MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training...

266
MINISTRY OF EDUCATION AND TRAINING PROJECT MANAGEMENT UNIT OF VIETNAMESE-GERMAN UNIVERSITY DEVELOPMENT VIETNAMESE GERMAN UNIVERSITY CONSTRUCTION PROJECT ENVIRONMENTAL IMPACT ASSESSMENT (Updated) December 2015 SFG1869 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training...

Page 1: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

MINISTRY OF EDUCATION AND TRAINING

PROJECT MANAGEMENT UNIT OF VIETNAMESE-GERMAN UNIVERSITY

DEVELOPMENT

VIETNAMESE – GERMAN UNIVERSITY CONSTRUCTION PROJECT

ENVIRONMENTAL IMPACT ASSESSMENT

(Updated)

December 2015

SFG1869P

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

ed

Page 2: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

i

TABLE OF CONTENTS

INTRODUCTION .................................................................................................................. 1

a. Implementation of the environmental impact assessment.................................................. 3 a.1. The Consultant of EIA Report .................................................................................... 3 a.2. Organization for preparing EIA Report ...................................................................... 3

b. Applied methods during implementation of EIA ................................................................ 4

CHAPTER I PROJECT DESCRIPTION ............................................................................... 5

1.1. Project name ............................................................................................................... 5 1.2. Project owner .............................................................................................................. 5

1.3. Project location ........................................................................................................... 5 1.4. Main contents of the project ....................................................................................... 8

1.4.1. Project objectives ................................................................................................. 8 1.4.2. Project scope of works and construction items .................................................. 9

1.4.3. Description of construction method and volume of project ............................ 26 1.4.4. Organizing project implementation .................................................................. 28 1.4.5. List of machinery and equipment ..................................................................... 29 1.4.6. Demand of materials and chemicals of the project ......................................... 31

1.4.7. Project implementation plan............................................................................. 32 1.4.8. Investment capital ............................................................................................. 32

1.5. Policy, Legal and Administrative Framework .......................................................... 38

1.5.1 National laws and regulations ........................................................................... 38

1.5.2 Applicable World Bank Safeguard Policies ...................................................... 40

CHAPTER 2 ......................................................................................................................... 41

NATURAL, ENVIRONMENTAL AND SOCIO-ECONOMIC CONDITIONS ..................... 41

2.1 Natural and environmental conditions ....................................................................... 41

2.1.1. Geographical and geological conditions .......................................................... 41

2.1.2. Climate conditions ............................................................................................ 42 2.1.4. Existing conditions and environmental quality ............................................... 46

2.2. Socio-economic conditions: ...................................................................................... 54

2.2.1. Economic conditions: ....................................................................................... 54

2.2.2. Social conditions ............................................................................................... 55

CHAPTER 3 ......................................................................................................................... 57

ASSESSMENT, PREDICTION OF PROJECT’S ENVIRONMENTAL IMPACTS .............. 57 3.1. Impact assessment and prediction ............................................................................. 57

3.1.2.1. Pollution sources to air environment ............................................................ 58 3.1.1.2. Impacts to water environment ....................................................................... 70 3.1.2.3. Environmental impacts due to solid waste .................................................... 72

3.1.2.4. Impact to soil environment ............................................................................ 73 B. Pollution sources not related to waste ................................................................. 73 3.1.2.1. Impacts to air environment ............................................................................ 78 3.1.2.2. Impacts to water environment ....................................................................... 83

3.1.3.3. Source generating solid waste ....................................................................... 86 3.1.3.4. Noise ............................................................................................................... 88 3.1.3.5. Impacts to socio-economic conditions........................................................... 89

3.2. Comments on detail level, reliability of assessment ................................................. 91

3.2.1. Methods used for environmental impact assessment ...................................... 91 3.2.2. Remarks on detail, reliability of assessment and forecasted results ............... 91

Page 3: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

ii

CHAPTER 4 ......................................................................................................................... 93

NEGATIVE IMPACT PREVENTION, MITIGATION MEASURES, AND RISK &

INCCIDENT PREVENTION, RESPONSE MEASURES OF THE PROJECT .................... 93 4.1. Negative impact prevention and mitigation measures .............................................. 93 4.1.1 Negative impact prevention and mitigation measures in the preparation stage...... 93 4.1.2 Negative impact prevention and mitigation measures in the construction stage .... 93 A. Impacts that relates to waste ....................................................................................... 93

4.1.2.1. Prevention measures of air pollution ............................................................ 93 4.1.2.2 Mitigation Measures on water environment .................................................. 94 4.1.2.3. Minimization caused by solid waste .............................................................. 96 B. Impacts sources not related to waste ..................................................................... 98

4.12.4. Mitigation measures for impacts of noise, vibration ..................................... 98

4.1.2.5. Prevention and minimization of security and social order issues ................ 98 4.1.3. Negative impact prevention and mitigation measures during operation ............... 99

A. Impact sources related to waste .................................................................................. 99

4.1.3.1. Environmental Impact Minimization caused by waste gases ....................... 99 4.1.3.3. Environmental Impact Minimization caused by solid waste ...................... 110 4.1.3.4. Culture - society impact mitigation measures to in the area ...................... 115

4.1.3.5. Mininization of traffic accidents: ................................................................ 116 4.2. Prevention, management and response measures to incidents of the Project

during construction ................................................................................................... 116 4.2.2. Prevention, management and response measures to incidents of the Project

during operation ........................................................................................................ 118

4.2.2.1. Firefighting preventive measures ................................................................ 118

4.2.2.2. Mitigation measures to the risk of leakage of chemical vapor and chemical

accidents .................................................................................................................... 119

4.2.2.3. In case of electricity failure (short circuit, electrical accidents) ................ 119 4.2.2.4. In case of epidemic diseases ........................................................................ 119 4.2.2.5 Supporting measures .................................................................................... 120

CHAPTER 5 ....................................................................................................................... 121

ENVIRONMENTAL MANAGEMENT AND MONITORING PROGRAM ......................... 121 5.1. Environmental Management Program .................................................................... 121

5.1.1. Responsible units ............................................................................................ 121 5.1.2. Environmental management and monitoring................................................ 122

5.1.3. Grievance redress mechanism ........................................................................ 124 5.2. Detailed Environmental Management Program ..................................................... 125

5.2.1. Construction stage .......................................................................................... 125

5.1.2. Operation stage ............................................................................................... 126 5.3. Environmental compliance framework ................................................................... 143

5.4. Estimated costs for construction of environmental treatment works ..................... 145 5.5. Environmental monitoring program ....................................................................... 146

5.5.1. Construction stage .......................................................................................... 146

5.5.2. Operation stage ............................................................................................... 147 5.5.3. Monitoring frequency: .................................................................................... 148 5.5.4. Estimated cost for monitoring ........................................................................ 148

5.5.4.1. Construction stage ....................................................................................... 148

CHAPTER 6 ....................................................................................................................... 149

PUBLIC CONSULTATION ............................................................................................... 149 6.1. Comments made by Thoi Hoa Ward People's Committee and local communities 149

6.2. Feedbacks and commitment of the Project owner on comments of Thoi Hoa WPC

and local communities in the project area. .................................................................... 150

Page 4: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

iii

6.3. Disclosure ............................................................................................................... 150

CONCLUSION, RECOMMENDATION AND COMMITMENT ....................................... 152

1. Conclusion ..................................................................................................................... 152

2. Recommendation ............................................................................................................ 152

3. Commitment ................................................................................................................... 152 3.1. Commitment to measures, regulations on environmental protection related to the

Project ............................................................................................................................ 152

3.1.1. Air environment in the area shall have to attain the following standards: .. 152 3.1.2. Labour environment in the area shall have to attain the following standards:

................................................................................................................................... 152 3.1.3. Water environment.......................................................................................... 152

3.1.4. Waste ............................................................................................................... 153 3.2. Commitment to completion time of environmental treatment facilities ................. 153

APPENDICES .................................................................................................................... 154

APPENDIX 1. STANDARDIZED ENVIRONMENTAL CODES OF PRACTICE (ECOP) 155

APPENDIX 2. LEGAL DOCUMENTS .............................................................................. 175

APPENDIX 3. BASELINE ENVIRONMENTAL MONITORING MAP ............................. 192

APPENDIX 4. ENVIRONMENTAL MONITORING MAP IN CONSTRUCTION STAGE 208

APPENDIX 5. ENVIRONMENTAL MONITORING MAP IN OPERATION STAGE ....... 210

APPENDIX 6. BASELINE ENVIRONMENTAL ANALYSIS RESULTS............................. 212

APPENDIX 7. MINUTES OF PUBLIC CONSULTATION ............................................... 231

APPENDIX 8. SOME PICTURES OF ENVIRONMENTAL SAMPLING ......................... 245

APPENDIX 9. RELATED DRAWINGS ............................................................................. 246

APPENDIX 10. BASIS FOR CALCULATION OF WATER SUPPLYAND DRAINAGE ... 253

Page 5: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

iv

LIST OF TABLES

Table 1. List of personnel who were directly involved in preparation of the EIA Report of

the Project .............................................................................................................................. 3 Table 2. Coordinates of project location (VN2000 Coordinates) .......................................... 5 Table 3. Main buildings and infrastructure in Phase 1 .......................................................... 9 Table 4. Major buildings and infrastructure in phase 2 ....................................................... 11

Table 5. Training programmes of the Vietnamese - German University (VGU) ............... 12 Table 6. Construction items in Phase 1 ................................................................................ 16 Table 7. Investment items in Phase 2 .................................................................................. 19 Table 8. Summary of water demand of the project .............................................................. 22 Table 9. Statistic of stored water of the Project ................................................................... 22

Table 10. Wastewater flow of the project ............................................................................ 23 Table 11. List of equipment ................................................................................................. 29

Table 12. List of machinery and equipment used during construction phase ...................... 30 Table 13. List of basic chemicals ......................................................................................... 31 Table 14. Summary of key information of the Project ........................................................ 33 Table 15. Analyzing air quality results in project area (at 7h00) ........................................ 47 Table 16. Analyzing air quality results in the project area (at 11h00) ................................. 48

Table 17. Analyzing air quality results in the project area (at 16h00) ................................. 50 Table 18. Analyzing results of groundwater quality ............................................................ 52 Table 19. Analyzing results of surface water quality .......................................................... 53 Table 20. Analyzing results of soil/mud quality .................................................................. 54

Table 21. Subject and scale of impacts ................................................................................ 57

Table 22. Dust quantity generating from leveling process .................................................. 60 Table 23.. Summary of transport frequency ........................................................................ 61 Table 24. Summary of amount of diesel for transportation ................................................. 61

Table 25. Total polluted substances during transportation of wastes .................................. 62 Table 26. Summary of material transportation time ............................................................ 62

Table 27. Summary of diesel quantity used for material transportation .............................. 63 Table 28. Polluted substances from transportation means ................................................... 63 Table 29. The impacts of dust and emissions ...................................................................... 64

Table 30. Generating dust factor due to transportation ....................................................... 65 Table 31. Results of calculated concentration of dust arising from abundant soil transport

from the project areas .......................................................................................................... 67

Table 32. Dust concentration generating from road surface ................................................ 68 Table 33. Calculating results of dust concentration generating from road surface caused by

transportation means ............................................................................................................ 69 Table 34. Component and average concentration of polluted substances in domestic

wastewater ........................................................................................................................... 70 Table 35. Component and average concentration of polluted substances in construction

wastewater ........................................................................................................................... 71

Table 36. Polluted concentration in storm water ................................................................. 72 Table 37. Noise of some construction equipment and machineries .................................... 74

Table 38. Anticipated noise transmission during construction phase .................................. 75 Table 39. Vibration of construction means .......................................................................... 75

Table 40. Subjects and scale of impacts .............................................................................. 77 Table 41. Summary of number students and staffs at Vietnamese - German University

(VGU) .................................................................................................................................. 78

Table 42. Summary of transportation means of students and staffs at Vietnamese - German

University (VGU) ................................................................................................................ 79 Table 43. Pollution factor of transportation means .............................................................. 79

Page 6: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

v

Table 44. Polluted load from material transportation means (mg/m.s) ............................... 79

Table 45. Calculated results of polluted substance from transportation means ................... 80

Table 46. Consumed fuel and emission of generators ......................................................... 81 Table 47. Discharging coefficient of polluted substances from generator .......................... 82 Table 48. Load and polluted concentration from emergency generator of Vietnamese -

German University (VGU) .................................................................................................. 82 Table 49. Concentration of NH3, H2S - odorous gases Nin the WWT area ....................... 83

Table 50. Polluted concentration in domestic wastewater ................................................... 84 Table 51. Quantity polluted substances in wastewater toilet ............................................... 84 Table 52. Concentrations of a number of metals in laboratory wastewater ........................ 85 Table 53. Estimated domestic solid of VGU ....................................................................... 86 Table 54. Estimated hazardous solid waste quantity ........................................................... 87

Table 55. Noise of vehicle ................................................................................................... 89 Table 56. Technical speficiation of wastewater treatment facilities .................................. 108

Table 57. Detailed explanation of the environmental management and monitoring diagram

........................................................................................................................................... 123 Table 58. A summary of Environmental Management Program ....................................... 126 Table 59. Estimated costs for construction of environmental treatment works ................. 145 Table 60. Contents of Environmental monitoring in construction stage ........................... 146

Table 61. Contents of waste monitoring in operation stage of the project ........................ 147

LIST OFFIGURE

Figure 1: Layout of construction area .................................................................................... 6 Figure 2: Location of construction area and surroundings .................................................... 7 Figure 3: Overall layout ....................................................................................................... 14

Figure 4: Zoning for functional purposes ............................................................................ 15 Figure 5: Sketch of construction items in Phase 1 ............................................................... 16

Figure 6: Entrance gate and internal roads of the Project .................................................... 21 Figure 7: Flood peak point survey of in the project area ..................................................... 46 Figure 8: Some models of mobile toilet............................................................................... 95

Figure 9: Some pictures of the oil filter fabrics ................................................................... 96 Figure 10: Some pictures of hoods in the laboratory ......................................................... 100 Figure 11: Grease trap picture ........................................................................................... 104

Figure 12:Wastewater collection diagram ......................................................................... 105 Figure 13: Wastewater Treatment Technological line ....................................................... 107

Figure 14: A number of rubbish bins can be used for buildings ........................................ 111 Figure 15: Some bins with wheels and lids are used for waste collection and transportation

to waste gathering site ........................................................................................................ 112 Figure 16: Solid waste and hazardous waste collection diagram ...................................... 113 Figure 17: Diagram of environmental management and monitoring ................................ 123

Page 7: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

vi

LIST OF ABBREVIATIONS

AS Allowable Standards

BIWASE Binh Dong Water Supply, Sewerageand Environment Company

BOD Biological Oxidation Demand

CMC Construction Management Consultant

COD Chemical Oxidation Demand

CP Construction Planning

DOM Domitory

DONRE Department of Natural Resources and Environment

DP Detailed Planning

EIA Environmental Impact Assessment

EM Environmental Monitoring

EMP Environmental Monitoring Plan

EPA Environmental Protection Agency

ES Environemntal Sanitation

E-T Education - Training

FF Fire-fighting

FS Feasibility Study

GDP Gross Domestic Product

IZ Industial Zone

NSV National Standards of Vietnam

ODA Official Development Agency

PMU Project Management Unit

PPC Provincial People‘s Committee

RP Resettlement Plan

SEMP Site Environmental Management Plan

ST Site Clearance

TSP Total Suspended Particulate

TSS Total Suspended Solids

UE Undergraduate Education

VGU Vietnamese – Germany Univeristy

VMU PMU of VGU

VND Vietnam Dong

WB World Bank

WHO World Health Organization

Page 8: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

1

INTRODUCTION

In order to speed up the sustainable economic development of the country, requirement of

training human resource with high quality has been becoming the core mission of all

people in general and training and education sector in particular. To meet this requirement,

Vietnamese Government has been promulgating many policies and guidance with long-

term vision to develop university education of Vietnam.

One of the detailed objectives defined by Vietnamese Government is to "develop

curriculums in university education toward to researching, occupation, and application and

to ensure inter-reactive capacity among curriculums in whole system to develop and

complete solutions to meet quality and quality assurance system at university education

and establishment of some universities at international standard". To achieve these

objectives, Vietnamese Government has prepared a plan to increase investment capital for

university education development from Official Development Assistance (ODA) sources,

funding by some international financial organizations, particularly investment and

construction of high quality universities, including Vietnamese - German University

(VGU) from the World Bank (WB).

This project origins from initial idea of establishing Vietnamese - German University

(VGU) between Vietnamese Ministry of Education and Training (MOET) and Hessen

State Ministry of Higher Education, Research and the Arts (HMWK) (HMWK) in 2006.

This project rapidly received spreading support during short time. German relevant

stakeholders and others instructed the development of project components and put the

objectives to ensure researching curriculums of Vietnamese – German University (VGU)

can reach high quality and put Vietnamese – German University (VGU) to become

outstanding university. Mission of Vietnamese – German University (VGU) is that to be

the top researching university in Vietnam and region. Vietnamese – German University

(VGU) will implement curriculums for university level and post graduated training with

high quality, based upon German model that will be suitable with the requirements of

Vietnam. Vietnamese – German University (VGU) also will implement researching

activities on main science to serve socio-economic development demands of Vietnam;

Organizational and operational model of this university are one of new experiment and

create dynamic to push up the innovation of university system of Vietnam and contribute

to improve the quality of university education of Vietnam to the same level of regional and

international university. Results and experience learnt from this project will contribute to

the establishment of creative management mechanism of universities in Vietnam. Hence,

Vietnamese – German University (VGU) is one essential project for university education

of Vietnam.

And Vietnamese - German University (VGU) was established according to the Letter of

Intention, signed on 21 May 2007 and ―Joint Declaration on the Cooperation for the

Establishment of the Vietnamese-German University (VGU)‖, signed at Hanoi on 29

February 2008 between the Ministry of Education and Training (MOET) and Research and

the Arts (HMWK). Vietnamese - German University (VGU) was issued its business

license on 01 September 2008 by the Decision No. 1196/QD-TTg of Prime Minister and

officially operated on 10 September 2008.

Vietnamese - German University (VGU) Project is a new Construction Project comprising

of four main components:

Page 9: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

2

- Component 1: Development of a policy and management framework for the

University: implementation of detailed arrangement on management, finance

and quality assurance system for new researching university model;

- Component 2: Development of education and scientific research: establishment

of academic management system, development of comprehensive studying and

researching curriculums for important sectors; development and provision of

training programmes for leaders, and managers, teachers and researchers;

- Component 3: Development of new campus and infrastructure: designing,

building and equipping for a new research university model (administration,

teaching, researching, library and services for student) in the construction area

in Binh Duong Province.

- Component 4: Project Implementation Management: Project management,

coordination of project activities and monitoring and evaluation of the project

and outcomes.

The Component 3 of the project is the basic construction investment. The Ministry of

Construction takes full responsibility for approving investment and construction project for

this Component. Preparing Environmental Impact Assessment (EIA) Report for the VGU

Project was implemented for this Component only.

The VGU prepared the Environmental Impact Assessment (EIA) Report for the Project

which was approved by Binh Duong Provincial People‘s Committee via the Decision No.

2412/QD-UBND on 26 August 2011 and approved by the WB.

However, due to some delay and changes in the scope of several investment items, the

project has not yet commenced so far. As provided for in the Article 18 of the

Environmental Protection Law 2014, VGU Project must re-prepare Environmental Impact

Assessment (EIA) Report then submit to Binh Duong Provincial Department of Natural

Resources and Environment (DONRE) and Binh Duong Provincial People‘s Committee

(PPC) and WB re-approved.

Since establishment day, a campus with total area of 20 ha within National University at

Hochiminh City was agreed to be constructed for the Vietnamese - German University

(VGU). However, in September 2009, relevant stakeholders agreed to find other location

because this location was not suitable with long-term development orientation of

Vietnamese - German University (VGU). Hence, Vietnamese - German University (VGU)

was moved to Thoi Hoa Industrial and Residential Area, Thoi Hoa Ward, Ben Cat Town,

Binh Duong Province with total area of approximately 50.5ha.

Project area includes a part of Hamlet 3 and Hamlet 5C Residential Area of Thoi Hoa

Ward. According to the approved general plan and zoning with scale 1/2000 of Hamlet 3

and Hamlet 5C Residential Area, area for constructing Vietnamese is the separated area for

constructing social infrastructure facility of the area, including: primary University,

kindergarten, market, service and commercial centers. Hence, construction of Vietnamese -

German University (VGU) is suitable with plan and Vietnamese - German University

(VGU) itself is a social infrastructure facility, serving not only Binh Duong Province but

also whole Southern region and other provinces within this country. Environmental Impact

Assessment Report was prepared and approved for construction projects and infrastructure

business at Hamlet 3 and 5C Residential Area by the Decision No. 801/QD-UBND on 05

March 2009 and Decision No. 3530/QD-UBND on 17 December 2012 of Binh Duong

Provincial People's Committee.

The land for construction of the VGU has been planned in details with the scale of 1/500

and approved by Binh Duong PPC at its Decision No. 1865/QD-UBND dated 5/8/2014.

Page 10: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

3

a. Implementation of the environmental impact assessment

a.1. The Consultant of EIA Report

Environmental Impact Assessment (EIA) Report of the Project headed by the Project

Management Unit of Vietnamese - German University (PMU) Construction Project and

implemented by Lac Viet Investment, Environmental Technology and Engineering

Infrastructure JSC. The details are as follows:

- Consultant: Lac Viet Investment, Environmental Technology and Engineering

Infrastructure JSC.

- Representative by: Mr. Phan Ngoc Anh

- Position: Director

- Address of headquarter: No. 9, Duong Thanh Street, Cua Dong Ward, Hoan Kiem

District, Hanoi

- Telephone: (84-4)8288952 Fax: (84-4)9232965

- Email: [email protected]

a.2. Organization for preparing EIA Report

The Environmental Impact Assessment (EIA) Report of the Project was prepared with

consultation of staffs of Lac Viet Investment, Environmental Technology and Engineering

Infrastructure JSC. During the Report preparation, the measurement, sampling, and

analysis of baseline environmental quality in the project area were involved by the

coordination of staffs at laboratory of Dai Viet Investment and Environmental

Development JSC, and Vietnam Water and Environment JSC.

Table 1. List of personnel who were directly involved in preparation of the EIA

Report of the Project

No. Name Position and qualification

I Project Management Unit of Vietnamese - German University (PMU)

1 Nguyen Khac Huy Engineer

2 Huynh Khanh Vu Architect

II. Lac Viet Investment, Environmental Technology and Engineering

Infrastructure JSC.

1 Nguyen Viet Hung PhD in Environmental Science

2 Ho Thi Huong M.Sc. in Environmental Science

3 Bui Thai Bach Duong M.Sc. in Environmental Science

4 Tran Thi Hien M.Sc. in Environmental Science

III. Dai Viet Investment and Environment Development JSC.

1 Ta Tien Lap B.A in Environmental study

2 Dinh Quang Trieu B.A in Environmental

3 Tran Cao Tri B.A in Environmental

IV. Vietnam Water and Environment JSC.

1 Phan Thi Tram B.A in Environmental

Page 11: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

4

2 Nguyen Thi Dien B.A in Environmental

b. Applied methods during implementation of EIA

The following methods were applied during implementation EIA Report:

EIA method:

- Social surveying method (community consultation): used during interviewing

leaders and local people living around project areas;

- Rapid assessment method: was established by the WHO and based on the natures

of technology, productivity, etc – according to statistics in reality- in order to

estimate load of pollutants. This method has a quite good reliability;

- Expert method: select and offer the most likely assumptions in order to calculate

and forecast pollution capabilities, making potential proposals for pollution

treatment for the specific case of the project. With many years experience in the

environmental impact assessment, experts of the Consultants deem that this method

is a reliable one.

