A3
Station A1(1)/Sheath A2 Station D9/Sheath D9Station C9/Sheath C9
Station A1(7)/Sheath A8
Station A1(6)/Sheath A7
Station A9/Sheath A9
Station A1/Sheath A1
Platform term 2/EFGH Sheath
Platform term 1/ABCD Sheath
H9G9
F9E9
F1E1
H1G1
DIg
SIL
EN
T
Figure 5-4 Case 1. Power Factory. Sheath network
Then the Single Core Cable Types, the Cable Definitions and Cable System Types have
to be created for the cables, as the subsection 4.5.7 in page 92 explained. Here is
important to notice that if the same cable is used in the collection grid, only one Single
Core Cable Type and Cable Definition can be used. However a Cable System Types has
to be created for each cable.
Once the cable systems were created, the electrical equipment connected on each wind
turbine has to be defined. Here a step-up transformer and a LV load were included in
each wind turbine terminal, where only in A01 a capacitor bank was include (Figure
5-5).
At this stage all the information regarding the voltage source, cables, transformers,
capacitor banks and filters has to be confirmed and verified before the switching
simulations begins, since finding a problem on the equipment in such a network is fairly
complicated.
Once the collection grid was complete, the switching events can be simulated based on
the measurements. The most important thing to remember here, is the switching time
and switching angle. The cubicle where the switching operation occurred can be seen in
Figure 5-5 at the end of the cable “RootA”.
System modeling
111
Figure 5-5 Case 1. Power Factory. A01
In Power Factory the distance between single phase conductors is set in the Cable
Definition. And base on the manufacturers datasheets a radial separation of 50 mm
between conductors can be calculated. The position of each phase is stated in Table 5-2
and shown graphically in Figure 5-6.
Table 5-2 Case 1. Power Factory. Cable 50 mm
A B C
X 0 0,0235 -0,0235
Y 0,98 1,03 1,03
Figure 5-6 Case 1. Power Factory. Cable 50 mm
However a comparison case had to be done in order to decrease the capacitive coupling
between phases, under sequential energization of the phases. Here a separation of 50 cm
System modeling
112
between phases horizontally placed was used, where the Table 5-3 presents the position
of each phase and Figure 5-7 shows graphically this separation.
Table 5-3 Case 1. Power Factory. Cable 50 cm
A B C
X -0,5 0 0,5
Y 1 1 1
Figure 5-7 Case 1. Power Factory. Cable 50 cm
6.0005.6005.2004.8004.4004.000 [ms]
40.00
20.00
0.00
-20.00
-40.00
6.0005.6005.2004.8004.4004.000 [ms]
40.00
20.00
0.00
-20.00
-40.00
6.0005.6005.2004.8004.4004.000 [ms]
40.00
20.00
0.00
-20.00
-40.00
DIg
SIL
EN
T
Figure 5-8 Case 1. Power Factory. Separation
The results from different simulation done in Power Factory are shown in Figure 5-8,
where the plots represent:
Top. 50 cm separation and 1950 Hz as frequency for parameter approximation.
Middle. 50 cm separation and 50 Hz as frequency for parameter approximation.
Bottom. 50 mm separation and 1950 Hz as frequency for parameter
approximation.
System modeling
113
From this figure it can be seen that the separation between phases and frequency for
parameter approximation are very important parameters for the emt simulations in
Power Factory. However is important to notice that a geometrical variation on the cable
has an influence on the impedance, nevertheless this variation gives reasonable results
for the study cases 1 and 2.
Another important difference at this stage, is that even with the relative permittivity
correction due to semiconductive layers on both sides of the insulation between the
conductor and the sheath, the velocity of the simulated voltage wave is different to the
measured one.
As mentioned before the pre-strike modeling was left out of the scope of the project due
to the reduced time for the theses. However sequential opening and closing operations
are possible to define in Power Factory. The Table 5-4 shows the closing and opening
times for the breaker operations, to emulate the measured pre-strike of the first study
case (Figure 3-11, page 44). Although, for the breaker to open/close, in emt simulation
in Power Factory, the breaker needs certain conditions to be met (zero crossing).
Therefore, no further simulations were done on this area.
Table 5-4 Case 1. Power Factory. Pre-strike times
Operation Phase B Phase A Phase C
Close 4,378 4,605 4,745
Open 4,472 4,700 4,837
Close 4,532 4,827 4,862
Open 4,625 4,956
Close 4,677 4,992
Open 4,775 5,088
Close 4,816 5,102
Another important result from Figure 5-8 is that it‟s not possible to achieve round
corners in the voltage steps after the closing of the breaker. Not even increasing
manually the resistivity of the conductor.
Another discovery here, is that it is not possible to notice the reflection of the voltage
waves when it arrives to the platform (at 4,47 ms for the green phase) and doubles, as
Figure 3-8 in page 42 shows. The voltage increases during the first ms of the event are
the reflection of the voltage wave bouncing between the platform and wind turbine A09.
If the voltage of phase B is plotted for each wind turbine of row A (Figure 5-9), it‟s
possible to see that the transformers are stressed non-uniformly, depending on the
position of it, within the collection grid as Liljestrand reported in (Liljestrand, et al.,
2008).
System modeling
114
4550.4514.4478.4442.4406.4370. [us]
0.40
0.00
-0.40
-0.80
-1.20
-1.60
-2.00
Platform
A1
A9
DIg
SIL
EN
T
Figure 5-9 Case 1. Power Factory. Phase voltage B
Further comparison between the results from Power Factory and the measurements was
done in the next subsections.
5.2.2 PSCAD
The procedure to create the model of Nysted offshore wind farm for transient
comparison of the study case 1 and 2 is presented in this subsection.
The procedure to create the network is in essence, the same as in Power Factory. Here
everything begins with the voltage source on the top, connecting the park transformer
through two HV cables, represented here as PI sections. Then on each winding, a
connection to three phase breakers, followed by a cable interfaces is made. The previous
mentioned models are shown in Figure 5-10. Here is important to remember that is
recommended that all the equipment is grounding with a small resistance using wires.
The Time breaker logic for the breakers “Row A”, “Row B,C,D” and “Row E, F, G, H”,
are shown in the top-right of Figure 5-10. To avoid numerical problem on the solution
the cables of the rows B, C and D were modeled together where the rows E, F, G and H
were also modeled together. The cables are modeled as explained in subsection 4.5.8 on
page 95. In Figure 5-11the cable interfaces and cable configuration for the cables
“RootA” , “RootBCD” and “RootEFGH” are shown.
System modeling
115
Figure 5-10 Case 1. PSCAD. HV network
Figure 5-11 Case 1. PSCAD. MV network
Then, on each wind turbine a breaker on the primary side of the wind turbine
transformer was connected, followed by a LV load. In wind turbine A01 a capacitor
bank was modeled as subsection 4.7 in page 99 explained. The capacitances for high
frequency studies in the transformers are shown in Figure 5-12. Where the capacitance
between the HV windings to ground, LV winding to ground and LV to HV windings are
shown as C1, C3 and C2, respectively.
System modeling
116
Figure 5-12 Case 1. PSCAD. A01
The same procedure is repeated for the eight remaining wind turbines, with the
exception that the voltages and current fore each phase are only measured in A01 and
A09.
5.2.3 Transient comparison
The following figures and explanation accounts for the comparison between
measurements and simulation results in Power Factory and PSCAD for the study case
number 1.
Throughout this subsection the instantaneous value of the current and voltage for the
measurements, results from Power Factory and PSCAD are plotted as “–m”, “-pf” and
“-ps” respectively. Where the rms values of the current and voltage for the
measurements, results from Power Factory and PSCAD are plotted as “m”, “PF” and
“PSCAD” respectively.
The same color nomenclature for instantaneous current and voltages for each phase was
used as well in this subsection; where the blue is used for phase A, green is used for
phase B and red is used for phase C. A common use of line nomenclature was used;
where the solid line represents the measurements, the dot-slash line represents the
results from Power Factory and the dashed line the results from PSCAD. However in
the rms, FFT and power comparison of the results another color and line nomenclature
was used.
The Figure 5-13 shows the first milliseconds of the three phases in the platform. It can
be seen that the overvoltages due to voltage reflections in the row are not replicated by
any software. As well is possible to notice a decrease on the voltage of phase C in
PSCAD, before this phase is energized.
System modeling
117
Figure 5-13 Case 1. Platform voltages (4,3-5,5 ms)
If each phase (A: Figure 5-14; B:Figure 5-15; C:Figure 5-16) is separated by location is
possible to see that the velocity of the wave in both simulation programs is higher than
the measured velocity.
Figure 5-14 Case 1. Phase A voltage for each location (4,3-5,5 ms)
For phase A the voltage at A09 (Figure 5-14-bottom) it can be seen that PSCAD
overestimate the doubling effect under open circuit of the voltage wave. For phase B the
voltage at A09 (Figure 5-15-bottom) it can be seen that Power Factory overestimate the
System modeling
118
doubling effect under open circuit of the voltage wave. Where the voltage phase C at
A09, the overvoltage is higher in the measurements.
From the same comparison in the platform for phase A, B and C (Figure 5-14-top,
Figure 5-15- top, Figure 5-16-top) is possible to notice that only PSCAD can simulate
the reflections on the platform, or at least the wave seems less random.
Figure 5-15 Case 1. Phase B voltage for each location (4,3-5,5 ms)
Figure 5-16 Case 1. Phase C voltage for each location (4,3-5,5 ms)
If now the voltage at the platform is plotted until 10 ms, it‟s possible to see that the
oscillations in the voltage were not presented in any of the simulation programs.
System modeling
119
Figure 5-17 Case 1. Platform voltages (4-10 ms)
If the voltage is now plotted for the first 50 ms is possible to notice that there are small
differences between the measured and simulated voltages. On the lower part of the wave
the discrepancy is larger on phase A, where in the lower part of the wave the measured
voltage seems to have higher amplitude. For phase A is also visible some kind of phase
shift but only when the voltage varies from maximum to minimum value.
Figure 5-18 Case 1. Platform voltages (4-50 ms)
System modeling
120
These differences could be due to measurement errors, but also to the simplification in
the voltage source, where the source is assumed as balanced.
To continue with the comparison, the instantaneous current in the platform are shown in
Figure 5-19, for the first milliseconds corresponding to the time to charge the MV cable.
Here is possible to see that the measured current in all phases is interrupted after zero
crossing, where the simulated currents are not. Here the only comparison that can be
made is that the relative value of the charging currents for the first “half-waves” is
similar for both simulation programs and the measurements.
Figure 5-19 Case 1. Platform currents (4-5,5 ms)
A further comparison for the first 50 ms of the current in the platform (Figure 5-20)
illustrates the inrush current required by the nine transformers of the row. Here is
possible to visualize that the currents simulated in Power Factory are higher than the
ones in PSCAD. However both are higher than the actual measured current, this could
be explain by the fact that it was assumed that the saturation characteristic of the nine
transformers were the same. Maybe in reality the transformers in wind turbines A02,
A03, A04, A05, A06, A07 and A08 are not identical to the ones in A01 and A09.
Another reason for the different inrush currents is the voltage, since the magnetic flux in
the transformers is the integral of the voltage, an increased voltage would produce and
increased flux, and this, based on the saturation curve would demand higher current.
