1.040 Project Management
Spring 2009
For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms.
http://ocw.mit.edu/http://ocw.mit.edu/termshttp://ocw.mit.edu/termshttp://ocw.mit.edu/ -
7/31/2019 MIT1_040s09_lec01
2/21
1.040/ 1.4011.040/ 1.401
Pr oj ect Managem entPr oj ect Managem entSpring 2009Spring 2009
Course IntroductionCourse Introduction
Fred Moavenzadeh
Depart ment of Civil and Environmental EngineeringDepart ment of Civil and Environmental Engineering
Massachuset t s Inst it ut e of TechnologyMassachuset t s Inst it ut e of Technology
-
7/31/2019 MIT1_040s09_lec01
3/21
OutlineOutline
IntroductionIntroduction
Course InformationCourse Information
Lecture OutlineLecture Outline
T.A.T.A.
Students; Background, Interests, &Students; Background, Interests, &
ExpectationsExpectations
-
7/31/2019 MIT1_040s09_lec01
4/21
Project ManagementProject Management
Focus of ClassFocus of ClassConstruction Projects;Construction Projects;
Primarily Infrastructure ProjectsPrimarily Infrastructure Projects
-
7/31/2019 MIT1_040s09_lec01
5/21
TopicsTopics
The Course is divided in three parts:The Course is divided in three parts:
Part 1: Project FinancePart 1: Project Finance
Part 2: Project EvaluationPart 2: Project Evaluation
Part 3: Project OrganizationPart 3: Project Organization
There will be a few Guest LecturersThere will be a few Guest Lecturers
-
7/31/2019 MIT1_040s09_lec01
6/21
Term Project (1.401)Term Project (1.401)
Step 1: Preliminary Project ProposalsStep 1: Preliminary Project Proposals
Step 2: Project DetailsStep 2: Project Details
Step 3: DeliverablesStep 3: Deliverables
ReportReport PresentationPresentation
-
7/31/2019 MIT1_040s09_lec01
7/21
DESIGN CLOSEOUTDEVELOP-
MENT DIVESTMENTOPERATIONS
Construction PhasesConstruction Phases
& Class Topics& Class Topics
FEASIBILITYANALYSIS
PROJECTMANAGEMENT
-
7/31/2019 MIT1_040s09_lec01
8/21
Construction Phases
Strategic Planning, or conceptualization The need for a project isidentified, so that specific Objectives are achieved Alternative
projects (including the do-nothing option) are examined System DesignThe approach for addressing the organizations
strategic concerns is established during systems design Therequirements are translated into specific technical specifications
Detailed Design is the phase in which the optimal systems designis translated into a detailed technical implementation scheme
Development refers to the implementation of the detailed design
Operations and Lifecycle Support represents the period during
which the project yields benefits to the organization DivestmentThe initial design again determines the potential for
proper divestment in the context of the sociopolitical and naturalenvironment
-
7/31/2019 MIT1_040s09_lec01
9/21
Feasibility Studies and PreliminariesFeasibility Studies and Preliminaries
Understanding project finance and evaluationUnderstanding project finance and evaluation Helps understand economic challenges faced by ownerHelps understand economic challenges faced by owner
and contractorand contractor
Risk managementRisk management
Deciding on fundamentals of contractDeciding on fundamentals of contract
Delivery systems (organizational method)Delivery systems (organizational method) Contract type (how pay?)Contract type (how pay?)
Award method (how decide who hired?)Award method (how decide who hired?)
