Minnesota Department of Transportation Design-Build Introduction Program November 30, 2000 Ron...
-
Upload
jayden-craig -
Category
Documents
-
view
230 -
download
11
Transcript of Minnesota Department of Transportation Design-Build Introduction Program November 30, 2000 Ron...
Minnesota Department of Transportation
Design-Build Introduction Program
Design-Build Introduction Program
November 30, 2000November 30, 2000Ron Williams, PE
State Construction EngineerArizona Department of Transportation
Ron Williams, PEState Construction Engineer
Arizona Department of Transportation
Arizona’s New Design-Build Law and Experience
Purpose
The Arizona Department of Transportation Desires to Have the
Design-Build Process Available to Use Whenever an Opportunity or Need
Arises to Construct a Project Quickly to Reduce Public Inconvenience.
The Arizona Department of Transportation Desires to Have the
Design-Build Process Available to Use Whenever an Opportunity or Need
Arises to Construct a Project Quickly to Reduce Public Inconvenience.
Arizona Department of Transportation Design-Build Procurement and
Administration Policy
To establish the department’s process for procuring and administering the highway design or facility and construction
services within one contract. The process will clearly delineate all known data to keep the unknown risk transfer to the design-build
firm to a minimum, thereby producing the most economical project. The purpose of the process is to provide a substantial fiscal benefit
or accelerated delivery schedule for transportation projects.
Partnering — Working together to solve problems is a must for design-build to be successful.
To establish the department’s process for procuring and administering the highway design or facility and construction
services within one contract. The process will clearly delineate all known data to keep the unknown risk transfer to the design-build
firm to a minimum, thereby producing the most economical project. The purpose of the process is to provide a substantial fiscal benefit
or accelerated delivery schedule for transportation projects.
Partnering — Working together to solve problems is a must for design-build to be successful.
Why Use Design-Build?• Speed!! To Complete a Project Where There is Need
for Immediate Improvement
• Example:– Large Traffic Volume Increases– Safety– Area Growth– Over-Loaded Freeways
• Funding Must Be Available in the Five-Year Program for the Design-Build Contracting Method to Be Considered
• Speed!! To Complete a Project Where There is Need for Immediate Improvement
• Example:– Large Traffic Volume Increases– Safety– Area Growth– Over-Loaded Freeways
• Funding Must Be Available in the Five-Year Program for the Design-Build Contracting Method to Be Considered
Reasons for Design-Build
• Earlier Completion
• Permits Phase Work
• Allows Concurrent Operations
• Encourages Joint Contractor/Engineer Planning
• Permits Innovative Financing
• Single Source Responsibility
• Earlier Completion
• Permits Phase Work
• Allows Concurrent Operations
• Encourages Joint Contractor/Engineer Planning
• Permits Innovative Financing
• Single Source Responsibility
ADOT Project Scheduling Comparison
Initial Design Concept & EISInitial Design Concept & EIS Traditional (Design-Bid-Build)Traditional (Design-Bid-Build)DesignDesign
ROWROW
BidBid
Utility ClearanceUtility Clearance
ConstructionConstruction
Initial Design Concept & EISInitial Design Concept & EIS Select FirmSelect Firm
DesignDesign
ROWROW
Utility ClearanceUtility Clearance
ConstructionConstruction
Design-Build (Select-Design-Build)Design-Build (Select-Design-Build)
44 88 1212 1616MonthsMonths
Time Savings
Constraints and Threats to Design-Build
Lack of Experience and Expertise within Owner organizations to administer and manage this deliver
method, while supporting a “fast-track” Project Schedule.
Design-Build project delivery assigns new responsibilities to the contracting parties, and many Owner organizations
are not prepared to operate differently than they have under the Design-Bid-Build approach. Since the Design-
Builder is the Engineer of Record, he has some latitude to make changes in the design as long as it still meets
Project requirements as outlined in the Prime Contract.
Lack of Experience and Expertise within Owner organizations to administer and manage this deliver
method, while supporting a “fast-track” Project Schedule.
Design-Build project delivery assigns new responsibilities to the contracting parties, and many Owner organizations
are not prepared to operate differently than they have under the Design-Bid-Build approach. Since the Design-
Builder is the Engineer of Record, he has some latitude to make changes in the design as long as it still meets
Project requirements as outlined in the Prime Contract.
Constraints and Threats to Design-Build
Many Owners want total control over all those changes, and the right to impose their own standards on all design
that the Design-Builder may develop. This defeats the purpose of the Design-Build Approach.
In addition, it’s difficult for many Owner organizations to redirect their staff efforts toward supporting the Design-
Build. Design-Build must have close cooperation, a supportive environment and a risk sharing approach
between the Owner and the Design-Builder.
Many Owners want total control over all those changes, and the right to impose their own standards on all design
that the Design-Builder may develop. This defeats the purpose of the Design-Build Approach.
In addition, it’s difficult for many Owner organizations to redirect their staff efforts toward supporting the Design-
Build. Design-Build must have close cooperation, a supportive environment and a risk sharing approach
between the Owner and the Design-Builder.