System modeling
121
Figure 5-20 Case 1. Platform currents (4-50 ms)
The current in A01 is shown in Figure 5-21, and again, a higher inrush current is
achieved from Power Factory. Here a high harmonic current is present on the three
phases in the measurements and simulations. However this is more accentuated in phase
B and C from PSCAD. The current on phases B and C from Power Factory fits better
the measurements after 20 ms, in comparison with PSCAD.
Figure 5-21 Case 1. A01 currents (0-50 ms)
System modeling
122
The Figure 5-22 presents the current at A01 for the entire simulation time. It‟s possible
to see from this figure that the first cycles present the highest instantaneous current, of
the entire period.
Figure 5-22 Case 1. A01 currents (0-500 ms)
The FFT spectrum for each phase on each simulation program and the measurements on
A01, is shown in Figure 5-23. It‟s possible to see that in phase A and C the harmonic
content for 200 Hz is higher in Power Factory than in the measurements or the results
from PSCAD. Another important difference is that none of the simulation programs
could emulate the harmonic contents of the measurement around 211 Hz.
This same figure also shows that the harmonic content of the current on all the phases in
PSCAD has a component around 470 Hz. This is caused by an error when defining the
capacitor bank‟s inductance.
The Figure 5-24 presents the inrush current for each phase in A09, from the
measurements and the results from both simulation programs. It can be seen from this
figure that the inrush currents for the first cycle are overestimated in Power Factory and
PSCAD, however the currents are higher is Power Factory.
If the same currents are now plotted for the entire simulation period (Figure 5-25), it can
be seen that both simulation programs fits very well to the overall instantaneous current.
System modeling
123
Figure 5-23 Case 1. A01 currents FFT
Figure 5-24 Case 1. A09 currents (0-50 ms)
System modeling
124
Figure 5-25 Case 1. A09 currents (0-500 ms)
If the same currents are plotted only for the first milliseconds (Figure 5-26), is possible
to see the current spikes appearing due to the charging of the capacitances in the
transformer. However is not very clear the difference between each simulation program.
Figure 5-26 Case 1. A09 currents (4-6 ms)
For this, the Figure 5-27 presents only the current for the phase B on A09 for the first
milliseconds. From here is possible to see that neither one of the simulation programs
can emulate the magnitude of the current spikes.
System modeling
125
Figure 5-27 Case 1. A09 current phase B (4-6 ms)
Once the instantaneous voltage and currents have been compared between simulation
results in both programs and measurements, a comparison of the rms values can be
done. First the rms currents at the platform from the measurements, Power Factory and
PSCAD are shown in Figure 5-28. It can be seen here that the inrush current in the real
system decays slower that in the simulations.
Figure 5-28 Case 1. Rms current at platform
System modeling
126
From the last figure is important to notice as well that two of the highest currents on the
first cycle are from Power Factory, as explained before in the instantaneous current.
Another important difference in the current is the final state of it; further discussion was
done in the next subsection for the currents in the three locations, with both simulation
programs and the measurements at steady state.
The Figure 5-29 presents the results from the calculated rms current at A01 and A09.
Here, the currents in A01 are higher than the ones at A09, due to the capacitor bank
connected at A01. It‟s also important to notice an increase in the current from Power
Factory in A01 between 10 and 20 cycles compared with the measured current and the
results from PSCAD.
Figure 5-29 Case 1. Rms current at A01 and A09
If the active power is calculated as mentioned in subsection 3.4.3 in page 50, is possible
to compare the results from the simulations and the measurements a little further. The
calculated active power in the platform is shown in Figure 5-30. Here the active power
calculated from the measurements is shown in blue, the active power calculated from
the Power Factory is shown in green and finally the active power calculated from the
PSCAD is shown in red. In this figure a discrepancy in the results from Power Factory
is clear. A difference of 3,7 MW at the end of the simulation period is present here, the
explanation of this discrepancy is explained in the next subsection.
System modeling
127
Figure 5-30 Case 1. Active power at platform
If the active power is now calculated for the wind turbines A01 and A09, the difference
between the equipment connected at the LV side of the transformer can be noticed
(Figure 5-31).
With respect to the active power consumption in A01 is possible to see that there are
differences between the real system and the simulations. There are considerable
variations in the active power consumption from the measurements; however the most
surprising variation is in the simulation results, where negative consumption is
calculated in both programs. Here the only explanation is the method to calculate the
active power from instantaneous values, and the addition of harmonic current to the
signal.
The active power consumption in A09 reach steady state after 5 cycles in both
simulation programs, however in reality the decay of the inrush current in the
transformer is decided by the internal and external losses to the transformer. If the
resistance (damping) in the system is very low, the inrush current will take several
seconds to decay. Hence the damping in the real system is lower than in the simulations.
Now, if the reactive power is calculated from the voltages and current at the platform,
the difference between the measurements, Power Factory and PSCAD can be seen
(Figure 5-32). Here, as explained before, the damping of the inrush current is lower in
the real system than in the simulations, however Power Factory presents the highest
damping, this fact is important for the following subsection where the steady state
comparison is made.
System modeling
128
Figure 5-31 Case 1. Active power at A01 and A09
From Figure 5-32 is not very clear the value of the reactive power at 25 cycles, however
additional remarks are done in the following subsection.
Figure 5-32 Case 1. Reactive power at platform
Then, the reactive power for A01 and A09 is shown in Figure 5-33. Here is possible to
see that at 25 cycles the reactive power consumption at A01 reach a negative state
(reactive power production) in both simulations, explained only by the capacitor bank of
System modeling
129
180 kVAr on the LV side of this transformer. However the measurement does not show
this negative excursion since the energizing of the transformer has not finished.
On the other hand, the reactive power never reaches a negative value on A09, for any
simulation program. It is clear from this figure as well, that the damping from Power
Factory is very different between A01 and A09, where the only physical difference is 4
km of cable.
Figure 5-33 Case 1. Reactive power at A01 and A09
The active and reactive power consumption during the first cycle in at the platform and
at A09 are shown in Table 5-5:
Table 5-5 Case 1. Active and reactive power during the first cycle.
Active Power [MW] Reactive Power [MVAr]
A09 9xA09 Platform Difference A09 9xA09 Platform Difference
Measurements 0,09 0,81 1,2 0,39 3,0 27,0 30 3,0
Power Factory 0,04 0,36 6,0 5,64 5,0 45,0 57 12,0
PSCAD 0,04 0,36 1,2 0,84 4,3 38,7 40 1,3
From the last table, it can be seen that there is a large difference during the first cycle in
the reactive and active power in Power Factory, between the values at the platform and
a simple addition on the active and reactive power consumption in A09. The only place
where this power can be consumed is the collection cables. Further discussion was done
in the following subsection.
The rms voltage at the platform, calculated each cycle is shown in Figure 5-34, for the
measurements and both simulation programs. Here is possible to see that the phase
System modeling
130
voltages from the measurements are not balanced and that they increase with the time,
as (Abdulahovic & Thiringer, 2007) reported. This is due to the charging of the
capacitance in the cable, which does not seem to be well replicated in any simulation
program.
Figure 5-34 Case 1. Rms voltage at platform
If only the calculated rms voltages from the measurements are plotted (Figure 5-35), is
possible to see that the voltage at A09 is higher that the voltage at A01. This could be
related to the charging of the cable capacitances.
However, if the calculated rms voltages from Power Factory are plotted (Figure 5-36) a
voltage drop in the cable between the platform and A01, and between A01 and A09 is
visible. This could be explained from the steady state current in the platform from
Power Factory (Figure 5-28) where a current of 70 A is flowing.
In the same way, if only the calculated rms voltages from PSCAD are plotted, shown in
Figure 5-37, the voltage drop in the cables is not visible. However all the voltages are
lower than in Power Factory. This could be due to the voltage drop in the HV cables and
the park transformers, since the p.u. value of both voltage sources was the same and
neither the park transformer nor the HV cables were compared between simulation
programs.
System modeling
131
Figure 5-35 Case 1. Rms voltage from measurements
Figure 5-36 Case 1. Rms voltage from Power Factory
System modeling
132
Figure 5-37 Case 1. Rms voltage from PSCAD
Once the transient comparison of the study case has been made, the steady state
comparison can be realized.
5.2.4 Steady state comparison
In the Table 5-6 the steady state values of the current and voltages for each phase, based
on the calculations done in Table 3-2 on page 56 and the results from the previous
subsection, are summarized.
Here is possible to see that the rms currents from the measurements and Power Factory
are extremely large in comparison with the ideal case (calculated). However the current
difference in the measurements is due to the low damping in the system, as explained
before. Nevertheless the disparity in Power Factory has not been yet clarified. For this,
four additional simulations were done where the method for solution was changed (rms
instead of emt), as well as the frequency for parameter approximation in the cables and
the core characteristic in the transformers were changed.
The four cases are shown in Figure 5-38, where the top plot is the real power and the
bottom plot the reactive power in the platform for the study case 1. The color
nomenclature is:
Red. Emt simulations, with 1950 Hz as frequency for parameter approximation
in cables and two slope representation of the core reactances.
Green. Emt simulations, with 1950 Hz as frequency for parameter approximation
in cables and polynomial representation of the core reactances with saturation
exponent 7.
System modeling
133
Blue. Emt simulations, with 50 Hz as frequency for parameter approximation in
cables and two slope representation of the core reactances.
Pink. Rms simulations.
Here, is important to notice that the model representation in Power Factory, for the same
equipment, is different depending on the type of simulation (rms or emt). Where the rms
results (pink), are closer to the calculated values.
In Figure 5-38 is possible to notice that the emt results using 1950 Hz as frequency for
parameter approximation, gives a active power consumption of 3,7 MW, where the rms
results as well as the emt using 50 Hz as frequency for parameter approximation are
closer to the calculated steady state value. This problem is easily explain since the
impedance value of the cable is frequency dependant as equation (4.15) presented, and
this value is fixed in Power Factory as the frequency for parameter approximation,
where in PSCAD is variable. A value of 1950 Hz as the frequency for parameter
approximation would increase the impedance largely in comparison with only 50 Hz.
If the reactive power is compared (bottom plot in Figure 5-38) is possible to see that the
only case where the reactive power is consumed in the network is with the polynomial
representation of the core reactances with saturation exponent 7. As Figure 4-10 in page
77 shows, around the knee flux the reactance varies largely from a two-slope
representation and a polynomial representation. And since the voltage in the platform in
Power Factory is higher than 19 kV (1 p.u.), the flux would also be higher than 1 p.u.,
near the knee flux value of 1,1 p.u.
0.5000.4800.4600.4400.4200.400 [s]
5.00
3.75
2.50
1.25
0.00
-1.25
RootA: P in MW (emt-1950 Hz-Tw o-slope)
RootA: P in MW (emt-1950 Hz-Polynomial)
RootA: P in MW (emt-50 Hz-Tw o-slope)
RootA: P in MW (rms)
0.5000.4800.4600.4400.4200.400 [s]
5.00
3.75
2.50
1.25
0.00
-1.25
RootA: Q in MVAr (emt-1950 Hz-Tw o-slope)
RootA: Q in MVAr (emt-1950 Hz-Polynomial)
RootA: Q in MVAr (emt-50 Hz-Tw o-slope)
RootA: Q in MVAr (rms)
DIg
SIL
EN
T
Figure 5-38 Case 1. Power Factory. Steady state
System modeling
134
Table 5-6 Steady state values (at 25 cycles) for current and voltages
Steady state comparison Phase A Phase A Phase A Average
Cu
rren
t [A
] Platform
Calculated 8,50 8,50
Measured 50,00 49,00 21,00 40,00
Power Factory 70,00 71,00 72,00 72,00
PSCAD 8,00 9,00 9,00 8,67
WT A09
Calculated 0,10 0,10
Measured 5,00 1,40 5,00 3,80
Power Factory 0,50 0,30 0,40 0,40
PSCAD 0,40 0,20 0,40 0,33
Vo
ltag
e
[kV
]
Platform
Calculated 19,05 19,05
Measured 19,84 19,67 19,98 19,83
Power Factory 19,47 19,47 19,47 19,47
PSCAD 19,11 19,11 19,11 19,11
In Table 5-7, the steady state values of the real and reactive power at A09 and the
platform are shown. Here is clear the difference mentioned before about the active
power consumption in Power Factory, due to defining the frequency for parameter
approximation to 1950 Hz.
