Simpson's house – group members
Linda Luna Milca Centellas Elvia Muriel Alex Pedraza Timoteo Ponce * Julio Gutierrez
Timeboxes length (before)
Release planning meeting – 1h 30m Sprint planning meeting – 1~2m Sprint length – 30m Story points (initial): 201 Total length (initial): 7 sprints
Timeboxes length (after)
Estimated velocity: 13 Missing story points: 25 Spent time: 16 sprints
Team
Product owner – timoteo > didn't work at all Scrum master – linda Team
milca elvia alex
Release planning
Team estimation
Charters
Base design
First sprint
Team work
Team work
PO committed to his role
Release burndown chart
Release burndown chart
Initial progress
After some few sprints
More work done
Updated burndown chart
RC1?
At the end
Conclussions
Estimated time was completely wrong Metrics and scales are very important. Without a charter it's hard to say when you are
done or not. Almost all sprints left a technical debt. The team worked in a pair-styled way. When the pace is set, the team starts working
in a self-organized way.