- Comparison method: will compare between the results of survey and measurement

on site, analysis in the lab, calculation in theory and Vietnamese Standards (TCVN)

in order to determine the quality of environment in the area.

- Modeling Method: is used to predict and forecast impacts of the Project during the

environmental impact assessment

- Integrated analysis method: the EIA report is prepared based on EIA research

results as prescribed.

Other methods:

- Statistical method: to collect and process data on hydrology and meteorology,

socio-economic as well as other data in the project area;

- Site Survey Method: performed by the EIA Consultant staff in order to have a

highly reliable output.

- Site Sampling and Analyzing method: is carried out in order to define parameters of

air environment quality in the project areas. Surveying, monitoring and sampling

on site and analyzing in laboratory according to Vietnamese Standards (TCVN) and

National Technical Norm (QCVN) on environment to define parameters existing

conditions on quality and quantity of air, water and soil environment and ecology in

the area;

Page 12: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

5

CHAPTER I

PROJECT DESCRIPTION

1.1. Project name

Vietnamese - German University (VGU) Construction Project

1.2. Project owner

Proposed and governance agency: Ministry of Education and Training (MOET)

Address: No. 49, Dai Co Viet, Hai Ba Trung District, Hanoi

Representative of the Project owner: Project Management Unit of Vietnamese - German

University (VGU) Construction Project.

Address: No. 12 A, Hai Ba Trung Street, Hoan Kiem District, Hanoi

Representative: Mr. Phan Quang Dung

Position: Director of Project Management Unit

Telephone/Fax: 0438 691 41/ 0438 694 085

1.3. Project location

Vietnamese - German University (VGU) will be constructed in a total area of

approximately 50,5hectares in Thoi Hoa Industrial Zone and Residential Area, at Thoi Hoa

Ward, Ben Cat Town, Binh Duong Province.

Location of project area is defined as follows:

- Borders with: National Road No. 13 to the East

- Borders with: D9 Road and Hamlet 5C Residential Area to the West

- Borders with: existing residential area to the South

- Borders with: Ring Road No. 4 and Hamlet 3 Residential Area to the North.

Table 2. Coordinates of project location (VN2000 Coordinates)

No. X axis Y axis

1 1228522.117 594483.247

2 1228164.696 594646.509

3 1228061.934 594363.241

4 1227952.203 594067.035

5 1228612.979 593821.746

6 1228619.406 593824.693

7 1228678.303 593983.353

8 1228696.191 594031.540

9 1228913.277 594617.456

10 1228899.320 594645.487

11 1228633.329 594728.833

Page 13: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

6

At the North of construction site, there is K1 Channel the width of 35m, dividing

construction site into two parts as the following Figure:

Figure 1: Layout of construction area

Page 14: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

7

Figure 2: Location of construction area and surroundings

The Vietnamese - German University (VGU) is located in the industrial zone and

residential areas of Thai Hoa. According to the planning area of Hamlet 3 Residential Area

and Hamlet 5CResidential Area, one part of VGU is located in Hamlet 5C Residential

Area and another part in Hamlet 3 Residential Area. This is the service land, it is not

located in the living area, and it is the location of social infrastructure works, serving the

needs of the district and of the region.

The VGU land is located in the corner between the NH.13 and the Ring Road No. 4, which

are the main roads crossing industrial zone and Thoi Hoa residential area, as well as the

main roads passing through Ben Cat town, connecting with the industrial and residential

areas of Ben Cat town.

VGUis about 10 km far from Ben Cat town, 6km to My Phuoc Ward Centre and about 14

km from Thu Dau Mot along the National Road No. 13, and about 46 km from Hochiminh

City Centre.

My Phuoc Ward and Thoi Hoa Ward has a natural area of approximately 6000 hectares,

My Phuoc and Thoi Hoa Urban-Industrial Development Area has total area of

approximately 4700 hectares, which the Investment and Industrial Development Company

serves as the Project owner, in which, it has nearly 2200 ha industrial land and 2500 ha

urban development and service land.

Remaining area is approximately 1300 ha central administrative and service land of

districts, towns and wards, existing residential areas and some industrial development and

small residential projects.

Page 15: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

8

In these industrial – service and urban areas, public facilities were planned such as high

universities; cultural and sport building planned at the town centre, My Phuoc 2&3

Residential Area.

Thoi Hoa and My Phuoc Industrial Zone and Residential Area have a close relationship in

terms of space and facilities. For the space, those residential areas are integrated with

public service facilities, parks, and trees… in a unique area.

The infrastructure is also connected in that way. Main roads of My Phuoc and Thoi Hoa

are connected to the main road such as Ring Road No. 4 to Cu Chi; to National Road

No.22 from Hochiminh to Tay Ninh (Asian Highway AH1), and National Road No. 13 to

Hochiminh City and Binh Phuoc Province. Hence, the project location has many

advantages because it is the linkage to many key and life-line roads in the area.

There is a K1 drainage channel within the project area, connecting to N1 and N2 drainage

channel, starting from My Phuoc Industrial Zone and Residential Are. This is a drainage

channel for the whole My Phuoc and Thoi Hoa Industrial Zone and Residential Area and

then discharge to Thi Tinh River to the West of the project.

The power supply system, communication and water supply network will be also

connected in a unique system in order to make the synchronousness for public facilities.

1.4. Main contents of the project

1.4.1. Project objectives

Overall objectives:

- Vietnamese - German University (VGU) Construction project aims to construct a top

university, providing a high-ranking training and researching centre in Vietnam at

regional and international level;

- The Vietnamese - German University (VGU) will organize advanced and higher

education and postgraduate training courses with high quality, particularly for the

state-of-the-art specialization of German universities that shall be suitable with

demand of the Vietnamese. The university will carry out leading-edge science

researched to serve the demand of socio-economic development of Vietnam;

- Organization model and activities of the university is new pilot model that will create a

dynamic environment to encourage the innovation of education system in Vietnam and

contribute to increase the quality of Vietnam university education to the same level of

advanced universities region-wide and worldwide. Results and lessons learned from the

Project will contribute to the innovative management mechanism for the universities in

Vietnam;

- The Vietnamese – German University (VGU) will strive to be ranked in 200 top

universities in the world up to 2020-2025 phase.

Detailed objectives:

- Establishing and piloting a new model on policy framework of administration, finance

to ensure the quality of autonomy and qualified university and contribute to the

creation of a national financial mechanism applying for a new model university;

- Providing high quality human resource to meet the demand of different sectors and

fields in the society; providing high quality lecturers to training centers and

universities, as well as a nursery garden of scientific talents to meet the requirement of

industrialization and modernization of the country;

Page 16: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

9

- Establishing and developing within the project scale a university with role play of

excellent researching and training centre to create a dynamic combination between

researching and training via relationship among university and industrial sectors in

science and technology;

- Building modern and synchronous facilities to serve scientific training and researching

for university in order to meet international standards with training scale up to 2020 of

5.000 students and 12.000 students to 2030.

1.4.2. Project scope of works and construction items

1.4.2.1. Proposals in the former construction investment project.

According to prepared and approved EIA reports thunder the Decision No. 2412/QD -

UBND dated August 26, 2011 of Binh Duong PPC, proposed contents of the construction

investment project are summarized as follows:

Scope of the project: According to the plan, the VGU project construction is carried

out in two stages. The enrollment plan is 5000 students in Phase 1 and 12,000

students phase 2.

The fields of training and scientific research includes:

- Electricity Engineering and IT;

- Civil Construction Engineering

- Biological Technology;

- Economics and Industrial Engineering

- Mechanics and Manufacturing

- Computer Science

- Natural Science

Construction of its campus and infrastructure: List of buildings is shown in the following

table:

Table 3. Main buildings and infrastructure in Phase 1

No. Functional areas Qty Total for

construction land

area (m2)

Total area (m2)

I Science park 3.148

1.1 Exhibition Area 1 1.963

1.2 Show room 1 640

1.3 Club area 1 545

II. Lecture area 74.802

2.1 Administration rooms 5 19.895

Computer center

Language center

Seminar room

Academy building VI

Page 17: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

10

2.2 Academy building I 7 7.089

2.3 Academy building II 7 7.249

2.4 Academy building III 8 10.390

2.5 Academy building IV 4 5.028

2.6 Academy building V 5 4.524

2.7 Academy building VII 8 13.127

2.8 Meeting Hall and

Library

2 7.500

III. Sport and canteen

area

13.981

3.1 Sporting Event Hall 2 5.000

3.2 Stand 1 1.440

3.3 Grocery shop 1 2.766

3.4 Canteen 3 4.400

3.5 Religion center 1 375

IV. Dormitory 78.660

4.1 Buildings for general

activities

1 800

4.2 Buildings for students 5-9 77.860

V. Academy area

5.1 Buildings for

professionals

2 12.000

5.2 Clubs for

professionals

2 360

5.3 Guest house 5 2.305

Total area in Phase 1 52.192 185.256

VI. Infrastructure

6.1 Water fountain 1

6.2 Stadium 1 16.650

6.3 Tennis court 5 2.200

6.4 Baseball court 2 1.140

6.5 Badminton court 4 560

6.6. Swimming pool 2 2.520

6.7 Internal road 22.413

6.8 Pavement 35.787

6.9 Parking 10.583

6.10 Surface 28.729

Page 18: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

11

6.11 Park and

landscaping (green

trees)

306.168

6.12 Bridge (40m x 80

m)

1 3.200

Table 4. Major buildings and infrastructure in phase 2

No. Functional area Quantity Total land area

for construction

(m2)

Total land area

(m2

I Lecture area

1.1 Faculty Building VIII

1.2 Faculty Building IX

1.3 Faculty Building X

1.4 Faculty Building XI

1.5 Faculty Building XII

1.6 Faculty Building XIII

II. Sport and canteen 6.550

2.1 Canteen 3 6.550

III. Dormitory 52.700

3.1 Dormitory 5-9 52.700

Total areas of buildings in Phase 2 30.004 154.050

1.4.2.2. Proposed contents in 2015 in the construction investment project

Project scope of works

The VGU will be constructed in a total area of approximately 50.5 hectares, including

about 50 buildings and facilities in the both two phases. Phase 1 of the Project to 2020 will

serve for 5000 students. Up to the end of Phase 2 (2030), the university will provide a

space for studying, researching and dormitory of total 12.000 students and about 160

people, including teachers and their family, excluding guests.

Regarding the training scale, the Vietnamese - German University (VGU) will provide 23

faculties as summarized in the following table:

Page 19: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

12

Table 5. Training programmes of the Vietnamese - German University (VGU)

No. Training programmes University/Master Operation year

I

Faculty I: Electrical Engineering and

Information Technology

1

Electrical Engineering and Information

Technology (IT), Electric Semiconducting,

Telecommunication Higher education 2008

2 Mechatronics and Sensor Technology Master‘s degree 2010

3 Technical Calculation and Modeling Master‘s degree 2009

II Faculty II: Civil Engineering

4

Civil Engineering (construction design,

construction supervision, project management,

land management, environmental construction)

5 Transport and Logistics Master‘s degree 2012

6 Stable Urban Development Master‘s degree 2009

7 Architecture Higher education 2017

8 Civil Engineering Master‘s degree 2020

III

Faculty III: Processing technology and

Environment

Lab for Processing Technology is one part of the

academy building

9 Processing Technology and Environment Master‘s degree 2020

10 Textile Technique Master‘s degree 2017

11 Water Technology Master‘s degree 2021

IV Faculty IV: Economics and Administration

12 Finance and Accounting Master‘s degree 2011

13

Business Management (Accounting, Marketing,

Human resource) Master‘s degree 2015

14

Small and Medium Business Development

(MBA) – part-time Master‘s degree 2012

15 Economics Master‘s degree 2016

16

Industrial Engineering and Technology

Administration Higher education 2018

17 Medical Administration Master‘s degree 2019

V Faculty V: Production and Mechanical

Page 20: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

13

No. Training programmes University/Master Operation year

Engineering

18

Mechanical engineering (Accuracy engineering,

Mechatronics; Design and automobile

engineering; Processing engineering and energy;

Material sciences; Biomedical engineering;

Basic Aviation Engineering; production

engineering) Higher education 2015

19 Material science Master‘s degree 2018

20

Global Production Engineering and

Administration Master‘s degree 2013

VI Faculty VI: Computer sciences

21 Computer sciences Higher education 2013

22 Internet security Master‘s degree 2019

23 Business Information System (part time) Master‘s degree 2009

Land use structure

Total area: 505.000 m2

in which:

K1 Channel and buffer zone of K1 Channel: 38.414,2 m2

Safe corridor of National Road No. 13: 2.888,8m2

Construction area of university: 463.701,8m2, in which

- Lecture halls: approximately 20-25%

- Dormitory: approximately 15-20%

- House for teachers: approximately 3-5%

- Sport area: approximately 10-12%

- Trees: approximately 40%

- Internal transportation and infrastructure: approximately 7-10%

Functional area

Main functional facilities of the project:

Campus will be organized as 6 main functional areas with facilities serving for

detailed purpose. Proposed facilities will be constructed at campus including:

Scientific exhibition area: it is public space of university, serving for all

community of Binh Duong Province and people in general, including an

exhibition hall, researching hall and a researching club.

Studying area includes 9 facility cluster of facilities and an administrative

building.

Lecture halls, library, meeting hall and cantina will create a general square of

university with public garden surrounding.

Sport area and service area include a cantina, a sport centre, a sport hall, and a

stadium, and administrative facilities.

Page 21: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

14

Dormitory will provide an accommodation for about 12.000 students after two

phases. Dormitory of students also includes motorbike parking lot, self-service

cantina and other service facilities.

Houses for staffs and lectures (science village) with housing (housing and

living square) and community center for professor and staff.

Master plan with spatial consideration for the university:

Public opened space for relaxation and recreation;

Landscape for collecting and managing storm water;

Suitable and safe access road for ambulance and fire truck;

Facilities

Figure 3: Overall layout

Land use of functional areas:

Scientific exhibition

Administrative area

Public area

Sport area

Sport area

Houses

Page 22: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

15

Functional area AL: Administrative area, public area and research area,

including two areas: Scientific exhibition area and administrative area, include

administrative buildings, meeting hall, Library in Phase 1 and Phase 2, lecture hall

Phase 1 and Phase 2, basic faculty, facilities for faculty group I, II, III, V, VI, VII,

VIII, and IX, festival gate and covered pathway to connect to administrative,

public and researching area.

Functional area DL: Dormitory and cantina

Providing accommodation for about 12000 students after 2 phases, the dormitory

will have motor packing lot, self-service cantina, and other service facilities.

Detailed facilities will be: cantina GD1 and GD2, dormitory No. 1 - 12,

community centre and covered pathway to facilities of dormitory and cantina.

Functional area HL: teachers‘ houses

Including: single village, double village, multi-family house, public house for

about 160 people

Functional area SL: sport facilities

Including: covered sport hall, swimming pool and stadiums

Functional area IL: facilities

Including: electric and mechanic areas, wastewater treatment plant, water tower

and other auxiliaries

Functional area GL: green area

Including: centralized park, sport area and water landscape

In addition, there is some specific transportation facility such as two bridges

crossing K1 Channel.

Figure 4: Zoning for functional purposes

Page 23: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

16

Scale of investment items

Construction items that will be invested in Phase 1

Figure 5: Sketch of construction items in Phase 1

Phase 1 includes 24 construction items and sport facilities. Detailed construction items will

be summarized in the following table:

Table 6. Construction items in Phase 1

Code

Name of construction items

in Phase 1

Description

1.1+1.2 Scientific Exhibition Area

Is an open space, two floors. Total area of

construction land is 3.08 m2. Total construction

floor is 1.924 m2. Capacity: 901 people.

2.1 Administration Building

Administrative building has 6 floors in total with

the height of construction item of approximately

33.625m. Total area of construction land is 4.840

m2. Total area of construction floor is 17.948

m2. Building will provide working and living

space for total number of about 1.704 people.

2.7 Meeting Hall

Meeting hall has function of organizing graduate

events, lecture, exhibition, and other events. It

will be constructed with large opened space.

Building includes 2 floors, total area of

construction land: 2.794 m2. Total area of

construction floor is 2915 m2, serving maximally

Page 24: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

17

1.800 people.

2.16.1 Library Phase 1

Library has 5 floors with the height of about 24

m. Total area of construction land: 2.633 m2.

Total area of floor: 6.244 m2. Building has

capacity of about 1.000 students.

2.15.1 Eastern lecture hall

Building has 7 floors, height 31.75m. Total area

of construction land: 3.632 m2, total area of

floor: 16.788 m2. Building has capacity of about

4.737 students.

2.4

Academy building 1– General

faculty

Construction item will be arranged studying and

working space for general faculty (2.4). And in

Phase 1, it will be arranged space for IT

Faculties (until construction items of This

Faculty were constructed in Phase 2).

Building includes 6 floors, including technical

roof Total area of construction land: 1.917 m2,

total area of floor: 8.477 m2, Building provides

studying and working space for maximum of

about 1.228 people.

2.12

Academy building 2 –

Processing engineering and

environment

Arranging studying and working space for

Processing Technique and Environment Faculty,

Textile Technique Faculty, Water Technology

and office for dean and staff.

Building includes 6 floors, including technical

roof. Total area of construction land: 1.486 m2,

total area of floor: 6.310 m2, Building provides

studying and working space for total of about

931 people

2.8

Academy building 3 –

Electrical engineering and

Information technology

Arranging studying and working space for

Electric Technique and IT Faculty, including

sensor system and mechanism, computer

science, office of dean and staff and other

development space for M.Sc. programme in

future.

Building includes 6 floors, including technical

roof. Total area of construction land: 1.486 m2,

total area of floor: 6.520 m2, Building provides

studying and working space for total of about

940 people

2.14

Academy building 5 –

Mechanical and production

engineering

Including Global Mechanism Technique Faculty,

Material Science, dean office, office of teachers

and space for M.Sc. Programme in future.

Building includes 6 floors, including technical

roof. Total area of construction land: 2566 m2,

total area of floor: 10.349 m2, Building provides

studying and working space for total of about

1.354 people.

Page 25: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

18

2.9

Academy building 6 – Civil

engineering

Including Civil Construction and Environment

Engineering Faculty, Architecture Faculty,

Urban Sustainable Development Faculty,

Transportation Faculty, dean office and office

for teachers

Building includes 6 floors, including technical

roof. Total area of construction land: 2.242 m2,

total area of floor: 9.331 m2. Building provides

studying and working space for total of about

1.150 people.

Z.1 Festival hall Total area of approximately 534 m2.

Z.2.1

Roof on walkway through

work items AL area

Total area of construction land is approximately

4.503 m2

3.1.1 Canteen Phase 1

Cantina will be constructed with 3 floors. Total

area of construction land: 1.736 m2, total area of

floor: 3.938 m2, serving maximally of 1.092

people.

4.1.1 Dormitory 1

Dormitory has 7 floors with roof.

Total area of construction land: 2.674 m2, total

area of floor: 15.526 m2. Dormitory 1 will have

1.138 students

4.1.2 Dormitory 2

Dormitory has 7 floors with roof. Total area of

construction land: 2.674 m2, total area of floor:

15.526 m2. Dormitory 2 will have 1.063

students

Z.2.2

Roofed walkway through

work items DL area

Total area of construction land: 728 m2

5.1.1 Lecturers‘ house (single villa)

Total area of construction land: 1.205 m2. Total

area of floor: 806 m2

5.1.2

Lecturers‘ house (double

villa)

Total area of construction land: 825 m2. Total

area of floor: 519 m2

5.2.1

Public service house

(compound house) Area 1

Including 20 houses with 2 floors, double. Total

area of construction land: 792 m2, total area of

floor: 1.360 m2, serving 40 people

3.3

Roofed gym house and

walkway

Building has 2 floors, height 12.2 m. Total area

of construction land: 4.512 m2, total area of

floor: 3.831 m2 and capacity of 950 people.

Pool

Locating at the North of sport hall. Total area of

construction land: 998 m2

Outdoor gym yard

Locating at the East of sport hall. Total area of

construction land: 2.123 m2

A.1

Mechanical & electrical

engineering infrastructure

Building has single structure including

centralized cooling system, transformer station,

wastewater treatment plant, and data centre.

Page 26: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

19

There is separate reservoir and pumping station

at the South of main building. Water in the

1,000m3 tank is potable (it is water reused from

the wastewater treatment plant) 1000 m3. The

500m3 tank is used for firefighting. The tank of

potable water has a capacity of 1,000m3. Facility

has 2 floors, height 12.2m. Total area of

construction land: 2.676 m2, total area of floor:

6.110 m2

A2 Pumping station Total area of construction land: 130 m2.

Z3 Bridge Z3 for pedestrian

Will be designed as light arched roof with the

length of 40m along the width of channel

without middle beam. Bridge will be constructed

by steel with metal handrail. 8m width is for

concrete bridge floor with steel panel. Bridge

foundation will be supported by 2-3m wall

outside existing walls. Bridge is for pedestrian;

car and motorbike is prohibited. Total area of

construction land: 572 m2.

Z4 BridgeZ4 for pedestrian

Main bridge span is approximately 48 m along

width of channel without any support. Other

extra span is approximately 25 m of bridge

crossing H1 pathway to administrative building.

Bridge structure is separated from administrative

building at this location. Total area of

construction land: 386 m2

Z.2.3

Roofed walkway through

work items to internal roads

and landscape area

Cover pathway through construction items (Z.2),

connecting other studying area and residential

areas.

Total area of construction land: 225 m2

Signboard Vietnamese

German University

University plate will be 45 m height at Northeast

connect at intersection of two main roads

surrounding campus, those are National Road

No. 13 and Ring Road No. 4. Total area of

construction land: 56 m2.

Construction items that will be invested during Phase 2:

Table 7. Investment items in Phase 2

Code

Name of construction items

in Phase 2

Description

2.11+2.13;

X.1; X.2 Extended studying building

Total construction area is approximately 6.515

m2, building height is from 5-7 floors, and total

height is approximately 35 m. This height

excluding basement and other technical floors (if

any), and roof of construction items, or roof of

technical blocks, stairs, and elevator above

construction items.

Page 27: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

20

8 dormitories

Total area is approximately 22.646 m2, building

height is from 7-9 floors. The height is

approximately 34 m. This height excluding

basement, technical floors (if any), and roof

construction items, or roof technical blocks,

stairs, elevator above construction items.

3.1.2 Canteen

Total area is approximately 2000 m2, 5 floors;

the height of construction items is approximately

22m.

4.2 Community center Total construction area is 729 m2.

2.15.2 Lecture hall

Total area is approximately 4.317 m2, 8 floors,

the height construction items is approximately

37m.

5.2.2

House Area No.2 (multi-

family houses)

Total construction area is 492 m2

2.16.2 Extended library

Total area is approximately 1.864m2, 7 floors,

the height construction items is 27 m.

Transport

Roads

Internal roads of the university are: urban road: class IV, calculated speed ≤ 40 km/h

Road system includes the following sections:

Road V1, V1a, V2, V3 (section 1), H2a, H2b, H4a, H4b, H5: road line 11 m, cross

section 3 m (pavement) + 5 m (roadway) + 3 m (pavement);

Road H1: road line 11m, cross section 3 m (pavement) + 8 m (roadway) + 0 m

(pavement);

Road V3 (section 2): road line 14.5 m, cross section 3 m (pavement) + 8.5 m

(roadway) + 3 m (pavement);

Road H3, V4: road line 13 m, cross section 3 m (pavement) + 7 m (roadway) + 3 m

(pavement);

Road V1b: road line 8 m, cross section 3 m (pavement) + 5 m (roadway) + 0 m

(pavement);

Road H6: road line 18m, cross section 8 m (pavement) + 7 m (roadway) + 3 m

(pavement);

Designed elevation for connection and abutment with existing roads shall ensure the

agreed elevation and coordinates, creating synchronousness with surrounding area in order

to meet technical and aesthetic aspects of the project.