Where the difference between the real system and the ideal one (calculated), is the
damping in the inrush currents. In both simulation programs the cables generate reactive
power close to the ideal system, where the difference is that in Power Factory the
reactive power generation is higher due to the increased voltage in the platform.
Table 5-7 Steady state values (at 25 cycles) for real and reactive power
Real Power [MW] Reactive Power [MVAr]
Platform WT A09 Platform WT A09
Calculated 0,050 0,005 -0,483 0,000
Measured 0,152 0,015 1,519 0,132
Power Factory 3,690 0,005 -0,625 0,030
PSCAD 0,048 0,005 -0,555 0,020
Once the study case 1 has been fully analyzed, the other study cases can be examined.
5.3 Study case 2: Connection of Row A-II
In essence the second study case and the first one are the same, only the switching
moment had changed. This time difference in the point-in-wave of the voltage caused
higher overvoltages and inrush currents. The main figures are presented next, where the
rest of them are attached in the appendix B.
5.3.1 Power Factory and PSCAD
The model for the first study case was used in both programs. However, the phase angle
and the magnitude in the voltage source had to be changed. Then the switching events
for each phase in the breaker were defined based on the measurements.
System modeling
135
5.3.2 Comparison
Figure 5-39 shows the platform voltages from the measurements and both simulation
programs. It is possible to see in phase A (blue) several overvoltages due to the
reflection of the voltage wave. These overvoltages are also visible in phase B (green)
and phase C (red), nonetheless these values are not as high in comparisson with phase
A.
From this same figure is possible to see, that none of the simulation programs can
emulate the overvoltages due to wave reflections.
Figure 5-39 Case 2. Platform voltages (20-22 ms)
If the current in the platform is plotted for the first 50 ms after the switching event
(Figure 5-40), is possible to see the inrush current from the nine transformers. As
explained before, the measurements present a flat top, due to measurement errors.
However is important to notice that the inrush current in both programs decay faster
than in the real system. This is due to a higher damping in the digital systems, as
explained in the previous subsection.
The difference in the current peak is caused by a lower voltage in the simulations, as
Figure 5-43 shows graphically. Here is possible to notice that the real system has an
initial higher voltage than both simulation models.
System modeling
136
Figure 5-40 Case 2. Platform currents (20-70 ms)
When the currents at A01 are plotted (Figure 5-41), a high harmonic current in all
phases is visible. This is caused by the capacitor connected on the LV side of the
transformer. As well is important to mention, that the inductance in the capacitor bank
from PSCAD has the wrong value, and the system is tuned incorrectly.
Figure 5-42 shows the current at A09. In this turbine no capacitor bank is connected,
hence no harmonic currents are present.
Figure 5-41 Case 2. A01currents (10-70 ms)
System modeling
137
Figure 5-42 Case 2. A09 currents (10-70 ms)
Figure 5-43 Case 2. Rms voltage at platform
The rest of the plots from this study case are attached as appendix B, at the end of the
report. However no additional conclusion, different from the first study case, can be
made
System modeling
138
5.4 Study case 3: Switch A09
Just as a reminder the Figure 5-44 shows the simplified network of the third study case,
where seven wind turbine generators were under production, and the transformer in A09
is energized.
Figure 5-44 Simplified network for study case 3
It‟s important to notice that in this study case it was not necessary to model the cable as
in the previous two cases. Here the cables were modeled as PI sections in PSCAD and
as Lines in Power Factory. In Power Factory seven generators were connected on the
low voltage side of the wind turbine transformer with its capacitor bank. In PSCAD one
wind turbine was connected with seven coherent machines, with a larger capacitor bank
and larger transformer.
The capacitor bank in A01 was set to 180 kVAr as in the previous cases with the same
low voltage load. For A09 the low voltage load was increased to 0,08 MW.
5.4.1 Power Factory
As mentioned before, a new model of the collection grid was created in Power Factory.
Figure 5-45 shows the new MV network. Here, the cables in row A were modeled as
simple lines with positive and negative sequence resistance and reactance, to decrease
the time of simulation. This was done because in this switching event no transient
phenomena occurred in the collection cables.
System modeling
139
The transformers on each wind turbine were modeled as in the previous study cases.
Although the low voltage equipment connected on the wind turbines was changed. In
A01 the only equipment connected was the LV load and the capacitor bank. In the wind
turbines A02, A03, A04, A05, A06, A07 and A08 an induction generator and a
capacitor bank were connected. In A09 the LV load was increased to 0,08 MW.
C(7)
C(6)
C(5)
C(4)
C(3)
C(1)
C(2)
WTG(..
G~
WTG(..
G~
WTG(..
G~
WTG(..
G~
WTG(..
G~
WTG(..
G~
WTG
G~
LV load(8)
LV load
Sea cableSea cable
A8-A9A8-A9
A7-A8(1)A7-A8(1)
A6-A7A6-A7
A5-A6A5-A6
A4-A5A4-A5
A3
-A4
A3
-A4
132 kV network
V~
A2-A3A2-A3
A1-A2A1-A2
Shunt/Filter
Lin
eL
ine
A8(1)A8(1)
A7(1)A7(1)
A6A6
A5A5
A4(1)A4(1)
A3(1)A3(1)
A2(1)A2(1)
A1(1)A1(1)
A9(2)A9(2)
H1
-H9
H1
-H9
G1
-G9
G1
-G9
F1-F
9F
1-F
9
E1
-E9
E1
-E9
DDCCBB
Ro
otH
Ro
otH
Ro
otG
Ro
otG
Ro
otF
Ro
otF
Ro
otE
Ro
otE
Ro
otD
Ro
otD
Ro
otC
Ro
otC
Ro
otB
Ro
otB
Ro
otA
Ro
otA
132/33/33 Transformer132/33/33 Transformer132/33/33 Transformer
Platform/Sea
Raadsand/B1
Radsted/Shore
H9G9F9E9
D9C9B9
A9(..A9
H1G1F1E1
D1C1B1
Platform Term 2/EFGH
A8
A7
A6(1)
A5(1)
A4
A3
A2
A1
Platform Term 1/ABCD
Figure 5-45 Case 3. Power Factory. MV network.
5.4.2 PSCAD
In PSCAD a new model of Nysted was created as well. However the cables between
A01 and A09 were joined in two equal π sections, to simplify calculations. As explained
in subsection 4.8, page 101, the generators in PSCAD had to be started in speed control
followed by torque control. The generator model used for this simulation is showed in
Figure 5-46, with an increased capacitor bank and step-up transformer.
System modeling
140
Figure 5-46 Case 3. PSCAD. Induction generator
Since the starting of the induction machine has to follow a control sequence, the
simulation time increase dramatically, as well as the output file. Due to computational
constrains, the sampling time for this study case in PSCAD had to be doubled. This
variation in the resolution of the results, caused the current spikes in the transformer
A09, due to switching operation, to disappear from the results.
Other differences between measurements and simulation results were mentioned in the
following subsections.
5.4.3 Wind turbine generator
The generators at Nysted offshore wind farm are induction machines, as previously
explained. However, the details of the slip characteristic of the machine have not been
mentioned so far. The aim of this subsection is to clarify the phenomena occurring in
the rotor of an induction machine, subjected to a voltage decrease on the stator.
The active power characteristic for different percentage of slip and voltage levels is
shown in Figure 5-47. At nominal power and voltage (blue line) the generator slip is
around -0,7%. If the power production remains the same during a voltage dip, e.g.
caused by the energization of a transformer, the machine would accelerate by shifting to
the 0,95 Vnom line (green). This would cause certain amount of oscillation in the
system depending on the inertia of the generators and the damping in the system.
Similar sequence of events would cause variations in the reactive power consumption in
the generator. The reactive power characteristic for different percentage of slip and
voltage levels is shown in Figure 5-48.
System modeling
141
Figure 5-47 Active power characteristic of induction generator
Figure 5-48 Reactive power characteristic of induction generator
Although the oscillating phenomena can be simplified, the dynamic response of wind
turbines is out of the scope for this project.
5.4.4 Comparison
To simplify the vizualization of the voltage variations in the platform and A01 due to
the switching in A09, each phase voltage has been separated. Figure 5-49 shows the
System modeling
142
phase voltage A for the three locations of the measurements, and both simulation
results. Figure 5-50 and Figure 5-51 show the voltage of phase B and C, respectivelly. It
is possible to see in these figures that there is no variation in the voltage on the platform
during the switching in A09, for any of the phases. On the other hand small changes in
the voltage at A01 are visible.
Figure 5-49 Case 3. Phase A voltage for each location (2-6 ms)
From Figure 5-49 is possible to see a voltage oscilation from the measurements, that
none of the simulators can emulate. This voltage variation could be due to the magnetic
coupling in the core transformer, since the primary side of the transformer is connected
in delta and the vectorial sum of the magnetic fluxes should be zero.
From Figure 5-50 and Figure 5-51 is possible to notice that in phase B and C no
oscilation is present, and that the simulation results follow very acurately the
measurements.
System modeling
143
Figure 5-50 Case 3. Phase B voltage for each location (2-6 ms)
Figure 5-51 Case 3. Phase C voltage for each location (2-6 ms)
If now the measurements, results from Power Factory and results from PSCAD at A01
are separated (Figure 5-52), is possible to notice that the voltage variation are only
present in Power Factory. The cause of this is not very clear, since the sequence
resistance and reactance for the cables between A01 and A09, are the same for both
models.
System modeling
144
Figure 5-52 Case 3. A01 voltages (2-6 ms)
Figure 5-53 is important to show that the initial conditions at A01, in both simulation
programs were very simlar to the real system. However, after certain time the results
from Power Factory differ largely from the measurements (Figure 5-54) in all phases.
The current of phase A and B, from PSCAD, follows the measurements more acuratetly,
without taking into acount the high frequency current due to the faulty sintonization of
the capacitor bank.
Figure 5-53 Case 3. A01 currents (0-400 ms)
System modeling
145
Figure 5-54 Case 3. A01 currents (300-400 ms)
The Figure 5-55, shows the current at A09 for the entire period, where only a small shift
around zero current is present after 100 ms in phase A and B. The Figure 5-56, shows
the same currents but only for the first 50 ms. Here is possible to see that both
simulation currents are higher that the measurements. This is due to a higher voltage in
the digital models, as Figure 5-66 shows futher in the report. However, is important to
see that the simulated currents fits very well the flat current measurements.
Figure 5-55 Case 3. A09 currents (0-400 ms)
System modeling
146
Figure 5-56 Case 3. A09 currents (0-50 ms)
The Figure 5-57 shows the same currents as Figure 5-56, but only for the first
miliseconds after the switching event. Here is possible to see that some current spikes
are present in the measurements every time a pole closes in the breaker. These current
spikes are relatively larger that the current spikes when the fast-front-voltage-wave
arrives to each transformer, as in study cases 1 and 2. The current spikes from the first
and second study cases hardly reach 20 A, where the current spikes in this study cases
surpases 50 A in phase B.