Design-Build History
Studied and Modified Other Plans
• 2-Day Training — Design-Build Institute of America — ASU
• Maricopa County
• Florida, Utah, Michigan, New Jersey, Alaska, California and North Carolina
• AGC and American Consulting Engineers
• 2-Day Training — Design-Build Institute of America — ASU
• Maricopa County
• Florida, Utah, Michigan, New Jersey, Alaska, California and North Carolina
• AGC and American Consulting Engineers
Design-Build Authorization
Senate Bill 1253
ARS 28 1812
One ADOT Project Pima County
One ADOT Project Maricopa County
One Project Maricopa County
1996
Senate Bill 1253
ARS 28 1812
One ADOT Project Pima County
One ADOT Project Maricopa County
One Project Maricopa County
1996
Process Development(Use Existing Documents Whenever
Possible)• Design Scoping Document• Revised Standard Specifications General
Conditions• Revised Contract Documents• Technical (Section 200-1000) Standard
Specifications• Project Specific Special Provisions
• Design Scoping Document• Revised Standard Specifications General
Conditions• Revised Contract Documents• Technical (Section 200-1000) Standard
Specifications• Project Specific Special Provisions
Method/Prescriptive Specs
Performance Specs
Design-Build is a Combination of Both
Design-Build is a Combination of Both
Design-BuildDevelopment Team
Deputy State Engineer, OperationsAssistant State Engineer, Construction Group
Assistant State Engineer, Design GroupAssistant State Engineer, Valley Project Management Group
Assistant State Engineer, Statewide Project Management GroupAssistant State Engineer, Support Services Group
Manager, Engineering Consultant ContractsManager, Contracts & Specifications Services
Project Manager, Tucson DistrictProject Manager, Phoenix District
Assistant Attorney General, ADOT LegalAssociated General Contractors
Arizona Consulting engineer AssociationFederal Highway Administration
Deputy State Engineer, OperationsAssistant State Engineer, Construction Group
Assistant State Engineer, Design GroupAssistant State Engineer, Valley Project Management Group
Assistant State Engineer, Statewide Project Management GroupAssistant State Engineer, Support Services Group
Manager, Engineering Consultant ContractsManager, Contracts & Specifications Services
Project Manager, Tucson DistrictProject Manager, Phoenix District
Assistant Attorney General, ADOT LegalAssociated General Contractors
Arizona Consulting engineer AssociationFederal Highway Administration
Features of 1998 Arizona Design-Build Law
Projects Allowed:• Department of Transportation 3
• Department of Administration 2
• Counties/Cities > 330,000 1 each
Controls:• Single Project
• Minimum Size — 10 Million Dollars
• Owner Obtains Right-of-Way
• Owner Obtains Environmental Document
• Owner Obtains Railroad Approval of Concept Prior to Award
Projects Allowed:• Department of Transportation 3
• Department of Administration 2
• Counties/Cities > 330,000 1 each
Controls:• Single Project
• Minimum Size — 10 Million Dollars
• Owner Obtains Right-of-Way
• Owner Obtains Environmental Document
• Owner Obtains Railroad Approval of Concept Prior to Award
HB 2340 2000 Design-Build Law Modifications
• Allows two Design-Build Contracts per year. Must be a single specific project with minimum cost of forty (40) million dollars.
• All projects must be awarded by June 30, 2007.
• Requires annual report to legislature on design-build costs and benefits
• Must announce technical proposal score for each proposer.
• Specifies at least three But not more than five firms to be on the short list.
• Mandates the Department to pay a stipend of two-tenths of one percent to each unsuccessful proposer. Unsuccessful proposer may retain his proposal and waive stipend.
• Allows two Design-Build Contracts per year. Must be a single specific project with minimum cost of forty (40) million dollars.
• All projects must be awarded by June 30, 2007.
• Requires annual report to legislature on design-build costs and benefits
• Must announce technical proposal score for each proposer.
• Specifies at least three But not more than five firms to be on the short list.
• Mandates the Department to pay a stipend of two-tenths of one percent to each unsuccessful proposer. Unsuccessful proposer may retain his proposal and waive stipend.
Arizona’s Alternative Contracting Legislation
HB 2340
2000 Legislative Session
Internet Addresshttp://www.azleg.state.az.us/legtext/44leg/2r/laws/0135.htm
HB 2340
2000 Legislative Session
Internet Addresshttp://www.azleg.state.az.us/legtext/44leg/2r/laws/0135.htm
Design-Build Projects
I-10/Cortaro RoadInterchange Reconstruction
Bid July 1997 $2,760,500
Complete August 1998 $3,714,75*
Bid July 1997 $2,760,500
Complete August 1998 $3,714,75*
Completed four months ahead of conventional Design-Bid-Build
Completed four months ahead of conventional Design-Bid-Build
Developer contributed $500,000 to cost of project.
*Encountered large areas of unstable subgrade that need to be replaced.
Developer contributed $500,000 to cost of project.
*Encountered large areas of unstable subgrade that need to be replaced.