Approach and solutions for firefighting

Main entry for guests and staffs will be allocated at Road VD4, providing access road to

administrative building and exhibition area via internal road H1.

Page 28: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

21

Second exit will be provided via Road H1B. These roads will serve fire truck to access all

side of exhibition hall at the North, South and East and will be organized in harmonization

with surrounding landscape of construction items.

Two main entrances will be arranged from D9 Road for students and transportation means

at Road H2b and H3 in campus. Guard house will be located at entry to allow accessing

right or change direction to the main gate. Emergency exit and firefighting will be

organized with surrounding landscape of construction items of those roads do not go direct

internal road of campus (see Figure 5.2.7.A). Firefighting road shall ensure the distance

from road edge to construction items from 5-8m according to regulations. Firefighting

roads will be presented in below Figure with combination among internal road (violet) and

firefighting road (yellow).

Whole firefighting road will be designed with 20-ton firefighting truck.

Figure 6: Entrance gate and internal roads of the Project

Drainage system

Drainage system will be designed separately with the domestic wastewater system.

Surface storm water from whole southern area of the project will be collected to the

centralized lakes at the South of the project. Those lakes will slow down storm water flow

during the highest rain with frequency of 10 years. Higher volume of those lakes will be

drained to the channel by sewerage system.

Surface storm water of remaining areas will be collected by drainage system on the roads,

then it will be collected by sewerage system under the road and direct discharged to K1

Channel.

Page 29: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

22

After collecting to sewerage, whole surface water of designed area will be directly

discharged to K1 Channel. This channel will run to Thi Tinh River at the border of the

West of Thoi Hoa IRP that is a branch of Sai Gon River.

Drainage system includes:

+ Infiltration channel

+ Manhole with depressed part, sand trap, and screen at all outlets to sewerage

system from street inlets.

+ Underground slow down tank

+ Storm water channel with coverage (on Road H6 to collect storm water from

surrounding areas).

Water supply network

Domestic water for Vietnamese – German University (VGU) will be separated into two

types: potable and non-potable water. Potable water will be used for drinking, washing,

cleaning and other purposes. Non-potable water will be used for flushing toilet, watering

and other purposes.

o Potable water:

Potable water intended to connect with main existing pipeline network D400

BIWASE (inside diameter 400 mm) along the South of K1 Channel.

o Non-potable water:

Non-potable water will be provided from wastewater treatment system for

recycling.

o Firefighting water

Firefighting water will be provided by water supply system.

Water will be supplied from Binh Duong Water Supply Company that is inadequate to

provide continuously water for VGU campus due to unequal pressure. Hence, an indirect

water supply system will be used - storage reservoir, transmission pump and a pipeline

network to supply water to the campus.

Water storage will be implemented for potable and non-potable water sources. For potable

water source, storage will be based on daily demand and firefighting capacity. Storage

water will be summarized in the following table:

Table 8. Summary of water demand of the project

Average water demand Potable water Non-potable water

Phase 1 545 m3/day 863 m3/day

Phase 2 430 m3/day 1057 m3

Note: Water Supply Standard and basis for calculation, Refer to Appendix 8.

Table 9. Statistic of stored water of the Project

Potable water Phase 1 Phase 2

Potable domestic water 600 m3 1100 m3

Water for fire fighting 500 m3 -

Total portable water volume

(portable)

1100 m3 1100 m3

Page 30: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

23

Non-portable water volume (Non-

portable)

Non-portable domestic water 1000 m3 500 m3

Total Non-portable water volume

(Non-portable)

1000 m3 500 m3

Wastewater system

- Wastewater system will be used by both gravity sewers and pressure pipe and

collect all wastewater from constructions.

- Wastewater from facilities must be treated via 3-chamber septic tank before

discharging to wastewater collection system of the area.

- Wastewater at centralized wastewater treatment plant will be treated as category

A of QCVN 14:2008/BTNMT before discharging to public channel or

communities.

- Most of treated wastewater will be reused for non-potable water resources.

Table 10. Wastewater flow of the project

Wastewater flow

Phase 1 Phase 2

Daily average flow 567 m3/day 1.355 m3/ day

Daily max flow 737 m3/ day 1.762m3/ day

Note: Refer to Appendix 8 for Discharge standard and basis for calculation

Power supply system

Vietnamese - German University (VGU) will be supplied with power from the existing

medium-voltage wire 22kV along National Road No.13 to central transformer 22KV,

from medium-voltage station 22KV to transformer stations 22/0,4KV in the area.

Whole power supply system and lighting system for designed area will be connected to

transformer stations and generator 0,4KV.

Emergency source will provide 100% electricity for administrative building, faculties,

central electric and mechanic building and meeting hall. Lecture hall will be provided

with electricity for all areas except air conditioners. Exhibition hall and teachers‘

house/guest house won‘t have emergency source. Other areas such as dormitory, sport

areas and canteen will be provided from normal source.

Total power supply capacity for the whole project is 11,615 KW, in which 7,744 KW is

in Phase 1.

Ventilation system and air conditioners

Most of the buildings will be cooled by VAV with the Air handling unit (AHUs) at the

central room at the top of buildings. Cold water (CHW) for cooling system will be

generated from the central cooling system. CHW will be pumped around construction

items via underground pipeline. Some space in the campus will only be provided with

natural ventilation system to reduce energy, carbon discharge and maintenance cost as

well as capacity for central cooling system.

Page 31: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

24

CHW will be produced by 3 centrifugal cooling machines with capacity of 1,450

RT/one and 2 centrifugal cooling machines with capacity of 750 RT/one. Centrifugal

cooling machine with capacity 750 RT/one will be equipped inverter to control

capacity. 2 cooling system with capacity of 1450 RT and 01 cooling system with

capacity of 750 RT will be installed in Phase 1. Other remaining cooling system will be

installed in Phase 2. CHW will be at 5oC for supplying and 14

oC for returning.

Fire alarm system

Each construction items will be provided a specific and separated fire alarm system.

This automatic fire alarm system will connect to control centre.

In case of fire alarm equipment activates, system will provide:

• Transmission of evacuation signal to fired floors, upper floors and lower floors

• Automatic calling of elevator to lower floors

• Automatic stopping ventilation systems and air conditioners

• Automatic starting pressured aerator system as well as open/close of suitable

chambers (if any)

• Open all locks of security gates (if any)

• Displaying all control table of fire alarm system at central fire alarm panel at first

floor (control/security room)

• If first alarm will not be confirmed in 5 minute, evacuation signal will be transferred

to all construction items.

Instruction system will be integrated to signal transmission system to allow informing

access right.

Each two-way telephone system for fire fighters according to integrated UL standard

will be provided at emergency exists that allow direct communication with fire fighter

and firefighting control center.

Central fire alarm table include 1 CPU, printer and color display to allow recognizing

the status of fired area.

This system will communicate security system, administrative system and elevator

management system, etc.

Firefighting system

Water supply network for firefighting includes out-door and in-door system.

Water supply network for firefighting includes:

- Control unit

- Flameproof substances storage and provision unit

- Flameproof distribution system and nozzle

- Pipelines.

- Power supply unit

Designed firefighting system must ensure the flow of flameproof substances. This flow

depends on type, total area and volume of firefighting.

Firefighting system must ensure the flow of water and pressure.

Page 32: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

25

Power supply unit must ensure to provide adequate energy for firefighting system. It

must have emergency power supply for replacement if the main source stops.

It must provide extra firefighting pump with the same capacity as the main pump.

Whole buildings in the campus will be provided with water for firefighting directly from

main reservoir of the project. Initial calculation shows that pressure from main firefighting

system of the project is adequate to provide for automatic nozzles and firefighting pipeline

with required pressure without boosting at each building

Buildings will be protected by an automatic firefighting system. All pumps are fully

automatic and they will be started if flow switch and smoke alarm (at least from two

locations) inform to fire control board.

In addition, project will be equipped with fire extinguisher (CO2 and ABC). They will

be provided in the areas such as electric and mechanic room, control room, computer

room, fire hose box and other areas according to national standards. And air and

FM200 firefighting system or equivalent will be designed for server room at central

building and some laboratories at studying buildings such as: server room, computer

laboratory and electric workshop.

Firefighting designs will be prepared, appraised and approved by Firefighting Police.

Lighting system

Power source for transport lighting system from control boards for lighting system:

lighting control at transformer station. Operation mode: Automatic and manual.

Communication system

Vietnamese - German University (VGU) will receive signal from the existing optical

cable along National Road 13 to optical board at MDF room and to IDF at each

building.

Parking lots

Besides parking place along Road H1, first floor of administrative building will be for

parking. Parking area will be coved by punched metal sheets with natural ventilation. It

can grow climbing plant to decorate and create a green curtain to reduce pollution of

parking lots. Whole first floor will provide space for 122 car parking lots and 180

motorbike parking lots.

Parking lot for motorbike/scooter of students will be provided at first floor of each

dormitory.

Fence and guard house

Security is an important issue of universities. Existing channels are providing a natural

security at northern border of main campus. Southern, eastern and western border will

be secured by 2.5 m fence. Eastern fence will be constructed by block bricks

(concreted) with 2.5 m height to isolate campus with surrounding residential area;

guard house will have guardian with mechanic lifting system. The Guard house will be

arranged at entrance of H2 and H3 internal roads from D9 Road. Additional guard

house will be at northern gate to Z.3 Bridge; this guard house will supervise access

right for pedestrian to campus from northern area. Guard house is about 5 m2 in the

area, installed glass at four sides so that it can control all directions.

A fence at channel will be provided along northern and southern parts of channel.

Handrail will be designed as safety purpose for students, not security. Height of fence

is 1.1m, made by steel with two median rails.

Page 33: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

26

1.4.3. Description of construction method and volume of project

Material of construction items:

All facilities listed in construction items will be invested as permanent items with the

lifetime of at least 20 years and 100 years maximally. All class of construction items

will be from II above except canteen and teachers‘ houses could be class III.

Main coverage material will be from local, making by reinforced concrete, brick wall,

and glass windows.

Construction method:

Preparation and receipt of construction site:

Organizing and assigning responsibility for each individual in management board

Receiving construction site for working office, storage, temporary house, etc.

Submitting construction drawings, site investigation to implement installation

drawings

Submitting schedule and materials

Submitting and implementing procurement plan

Preparing temporary house and storage:

Material storage: Material storage at construction site will be constructed inside the

project area. Storage will be constructed stably with high foundation to avoid

damage of materials due to storm water or other factors. If construction site is too

narrow, contractor shall rent a location near construction items for material storage

in order to be advantage for providing materials.

Equipment storage: imported or main equipment will be saved at the store of

construction contractor. They will be only transported to construction site once the

construction was prepared and collected all conditions on approved transportation

means and installation method to ensure shortest installation time on site.

Temporary house: including working office of Management Unit and workshop at

construction site.

Transportation of materials and equipment:

Materials and equipment will be transported from storage of construction contractor

to construction site by special means such as lifting truck, crane, etc. Materials for

construction works will be transported to construction site according to plan so that

it is suitable with construction schedule, avoiding delay that can be influenced to

schedule or long-time storage at construction site. It must ensure the materials and

equipment will be transported to construction site at least 05 days before

installation.

Imported equipment will be checked before putting into the store of Construction

contractor (or Project owner) to ensure there is no damage. And they will be

transported to construction site according to schedule, avoiding long-time storage at

construction site that can be damage of equipment. Loading capacity will be

calculated and submission with Register Certificate for installed and other specific

equipment before implementing, avoiding accident that can be damage of

equipment and causing delay of schedule.

Preparing working tools:

Page 34: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

27

List of tools and specific equipment for construction works will be prepared and

submission to the Project owner for consideration before bringing to construction

site.

Measuring equipment, Testing & Commissioning Equipment will be adjusted and

stamped by National Quality Assurance agencies before use.

All electric tools shall be ensured safety and adequate protecting equipment in case

of incident.

Temporary power supply during construction: including electric panels on the floor

(with shelf) shall have protecting automatic circuit breaker from electric shock and

short circuit. Bushes and circuit breakers will be from source of construction.

Construction machineries:

Transportation and installation mean such as cranes, trucks, etc. shall meet all

demand of construction items during construction phase. We committed to select

the Contractor having good means and pro-active for these construction items in

order to shorten construction phase.

Construction machineries: Construction machineries include excavator, bulldozer

and specific equipment for construction works such as: cutter, driller, soldering, etc

Measure equipment and testing: measure equipment with high liability and

accuracy shall meet strictest requirement of testing standards, regulated by bidding

document.

Preparing materials and equipment provision: to ensure quality, Contractor shall

prepare the following steps:

Planning and submitting all materials and equipment that will be used for

construction items and submitting to designer, construction supervisor and Project

owner for approval

Preparing procurement plan for materials and equipment and submitting some

sample of installed materials to Project owner and consultant for consideration

Contractor shall implement installed material provision to construction site

according to prepared schedule, sign importing contract of equipment; and ensure

the provision time for materials and equipment to construction site in the shortest

time.

Provision plan of materials and equipment can be changed so that it could be

suitable and meeting construction schedule or any change on site construction, as

well as meeting coordination with other contractors.

Registering construction plan of all construction items, the Contractor shall

commit:

Completing construction items according to schedule from receiving commencing

day from Project owner.

Detailed construction schedule and personnel mobilization plan should be prepared

on MS Project that is convenient for monitoring, updating and adjusting in each

construction phase (weekly, monthly).

Construction plan will give priority to the works that can be influenced to the

construction schedule of construction contractor. It should ensure to hand over the

construction site in fastest way for completion.

Page 35: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

28

1.4.4. Organizing project implementation

The Ministry of Education and Training (MOET) is the highest agency in all aspects within

the VGU construction investment project.

As assigned by the MOET to act on its behalf, the PMU of VGU construction project will

take full responsibility for managing and administering the design, and construction of

Component 3 of the Project. Units under the MOET (Department of school material

facilities and equipment, children‘s toys; department of finance, Office of the MOET, etc.)

shall cooperate and give guidances to the PMU to perform the tasks.

Organizational structure of the PMU is shown in the following diagram.

BOARD OF DIRECTOR

Director

Deputy director

Procurement division

- Procurement

assistance

- 01 International

procurement specialist

- 01 Domestic

procurement specialist

Basic construction

division

- Basic construction

assistance

- 04 Construction

engineers (01 in

Hanoi, 03 in South

area)

Financial –

Economic division

- Chief accountant

- 03 Accountants (02

in Hanoi, 1 South

area)

General administrative

division

- 01 Administrative officer

- 02 Interpreters (01 in

Hanoi, 01 in South area)

- 02 driving staffs (01 in

Hanoi, 01 in South area)

- 01 Evaluation and

assessment specialist

Page 36: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

29

In the construction stage, basic construction division will dispatch dedicated staff to be in

charge of and manage labor safety, environmental hygiene, fire fighting and problem

solving.

After completion, the Project shall be managed and operated directly by the VGU. The

organizational structure of the VGU is expected to be as follows:

In which, infrastructure management division will manage technical and operating staff in

charge of electrical system of the University, including 02 dedicated staffs for sanitation

and wastewater treatment, one engineer and one bachelor.

1.4.5. List of machinery and equipment

Types of machinery and equipment using for the project during operation phase include all

types of machinery and equipment serving for teaching and studying in university, kitchen

equipment, electric and mechanic equipment installing at central electric and mechanic

building. Equipment will be summarized in the following table:

Table 11. List of equipment

No. Equipment Existing conditions

(% new/old)

1. Chair New

2. Table New

3. Fan New

4. Lamp New

5. Speaker New

6. Computer New

7. Air conditioner New

8. Screen, projector New

9. Signal generator New

10. Oscilloscope New

11. Universal manipulator New

12. Main board New

13. Electric spare part New

VGU Board

Educatio

n Dept

Faculi

ties Office

and

strategic

develop

ment

Dept

MKT

&

Comun

ication

Accoun

ting

&

Finance

Office

Of

Student

Affairs

IT Manage

ment of

facility

HR

Dept

Page 37: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

30

Types of machinery and equipment used in the project during construction phase include:

Table 12. List of machinery and equipment used during construction phase

No. Machinery and equipment Existing conditions

(% old/new)

1 7-ton truck 70%

2 Plate vibrator 1Kw 70%

3 Spud vibrator 1,5 KW 70%

4 Vibrating ram 18T 70%

5 Vibrating hammer BP170 70%

6 25-ton wheel-chain crane 70%

7 Excavator 1,25m3 70%

8 Cutter 5KW 70%

9 Welder 23 KW 70%

10 Bulldozer 180CV 70%

14. Impulse generator New

15. Lathe New

16. Welder New

17. Miller and shaving

machine

New

18. Hydraulic presser New

19. Punching Machine New

20. Bender New

21. Grinder New

22. Drilling machine New

23. Surveying machine New

24. Lifting equipment New

25. Refrigerator New

26. Sink, kitchen, dishwasher New

27. Generator, transformer New

28. Pump New

29. Water cooler New

30. Smoke consumer New

31. Wastewater treatment

equipment

New

Page 38: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

31

11 Batch mixer 250l 70%

12 6-ton wheel-mounted crane 70%

1.4.6. Demand of materials and chemicals of the project

Construction materials include: sand, stone, brick, paving tile, cement, iron, paint, etc.

Total quantity of construction materials for item in Phase 1 of the project is about 693.924

tons, and Phase 2 is about 351.478 tons.

In the operation period, it will use several types of energy, including:

- Petroleum for generator and other machineries

- Electricity for buildings such as lighting system, air conditioners, ventilation, cooking.

It is main energy consumption of the project.

- Gas for cooking at canteens and laboratories

Chemicals in laboratory are shown in the following table

Table 13. List of basic chemicals

No. Name Chemical formula

Types of acid Hydrochloric acid HCl

Nitric acid HNO3

Sulfuric acid H2SO4

Phosphoric acid H3PO4

Sulfur acid H2SO3

Hydrochloric acid HClO3

Carbonic acid H2CO3

Nitrous acid HNO2

Acetic acid CH3-COOH

Benzoic acid C6H5-COOH

……………….

Types of base Sodium hydroxide NaOH

Calcium hydroxide Ca(OH)2

Copper (II) hydroxide Cu(OH)2

Iron (II) hydroxide Fe(OH)2

Barium hydroxide Ba(OH)2

Magnesium hydroxide Mg(OH)2

………………………….

Types of salts Ammonium nitrate NH4NO3

Ammonium chloride NH4Cl

Sodium chloride NaCl

Page 39: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

32

No. Name Chemical formula

Barium chloride BaCl2

Sodium nitrate NaNO3

Copper (II) nitrate Cu(NO3)2

Sodium phosphate. Na3PO4

………………………….

1.4.7. Project implementation plan

Expected progress of Phase 1 of the project shall be as follows:

+ Preparation of the basic design, the total investment and feasibility study reports

of the construction works: 3rd Quarter /2015

+ Preparation of the Construction drawing and cost estimate

To accelerate the project implementation, the preparation of the construction design

and cost estimate will be divided into 05 package designs, 03 of which package

shall be completed in 3rd

Quarter, 2016 and the two others will be completed in 2nd

Quarter in 2017.

+ Plan for construction, equipment installation

Construction, construction and installation of furniture for the entire works of the

Project will be completed in 2nd

Quarter, 2019.

Expected progress of Phase 2 of the project shall be as follows:

+ 2021: Preparation of the investment project, and basic design

+ 2022: Design of construction drawing

+ 2023-2024: Construction and installation of equipment

1.4.8. Investment capital

Financial source of the project:

- IDA loan of WB (89.92%)

- Counterpart fund of Vietnamese Government (10.08%)

Total investment capital of the project: 200.618.388 USD equivalent to 3.720 billion VND.

- ODA loan: 180.392.998 USD, equivalent to 3.345 billion VND

- Counterpart fund: 20.225.390 USD, equivalent to 375 billion VND.

Of which, cost for environmental protection and construction of environmental protection

works shall be appropriately VND 9,050.393 USD equivalent to VND 190 Billion.

Page 40: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

33

Table 14. Summary of key information of the Project

No. Preparation

stage

Activities Implementation

progress

Technology/

implementation method

Potential environmental

impacts

1 2 3 4 5

Preparation

period

1.1 Trees clearance Complete before

construction

(9/2016)

Manual. Use simple

machines (truck, excavator,

manpower, etc.)

A few impacts. Solid water

(bricks, stone, trees, wild

grass, etc)

II. Construction

period

2.1 Land excavation for grading for

the foundation of construction

works, installing the water

supply and drainage system,

electric and communication

systems

6 months Use machines such as truck,

excavator, bulldozer

Impacts on air environment:

smoke, dust, noise, vibration.

Solid water: abandon soil

2.2 Transport of materials During

construction period

Use 15 tone truck Impacts on air environment:

smoke, dust, noise, vibration.

Impacts on traffic: due to the

increase of transport vehicles.

Risk of traffic accidents

Grease from transport

vehicles

2.3 Storage and unloading materials

and excavated soil

During

construction period

use temporary house at the

site, manpower

Smoke and dust

2.4 Operation of construction

machines

During

construction period

Concrete mixing machines,

bulldozer, excavator,

Impacts on air environment:

smoke, dust, noise, vibration

Page 41: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

34

No. Preparation

stage

Activities Implementation

progress

Technology/

implementation method

Potential environmental

impacts

1 2 3 4 5

compressor, piling machine,

trucks, etc.

Grease

Wastewater from cleaning of

machine, equipment.

2.5 Construction activities:

construction of project items

2016-2019 Use concrete mixing

machines, bulldozer,

excavator, compressor,

piling machine, trucks, etc.

Water environment will be

affected by spillage of sand,

stone, construction materials,

by the penetration of leakage

of chemicals into the water.

The piling for construction of

abutment disturbs mud in the

water and waste derived from

from penetration drilling into

water sources.

Waste oil from cleaning,

maintenance of construction

equipment.

Hazardous waste: from

construction activities such as

waste oil, disposal of paint

and chemical containers,

viscous and oil- contaminated

rags.

Construction solid waste:

mainly excavated soil,

concrete debris, broken

Page 42: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

35

No. Preparation

stage

Activities Implementation

progress

Technology/

implementation method

Potential environmental

impacts

1 2 3 4 5

bricks. The majority of

excavated soil will be reused

for backfilling, earthworks for

the greening and landscaping

areas.

Risk of causing damages to

K1 channel

The construction process will

increase demand for

electricity and water supply in

the project areas.

2.6 Overflow rainwater Construction

period

Gone with the rocks, soil,

waste grease, leveling

materials, waste

2.7 Cleaning transport vehicles Construction

period

Car washing area at the site wastewater

2.8 Concentration of laborers at the

site

During

construction period

(2016-2019)

Temporary houses at the

site

Wastewater of workers: from

eating, drinking and hygiene

activities.

Solid domestic waste: of

workers such as canning,

packaging, paper, plastic,

glass, food scraps.

Social evils and public

Page 43: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

36

No. Preparation

stage

Activities Implementation

progress

Technology/

implementation method

Potential environmental

impacts

1 2 3 4 5

hygiene may arise

Mobilize idle laborers in

localities, which will

contribute to creating job and

increase temporary income

for workers

Stimulate the development of

some types of food services,

other recreational activities in

order to cater for the needs of

workers living in the project

areas.

Labor accidents during

construction period.

