Missouri's Experience w-RAS in HMA - Purdue Engineeringncaupg/Activities/2014... · accordance with...
Transcript of Missouri's Experience w-RAS in HMA - Purdue Engineeringncaupg/Activities/2014... · accordance with...
Steve Jackson, PE Technical Manager NB West Contracting
As seen on shinglerecycling.org
NCAUPG Kansas City, MO
With Solutions
B.S. of Civil Engineering B.S. of Economics
University of Missouri- Rolla
Professional Engineer 23 years in construction 15 years in asphalt
First shingle research in 2003 2.5%, 5%, 7.5%, 10%, 15%
First shingle project 2004
First MoDOT shingle project 2005
First MoDOT shingle – WMA project 2009
Most contractors were using RAP & RAS concurrently (2006-2010) 18% RAP and 2% RAS 17% RAP and 3% RAS
Due to the Smooth Road Initiative most work was being done on interstates Superpave mixes Percent Within Limits (Pay Factors)
20 610
8,400
24,000
53,000 54,800
80,700
58,800
0%
5%
10%
15%
20%
25%
30%
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
2005 2006 2007 2008 2009 2010 2011 YTD 2012
Perc
ent R
ecyc
le
Tons
RAS in Asphalt Mixtures in Missouri (MoDOT)
RAS Percent Recycle
COARSE
FINE
COARSE
FINE
Shingle size is key to success
Overheating shingle mixes to “melt” the shingles (370° - 390° F)
Variability in RAS asphalt content Real and perceived
Inflated specific gravities impact mixes*
Sporadic Mixing Problems Confined to Plants not Mixture
Harder to Place in Cool Weather Low Voids on Long Haul Tenderness Asphalt Foamers Run at HMA Temps. Shingle Pancakes – Clumps, Wads, Clinkers
Emphasis shifted from Primary Routes to Secondary Routes Bituminous Pavements (MoDOT Section 401) in
lieu of Superpave (MoDOT Section 403) Less advanced quality control testing ▪ Gradation, deleterious, asphalt content and density ▪ No Percent Within Limits
Contractor Perspective - 2008 Asphalt Cement prices are high Supply of shingles is high Less “Mill & Fill” projects ▪ Less RAP from projects ▪ Large amounts of RAP stockpiled
Fiercely competitive market Longer haul distances
401.4.4.1 Base, BP-1 and BP-2 mixtures shall have the following properties, when tested in accordance with AASHTO T 245. The number of blows with the compaction hammer shall be 35 or the number of gyrations shall be 50 with the gyratory compactor.
Air Voids Stability lb (N) VMA 3.5-4.5 750 (3350) 13.0
Sieve Percent Passing by Weight (Mass)
Base BP-1 BP-2
1 inch (25.0 mm) 100 100 100 ¾ inch (19.0 mm) 85-100 100 100 ½ inch (12.5 mm) 60-90 85-100 95-100 No. 4 (4.75 mm) 35-65 50-70 60-90 No.8 (2.36 mm) 25-50 30-55 40-70 No. 30 (1.18 mm) 10-35 10-30 15-35 No. 200 (75 µm) 6-12 5-12 5-12
Sieve Percent Passing by Weight (Mass)
BP-1 BP-2
1 inch (25.0 mm) 100 100 ¾ inch (19.0 mm) 100 100 ½ inch (12.5 mm) 85-100 95-100 No. 4 (4.75 mm) 50-70 60-90 No.8 (2.36 mm) 30-55 40-70 No. 30 (1.18 mm) 10-30 15-35 No. 200 (75 µm) 5-12 5-12
403.2.6.2 Reclaimed Asphalt Shingles. Reclaimed Asphalt Shingles (RAS) may be used in any mixture specified to use PG 64-22 in accordance with AASHTO PP 53 except as follows: When the ratio of virgin effective binder to total binder in the mixture is between 60 and 70 percent, the grade of the virgin binder shall be PG 52-28 or PG 58-28.
Shingles shall be ground to 3/8-inch minus.
Higher percentages of recycled materials Less virgin binder in the mixes Dryer looking mixes Rut resistant roadways Fatigue cracks earlier?