1st Project
Tucson Lessons Learned
• Public Involvement Delays (Lost Three Weeks)– Two-way vs. One-way– Frontage Roads
• Right-of-Way Delays — Resolved by Working Together
• Reluctance of Subcontractors to Use Incomplete Plans without Quantities
• Finished Early By 120 Days
• Public Involvement Delays (Lost Three Weeks)– Two-way vs. One-way– Frontage Roads
• Right-of-Way Delays — Resolved by Working Together
• Reluctance of Subcontractors to Use Incomplete Plans without Quantities
• Finished Early By 120 Days
Cost Analysis
Utility and Archeological Investigation $215,948
Wet Subgrade (Changed Condition $554,640
$770,588
Scope and Design Changes 5.7% Over Bid $183,627
Eleven Subcontractors Involved
Utility and Archeological Investigation $215,948
Wet Subgrade (Changed Condition $554,640
$770,588
Scope and Design Changes 5.7% Over Bid $183,627
Eleven Subcontractors Involved
Phoenix Black Canyon FreewayI-17 — Thomas to Peoria Corridor
ImprovementAdd an HOV Lane for 7.5 Miles
• Add Auxiliary Lanes at Interchanges
• Reconstruct and Widen Camelback Road Bridge
• Reconstruct and Widen Glendale Avenue Bridge
• Design and Install Lighting and Signs
• Design and Install Freeway Management System
• Approximate Cost — $75 Million
• Anticipated Completion — September 2000*
*One year earlier than ADOT schedule
Add an HOV Lane for 7.5 Miles
• Add Auxiliary Lanes at Interchanges
• Reconstruct and Widen Camelback Road Bridge
• Reconstruct and Widen Glendale Avenue Bridge
• Design and Install Lighting and Signs
• Design and Install Freeway Management System
• Approximate Cost — $75 Million
• Anticipated Completion — September 2000*
*One year earlier than ADOT schedule
2nd Project
I-17 History and Plan
Thomas Road Bridge 1992Indian School Bridge 1996Dunlap Bridge 1997Northern Bridge 1998Bethany Bridge 1998I-17 Widening at Thomas 1995I-17 Widening Peoria North 1996Camelback and Glendale Bridges 2001Remaining Widening 2004
Thomas Road Bridge 1992Indian School Bridge 1996Dunlap Bridge 1997Northern Bridge 1998Bethany Bridge 1998I-17 Widening at Thomas 1995I-17 Widening Peoria North 1996Camelback and Glendale Bridges 2001Remaining Widening 2004
12 Years — Too Long!! Let’s Get Done
12 Years — Too Long!! Let’s Get Done
Reasons for Selecting This Project
• Solves Serious Congestion Problem
• Increases Capacity by 25-30%
• Completes Reconstruction of I-17 Three Years Sooner than Current Plan
• Construction and Design Cost Savings Due to Combining Projects and Shortening Time
• Allows ADOT to Consider Additional HOV Lanes on Other Freeways Sooner
• Solves Serious Congestion Problem
• Increases Capacity by 25-30%
• Completes Reconstruction of I-17 Three Years Sooner than Current Plan
• Construction and Design Cost Savings Due to Combining Projects and Shortening Time
• Allows ADOT to Consider Additional HOV Lanes on Other Freeways Sooner
Phoenix I-17 Lessons Learned
• Teamwork is a Must
• Classification of Roles
• Preferable to Co-House Team
• Only 176 Change Orders
• 4.8 Percent Overrun (3% Value Added by Owner
• Only Two Minor Issue Escalations• State Estimate 900 Days
Completion 603 Days
• Successful Use of Incentives
• Teamwork is a Must
• Classification of Roles
• Preferable to Co-House Team
• Only 176 Change Orders
• 4.8 Percent Overrun (3% Value Added by Owner
• Only Two Minor Issue Escalations• State Estimate 900 Days
Completion 603 Days
• Successful Use of Incentives
$1.7 Million Dollars Motorist Delay Savings$1.7 Million Dollars Motorist Delay Savings
Design-Build Typical Team Composition
ContractorContractorPrime Subcontractors
1 2 (P)
1 5 (2P)
1 - (1P)
1 -
1 2 (P)
1 1 (P)
Prime Subcontractors
1 2 (P)
1 5 (2P)
1 - (1P)
1 -
1 2 (P)
1 1 (P)
Design FirmsDesign FirmsPrime Subcontractors
1 4
1 -
1 3
1 -
1 5
1 3
Prime Subcontractors
1 4
1 -
1 3
1 -
1 5
1 3
On the I-17 Project, 36 percent of work is by subcontractors
70 Subcontractors11 Engineering Firms
On the I-17 Project, 36 percent of work is by subcontractors
70 Subcontractors11 Engineering Firms
I-17 Design-Build Incentive Performance Summary
Superior Public Relation
Quality Workmanship
Auxiliary Lanes
Early Median Lighting
Camelback T.I. In 180 Days
Glendale T.I. In 180 Days
AR-ACFC Smoothness
PCCP Strength & Thickness
$150,000
$260,000
$400,000
$300,000
$600,000
$600,000
$1,162,909
$417,989
$150,000
$241,371
$400,000
$300,000
$600,000
$600,000
$487,599
$271,807
IncentivePotential Amount
Available Amount Earned
100%
93%
100%
100%
100%
100%
42%
65%
% of Available
Change Order Log
11a2345677a7b89101111a11b1213141516
