MINISTRY OF WORKS AND TRANSPORT - Amazon Web … · MINISTRY OF WORKS AND TRANSPORT ... are faced...
Transcript of MINISTRY OF WORKS AND TRANSPORT - Amazon Web … · MINISTRY OF WORKS AND TRANSPORT ... are faced...
1|P a g e
MINISTRYOFWORKSANDTRANSPORT
STANDARDGAUGERAILWAYPROJECT
DRIVINGSOCIALECONOMICTRANSFORMATIONTHROUGHDEVELOPMENTOFSTANDARDGAUGE
RAILWAY
1.0 INTRODUCTION
TheGovernment ofUgandahas put emphasis on infrastructure development in order to achieve the
aspirationsofUgandansasenshrinedintheUgandaVision2040.ThetargetistoobtainaGDPpercapita
ofUSD9500by2040.Infrastructuredevelopmentisprimarilymeanttoprovideaconduciveinvestment
climatethusattractinglargeforeigndirectinvestmentespeciallyinheavyindustriesandservices.Since
we have limitedmarket size and capacity, it is important that investors who are attracted primarily
produce goods for export to high-endmarkets in Europe, North America, Asia and other developed
countries.Itisimportanttoknowthatthereisworldwidecompetitionofattractinginvestorsbydifferent
countries,itisimperativethatourinvestmentclimateiscompetitiveatglobalstage.Theseinvestorsmust
beassuredofreliable,cheapandadequatetransportservicestothehighendmarkets.Reviewofworld
tradeandcountries’economicgrowthtrendsdepictthatparticipatinginglobalvaluechainsisimperative
forgrowth.
Notingtheaboveneed,theHeadofStateofKenya,Uganda,RwandaandSouthSudanundertheauspices
ofNorthernCorridor IntegrationProjects (NCIP)agreed todevelopa seamlesshighcapacity,modern,
reliableandsafeSGRsystemacrossthefourcountries.
StandardGaugeRailwayasabackboneoftransportinfrastructuremustprovideatransportservicefor
exportandimportthat iscomparabletootherservices inothercountries intermsofquality,costand
reliability.
2|P a g e
Thesecountriesandtheirneighborsareatdifferentstagesofdevelopingtheirrespectiverailwaysystems
inordertofullyparticipateininternationalglobaltradeandproduction.
Althoughdifferentpoliticalagendahavebeensetespeciallyonthedevelopmenttimelines,thecountries
are faced with challenges of raising the necessary resources either internally or through external
borrowing.Externalborrowingislargelydependentonthecountry’sGDP,DebttoGDPratio,Revenueto
GDPRatio,andthecountry’sriskasassessedbyinternationalcreditratingagencies.
Thetablebelowprovidessomeinformationonthekeymacroparametersfortherespectivecountries.
Indicator Uganda Kenya Tanzania Ethiopia
Population(Million) 38.32 46.79 52.48 99.47
GDPUSD(Bn) 25.61 69.17 46.70 69.22
PerCapitaIncome 668.3 1,478.3 889.9 695.9
CreditRating* B B+ NA B
Source:TheWorldFactbook-CentralIntelligenceAgency(2015figures)
*http://www.tradingeconomics.com-list/rating
Note:TheDebttoGDPratioforalltheabovecountriesisabove30%implyingthattheyallhavelimited
roomforadditionalborrowing.
2.0 WHYUGANDAISPRIORITIZINGTHENORTHERNCORRIDORASTHEPRIMARYROUTE
Uganda’sstrategicgeographicalpositioning,putsitattheheartoftheEastandCentralAfrica
logisticschainandcanevacuateitsproductsthroughtheportsofDjibouti,MombasaandDar
EsSalaamamongothers.
However,due tomany factors, theportofMombasa inKenyaand theportofDarAsSalaam in
Tanzania are anchor points for two transport routes—the Northern Corridor and the Central
Corridor—bothcrucial for thedomestic, regional,and international tradeof fiveEasternAfrican
countries.