Figure 5-57 Case 3. A09 currents (2-7 ms)
System modeling
147
Figure 5-58 Case 3. Phase B currents in A09 (2-7 ms)
Figure 5-58 shows only phase B at A09 for the first milliseconds after the first
switching. The simulated current spike in Power Factory due to the closing of phase B
at A09, is very similar to the measurements. Here is important to remember that the step
time in PSCAD is 800 ns, and not 400 ns as in Power Factory, due to computational
constrains.
Figure 5-59 Case 3. Rms currents at platform
System modeling
148
Figure 5-60 Case 3. Rms currents at A01 and A09
The calculated rms currents at the platform from the measurements, and both simulation
results are shown in Figure 5-59. Here is very clear an oscillation from Power Factory,
however further in the report the oscillation difference was treated. On the other hand is
important to notice that there is an initial difference of 20 A between phases for the
measured and simulated currents. This is due to the inrush current in the transformer
A09, as Figure 5-60 illustrate.
It‟s important to remember that the instantaneous current was not measured correctly at
A09, and a lower rms current is the result from this error (less than 10 A). However, the
current limit set in the platform was not reached (1,25 kA).
Another important difference between simulations and measurements is shown in
Figure 5-60, where the rms current in A01 from Power Factory increases from 3 A in
the first cycle to 12 A at the end of the simulation. This current variation is not present
in PSCAD or the measurements.
The current in phase A from the measurements presents a constant value of 6 A, this
could be due to a unsymmetrical load connected on the LV side of the transformer. No
additional simulations were repeated to achieve this value, since no information was
available to correctly identify the LV load.
The calculated active power in the platform and in the wind turbines A01 and A09 is
shown in Figure 5-61 and Figure 5-62, respectively.
System modeling
149
Figure 5-61 Case 3. Active power at platform
Figure 5-61 and Figure 5-62 are very important because clear differences between
digital and real systems are noticeable. First, the active power production in the
platform from PSCAD is lower than the real system. This is due to the fact that the
torque control in the induction machine was set to a value lower than the actual
production, however this difference is not relevant to the overall system characterization
for switching transient studies.
Figure 5-62 Case 3. Active power at A01 and A09
System modeling
150
On the other hand, the amplitude of the oscillation in the active power from Power
Factory is extremely large. The difference between the first four cycles is almost 2 MW,
only due to the voltage dip caused by a transformer energizing. Although the real
system presents a lower frequency oscillation, with a variation less than 0,5 MW in six
cycles, it can be concluded that Power Factory overestimates the oscillation in the
machines.
The active power consumption in A01, between measurements and PSCAD has a
relative offset of 3 kW, this could be due to:
Copper losses in the transformer for the increased current of phase A as Figure
5-60 shows.
Core losses in the transformer due to the different voltage in A01, as Figure 5-67
and Figure 5-69 indicates.
Unsymmetrical LV load
On the other hand, the parabolic variation in the active power consumption in A01,
between measurements and Power Factory, is more likely to be related to the active
power calculation with high harmonic current.
The Figure 5-63 shows the influence of the inertia of the induction generators and the
power production during switching of the transformer in A01. It‟s important to notice
that for this comparison four additional simulations were done, where the differences
are:
Pm. Active power from measurements
PPF-20-2,3. Active power from Power Factory, with 20 kg∙m2 of inertia and 2,3
MW of generation each machine
PPF-60-2,3. Active power from Power Factory, with 60 kg∙m2 of inertia and 2,3
MW of generation each machine
PPF-20-2,1. Active power from Power Factory, with 20 kg∙m2 of inertia and 2,1
MW of generation each machine
PPF-180-2,3. Active power from Power Factory, with 180 kg∙m2 of inertia and
2,3 MW of generation each machine
System modeling
151
Figure 5-63 Case 3. Influence of generators inertia in active power at platform
It is clear from the previous comparison, that the amplitude of the oscillation does not
depend on the inertia of the generators. However the inertia changes the oscillation
frequency.
No further simulations to fit the results from Power Factory to the measurements, were
done due to time limitations. However, the oscillation amplitude might be dependant in
the damping of the system.
The calculated reactive power in the platform and in the wind turbines A01 and A09 is
shown in Figure 5-64 and Figure 5-65, respectively.
In the platform, the oscilation of the generators in Power Facotry is visible. Where the
results from PSCAD shows a higher damping in the model than the actual system. This
results match the conclusion of the first and second study cases.
Figure 5-65 shows a difference in the reactive power consumption, between the
measurements and the simulations in A01. These differences could be due to the high
harmonic current in A01 and the voltage difference. However, it‟s important to notice
that the reactive power generation in A01 remains at 300 kVAr, and that no information
regarding the equipment connected in this wind turbine was available.
In Figure 5-65, the difference in reactive power in A09 due to the transformer
energizing, is very large. If a comparison for the first and last cycle is made for the
measurements and both simulations (Table 5-8), at the platform and at A09, some
important conclusions can be made:
During the first cycle from the measurements, there is higher reactive power
consumption at the platform than in A09 (∆Q=600 kVAr). This could is due to:
System modeling
152
o The reactive consumption of the transformers under nominal load
(200 kVAr x 7=1400 kVAr)
o The reactive power production of the cables at increased voltage
(-600 kVAr)
o The reactive power from the capacitor bank in A01 at increased voltage
(-200 kVAr)
During the first cycle from Power Factory, there is higher reactive power
consumption in A09 than in the platform. This is due to the high inrush current
in A09 (voltage dependant). Where the reactive power compensation could
come from the capacitor banks in the other wind turbines, or the oscillation in
the generators.
During the first cycle from PSCAD, there is higher reactive power consumption
in A09 than in the platform. This is due to the high inrush current in A09
(voltage dependant). Where the reactive power compensation come from the
large capacitor bank connected with the induction generator and the cables.
During the last cycle from the measurements, there is the same reactive power
consumption at the platform than in A09.
During the last cycle from Power Factory, there is almost the same reactive
power consumption at the platform than in A09. The difference could be due to
the reactive power consumption in the cables.
During the last cycle from PSCAD, the reactive power consumption in A09 is
the same as in Power Factory. This reactive consumption is due to the lower
damping in the simulated system for both programs. And the difference from
PSCAD between the reactive power in the platform and A09, is due to the
decreased reactive consumption in the generators, and the capacitor bank
connected to it.
Another important conclusion from here, is that the damping in the real and simulated
systems is very similar for this study case in comparison with the first two cases.
Table 5-8 Reactive power comparison in MVAr
Measurements Power Factory PSCAD
1 cycle Platform 5,1 7,9 3,7
A09 4,5 12 9
20 cycle Platform 1,7 3 -1
A09 1,7 2,5 2,5
System modeling
153
Figure 5-64 Case 3. Reactive power at platform
Figure 5-65 Case 3. Reactive power at A01 and A09
The calculated rms voltage at the platform from the measurements and both simulation
programs is shown in Figure 5-66. The rms voltage from the measurements seems
unbalanced, however this difference is less than 2%, hence this difference is due to
measurement uncertainty.
System modeling
154
Figure 5-67 shows the measured voltages at each location. As in the previous cases, the
voltage at A01 is lower than in A09 and the platform.
Figure 5-66 Case 3. Rms voltage at platform
Figure 5-67 Case 3. Rms voltage from measurements
Figure 5-68 and Figure 5-69 shows the rms voltage from Power Factory and PSCAD,
respectively. It is possible to see an oscillation in the voltage from Power Factory,
caused by the generators, which is not present in PSCAD.
System modeling
155
On the other hand is important to notice that both simulation programs seem to be able
to increase the voltage, caused by the reactive power generation in the cables. This has
changed from the first two study cases, most likely because the Line model in Power
Factory and the π section in PSCAD are able to increase their voltage.
Figure 5-68 Case 3. Rms voltage from Power Factory
Figure 5-69 Case 3. Rms voltage from PSCAD
Finally, a remark should be made because in both simulations, the voltage in A09 is the
highest followed by the voltage in A01, where the voltage in the platform is the lowest.
System modeling
156
5.5 Worst case switching- voltage
In terms of transient overvoltage, the worst switching would appear when the breaker
energizes the cable during peak voltage. In the first study case the switching took place
before the voltage in one of the phases reached peak value, where in the second study
case the first pole closed after one of the phases reached peak voltage.
This theoretical switching event was simulated in the network model used for study
cases 1 and 2, with Power Factory as Figure 5-70 shows. Here, the voltage from the grid
is presented in back color for all phases (phase shift in the park transformer was not
included), and the voltage for each phase in the platform and A01 are shown in colors as
the legend shows.
8.337.336.335.33 [ms]
2.500
1.500
0.500
-0.500
-1.500
-2.500
RootA: Phase Voltage A/Terminal i in p.u.
RootA: Phase Voltage B/Terminal i in p.u.
RootA: Phase Voltage C/Terminal i in p.u.
A9(2): Phase Voltage A/HV-Side in p.u.
A9(2): Phase Voltage B/HV-Side in p.u.
A9(2): Phase Voltage C/HV-Side in p.u.
Sea cable: Line-Neutral Voltage A/Terminal i in p.u.
Sea cable: Line-Neutral Voltage B/Terminal i in p.u.
Sea cable: Line-Neutral Voltage C/Terminal i in p.u.
5.998 ms-2.291 p.u.
Figure 5-70 Worst case switching at peak voltage
From this figure it‟s important to notice that the highest voltage appears in the last
transformer due to the voltage reflection, with a value of 2,29 p.u. (43,5 kV), even
higher than the overvoltage in the second case (Figure 5-39 page 135).
5.6 Worst case switching -current
As it was revealed in subsection 4.4.4.2 page 80, the worst inrush current in a
transformer would appear if one of the phase voltages was zero. In this subsection, a
theoretical worst switching scenario for the inrush current, when the breaker in the
platform energizes row A (study case model 1 and 2), was simulated.
The same voltages as in Figure 5-70 are shown in Figure 5-71, with the same color
nomenclature, for the worst inrush current switching. Here, the switching event was
defined as simultaneous pole closing in the breaker with no residual flux in the
transformers. The highest instantaneous peak current in one of the phases, during the
first cycle in the platform was 4,30 p.u., however no additional simulation or analysis
was done in this subsection because in the next section (page 163), different amount and
System modeling
157
combination of transformers were energized in sequence in order to assess the voltage
dip at the PCC.
20.0016.0012.008.004.00 [ms]
2.00
1.00
0.00
-1.00
-2.00
RootA: Phase Voltage A/Terminal i in p.u.
RootA: Phase Voltage B/Terminal i in p.u.
RootA: Phase Voltage C/Terminal i in p.u.
A9(2): Phase Voltage A/HV-Side in p.u.
A9(2): Phase Voltage B/HV-Side in p.u.
A9(2): Phase Voltage C/HV-Side in p.u.
Sea cable: Line-Neutral Voltage A/Terminal i in p.u.
Sea cable: Line-Neutral Voltage B/Terminal i in p.u.
Sea cable: Line-Neutral Voltage C/Terminal i in p.u.