#
Shoulder widenings in depressed roadway (Northern & Dunlap approved) Seg. 3Shoulder widenings in depressed roadway Seg.1 & 2 (includes slope paving)Reconstruct NB offramp at Thomas and NB HOV Lane Start I-10/ThomasTemporary concrete barrierFrontage Rd work south of Dunlap/27th Ave (NB & SB) & Dunlap TI WorkIncrease in gross receipt tax to 7%Change in traffic control device - barricade with light to large vertical panelGlendale Bridge damage SB repair #1 -Truesdell girder repairGlendale Bridge SB repair #2Glendale Bridge slab repair - south halfCamelback City of Phoenix improvementsVMS relocation (change order complete ‘no cost’)Full freeway lighting specification changeKiewit & Sundt previous I-17 project additional work items & misc. itemsNorthern additional B22.70 fence for wing extensionsSawcut/remove SPUI ramp wedge48” fenceNB Indian School catch basin repairSpall repair under existing asphalt rubberMaryland pedestrian bridge pierLedge beam removal at Bethany, Northern & Dunlap
Approximate Total
Description
$628,075.00$1,777,361.00
$895,513.00$45,468.00
$128,331.00$99,174.00
$68,718.00$4,956.50$4,997.18
$304,604.00$0.00$0.00
$165,870.13$3,606.47$9,162.78
$86,472.60$21,802.89
$100,527.64
$4,364,639.99
Value
Finalized C.O. 5Finalized C.O. 9Finalized C.O. 12Finalized C.O. 3Finalized C.O. 11Finalized C.O. 7Finalized C.O. 1Finalized C.O. 6Finalized L.A. 3Finalized L.A. 2Finalized C.O. 10Finalized C.O. 2Finalized C.O. 4Finalized C.O. 13Finalized L.A. 1Finalized C.O. 8Finalized C.O. 13Finalized F.A. 1F.A. 2F.A. 3Finalized C.O. 14
Status/Comments
16 Change Orders — 4.9% — $2 Million Value Added16 Change Orders — 4.9% — $2 Million Value Added
SR 68 Davis Dam - Kingman HighwayBullhead City to Golden Valley
• Convert Two-Lane to Four-Lane Highway
• Approximate Cost $45 Million
• Construction Start April 2000
• Anticipated Completion November 2001
• Original Completion July 2004
• Convert Two-Lane to Four-Lane Highway
• Approximate Cost $45 Million
• Construction Start April 2000
• Anticipated Completion November 2001
• Original Completion July 2004
3rd Project
SR 68Davis Dam - Kingman Highway
Kiewit Western/Parsons Trans
Pulice/AGRA
Sundt/Granite/URS Greiner
Total Points
State Estimate
119.7
105.7
114.6
138
$42,118,780
$38,828,846
$53,701,360
$39,391,360
Design-Build FirmTechnical
Proposal Score Price Proposal
$42,118,780119.7
$38,828,846105.7
$53,701,360114.6
PriceTech. Proposal
351,869
367,349
468,598
BestValue
Seven Firms Submitted RFQsSeven Firms Submitted RFQs
US 60/Superstition Freeway
• Location: Jct I-10 — Val Vista Road
• Length: 13.5 Miles
• Features– I-10 — US 60 HOV Freeway to Freeway Interchange– Median HOV Lanes from I-10 — Val Vista Road (EB & WB)– Two Additional General Use Lanes from Loop 101 — Val Vista
Road– Auxiliary Lanes Between Interchanges
• Total Cost: $255 Million$200 Million in FY 00-04 — five-year program
GNS Loans — $100 Million due to 30-36 month construction time
• Location: Jct I-10 — Val Vista Road
• Length: 13.5 Miles
• Features– I-10 — US 60 HOV Freeway to Freeway Interchange– Median HOV Lanes from I-10 — Val Vista Road (EB & WB)– Two Additional General Use Lanes from Loop 101 — Val Vista
Road– Auxiliary Lanes Between Interchanges
• Total Cost: $255 Million$200 Million in FY 00-04 — five-year program
GNS Loans — $100 Million due to 30-36 month construction time
4th Project
US 60/Superstition Freeway
• Design-Bid-Build Process:– Require minimum four separate construction projects– Require 18 month design time, then 18-24 month
construction time per project– Last segment would advertise in FY04 with
completion in FY06
• Design-Bid-Build Process:– Require minimum four separate construction projects– Require 18 month design time, then 18-24 month
construction time per project– Last segment would advertise in FY04 with
completion in FY06
Using Design-Build Process Saves a Minimum of 1 1/2 Years
Using Design-Build Process Saves a Minimum of 1 1/2 Years
Design-Bid PackageProposal Contents
A Proposal ProcessA-IPublic Advertisement
A-II Introduction
B Request for Qualifications
C Request for ProposalC-I Final Selection Process
C-II General Requirements
C-III Design Scope of Work
C-IV Technical Specifications
Standard Stored Specs & Special Provisions
(Section100, General Provisions of Specifications have been modified to fit the Design-Build Process)
D Contract Documents
A Proposal ProcessA-IPublic Advertisement
A-II Introduction
B Request for Qualifications
C Request for ProposalC-I Final Selection Process
C-II General Requirements
C-III Design Scope of Work
C-IV Technical Specifications
Standard Stored Specs & Special Provisions
(Section100, General Provisions of Specifications have been modified to fit the Design-Build Process)
D Contract Documents
Request for Qualifications Format
