MnDOT-ACEC/MN Annual Consultant Conference March 5, 2012 Leveraging SUE Data for Utilities on...
-
Upload
madeleine-gibbs -
Category
Documents
-
view
217 -
download
0
Transcript of MnDOT-ACEC/MN Annual Consultant Conference March 5, 2012 Leveraging SUE Data for Utilities on...
MnDOT-ACEC/MN Annual Consultant Conference
March 5, 2012
• Leveraging SUE Data for Utilities on Projects
• Tom Swafford- Utility Mapping Services, Inc.
What will be covered: Utility Challenges What is Subsurface Utility Engineering (SUE)?
Leveraging SUE data for:
DesignersUtilitiesProject OwnersContractorsExcavators
My Experiences
State Aid Precons
Preparing for Region Utility Engineer Interview –SUE
My First Phone call to Telecom as Region Utility Engineer
Co Project “contractor is responsible for coordinating all utility relocations”
State Utility Engineer- “Reasonable Notice Issues”
Utilities Best Practices
3 C’s of Project Utilities Efforts
Communication (Early and Often)
…and Coordination
…result in…Cooperation
Lessons learned from Design Build “…contractors must include utility companies in the project development process at the very beginning and make them active members of the team.”
Observations.…
Perception…..Utility Company Incentives must be monetary…..
Reality…..Showing a commitment to minimize utility relocations and efficient use of utility crews are highly recognized incentives.
What is SUE?
• Engineering Process to manage risk utilities bring to the project
– ASCE 38-02 “Standard Guideline for the Collection and Depiction of Existing Subsurface Utility Data”
• Utility Information Quality Levels A,B,C,D
– Utility Conflict Analysis– Utility Coordination
Nightmare-Unexpected encounter
(SUE) Spaghetti Utility Engineering
Quality Level “D”
The least reliable utility data- Great for Project Planning Purposes
• Plotted on plans from records.
• Sometimes a field visit - to look for utility indications on the site - is made.
• Sometimes “verbal recollections” are plotted.
Quality Level “C”- Traditional utility depiction
• Surface Appurtenances are surveyed and accurately plotted on a current site plan
• Utility data from records (QL D) are correlated to the appurtenances
Quality Level “B”
A significant upgrade in quality
• Surface Geophysical Methods used to search for and trace existing utilities.
• Designated utilities are then surveyed and plotted on site plan.
SUE Provider Typical Field EquipmentMany different depiction and location tools are needed to attain Quality Level “B” on a project.
Quality Level “A”A guarantee in 3-D
• Utilities exposed via non-destructive air-vacuum means
• Exposed utilities are then surveyed and plotted on site plan
• Elevations, Size, Condition, Materials, Precise Horizontal Positions are measured and documented
One-Call vs Quality A SUE
One Call Marks do not suffice for design decisions
2-14-2012Whew! I found it. The Telecom duct run is actually where Bill thought it was, on the west side of the south bound bridge, so it is on the bridge that will remain in place. It is definitely there,
you can actually see into a small handhold area on the bridge just
above the duct run (I got some photos of that). I also got it located
out all the way to the north end of the corridor. It is not out by the
street where one-call had it marked on the north side of the bridge, it
is well over 50 feet west of the street, way back in the trees. There is
a phone manhole way back in that area that is a pain to find, but is
the best access to the cables. Anyway, it's done.
Project Development Process
Preliminary Design Phase Design PhaseLetting Phase
PRELIMINARY DESIGN
Preliminary Design Conference
Geometric Schematic Approval
ENVIRONMENTAL
Environmental Clearance
LETTING
PLANNING AND PROGRAMMING
Construction Funding
Identification
RIGHT OF WAY AND UTILITIES
Utility & Right ofWay Certifications
Right of Way Release
PS&E DEVELOPMENT
Design Conference
PS&E Assembly
30% 60% 90%
Start Right of Way Map
Time
Planning PhaseConstruction Phase
Post-Construction Phase
CONSTRUCTION
POST- CONSTRUCTION
Project Award
Construction Start
Construction End
CCC often missing from PD Process
Utility Coordination Process
Preliminary Design Construction
after QLB
Design
additional data
processing
Proj
ect
Com
pleti
on
Post-Construction Utility Permitting
Utility as-builts
Utility Data Input
Utility Data Processing
30% 60% 90%
QLBdata
QLAdata
Project Development Process
after QLA
QLDdata
QLCdata
afterQLD
afterQLC
Planning
Letti
ng
Utility Conflict Resolution
Leveraging SUE for Design
• Perception…
A utility conflict is identified when there is a “direct hit”
Rural City Paver experience with waterline on Dike Road
• Reality…
Very often “indirect” utility conflicts are the cause of costly and time consuming construction field problems…Subgrade Compaction, temp sheeting, vibrations, unstable cast iron utility, utility staging, etc.