Northern Corridor is the busiest andmost important transport route in East and Central Africa,
providingagatewaythroughKenyatothelandlockedeconomiesofUganda,Rwanda,Burundiand
EasternDRCongo.ItalsoservesSouthernSudan.
The less busy alternative transport network serving the landlocked Great Lakes Region is
throughTanzania,calledtheCentralCorridor linkedtoDarEsSalaam.ThisusesTanzania'sCentral
Line.
3|P a g e
Table2:ProvidessomeoftheadvantagesoftheNortherncorridorovertheCentralCorridoreven
iftheSGRisdevelopedasplannedinthethreecountries.
ITEM THENORTHERNCORRIDOR
(Mombasa–Kampala)
THECENTRALCORRIDOR
(Dar Es Salaam-Morogoro-Tabora-Mwanza-
Kampala)
Distance
1,250KM 1548KM (1228Km on land and 320km on
water)
Capacity per
day
8640containers(if40SGRtrains
perday,eachtraincarrying216
containers)
216 containers (due to limitations on the
berth, vessels and loading and offloading
time). Each wagon ferry/vessel carries 44
containers.
Transittime Oneday(24hours) Threedayspertrain(72hours-optimistic)
Restrictions Norestrictions Some freight like oil and other chemical
productscannotbecarriedonfreshwater
Major trans-
shipment
None Two- AtMwanza and Port bell. Each vessel
carries44containers.Thusforatraincarrying
215 containers will require 5 vessels to
evacuatethefreightonthelake
Capacity of
Port
Mombasaport isnearly3times
biggerthanDarEsSalaamPort.
Planned expansion in the port
underway
DarEsSalaam,AthirdofMombasaPort
Current
freight to and
through
Uganda
10 Million tonnes of cargo per
year
0.5Milliontonnesofcargoperyear
Access to
higher end
markets
NearertheSuezCanalthemajor
shippingway
Further from Suez canal and will require
dedicatedVessels
4|P a g e
Expected
completion
time
Around 2020 -Kenya has nearly
completed Mombasa-Nairobi
SGR section (472KM) and is
already constructing the
Nairobi-Naivasha SGR Route
(120KM). Already sourcing for
financing for Naivasha-Malaba
section (369KM)). Thus already
nearingtheUgandanBoarder
Tanzaniahasnotcommenceddevelopmentof
the 1219km route from Dar Es Salaam to
Mwanza. Only contract for Dar Es Salaam-
Morogoro(205KM)signed.MwanzaandPort
Bellinlandportswillneedtoberedeveloped.
Newwatervesselswillberequiredtobebuilt
andbuildingavesseltakesaboutthreeyears.
Other
Infrastructure
requirements
Railwayinfrastructure Mwanza Port, Bukasa Port, Railway
infrastructureandVessels
TheimportanceoftheNorthernrouteisfurtheraugmentedbythealreadymuchbiggertradebetween
KenyaandUgandawhichisoverUSD1bn.
Despitedevelopmentoftherailway,cargocapacityonthecentralcorridorwillbeseverelylimitedbythe
constraintsonLakeVictoria,notably,eachwagonferry/vesselcarries44containerswhereasatraincan
carryupto216containers.Therefore,eachtraincanonlybeoffloadedontofivevesselsrequiringabout
15hourstoloadandoffloadthevesselsoneithersideofthelakethussignificantlyincreasingthetransit
timeandcost.
Thiscargocapacitylimitation,distancefromtheport,sizeanddepthoftheportandlake,andrestrictions
oncarryingoilsandchemicalsonfreshwater,makesitimportantthatthecentralcorridorisplannedas
analternativetothenortherncorridorwhichshouldbetakenasaprimaryroute.
FortheMalaba-KampalaSGR,upto40trainscanbeoperatedinadaytransporting8460containers.If
suchamountofCargowasgoingtobetransportedonthelake,assumingthatamassiveoffivewagon
ferriesarepurchased,wewouldrequire40daystoevacuatecargoofonetrain.Thismeansthattheroute
notbeviable.Thiscoupledwiththefactthatoilproductscannotbetransportedonfreshwatermakethe
DarEsSalaamMwanzaKampalaRoutecanonlybeaminoralternativetotheMombasa-KampalaRoute
whichshouldbelookedatasthebarkbornoftherailwaynetworktothesea.