US 60 Design-Build ProjectPart A Introductory Letter N/A 2
Part B Evaluation Criteria 28
1. Project Understanding& Approach 25
2. Design-Build Project Team 25
3. Proposers Capabilities 25
4. Quality Program 20
5. Safety Program 5
Part C Supportive Information N/A 10
Part D Design-Builder Proposer’sInformation Form N/A 5
Part E Work History Form N/A 5
Total 100 50
Part A Introductory Letter N/A 2
Part B Evaluation Criteria 28
1. Project Understanding& Approach 25
2. Design-Build Project Team 25
3. Proposers Capabilities 25
4. Quality Program 20
5. Safety Program 5
Part C Supportive Information N/A 10
Part D Design-Builder Proposer’sInformation Form N/A 5
Part E Work History Form N/A 5
Total 100 50
Technical Proposal Evaluation Criteria Design-Build Process
1. Responsiveness to RFP 75 Points• Design Management 10 Points• Quality Program 20 Points• Design Features 15 Points• Structure Features 10 Points• Overall Schedule & Milestones 6 Points• Public Relations Plan 5 Points• Geotechnical Investigation 3 Points• Lighting 2 Points• Signing & Pavement Marking 2 Points• Aesthetics & Landscaping 2 Points
2. Innovation 8 Points• Constructability 5 Points• Miscellaneous 3 Points
3. Construction 35 Points• Construction Management 10 Points• Maintenance & Protection of Traffic 10 Points• Utility Relocation Plans 85 Points• Safety Plan 70 Points
1. Responsiveness to RFP 75 Points• Design Management 10 Points• Quality Program 20 Points• Design Features 15 Points• Structure Features 10 Points• Overall Schedule & Milestones 6 Points• Public Relations Plan 5 Points• Geotechnical Investigation 3 Points• Lighting 2 Points• Signing & Pavement Marking 2 Points• Aesthetics & Landscaping 2 Points
2. Innovation 8 Points• Constructability 5 Points• Miscellaneous 3 Points
3. Construction 35 Points• Construction Management 10 Points• Maintenance & Protection of Traffic 10 Points• Utility Relocation Plans 85 Points• Safety Plan 70 Points
Project Team Organization
I-17 Design-Build Team
Project Managers:Terry Bourland - Development
John Akin - Construction
QualityAllan Samuels
QualityAllan Samuels
PartneringGinger Murdough
PartneringGinger Murdough
MaterialsGeorge Way
MaterialsGeorge Way
AGCAGC
City of PhoenixCity of Phoenix
StructuresJim Pyne
StructuresJim Pyne
FMSManny Agah
FMSManny Agah
Traffic EngineeringRichard Moeur
Traffic EngineeringRichard Moeur
UtilitiesVern Pagel
Brad Mortensen
UtilitiesVern Pagel
Brad Mortensen
Right-of-WayDave Edwards
Pete Main
Right-of-WayDave Edwards
Pete Main
LegalJoe Acosta
LegalJoe Acosta
ACEAACEA
ECSRon Thomas
ECSRon Thomas
FHWABill Vachon
FHWABill Vachon
C & SRichard Murphy
C & SRichard Murphy
Consultant EngineersDMJM
Kimley-Horn
Consultant EngineersDMJM
Kimley-Horn Sponsors:Ron Williams - Process/Facilitator
Dan Lance - ConstructionSteve Jimenez - Development
ADOT Design-Build Organization
ADOT Develop ScopeADOT Develop Scope ADOT Oversight & QA CheckingADOT Oversight & QA Checking
Design-BuildDesign-Build
ConstructConstructDevelopDevelop
Develop ScopeThrough
Use of Consultants
Develop ScopeThrough
Use of Consultants
ResponsibilitiesResponsibilities
Design-Build Short & Long-Term Organization for I-17 Corridor
ProjectState EngineerState Engineer
Project Manager
Terry Bourland
Project Manager
Terry Bourland
District ConstructionDistrict Construction
Resident Engineer
John Akin
Resident Engineer
John Akin
Technical GroupsTechnical Groups
Design-Build Process
Ron Williams
Design-Build Process
Ron Williams
ADOT DevelopmentADOT Development
Technical GroupsTechnical Groups
ADOT Design-Build TeamPossible Issue Resolution Structure
State EngineerState Engineer
Project Manager
Terry Bourland
Project Manager
Terry Bourland
Design-Build Process Manager
Ron Williams
Design-Build Process Manager
Ron Williams
ADOT Development GroupsTechnical Manager
ADOT Development GroupsTechnical Manager
Granite-SundtManagement Board*
Granite-SundtManagement Board*
Or ADOTManagement Team
Or ADOTManagement Team
District Engineer
Dan Lance
District Engineer
Dan LanceProject DirectorProject Director
Daily OperationsDaily Operations
District ConstructionTechnical Manager
District ConstructionTechnical Manager
Development Technical Leader
Development Technical Leader
Eric CroweEric Crowe
Construction Technical Leader
Construction Technical Leader
John AkinJohn Akin
Design ManagerDesign Manager Quality ManagerConstruction
Quality ManagerConstruction
ConstructionManager
ConstructionManager
*Granite Sundt in Yellow*Granite Sundt in Yellow
Project Manager coordinates all activities within scope, schedule, budget, parameters.Project Manager coordinates all activities within scope, schedule, budget, parameters.