III. Operaion

period

3.1 Activities of students, lecturers In operation period Office, kitchen, , restaurant,

dormitory

Domestic waste

Affect traffic on Nh No. 13,

Ring Road No.4 due to the

large number of students and

lecturers

Safety issues

3.2 Activities in laboratory In operation period Testing, analysis Expired chemicals, liquid

containing disposed

chemicals in testing.

3.3 Activities of WWTP In operation period Biological treatment Sludge

Page 44: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

37

No. Preparation

stage

Activities Implementation

progress

Technology/

implementation method

Potential environmental

impacts

1 2 3 4 5

technology Odors

Risks of having accidents

when the plant is not

operated.

3.4 Concentration of students from

various regions and localities.

In operation period Issues on social orders and

security

Page 45: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

38

1.5. Policy, Legal and Administrative Framework

1.5.1 National laws and regulations

The Project shall be implemented in accordance with national law on environmental

protection 2014 and other relevant laws and environmental regulations, including:

Environmental Protection Law No. 55/2014/QH13 dated 23/06/2014;

Water Resource Law No. 17/2012/QH13;

Construction Law No. 50/2014/QH13 dated 18/6/2014;

Law on Adjustment and Supplementation of some Articles related to Basic

Construction law No. 38/2009/QH12 dated 19/6/2009

Vietnam Technical Norms No. 68/2006/QH11 dated 29/6/2006;

Decree No. 18/2015/ND-CP dated 14/2/2015 of Vietnamese Government about

environmental protection planning, strategic environmental assessment,

environmental impact assessment and environmental protection plan.

Decree No. 201/2013/ND-CP dated 27/11/2013 of Vietnamese Government about

detailed implementation of some articles of Water Resource Law.

Decree No. 59/2007/ND-CP dated 09/4/2007 of Vietnamese Government about Solid

waste management;

Decree No. 38/2015/ND-CP dated 24/4/2015 of Vietnamese Government about

managing waste and wastage;

Decree No. 174/2007/ND-CP dated 29/11/2007 on Environmental protection fee for

solid waste;

Decree No. 25/2013/ND-CP dated 29/3/2013 of Vietnamese Government about

Environmental protection fee for wastewater;

Decree No. 12/2009/ND-CP dated 10/02/2009 of Vietnamese Government about

managing the investment of construction;

Decree No. 15/2013/ND-CP dated 6/2/2013 of Vietnamese Government about

managing the quality of construction;

Decision No. 3733/2002/QD-BYT dated 10/10/2002 about Issuance of 21 standards

on labour sanitation, 05 principles, 07 parameters of labour sanitation.

Circular No. 27/2015/TT.-BTNMT dated 29/5/2015 of Ministry of Natural

Resources and Environment about detailed regulation of some Articles of Decree No.

18/2015/ND-CP dated 14 February 2015 of Vietnamese Government about strategic

environmental assessment, environmental impact assessment and environmental

protection plan;

Circular No. 36/2015/TT.-BTNMT dated 30/6/2015 of Ministry of Natural

Resources and Environment about regulation on managing hazardous waste;

Circular No. 02/2009/TT.-BTNMT dated 10/03/2009 of Ministry of Natural

Resources and Environment about assessment of wastewater load capacity of

receiving bodies;

Decision No. 63/2012/QĐ-UBND ated 18/12/2012 of Binh Duong PPC on issuing

regulations on environmental protection in the province of Binh Duong.

Vietnamese Standards and Norms on environment, including:

Page 46: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

39

QCVN 03:2008/BTNTM - National Technical Norm on allowed limitation of heavy

metal in soil;

QCVN 07:2009/BTNMT - National Technical Norm on ranges of hazardous waste;

QCVN 50:2013/BTNMT - National Technical Norm on hazardous limits for sludge

from water treatment process;

QCVN 05:2013/BTNMT - National Technical Norm on surrounding air quality;

QCVN 06:2009/BTNMT - National Technical Norm on some toxic substance in

surrounding ambient;

QCVN 08:2008/BTNMT - National Technical Norm on surface water quality;

QCVN 09:2008/BTNMT - National Technical Norm on ground water quality;

QCVN 14:2008/BTNMT - National Technical Norm on domestic wastewater

quality;

QCVN 26:2010/BTNMT - National Technical Norm on noise;

QCVN 27:2010/BTNMT - National Technical Norm on vibration;

QCXDVN 01:2008/BXD – Vietnamese Construction Norms - Construction plan

QCVN 07:2010/BXD - National Technical Norm on urban technical infrastructure;

TCVN 6705:2009 – normal solid waste - categorizing;

TCVN 6706:2009 - Hazardous waste - categorizing;

Legal documents, decision or written comments of relevant stakeholders on the project:

- Official Document No. 2159/VPCP-KGVX dated 29/4/2008 of Vietnamese

Government Office informing comments of Prime Minister on steering to construct

04 international-level universities, funded by ODA loan of the World Bank (WB)

and Asia Development Bank (ADB);

- Decision No. 1196/QD-TTg dated 01/9/2008 of Prime Minister on the

establishment of Vietnamese - German University (VGU);

- Decision No. 380/QD-TTg dated 24/3/2009 of the Prime Minister on Issuance of

Organizational Structure and Operation Mechanism of Vietnamese - German

University (VGU);

- Decision No. 3052/QD-BGD ĐT dated 20/4/2009 of the Minister of Education of

Training on Approving Technical Assistance Project ―Building Vietnamese -

German University (VGU) following to New Model‖;

- Official Document No. 760/TTg-QHQT dated 12/5/2010 of the Prime Minister

approving list of construction project of Vietnamese - German University (VGU),

funded by WB;

- Official Document No. 2120/QD-BGDT, dated 27/5/2010 on the issuance of

investment and construction project of Vietnamese - German University (VGU),

using the World Bank (WB) loan;

- Binh Duong Provincial People‘s Committee issued land acquisition document with

total area of approximately 50.5 hectares at Ben Cat District, Binh Duong Province

to hand over to Vietnamese - German University (VGU) for implementation of

Page 47: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

40

construction project of Vietnamese - German University (VGU) according to

Official Document No. 973/QD-UBND dated 29//3/2010;

- Ministry of Planning and Investment also issued an Official Document No.

2428/BKHDĐT-KHGDTNMT dated 20/4/2011 to define land compensation and

resettlement

- Ministry of Education and Training issued the Decision No. 2129/QD-BGDDT

dated 27/5/2010 on approving project on ―Building Vietnamese - German

University (VGU)‖, funded by World Bank (WB) loan;

- Ministry of Education and Training issued the Decision No. 6158/QD-BGD ĐT

dated 31/12/2013 on approving Bid Evaluation Result of Overall Design Consultant

for the project on Vietnamese - German University (VGU);

- Project owner prepared outlines of detailed construction plan of Vietnamese -

German University (VGU) scale 1/500 and approved by Binh Duong Provincial

People‘s Committee via the Decision No.: 904/QD-UBND dated 5/8/2010;

- Documents of detailed construction plan of Vietnamese - German University

(VGU) with the scale 1/500 was approved by Binh Duong Provincial People‘s

Committee via the Decision No.: 1865/QD-UBND dated 5/8/2014.

Documents and data prepared by Project owner for preparing environmental impact

assessment:

Detailed plan scale 1/500 of construction project of Vietnamese - German University

(VGU).

Investment and construction project (FS) of Vietnamese - German University

(VGU).

1.5.2 Applicable World Bank Safeguard Policies

Only OP 4.01 (Environmental Assessment) is triggered due to the project‘s environmental

impacts. The project will finance construction of VGU campus which is located in an area

of about 50.5 ha in Thoi Hoa Industrial and Residential Area, Thoi Hoa Ward, Ben Cat

Town, Binh Duong Province (including lecture hall, library, multi-functional rooms,

laboratories, sport and dining area, student and professional housing). The construction

activities would generate noise, vibration, dust, solid waste and wastewater, accident risk,

local traffic and social disturbance during the construction. During operation, the project is

anticipated to generate solid waste, wastewater, and waste gases from teaching activities

and laboratories. Thus, an Environmental Impact Assessment (EIA) including

Environmental Management Plan (EMP) has been developed by VGU to address these

issues.

Page 48: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

41

CHAPTER 2

NATURAL, ENVIRONMENTAL AND SOCIO-ECONOMIC CONDITIONS

2.1 Natural and environmental conditions

2.1.1. Geographical and geological conditions

Topography:

In general, topographic conditions in the construction area is quite flat. Geological

structure is hard and stable. Typical topography is mature sedimentation with the slope of

less than 3-15%.

Topographical elevation of the construction area fluctuates from 3 to 10 m. It reduces to

K1 Channel towards both South and North direction of channel. Typical topographical

elevation of construction area is about 5 - 6 m. The highest is at southern construction area

with elevation from 6 – 10 m.

Geology:

According to the geological survey taken in 2004 and topographical survey results of 10

bored holes with the depth of 40m at construction area; soil layers of construction area

have the following features:

- Layer 1: Sandy clay, medium hardness, thickness 0.7 m at bored holes BH2 to 2.4

m at bored hole BH9. This is soft soil layer with low bearing and wet contraction.

- Layer 2: Sandy clay with stone, medium to very high hardness, thickness 1.2 m at

bored hole BH5 to 3.3 m at bored hole BH2. This layer only appears at bored hole

BH1, BH2, BH5 and BH8 with medium bearing.

- Layer 3: Sandy clay, medium hardness, thickness 1.9 m at bored hole BH5 to 5.8

m at bored hole BH4. This is soft soil layer with low bearing.

- Layer 4: Layer sand, low to medium compactness, appearing at bored hole BH4,

HB7 and BH10, thickness 4.0 m to 7.8 m. This is soft soil layer, low bearing.

- Layer 5a: Sedimentation, medium to high hardness, thickness 1.8 m at bored hole

BH5 to 3.9 m at bored hole BH1. This is soft soil layer, low bearing.

- Layer 5b: Sedimentation, high to very high hardness, thickness 6.5 m at bored

hole BH3 to 16.6m at bored hole BH8. This is soil layer with quite high bearing

and suitable for construction.

- Layer 6: Sandy clay, high to very high hardness, thickness 1.6 m at bored hole

BH2 to 9.8 m at bored hole BH6. This is soil layer with medium bearing, suitable

for construction.

- Layer 7: Layer muddy sand, medium compactness, thickness 0.5m at bored hole

BH3 to 6.8 m at bored hole BH4. This is soil layer with medium bearing, suitable

for construction for small and medium projects.

- Layer 8: Layer sandy clay, very hard, thickness 3.7 m at bored hole BH6 to 4.8 m

at bored hole BH9. This is soil layer with medium bearing and suitable for

construction.

- Layer 9: Sedimentation, very hard and solid, appearing from average depth at 26.2

m, average thickness 7.6 m (particularly at bored hole BH3 with thickness 25.4

m). This is soil layer with high bearing and suitable for construction.

Page 49: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

42

- Layer 10: muddy sand, solid, appearing from average depth at 34.4 m with

average thickness 5.5 m. This layer has physical feature and suitable for

construction.

- Layer 11: hard sandy clay, only appearing at bored hole BH7 and BH8, thickness

1.2 m to 1.5 m. This is soil layer with high bearing and suitable for construction.

2.1.2. Climate conditions

The Project will be constructed in Binh Duong Province and be influenced by monsoon

tropical climate. Flood and storm rarely occur. Annually, there are rainy seasons and dry

seasons; rainy season is usually from May to November and dry season is from December

to April next year. Rainfall intensity in the area is high.

The Project is located in the area IIc - southern weather, including all lowlands of the

provinces and cities, namely: Dong Nai, Binh Duong, Binh Phuoc, Tay Ninh, Hochiminh

City, Ba Ria Vung Tau, Vinh Long, Tra Vinh, Dong Thap, Ben Tre, Long An, Tien Giang,

An Giang, Hau Giang, Can Tho, Soc Trang, Kien Giang, Bac Lieu and Ca Mau.

Temperature:

Enjoying the rich and stable radiation as well as the temperature of relatively high and little

changed over the month in the year in Ben Cat area, and according to So Sao meteorology

station (Binh Duong) from 2010-2014, the temperature in the area is shown as follows:

Annual average temperature (2010-2014): 26.4° C

Annual average temperature varies in a range of: 24.62 -28.36°C

Difference of temperature between the hottest and coolest month is approximately 3.7°C.

The lowest temperature is in December and January, and the highest temperature is in

April and May.

Average temperature from 2010-2014

Monthly average temperature (0C)

1 2 3 4 5 6 7 8 9 10 11 12

24,62 26,96 26,6 28,36 27,84 27,34 26,48 26,56 26,42 26,42 26,32 24,98

Source: Statistical Yearbook of Binh Duong province, 2014

Air temperature directly affects the dispersal, dilution and transformation of pollutants in

the atmosphere. The higher the temperature is, the faster the speed of chemical reaction in

the atmosphere and the less time the retention of substances in the atmosphere. And the

temperature is also a factor altering the organic solvent evaporation, odor causing

substances, and a significant factor having directly impact on the health of workers at

work. Therefore, it is required to analyze the temperature factor when calculating and

forecasting air pollution and proposing solutions.

Solar radiation:

The project area is located in the low latitudes where the sun position is always high and

little changed over the month in the year, therefore, solar radiation regime in the project

area is very stable. The total amount of radiation is about 150 Kcal/ cm2. The high levels

of radiation are in drought season. The average maximum number of sunshine hours per

day is about 8.5 in the January, February and April. Average sunshine hours per year are

about 7.2 hours/ day and 217 hours/ month.

Average sunshine hours in months from 2010-2014

Page 50: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

43

Average sunshine hours in months (hours)

1 2 3 4 5 6 7 8 9 10 11 12

226,1 247,7 256,58 243,62 193,2 180,9 165 174,14 166,28 172,36 203,8 183,58

Source: Statistical Yearbook of Binh Duong province, 2014

Wind, evaporation and air humidity

In the project area, the wind blows prevailingly to the southwest and mostly in June, July,

August and September, and it brings much moisture vapor. The average wind speed is 0.7-

0.8 m/s. North and northeast winds appear mainly from November to January without rains

with the average speed of 0.8 m/s. South and Southeast winds blow primarily in March,

April and May and in drought months without rains. The average velocity is 0.8 m/s.

Evaporation makes an increase of humidity and brings odors into the air. The average

evaporation measured at So Sao station is 1,312 mm. Evaporation in drought months is

higher than thatin cooler months. March is the month when the highest evaporation occurs,

and the lowest evaporation is in August, September and October.

Air humidity is a factor affecting the metabolism of air pollutants and is a microclimate

factor influencing the health of workers. The results monitored at So Sao meteorological

station showed that its annual average air humidity is 79.2%, the lowest atmospheric

humidity in the year is 54%. Air humidity varies by seasons and by region. The difference

between the wettest and driest places in Binh Duong province is about 5%. The moist

period coincides with rainy period (from May to July). The dry period coincides with the

dry season. The highest average humidity month is in September and October, the lowest

humidity months are in February and March.

Monthly average humidity (%)

1 2 3 4 5 6 7 8 9 10 11 12

86,4 86,6 83,2 81,2 86,8 89,6 90,2 91,2 90 90 87,4 86,8

Source: Statistical Yearbook of Binh Duong province, 2014

Similar to the temperature, the air humidity is one of the natural factors affecting the

process of dilution, transformation of pollutants, to the heat exchanging within the body

and human health. Therefore, as the above factors, it is necessary to pay attention to the

moisture in the assessment and forecast of the environmental impacts.

Atmospheric durability

The air pollutants are in granules (dust) and gaseous. Determinants of dust and gas

emission are the atmospheric durability. Pollutants will be mixed and dispersed at the

highest level if atmospheric conditions fall into sustainable groups of A, B, C (sustainable

groups)

When atmospheric durability of Groups A, B, C - small wind speed, the concentration of

pollutants is higher when the wind speed is large.

Atmospheric durability of neutralizing Group D or sustainable Group D or E, F, the ability

to diffuse pollutants will be lowest.

Diffusal in drought seasons will be higher than that in rainy seasons.

Atmospheric durability

Page 51: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

44

Wind speed

(m/s)

Daytime radiation Nighttime coverage

Strong Weak Average A few days Much cloud

2-4 A-B B C E F

4-6 B B-C C D E

Note:

A: Unsustainable of extremely type

B: Unsustainable of average type

C: Weak unsustainable

D: Neutralizing

E: Relatively sustainable

F: Sustainable

The comparison between the average wind speed in the project area of about 0.8 m/sas

presented in the meteorological data and the above table shows that in the project area,

atmospheric durability is generally stable in the daytime and is more sustainable in the

nighttime.

Rainfall

Rains help to purify pollutants in the air and dilute pollutants in the water. Rains also

sweep away pollutants from the ground to water resources. The average rainfall in many

years in Ben Cat is presented as follows:

Monthly average rainfall (mm)

1 2 3 4 5 6 7 8 9 10 11 12

6,14 11,36 8,74 35,92 235,24 163 215,54 191,12 255,28 208,66 112,74 31,56

Source: Statistical Yearbook of Binh Duong province, 2014

Rainfall regime will affect the air quality. Rainfall will sweep away and clean dust and

pollutants in the atmosphere, reduce the concentration of pollutants, dilute and carry

materials on the ground, reducing level of pollution to the soil environment. Therefore,

when considering, assessing and forecasting the environmental quality and propose

solutions to minimize environmental pollution, the analysis and calculation of natural

rainfall is necessary.

2.1.3. Hydrological conditions

There are three main rivers of Dong Nai River system in the locality of Binh Duong

Province, namely: Be River, Dong Nai River and Sai Gon River. Besides three main rivers,

there are Thi Tinh River that is a branch Sai Gon River, Ba Lo Channel, Ba Hiep Channel,

Vinh Binh, Ong Co Channel, etc. Density of channel and river in the provincial locality is

0,4-0,8 km/km2.

Drainage channel K1 runs through the project area and is connected to two drainage

channels N1, N2, which are derived from industrial and residential zones of My Phuoc.

The entire water and wastewater of industrial park and residential area of My Phuoc, Thoi

Hoa will be served by this drainage channel and will then be discharged into Thi Tinh river

Page 52: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

45

(a branch of Saigon River) in the west of industrial and residential areas of Thoi Hoa. At

present, the density of population and factories, enterprises in industrial zones and

residential areas of My Phuoc and Thoi Hoa has not been high, so the water flow in the

channel K1 is not great. Results of the hydrological environment survey in the project

areas in April/2015 (dry season) show that the flow of water in the channel K1 is low

without flow, and section flowing through the project area is so low that the bottom can be

seen.

The followings are observed in Thu Dau Mot and Phu An stations.

Station River Coordinates Monitoring

time

Measuring

N latitude E longitude

Thu Dau Mot Sai Gon 1058‘ 10639‘ 1971 to now Tidal zone

Phu An Sai Gon 10 46‘ 106 43‘ 1912 to now Tidal zone

Monthly feature of water level (cm) at Phu An and Thu Dau Mot Station

Month I II III IV V VI VII VII

I

IX X XI XII Year

Sai Gon River: Thu Dau Mot Station

Average 33 26 21 12 2.7 -8.2 -6.3 -1.3 14 39 41 37 18

Max 137 134 137 131 117 124 115 124 138 147 144 144 147

Min -

171

-

204

-

212

-

198

-

225

-

249

-

248

-

243

-

228

-

175

-

173

-

169 -249

Sai Gon River: Phu An Station

Average 124 119 115 108 102 95 98 106 120 129 129 127 114

Max 154 147 150 144 130 129 125 137 150 162 158 160 162

Min -

194

-

210

-

212

-

210

-

234

-

246

-

252

-

245

-

223

-

195

-

195

-

195 -252

Source: Southern Regional Hydro-meteorological Center.

Highest and lowest water according to frequency at Phu An and Thu Dau Mot Stations

Station 1% 2% 3% 4% 5% 10% 25%

Thu Dau

Mot

Max (cm) 156 149 144 142 139 131 122

Min (cm) -267 -262 -258 -256 -254 -247 -235

Phu An Max (cm) 171 164 160 158 156 149 139

Min (cm) -256 -254 -253 -252 -251 -247 -241

Source: Southern Regional Hydro-meteorological Center

Page 53: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

46

Annual flow distribution at Thu Dau Mot Station on Sai Gon River

Monthly Qtb

I II III IV V VI VII VIII IX X XI XII

41.0 34.0 29.4 28.7 36.3 55.1 92.2 146.4 203.1 200.9 137.6 58.0 88.6

Source: Southern Regional Hydro-meteorological Center

Study on the elevation of highest flood in the construction area was prepared by the Client

and detailed planning Consultant in 2014.

According to the investigation report on flood level in many years in the construction area,

investigation point of highest flood level will be reported as follows:

Investigation point 1: 3,762 mm (3,76m) according to water marks in 2013

Investigation point 2: 4,035 mm (4,04m) according to water marks in previous

years.

Investigation point 3: 3,081 mm (3,08m) according to water marks in 2013

Investigation point 4: 3,097 mm (3,10m) according to water marks in 2013

Figure 7: Flood peak point survey of in the project area

2.1.4. Existing conditions and environmental quality

In order to have basis for assessment of the existing environmental quality in the project

area, we, EIA Report Preparation Consultant of the project in collaboration with Dai Viet

Investment and Environmental Development JSC. and Vietnam Water and Environment

JSC carried out the survey, sampling, measuring and analyzing some typical environmental

criteria at the project area to assess baseline environmental quality. Sketch of sampling

location is presented in the Annex.

Analyzing results of environmental samples are presented in the following tables.

2.1.4.1. Air environment and micro-climate

Page 54: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

47

Consultant implemented measurement and sampling of air at 5 locations in the project

area, in which, it took three samples at each location in different time of 7h00, 11h00 and

16h00.