5|P a g e
InordertoappreciatethesimilaritiesandthedifferencesoftheproposedStandardGaugeRailwaysbeing
built inEthiopia,Kenya,UgandaandTanzania,wehaveinatabularformoutlinedthekeyelementsof
eachcountry’sproposedsystem.Therearegeneralissuestonoteinclude:
1. TheMinistryofWorksandTransportcarriedoutastudyconductedbyaninternationalGerman
consultantGauffIngenieurewhoprovidedthepreliminaryEngineeringandfeasibilitystudyfor
theMalaba-KampalaSGRbasedonAREMA(AmericanRailwayEngineeringandMaintenanceof
wayAssociation)standards.TheconsultantestimateWITHOUTlocomotivesandrollingstockwas
USD2.4billionforanelectrifiedrailwaysystemandUSD2.0billionfordieselsystem.Thecontract
priceforthesameelectrifiedroutebasedontheChinesestandardswasnegotiatedtoUSD2.04
billionwithoutrollingstockandlocomotives.ThepriceofUSD2.3billionusuallyquotedincludes
locomotives,rollingstockandprovisionalsums.It’simportanttonotethatChinesestandardsare
animprovementofAREMAstandardsandaresafer,robustanddurable.Thisisexplainedfurther
in this paper aswe analyse the Dar Es SalaamMorogoro and theMalaba-Kampala proposed
systems.
2. ThecontractpriceandnegotiationsfortheEPCturnkeycontractforMalaba-KampalaSGRwas
basedontheEmployersrequirementsderivedfromtheGauffdesign,andNCIPagreementswhich
werethenprovidedthecontractor.Thereforeitisnottruetherewasnobasisfornegotiationsof
thiscontract.TheteambenchmarkedfromEthiopiaandKenyaandlearntfromtheirsimilarities
anddifferencesintermsoftechnicaldesignsandcontractingmodes.
3. It is important to note that the railway systems can all be Standard Gauge but designed to
differentstandardse.g.AREMAorChineseoranyotherstandards.
4. TheNorthernCorridorcountriesagreedonChinaClass1Railwaystandardtoensureaseamless
transportnetworkwhileTanzania isbasingonAREMAstandardwhileEthiopia isChinaClass2
Standard.KenyahasbuiltChinaClass1railwaysystemwhichUgandamustbuildforpurposesof
seamlessness.
5. TheAREMAstandardisnotanationalstandardbutastandardofanassociationofsomerailways
inNorthAmericawhiletheChineseStandardisanationalstandardapprovedandfollowedbythe
GovernmentofChinawhichtodayisbuildingmorelengthsofrailwaysinChinathananyother
countryintheworld.Moreresearchanddevelopmenthasbeendoneonthesestandardsinthe
last30yearsbecauseoftheheavyinvestmentintherailwaybytheChineseGovernment.
6. TheChineseStandardswereengineeredfromAREMAandotherstandardsandaremuchsafer,
robust, and durable. As illustrated later in this paper, the formation width of the Chinese
6|P a g e
standardsis7.7Metrescomparedto6.6MetresofAREMA,theminimumheightofembankment
is 2.5Metres high for Chinese standards while AREMA is 0.64Metres. The requirements for
protectionoftheembankmentsinChineseisstrictlybyconcretehellingbonestructureandstone
masonryandeventheconstructionoftheembankmentsandthesoiltreatmentmechanismsare
more stringent with the Chinese standard than AREMA. This is simply because the Chinese
standardtargetslowoperationandmaintenancecoststhanAREMAoverthelifeoftheproject.
Overall,thelifecycle-costsoftheChinesestandardislowerthanrailwaysbuilttoAREMA.