EscalationEscalation
Design Team Coordination with Construction and Maintenance
StaffTuesdays (AM)Tuesdays (AM)
Design Team MeetingD-B Project Manager
Design ManagerDeputy Design ManagerChief Roadway EngineerDesign Quality Manager
Construction Quality ManagerTask Leaders (as req’d)ADOT PM & Other Reps
Design Status Progress
Design Team MeetingD-B Project Manager
Design ManagerDeputy Design ManagerChief Roadway EngineerDesign Quality Manager
Construction Quality ManagerTask Leaders (as req’d)ADOT PM & Other Reps
Design Status Progress
Tuesdays (PM)Tuesdays (PM)
Design/Construction MeetingDesign Manager
Deputy Design ManagerTask Leaders (as req’d
Construction Project Engineer
Updated Design Schedule
Design/Construction MeetingDesign Manager
Deputy Design ManagerTask Leaders (as req’d
Construction Project Engineer
Updated Design Schedule
Wednesday (PM)Wednesday (PM)
Construction Schedule MeetingD-B Project Manager
Construction Quality ManagerConstruction Manager
Construction Project Engineer(and staff)
Field SupervisorPublic Relations Manager
Update 5-WeekConstruction Schedule
Construction Schedule MeetingD-B Project Manager
Construction Quality ManagerConstruction Manager
Construction Project Engineer(and staff)
Field SupervisorPublic Relations Manager
Update 5-WeekConstruction Schedule
Thursdays (AM)Thursdays (AM)
Design-Build Schedule/Quality MeetingADOT Resident EngineerADOT Project Manager
ADOT Other Reps (as req’d)D-B Project ManagerConstruction Manager
Construction Quality ManagerSafety ManagerDesign Manager
DPS/Law EnforcementConstruction Project Engineer
2 Superintendents1 Field Engineer
Design-Build Schedule/Quality MeetingADOT Resident EngineerADOT Project Manager
ADOT Other Reps (as req’d)D-B Project ManagerConstruction Manager
Construction Quality ManagerSafety ManagerDesign Manager
DPS/Law EnforcementConstruction Project Engineer
2 Superintendents1 Field Engineer
Thursdays (PM)Thursdays (PM)
ADOT Public Relations MeetingADOT District PR RepD-B Project Manager
Public Relations ManagerDesign Manager
Construction Project ManagerMOT Engineer
Regional Traffic Engineer
Updated Public Informationfor Release on Friday
ADOT Public Relations MeetingADOT District PR RepD-B Project Manager
Public Relations ManagerDesign Manager
Construction Project ManagerMOT Engineer
Regional Traffic Engineer
Updated Public Informationfor Release on Friday
I-17 Design-Build Plan Review and Release Process
Plan Developed by Lead DisciplinePlan Developed by Lead Discipline
Plan Routed to All Other Technical Disciplines and Construction StaffPlan Routed to All Other Technical Disciplines and Construction Staff
Plan Revised by Lead DisciplinePlan Revised by Lead Discipline
Constructibility InputConstructibility Input Plan Developed by Lead DisciplinePlan Developed by Lead Discipline
50% Comment Resolution Meeting50% Comment Resolution Meeting
Plan Revised by Lead DisciplinePlan Revised by Lead Discipline
80% Comment Resolution Meeting80% Comment Resolution Meeting
Audit of QC DocumentationAudit of QC Documentation
Design Team Manager Approves for ConstructionDesign Team Manager Approves for Construction
Construction Project Engineer Releases Plan for ConstructionConstruction Project Engineer Releases Plan for Construction