Is there a limit on recycled materials? Contractors attempted to run up to 12% RAS
Changed design air voids to 3.5% Increased VMA requirements: Bit Base 13.0% BP-1 13.5% BP-2 14.0% (Surface Leveling)
50 gyration mix design was eliminated and
replaced with a 35 gyration mix design Requires a higher asphalt content
Corelok specific gravities were used in lieu of traditional AASHTO T 84/T 85
Gse values were variable 2.450 to 2.800 Could be impacted by reported asphalt content
No significant change in virgin binder content
in some areas, but some higher quality aggregates were used
𝐺𝐺𝐺𝐺𝐺𝐺 = 100−𝑃𝑃𝑃𝑃100𝐺𝐺𝐺𝐺𝐺𝐺−
𝑃𝑃𝑏𝑏𝐺𝐺𝑏𝑏
Pb = Percent binder in the shingles Gmm = Rice value of the shingles Gb = Specific gravity of the shingle binder
Gse is used as the Gsb during mix design
𝐺𝐺𝐺𝐺𝐺𝐺 = 100−𝑃𝑃𝑃𝑃100𝐺𝐺𝐺𝐺𝐺𝐺−
𝑃𝑃𝑏𝑏𝐺𝐺𝑏𝑏
Higher RAS asphalt content the higher the specific gravity
Higher specific gravity makes it easier to meet the VMA requirements however it allows for lower asphalt content
14.1 14 14.2 14.1 14.3 12.6
11.8 11.3 11.9 11.4 12.5 11.5
11 11.7 11.1 12.4
11.4 10.8 11.5 10.9
0
2
4
6
8
10
12
14
16
20% RAP 30% RAP 40% RAP 30%FRAP
40%FRAP
VMA (%) Gse
Gsb (Ignition)
Gsb (Extract)
RAP Gmm
KDOT Requirement
Research on RAS and VMA increase High quality aggregates Fibers
Contractors were meeting the VMA requirements.
Virgin asphalt cement was decreased
Total asphalt contents was also decreased
20% effective binder replacement from RAS used in the surface leveling mixtures for the May and June contracts.
Not very many contracts - 2
Did not impact Superpave or other low volume route mix designs
Contractors got together in a morning session, worked together to provide recommended specification changes.
Met with MoDOT representatives after lunch and discussed the recommendations.
Adopted as a job special provision for the next bid letting.
Set Gsb of RAS at 2.600
Changed the gradation of the Surface Leveling mix design: 90-100% passing the 3/8” sieve.
Set Gsb of RAP at the Gsb of the virgin aggregates*
VMA minimum: 14.5%
MoDOT EPG 403.1.11
“The RAS fraction may be adjusted by a maximum of 3% from the original JMF.”
“The RAP fraction may be adjusted by a maximum of 15% from the original JMF.”
Variations in materials Mix design was based on materials sampled many
months in advance Asphalt content of reclaimed materials is different
than what was used during mix design
Mix was not performing as expected Allow for the removal of RAS in Fall
* Any time that adjustments are made to the plant percentages, including the hot bin percentages, the inspector and RE must be notified immediately. The resulting combined aggregate gradation of the adjusted mix must be within the master range for that particular type of mix (see Standard Specification Section 403.3.1). During production of the adjusted mix, the combined aggregate gradation must be within the limits of Standard Specification Section 403.5.1.1 or 403.5.1.2, whichever is applicable. If the cold feed settings have been adjusted, the composition of the mix has been changed. Therefore, the new bulk specific gravity of the combined aggregate (Gsb) must be calculated using the adjusted cold feed percentages so that the VMA can be accurately calculated during production. If an adjustment from the job mix is made, the contractor should be required to recalculate the porphyry/Non-carbonate percentage to assure that is still meets the contract requirements. A spreadsheet has been developed to assist in checking the contractor’s calculation. The spreadsheet can be found in the same folder on the V drive as the SuperPave spreadsheet. If the percentage of RAS or RAP is increased from the original JMF the percent virgin effective binder replacement (Pbv) should be recalculated to assure compliance with section 403.2.5 of the Standard Specifications. The Pbv should also be recalculated when the percent of binder in the RAP changes as determined by Section 403.19.3.