Figure 5-71 Worst case switching at zero voltage
5.7 Fit traveling time of the voltage wave
At this stage all the simulations have been done with the available information from the
cable manufacturers, yet the velocity of the voltage wave from the simulations was
found to be higher than in the real system. In this subsection the velocity of the voltage
wave was fitted to the measurements, in order to visualize better the reflections.
This was done in both simulation programs in the digital systems used for study case 2,
where only the relative permittivity of the cable was increased. This study case was
selected because here the overvoltages caused by the reflections were higher than in the
first study case.
The changes in permittivity were made first in Power Factory, as Figure 5-72 shows.
Here the relative permittivity was increased from 2,1 to 3,2 with a frequency for
parameter approximation of 1950 Hz. This figure is based on Figure 7-9 page 188,
where the top plot shows the phase A voltage in the platform, the middle plot shows the
phase A voltage in A01 and the bottom page shows the phase A voltage in A09.
In Figure 5-72 is clear that the velocity of the voltage wave is inversely proportional to
the relative permittivity, as explained in subsection 4.5 page 88. It is also visible from
this figure that the voltage wave that match the best with the measurements is the one
with relative permittivity of 3,2. This is a very high value for the relative permittivity
however, it‟s important to notice that no variation in the relative permeability of the
conductor was done in any simulation at this stage.
System modeling
158
20.5020.4220.3420.2620.1820.10 [ms]
10.00
0.00
-10.00
-20.00
-30.00
-40.00
20.5020.4220.3420.2620.1820.10 [ms]
10.00
0.00
-10.00
-20.00
-30.00
-40.00
2.1
2.3
2.8
3
3.2
20.5020.4220.3420.2620.1820.10 [ms]
10.00
0.00
-10.00
-20.00
-30.00
-40.00
20.275 ms-11.611 kV
20.280 ms-11.713 kV
20.292 ms-12.231 kV 20.297 ms
-12.149 kV
20.198 ms 0.000 kV
20.202 ms 0.000 kV
20.204 ms 0.000 kV
20.196 ms 0.000 kV
20.205 ms 0.000 kV
20.301 ms-12.558 kV
DIg
SIL
EN
T
Figure 5-72 Fit traveling time of voltage wave. Power Factory. Relative permittivity.
Next, the frequency for parameter approximation was changed in order to visualize the
effect of this parameter in the velocity of the wave. The results from this variation is
shown in Figure 5-73, where the relative permittivity was set to 3,2 and the frequency
for parameter approximation was increased to 10000 Hz.
20.5020.4220.3420.2620.1820.10 [ms]
10.00
0.00
-10.00
-20.00
-30.00
-40.00
-50.00
RootA: Voltage A in kV- 1950 Hz, 3.2
RootA: Voltage A in kV- 10000 Hz, 3.2
A1(1): Voltage A in kV- 1950 Hz, 3.2
A1(1): Voltage A in kV- 10000 Hz, 3.2
A9(2): Voltage A in kV- 1950 Hz, 3.2
A9(2): Voltage A in kV- 10000 Hz, 3.2
DIg
SIL
EN
T
Figure 5-73 Fit traveling time of voltage wave. Power Factory. Frequency.
It‟s possible to see from Figure 5-73 that Power Factory calculates the traveling velocity
of the voltage wave using the frequency for parameter approximation, although in
theory the velocity of the wave depends only in the relative permittivity and relative
permeability of the cable.
System modeling
159
During the simulations in PSCAD, some problems appear when the relative permittivity
of the insulation was increased to 3,2. However these problems were solved by
changing the earth resistivity to the standard value of 100 Ω∙m and by simplifying the
network with only one cable between wind turbines A01 and A09, instead of eight short
sections.
The comparison between the measurements and both simulation results, for the voltage
of phase A, in the three different locations is shown in Figure 5-74. From this figure
several important conclusions can be made:
None of the simulation programs can emulate the measured overvoltage in the
platform, caused by the voltage wave reflection. The difference between Power
Factory and the measurements at 0,0203 s is 15 kV. The difference between
PSCAD and the measurements at 0,0203 s is 9 kV.
None of the simulation programs can emulate the measured overvoltage in A01,
caused by the voltage wave reflection. The difference between Power Factory
and the measurements at 0,02035 s is 20 kV. The difference between PSCAD
and the measurements at 0,02035 s is 10 kV.
None of the simulation programs can emulate the measured overvoltage in A09,
caused by the voltage wave reflection. The difference between Power Factory
and the measurements at 0,02027 s is 7 kV. The difference between PSCAD and
the measurements at 0,02027 s is 5 kV.
The round corners in the fast front of the voltage wave in all locations are only
simulated in PSCAD. As explained before this is caused by the skin effect in the
conductor.
The behavior of Power Factory after the first reflection period (90 μs) looks
fairly random in all locations. Where in PSCAD the voltage reduction seems
gradual, nonetheless the results are not similar to the measurements.
In Power Factory the voltage level surpasses -40 kV at 0,02041 s in A09, just as
in Figure 5-73. This could be due to the voltage reflection; however no
information regarding the model is available from DigSILENT.
The results from Power Factory before the wave reflected from A09 arrives to
the platform, is very similar to the actual measurements. Here is visible some
kind of step-wise decrease in the voltage from 0,02022 s to 0,02025 s. This
phenomena is not present in the results from PSCAD.
System modeling
160
Figure 5-74 Fit travelling time of voltage wave. Comparison
System modeling
161
5.8 Summary
In this section the general procedure followed to create the models of Nysted offshore
wind farm in Power Factory and PSCAD was presented. Then, the results from both
simulation programs and the measurements for each study case were compared. Next
two additional simulations were done to assess the worst switching angle for the voltage
and the current. Finally the relative permittivity in the cables was increased in both
simulation programs to fit the velocity of the voltage wave to the measurements. Some
of the most important conclusions from the first two study cases were:
None of the simulation programs can accurately account for the transient
overvoltages, due to voltage wave reflections.
The cable models in both simulation programs overestimate the damping in the
system.
The cable models in both simulation programs do not contribute to the voltage
increase in the system, due to the charging of the capacitances in the cable.
The cable model in Power Factory with high frequency for parameter
approximation, cannot be used to compare the system at steady state.
The saturation exponent in the transformer model from Power Factory could
result in errors if a high value is not used.
Some of the most important conclusions from the last study case were:
The voltage dip due to the energizing of a transformer caused power oscillations
from the induction generators connected in the same row. However these
oscillations were overestimated in the model from Power Factory.
The simulated switching event in A09 using Power Factory, caused voltage
transients in A01 not present in the measurements nor the results from PSCAD.
The simulated switching event in A09 using Power Factory, caused an increase
in the current in A01 not present in the measurements nor the results from
PSCAD.
The damping in the real and simulated systems is very similar for this study case
in comparison with the first two study cases.
The most important conclusion from the worst switching cases was:
None of the study cases happened at the worst possible moment for the transient
overvoltage or the inrush current.
The most important conclusion from fitting the traveling wave velocity was:
None of the simulation programs can emulate accurately the measured
overvoltage in the platform, A01 or A09 caused by the voltage wave reflections.
System modeling
162
Voltage dip at the PCC, due to the connection of different amount of transformers at the
same time
163
6 VOLTAGE DIP AT THE PCC, DUE TO THE CONNECTION OF DIFFERENT AMOUNT OF TRANSFORMERS AT THE SAME TIME
In this section the voltage dip at the point of common coupling with the grid, due to the
connection of different amount of transformers at the same time, was assessed with 20
simulations in Power Factory and 8 in PSCAD.
The Figure 6-1 shows the overview of the simulated network, where the equipment in
black represents the devices without voltage. It‟s clear from this figure that no transient
phenomena had to be simulated in the cables; hence a new model for each program had
to be created where the cables were modeled accurately for steady state conditions.
Since the network in both programs is essentially the same as the first study case, no
figures showing the network in any program were included.
Figure 6-1 Overview of sequential energization of transformers
On the other hand, after several preliminary simulations in Power Factory, it was found
that the saturation characteristic had to be simulated as a polynomial curve with a high
saturation exponent. Figure 6-2 shows the phase current A in the platform for five
Voltage dip at the PCC, due to the connection of different amount of transformers at the
same time
164
different cases where the saturation characteristic and the frequency for parameter
approximation in the cable models were changed.
The characteristics of the model for each case is shown in the legend; where the last
value in the legend is the frequency for parameter approximation in the cable and the
second-last value is the saturation representation in the core of the transformer.
10.0008.0006.0004.0002.0000.000 [s]
0.800
0.560
0.320
0.080
-0.160
-0.400
RootA: Phase Current A in p.u. Tw o slope, 100 Hz
10.0008.0006.0004.0002.0000.000 [s]
0.800
0.560
0.320
0.080
-0.160
-0.400
RootA: Phase Current A in p.u. Polynomial 15, 100 Hz
10.0008.0006.0004.0002.0000.000 [s]
0.800
0.560
0.320
0.080
-0.160
-0.400
RootA: Phase Current A in p.u. Polynomial 15, 50 Hz
10.0008.0006.0004.0002.0000.000 [s]
0.800
0.560
0.320
0.080
-0.160
-0.400
RootA: Phase Current A in p.u. Tw o slope, 50 Hz
10.0008.0006.0004.0002.0000.000 [s]
0.800
0.560
0.320
0.080
-0.160
-0.400
RootA: Phase Current A in p.u. Polynomial 7, 1950 Hz
Figure 6-2 Sequencial energization. Power Factory. Saturation exponent.
It is clear from the last figure, that the current with the two slope representation, is
unstable at the voltage level used. Another important conclusion is that the cable with
high value of frequency for parameter approximation would give wrong steady state
current.
After these preliminary results, the cable models in Power Factory were defined as
“Line” models to avoid problems and reduce the simulation time; where the saturation
exponent for the polynomial curve representation in the core was set to 15.
6.1 Sequence energization
As a start, four main sequences were defined to compare the influence of the number of
transformers simultaneously energized. Here the transformers were divided in groups
for energization with 1, 2, 5, or 9 transformers corresponding to 1WT, 2WT, 5WT and
9WT respectively. The time when each transformer would be energized is shown in
Table 6-1.
After the characterization of the energizing sequences, the switching scenarios have to
be defined. Here the conclusions from previous sections are important, since the inrush
current depends on the switching angle, the residual flux and the rest of the system.
Hence five different switching scenarios were defined:
Voltage dip at the PCC, due to the connection of different amount of transformers at the
same time
165
1. Vzero A01-A09. With simultaneous pole switching when one of the phase
voltages was zero and all rows connected. Here the order to energize the
transformers starts from A01 and not from A09, however the time intervals
remain the same.
2. Vzero. With simultaneous pole switching when one of the phase voltages was
zero and all rows connected.
3. Vpeak. With simultaneous pole switching when one of the phase voltages had
peak value and all rows connected.
4. Row B. With simultaneous pole switching, zero voltage and only the Row B
connected.
5. Residual flux. With simultaneous pole switching, zero voltage, all rows
connected and residual flux in the same polarity to that to which the flux would
normally attain under equivalent normal conditions.
6. Reduced grid. With simultaneous pole switching, zero voltage, all rows
connected and increased grid impedance (lower grid capacity).