ADOT Attendance & CommentADOT Attendance & Comment
ADOT Attendance & CommentADOT Attendance & Comment
Constructibility InputConstructibility Input
Utility Relationships
Utilities in the Design-Build Process
1. ADOT Locates Utilities and Probable Conflicts. Through June 1998
2. ADOT Obtains New R/W on Glendale Avenue and Camelback Road (10’ to12’).
No R/W Needed for I-17. Through December 1998
3. ADOT Determines Prior Rights Where Possible. Through December 1998
4. Design-Build Firm Starts Design From Concept Report.
Through January 1999
5. Design-Build Firm Determines Utility Conflicts as First Work Item.
Through March 1999
1. ADOT Locates Utilities and Probable Conflicts. Through June 1998
2. ADOT Obtains New R/W on Glendale Avenue and Camelback Road (10’ to12’).
No R/W Needed for I-17. Through December 1998
3. ADOT Determines Prior Rights Where Possible. Through December 1998
4. Design-Build Firm Starts Design From Concept Report.
Through January 1999
5. Design-Build Firm Determines Utility Conflicts as First Work Item.
Through March 1999
Relocation Process
• Design-Build Firm Has Responsibility to Adjust and Relocate Utilities as Needed
• ADOT Will Pay to Move Utilities with Prior Rights
• Utilities Will Pay for Betterment
• Permitted Utilities Will Coordinate Their Move with Design-Build Firm
• Design-Build Firm Has Responsibility to Adjust and Relocate Utilities as Needed
• ADOT Will Pay to Move Utilities with Prior Rights
• Utilities Will Pay for Betterment
• Permitted Utilities Will Coordinate Their Move with Design-Build Firm
Working Relationships
• Design by Design-Build Firm
• Design by Utility Companies
• Relocation by Design-Build Firm
• Relocation by Utility or Its Agent Prior to Road Construction
• Relocation by Utility or Its Agent During Construction
• Design by Design-Build Firm
• Design by Utility Companies
• Relocation by Design-Build Firm
• Relocation by Utility or Its Agent Prior to Road Construction
• Relocation by Utility or Its Agent During Construction
Selection of Best Value Offer for Design-Build
Projects
Selection Process — Two Step
Request for Qualifications — Team
Request for Proposal — Technical
Request for Qualifications — Team
Request for Proposal — Technical
Best Value Proposal
Cost
Technical Score
Cost
Technical Score
SR 68 Evaluation PanelsShort List Panel
1. George Wallace, PE Pre-Design 21+ years with ADOT, PE for 23 yearsPre-Design Section Manager
2. Debra Brisk, PE Kingman District 16 years with ADOT, PE for 12, yearsKingman District Engineer
3. Julie Trunk FHWA 11 years with FHWA, non-PE position,materials background
4. Dee Bowling EnvironmentalPlanning
10 years with ADOT, non-PE position,environmental background
5. Mike Bluff AGC 22 years as a contractor, non-PE position,24 years in construction
Panel MemberPanel Member SectionSection QualificationsQualifications
SR 68 Evaluation PanelsTechnical Proposal Panel
1. Bahram Dariush, PE S/W ProjectManagement
15 years with ADOT, PE for 4 years,SR 68 D-B Design Project Manager
2. Jennifer Livingston,PE, BSCE, MSE
Kingman District 4 years with ADOT, PE for 1 year,SR 68 D-B Resident Engineer
3. John Lawson, PE Materials Section 29 years with ADOT, PE for 25+ years,materials/geotechnical background
4. Shafi Hasan, PE Bridge Group 9 years with ADOT, PE for 16+ years,structures background
5. Tay Dam FHWA 5 years with ADOT, non-PE position,environmental background
Panel MemberPanel Member SectionSection QualificationsQualifications
6. Arif Kazmi, PE Traffic Group 16 years with ADOT, PE for 14 years,traffic background
7. Art Brooks, PE ACEA 18 years as an owner of a design firm,PE for 26 years
SR 68 Design-Build Project
Panel#1
Panel#1
Panel#2
Panel#2
Panel#3
Panel#3
Panel#4
Panel#4
Panel#5
Panel#5
Panel#6
Panel#6
Panel#7
Panel#7FirmFirm AvgAvg RankRank
1. Kiewit Western 105 137 124 130 115 124 103 119.7 1
3. Sundt/Granite 93 115 117 131 122 120 104 114.6 2
2. Pulice 81 103 99 122 106 115 114 105.7 3
Overall Ranking by Score SelectionOverall Ranking by Score Selection
Panel#1
Panel#1
Panel#2
Panel#2
Panel#3
Panel#3
Panel#4
Panel#4
Panel#5
Panel#5
Panel#6
Panel#6
Panel#7
Panel#7FirmFirm AvgAvg RankRank
1. Kiewit Western 1 1 1 2 2 1 3 1.6 1
3. Sundt/Granite 2 2 2 1 1 2 2 1.7 2
2. Pulice 3 3 3 3 3 3 1 2.7 3
Overall Ranking by Rank Order SelectionOverall Ranking by Rank Order Selection
SR 68 Design-Build Project
Panel#1
Panel#1
Panel#2
Panel#2
Panel#3
Panel#3
Panel#4
Panel#4
Panel#5
Panel#5
Panel#6
Panel#6
Panel#7
Panel#7Evaluation CriteriaEvaluation Criteria AvgAvg
#1Frim#1
Frim
1. Responsiveness to RFP 71 43 58 49 60 54 59 60 54.7 62.7 -8.0
2. Innovation 32 17 19 24 29 25 26 25 23.6 27.0 -3.4
3. Construction 30 19 23 21 29 23 25 25 23.6 26.0 -2.4
4. Oral Interviews 5 2 3 5 4 4 5 4 3.9 4.0 -0.1
Maximum Possible Points (RFP) 138 81 103 99 122 106 115 114 105.7 119.7 -14.0
Rank Orders 3 3 3 3 3 3 1
MaxPtsMaxPts D
iffe
ren
ceD
iffe
ren
ce
Firm: Pulice Rank: 3Representative:
Panel Composition:1 Spmg - Phx2 Kingman District3 Bridge Group4 Materials Group5 ACEA6 FHWA7 Traffic
Firm: Pulice Rank: 3Representative:
Panel Composition:1 Spmg - Phx2 Kingman District3 Bridge Group4 Materials Group5 ACEA6 FHWA7 Traffic
Selection DebriefingSelection Debriefing
SR 68 Design-Build Project
Panel#1
Panel#1
Panel#2
Panel#2
Panel#3
Panel#3
Panel#4
Panel#4
Panel#5
Panel#5
Panel#6
Panel#6
Panel#7
Panel#7Evaluation CriteriaEvaluation Criteria AvgAvg
1. Responsiveness to RFP 71 55 70 64 66 62 65 57 62.7
2. Innovation 32 22 32 30 30 25 28 22 27.0
3. Construction 30 24 30 27 29 24 26 22 26.0
4. Oral Interviews 5 4 5 3 5 4 5 2 4.0
Maximum Possible Points (RFP) 138 105 137 124 130 115 124 103 119.7
Rank Orders 1 1 1 2 2 1 3
Selection DebriefingSelection Debriefing
MaxPtsMaxPts
Firm: Kiewit Western Rank: 1Representative:
Panel Composition:1 Spmg - Phx2 Kingman District3 Bridge Group4 Materials Group5 ACEA6 FHWA7 Traffic
Firm: Kiewit Western Rank: 1Representative:
Panel Composition:1 Spmg - Phx2 Kingman District3 Bridge Group4 Materials Group5 ACEA6 FHWA7 Traffic
Request for Qualifications Format
US 60 Design-Build Project
State Estimate
Kiewit Western Co.