Must meet the master range gradation
Bulk Specific Gravity (Gsb) must be re-calculated
VMA will be impacted by Gsb change
Porphyry requirements must be maintained
The virgin effective binder replacement must be re-calculated when the RAP or RAS percentage changes
or when the percent of binder in the RAP changes
403.2.6.2 Reclaimed Asphalt Shingles. Reclaimed Asphalt Shingles (RAS) may be used in any mixture specified to use PG 64-22 in accordance with AASHTO PP 53 except as follows: When the ratio of virgin effective binder to total binder in the mixture is between 60 and 70 percent, the grade of the virgin binder shall be PG 52-28 or PG 58-28.
𝐺𝐺𝐺𝐺𝐺𝐺 = 100−𝑃𝑃𝑃𝑃100𝐺𝐺𝐺𝐺𝐺𝐺−
𝑃𝑃𝑏𝑏𝐺𝐺𝑏𝑏
Lower RAS asphalt content the lower the effective binder replacement
Allows more shingles to be used in the mix
www.modot.org/business/contractor_resources/forms.htm
Contribution of Binder from Recycled Materials
Effective Binder ComputationPb 5.70 Gmm 2.434 Gse 2.653 Type of StockpilePbmv 4.50 Gb 1.030 Pba 1.52 virgin - Quarried aggregate
Gsb 2.547 Pbe 4.18 reclaim - Reclaimed aggregate such as concrete, steel slag, wet bottom slag, chatRAP - Reclaimed asphalt pavement
Stockpile Type Ps Pbr Psr x Pbr Psmv Psmr Pbmr RAS - Reclaimed asphalt shingles1 virgin 80 76.412 RAS 2 25 0.50 1.43 0.473 RAP 18 4.3 0.77 16.45 0.7345678
100 94.29Pbe 4.18Pbev 2.98Psmv 76.41Psr x Pbr 1.27Psmr 17.88Pbmr 1.20R 71
Pb - Percent total binder in mixturePsv(1,2,..) - Pecent stone by fraction for virgin or reclaimed aggregatePsr(1,2,..) - Pecent stone by fraction for RAP or RAS aggregatePbr(1,2,..) - Percent binder by fraction in RAP or RASPsmv(1,2,..) - Pecent stone by fraction for virgin or reclaimed aggregate by weight of total mixturePsmr(1,2,..) - Pecent stone by fraction for RAP or RAS aggregate by weight of total mixturePsmr - Pecent stone of RAP or RAS aggregate by weight of total mixturePbmr(1,2,..) - Percent binder by fraction in RAP or RAS by weight of total mixturePbmr - Percent binder of RAP or RAS by weight of total mixturePbmv - Pecent new binder by weight of total mixtureR - Percentage of new binder (Pbev) to total binder (Pbe)
Pbr1
Pbr2
RAS
RAP
Steel Slag
Limestone
Pbmv
Pbmr2
Pbmr1
Psmr1
Psmr2
Psr1
Psr2
Psv1
Psv2
Psmv1
Psmv2
Pb Pbr2
Pbr1
Psm
( )( )( )100/...100
100
332211
11 +×+×+×−
−×=
brsrbrsrbrsr
bsvsm v PPPPPP
PPP
( ))100/...)((100
100)100/(
332211
1111 +×+×+×−
−××−=
brsrbrsrbrsr
bbrsrsrsmr PPPPPP
PPPPP
...321 +++= smrsmrsmrsmr PPPP( )2
111 100
100 bbrsrbmr
PPPP −××=
...321 +++= bmrbmrbmrbmr PPPP
be
bev
PPR 100×
=
...321 +++= smvsmvsmvsmv PPPP
bmrbbmv PPP −=
17% RAP at 5% asphalt content
2% RAS at 25% asphalt content
Gmm = 2.434 Gsb = 2.547 Total Binder 5.77% Virgin Binder 4.5%
Contribution of Binder from Recycled Materials
Effective Binder Computation
Pb 5.77 Gmm 2.434 Gse 2.656 Pbmv 4.50 Gb 1.030 Pba 1.56
Gsb 2.547 Pbe 4.21
