ML81N Creating an Entry Sheet 03-29-2007

29
Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 : File name: ML81N_CREATING_AN_ENTRY_S HEET_03-29-2007 Reference Number: ML81N-10-27- 2006 Version: Not Started Last Modified: 4/7/2011 10:58:00 AM SAP Parent Page 1 / 28 ML81n_Creating_A_Service_Entry_Sheet ML81N

Transcript of ML81N Creating an Entry Sheet 03-29-2007

Page 1: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 1 / 28

ML81n_Creating_A_Service_Entry_Sheet ML81N

Page 2: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 2 / 28

Purpose

Use this procedure to create an entry sheet on a service purchase order.

Trigger

Perform this procedure when you need to release a purchase order for payment. Typically you will receive a signed off invoice.

Prerequisites

You will need to know the purchase order number.

You should have a signed invoice in hand.

You should always enter the following information in the short text, starting with invoice number followed the amount of the invoice

Menu Path

Use the following menu path(s) to begin this transaction:

Select ML81N to allow you to the select purchase order or (entry sheet number if you what to amend the entry sheet), once you enter in either the p.o. number or entry sheet number. Click on the green check. Now you should be at the service entry against p.o. screen. Next click on

the new sheet icon to be able to enter in data

Transaction Code

ML81N

Helpful Hints

Always enter the invoice characters exactly as they appear on the hard copy of the invoice in the “reference” field which is under the “accept Data” tab. This field must match exactly, if not the invoice will be blocked from payment. Do not put inv. or letters of the vendors name in this field. Unless these characters are on the hard copy of the invoice and that is how the vendor produces their invoice. Also if the vendor use zero’s as part of the characters you must also include these in the reference field. If you do not know the exact invoice number, than leave the reference field blank.

Always put the amount of the invoice in the short text, so when your management performs the 02 release they can double check the amount released to make sure it matches the amount of the invoice. If you cannot get the amount of your entry sheet to match the invoice exactly you will need to contact Procurement to get the purchase order changed in order to allow them to match exactly otherwise your purchase order will show as open on the outstanding P.O. report due to the variance between the amount released and the amount paid regardless if it is more or less.

Page 3: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 3 / 28

Procedure

1. Start the transaction using the transaction code ML81N.

Page 4: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 4 / 28

SAP Easy Access

2. Double-click on this transaction code. The screen below appears. Enter in either a purchase order number for the initial creation of the entry sheet. Please note if the P.O. has more than one operation you will need to select which operation you want to release for payment. Use the field to the right of the P.O. number field. Please note, if you do not enter an operation number SAP will automatically default to operation 10. If you are simply amending an entry sheet previously created, enter in that entry sheet number.

Page 5: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 5 / 28

Select Purchase Order/Entry Sheet

3. As required, fill in one of the following fields, either enter in a P.O. number or a service entry sheet

number.

Field Name R/O/C Description

Purchase order R Description of the Purchase order.

Example: 4500458468

Service Entry R Description of the entry sheet

Example: 1000081046

4. Once that is done click on this icon .The screen below appears.

Page 6: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 6 / 28

Service Entry Against Purchase Order 4500458468 00010

5. Next click on this icon to create your entry sheet .The screen below appears

Page 7: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 7 / 28

1000081046 Create Entry Sheet

6. As required, complete the following field:

Field Name R/O/C Description

Short text R Description of the Short text.

Example: Inv.5285 amt. $2,040.00

7. Next click on this icon .

Page 8: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 8 / 28

1000081046 Create Entry Sheet

8. As required, complete the following fields.

Field Name R/O/C Description

Service loc. R Description of the Service loc.

Example: Southwest Middle School

Period R Description of the Period. You could use this field for required monthly service tracking or total time involved to complete the work.

Example: 07-01-2006 thru 10/27/2006

PRsp. intern. R Description of the PRsp. internal.

Example: Gary Green (person responsible for overseeing the work)

PRsp. extern. R Description of the PRsp. external.

Example: Charron Sports(vendor performing the work)

Page 9: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 9 / 28

9. Now click on this icon The screen below appears.

Page 10: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 10 / 28

1000081046 Create Entry Sheet

10. As required, complete the following fields:

Field Name R/O/C Description

Reference R Description of the Reference.