Pulice Construction, Inc.
Sundt/Granite, J.V
BidderBidder
Technical Proposal
Score (TPS)
Technical Proposal
Score (TPS)
PriceProposal
PriceProposal
Adjusted Score(AS)=
(PP)(TPS)
Adjusted Score(AS)=
(PP)(TPS)
N/A
119.70
105.70
114.60
$39,391,360
$42,118,780
$38,828,846
$53,701,360
N/A
351,869
367,349
468,598
Bid Opening: 06/09/00Bid Opening: 06/09/00
Value Items in Kiewit Proposal
• Five Segments Permit Early Opening
• Relocate Bridge to Construct a Square, Not a Skewed Bridge
• Independent Roadways; Super Elevation Improves Drainage
• Grade Modification at Union Pass Crest Allows 60 MPH Roadway Instead of 45 MPH– Improved Vertical Site Distance– Improved Horizontal Sight Distance
• Five Segments Permit Early Opening
• Relocate Bridge to Construct a Square, Not a Skewed Bridge
• Independent Roadways; Super Elevation Improves Drainage
• Grade Modification at Union Pass Crest Allows 60 MPH Roadway Instead of 45 MPH– Improved Vertical Site Distance– Improved Horizontal Sight Distance
Review Comments — SR 68Kiewit Proposal
• In-depth understanding
• Most innovative proposal
• Stressed BLM relationships
• Discussed every item
• Quite innovative in design and construction matters
• Complete 4 months early. Stop work on Friday at noon
• Solid construction management approach
• Clearly understood the impact to traveling public is a major issue
• In-depth understanding
• Most innovative proposal
• Stressed BLM relationships
• Discussed every item
• Quite innovative in design and construction matters
• Complete 4 months early. Stop work on Friday at noon
• Solid construction management approach
• Clearly understood the impact to traveling public is a major issue
Review Comments — SR 68Pulice/AGRA Proposal
• A lot of unanswered questions
• Would complete 6 months early
• All 13 miles under construction at the same time — 2 segments
• Constructability very brief
• Organizational plan not clear
• Lacking technical response in panel interview. Answers unclear
• A lot of unanswered questions
• Would complete 6 months early
• All 13 miles under construction at the same time — 2 segments
• Constructability very brief
• Organizational plan not clear
• Lacking technical response in panel interview. Answers unclear
Bid TabulationsI-17 Design-Build Project
Engineer
J.D. Abrams, Inc.
Granite/Sundt
Meadow Valley/Parsons Brinkerhoff
BidderBidderTechnical
ScoreTechnical
Score
N/A
85.30
88.10
85.90
Proposed Days
Proposed Days
910
700
609
800
“A” = PriceProposal
“A” = PriceProposal
$64,749,450
$89,917,800
$79,729,000
$93,017,800
“B” = TimeValue
“B” = TimeValue
$14,560,000
$11,200,000
$9,744,000
$12,800,000
“A+B”=Adjusted Price
“A+B”=Adjusted Price
$79,309,450
$101,117,800
$89,473,000
$105,817,800
“A+B”/TPS=Adjusted Score
“A+B”/TPS=Adjusted Score
N/A
$1,185,437
$1,015,584
$1,231,871
Bid Opening: 11/13/98Bid Opening: 11/13/98
Value Items in Granite/Sundt I-17 Proposal
• Extra Widening for Typical Section
• Improved NB Transition to H.O.V.
• Clearly Defined Organization
• Outside — In Approach Permitted Completion One Year Early
• Extra Widening for Typical Section
• Improved NB Transition to H.O.V.
• Clearly Defined Organization
• Outside — In Approach Permitted Completion One Year Early
Cortaro Road Design-Build
1 892 873 874 835 816 807 71
Average87.6
84.1to get in
I-17 Design-Build
1 882 883 874 845 75
Average87.6
84.1to get in
1 88.62 81.83 74.4
1 88.12 85.93 85.3
SR 68 Design-Build
1 912 903 894 875 836 817 74
Average90
86.4to get in
FirmAve
Score FirmAve
Score FirmAve
Score
FirmAve
Score FirmAve
Score
Fin
al S
elec
tio
nS
ho
rt L
ist
Pro
cess