Table 15. Analyzing air quality results in project area (at 7h00)

Page 55: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

48

Table 16. Analyzing air quality results in the project area (at 11h00)

No. Parameter Unit Results QCVN:

26/2010/BTNM

T

QCVN

:05/2013/BTNMT

QCVN 27:

2010/BTNMT KK6 KK7 KK8 KK9 KK10

1 Temperature oC 35,6 34,7 34 32,6 34,1

2 Humidity % 62,8 59,3 61,7 59,4 61,0

3 Wind speed m/s 1,0 0,4 0,5 0,2 1,0

4 Wind direction - Southwest

5 Noise dBA 60,5 56,7 52,4 55,8 63,7 70

6 Total dust mg/m3 0,22 0,17 0,15 0,13 0,18 0,3

No. Parameter Unit Results QCVN:26/201

0/BTNMT

QCVN

:05/2013/BTNMT

QCVN 27:

2010/BTNMT KK1 KK2 KK3 KK4 KK5

1 Temperature oC 31,5 32,3 32,8 32,9 32,4

2 Humidity % 64,6 56,3 58,6 57,3 63,2

3 Wind speed m/s 1,3 0,2 0,9 0,7 1,4

4 Wind direction - Southwest

5 Noise dBA 65,5 53,5 55,2 53,6 65,3 70

6 Total dust mg/m3 0,20 0,15 0,16 0,12 0,19 0,3

7 NO2 mg/m3 0,067 0,070 0,081 0,068 0,070 0,2

8 SO2 mg/m3 0,079 0,062 0,070 0,059 0,086 0,35

9 CO mg/m3 5,21 5,28 5,37 5,10 5,37 30

10 Vibration dB 46 59 51 56 65 75

Page 56: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

49

7 NO2 mg/m3 0,071 0,077 0,077 0,071 0,079 0,2

8 SO2 mg/m3 0,083 0,072 0,083 0,067 0,082 0,35

9 CO mg/m3 5,34 5,38 5,43 5,17 5,45 30

10 Vibration dB 51 64 53 50 62 75

Page 57: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

50

Table 17. Analyzing air quality results in the project area (at 16h00)

No. Parameter Unit Results QCVN 26:

2010/BTNMT

QCVN

05:2013/BTNMT

QCVN 27:

2010/BTNMT KK11 KK12 KK13 KK14 KK15

1 Temperature oC 32,4 31,3 32,0 31,1 31,9

2 Humidity % 61,1 62,3 57,4 60,5 62,1

3 Wind speed m/s 0,7 0,6 1,2 0,4 1,0

4 Wind direction -

5 Noise dBA 63,2 61,7 60,8 50,6 66,2 70

6 Total dust mg/m3 0,18 0,14 0,18 0,14 0,20 0,3

7 NO2 mg/m3 0,071 0,072 0,076 0,073 0,072 0,2

8 SO2 mg/m3 0,080 0,083 0,083 0,067 0,081 0,35

9 CO mg/m3 5,37 5,3 5,27 5,24 5,30 30

10 Vibration dB 51 52 55 53 62 75

Note:

Sampling location:

Location 1: KK01, KK06, KK11: Beginning of road VĐ4, intersection with National Road No. 13 (X =1228914, Y=594597, VN 2000 Coordinates)

Location 2: KK02, KK07, KK12: Beginning of road VĐ4, intersection with D9 Road (X=1228619, Y=593818, VN 2000 Coordinates)

Location 3: KK3, KK8, KK13: Residential area at the end ofD9 Road (X=1228032, Y=594067, VN 2000 Coordinates)

Location 4: KK4, KK9, KK14: Residential area at the South of project, between location 1 and location 5 (X=1228124, Y= 594357, VN 2000 Coordinates)

Location 5:KK5, KK10, KK15: National Road No. 13, next to residential area (X=1228707, Y=594731, VN 2000 Coordinates)

QCVN 26: 2010/BTNMT: National Technical Norm on noise

QCVN 05:2013/BTNMT: National Technical Norm on quality surrounding ambient

Page 58: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

51

QCVN 27:2010/ BTNMT: National Technical Norm on vibration

Page 59: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

52

Results of air environment quality measurement in the project area showed that all checked

parameters are lower than the limits as regulated in the QCVN 5:2013/BTNMT. The

results are also suitable with actual conditions because at measuring time, the air quality

around the project area has no pollution sources that can be influenced to air environment

quality such as: no construction activity, less transportation means in Ring Road and

National Road No. 13.

Results of noise and vibration measurement also are in allowable limits of QCVN 26:

2010/BTNMT and QCVN 27: 2010/BTNMT.

2.1.4.2. Groundwater environment

Table 18. Analyzing results of groundwater quality

NO. Parameter Unit Results QCVN

09:2008/BTNMT NN1 NN2 NN3 NN4 NN5

1 Temperature 0C 27,7 28,1 27,6 27,5 28 -

2 pH - 5,69 6,02 6,15 6,24 6,56 5,5-8,5

3 Total

hardness

mg/lCaCO3 18 8 6 40 14 500

4 NO3- mg/l 0,5 0,5 0,3 0,3 0,5 15

5 Fe mg/l 0,05 0,05 0,03 0,04 0,03 5

6 Coliforms MNP/100ml 0 0 0 0 0 3

Note:

QCVN 09:2008/BTNMT: National Technical Norm on groundwater quality

Sampling location:

NN1: At Ngu Sac Printing Ltd., Co. (323, Alley 10, Sub-ward 4, Thoi Hoa Ward, Ben Cat,

Binh Duong). (X = 1228033, Y = 594260m, VN 2000 Coordinates), 14h20

NN2: Ground water at the house of Nguyen Thi Thanh Nga (Alley 10B, sub-ward 4, Thoi

Hoa Ward, Ben Cat, Binh Duong). (X = 1227984, Y = 594192, VN 2000 Coordinates),

15h00

NN3: Ground water at the house of Truong Van Ly (365, Alley 10, sub-ward 4, Thoi Hoa

Ward, Ben Cat, Binh Duong) (X = 1228006, Y = 593896, VN 2000 Coordinates), 15h20

NN4: At Thoi Hoa Temple (Ben Cat, Binh Duong) (X = 1228334, Y = 593827, VN 2000

Coordinates), 15h30

NN05: At the house of Mr. Vinh (Road DV4, intersection D9) (X = 1228610, Y =593803),

15h40

Description of samples: NN1, NN2, NN3, NN4, NN5: clean water, less sedimentation.

Wells have a depth from 20 to 30metres. They are in good exploitation conditions.

Analyzing results of groundwater quality shown all checked parameters are in allowed

limits of QCVN 09:2008/BTNMT

2.1.4.3. Surface water

Page 60: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

53

Table 19. Analyzing results of surface water quality

No. Parameter Unit Results QCVN

08:2008/BTNMT

Column B1 NM1 NM2 NM3 NM4 NM5

1 Temperature 0C 43,1 44,7 35,6 32,4 31,6 -

2 pH - 7,96 7,82 8,01 7,90 7,68 5,5-9

3 BOD5 mg/lO2 <3 < 3 < 3 < 3 < 3 15

4 COD mg/lO2 <5 < 5 < 5 < 5 < 5 30

5 TSS mg/l <5 < 5 < 5 < 5 < 5 50

6 NH+

4 mg/l 0,05 0,05 0,11 0,26 0,1 0,5

7 NO3- mg/l 7,6 6,5 7,5 6,5 4,1 10

8 PO43-

mg/l 2,35 0,35 2,1 0,36 1,1 0,3

9 Coliforms MNP/100ml 1900 600 200 350 250 7500

Note:

QCVN 08:2008/BTNMT: National Technical Norm on surface water quality - Column B1:

irrigation purpose

Sampling location:

NM1: K1 Channel, segment under bridge on National Road No. 13 in the project area (X =

1228781, Y = 594633, VN 2000 Coordinates), 13h15

NM2: K1 Channel, segment between National Road No. 13 and Ring Road 4 (X =

1228654, Y = 594171, VN 2000 Coordinates), 13h45

NM3: K1 Channel, segment under bridge on Ring Road 4 in the project area (X =

1228682, Y =594016, VN 2000 Coordinates), 14h05

NM4: K1 Channel, about 400 m far from Ring Road 4 to downstream (X = 1228867, Y =

593884, VN 2000 Coordinates), 14h50

NM5: Thi Tinh River, segment under bridge on Ring Road 4 (X = 1228093, Y = 592276,

VN 2000 Coordinates), 15h20

Description of samples:

NM01, NM02, NM03: quite clean water, less sedimentation

NM04, NM05: litter turbidity, less sedimentation

Analyzing results of surface water quality on K1 Channel shown all checked parameters

are in allowed limits according to column B1, QCVN 08:2008/BTNMT, but the PO42-

parameter of the Water Plant 1 and Plant 2 is higher than the allowable limit, which can be

explained that surface water of K1 channel in Water Plant 1 and Plant 2 is affected by

domestic wastewater of the project‘s southern residential area, adjacent to national

highway No. 13.

2.1.4.4: Soil environment

Page 61: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

54

Table 20. Analyzing results of soil/mud quality

NO. Parameter Unit Results QCVN

03:2008/B

TNMT

Đ1 Đ2 Đ3 Đ4 Đ5

1 Pb mg/kg soil 0,3 0,28 0,28 0,27 0,29 12

2 As mg/kg soil 0,015 0,013 0012 0,012 0,011 5

3 Cu mg/kg soil 0,8 0,7 0,8 0,8 0,9 100

4 Cd mg/kg soil 0,01 0,01 0,03 0,01 0,01 200

5 Zn mg/kg soil 2,0 1,8 1,8 1,7 1,9 300

Note:

QCVN 03:2008/BTNMT: National Technical Norm on limits of heavy metal in soil

Sampling location:

Đ1: mud on K1 Channel, segment under bridge on National Road No. 13 in the project

area (X=1228757, Y= 594061)

Đ2: Middle construction area, depth 30 cm (X= 1228062, Y=594090)

Đ3: Middle construction area, depth 60 cm (X= 1228062, Y=594090)

Đ4: Middle construction area, depth 30 cm (X= 1228154, Y=594351)

Đ5: Middle construction area, depth 60 cm (X= 1228154, Y=594351)

Analyzing results of heavy metal in soil shown checked soil samples are in allowed limits

of QCVN 03:2008/BTNMT

2.15. Existing conditions of biological resources

The construction area was acquired by Becamex Company. Almost all of plant and

constructions was demolished and leveled to prepare the new development. However, after

cutting trees, Becamex Company planted tree strip at the North, the East and along K1

Channel at the West of construction area. All trees are acacias. The remaining areas of

construction area are empty land and lawn.

For K1 Channel, crossing construction area, it is drainage channel of area with low water

level. It received domestic wastewater of people along channel daily hence there is no aqua

flora and fauna in K1 Channel.

2.2. Socio-economic conditions:

2.2.1. Economic conditions:

Ben Cat Town was established according to Resolution No. 136/NQ-CP of Vietnamese

Government, with natural area: 23,442.24 hectares, population: 203,420 people, including

8 administrative units.

Almost of previous producing land area of Ben Cat Town was changed into industrial and

service land. There is a small area for agriculture. Economic structure of Ben Cat Town:

Industry (85.73%) – Service (13.5%) – Agriculture (0.77%)

Total GDP per capita of town is 53 million VND/person/year.

Thoi Hoa Ward is a ward at the South Ben of Cat Town with natural area of 3,793.01 ha

and total population is 44.990 people. In the locality of Thoi Hoa Ward, there are 03

Page 62: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

55

industrial zones of My Phuoc 1, My Phuoc 2, My Phuoc 3 and Thoi Hoa Industrial Zone

and Residential Area.

Most of previous producing area of Thoi Hoa Ward was used for industry. Total remaining

agricultural land is approximately 760.43 ha. Labour force of ward is mostly working in

factories in the locality and family business and service. Number of labour in agricultural

sector is not significant anymore.

There is total of 1,086 business households. In which, producing: 32 households,

transportation: 26 households, restaurants: 130 households, commercial: 391 households,

service: 507 households. Total non-industrial companies and enterprises in the ward: 205

ones.

Livestock: being together with ward clinic and veterinary station of Ben Cat Town

organized checking and vaccinating livestock in the locality, providing disinfection

chemicals. Checking work for slaughter places in local markets also has been

implementing well.

2.2.2. Social conditions

Thoi Hoa Ward People‘s Committee has implemented the dissemination and propaganda

on economic, cultural and social conditions to the people with good results via loudspeaker

system of the ward, transmitting other radio programme of centre, province and town.

Loudspeaker system of the ward is to propaganda legal regulation, fire preventive, children

protection law, etc.

Health care - disease inspection and treatment: national health care programme: children

below 1 year old will be vaccinated fully. Reproductive health care, family planning and

disease check and treatment for all people has been implementing well. Food safety is

focused. Checking results shown that 171 unit meeting the requirement 100%.

Poverty situation: There are 12 poor households and 14 closed-poor households as the

results of the checking and consideration of poor households, closed-poor households in

the 2014-2015 period according to the new poverty standard. After organizing a meeting to

consider poverty situation in 2014 and poor household in 2015, there are 02 poor

households and 03 closed-poor households. It was submitted to Town People‘s Committee

to recognize 10 poor households and 11 closed-poor households.

Education:

There are schools for all education levels in the locality of Thoi Hoa Ward: kindergarten,

primary school, and secondary school. Assessment results of the Universities will be as

follows:

+ Thoi Hoa Kindergarten: ratio of malnutrition 1.7%; obesity : 9.1%; hardworking:

90.2%; good: 88%

+ Thoi Hoa Primary school: good: 287 pupils (30.43%); medium: 420 pupils

(44,53%); average: 204 pupils (21.6%); week: 32 pupils (3.9%), behavior

assessment: 96.1% good pupil.

+ Thoi Hoa Secondary school: good: 120 pupils (14%), medium: 248 pupils (29%);

average: 367 pupils (42.9%); week: 115 pupils (13.5%); below poor: 05 pupils

(0.6%), behavior assessment: 78.6% good pupils, medium: 19.9% pupils and

average (1.5%) pupils.

Culture and communication: publishing and propaganda works have been implementing

well during holidays. There are some propaganda about disease, law dissemination and

other activities at local.

Page 63: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

56

It coordinates with Ward Youth Union to demolish illegal commercial advertisement on

electric poles, public areas to ensure beautiful landscape.

It was implemented checking business and service place in locality ward. It reminds

business units to operate according to requirement and request to commit not to violate

laws and immoral behavior.

Religion and peoples: in the locality of Thoi Hoa Ward, there are total 21 minority

households with 66 people in which there are 36 males and 30 females.

Security: in the locality of Thoi Hoa Ward, there are total 3,783 households, 44,790

people. In which 3,783 households with 13.160 people are permanent habitants. Number of

temporary people is 31,630. Hence, it can say that, labour force who is working in

industrial zones and temporary habitants in the locality is quite high. It is the main reason

of insecurity and other bad behavior in this ward such as robbery, traffic accident, drug

addiction and gambling.

Page 64: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

57

CHAPTER 3

ASSESSMENT, PREDICTION OF PROJECT’S ENVIRONMENTAL IMPACTS

3.1. Impact assessment and prediction

3.1.1. Impact assessment and prediction during the project preparation

Existing conditions of land use: total area of construction that will be handed over to the

project is cleared out and compensated by Becamex Company. Regarding existing

conditions of architecture, there are some class-4 houses of households that have not been

demolished after removal. Regarding existing conditions of landscape, Becamex planted

some tree strips at the North along K1 Channel and at the West of the project. Remaining

area is lawn and empty land. Hence, site clearance will include the demolishment of those

structures, cutting some trees at the area in the construction items, site clearance in order to

prepare empty land for construction works.

In this phase, there are no significant impacts to the natural environment and local

economic conditions. However, during site clearance and demolishment of some

constructions, it will generate a high volume of construction materials of approximately

200-300 tons. This waste volume will be reused for backfilling during the construction

phase. In addition, waste generated from cutting some trees at the area of K1 Channel and

other construction items will be reused as firewood for construction workers or selling to

local people or giving for free.

3.1.2. Impact assessment and prediction during construction phase of the Project

Pollution sources related to environment:

Subject and scale of impacts will be presented in the following table:

Table 21. Subject and scale of impacts

NO. Subject Factor Scale

1 Construction phase

1.1 Pollution sources related to waste

Air environment Dust and emission from

transportation means

Average, short time,

controllable

Dust generated during

construction phase

Average, short time,

controllable

Noise of equipment,

machineries, construction

means

Average, short time,

controllable

Environment of

surface water, soil

and ground water

Bio-mass of cleaned plant Low, short time, controllable

Domestic wastewater Low, short time, controllable

Wastewater generating

from car washing, floor

cleaning

Low, short time, controllable

Wastewater during

construction phase

Low, short time, controllable

Page 65: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

58

NO. Subject Factor Scale

Domestic solid waste and

construction solid waste

Low, short time, controllable

Wasted oil and grease Low, short time, controllable

1.2

Impacts not related

to waste

Noise of equipment,

machineries, construction

means

Average, short time,

controllable

Impacts to transportation

activities of area

Low, short time, controllable

Impacts to surrounding

structures in the area

Low, short time, controllable

Impacts to religion, belief

and historical relics

Low, short time, controllable

Conflict between

construction workers and

local people

Low, short time, controllable

1.3 Environment

incident

Working accident,

Traffic accident

Fire, electric shock

Low, short time, controllable

Environmental impacts from above-mentioned pollution sources were addressed as negative

in low and average levels. And those impacts only happen during construction phase, so that

they were assessed as short time and internal characteristics.

A. Pollution sources related to waste

3.1.2.1. Pollution sources to air environment

In construction phase, impacts to the air environment are the highest. However, impacts

mostly concentrated in construction area and on roads for transporting excavation materials

and redundant backfilling, construction materials…

Air quality in this phase mostly was influenced by increasing concentration of dust and

other polluted substances such as NO2, SO2, CO, Total hydrocarbon (THC) generating from

construction activities such as:

- Leveling, excavation and backfilling according to designed elevation of construction

items, excavating foundation, channels, trenches to construct water supply, drainage,

power supply and telecommunication system.

- Activities of construction machineries that use diesel, emission of those machineries

contains NO2, SO2, CO, THC, dust.

- Activities of transportation means such as trucks to transport construction materials,

soil, sand and other materials to/from construction site. Activities of those means will

increase density of transportation on main roads of the project such as National Road

Page 66: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

59

No. 13 and Ring Road No. 4. It can lead to traffic jam in those roads at location

entrance of construction area and increase loading capacity of the waste on the roads,

particularly at location of construction area

- Inefficient transportation, storage and unload of construction, excavation and

backfilling materials will generate dust

a. Impacts by dust from leveling activities:

In general, topography of construction area is quite flat. Topographical elevation of

construction area fluctuates from 3 to 10 m. Topographical elevation of construction area

gradually reduce to K1 Channel in both the North and South of the channel. Topographical

elevation of construction area is mostly approximately 5-6m. Highest point is at southern

area of construction area with elevation fluctuate from 6m-10m. Hence, the project must

implement leveling for whole construction site to ensure designed elevation of facilities.

According to results of measuring calculation of designing consultant construction and site

investigation at construction site, leveling quantity will be calculated as follows:

Total necessary leveling area is 459,819.93 m2 that is the total construction area of

Vietnamese - German University (VGU). Excavating plantation of whole total will be

implemented at the average depth of 30 cm. Quantity is 76871 m3. This quantity will not

be transported out of the project area. This quantity will be kept for backfilling landscape

and growing trees. Hence, dust-generated source is only within the project area.

After excavating plantation, it will be backfilled to the designed elevation of facilities.

+ Quantity of excavation: 74,869 m3

+ Quantity of backfilling: 75,966 m3

+ Quantity of excavating facility foundation in Phase 1: 131,991 m3

+ Quantity of excavation facility foundation in Phase 2: 60,776 m3

Hence, in Phase 1:

Total quantity of excavation: 206,868 m3

Total quantity of backfilling: 152,837 m3

Quantity of redundant excavated soil needs to transport: 54,022 m3

In Phase 2:

Total quantity of excavated soil needs to transport: 60,776 m3

Hence, dust-generated source due to leveling activities mostly come from excavating

locations.

It is intended that backfilling duration of construction site, leveling and excavating

basement and foundation of construction facilities in each phase are approximately 6

months. Each month has 30 working days. Each working day has 8 working hours.

In average, when implementing excavation or backfilling 1m3 of soil will generate

approximately 0.75kg dust, in which 10% is suspended dust (Source: Environment in

Construction Activities Handbook – Ph.D. Nguyen Khac Cuong – Hochiminh Multi

Faculty University). It estimated the quantity of dust generated during leveling, and

excavating foundation for the facilities will be as follows:

Page 67: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

60

Table 22. Dust quantity generating from leveling process

Polluted factors Component Total

Phase 1

Excavating soil Volume of excavated soil (m3) 206,868

Dust Volume of dust generated (kg) 155,151

Generated dust (kg/h) 107,74

Suspended dust Volume of suspended dust (kg) 15,515

Volume of suspended dust

(kg/h)

10.77

Backfilling soil Volume of backfilling soil (m3) 152,837

Dust Volume of dust generated (kg) 114,627

Generated dust (kg/h) 79.6

Suspended dust Volume of suspended dust (kg) 11,462

Generated suspended dust

(kg/h)

7.96

Phase 2 Volume dust (kg/h)

Backfilling soil Volume of backfilling soil (m3) 60,776

Dust Volume of dust generated (kg) 45,582

Volume dust (kg/h) 31.65

Suspended dust Volume of dust generated (kg) 3.17

Volume of generated dust

(kg/h)

0.002

At present, dust concentration in construction area of the project is quite low (0.06 – 0.16

mg/m3), that is much lower than allowed standards for surounding ambient (allowed

concentration in an average of 1hour is 0.3 mg/m3). In the construction phase, dust

concentration will increase obviously and significantly. The measurement results of some

projects and when the wind blows strongly showed thatdust concentration insome

construction location, where is 50 m – 100 m far from the project site at the end of wind

direction, is at 20-30 mg/m3, that is 60 – 100 times higher than regulated standards for dust

concentration limits in surounding ambient environemnt (Centema, 2005). At present,

residential areasin the West of the project, there is only one household. The southern area is

the accomodation of old residential area with high population density. Being with main wind

direction of Southwest, the residential area in the West and the South of the project,

particularly households near the project border will be influenced by dust during site

excavation and backfilling. Besides, the dust in the construction site will direct affect to

construction workers in construction site. Therefore, during construction phase, contractor is

required to strictly apply mitigation measures to limit impact level to around ambient,

especially during the construction period of works in the Phase 2 of the Project when the

Vietnamese German University is operated stabily with aquite large number of students and

staff, the contractor is required to have a construction plan and use appropriate construction

Page 68: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

61

methods to minimize impacts on learning and living activities, as well as the operation of the

works under Phase 1 of the Project.

b. Dust,emission generating from transporting redundant soil out of the project area

In Phase 1, volume of excavated redundant soil after leveling and foundation excavation is

approximately 54,022 m3 equivalent 81,046 tons.

In Phase 2, volume of redundant soil needs to be transported is approximately 60,776 m3

equivalent 91,164 tons.

It is intended the transportation and disposal of redundant soil out of the project area will be

implemented during excavating and backfilling foundation of construction items in phase 1 is

6 months. If using 15-ton trucks, the number of transporting time to transport all quantity of

redundant soil out of the project site will be calculated as follows:

Table 23.. Summary of transport frequency

Transporting

quantity (ton)

Total time

(h)

Duration

(month)

Output

(truck/day)

Phase 1

81,046 5,403 06 27

Phase 2

91,164 6,077 06 30

According to technical documents, within about 10 km of trip, a truck will use

approximately 0.0025 – 0.003 tons of diesel. It assumed that the road is about 30 km long,

number of km for going and returning in a day and diesel quantity used during

transportation will be calculated as follows:

Table 24. Summary of amount of diesel for transportation

Number of km

(both arrival

and departure)

Amount of diesel

used /10 km (ton)

Diesel

quantity

used/day

(ton)

Phase 1 1620 0.0025-0.003 0.405-0.486

Phase 2 1800 0.0025-0.003 0.45-0.54

At present, there is no standards about polluted substances causing by transportation means

in Vietnam so that we referred to the documents of World Health Organization (WHO) on

rapid defining disposed source according to ―air pollution factor‖ to calculate air polluted

substances due to transportation of materials and waste. Preliminary calculation will be as

follows:

Page 69: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

62

Table 25. Total polluted substances during transportation of wastes

Polluted substance Pollution factor (kg

emission/ton diesel

used)

Disposing quantity

(kg/day)

Phase 1

Dust 4.3 1.74-2.09

SO2 20S 0.032-0.039

NOx 55 22.28-26.73

CO 28 11.34-5.51

VOC 12 4.86-5.83

Phase 2

Dust 4.3 1.94 -2.32

SO2 20S 0.036-0.040

NOx 55 24.75 -29.7

CO 28 12.60 -15.12

VOC 12 5.40 -6.48

S: % of S in fuel (approximately 0,4% in diesel and petroleum)

c. Dust, emission generating from transportation means of materials:

Construction materials include: sand, stone, brick, paving tile, cement, iron, paint, etc.

Total quantity of construction materials in Phase 1 of the project is about 693,924 tons,

Phase 2 is about 351,478 tons. It assumed that the construction duration of each phase is

about 2 years, the number of transportation time of the project will be about 92 times/day

in Phase 1 and about 60 times/day in Phase 2.