Stockpile Type Ps Pbr Psr x Pbr Psmv Psmr Pbmr 1 virgin 81 77.37 2 RAS 2 25 0.50 1.43 0.47 3 RAP 17 5 0.85 15.43 0.80 4 5 6 7 8
100 94.2
Pbe 4.21
Pbev 2.94
Psmv 77.4
Psr x Pbr 1.35
Psmr 16.9
Pbmr 1.27 R 70
27% RAP at 5% asphalt content
0% RAS
Gmm = 2.434 Gsb = 2.547
Contribution of Binder from Recycled Materials
Effective Binder Computation
Pb 5.77 Gmm 2.434 Gse 2.656 Pbmv 4.50 Gb 1.030 Pba 1.56
Gsb 2.547 Pbe 4.21
Stockpile Type Ps Pbr Psr x Pbr Psmv Psmr Pbmr 1 virgin 73 69.73 2 RAS 0 25 0.00 0.00 0.00 3 RAP 27 5 1.35 24.50 1.27 4 5 6 7 8
100 94.2 Pbe 4.21 Pbev 2.94 Psmv 69.7 Psr x Pbr 1.35 Psmr 24.5 Pbmr 1.27 R 70
We would still need to re-calculate Gsb We did remove virgin aggregate
Porphyry requirements would have to be checked if applicable
Gmm may change
27% RAP Mix Designed at 5% RAP asphalt content
Mix total asphalt content is 0.4% high Gmm dropped Low air voids
Contribution of Binder from Recycled Materials
Effective Binder Computation
Pb 6.17 Gmm 2.425 Gse 2.662 Pbmv 4.50 Gb 1.030 Pba 1.64
Gsb 2.547 Pbe 4.53
Stockpile Type Ps Pbr Psr x Pbr Psmv Psmr Pbmr
1 virgin 73 69.74 2 RAS 0 25 0.00 0.00 0.00 3 RAP 27 6.6 1.78 24.09 1.67 4 5 6 7
8
100 93.8
Pbe 4.53
Pbev 2.86
Psmv 69.7
Psr x Pbr 1.78
Psmr 24.1
Pbmr 1.67
R 63
Reduce virgin asphalt content by 0.4%
This is not a change to the mix design because you have not changed the total asphalt content
Contribution of Binder from Recycled Materials
Effective Binder Computation
Pb 5.78 Gmm 2.434 Gse 2.656 Pbmv 4.10 Gb 1.030 Pba 1.57
Gsb 2.547 Pbe 4.21
Stockpile Type Ps Pbr Psr x Pbr Psmv Psmr Pbmr
1 virgin 73 70.03 2 RAS 0 25 0.00 0.00 0.00 3 RAP 27 6.6 1.78 24.19 1.68 4 5 6 7
8
100 94.2
Pbe 4.21
Pbev 2.53
Psmv 70
Psr x Pbr 1.78
Psmr 24.2
Pbmr 1.68
R 60
Could have a dry looking mix
Could have a dry performing mix
By specification this mix would require an AASHTO M323 blending chart analysis
Mixtures containing a combination of RAS and RAP may have a 30 to 40 percent effective virgin replacement under the following conditions: (1) with a virgin binder grade change from a PG64-22 to a PG 58-28 or (2) with a combination of a PG64-22 binder and a rejuvenator provided testing demonstrates that a PG58-28 , meeting the requirements of AASHTO M320, is achieved.
Compaction Aid
Surfactant
Anti-Strip
Shingles are only part of the problem Grind size Meet current specification
Late season paving Moisture Temperatures WMA chemical admixtures can help
VMA requirements were a big part of the problems Increase VMA for low volume routes Gse calculations can inflate VMA RAS increases VMA
Watch your requirements when making field
adjustments
The asphalt cement that we are using today is not the same asphalt we were using 10 years ago MSCR Shale oil versus oil from Venezuelan coast Crude slates are changing rapidly
MoDOT and MAPA have a GREAT working relationship MoDOT and MAPA have a small Technical
Working Group that meets to “Talk Geek” Afternoon session has MoDOT and MAPA
contractors