MLA Huntington- Comments on Massey Tunnel Replacement Project - Project Description and Key Areas of...

download MLA Huntington- Comments on Massey Tunnel Replacement Project - Project Description and Key Areas of Study

of 3

Transcript of MLA Huntington- Comments on Massey Tunnel Replacement Project - Project Description and Key Areas of...

  • 7/24/2019 MLA Huntington- Comments on Massey Tunnel Replacement Project - Project Description and Key Areas of Study

    1/3

    Legislative Office:

    Room 145 Parliament Buildings

    Legislative Assembly

    Province of Brit sh Columbia

    Vicki Huntington, M.L.A.

    Delta South)

    Constituency Office

    4805 Delta Stree

    Victoria, B.C. V8V 1X4

    Phone: 250 952-7594

    Fax: 250 952-7598

    Fax: 604 940-792

    www. vicki hu nti ngton ,c

    Delta, B.C. V4K 2T

    Phone: 604 940-7924

    e-mail: vicki.huntington.rnla leg.be,ca

    February 15, 2016

    B.C. Environmental Assessment Office

    836 Yates St.

    Victoria, BC V8W 1L8

    To whom it may concern:

    Re: Massey Tunnel Replacement Project, Project Description and Key Areas of Study

    Please consider the following my comments on the Project Description and Key Areas of Study

    Document for the proposed George Massey Tunnel Replacement Project.

    As a general comment, I am concerned that the timeline of the environmental assessment

    process is too short to give proper consideration and deliberation on the project s potential

    effects. I am concerned this will undermine the credibility and quality of the project assessment

    and suggest the timeline should be extended.

    Additionally, I trust that the concerns identified by Corporation of Delta staff will be given due

    attention as part of the assessment process, including hedgerow loss, irrigation, post

    construction air quality monitoring, cycling linkages, and heritage resources.

    I would also like to highlight Delta's concern about assessing and mitigating temporary effects

    during construction, which will directly affect residents and wildlife. Noise due to pile driving

    and other activities, as well as the effects of construction delays, should be minimized as much

    as possible. Details on mitigation efforts for noise and construction delays should be identified

    during the assessment process. Temporary environmental effects for staging and temporary

    road-use activities should also be minimized and fully reversible. Finally, 1 support Delta's

    statement that the Marina Gardens development must be included as part of the assessment,

    looking at both human health impacts and cumulative environmental effects.

    I have provided a number of comments on specific sections on the Project Description and Key

    Areas of Study document below.

    2.3 - Reduced congestion - The proponent should be required to quantify and

    consider the impacts on congestion beyond the scope of the project. It is plausible that

  • 7/24/2019 MLA Huntington- Comments on Massey Tunnel Replacement Project - Project Description and Key Areas of Study

    2/3

    traffic may be improved at the crossing itself and this may have benefits for those

    making trips between Delta and Richmond. But the government s documents show 40

    per cent of northbound morning traffic is destined to Vancouver1. A key concern

    expressed by many stakeholders, including myself, is that the traffic bottleneck that

    exists at the Massey Tunnel will simply move north to the Oak Street Bridge, which

    already faces significant congestion issues.

    2.3 - Improved transit - The proponent should offer travel time savings estimates

    across all road users. Time savings for transit users, in comparison to the current

    baseline, should be quantified to better understand the extent of improvement offered

    by the project. The proponent should provide estimates of any increased demand

    expected to TransLink as a result of the improved transit for planning purposes. Further,

    the proponent should develop high-level planning documents that outline future rapid

    transit options enabled by the project.

    2.3 Enhanced environment A 2014 government commissioned report by MMK

    Consulting noted the new bridge scenario would not appreciably reduce greenhouse gas

    emissions in comparison to other replacement options for the Massey Tunnel. The

    bridge option was projected as having higher levels of traffic growth than [maintaining

    the existing tunnel]. 2 Though it was noted that reduced travel times would result in less

    idling times and therefore better fuel economy on average, On balance, total emissions

    [were] expected to be similar to [maintaining the existing tunnel]. 3 Given this

    discrepancy, the proponent should be required to quantify the amount of greenhouse

    gas reductions expected from the bridge, if any. The analysis should look beyond the

    footprint of the actual project and include the expected effects the project will have on

    other congestion areas across the Lower Mainland, including at the Oak Street Bridge. In

    particular, it is critical that the analysis estimate and consider any induced traffic

    demand the bridge may enable as part of its scope, and not simply the reduced idle

    times. If the project is found to increase emissions, the proponent should be required to

    offer potential mitigation options, including increased investment in local transit service.

    Finally, the analysis should control for increased fuel efficiency brought about by

    changes in automotive technology, so as not to skew conclusions.

    5.1-7; 5.9-14 - Marine Shipping and Cumulative Effects - The Ministry notes that

    studies will be conducted to determine marine traffic frequency and volume. There is

    widespread concern that replacing the tunnel with a bridge could increase marine vessel

    traffic beyond the bridge location, up the Fraser River, especially as new industrial ports

    come online. Any studies of marine use related to the project must examine this

    possibility. If marine vessel traffic is likely to increase as a result of this project, then the

    1 Government of British Columbia (November, 2012). George Massey Tunnel Replacement Project - Planning for

    the Future. Phase 1: Understanding the Need, Consultation Discussion Guide. Online at

    http://engage.gov.bc.ca/masseytunnel/files/2012/ll/George-IVlassey-Tunnel-Replacement-Project-Discussion-

    Guide.pdf

    2 MMK Consulting (March, 2014). George Massey Tunnel Replacement Project: Evaluation of Crossing Scenarios.

    Online at http://engage.gov.bc.ca/masseytunnel/files/2015/06/GMT-2014-March_Evaluation-of-Crossing-

    Scenarios.pdf

    3 Ibid.

  • 7/24/2019 MLA Huntington- Comments on Massey Tunnel Replacement Project - Project Description and Key Areas of Study

    3/3

    induced effects of that traffic on all aspects of the environment and human health need

    to be evaluated as part of the cumulative effects assessment for the project even if

    those effects are beyond the physical footprint of the project. This would include any

    effects on vulnerable marine species, including endangered Southern Resident Killer

    Whale populations.

    5.1 - Land and Water Use - The proponent anticipates no-net-loss of agricultural

    land , but exactly how this will be achieved will require more detail. This commitment is

    welcome, but the proponent should be required to offer further detail on the range of

    land loss or gain anticipated by the project.

    5.8 - Terrestrial Wildlife - The proponent notes the Ministry is documenting the

    presence of different bird species along the project alignment, and identifying the

    collision risk for bird species due to the construction of the bridge and associated

    infrastructure. The proponent should be required to mitigate any increased risk of

    collision with species-at-risk, such as the barn owl.

    5.9 - Air Quality - The proponent should be required to consider the effects the

    project will have on greenhouse gas emissions, in addition to the air contaminants

    identified in this section. As mentioned in my earlier comments on section 2.3, the

    analysis of emissions should include not only the effects of reduced idling time and

    increased fuel economy, but of increased traffic brought on by induced demand enabled

    by the bridge. It should also consider any added congestion brought about at locations

    outside the project boundaries, including the Oak Street Bridge.

    Thank you for consideration.

    Best regards,

    Vicki Huntington, MLA

    Delta South