Table 6-1 Times for sequencial energization in seconds
9WTx0s 5WTx5s 2WTx2s 1WTx1s
A01 0,1 5,1 6,1 8,1
A02 0,1 5,1 6,1 7,1
A03 0,1 5,1 6,1 6,1
A04 0,1 5,1 4,1 5,1
A05 0,1 0,1 4,1 3,1
A06 0,1 0,1 2,1 3,1
A07 0,1 0,1 2,1 2,1
A08 0,1 0,1 0,1 1,1
A09 0,1 0,1 0,1 0,1
All this scenarios were simulated in Power Factory, however only the second and third
scenarios were repeated in PSCAD due to the reduced time for the thesis. It‟s important
to mention that the scenario with residual flux is not realistic in the case of Nysted
offshore wind farm, since there is a permanent LV load connected in the transformer,
which de-energizes the core.
The “Vzero A01-A09” and “Row B” scenarios were developed to create guidelines on
how to energize the step-up transformers in the collection grid of an offshore wind farm,
presented in the last section of the thesis.
The “Reduced grid” scenario was developed to compare the influence of the grid in the
voltage dip when a weaker grid is used.
The results from the simulations are shown in Table 6-2. However the results were
discussed in the following subsections.
Voltage dip at the PCC, due to the connection of different amount of transformers at the
same time
166
6.2 Simulation in PF
From Figure 6-3 to Figure 6-8 the left side plot are the calculated rms current each cycle
and in the right plot the calculated rms voltage each half cycle from Power Factory.
Figure 6-3 shows the results from the scenario “Vzero A01-A09”. In this scenario only
the 1WT and 2WT sequences were simulated.
From Figure 6-3-left it is possible to see that in the 1WTx1s sequence, the current
increases each time a transformer is energized. Moreover, in the 2WTx2s sequence the
current increases each time two transformers are energized.
From Figure 6-3-right it is possible to see that in the 1WTx1s sequence, the voltage
decreases each time a transformer is energized. In addition, in the 2WTx2s sequence the
voltage decreases each time two transformers are energized. A voltage unbalance in
both sequences is also visible, for the first half cycle after the switching has occurred.
Figure 6-3 Sequence energization. Power Factory. Vzero A01-A09
Figure 6-4 shows the results from the scenario “Vzero”. In this scenario all sequences
were simulated.
From Figure 6-4-left it‟s possible to see an increase in current, each time a switching
operation occurs. However is important to notice that the highest current appear when
all transformers are energized simultaneously (9WTx0s), followed by 5WTx5s,
2WTx2s and finally by 1WTx1s.
The Figure 6-4-right shows that for the sequences 2WTx2s and 1WTx1s each time a
switching operation occurs, the voltage decrease compared with the previous switching.
Nevertheless the lowest voltage is present in the sequence 9WTx0s, followed by
1WTx1s.
Voltage dip at the PCC, due to the connection of different amount of transformers at the
same time
167
Figure 6-4 Sequence energization. Power Factory. Vzero
Figure 6-5 shows the results from the scenario “Vpeak”. In this scenario only the
sequences 2WTx2s and 9WTx0s were simulated.
From Figure 6-5-left it‟s possible to see an increase in current, each time a switching
operation occurs. It is important to notice that the highest current appear when all
transformers are energized simultaneously (9WTx0s).
The Figure 6-5-right shows that for the sequences 2WTx2s each time a switching
operation occurs, the voltage decrease compared with the previous switching. Between
these sequences, the lowest voltage is present in 9WTx0s.
Figure 6-5 Sequence energization. Power Factory. Vpeak
Figure 6-6 shows the results from the scenario “Row B”. In this scenario all sequences
were simulated.
From Figure 6-6-left it‟s possible to see an increase in current, each time a switching
operation occurs. It is important to notice that the highest current appear when all
transformers are energized simultaneously (9WTx0s), followed by 5WTx5s, 2WTx2s
and finally by 1WTx1s.
Voltage dip at the PCC, due to the connection of different amount of transformers at the
same time
168
The Figure 6-6-right shows that for the sequences 2WTx2s and 1WTx1s each time a
switching operation occurs, the voltage decrease compared with the previous switching.
However the lowest voltage is present in the sequence 9WTx0s, followed by 1WTx1s.
Figure 6-6 Sequence energization. Power Factory. Row B
Figure 6-7 shows the results from the scenario “Residual flux”. In this scenario all
sequences were simulated.
From Figure 6-7-left it‟s possible to see an increase in current, each time a switching
operation occurs. It is important to notice that the highest current appear when all
transformers are energized simultaneously (9WTx0s), followed by 5WTx5s, 2WTx2s
and finally by 1WTx1s.
The Figure 6-7-right shows that for the sequences 2WTx2s each time a switching
operation occurs, the voltage decrease compared with the previous switching, where this
phenomena is not present in the sequence 1WTx1s. In this scenario the lowest voltage is
present in the sequence 9WTx0s, followed by 5WTx5s.
Figure 6-7 Sequence energization. Power Factory. Residual flux
Finally Figure 6-8 presents the results from the scenario “Reduced grid”. In this
scenario all sequences were simulated.
Voltage dip at the PCC, due to the connection of different amount of transformers at the
same time
169
From Figure 6-8-left it‟s possible to visualize an increase in current, each time a
switching operation occurs. It is important to notice that the highest current appear when
all transformers are energized simultaneously (9WTx0s), followed by 5WTx5s,
2WTx2s and finally by 1WTx1s.
The Figure 6-8-right shows that for the sequences 2WTx2s and 1WTx1s each time a
switching operation occurs, the voltage decrease compared with the previous switching.
However the lowest voltage is present in the sequence 9WTx0s, followed by 1WTx1s.
Figure 6-8 Sequence energization. Power Factory. Reduced grid
6.3 Simulation in PSCAD
Figure 6-9 and Figure 6-10 presents on the left side plot the calculated rms current each
cycle and in the right plot the calculated rms voltage each half cycle from PSCAD.
The Figure 6-9 presents the results from the scenario “Vzero”. In this scenario all
sequences were simulated.
From Figure 6-9-left it‟s possible to visualize an increase in current, each time a
switching operation occurs. It is important to notice that the highest current appear when
all transformers are energized simultaneously (9WTx0s), followed by 5WTx5s,
2WTx2s and finally by 1WTx1s.
The Figure 6-9-right shows that for the sequences 2WTx2s and 1WTx1s each time a
switching operation occurs, the voltage decrease slightly compared with the previous
switching. However the lowest voltage is present in the sequence 9WTx0s, followed by
5WTx5s.
Voltage dip at the PCC, due to the connection of different amount of transformers at the
same time
170
Figure 6-9 Sequence energization. PSCAD. Vzero
The Figure 6-10 presents the results from the scenario “Vpeak”. In this scenario all
sequences were simulated.
From Figure 6-10-left it‟s possible to see an increase in current, each time a switching
operation occurs. It is important to notice that the highest current appear when all
transformers are energized simultaneously (9WTx0s), followed by 5WTx5s, 2WTx2s
and finally by 1WTx1s.
The Figure 6-10-right shows that for the sequences 2WTx2s and 1WTx1s each time a
switching operation occurs, the voltage decrease slightly compared with the previous
switching. However the lowest voltage is present in the sequence 9WTx0s, followed by
5WTx5s.
Figure 6-10 Sequence energization. PSCAD. Vpeak
If now the rms current and voltages are calculated each cycle from the results from
PSCAD and plotted, some conclusions can be made.
Voltage dip at the PCC, due to the connection of different amount of transformers at the
same time
171
Figure 6-11 Sequence energization. PSCAD. Vzero. Rms each cycle
Figure 6-12 Sequence energization. PSCAD. Vpeak. Rms each cycle
In Figure 6-11 the results from the “Vzero” scenario were plotted, while the results from
the “Vpeak” scenario were plotted in Figure 6-12. It is possible to see from both figures
that:
The highest rms current appears during the 9WTx0s sequence and in the
“Vzero” scenario.
The lowest rms voltage turn up during the 9WTx0s sequence and in the “Vpeak”
scenario. This is a contradictory results if the voltage is compared with Figure
6-9 and Figure 6-10, however the period for the calculation of the rms voltage is
different.
The voltage unbalance seems more severe in the “Vzero” scenario.
The voltage-current characteristic is different depending on the switching angle,
however is not different depending on the energizing sequence.
Voltage dip at the PCC, due to the connection of different amount of transformers at the
same time
172
6.4 Results
Once the plots have been compared, the lowest rms voltage each half cycle, the highest
rms current each cycle and the largest peak current were summarized in Table 6-2. Here
the values were classified by colors to simplify the comparison.
Table 6-2 Sequence energization results
1 2 3 4 5 6
Zero Zero Peak Zero Zero Zero
Residual 0 0 0 0 1 0
Sgrid 1 1 1 1 1 0,8
Connected All All All B All All
Sequence A01-A09 A09-A01 A09-A01 A09-A01 A09-A01 A09-A01
Half c
ycle
rm
s v
olta
ge d
ip
Pow
er
Facto
ry 1WTx1s+LV -4,9% -5,0% -4,8% -5,4% -4,9%
2WTx2s+LV -3,0% -3,5% -1,7% -3,1% -7,0% -3,3%
5WTx5s+LV -2,2% -3,6% -9,2% -3,9%
9WTx0s+LV -5,4% -3,5% -5,7% -13,8% -6,0%
PS
CA
D 1WTx1s+LV -0,6% -0,6%
2WTx2s+LV -1,7% -1,5%
5WTx5s+LV -2,2% -1,9%
9WTx0s+LV -4,3% -3,7%
Rm
s c
urr
ent
[pu]
Pow
er
Facto
ry 1WTx1s+LV 0,38 0,40 0,40 0,83 0,37
2WTx2s+LV 0,88 0,93 0,88 0,99 1,93 0,90
5WTx5s+LV 1,33 1,41 2,88 1,26
9WTx0s+LV 1,78 2,16 1,94 4,50 1,71
PS
CA
D 1WTx1s+LV 0,26 0,24
2WTx2s+LV 0,69 0,65
5WTx5s+LV 0,90 0,84
9WTx0s+LV 1,72 1,65
Peak c
urr
ent
[pu
]
Pow
er
Facto
ry 1WTx1s+LV 0,73 0,77 0,77 1,47 0,70
2WTx2s+LV 1,83 1,95 1,71 2,05 3,97 1,86
5WTx5s+LV 2,93 3,11 6,03 2,81
9WTx0s+LV 4,32 4,14 4,66 9,03 4,17
PS
CA
D 1WTx1s+LV 0,51 0,47
2WTx2s+LV 1,44 1,33
5WTx5s+LV 2,19 2,06
9WTx0s+LV 3,58 3,44
It‟s important to state that the measurements from the study cases cannot be directly
compared to the sequential energization results. The measurements from the first two
study cases are located below the circuit breaker in the platform, this location is ideal to
measure the transient phenomena in the cable; however a better location to measure the
voltage dip would have been in the other side of the breaker.
Voltage dip at the PCC, due to the connection of different amount of transformers at the
same time
173
With the time series available for the third study case, is not possible to calculate the
rms voltage dip since the event happened at 2 ms. In this study case is important as well
to mention that it was assumed since the beginning of the thesis that no generation was
present; however it was found further on that the induction machines were almost at full
production.
Although the study cases and the results from the sequential energization cannot be
compared directly, the transient voltage, current and powers were compared in the
previous section with acceptable differences. Hence it can be concluded that both
simulation programs can be extrapolated to practical cases with caution.