Table 26. Summary of material transportation time

Quantity

(ton)

Total

(time)

Duration

(month)

Output

(truck/day)

Phase 1

993,294 66,219 720 92

Phase 2

651,748 6,077 720 60

Transportation road mostly is National Road No. 13 and Ring Road No. 4. Hence, during

construction phase, it will increase transportation frequency in both roads, particularly

traffic jams at the entrance of the construction areas.

If transported distance of construction materials is about 30 km, diesel quantity consumed

in a day will be approximately 1.38 -1.66 tons in Phase 1 and from 0.9-1.08 tons in Phase

2.

Page 70: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

63

Table 27. Summary of diesel quantity used for material transportation

Number km (both

going and

returning)

Diesel quantity

used per 10 km

(ton)

Diesel

quantity used

per day (ton)

Phase 1 5520 0.0025-0.003 1.38-1.66

Phase 2 3600 0.0025-0.003 0.9-1.08

Polluted substances from transportation means of construction materials will be calculated

in the following table:

Table 28. Polluted substances from transportation means

Polluted substance Pollution

factor (kg

emission/ton

diesel used)

Disposed quantity

(kg/day)

Phase 1

Dust 4.3 5.93-1.66

SO2 20S 27.6-33.2

NOx 55.0 75.9-91.3

CO 28.0 38.64-46.48

VOC 12.0 16.56-19.92

Phase 2

Dust 4.3 3.87-4.64

SO2 20S 18.00-21.00

NOx 55.0 49.50-59.40

CO 28.0 25.20-30.24

VOC 12.0 10.8-12.96

Although quantity of construction materials is very high, material transportation to

construction site will be arranged to be suitable with construction plan. Material

transportation will be allocated during long time, not concentrated during some certain

time so that impacts caused by dust and emission from engine will be reduced

significantly.

Page 71: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

64

Table 29. The impacts of dust and emissions

Polluted

substance

Impacts

Dust - Causing rapid inhale, lung sclerosis, lung cancer

- harmful to skin, eye, intestine system

SOx, NOx

- Affects blood and respiratory system

- SO2 can be poisonous to skin, reducing blood alkali

- Creating acid rain, negative impacts to development of flora

- Increasing metal and concrete structure corrosion

- Negative impacts to climate, bios stem and ozone layer

CO

- Reducing oxidation transporting capacity in the blood to structure

and CO cells with hemoglobin and transferred into

carboxyhemoglobin

CO2

- Causing respiratory system malfunction

- Causing green-house effect

- Impact to bios stem

Total

hydrocarbon

- Acute poisoning: reducing, vertigo, headache, disturbing sensation

and fatality.

Diesel and

gasoline fumes

Gasoline fumes contain light hydrocarbon such as methane, propane,

butane, sulfur hydro. Poisoning level will be as follows:

- Concentration of gasoline fume from 45% above will lead to

suffocation due to lacking of oxidation. Inhaling gasoline fume will

get poisoning symptom such as drunk, convulsion, pneumonia, lung

abscess.

- If inhaling gasoline fume concentration of 40.000mg/m3, symptoms

will be acute such as chest pain, vertigo, disturbing sensation,

headache, nauseous, and vomit.

- Concentration of more than 60.000mg/m3 can lead to epilepsy, heart

attack, respiratory disorder, even fatality. In addition, sensitive person

with diesel can be influenced (scabies, hives, skin cancer).

c. Dust generated from road surface due to transportation means:

Dust generated from road surface will be from transportation means of soil and sand,

etc. Dust quantity and concentration depend on factors such as: speed of means, loading

capacity, quality and length of roads, number of truck tire and weather conditions, etc.

According to WHO (Assessment on soil, water, air pollution sources Part 1: Rapid

Assessment of environmental pollution, WHO, 1993), pollution factors of generated dust

from road surface (in dry season) due to transportation activities (in dry season) will be as

follows:

Page 72: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

65

Table 30. Generating dust factor due to transportation

Generating

source Type of road Unit

Generating dust factor

(kg/1.000 km/truck)

Transportation

activity

Stone road 1000km 3.7 x S x W0,7

x w0,5

Earth road 1000km 21 x S x W0,7

x w0,5

Paved road with

stone and asphalt,

width < 10m

1000km

15

Paved road with

stone and asphalt,

width > 10m

1000km

4.4

where

S: average speed (S= 40km/h).

W: average loading capacity (20 tons).

w: number of tire (w=10).

Dust from roads caused by excessive soil transportation from the project areas

Transporting redundant soil during leveling, construction of foundation and works is

mostly carried out on on asphalt pavement NH No. 13 and Ring Road No.4. It is

assumed that the average transport distance is 60 km (including arrival and departure).

Number of vehicles transporting in phase 1 are: 27 turns / day.

Number of vehicles transporting in phase 1 are: 30 turns / day

* Waste amount and concentration of dust:

Type of road Coefficient of dust

generation

Average amount

(g/m.s)

Wide asphalt

pavement > 10m

Phase 1

(kg/60km/27

vehicles)

7.128 0.0041

Phase 2

(kg/60km/30

vehicles)

7.920 0.0046

The concentration of dust arising from road surface is calculated by Sutton model as

shown as follows:

3

2

2

2

2

/2

)exp

2

)exp

.8,0)0,( mmg

hzhz

u

ExC

zzz

where

C = Emission (mg/m3).

Page 73: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

66

E= Load of source (g/m.s)

u = Average wind speed (u= 2m/s)

σz = Diffusion coefficient vertically:

Diffusion coefficient σz is a function of distance x and atmospheric stability is calculated

by the Slade formula:

σz= 0,53.x0,73

h: the height above the surrounding ground surface, select: h=0,5m.

z: the height calculated point, select: z=1m.

Page 74: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

67

Table 31. Results of calculated concentration of dust arising from abundant soil transport from the project areas

Distance (m) 1 2 3 5 10 50 100 200

Concentration of dust (mg/m3 Phase 1 0.174 0.010 0.004 0.0023 0.0012 0.0003 0.0002 0.0001

Concentration of dust (mg/m3) Phase 2 0.195 0.011 0.005 0.002 0.001 0.0004 0.0002 0.0001

QCVN 05:2013/BTNMT

(mg/m3)

0.3

The above results show that the concentration of dust arising from transporting of raw materials is much lower than the allowed limits.

Page 75: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

68

Dust concentration generating from road surface caused by transportation of

construction materials

Transporting construction materials coming out and in the project areas is carried out on

asphalt pavement NH No. 13 and Ring Road No.4. It is assumed that the average transport

distance is 60 km (both arrival and departure).

Number of vehicles transporting in phase 1 are: 92 turns / day.

Number of vehicles transporting in phase 1 are: 60 turns / day

* Waste amount and concentration of dust:

Table 32. Dust concentration generating from road surface

Type of road Coefficient of dust

generation

Average amount

(g/m.s)

Wide asphalt

pavement > 10m

Phase 1

(kg/60km/92

vehicles)

24.23 0.014

Phase 2

(kg/60km/60

vehicles)

15.84 0.0091

Similarly the calculation of dust arising from transporting of residual soil from the project

areas, the concentration of dust generated by the transport of construction materials also

use Sutton model. Calculation results are shown in following table.

Page 76: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

69

Table 33. Calculating results of dust concentration generating from road surface caused by transportation means

Distance (m) 1 2 3 5 10 50 100 200

Dust concentration(mg/m3

Phase

1 0.59 0.034 0.015 0.0081 0.0042 0.0012 0.00073

0.00044

Dust concentration(mg/m3)

Phase

2 0.387 0.022 0.01 0.0053 0.0027

0.0000007

9 0.00047

0.00028

QCVN 05:2013/BTNMT

(mg/m3)

0.3

From above-mentioned results, it shown dust concentration generating from road surface caused by transportation means is much lower than allowed

limits, except locations where is 1-2m from waste sources, the concentration of dust is higher or equal approximately to the permissible standards.

Page 77: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

70

3.1.1.2. Impacts to water environment

Including the following impacts:

a. Domestic wastewater of workers:

With the work quantity as mentioned in the project, it is expected that the during

construction phase at high peak, number of workers working in the construction site can

reach at 400 -500 people (including workers, guests and management staff). However, this

number will work on a shift basis and go home after working hours. There are not many

guardians and workers living at construction site. Hence, actual domestic wastewater will

reduce significantly. Water consumption of workers is estimated at an approximately of 60

l/person/day. Total estimated domestic wastewater of staffs and workers is approximately

20-30 m3/day according.

Therefore, the highest daily wastewater quantity in the construction phase can reach at

30m3/day discharged by about 500 construction workers.

Domestic wastewater mostly contains suspended solid (SS), organic substances

(BOD/COD), nutrient (N, P) and coliform that cause water pollution at the project area if

wastewater was direct discharged to the environment.

According to statistical data developed by the World Health Organization (WHO),

component and average concentration of polluted substances in domestic wastewater will

be as follows:

No. Pollutants Coefficient of discharge (g/c/d)

1 BOD5 45 – 54

2 Total suspended solid (SS) 70 – 145

3 Ammonia (N-NH4) 2.4 - 4.8

4 Total phosphate (P) 0.8 - 4.0

Source: Assessment on soil, water, air pollution sources Part 1: Rapid Assessment of

environmental pollution, page 155, WHO, 1993

The amount and concentration of pollutants in wastewater sources of workers working at

the site is calculated basing on the number of workers and wastewater flow.

Table 34. Component and average concentration of polluted substances in domestic

wastewater

NO. Parameter Unit Average

concentration

Vietnamese Norms

according to QCVN

14:2008/BTNMT

1 BOD5 mg/l 750 - 900 50

2 Total suspended

solid (SS) mg/l 1,167 -2,417 100

3 Ammonia (N-NH4) mg/l 40 -80 10

4 Total phosphate

(P) MNP/100ml 13 -67 10

Comparing to Vietnamese Norms, almost polluted substances in domestic wastewater are

higher than allowed norms many times. If not collected and treated, it will cause

Page 78: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

71

environmental pollution of surrounding area or it could be a pathogen to the workers on

construction site. If using septic tank at construction site, polluted load of organic

substances in wastewater can be reduced to 50-60 %. The wastewater volume can be

discharged into K1 channel.

b. Construction wastewater on site:

Wastewater from crushing and screening plants, construction materials, concrete mixing

station, boring holes with cement, sludge and sand, etc, clearing water and cooling water of

construction equipment and machineries contains leaking grease and oil, soil, sand.

Concrete mixing and car cleaning water usually contain high suspended solid and

contaminated other polluted substances such as solid waste, wasted oil and grease, leveling

materials and other waste. Estimated water quantity used in a day is approximately 20

m3/day.

Table 35. Component and average concentration of polluted substances in

construction wastewater

NO. Criteria Unit

QCVN

08:2008/BTNMT

B1 Column

1 pH - 5.5-9

2 TSS mg/l 50

3 Grease and oil mg/l 0,1

Source: Environmental Centre of Civil Construction University (CEETIA), 2005

QCVN 08: 2008 / BTNMT: National Technical Regulations on Quality of Surface Water

Comparing to the standard specified in Column B1, QCVN 08: 2008 / BTNMT - the

quality management standards of channel K1, the concentration of TSS in construction

wastewater is about 13 times higher. So, in order to restrict impacts on water quality in

channel K1, construction waste should be settled preliminarily to reduce TSS

concentration before being discharged into this channel.

c. Surface storm water:

Storm water on construction sites such as fuel storage, car parking, workshops or domestic

solid waste area without coverage will be contaminated by waste, grease, oil, organic

substances and chemicals from those locations that will lead to water and soil

environmental pollution.

According to Vietnamese Standards 7957-2008: Drainage - network and outdoor

construction, flow of storm water will be calculated as follows:

Qm = q .C .F (l/s.ha)

+ q: Calculated rainfall intensity, q = A (1 + lgP)/(t + b)n = 121.4 (l/s).

where t = 150-180 minute (rain duration).

At Binh Duong: using rainfall data of Hochiminh City to calculate:

A = 11650 (geographical parameter).

n = 0,95 (exponent coefficient according to region).

b = 32 (adjusted parameter according to region).

+ C: flow coefficient (selected C=0,58 due to hilly area).

Page 79: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

72

+ F: Total area F ~ 50.5 (ha).

+ P: 5 year (overflow frequency).

So: Qm= 121.4* 0,58 * 50.5 = 3.555 (l/s)

According to WHO, 1993, polluted concentration in surface storm water will be as

follows:

Table 36. Polluted concentration in storm water

No. Polluted

substance

Unit Concentration

1 Total N mg/l 0.5-1.5

2 Total P mg/l 0.004-0.03

3 COD mg/l 10-20

4 TSS mg/l 10-20

Source: Assessment on soil, water, air pollution sources Part 1: Rapid Assessment of

environmental pollution, page 155, WHO, 1993

In general, polluted concentration in storm water is small and less environmental impacts.

Comparing to the standard specified in Column B1, QCVN 08:2008 / BTNMT - the

quality management standards of channel K1, the concentration of pollutants in rainwater

is very small, hence, can be discharged into the K1 channel as well as into the rainwater

system of this area. However, if there is efficient coverage method for construction site,

storm water can wipe out less grease and oil, soil and sand to receiving bodies. Hence, it

needs to implement well domestic and construction waste on site every day.

3.1.2.3. Environmental impacts due to solid waste

a. Soil and sludge from excavating plantation:

During leveling process, it will implement excavating plantation on the ground with

thickness of 30cm and total area of 459,819.93 m2. Hence, total quantity is:

0.3m x 459,819.93 m2

= 76.871 m3

This quantity will be reused in tree growing area in the project campus.

b. Solid waste from construction phase:

Including construction waste, sand, stone, concrete, brick, sand, stone, wood, etc.

generating from construction site. Those types of waste can be reused (redundant iron bar,

cement bags can be sold to junk shops) or recycled. Hence, solid waste quantity is not high

and will be collected and disposed with redundant soil. Volume of redundant soil is

approximately 54.022 m3 in Phase 1 and 60,766m3 in Phase 2.

Affected area of construction waste is mostly at construction site that will be influenced to

internal transportation on site or accident to the workers so that it needs to clean

construction site and collect construction waste every day. Excavating soil shall be

collected clearly and a contract with Binh Duong Urban Environmental Company will be

signed to implement this work. Redundant soil can be reused as backfilling materials for

construction.

After completion of the construction, waste volume from removing sanitary facilities will

be created. However, this quantity is not very high because this is temporary construction

items, including temporary toilets and cabin at entrance of construction site, making by tin

and steel frame. This cabin can be removed to other place. Technical staff at Thoi Hoa

Page 80: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

73

Ward, or working unit on site can hire container office, putting at construction site for

working and resting. Hence, waste quantity caused by removing temporary construction

items is not too much.

c. Domestic solid waste:

Solid waste of workers working at construction site: highest daily quantity of workers at

construction site is 400-500 people. Total highest quantity of domestic solid waste during

construction phase is about (500 people x 0,5kg/person/day) = 250 kg/day.

d. Environmental impacts caused by hazardous waste:

During the construction phase, tar will be get generated from container and chemicals such

as: paint, sealant, etc. Those substances will seriously influence soil environment if they

won‘t be collected.

Wasted oil and grease is defined as hazardous waste according to the Circular No.

12/2011/TT-BTNMT. Wasted oil and grease can be generated from maintenance and

repairing processed of transportation and construction means in the project area. Referring

to surveyed results at HCM City, it is seen that:

- Lubricant discharging from transportation and construction means is about 7

l/changing time.

- Frequency of changing and maintenance times of machineries: average from 3

month/time.

- Number of construction machinery at high peak on site is about 45-50 car/day.

- Highest waste lubricant generating at the project during construction phase is from

105-116 l/month.

However, transportation means will change lubricant at garage and maintenance station.

Hence, actual lubricant waste at construction site will be much smaller.

3.1.2.4. Impact to soil environment

During construction phase, excavation and backfilling will break soil stability at two sides

of K1 Channel that lead to erosion.

If wastewater sources during construction such as construction wastewater, surface storm

water wiping out soil and sand, domestic wastewater of workers were not collected

according to procedures, they will be soil pollution sources.

Solid waste caused by construction activities such as concrete, waste, iron, tin, work form,

etc, domestic solid waste of workers, grease, oil and chemical leakage on the surface also

are soil pollution sources.

In the soil, those substances will change and become disintegrated that will destroy soil

structure, increase loading capacity and can influence humidity and ventilation. However,

most of project area surface will be covered by concrete and asphalt so that those impacts

are not significant.

B. Pollution sources not related to waste

3.1.2.5. Noise of transportation means and construction equipment

Noise in this phase is mostly caused by activities of transportation and construction means

and equipment. Reducing and increasing distance between people and machineries double

will increase and reduce the noise of 6dBA.

Page 81: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

74

Table 37. Noise of some construction equipment and machineries

No. Equipment Noise level at the distance (dBA)

7,5m 15m 30m

1 Bulldozer 99 93 87

2 Chainsaw 88 82 76

3 Diesel compressor 86 80 74

4 1.5-ton hammer 81 75 69

5 Diesel batch mixer 81 75 69

6 Pile driver 101-112 95-106 89-100

7 Roller 78-80 72-74 66-68

8 Compressor 81-93 75-87 69-81

QĐ3733/2002/QĐ-BYT 85 dBA

QCVN 26:2010/BTNMT 70 dBA

(Source: Air environment - Pham Ngoc Dang, 1997 and Mackenzie, L.da, 1985)

(Note: QĐ3733/2002/QĐ-BYT: Decision of the Minister of Health on issuing 21

occupational health standards, 05 principles and 07 parameters of occupational health)

Hence, overall noise for each construction equipment on site can be anticipated at an

approximately of 70-112 dBA. Comparing to allowed noise standards at public area, this

noise is quite loud.

From above table, if construction equipment at the area is one place, total noise of

construction equipment is: Lo=10.log n

Li

1

.1,010 (according to Pham Ngoc Dang – Air

environment, 1997).

where:

- Lo: Overall noise

- n: Total noise source

- Li: Source number i.

From above formula, it can calculate highest noise on site of 112.3 dB.

To forecast noise of construction equipment at the area to surroundings, we calculated

noise transmission as follows:

This noise level is typical source at height of 1,2 - 1,5m, comparing to road surface at the

distance r1, noise of r2> r1 will less than the noise at the distance r1 a Figure of L (dBA)

according to the following formula (Pham Ngoc Dang, Air environment, Technique and

Science Publisher, 1997):

- If noise source is a point: L = 20 lg (r2/r1)1+a

(dBA)

- If noise source is a road: L = 10 lg (r2/r1)1+a

(dBA)

Page 82: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

75

In which: a is affected coefficient of terrain to absorb and reflect noise.

With: a= - 0,1 with asphalt and concrete road surface

a= 0 with empty land, no tree.

a= 0,1 with lawn

Selected a= 0. Most of means and equipment on site have narrow space so that noise

source during construction phase is a point. From assumed data as mentioned above,

calculated results will forecast that the noise will be reduced according to the distance from

project area to surroundings as follows:

Table 38. Anticipated noise transmission during construction phase

Reduced noise according to the distance (dB)

10m 20m 30m 40m 50m 60m 70m 80m 90m 100m 150m 200m 250m 300m

109.55 102.93 99.05 96.31 94.17 92.43 90.96 89.68 88.56 87.55 83.68 80.93 78.80 77.05

* Comments: From above-mentioned table, the noise from construction equipment is over

allowed standards at construction site and will influence the surrounding areas. Details:

Within radius of 100 m, the noise is over standards for labour environment. Within radius

from 150-300 m, the noise is over standards for surrounding environment.

Table 39. Vibration of construction means

No. Construction equipment Vibration at 10m (dB)

1 Bulldozer 79

2 Air compressor 81

3 Concrete pile driver 98

4 Truck 74

5 Batch mixer 88

6 Crane 86

7 Driller 95

Source: US Road Department

Project area is next to Thoi Hoa 5C Hamlet Residential Area to the South and Thoi Hoa 3

Hamlet Residential Area to the West. Hamlet 3 Residential Area is a new area with 2-3

households only. The Residential Area at the South of the project is old and crowded,

however, the project is not constructed near the residential area, therefore, the construction

does not have effects to households nearby caused by noise and vibration. However, the

construction of items in Phase 2 will likely affect buildings of Phase 1, as such items,

buildings of phase 2 are located next to, or very close to the works of the Phase 1.

Therefore, it is necessary to apply appropriate construction methods to minimize noise and

vibration caused to buildings of the Phase 1 as well as the learning, teaching and activities

of students and officers of the Unversity during the course of construction.

3.1.2.6. Impacts to religion, relief and historical relics

Because this project is located in Thoi Hoa Industrial Zone and Residential A, there is no

impact of this project to religion, relief and historical relics. However, at the West of the

project, next to D9 Road, about 100m of distance away from D9, there is a new small

Page 83: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

76

temple constructed by residential areas no.3 and no.5. The width of small temple is 20 m2,

is constructed on 100m2 of land area so it should be considered during construction phase.

3.1.2.7. Impacts to surrounding architecture and infrastructure

Except southern area of the project, next to existing residential area, there are some

households at Hamlet 3 Residential Area at the West, the North, next to Ring Road No. 4

and the East next to National Road No. 13. Hence, there are not so many people

surrounding project area and not so much architecture and infrastructure next to

Vietnamese - German University (VGU) project area so that impacts to surrounding

architecture are not high in Phase 1. However, during the construction of phase 2, some

buildings and works of Phase 1 and Phase 2 are located near or adjacent to each other,

some buildings and works of Phase 1 will have a high risk of being cracked or sunk unless

reasonable construction measures are applied. Therefore, during construction phase,

Project owner will require construction contractor to implement construction method in

effective manner and cover construction site to reduce maximally impact to works in Phase

1, particularly for D9 Road at the West of the project. Project owner will commit to take

full responsibility for generating impacts to surrounding constructions due to construction

activities of Vietnamese - German University (VGU) project.

3.1.2.8. Impacts to transportation

Construction area of Vietnamese - German University (VGU) project locates at

intersection between Ring Road 4 and National Road No. 13. People mostly locate at the

South, the North (at other side of Ring Road No. 4) and a newly established Eco Lake

residential area – a sparse population - to the East at the other side of National Road No.13.

They are new residential area and not so much people. Hence, construction works do not

affect much to people living in surrounding area 1. However, material transportation will

increase traffic density surrounding project area (it is 92 times/day at high peak as

estimation), particularly at National Road No. 13 that is main road from Hochiminh City,

Thu Dau Mot to Binh Phuoc Province. They influence transportation means and travelers

on National Road No. 13. Using big trucks will obstruct vision of travelers and occupy

most of total traffic area on this road, particularly at entrances of construction site. At those

locations, transportation means will enter construction site, turn on National Road No. 13

and Ring Road No. 4 that will create traffic jams. It shall install traffic signal and

controller to reduce traffic accident. Transportation process of Project construction

material shall be used heavy-duty trucks, causing risks of landslide and damage of

Highway 13 and beltway 4, especially in project surrounding areas. hence, there need to

carry out correctly the regulations on allowable load for each kind of construction vehicles

to mitigate the damage of road

3.1.2.9. Impacts to security and socio-economic conditions

Security: usually, concentration of workers at construction site can create conflict between

worker and local people and increase local security. Being with large number of workers

on site, sometime it can be 400-500 workers, security in the area shall be considered

carefully. In order to reduce those impacts, contractor can hire local laborers and closed

management of workers on site. It shall register permanent and temporary residence. The

workers must have entrance card to get in and out construction site and contractor shall

coordinate with management agency to manage people according to the laws.

Facilities: movement of workers, and removing construction machinery and equipment,

and transporting material will increase traffic flow that affects to the roads.

Concentration of construction workers also will increase frequency of facility usage, and

will damage public facilities in the area.