Example: 5285 (This must be inputted exactly as listed on the invoice.) other wise the invoice will be blocked from payment.

Doc. text O Description of the Doc. text.

Example: signed off on 10-26-2006(this field is a free text and is optional)

11. Next click on this icon .

Page 11: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 11 / 28

1000081046 Create Entry Sheet

12. As required, complete the following fields: Please enter a percentage ranging from 1% to 100%

depending on how the vendor performed in quality and timeliness.

Field Name R/O/C Description

Quality of service R Description of the Quality of service.

Example: 100

Service timeliness R Description of the Service timeliness.

Example: 100

13 Now click on this icon to add any additional reference that is needed .Push the “F-6”

key to open use field.

Page 12: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 12 / 28

14 1000081046 Create Entry Sheet

Page 13: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 13 / 28

15 Change Entry sheet long text: Language EN. This field is an open text, meaning you can document as much information you want. You can also copy and paste an email in this text field.

Page 14: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 14 / 28

16 When you are done entering all your needed information, click on the back green arrow to return to the main screen.

Page 15: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 15 / 28

17. Next click on this icon .The screen below appears.

Page 16: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 16 / 28

Service Selection

18. Now click on this icon .The screen below appears.

Page 17: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 17 / 28

Select Services as Reference

19. Next click on all the service specification lines in order to select the ones you want to release for

payment. If you want to select all lines go to the header look for “Edit then click on “select all” from the drop down list.

20. Now click on this icon The screen below appears.

Page 18: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 18 / 28

1000086733 Create Entry Sheet

21. Next click on this icon to verify that you released the correct amount. Make sure the

amount you released matches the exact amount of the invoice. If not amend the quantities accordingly.

Page 19: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 19 / 28

1000086733 Create Entry Sheet

22. Next click on this icon to release the entry sheet.The dialog box below appears

Page 20: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 20 / 28

Enter Release Code

23. Now as required, complete the following fields:

Field Name R/O/C Description

Release code R Description of the Release code.

Example: 01

24. Next click on this icon to accept the release .

Page 21: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 21 / 28

1000081046 Create Entry Sheet

25. Finally click on this icon to save the entry sheet The dialog box below appears.

Page 22: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 22 / 28

Entry sheet 1000086733

26. Ignore this message and simply click on this icon This will complete your release

process. If you want to learn how to attach an invoice to your entry sheet please follow the steps below.

Page 23: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 23 / 28

1000081046 Display Entry Sheet

27. Click on this icon to attach a document to your entry sheet.Note in order to do this, you

must have to already scanned the invoice and saved it to your documents or have saved as PDF file to your documents

28. From the drop down list select Create.follow across to. Create Attachment. The dialog box

below appears.

Page 24: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 24 / 28

Import file

29. Click on this icon and search for the correct document you want to attach.

30. Click on this icon to attach it to your entry sheet.

Page 25: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 25 / 28

1000081046 Display Entry Sheet

31. Click on the attachment icon again .

32. This time Select “Attachment list” The screen below appears.

Page 26: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 26 / 28

Service: Attachment list

33. Double-click on this icon to open it .The screen below appears. At this point anyone could print

a copy

Page 27: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 27 / 28

Adobe Acrobat Professional - [~Charron_Sports_SW_Southwest_MS_5285_20061027140113_X.PDF]

34. Click on this icon to exit .The screen below appears.

Page 28: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 28 / 28

Service: Attachment list

35. Click on this icon to exit .The screen below appears.

Page 29: ML81N Creating an Entry Sheet 03-29-2007

Title: ML81n_Creating_A_Service_Entry_Sheet Category 1 : Category 2 :

File name:

ML81N_CREATING_AN_ENTRY_SHEET_03-29-2007 Reference Number: ML81N-10-27-

2006

Version: Not Started Last Modified: 4/7/2011 10:58:00 AM

SAP Parent Page 29 / 28

1000081046 Display Entry Sheet

36. Click on this icon to return to the main menu .

37. You have completed this transaction of creating an entry sheet and attaching a document

Result

You have performed the first phase of this two stage release, now this should appear in your management’s queue for the 02 release (Goods Receipt).

Comments

You should check the next day to see if all of your service entries were converted into Goods Receipts. This can be done by simply checking on the purchase order history. If not check to make sure you released all your service entry sheets by using transaction code ML85.