Project Plan View
30” Water18” Drainage
Conflict?
How deep is the water pipe?
30” Water
?
?
?
?
?
?
?
?
How deep is the water pipe?
30” Water
Utility Conflict MatrixUtility Owner
ID Sheet No.
Utility Type
Size/ Material
Utility ConflictDescription
Start Sta.
End Sta.
Start Offset
End Offset
Inv. Need
Test Hole
Recommended Action
Rsp. Party
Est. Res. Date
Res. Status Cost Analysis
AWS C16 1 WM 30” ductile iron pipe
Proposed 18” drainage pipe would cross WM.
36+50 47’ LT QLA 17 Review possibility of adjusting drainage pipe up to avoid conflict.
U n/a Utility conflict identified.
CPS C32 1 OE 45’ pole Existing pole in proposed roadway
34+55 40’ RT QLC Pole to be relocated.
U n/a Utility conflict identified.
AWS C43 1 W 12” Proposed sidewalk in conflict with 12” water main.
37+00 53’ LT QLA 21 Highway/sidewalk re-design to avoid utility impact.
D n/a Utility conflict identified.
CPS C54 1 OE 45’ pole Existing pole in proposed curb line
38+30 57’ RT QLC Pole to be relocated U n/a Utility conflict identified.
CPS C55 1 OE 45’ pole Existing pole in area of grade cut
38+50 63’ RT QLC Pole may need to be supported or replaced with taller pole
U n/a Utility conflict identified.
CPS C61 1 OE 45’ pole Existing pole in proposed curb line
40+00 52’ RT QLC Pole to be relocated U n/a Utility conflict identified.
ATT C28 1 OTV 45’ pole Existing pole in conflict with proposed drainage
40+15 65’ LT QLC Pole to be relocated U n/a Utility conflict identified.
Cost Estimate Analysis
Alternative Number
Alternative Description
Alternative Advantage Alternative Disadvantage
Engineering Cost
(Utility)
Direct Cost
(Utility)
Engineering Cost
(DOT)
Direct Cost
(DOT)
Total Cost Feasibility Decision
0 Relocation before construction.
No design change required, no additional cost to DOT.
Cost to utility for relocation.
$10,375 $63,875 $0 $0 $74,250 Yes Selected
1 Protect in-place. Utility can remain in place.
Access to utility for maintenance problematic.
$7,875 $32,375 $0 $0 $40,250 No Rejected
2 Change highway design.
Utility can remain in place.
High cost and project delay.
$0 $0 $95,375 $0 $95,375 Yes Rejected
3 Exception to policy. No cost to utility or DOT.
High risk of damage to utility and maintenance problems.
$0 $0 $0 $0 $0 No Rejected
Conflict ID: 1
Utility Owner: AT&T
Utility Type: Telephone
Size and/or Material: Fiber Optic
Project Phase: 60% Design
Leveraging SUE for Utilities
• Observations
Utilities’ initial reaction is wariness
When they hear that they will be involved in design decisions they begin to warm
After multiple meetings to coordinate best design scenario they are part of solution
Leveraging SUE for Contractors
• Pre-proposal utility meeting on TH 610
– Shortlisted DB teams were ecstatic on having quality information to manage their utility risks on the project.
Leveraging SUE for Excavators
• SR 77 UDOT Bridge piling experience
• CRC Geotech experience in damaging sewer line during environmental investigation
Final Thoughts
• SUE is a proven engineering practice and should be sized to project risks
• Purdue University Study shows Average savings of $4.62 saved on every $1 spent on upgrading traditional Quality Level “D and/or “C” data to quality Level “B” and “A” data
• Thank you- Tom Swafford