Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating...

18
Mitigating Risk to Underwater Crossings to Improve Water Supply Reliability: Two Case Studies 10 th CTWWA/JWWA/WRF Water System Seismic Conference Tainan, Taiwan – October 18-21, 2017 Serge Terentieff, P.E., G.E.

Transcript of Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating...

Page 1: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Mitigating Risk to Underwater Crossings to Improve Water Supply Reliability:

Two Case Studies

10th CTWWA/JWWA/WRF Water System Seismic ConferenceTainan, Taiwan – October 18-21, 2017

Serge Terentieff, P.E., G.E.

Page 2: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Outline

• Background

• Risk Assessment

• Mitigation Strategy

• Summary

2

Case Study #1Raw water supply: Aqueduct Interconnections & River Crossing Repair Concept

Case Study #2Potable water supply: Alameda estuary crossings

Page 3: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

3

EBMUD Water Supply System

Case Study #1: MokelumneAqueducts in the Delta Region

Case Study #2: Estuary crossings to Alameda

San Joaquin River Crossing

Old & Middle River Crossings

Page 4: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Risk-Based Approach to Assess LOF & COF and Guide Mitigation Strategy

The probability an underwater crossing will fail

The resulting magnitude of consequence if the underwater pipe breaks

LOF COF

Likelihood of FailureLow High

Con

sequ

ence

of F

ailu

reH

igh

L

ow

The probability an underwater crossing will fail

Alameda Estuary Crossings

Case Study #2MOK AQ #3

River CrossingsCase Study #1B

MOK AQ #1 & 2(interconnections)

Case Study #1A

Page 5: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

5

Case Study 1: Natural Hazards & Risks to Mok AQs in the Delta

• Natural hazards:– Flooding

– Seismic Events

– Subsidence

• Risk to AQs:– Structural failure

of AQ #1 & 2

– Damage from levee failure & flooding

– Damage to AQ #3 at a river crossing

Page 6: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Typical Levee Cross-Section

6

CRESTEL +10.0

HIGH TIDEWSEL +6.0

EL -10.0 +/-

LEVEE FILLS

DENSE SAND [Pleistocene deposits]

LOOSE SAND [Halocene deposits]

PEAT / ORGANICS EL -20.0 +/-

EL -40.0 and deeper

Page 7: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Case Study 1A: Risk to MOK AQs #1 & 2: High Likelihood/Consequence

BixlerInterconnection

Stockton Interconnection

Page 8: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

8

Delta Interconnections to Mitigate Risk to MOK AQs #1/2

To increase Mokelumne Aqueduct conveyance following Delta emergency events

0 MGDMokelumne 2 - 53 MGD

Lafayette 1Mokelumne 1 - 41 MGD

Lafayette 2Mokelumne 3 - 105 MGD

Campo Seco

0 MGD

0 MGD 0 MGD

Walnut Creek

199 MGD

Bixler

41 MGD

105 MGD

Pardee

567 ft

I-5

41 MGD

105 MGD0 MGD 0 MGD

53 MGD53 MGD

42 MGDMokelumne 2 - 42 MGD

Lafayette 1Mokelumne 1 - 33 MGD

Lafayette 2Mokelumne 3 - 87 MGD

Campo Seco

43 MGD

33 MGD 34 MGD

Walnut Creek

162 MGD

Bixler

34 MGD

85 MGD

Pardee

567 ft

I-5

0 MGD

162 MGD75 MGD 77 MGD

43 MGD0 MGD

Existing Gravity Flow Capacity

= 199 MGD

Post-Disaster Gravity Flow Capacity

= 105 MGD

XX

Post-Disaster Gravity Flow Capacity

= 162 MGD

XX

Aqueducts without Delta Interconnections

Aqueducts with Delta Interconnections

Page 9: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Case Study 1B: Risk to MOK AQ#3 @ River Crossings

9

Low Likelihood/High Consequence Event:AQ No. 3 River Crossing Repair Concept at San Joaquin River

• Conventional Repair ~ 8+ Months

• Terminal Storage ~ 6 Months

• “Float & Sink” Repair ~ 6 Months

Page 10: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Case Study 2: Natural Hazards & Risks to Estuary Crossings

10

Page 11: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Case Study 2: Alameda Estuary Crossings: Overview & Purpose

11

Crossing No. 1

Crossing No. 3

Crossing No. 2Proposed Crossings

• Severn underwater pipelines crossings built (1917 – 1987)

• Four crossings remain in-service today

• Three new 24” crossings & open-trench pipelines needed

• Ensure long-term reliability and redundancy

• Meet existing and future demands

• Repair and replace aging infrastructure

In-service Crossings

Page 12: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Selected Project: Crossing No. 1

• Install 1,780 feet of 24-inch HDD pipeline in new alignment

• Install ~5,000 feet of connecting pipeline on each side

• Estimated project cost = $14M

Page 13: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

HDD Option: Selected Project

Page 14: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Summary

14

• Assess risk, considering LOF and COF

• Adopt a mitigation strategy based on risk/consequence: Case Study #1A: Pre-disaster

mitigation (High LOF & High COF) Case Study #1B: Post-disaster

response (Low LOF & High COF) Case Study #2: Pre-disaster

mitigation (High LOF & High COF)

Thank you for your kind attention

Page 15: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Serge [email protected]

Questions?

15

Page 16: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Atlantic Ave

Buena Vista Ave

Lincoln Ave

Alternative Alignments for Crossing No. 1

• Alice-Webster vicinity – 5 alternatives

• Northeast corridor – 4 alternatives

• Connection to Bay Farm Island

– 2 alternatives

Page 17: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Microtunneling Option

Page 18: Mitigating Risk to Underwater Crossings to Improve Water Supply … · 2017. 10. 24. · Mitigating Risk to Underwater Crossings to ... Serge Terentieff, P.E., G.E. Outline • Background

Jet Grouting to Reduce Potential for Differential Settlement

18

HDD 24-inch (600 mm) Diameter Water Main w/Conductor Casing

PLAN

PROFILE