7. Therailwaysinthefourcountriesaredominantlyfreightbutwillhavepassengerservices.Allthe
majordesignparametersarebasedonfreightrailwaysystem.Passengertrainscanmoveonthese
railwaysatafasterspeedcomparedtofreighttrainsbecausetheyareshorterandlighterwhile
thefreighttrainsarelongerandheavier.Itisimportanttodifferentiatetheattainablespeedsof
passengerandfreighttrainswhenanalyzingthecapabilitiesoftherailwaysystems.Thereforethe
speedofpassengertrainsislargelyinconsequentialtothedesignparametersandthereforethe
changeinthespeedofthepassengertrainswillnotaffectthecostofdevelopmentoftherailway.
8. It’simportanttonotethatinrailwaydevelopment,thehighestcostisinbridges,followedbythe
earthworks(embankment),followedbytruck,stationselectrification,signalingetc.Forexample,
onMalaba-Kampala,35%oftherouteisinbridges,25%isinearthworksand10%intrack,10%
stations,5%electrification,5%signalingand10%others.Thebridgesandearthworksarearesult
of hydrology (Rivers, swamps, and amount of rainfall), terrain and geology of the respective
routes. These parameters vary significantly among the various project sites in the different
countries.EvenonroadprojectsinUganda,variancesinprojectcostscanbeseeninwetandhilly
areaslikeKanungu,Kisoro,Kabaale,KapchorwaandMbale,comparedtotheflatareasinTeso
andKaromojaregion.
9. StrictlyfromprofessionalEngineeringperspective,thecostofacivilengineeringstructureisbuilt
up using the engineers build up cost estimate method whereby the cost of various inputs,
(material, labour, technology, equipment) and the quantities are computed to come upwith
engineer’s estimates. The cost comparison should be made on this basis. From the limited
informationobtainedfromtherespectivecountries,ananalysisonthekeyparametersandcosts
hasbeendonebetweenthevariousprojectsinthedifferentcountries.Agooddetailedanalysis
can only be done using detailed designs and understanding the environmental and
macroeconomicparametersofeachcountry.
7|P a g e
Table 3: Comparison of Major Characteristics of the Malaba-Kampala and Mombasa-Nairobi SGR
Projects
Item Uganda Kenya
RouteLength 273KM 472KM
Tracklength 338KM 609KM
Standard ChinaClass1 ChinaClass1
System SGR SGR
Traction Electric Diesel
welding Continuous Jointed
Curvatures 1200/800 1200/800
Gradient 1.2% 1.2%
TrailingLoad 4000/5000metrictonne 4000/5000metrictonne
StructureGauge DoubleStack DoubleStack
Signaling FullyAutomatic FullyAutomatic
PercentageofBridgesalong
theroute
8.8%oftheroute 5.9%oftheroute
SuperBridge 1KMBridgeoverriverNile None
CostperrouteKm(excluding
locomotives)
7.32m/Km 7.288M/Km
Total costs excluding
locomotives
USD2.04Billion USD3.44Billion
Note:
a) GiventhattheUgandanSystemiselectric(atadditionalcostof0.54m/km),withamajorsuper
bridgeovertheNile,andwith53KMinaswamp.Malaba-KampalaSGRcostiscomparabletothe
Mombasa-NairobiSGRsectioninKenya.ItisimportanttonotethatthecostinKenyaincludesthe
developmentsatMombasaportofconnectingalltheberths,anddredgingamongothers.
b) Uganda deliberately took a decision to invest in an electric system due to the lower
operationandmaintenancerequirements(atleast40%)comparedtothedieselsystem.
Thiswill significantly reduce theproject life timecost.A report signedbyUgandaand
Kenyaattestingtothisisavailable.
8|P a g e
c) Todemonstratetheimpactofterrainonthecost,istolookattheNaivasha-Kisumusectionthat
passes through the rift valley and for 262KM, the cost is estimated at USD 3.6bn roughly
translatingintoUSD13.7Mperroute-KM.Inthissection,majorbridgeswillberequiredduetothe
uniqueterrain.