-
7/31/2019 MIT1_040s09_lec01
10/21
DESIGN CLOSEOUTDEVELOP-
MENT DIVESTMENTOPERATIONSFEASIBILITY
ANALYSIS
PROJECTMANAGEMENT
Construction PhasesConstruction Phases
-
7/31/2019 MIT1_040s09_lec01
11/21
Design PhaseDesign Phase
EstimationEstimation
Successive estimates producedSuccessive estimates produced Planning & SchedulingPlanning & Scheduling
WBSWBSWeb Based SchedulingWeb Based Scheduling
Deterministic & probabilistic schedulingDeterministic & probabilistic scheduling
Resource planningResource planning
SimulationSimulation
-
7/31/2019 MIT1_040s09_lec01
12/21
Project DynamicsProject Dynamics
AsAs--planned vs. asplanned vs. as--built (e.g., errors and changes)built (e.g., errors and changes)
Significance of feedbacksSignificance of feedbacks -- CounterCounter--intuitive effects ofintuitive effects of
policies (e.g., overtime)policies (e.g., overtime)
-
7/31/2019 MIT1_040s09_lec01
13/21
DESIGN CLOSEOUTDEVELOP-
MENT DIVESTMENTOPERATIONSFEASIBILITY
ANALYSIS
PROJECTMANAGEMENT
Construction PhasesConstruction Phases
-
7/31/2019 MIT1_040s09_lec01
14/21
Project ManagementProject Management
1. The phases of1. The phases of-- DevelopmentDevelopment
-- Close OutClose Out
Resource SchedulingSimulation
Basics of Project Monitoring and Control
Changes and Claims
Earned Value Analysis
Quality Reviews and Audits
-
7/31/2019 MIT1_040s09_lec01
15/21
Project ManagementProject Management
1. The phases of1. The phases of-- DevelopmentDevelopment
-- Close OutClose Out
Resource Scheduling
Simulation
Basics of Project Monitoring and Control
Changes and Claims
Earned Value Analysis
Quality Reviews and Audits
Resource Scheduling
- How to allocate resources ($, time, etc.) to execute a given task efficiently-Trade offs between conflicting/competing resources
Tools: graphical analyses, programming (linear, integer, heuristic, etc.)
-
7/31/2019 MIT1_040s09_lec01
16/21
Project ManagementProject Management
1. The phases of1. The phases of-- DevelopmentDevelopment
-- Close OutClose Out
Resource SchedulingSimulation
Basics of Project Monitoring and Control
Changes and Claims
Earned Value Analysis
Quality Reviews and Audits
Simulation
- Involves mathematical description/representation of the management process
- Helps identify optimal schedules and decisions
- Helps to quickly determine impact of alternative schedules
-Tools: algorithms implemented on computers
-
7/31/2019 MIT1_040s09_lec01
17/21
Project ManagementProject Management
1. The phases of1. The phases of-- DevelopmentDevelopment
-- Close OutClose Out
Resource SchedulingSimulation
Project Monitoring and Control
Changes and Claims
Earned Value Analysis
Quality Reviews and Audits
Project Monitoring and Control
-How to track your project costs, schedule (time), and other resources- Helps ascertain whether targets are being met
- Needed so that due changes can be made to schedule as and when necessary
-
7/31/2019 MIT1_040s09_lec01
18/21
Project ManagementProject Management
1. The phases of1. The phases of-- DevelopmentDevelopment
-- Close OutClose Out
Resource SchedulingSimulation
Basics of Project Monitoring and Control
Changes and Claims
Earned Value Analysis
Quality Reviews and Audits
Changes and Claims
-What are the causes of time delays, cost overruns, change orders?
- How can such problems be prevented or mitigated
- Conflict resolution
-
7/31/2019 MIT1_040s09_lec01
19/21
Project ManagementProject Management
1. The phases of1. The phases of-- DevelopmentDevelopment
-- Close OutClose Out
Resource SchedulingSimulation
Basics of Project Monitoring and Control
Changes and Claims
Earned Value Analysis
Quality Reviews and Audits
Earned Value Analysis
-is a snapshot in time (as the project is in progress)- compares work plan vs. actual work progress
- is a standard method of (a) measuring project progress at any given point in time,(b) updating forecasts of completion date and final cost,
- Is an early warning system to detect deficient or endangered progress.
-
7/31/2019 MIT1_040s09_lec01
20/21
Project ManagementProject Management
1. The phases of1. The phases of-- DevelopmentDevelopment
-- Close OutClose Out
Resource SchedulingSimulation
Basics of Project Monitoring and Control
Changes and Claims
Earned Value Analysis
Quality Reviews and Audits
Quality Reviews and Audits
-Quality Control (typically done by owners inspectors at the end of major production phases.
- Quality Assurance (typically done by contractor throughout the production, incl. raw materials
- Audits and QA/QC Reviews (retrospective in nature)
-
7/31/2019 MIT1_040s09_lec01
21/21
Project ManagementProject Management
1. The phases of1. The phases of-- DevelopmentDevelopment
-- Close OutClose Out
2. Related Topics2. Related Topics
-- Risk and Uncertainty, etc.Risk and Uncertainty, etc.