Page 84: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

77

Construction phase will increase power supply and water supply so that it can lead to

overload and lacking water and electricity in the area.

Economic: the project will mobilize labour in the locals so that it can contribute to create

jobs and income of laborers;

Encouraging some services such as restaurant and other relaxation for workers at the

project area.

3.1.3. Impact assessment during operation phase

During operation phase of university, impacts to the environment mostly are presented in

the following table:

Table 40. Subjects and scale of impacts

No. Subjects of

Impacts

Factor

Scale

1.1 Impacts related to waste

Air environment Emission from transportactivities Low, long-term, unavoidable

Emission from emergency generator Low, short time, controllable

Chemical vaporfrom laboratory

Odor from wastewater treatment

system

Low, long-term, controllable

Discharging aerosol from wastewater

treatment system

Low, long-term, controllable

Odor from kitchen Low, long-term, controllable

Odor from toilets Low, long-term, controllable

Odor from solid waste storage, sludge

from wastewater treatment plant

Low, long-term, controllable

Environment of

surface water, soil

and ground water

Domestic wastewater from buildings Low, long-term, controllable

Wastewater from laboratory Average, long-term, controllable

Wastewater from kitchen Low, long-term, controllable

Domestic solid waste Low, long-term, controllable

Solid waste generating from

laboratory

Average, long-term, controllable

Other solid waste from old and

damage equipment

Low, long-term, controllable

Expired chemicals in laboratory or

discarding after experiment

Average, long-term, controllable

Exceeded sludge from wastewater Average, long-term, controllable

Page 85: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

78

treatment system

Use pesticides to protect and prevent

pets

Fertilizer use to take care of trees,

flowers and grass

Insignificant, long-term

1.2 Impacts not related to waste

Noise Noise generating from transportation

means

Low, long-term, controllable

Socioeconomic

conditions in

locality

Business and service activities

Social orders

High, long - time, controllable

1.3 Environment

incidents

Leak chemicals for wastewater

treatment system (chlorine), leak gas

for cooling, compressed gas in

laboratory, leak chemicals in

laboratory

High, short time, controllable

Fire and explosion High, short time, controllable

Working accident High, short time, controllable

A. Impacts not related to waste

3.1.2.1. Impacts to air environment

a. Dust and emission generating from transportation means

At entrance and garage: activities of transportation means such as taxi, vehicles for staff

and students... can create emission including dust and poisoning gases such as SO2, NOx,

CO, VOCs.

According to project phase out, in Phase 1, there are 5,000 students and 500 teachers and

staffs. In Phase 2, there are 12,000 students and about 1,200 teachers and staffs

Table 41. Summary of number students and staffs at Vietnamese - German

University (VGU)

Students Teachers Non-resident

students

Non-

resident

teachers

Phase 1 5,000 500 250 450

Phase 2 12,000 1,200 600 1808

Assumed there are 10% teachers using car, 100% students using motorbike and number of

car of guest working at university of about 10%, number of motorbike of about 10%

number of motorbike of teachers and students of university. Total transportation means at

university at high peak hours such as morning, noon and afternoon will be estimated as

follows:

Page 86: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

79

Table 42. Summary of transportation means of students and staffs at Vietnamese -

German University (VGU)

Car Motorbike

Phase 1

Teachers‘ 45 405

Students‘ 250

Guests‘ 5 33

Total 50 688

Phase 2

Teachers‘ 216 864.00

Students‘ 600.00

Guests‘ 22 73.20

Total 238 1,537

According to rapid polluted assessment Figure of World Health Organization (WHO) in

1993, types of transportation means will be as follows:

Table 43. Pollution factor of transportation means

Type of vehicle Unit (U) Dust

(kg/U)

SO2

(kg/U)

NOx

(kg/U)

CO

(kg/U)

Big, diesel engine,

3,5-16 tons 1,000km 0.9 4.29S 11.8 6,0

Motorbike (50-

175cc) 1,000km 0.12 0.6S 0.08 22

According to pollution factor do US Environmental Management Bureau (USAPA) and

World Health Organization (WHO) in 1993, it can calculate emission load from those

types of vehicles as follows:

Table 44. Polluted load from material transportation means (mg/m.s)

Phase 1

Polluted

substance

Load from 50

vehicles (3,5-16T)

Load from 688

motorbike

Total

Dust 0.01250 0.02 0.03562

SO2 0.01492 0.03 0.04358

NOx 0.16387 0.02 0.17917

CO 0.08331 4.20 4.28775

Phase 2

Polluted

substance

Load from 238

vehicle (3,5-16T)

Load from 1537

motorbike

Total

0.0595 0.05 0.1111

Page 87: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

80

0.0710 0.06 0.1350

0.7800 0.03 0.8142

0.3965 9.39 9.7893

To calculate polluted substance generating from emission of transportation means during

this time, assuming road length is unlimited, polluted concentration on the ground at

distance x on direct wind direction axis with road will be defined according to the

following formula (Tran Ngoc Chan- Air pollution and emission treatment, volume 1-

2002).

3

23

/2

1XP

2

10.2)0,( mmg

HE

u

MxC

Zz

In which:

C = Emission concentration (mg/m3).

M= Load of pollution source (g/m.s)

u = Average wind speed (selected u= 2m/s)

σz = Diffusion factor according to vertical axis:

Diffusion factor σz is function according distance x and atmosphere stability will be

calculated according Slade formula:

σz= 0,53.x0,73

H = high difference between road surface to ground level (m) (selected H = 0,5m).

Polluted substance generating from the road will be as follows:

Table 45. Calculated results of polluted substance from transportation means

Phase 1

Distance x (m) Polluted concentration (mg/m3)

Dust SO2 NOx CO

1 0.02263 0.02806 0.04108 3.72773

2 0.01207 0.02245 0.04931 1.98890

3 0.00965 0.01197 0.039425 2.38530

5 0.01046 0.01296 0.02846 1.72196

10 0.00648 0.00803 0.01175 1.06661

20 0.00394 0.00326 0.0107 0.64941

50 0.00203 0.00251 0.00552 0.33405

100 0.00123 0.00151 0.00333 0.20159

200 0.00049 0.00061 0.00201 0.24316

QCVN

05:2013/BTNMT

0,3 0,35 0,2 30

Page 88: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

81

Phase 2

Distance x (m) Polluted concentration (mg/m3)

Dust SO2 NOx CO

1 0.07058 0.0869 0.1867 8.5108

2 0.03766 0.0696 0.2241 4.5409

3 0.03011 0.0371 0.1792 5.4459

5 0.03261 0.0401 0.1293 3.9314

10 0.02020 0.0249 0.0534 2.4352

20 0.01229 0.0101 0.0488 1.4827

50 0.00633 0.0078 0.0251 0.7627

100 0.00382 0.0047 0.0151 0.4603

200 0.00154 0.0019 0.0091 0.5552

QCVN

05:2013/BTNMT

0,3 0,35 0,2 30.0000

(Note: QCVN 05:2013/BTNMT: National Technical Norm on quality of surrounding

ambient.)

Hence: from above results, it shown that polluted substance generating from transportation

means is lower than allowed standards.

b. Dust and emission generating from emergency generators

To provide electricity to university in case of power cut, project will install generators

0.4KV. Total consumed capacity is 8.25MVA (5.5 MVA for Phase 1 and 2.75 MVA for

Phase 2).

Emission

Fuel consumption of generators will be based on capacity and activities

In normal condition, emission generated when fully burning 1 l of DO oil is about 26 m3

Fuel quantity and emission when operating generators will be estimated as follows:

Table 46. Consumed fuel and emission of generators

Capacity Consumed DO oil

(l/hours)

Emission

(m3/hours)

Phase 1 5.500KVA 1.485 38.610

Phase 2 2.750KVA 742 19.305

Load and polluted concentration

Generator uses DO oil (0.05S), emission generating from generators mostly is SO2, NOx,

CO and dust. Discharging coefficient of polluted substances from generator was referred

from “Assessment of soil, water and air pollution source‖ - Part 1 Rapid Assessment of

Environmental Pollution of World Health Organization (WHO) in 1993.

Page 89: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

82

Table 47. Discharging coefficient of polluted substances from generator

Polluted substance Discharging coefficient

(kg/MWh)

TSP 0.369

SO2 10.4S

NOx 5.01

CO 1.14

VOC 0.415

(Source: WHO, 1993)

Based upon emission, discharging coefficient of polluted substances, predictable volume

of generator room (50m x 4 m), load of pollution and pollutants from emergency generator

of Vietnamese - German University (VGU), it will be anticipated in the following table:

Table 48. Load and polluted concentration from emergency generator of Vietnamese

- German University (VGU)

Polluted substance Dust (TSP) SO2 NOx CO VOC

Phase 1

Load (g/h) 2.030 2.860 27.555 6.270 2.283

Concentration (mg/m3) 0.010 0.014 0.138 0.031 0.011

Phase 2

Load (g/h)

Concentration (mg/m3) 1.015 1.430 13.778 3.135 1.141

QCVN

05:2013/BTNMT

(average of one hour)

(mg/m3) 0.005 0.007 0.069 0.016 0.006

(QCVN 05: 2013/BTNMT: National Technical Norms on ambient air environment)

Calculated results shown that polluted concentration in emission is lower than allowed

limits (average of 1 hour) the in QCVN 05:2013/BTNMT. In addition, those generators

only operate in case of power cut. In the condition of power supply at Binh Duong, power

cut possibility is maximally 1 day/month. Hence, total polluted load from generators will

be considered as insignificant. Hence, natural ventilation method is applied, instead of

installation of an emission treatment system for those generators.

c. Emission from laboratory

Laboratory of Processing and Environment Faculty will use odorous, toxic chemicals such

as chlorine, CH4, H2S, acids, and some different compressed air. Even though the amount

of such compressed air discharged during implementing experiments is minor, it will

directly affect the health of students and staffs working here. In order to reduce impacts of

toxic chemical vapor, mitigation measures such as natural ventilation design, scientific

arrangement of working tables, installation of toxic gas suction devices and eliminators at

the bottle opening positions, using of chemicals containers and other laboratory operations

shall be applied.

Page 90: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

83

d. Odor from canteen

Canteen, particularly at cooking place will be influenced by odor of oil, grease and food.

Therefore, it is necessary to apply natural ventilation method with expected results and

install de-odor and suction system.

e. Odor from waste storage and centralized wastewater collection and treatment system

This area will be influenced by odor caused by organic substances in digestible solid waste

and wastewater. Hence, waste storage will be designed according to the standards, and

collection and transportation of solid waste shall be implemented in daily basis to limit

impacts by odor from solid waste.

For wastewater collection and treatment system, centralized wastewater treatment plants

odors will disperse unpleasant smells due to the formation of NH3, H2S - odorous gases.

However, results of monthly monitoring of environmental quality in Bay Mau Lake

WWTP with capacity of 13,300 m3/day under the " Hanoi Drainage Project for

Environmental Improvement, 2nd

Project" showed that the concentration of NH3, H2S

odorous gases is not high, and falls within permissible limits. As a result, flow discharged

from the centralized wastewater treatment plant of the Vietnamese German University is

assessed not to be high. However, NH3, H2S gases are causing unpleasant smells, odor

minimization measures and odor treatment will be applied to limit the affect to activities of

students and officers of the University.

Table 49. Concentration of NH3, H2S - odorous gases Nin the WWT area

No. Analysis

parameters

Unit Results QĐ

3773/2002/QĐ-

BYT K1 K2 K3

1 NH3 mg/m3 0.074 0.053 0.002 17

2 H2S mg/m3 0.008 0.012 <0.001 10

Source: 3rd Quarter Environmental Monitoring Report, Bay Mau Lake WWTP under

Hanoi Drainage Project for Environmental Improvement, Project 2, in 2015

Note: QĐ3733/2002/QĐ-BYT : Decision of the Minister of MOH issuing 21 labour

sanitary standards, 05 rules and 07 labour sanitation papameters.

f. Toilets:

For public toilets at University, due to high number of students, if those toilets were not

managed and monitored well by daily cleaning, they can create disturbing odor and create

environment for flies, mosquitoes and pathogens, affecting to air environment and health

of teachers, students, guests and staffs.

3.1.2.2. Impacts to water environment

a. Domestic wastewater

Total wastewater was calculated as over 80% domestic water supply sink, including

wastewater from sinks, toilets, floor, kitchen…The maximum volume of domestic

wastewater need to be treated in Phase 1 is: 737 m3/day. The average wastewater amount is

567 m3/day. It is expected that the amount of wastewater will be highest of 1.762 m3 /day

discharged from works in phase 2 and the average is 1.35 m3/day.

So, domestic wastewater amount of 737 m3/day (Phase 1) and about 1.762 m3/ day (phase

2) will lead to the water environment pollution in the area if it is discharged directly into

the environment.

Page 91: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

84

According to Tran Duc Ha Researching Report B94-34-06, polluted concentration in

domestic wastewater will be as follows:

Table 50. Polluted concentration in domestic wastewater

No. Criteria Unit Concentration QCVN

14:2008/BTNMT

1 BOD5 mg/l 250 50

2 COD mg/l 315 -

3 TSS mg/l 270 100

4 TDS mg/l 750 -

5 NH3 mg/l 32 10

6 PO43-

mg/l 12,5 10

7 Coliform MNP/100ml 13.106

5.000

For wastewater from toilet, according pollution factor of World Health Organization

(WHO), volume of polluted substances in untreated domestic wastewater including toilet

wastewater discharged per each person/day will be as follows:

Table 51. Quantity polluted substances in wastewater toilet

Polluted substance Quantity (g/person/day)

BOD5 45-54

COD 72-102

SS 70-145

Grease and oil 10-30

Total N 6-12

Ammonia 2.4-4.8

Total P 0.8 – 4.0

At present, in the market, there are many high standard sanitary equipment with low water

consumption. University will invest that equipment to ensure sanitary conditions and

saving water.

Concentration of domestic wastewater is very high and cause negative impacts to

environment if direct discharging to the environment. To mitigate those impacts,

wastewater from toilet will be treated by 3-chamber septic tank then connect to combined

sewerage system to the centralized wastewater treatment plant.

b. Laboratory wastewater

Besides high volume of domestic wastewater, there is a small volume of wastewater from

laboratory, mostly from Processing and Environment Faculty. This wastewater contains

chemicals during testing. Lab wastewater contains very small amount of chemicals,

including liquid waste (is the solution used for chemical reactions) and water cleaning one

time laboratory instruments. This wastewater amount depends on the needs of scientific

research and its frequency of experiments of students. It is supposed that 200 students do

Page 92: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

85

testing each day, each student use estimated amount 10 litersof wastewater containing

chemicals. So, total amount of wastewater containing toxic chemicals is about 02 m3/day.

Laboratory wastewater is featured by acidic or alkaline, containing metal ions, organic

substances, etc. Composition, nature and concentration of pollutants in laboratory

wastewater will vary according to the frequency, the purpose of implementation of various

samples. Analysis results of 01 laboratory wastewater sample taken by the Institute of

Science and Technology and Environment, Hanoi University of Science and Technology

shows that concentrations of metals are as follows:

Table 52. Concentrations of a number of metals in laboratory wastewater

Name As Cd Cu Fe Pb Zn Ni Mn

Concentration

(mg/l)

0.12 0.15 1.75 25.5 0.0029 0.1 0.031 5.3

Source: Lac Viet Investment, Environmental Technology and Engineering Infrastructure

JSC, July 2015

Wastewater of other experimental division of other faculties such as faculty of engineering

production and mechanics is generated by cooling process, cleaning of equipment and lab

equipment. This source of wastewater is not toxic and can be discharged into the combined

drainage system.

Wastewater sources having same types of pollutants shall be separated and taken to

primary treatment clusters under each building where labs are located.

It estimated that wastewater discharged from laboratory wastewater is approximately

5m3/day in Phase 1 project and about 10 m

3/day in Phase 2 of the project.

In order not to influence treatment process of centralized wastewater treatment plant,

laboratory wastewater will be treated preliminarily before connect to combined sewerage

system than to treatment plant.

c. Wastewater from medical center

Wastewater discharged from medical facilities, health centers and hospitals usually

contains a lot of toxic contaminants like blood, treatment chemicals, parasites, etc.

However, the University‘s medical centeronly provide examination, medicines or

injections, infusions, treatment of common diseases like colds, digestive ..., doesnot

perform surgery, treatment of particulardiseases, or use chemicals in treatment. So,

wastewater arising from this medical center is not hazardous. Wastewater in the area is

connected directly to the combined drainage system of the building, then to the centralized

wastewater treatment plant.

d. Wastewater from kitchen

Wastewater from kitchen contains high volume of oil, grease and cleaning chemicals.

Wastewater from this area will be pre-treated before connecting to combined wastewater

collection system of the project.

e. Surface storm water

Surface storm water according to the regulation is clean water. However, in the university

area, it can be polluted due to solid waste, leaked grease and oil. Hence, surface storm

water can directly be discharged to the environment after separating solid waste by

screened manholes and then flowing via channel to K1 Channel within the university area.

For the area planting flowers, trees and grass in university campus, if using too much

chemical fertilizers and pesticides in the area, rainwater runoff through the area may have

Page 93: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

86

the risk of pollution caused by the penetration of plant protection chemicals as well as

increasing the risk of environmental contamination of soil and groundwater. However,

through discussions with VGU, method of care of trees, flowers in university campus

primarily is watering daily, combined with use of bio-fertilizers. In the case of detection of

pets will use biologic medications to reduce to the environmental pollution, especially the

limit of spread of chemical ordors. So it could be said the impactson water environment by

use of pesticides, crop protection chemicals and chemical fertilizers are negligible.

3.1.3.3. Source generating solid waste

During daily activities of VGU, it will generate waste that will be categorized as follows:

a. Non-hazardous waste:

This waste mostly is domestic solid waste from office, kitchen, restaurant, student

dormitory, teachers‘ houses, guest house and other public areas such as sport area, parking

lot, park, etc. Main component of these waste is solid waste, food (80%), gardening (cut

tree, grass), paper, newspaper, plastic bottles, glass, etc…

Taking reference from the theme on environmental protection of Hanoi Science and

Technology University, estimated domestic solid waste of VGU is shown in the following

table:

Table 53. Estimated domestic solid of VGU

Item Quantity Discharging

coefficient

per capita

(kg/person/day)

Daily solid waste

quantity

(kg/day)

Phase 1

Students 5,000 0.75 3,750

Lecturers 500 0.50 250

Guests 100 0.50 50

Staff 100 0.50 50

Phase2 4,100

Students 12,000 0.75 9,000

Lecturers 1,200 0.50 600

Guests 100 0.50 50

Staff 100 0.50 50

9,700

Total daily domestic waste quantity (kg) 13,800

b. Hazardous waste

Waste considered as hazardous waste shall be separately collected and treated according to

requirement on managing hazardous waste, including:

- Reacted chemicals from laboratory

- Grease and oil, lubricant from maintenance activities

- Broken electrical equipment such as lamp, computers and boards

Page 94: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

87

- Damage battery

- Sprayer

- Sludge from wastewater treatment system

- Broken lamp bulb

- Some medical waste such as wounded dressing, injector from health care room of

university.

The emission of such wastes is low and is not generated frequently. Refer to an

environmental protection scheme of Hanoi University of Science and Technology and the

scale of the project, hazardous waste of the project is estimated as follows:

Table 54. Estimated hazardous solid waste quantity

Code Toxicity Phase 1

(kg/month)

Phase 2

(kg/month)

Code

100 200

1 Waste from laboratory:

020101 Waste sulfuric acid, sulfur acid AM, OH, Đ,

ĐS

020102 Waste hydrochloric acid AM, Đ, ĐS

020103 Waste hydrofluoric acid AM, Đ, ĐS

020104 Waste Phosphoric acid, acid

phosphorous

AM, Đ, ĐS

020105 Waste Nitric acid, nitrous acid AM, N, OH,

Đ, ĐS

020106 Other waste acid AM, Đ, ĐS

020201 Waste sodium hydroxide,

ammonium hydroxide, potassium

hydroxide and residue containing

sodium hydroxide, ammonium

hydroxide, potassium hydroxide

AM, Đ, ĐS

020202 Other waste bases AM, Đ, ĐS

020302 Salt and Saline solution

containing heavy metals

Đ, ĐS

020303 Waste Metal oxides containing

heavy metal

Đ, ĐS

020403 Other wastes containing heavy

metal

Đ, ĐS

020501 Sludge with hazardous

constituents from wastewater

treatment process

Đ, ĐS

070101 Waste acid detergent AM

070102 Other waste acid detergents AM

070103 Waste Base detergents AM

Page 95: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

88

070401 Welding electrodes containing

heavy metals or other harmful

components

Đ

070402 Welding slag containing heavy

metals or other harmful

components

Đ

2 Hazardous medical waste 50 100

130101

Contaminants LN

130102

Waste Chemical containing or

having hazardous components

Đ, ĐS

130103 WasteCytotoxic pharmaceutical Đ

3 Waste grease, lubricants,

refrigerant

5 10

170601

Exhausted fuel oil and diesel C, Đ, ĐS

170602 Waste Petroleum C, Đ, ĐS

4 180201 Wiper with grease and oil Đ, ĐS 10 20

5 160113 Electric solid waste Đ, ĐS 50 100

6 160112 Battery Đ, ĐsS, AM 20 50

7 160105 Sprayer, chemical bottles Đ, ĐS 50 100

8 160106 Malfunction flourescent light Đ, ĐS 5 10

Total 540 1340

Note: Characteristics of hazardous waste (AM: Corrosion; OH: Oxidation; Đ: toxicity; ĐS:

ecological ecotoxicity; N: Explosive; C: Flammability, LN: Infection)

B. Impacts not related to waste

3.1.3.4. Noise

Noise generating from the following sources:

- Noise due to activities of transportation means: from engine and vibration of

vehicle parts, from exhausted pipe, from vehicle doors, etc

- Noise from human travelling and speaking...

- Noise from pumps, motor, generator,..

This noise depends on type, density and space of vehicle parking lot.

Refer to documents; noise of different vehicles is different:

Page 96: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

89

Table 55. Noise of vehicle

Type Noise (dBA) QCVN 26:2010/BTNMT

Small bus 79

70 dBA (6h-21h)

55dBA (21h-6h)

Mini bus 84

Sport car 91

Motorbike with 2 cylinder

and 4 phases

94

Motorbike with 1 cylinder

and 2 phases

80

(Source: Pham Ngoc Dang, Air environment, Technical and Scientific Publisher, 1997)

QCVN 26:2010/BTNMT: National Technical Norm on noise)

Normally, noise reduction on the road depends upon distance, so if the distance from

listener to noise source is increased by two times, sound intensity will reduce to ¼ and

noise level will reduce to 6dBA.

Hence, comparing to allowed noise, noise of vehicles is over allowed standard. However,

noise of transportation means mostly happens during the day and for short time. This noise

mostly affected at the entrance and garage, and no significant impact to other areas.

- For noise caused by human travelling and talking, there is no significant impact.

- For noise at electric and mechanic equipment, it can be high such as at the area of

motor.

3.1.3.5. Impacts to socio-economic conditions

Negative impacts

- This project plays a key role in developing and improving quality of higher

education in Vietnam in general and in particular Pacific. This is a university of

technology based on German model that is known over the world and successfully.

The project aims to become the leading research university and this will impact

positively on national education system. Besides, project is likely to attract and

create jobs for intellectual human resources in the region.

- Good conditions to develop culture, improve regional education level

- Contribute to create jobs for some local people, increase income and improve living

standard from services such as food, entertainment, restaurant, hotel…

Negative impacts

- The increase in a large number of businessmen, traders can lead to security

disorder, increase in social evils, and risk of traffic accidents accordingly.