The comparison was further separated depending on the variable being compared:
Half cycle rms voltage dip
o All sequences from the scenario “Vzero A01-A09” presents smaller
voltage dip than the scenario “Vzero”
o Vzero. Power Factory overestimates the voltage dip caused by the
sequence 1WTx1s and 2WTx2s compared with PSCAD
o Vzero. Power Factory and PSCAD reach similar results in the sequence
5WTx5s
o Vzero. Power Factory presents a higher voltage dip than PSCAD for the
sequence 9WTx0s
o Vpeak. Power Factory and PSCAD reach similar results in the sequence
9WTx0s, however in the sequence 2WTx2s PSCAD presents larger
voltage dip
o In PSCAD all sequences from the scenario “Vpeak” presents smaller
voltage dip than the scenario “Vzero”
o The sequence 5WTx5s and 9WTx0s from the scenario “Row B”
presents larger voltage dip than the scenario “Vzero”
o The largest voltage dip from Power Factory, for each sequence, is
present in the scenario “Residual flux”
o The sequence 5WTx5s and 9WTx0s from the scenario “Reduced grid”
presents larger voltage dip than the scenario “Vzero”
Rms current
o All sequences from the scenario “Vzero A01-A09” presents less current
than the scenario “Vzero”
o Vzero. Power Factory presents higher current in all sequences than
PSCAD
o Vpeak. Power Factory shows higher results in both sequences than
PSCAD
o In PSCAD all sequences from the scenario “Vpeak” presents lower
current than the scenario “Vzero”
Voltage dip at the PCC, due to the connection of different amount of transformers at the
same time
174
o The sequence 5WTx5s and 9WTx0s from the scenario “Row B”
presents larger current than the scenario “Vzero”
o The largest current from Power Factory, for each sequence, is present in
the scenario “Residual flux”
o All sequences from the scenario “Reduced grid” presents less current
than the scenario “Vzero”
Peak current
o All sequences from the scenario “Vzero A01-A09” presents less current
than the scenario “Vzero”
o Vzero. Power Factory presents higher current in all sequences than
PSCAD
o Vpeak. Power Factory shows higher results in both sequences than
PSCAD
o In PSCAD all sequences from the scenario “Vpeak” presents lower
current than the scenario “Vzero”
o The sequence 5WTx5s and 9WTx0s from the scenario “Row B”
presents larger current than the scenario “Vzero”
o The largest current from Power Factory, for each sequence, is present in
the scenario “Residual flux”
o All sequences from the scenario “Reduced grid” presents less current
than the scenario “Vzero”
In general, the results from Power Factory regarding the sequence 1WTx1s and
2WTx2s, are contradictory since a large voltage dip is present ever though the current
has not increase that much.
The previous results were used in the next section, to create recommendations regarding
the simultaneous energizing of different amount of transformers in large wind farms.
Conclusions
175
7 CONCLUSIONS
In this section, the comparison between simulation tools is presented; followed by a
summary of required information to realize switching transient studies. Then, the
guidelines for the simultaneous energizing of different amount of transformers were
stated. Finally, the perspectives and future work are presented.
7.1 Results- simulation tools
A comparison between the models of the electrical devices, present in the collection
grid of offshore wind farms, was done in Power Factory and PSCAD with similar
results from both simulation tools.
Once each digital device was validated, three study cases were realized based on
measurements to compare the transient behavior of both simulation tools. At this stage,
some differences were visible; however, a detail analysis was done in order to
understand the results and the causes of these discrepancies. From these disagreements
between the measurements and the simulations, some relevant conclusions can be made:
None of the simulation programs can emulate accurately the measured
overvoltage in the platform, A01 or A09 caused by the voltage wave reflections
The cable models in both simulation programs overestimate the damping in the
system.
The cable model in Power Factory with high frequency for parameter
approximation, cannot be used to compare the system at steady state.
The saturation exponent in the transformer model from Power Factory could
result in errors if a high value is not used.
The voltage dip due to the energizing of a transformer, caused power oscillations
from the induction generators connected in the same row. However these
oscillations were overestimated in the model from Power Factory.
The simulated switching event in A09 using Power Factory, caused voltage
transients in A01 not present in the measurements nor the results from PSCAD.
The simulated switching event in A09 using Power Factory, caused an increase
in the current in A01 not present in the measurements nor the results from
PSCAD.
Then, when Power Factory and PSCAD were used to assess the voltage dip due to the
sequential energization of different amount of transformers, there were some
contradictory results on certain sequences from Power Factory.
Conclusions
176
7.2 Results- required information
In general, it can be concluded that there are important differences between Power
Factory and PSCAD for switching transient studies:
The circuit breaker model in Power Factory is not fully developed to simulate
possible switching conditions in the collection grid of an offshore wind farm.
The magnitude of the highest overvoltage measured, due to voltage reflections,
was only achieved in Power Factory, while the shape of the voltage was similar
in PSCAD.
The cable model in Power Factory cannot be used to compare steady state
conditions, after a switching event. While the cable model in PSCAD works for
every stage of the event.
The results in Power Factory, from the voltage dip due to the sequential
energization of transformers, have to be treated without full confident.
As stated at the beginning of section 6, there is a large amount of information needed
for switching transient studies; however, some of the most important information that
the manufactures do not provide willingly to the system designer is:
Circuit breaker
o Rate of rise of re-striking voltage
o Rate of rise of dielectric strength
Transformer
o High frequency capacitances
o Characteristic impedance
o Open circuit characteristic
Cable
o Material properties
o Geometrical characteristics
This information is important to create digital models in the appropriate simulation tool,
to achieve results as close to reality as possible at the design stage of a project; since in
practical applications there are not many installed measurement systems with so high
definition to compare the simulations results with.
Another important constrain at the design stage of the collection grid of large offshore
wind farms, is the risk assessment and insulation coordination; these are based in
simulation results and as it has been proven in this thesis, the results from Power
Factory and PSCAD are vaguely analogous to the measurements in some situations.
7.3 Results- simultaneous energization of transformers
After the many sequences and scenarios from the last section, some recommendations
regarding the simultaneous energizing of different amount of transformers was done.
The idea is to apply the results to the voltage dip control in large offshore wind farms, in
Conclusions
177
order to energize the transformers and comply with the UK requirements. Some of the
recommendations are:
There is no need to use segregated point-in-wave closing methods in the circuit
breaker; since there is no large difference in the voltage dip for switching at
peak or zero voltage.
The smallest voltage dips occur if the wind turbine transformers are switched-in
independently. However, there cannot be a generalization because the voltage
dip depends on the system itself and its connection to the grid.
To avoid higher inrush current when the transformers have residual flux, its
recommended to connect a permanent low voltage load on the secondary side of
the transformers, to de-energize the transformer.
No conclusive results were achieved when the cables of the other rows were
disconnected, however the capacitance from the other rows are likely to reduce
the voltage dip.
No conclusive results were achieved when changing the sequence of
energization from A09-A01 to A01-A09.
7.4 Perspectives
Some of the results from this thesis could be used in other offshore wind farms under
development, where the projects are at the design stage. The protection system could be
upgraded; the control system could include additional components; supplementary
information could be asked to the manufacturer and in general the system designer
could become more aware of the imitations of the simulation tools.
7.5 Further work
This project reflects the interest of the large offshore wind farm developers, to predict
the possible risks and protection of the electrical devices in the collection grid prior to
its installation in the sea. In order to continue to understand the network and the
simulation tools, many switching events are left still to simulate from the measurements
performed within the project entitled “Voltage conditions and transient phenomena in
medium voltage grids of modern wind farms”, funded by Energinet.dk.
On the other hand, plenty of effort could be used to simulate each and every one of the
switching events, nevertheless, the accuracy of the results are limited by the accuracy of
the simulation tool. On this front, there is plenty of work to be done, in order to
correctly estimate the transient phenomena of the electrical devices and the collection
grid itself.
Important ongoing work by the IEEE, is the switching transients induced by
transformer-breaker interaction, since there are plenty of these components in the
Conclusions
178
collection grid. However, no significant results will be archived if the transformer and
circuit breakers manufacturers are not part of the development.
179
REFERENCES
A.M. Gole, D.W. Durbak, E.H. Camm, M.Marz, R.C. Degeneff, R.P. O‟Leary, R.
»Modeling Guidelines for Switching Transients.« IEEE PES Switching Transients
Task Force 15.08.09.03 1997.
ABB. Controlled Switching. Buyer‟s Guide. Application Guide. Sweden, 2006-09.
Abdulahovic, T og T. Thiringer. »Modeling of the energizing of a wind park radial.«
Nordic Wind Power Conference. Roskilde,, 2007.
Bollen, Math H. J. og D. Daniel Sabin. »International Coordination for Voltage Sag
Indices.« IEEE Power Engineering Society Transmission and Distribution
Conference 2006.
Bollen, Math H. J. Understanding Power Quality Problems: Voltage Sags and
Interruptions. Wiley-IEEE Press, 1999.
Brunke, J.H. og K.J. Frohlich. »Elimination of transformer inrush currents by controlled
switching. I. Theoretical considerations.« IEEE Transactions on Power Delivery
2001: 276-280.
Chapman, S.J. Electric Machinery and Power Systems Fundamentals. McGraw Hill,
2003.
Christensen, L.S., et al. »GPS synchronized high voltage measuring system.«
Proceedings. Nordic wind power conference 2007.
CIGRE. »State of the art circuit breaker modeling. Working group 13.01 of Study
committee 13.« 1998.
Czarnecki, L. og M. Lindmayer. »Measurement and Statistical Simulation of Virtual
Current Chopping in Vacuum Switches.« Proceedings - XIth International
Symposium on Discharges and Electrical Insulation in Vacuum. 1984: 253-260.
Daniel, A. og S. Gebre. Analysis of Transients in Wind Parks: Modeling of System
Components and Experimental Verification. Göteborg: CHALMERS UNIVERSITY
OF TECHNOLOGY, 2008.
de Leon, F. og A. Semlyen. »Complete transformer model for electromagnetic
transients.« IEEE Transactions on Power Delivery 1994.
Dick, E.P., et al. »Equivalent circuits for simulating switching surges at motor
terminals.« IEEE Transactions on Energy Conversion 1988: 696-704.
Dolinar, M., et al. »Determining the magnetically nonlinear characteristics of a three
phase core-type power transformer.« Journal of Magnetism and Magnetic Materials
Vol.304 Issue.2 . September 2006: e813-15.
180
Dufournet, D. og G.F. Montillet. »Harmonization of TRVs in ANSI/IEEE and IEC
standards for high-voltage circuit breakers rated less than 100 kV.« Power
Engineering Society General Meeting, 2005. IEEE Vol. 1. June 2005: 1019 - 1024.
ENA. Engineering recommendation P28. Planning limits for voltage fluctuations caused
by industrial, commercial, and domestic equipment in the United Kingdom. UK:
Energy Network Association, 1989.
Flurscheim, C. H. Power Circuit Breaker Theory and Design. UK: IEE, 1982.
Gliiikowslti, M.T., M.R. Gutierrez og D. Brauii. »Voltage escalation and re ignition
behaviour of vacuum generator Circuit Breakers during Load Shedding.« IEEE
Transactions on Power Delivery January 1997.
Greenwood, A. Electrical Transients in Power Systems. Wiley-Interscience, 1991.
Gustavsen, B., J.A. Martinez og D. Durbak. »Parameter determination for modeling
system transients-Part II: Insulated cables.« IEEE Transactions on Power Delivery
2005: 2045-2050.
Helmer, J. og M. Lindmayer. »Mathematical modeling of the high frequency behavior
of vacuum interrupters and comparison with measured transients in power systems.«
Proceedings of 17th International Symposium on Discharges and Electrical
Insulation in Vacuum 1996.