Table 4: Comparison of Major Characteristics of the Malaba-Kampala and Addis Ababa –
DjiboutiSGRProjects
Item Uganda Ethiopia
RouteLength 273KM 656KM
Tracklength 338KM 765KM
Standard ChinaClass1 ChinaClass2
System SGR SGR
Traction Electric Electric
Tonnageperyear Designedfor20-35mtonnesperyear Designedfor10-20mtonnesperyear
welding Continuous Jointedevery300metres
Curvatures 1200/800mradius 800/600mradius
Gradient 1.2% 1.85%-2.65%
TrailingLoad 4000/5000tonnes 3500/4000tonnes
LevelCrossings Nolevelcrossings SeveralLevelcrossings
StructureGauge DoubleStackcontainersystem SingleStackcontainersystem
Signaling FullyAutomatic Semi-automatic
PercentageofBridges 8.8%oftheroute 3%oftheroute
SuperBridge 1KMBridgeoverriverNile Maximumbridge155metres
EarthFill 51,620 m3/KM (365% higher than
Ethiopia)
11,110m3/KM
Soilcut 30,510 m3/KM (116% higher than
Ethiopia)
26,210m3/KM
HigherEmbankments 3634 m3/KM (185% higher than
Ethiopia)
1,961m3/KM
Geo-synthetics 19,803 m2/KM (966% higher than
Ethiopiaduetoswamps)
2,050m2/KM
9|P a g e
Rockfill 19,640 m3/KM (161% higher than
Ethiopia)
12,210m3/KM
Costofcement USD180/tonne USD125/tonne
Costofsteel USD680/tonne USD480/tonne
CostofDiesel USD0.76/Litre USD0.62/Litre
Royalties on materials
andbuyingoutlicenses
Land,royaltiesandlicenses Landonly
Distancefromthecoast 1,170KM 350KM
Costoffinancing 85%borrowed/15%domestic 55%borrowed/45%domestic
Cost per route Km
(excludinglocomotives)
USD7.32m/KM USD5.213M/KM
Total costs excluding
locomotives
USD2Billion USD3.42Billion
Note:
a) The Ethiopian system is designed for much lower tonnage and therefore would require
additionallinesinthenearfutureofthefreightincreasesdrastically.
b) Therearemajordifferencesasillustratedaboveintheterrain,topographyandhydrologyof
the twoproject sites thus resulting in higher amounts of rock fill, soil cut, embankments,
bridges,geo-syntheticsthataremajorcostcentresofrailwaydevelopment.
c) TheClassIIsystemlookscheaperatinvestmentstagebutwillbemoreexpensiveinoperation
andmaintenance.Becauseoftheconstructionstandardrequirement.
d) It is important for railways designed for 100 years to look at life cycle costs rather than
investmentcosts.
e) FortheUgandaprojectoneofthemajorcostcentresisthebridgeovertheRiverNilewhich
is1KMlongwhereasinEthiopiathebridgeoverAwashissignificantlynarrow.
f) ThedesignoftheEthiopianroutewaslimitedbythecapacityofDjiboutiPort
10|P a g e
Table5:ComparisonofMajorCharacteristicsoftheofMalaba-KampalaSGRwiththeDarEsSalaam-
MorogoroSGRProjects
Item Uganda Tanzania
RouteLength 273KM 205KM
Tracklength 338KM 300KM
Contractingmode** EPCTurnkey(Systemapproach)** DesignandBuild(Elementapproach)*
Standard ChinaClass1 AREMA
System SGR SGR
Traction Electric Electric
Welding Continuous Continuous
Curvatures 1200/800mR 1000mR
Gradient 1.2% 1.8%/2%
LevelCrossings Nolevelcrossings NoLevelcrossings
StructureGauge DoubleStackcontainersystem SingleStackcontainersystem
Signaling FullyAutomated Fullyautomated
PercentageofBridges 8.8%oftheroute 1.8%oftheroute
SuperBridge 1KMBridgeoverriverNile SmallbridgeoverRiverRuvu
Swamps 53KM Nomajorswamp
Formationwidth 7.7metres 6.6metres
Minimum embankment
height
2.5metres 0.64metres
Cost of cement (Normal
grade)
USD180/tonne USD110/tonne
Costofsteel USD680/tonne USD680/tonne
Transportationcapacity 20-35milliontonnesperannum 18milliontonnesperannum
Royalties on materials
andbuyingoutlicenses
Land,royaltiesandlicenses Onlypayforland
Distancefromthecoast 1,170KM 100KM
Costoffinancing 85%borrowed/15%domestic 50%borrowed/50%domestic
Cost per route Km
(excludinglocomotives)
USD7.3m/KM USD5M/KM
11|P a g e
Total costs excluding
locomotives
USD2.04Billion USD1.029Billion
As it canbe seen, themajordifferences in the standard as Tanzaniaopted forAREMAand theNCIP
countries including Uganda opted for Chinese standards. From the information obtained and
understandingoftheDarEsSalaamMorogororoute,therearemajordifferencesinthehydrology,(rivers,
swampsandtheamountofrainfall),geology,andtopography.Thepercentageofbridgesforthedifferent
projectsandgradientsvarygreatly.