»IEEE Application Guide for Transient Recovery Voltage for AC High-Voltage Circuit
Breakers.« IEEE Std C37.011-2005 (Revision of IEEE Std C37.011-1994) 2004.
JH- Franklin, A.C. og A.P. Franklin. J&P Transformer Book. London: Butterworths,
1983.
Kondala, B. og G Gajjar. »Development and application of vacuum circuit breaker
model in electromagnetic transient simulation.« Power India Conference 2006.
Kosmac, J. og P. Zunko. »A statistical vacuum circuit breaker model for simulation of
transient overvoltages.« IEEE Transactions on Power Delivery 1995: 294-300.
Kundur, P. Power System Stability and Control. USA: McGraw Hill, 1994.
Larsen, J., et al. »Experience from Middelgrunden 40 MW Offshore Wind Farm.«
Copenhagen Offshore Wind Conference. Denmark, 2005.
Liljestrand, L., et al. »Transients in collection grids of large offshore wind parks.« Wind
Energy Vol.11 Issue.1 2008: 45-61.
Ma, T. og A. Cadmore. »System studies of voltage dips resulting from energisation of
MV wind turbine transformers.« 18th International Conference and Exhibition on
Electricity Distribution 2006.
Martinez, J.A., et al. »Parameter determination for modeling system transients - Part III:
Transformers.« IEEE Transactions on Power Delivery 2005: 2051-2062.
Nagpal, M., et al. »Assessing and limiting impact of transformer inrush current on
power quality.« IEEE Transactions on Power Delivery Vol.21 Issue.2 2006: 890-
896.
Pedersen, K., et al. »Detailed High Frequency Models of Various Winding Types in
Power Transformers.« 2005.
References
181
Popov, M., L. van der Sluis og G.C. Paap. »A simplified transformer model for the
simulation of fast surges and adequate protection measures.« IEEE Power
Engineering Society Winter Meeting 2001.
PSCAD User's Guide. Manitoba: Manitoba HVDC Research Centre Inc. , 2005.
R. King, and N. Jenkins. »Switching Transients in Large Offshore Wind.« Madrid: 7th
International Workshop on Large Scale Integration of Wind Power and on
Transmission Networks for Offshore Wind Farms, 2008.
Rashidi, F., M. Rashidi og M. Bahadori. »Network modeling for digital simulation of
switching transients.« 29th Annual Conference of the IEEE Industrial Electronics
Society 2003: 1771-4 Vol.2.
Rioual, M. og M. Sow. »Study of the Sympathetic Interactions when Energizing
Transformers for Wind-Farms: Description of the Phenomena Involved and
Determination of the Stresses during their Energization.« Madrid: 7th International
Workshop on Large-Scale Integration of Wind Power into Power Systems and
Transmission Networks for Offshore Wind Farms, 2008.
Sluis, Lou van der. Transients in Power Systems. Wiley, 2001.
Smith, K.S. »Transformer Inrush Studies for Wind Farm Grid Connections.« ICPST
2005.
Steward, S. Distribution Switchgear. UK: IEE Power Series, 2004.
Styvaktakis, E, Bollen MHJ, Gu, IYH. »Transformer saturation after voltage dip.« IEEE
Power Eng. Rev 2000: 62-64.
Sweet, W. »Danish Wind Turbines Take Unfortunate Turn.« IEEE Spectrum (2004):
30-34.
Sørensen, P., et al. »Switching transients in wind farm grids .« European Wind Energy
Conference and Exhibition 7-10. May 2007.
Tziouvaras, D. A. »Protection of high-voltage AC cables.« 59th Annual Conference for
Protective Relay Engineers April 2006: 48-61.
Weber, F.U. Wiederverfestigung des Hochstrom-Vakuumbogens bei hoheren
Spannungen. 1988: Ph.D. tesis Braunschweig, u.d.
Wong, S.M., L.A. Snider og E.W.C. Lo. »Overvoltages and reignition behavior of
vacuum circuit breaker.« 6th International Conference on Advances in Power System
Control, Operation and Management 2003.
183
A NON-SIMULTANEOUS POLE CLOSING DURING THREE-PHASE TRANSFROMER ENERGIZATION IN POWER FACTORY
In this appendix the simulation results for non-simultaneous pole closing during a three-
phase transformer energization in Power Factory are presented. These results are
attached for the explanation in subsection 4.4.4.2, page 80.
The nomenclature showed in Table 7-1was used for the all the following figures in this
appendix.
Table 7-1 Color nomenclature for appendix A
Left side Right side
Color Name Color Name Blue Voltage phase A Blue Voltage phase A Green Voltage phase B Green Voltage phase B
Red Voltage phase C Red Voltage phase C Light blue Magnetizing flux phase A Light blue Magnetizing flux phase A Dark green Magnetizing flux phase B Dark green Magnetizing flux phase B Pink Magnetizing flux phase C Pink Magnetizing flux phase C
Blue Current phase A Blue Current phase A Green Current phase B Green Current phase B Red Current phase C Red Current phase C
The simulated events are presented in Table 7-2:
Table 7-2 Non-simultaneous simulation cases
Figure Δt [ms] Left side Right side
φd φq φd φq Figure 7-1 0,02 0 0 -1 0 Figure 7-2 2 0 0 -1 0 Figure 7-3 3,33 0 0 -1 0 Figure 7-4 5 0 0 -1 0 Figure 7-5 6,66 0 0 -1 0
Where
Δt is the time between pole closing
Φd is the residual flux in the d-axis
Φq is the residual flux in the q-axis
Non-simultaneous pole closing during three-phase transfromer energization in Power
Factory
184
35.0028.0021.0014.007.0000.000 [ms]
6.00
4.00
2.00
0.00
-2.00
-4.00
-6.00
35.0028.0021.0014.007.0000.000 [ms]
3.00
2.00
1.00
0.00
-1.00
-2.00
-3.0035.0028.0021.0014.007.0000.000 [ms]
3.00
2.00
1.00
0.00
-1.00
-2.00
-3.00
35.0028.0021.0014.007.0000.000 [ms]
6.00
4.00
2.00
0.00
-2.00
-4.00
-6.00
Vpsi and I(0.02ms)vs flux
Date: 4/5/2008
Annex: /6
DIg
SIL
EN
T
Figure 7-1 Non-simultaneous pole closing with 0,02 ms apart
35.0028.0021.0014.007.0000.000 [ms]
6.00
4.00
2.00
0.00
-2.00
-4.00
-6.00
35.0028.0021.0014.007.0000.000 [ms]
3.00
2.00
1.00
0.00
-1.00
-2.00
-3.0035.0028.0021.0014.007.0000.000 [ms]
3.00
2.00
1.00
0.00
-1.00
-2.00
-3.00
35.0028.0021.0014.007.0000.000 [ms]
6.00
4.00
2.00
0.00
-2.00
-4.00
-6.00
Vpsi and I(2ms)vs flux
Date: 4/5/2008
Annex: /7
DIg
SIL
EN
T
Figure 7-2 Non-simultaneous pole closing with 2 ms apart
Non-simultaneous pole closing during three-phase transfromer energization in Power
Factory
185
35.0028.0021.0014.007.0000.000 [ms]
6.00
4.00
2.00
0.00
-2.00
-4.00
-6.00
35.0028.0021.0014.007.0000.000 [ms]
3.00
2.00
1.00
0.00
-1.00
-2.00
-3.0035.0028.0021.0014.007.0000.000 [ms]
3.00
2.00
1.00
0.00
-1.00
-2.00
-3.00
35.0028.0021.0014.007.0000.000 [ms]
6.00
4.00
2.00
0.00
-2.00
-4.00
-6.00
Vpsi and I(3ms)vs flux
Date: 4/5/2008
Annex: /8
DIg
SIL
EN
T
Figure 7-3 Non-simultaneous pole closing with 3,33 ms apart
35.0028.0021.0014.007.0000.000 [ms]
6.00
4.00
2.00
0.00
-2.00
-4.00
-6.00
35.0028.0021.0014.007.0000.000 [ms]
3.00
2.00
1.00
0.00
-1.00
-2.00
-3.0035.0028.0021.0014.007.0000.000 [ms]
3.00
2.00
1.00
0.00
-1.00
-2.00
-3.00
35.0028.0021.0014.007.0000.000 [ms]
6.00
4.00
2.00
0.00
-2.00
-4.00
-6.00
Vpsi and I(5ms)vs flux
Date: 4/5/2008
Annex: /9
DIg
SIL
EN
T
Figure 7-4 Non-simultaneous pole closing with 5 ms apart
Non-simultaneous pole closing during three-phase transfromer energization in Power
Factory
186
35.0028.0021.0014.007.0000.000 [ms]
6.00
4.00
2.00
0.00
-2.00
-4.00
-6.00
35.0028.0021.0014.007.0000.000 [ms]
3.00
2.00
1.00
0.00
-1.00
-2.00
-3.0035.0028.0021.0014.007.0000.000 [ms]
3.00
2.00
1.00
0.00
-1.00
-2.00
-3.00
35.0028.0021.0014.007.0000.000 [ms]
6.00
4.00
2.00
0.00
-2.00
-4.00
-6.00
Vpsi and I(6ms)vs flux
Date: 4/5/2008
Annex: /10
DIg
SIL
EN
T
Figure 7-5 Non-simultaneous pole closing with 6,66 ms apart
187
B SECOND STUDY CASE PLOTS
Figure 7-6 Case 2. Phase A voltage for each location (20-22 ms)
Figure 7-7 Case 2. Phase B voltage for each location (20-22 ms)
Second study case plots
188
Figure 7-8 Case 2. Phase C voltage for each location (20-22 ms)
Figure 7-9 Case 2. Phase A voltage for each location (20-20,5 ms)
Second study case plots
189
Figure 7-10 Case 2. Platform voltages (20-30 ms)
Figure 7-11 Case 2. Platform voltages (10-60 ms)
Second study case plots
190
Figure 7-12 Case 2. Platform currents (20-22 ms)
Figure 7-13 Case 2. A01currents (0-500 ms)
Second study case plots
191
Figure 7-14 Case 2. A09 currents (0-500 ms)
Figure 7-15 Case 2. A09 currents (20-21,5 ms)
Second study case plots
192
Figure 7-16 Case 2. A09 current phase A (20-21,5 ms)
Figure 7-17 Case 2. A09 current phase B (20-21,5 ms)
Second study case plots
193
Figure 7-18 Case 2. Platform current (400-500 ms)
Figure 7-19 Case 2. Rms currents at platform
Second study case plots
194
Figure 7-20 Case 2. Rms currents at A01 and A09
Figure 7-21 Case 2. Active power at platform
Second study case plots
195
Figure 7-22 Case 2. Active power at A01 and A09
Figure 7-23 Case 2. Reactive power at platform
Second study case plots
196
Figure 7-24 Case 2. Reactive power at A01 and A09
Figure 7-25 Case 2. Rms voltage from measurements
Second study case plots
197
Figure 7-26 Case 2. Rms voltage from Power Factory
Figure 7-27 Case 2. Rms voltage from PSCAD
Second study case plots
198
www.dtu.dk/centre/cet
DTU Elektro
Centre for Electric Technology (CET)
Technical University of Denmark
Elektrovej 325
DK-2800 Kgs. Lyngby
Denmark
Tel: (+45) 45 25 35 00
Fax: (+45) 45 88 61 11
E-mail: [email protected]