ThemajordifferencesbetweentheChinesestandardandtheAREMAstandardare:
a) The formation width (top width of embankment) is 7.7 meters for Chinese standards while
AREMAis6.6meters.Seedetailsinattachment.Seeillustrationbelow:
b) Theheight,designandconstructionof theembankmentwhich is limitedtoaminimumof2.5
metershighforChinesestandardand0.64metersforAREMA.Thesehighembankmentsinthe
Chinesestandardsrequireslopeprotection.
c) The Chinese classification requires the herringbone concrete structure for protection of
embankments and concretemasonry for higher embankmentsof 6meterswhile this is not a
requirementfortheAREMAstandardsrequireonlybenchingandgrassing.Seeillustrationbelow:
12|P a g e
d) The safety factor in the concrete structures is higher in Chinese standards than the AREMA
standards.
e) Theutilisationofengineeringmaterialsespeciallythegeo-synthetics(geogridandgeotextile)for
treatmentofsoftground,thebackfillingmaterialandsoftgroundtreatmentsaredifferentinboth
ChineseandAREMAstandards.Thegeneraldesignandconstructionstandarddifferencesinthe
twostandardswouldthereforemakearailwaydesignedandconstructedtoChinesestandards
moreexpensivethantheonedesignedandconstructedtoAREMAstandards.However, this is
onlylookingatinvestmentcostandnotlifecyclecostswhicharemuchlowerinthecaseofthe
Chinesestandardsduetoloweroperationsandmaintenancerequirementsasexplainedearlier.
f) NeverthelessforUganda,theEngineeringcostestimateprovidedbyGauffIngenieurewhichwas
basedonAREMAstandards,ishigherthanthenegotiatedcontractpriceofMalaba-KampalaSGR
bsasedontheChinesestandard.Thiswasduetometiculousnegotiationsthatwerecarriedout.
g) ThereisnosuperbridgealongtheroutebutonUgandaroutethereisa1KMbridgeovertheRiver
Nile.
h) TheDarEsSalaam-Morogorocontractingmodeisdesign-and-build,wherebythecontractonly
stipulatesthedevelopmentofinfrastructurewhileinUgandaitisEPC/Turnkeymodewhichdoes
notonlylookattheinfrastructurebutalsoequippingitforoperationswithlocomotivesandrolling
13|P a g e
stock.Thedesign-and-buildplacesmajorriskstotheemployerincaseanydesigninadequacies
andor constructiondefects affect theoperations and theperformanceof the trains,while in
EPC/Turnkey,thecontractortakesallrisksassociatedwiththeconstructionandtestingthetrain
systemoperations.
3.0 CONLUSION
Fromtheanalysisabove,itisimportanttonotthefollowing:
• ThatboththeNorthernandthecentralcorridorareimportantforthelandlockedeastAfrican
countriesbutthenortherncorridorisamoreviablerouteforUgandaasithasahigherpotential
tospurgrowthinthecountry.
• That the construction cost of railways majorly depends on the unique characteristics of the
specificprojectasdeterminedbythedesignstandard,thegeology,terrainandhydrologyofthe
projectsite.