3.1.4. Assessment and forecast of impacts caused by risks and inccidents of the project

3.1.4.1.Impacts caused by risks and inccidents in construction stage

a) Labor safety:

The following may cause accidents in the course of construction:

Page 97: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

90

- Environmental pollution will likely affect health of worker working at the site.

These phenomenon may occur such as: dizziness, fatigue, and even faint (often

occurring to women workers or people who have weak health).

- Travelling of transport vehicles at the construction site may lead to traffic

accidents.

- Operation of motor vehicles like cranes, unloading equipment, high-piled materials

may fall down and broken which maycause labor accidents.

- Construction on high floors if not secure can increase the likelihood of accidents

caused by falling and slipping from scaffolding, on-going construction buildings, ...

- Bolts, lightning wire zinc, saw blades and other small metal objects can be

scattered over internal roads of the project areas during the construction period and

it is hard for workers to able to avoid stepping on them.

- Accidents may occur deriving from contacting electrical sources such as

construction of electrical supply system, colliding on horizontal power lines ...

b) Risks of causing fire:

The construction of big items can have many causes of fires, such as:

- Temporary houses of workers may be burned if the workers are not careful while

cooking, smoking, buring during the construction of the plan.

- Fuel sources that easily cause fire and explosion such as (FO, DO) are available at

the site.

- Other fires may occur in the case of short circuit, lightning.

c) Risk due to UXO

In this project, the arising risks of remaining bomb definitely are no because (i) in process

of backfilling and construction of Thai Hoa industrial zone and residential area, Investor

Becamex have already carried out measures of searching and detecting bombs, (ii) after

Becamex handed over to Vietnam-Germany university construction project, PMU made a

contract on searching and detecting bombs again for entire area of the project with 20

meter of land depth. This contract has finished in 2013s

3.1.4.2. Impacts caused by risks and inccidents in the operation stage

a). Fire

- Explosion may occur in the laboratory depending on the ways to keep and do

testing with chemicals, chemical overflow causing or chemical safety issues.

- Potential fires may happen due to short circuit and electric burning.

- Fire and explosion may be caused by gas leakage in the kitchen or the use of gas,

compressed air in laboratory.

- Inccidents may occur at wastewater treatment areas because untreated wastewater

is discharged into K1 channel and lead to the pollution of K1 channel water, and

affect directly to the water sources of Tinh river.

b). Traffic inccidents

Traffic congestion may occur in the following cases:

- At peak hours, a large number of students going to and leaving school may cause

local traffic jams at the school gate on the NH. No. 13, Ring Road No.4.

Page 98: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

91

- Traffic accidents in the area.

- Traffic inccidents will affect the aethsitic in the area as well as traffic activities and

daily life of people.

c) Potential impacts on community health

When VGU is put into operation, a large number of students and staff members will

concentrate here. They come from many different regions nationwide and may contract

various types of diseases if rules on hygiene and disease prevention are not implemented

strictly. This risk does not only happen with students, officials of the University but also

can spread to the community surrounding the University and Thoi Hoa ward residential

area.

3.2. Comments on detail level, reliability of assessment

3.2.1. Methods used for environmental impact assessment

List of methods for EIA

No. Assessment method Note

1 Statistic method

This method aims to collect and process the

data on meteorological, hydrological,

socioeconomic conditions in project area.

2 Sampling in the field and

laboratory analysis method

To determine the parameters of current status

of air quality and noise in project and

surrounding areas.

3

Rapid assessment method

This method is based on pollution ratio set by

World Health Organization to estimate

pollutant load from project activities.

4 Standard comparison method To evaluate the impact based on

environmental criteria in Vietnam

5 Public consultation method

This method inherits comments on the

operation, implementation method and

proposal of hamlet 5C, 3 and Thoi Hoa

communal People's Committee where project

is located.

6 Chemical model method

This method is used to predict and foresee

impacts of the project during the

environmental impact assessment.

3.2.2. Remarks on detail, reliability of assessment and forecasted results

During the EIA report preparation, the Consultant has combined all methods above. The

report lists all activities of project from preparation to operation stage, as a result, the

environmental impact assessment could be seen. The report also shows volume and

concentration of pollutants caused by project which can be compared with current criteria

and norm in Vietnam. Data used in the report were taken from specialized reference,

widely used in environmental impact assessment and is valid.

Page 99: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

92

The report also has statistic data on meteorological, socioeconomic conditions in

construction area that is rather complete and is updated according to official statistics of

Binh Duong, so it is highly reliable.

Surveying and measuring data comply with Vietnam regulations. However, these Figures

are only shown in certain time, not a long series, so they do not accurately reflect the

nature and represent current state of the environment in the project area. Therefore,

surveying data have low reliability.

The report uses public consultation method and receives written comments of Thoi Hoa

People's Committee. These are comments from project area, so the report mentions some

measures that suitable with local situation.

With an experienced team of consultants in preparation of EIA report for many years, it

can be said that results of evaluation and forecast that may occur during the project

construction are shown relatively adequate, realistic and high reliability.

Page 100: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

93

CHAPTER 4

NEGATIVE IMPACT PREVENTION, MITIGATION MEASURES, AND RISK &

INCCIDENT PREVENTION, RESPONSE MEASURES OF THE PROJECT

4.1. Negative impact prevention and mitigation measures

4.1.1 Negative impact prevention and mitigation measures in the preparation stage

As mentioned above, compensation and ground clearance has been completed before

allocating land to Vietnam German University. Becamex compensated and relocated

households in project area, conducted leveling and planted trees along K1 channel in the

north and west. During construction, project has to cut down some existing trees. So, this

chapter mentions several solutions of planting trees, restoring ecosystem and landscape

lost in project area.

As planned, approximately 40% of land is used to plant trees, landscaping and restoring

ecosystem lost due to ground clearance. Trees in VNU will be chosen to suit local

conditions and meet standards of "Plan of using public green trees in urban areas".

Accordingly, green plants in university must ensure following properties:

- Large, widespread, shadow, impressive

- Trees for campus yard: Choose local plants with flowers and leaves. Tree species

are as many as possible for research and study.

- Limit fruit trees

- Do not choose plants with thorns, toxic latex. Do not use trees that attracts flies,

mosquitoes such as: banian tree

- Table name of tree, planting date, origin

However, trees are recommended to use in university, including:

- Terminalia catappa tree, flamboyant, cassia tora, cassia javanica tree, rose…

- Bonsai, local plants: rose, amplexicaul tea, orchird…

4.1.2 Negative impact prevention and mitigation measures in the construction stage

A. Impacts that relates to waste

4.1.2.1. Prevention measures of air pollution

On the construction site, the Construction Company will implement regulations on hygiene

and safety in accordance with current regulations. The following measures will be applied

to reduce air pollution:

- Use canvas to screen and avoid things that fall from height at building construction

area.

- Screening in the area:

+ To collect materials such as sand, cement, digging soil

+ The transportation vehicles carrying materials, construction waste that cause dust and

dirty to environment shall be covered with canvas, avoid bringing sludge to street.

- When implementing piling work, Construction Company considers selecting suitable

equipment: good status, periodic quality registration to minimize vibration, smoke, dust

and noise during operation.

Page 101: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

94

- Idle machines/equipment are not allowed to stay on site.

- Construction Company commits not to use too old mechanical machines; machines

must meet environment criteria, traffic safety index and waste criteria TCVN

6438:2001 – Road transport – Allowable maximum limit of emission waste

concentration.

+ Emission waste standard of mechanical vehicles.

+ Noise standard of mechanical vehicles

+ Vibration standard of mechanical vehicles

- Arranging suitable wash stations when these vehicles come out of the site. Sprinklers

are arranged to spray water at site, and clean cars.

- To limit dust pollution in construction area, sprinkler used in irrigation and road wash

will be applied: Wet ground surface. Frequently wet the site ground surface in dry

season (2 times/day) to limit dust from transportation. Use cylinder sprinkler with

drainage holes that is evenly distributed on tube and has increasing diameter from

central to 2 ends. It will sprinkle more water and avoid erosion by reducing water

pressure on the surface. This equipment will be installed on vehicles instead of normal

sprinkler systems.

- Share shift, arrange working site during the day, limit working at night.

- Maintain equipment every 6 months

- Contractor often collects waste and cleans transportation roads and site.

- Limit construction and transportation from 21:00 to 6:00 to restrict effect on temporary

station of receiving addicts and residential areas along transport road.

- No construction and transportation in bad conditions (heavy rain, strong wind) reduce

spreading pollutants.

- Transport vehicles are not allowed to speed up and honk in residential areas.

- Provide training courses of safety and environment protection for truck drivers and

machine operation workers

- Well-manage and supervise construction site

- Surveying on air environment, noise, vibration to adjust and add suitable measures

during construction time.

Note: the project area is located at the corner of Ring Road 4 and Highway 13, it is

recommended to limit impacts on traffic in transporting materials, to arrange a gate in Ring

Road 4 or approach from D9 road that is near residential area Helmet 3 and not crowded to

reduce traffic jam and risk of accidents when vehicles come in and out of the site.

4.1.2.2 Mitigation Measures on water environment

a. Domestic water

During the construction stage, estimated officers and employees working in project area is

about 400-500 people on a shift working basis. Estimated wastewater is about 20-30 m3.

Therefore, in this stage, the Project owner will collect and carry out the treatment of

wastewater by installing 3-compartment or mobile septic tanks in camps (5 toilets at site),

which avoid direct discharge of domestic wastewater into the environment. This is simple

work, easy to perform, performance can reach at 60-65%.

Page 102: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

95

After wastewater goes through sedimentation tank 1, it will continue to go through

sedimentation tank 2, and then be taken up by Binh Duong water supply drainage or Ben

Cat urban works Company, 1 time a week. With such waste estimation, septic tanks can be

designed approximately 3 m3 capacity, located in the south where executing phase 2 (area

has not been used in this stage).

Figure 8: Some models of mobile toilet

Minimize wastewater by hiring more local employees who have houses. Well-manage

human resource in this phase.

Frequently check, dredge to prevent sewerage pipelines from sludge and garbage. Do not

obstruct, cause waste as well as impact on water of K1 drainage channel.

b. For wastewater during construction

The construction contractors have committed that they will not discharge wastewater

directly to the project areas, arrange receiving and conducting pipes, which are expected to

be placed underground to ensure the landscape for the University, to lakes in the southern

of the Project to handle construction wastewater for sedimentation, and sludge then will be

discharged into K1 canal.

Construction of drainage system and preparation of standby pumps will ensure the

thorough drainage and prevent flooding during construction. The drainage for the

University shall be designed in a way to prevent potential obstacles, causing unpleasant

odors and unsanitary conditions.

Construction wastewater generated from activities such as car washing, mixing station,

material cleaning, etc will go along temporary sewerage ditches, flow to sludge settling

compartments and grease separators. One or two consecutive sedimentation holes of from

2 to 3 m3 shall be dug to settle suspended solid substances and residue in wastewater by

the Contractor. An oil-absorbing piece fabric will be placed at or surrounding locations

where wastewater coming in and coming out sedimentation holes. Oil will be absorbed

into the fabric. After it is fully absorbed, oil shall be taken out by squeezing, and then the

fabrics can be reused or dry cleaned before reusing. The fabric after disposal will be

collected and processed in accordance with regulations.

Page 103: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

96

Figure 9: Some pictures of the oil filter fabrics

Oil filtering bag

Oil filter grid which do not hinder the flow

After settling, clear water can be discharged to the internal drainage ditches located inside

the industrial area and Thoi An residential area, or K1 canal going through the project. The

residues shall be outsourced and collected by the city sanitation unit or transported to the

waste dump site in Chanh Hoa ward by Ben Cat town urban enterprise. Lubricants and

other types of fuels used for equipment shall be kept carefully to prevent the overflow and

ensure regulations on safety.

Ensure that the construction shall be on schedule and prevent lengthening of construction

time in rainy seasons.

Cleaning of sites, camps, covering of material sites, disposal sites and petroleum shall be

taken on a daily basis to prevent the overflow of rainwater, bringing out materials and oils

which will lead to pollution of water sources.

The management of construction, fuels, oils, lubricants and maintenance of machine,

equipment should be taken strictly to prevent the leakage of oils coming to water sources.

4.1.2.3. Minimization caused by solid waste

a. Construction solid waste and domestic waste:

Solid waste in construction stage are mainly damaged materials such as debris, dead

concrete, damaged formwork, scrap of equipment outer... which are reused for leveling or

collected and transported to the waste dump at the landfill under an agreement between the

Project owner and local governments, or used for projects in the neighboring industrial

zones and residential areas of Thoi Hoa, My Phuoc 1,2,3 Industrial zone or treated by

Urban work Enterprise of Ben Cat town under a contract between this unit and contractors.

- Scrap, boxes, sheet metal, wood, protective steel for equipment outside are collected

and sold to scrap dealer;

- Domestic waste: prepare 5 barrels of 240L or 660L capacity at the site to collect

domestic waste on a daily basis, then contracts with urban transport enterprise of Ben

Cat town to transport to the waste dump site of the town for daily treatment.

b. Hazardous waste:

Page 104: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

97

Hazardous waste in the construction phase consists of waste oil and greasy rags with small

amount. In any leakage of these kinds of oils and grease, rainwater will flow through all

kinds of these greasy rags which then get wet and, therefore, oil will seep into soil or into

waterways around the area along rainwater. This will affect the quality of quality of soil

and water environment. As a result, proper collection and management measures should be

applied in accordance with specific rules: different types of hazardous waste and other

wastes will be separated; arrange temporary storage for hazardous waste safety; pack,

preserve each kind of hazardous waste in dedicated containers, tanks, packs under the

requirements on safety, technical aspects, ensure no leakage, scattering or dispersion of

such hazardous waste into the environment; label on the outside with the following

information:

a) Name and code of hazardous waste according to the list of hazardous waste;

b) Name and address of owners of the waste sources;

c) Description of potential risks caused by waste;

d) Warning and prevention signs under the Vietnam standard TCVN6707-2000 on

"hazardous waste-warning and prevention signs;

e) Date of packaging and preserving.

Hazardous wastes shall have to be strictly preserved until functional units transport them to

treatment area. Containers on flat floors are temporary houses surrounding to avoid

rainwater infiltration which will lead to oil spill.

Used oil/ motor oil emitted by machines must be disposed of in separate bins and cannot

be discharge into the environment. Oil storage tanks at the construction site must be able to

prevent the leakage. The Contractors have to follow regulations to ensure that all

hazardous substances, including oil from drums or containers on the site will be labeled

and stored properly and don‘t allow oil or other pollutants to be able to access to

waterways or groundwater. On the construction site, with a monthly output of about 150-

300l waste oil, two containers of 500 liters should be prepared and a contract with a

functional unit, who is licensed with hazardous waste treatment, transport waste in 2-3

month periodically.

Rags or solid waste contaminated with oil are regarded as hazardous waste, however,

waste volume of an approximately of 5 kg/week is negligible and can be collected in

separate bins of 200l capacity, then transported by a licensed unit for treatment in

accordance with regulations. The volume of this waste is not much, mostly oily rag can be

burned in medical waste incinerators or cement rotary clinker.

In Binh Duong province, Binh Duong Water Supply, Sewerage and Environment

Company is one of the units who have been licensed in the field of collection, management

and disposal of hazardous waste and the prestigious unit in the locality. The Client can sign

a contract with this company for collection and disposal of hazardous waste services for

the project.

Page 105: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

98

B. Impacts sources not related to waste

4.12.4. Mitigation measures for impacts of noise, vibration

Despite being rated as factors whose impacts are negligible, however, technical measures

should be applied in the course of construction to ensure that noise, vibration does not

exceed the prescribed standards:

- The installation of railing around the site is to minimize dust and ensure the safety of

construction sites, also contributes to minimization of noise impacts on nearby

residential areas. This measure can help reduce noise up to 15 dB.

- Advanced technology, special and dedicated construction machines, all trucks and

motor construction equipment will able to be operated if they meet the criteria as

required by the Registration Department on the level of technical safety and

environmentally safety. Construction motor equipment with low noise are encouraged.

- The construction equipment causing great noise such as hammers, drills, excavators ...

will not be operated during the period from 18 pm to 6 am the next day. If

construction at night is required to ensure the work progress, it must be approved by

local governments, and temporary noise and dust prevention shields for sensitive areas

must be installed.

- The construction equipment noise such as hammers, drills, excavators ... not be

allowed to operate during the period from 18 pm to 6 am curfew. If being constructed

at night to ensure the progress of the works must be approved by local governments

and temporary construction noise shields, dust for sensitive areas

- Equipment causing noise will be able to be operated in a short period of time in day

time only. Do not use many equipment causing noise and vibration at the same time to

avoid the cumulative impacts.

- Maintenance and inspection of construction equipment and transport vehicles should

be regularly taken to ensure environmental standards as prescribed. Avoid using

obsolete vehicles, machinery because they will create loud noise;

- For mandatory cases, when equipment causing noise and vibration is required, time

management shall be applied, which means that such equipment will be operated when

there is a lowest density of people and in a short period of time.

- Equip with necessary devices for workers to prevent noise such as noise earplugs, and

it is mandatory for workers when they are working.

- Install noise reduction device for machinery;

- Arrangement of appropriate vehicles also helps reduce traffic congestion, which also

causes noise.

- Applying pile jointing to reduce the noise level from 10-50 times compared with other

methods.

- Install metal fencing panels surrounding the site area;

- Construction Signaling System (road sign in front of road works, speed limit signal

5k/h, markers, rotating lights, etc.) are designed in compliance with provisions in the

Rules of road signs and signals No. 22TCN 237-01issued by the Ministry of Transport

under Decision No. 4393/2001/QD-BGTVT dated 20.12.2001 of the Ministry of

Transport. Materials of signboards are sheet metal signboards and luminous paint.

4.1.2.5. Prevention and minimization of security and social order issues

Page 106: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

99

- Publicize the progress, construction schedule, and aggregate gradation on the site.

- Collaborate with the local government and relevant authorities to organize the program

such as education, consciousness advocacy for construction workers in the project;

introduce with migrant workers on local customs and practices of local people in order

to avoid misunderstandings between migrant workers and local residents.

- All workers have the cards for entrance in the project area to facilitate the management.

- Collaborate with the local government and relevant authorities for the management of

migrant workers who come and work in the province; and avoid theft, robbery of

materials and equipment used for construction and other assets;

4.1.3. Negative impact prevention and mitigation measures during operation

A. Impact sources related to waste

4.1.3.1. Environmental Impact Minimization caused by waste gases

Mitigation measures to impacts caused by vehicles

- Contact public bus service provider of the province and Becamex to make a cooperation

and development of bus routes which will connect VGU with the important places in

Binh Duong and Ho Chi Minh City with preferential fares for students and staff of

VGU in order to encourage the transportation by public vehicles, reduce personal cars

coming to the field and thereby limit congestion, and reduce emissions from vehicles.

- Design VGU entrance on Ring Road 4 to avoid car traffic on Highway No.13 and

reduce the risk of congestion which causes the increase of air pollution.

Mitigation measures to impacts caused by generators’ exhausted gas

- Install chimneys with an appropriate height for generators to avoid the dispersal of air

emissions at lower air level, and also helps dilute the concentration of pollutants when

spreading away.

- Periodically maintain generators;

- Use diesel with low sulfur content (0.05 S) (in the market there are 2 types of DO, 0.05

S and 0.25S). Use biodiesel when possible.

Mitigation measures to impacts caused by chemicals during testing

- Exhausted gas emission arise from small laboratories and on an infrequent basis.

Therefore, the natural ventilation for lab is the top priority. Besides, the project was

designed and equipped with dedicated hoods and ability handle chemical vapor in order

to ensure the health of people working in the laboratory.

- Collection and treatment of chemical vapor in the laboratory: Laboratory will arrange the

desks, working areas in a reasonable manner. Performance of laboratory operations,

openning and taking chemicals for laboratory activities which arise chemical vapor shall

be into a separate area where will be install a dedicated hoods with suitable capacity to

ensure all smoke and chemical vapor shall be suctioned.

- Structure of a suction consists of:

1) Gas system pipeline from the hood, collector of exhaust gases, chemical fumes in

the laboratory to the collector, silencer (Pvc tube, with D = 114 mm, 200mm,

250mm, 300mm, 350mm , 500mm, ...)

2) One way valve for each separated collection pipeline

3) Emission collector and silencer of PVC

Page 107: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

100

4) Dedicated suction fans which can resist acid-base are installed for centralized

processor.

5) Adsorption (charcoal)

6) Water vapour hood (opposite direction gas and liquid processing)

7) Tube systems connecting devices in order to constitute a centralized exhaust gas

treatment systems.

Working principle of the hood: Exhaust air arising out from laboratory shall be

suctioned and collected into collecting equipment, silencer through the suction fan and

ordinary PVC tube system (resist chemical). Polluted emissions is handled by

specialized propeller fans (by PVC tube) which suction air from collection boxes,

silencer through tube system to two major parts of the system, namely: the adsorption -

filtration equipment, and absorption - filtration equipment. Use mist spray adsorption

solution that is in opposite direction to the emissions. The air soluble in water (acid

vapor, organic solvents vapor that is soluble in water) will be retained; adsorption

solution and laboratory waste are treated together. The exhaust air not soluble in water

shall be adsorbed by adsorption - filtration device containing activated carbon. Vapor

after coming out from absorbing device shall meet requirements under QCVN 05:

2013/BTNMT, QCVN 06: 2009/BTNMT)

Figure 10: Some pictures of hoods in the laboratory

Page 108: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

101

Impact mititation measures to Air environment surrounding toilets

In addition to the cleaning, sweeping, scrubbing, toilets will be equipped with ventilation

fan

Installation of hoods and deodorization of exhaust air In kitchen area before being

discharged to the outside

Handling odors from the centralized wastewater treatment plant

- In the concentrated wastewater treatment plant area, odor is arised mainly from

regulatory tank and anoxic treatment tank. To handle such smells, location of the

treatment plant is designed in a way to ensure the distance of 15 m away from other

works, including green belt 10. Smell will be handled by making regulatory tank and

anoxic treatment tank closed. Air generated will be collected through a tube and taken to

the high by the elevation of the tecnical building. At that time, these emissions will

disperse and diffuse into the air. This is a very effective solution, and is similar to the

ventlation for septic tank. Or we can install deodorizing equipment. This system consists

of:

+ Tube and suctionfan system is used to take exhaustair to the odor control

centre. Regulatory and anoxic treatment tanks are required to solve odor

problems.

+ Combination system for chemical treatment consists of: filters with chemical

feeding equipment (sodium hydroxide, sulfuric acid, hydrogen peroxide,

etc...)

+ Biological system: use microorganisms.

- Working principle of deodorizing equipment:

Page 109: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

102

First, the air will go through the filter which is installed in front of the biological filtering

equipment. The filter contains circulating water through circulating pump. Water

evaporated is automatically compensated by the compensation system through which

wastewater is treated preliminary and make full moisture. Next, emissions will be pushed

through biological buffers. Biological buffers are mainly made of natural materials such as

fiber roots / pine bark, peat ... The surface of particles as well as surrounding water layers

are implanted by microorganisms. Residues will be adsorbed onto the surface of particles

as well as onto the water layers. At the same time, the microorganisms will transform the

odorous organic ingredients, produce energy, biomass as well as CO2 and H2O – main

outputs of metabolism.

The air exchange rate can be up to 6-12 times. After treated by deodorization system,

exhaust gas is cleaned completely and can be discharged into the environment.

Type of Device: It is a container type device - is a prefabricated steel double-walled

rectangular. The outside is painted and the inside is wrapped in polyethylene. Containers

will be installed on reinforced concrete footings.

Basic parameters:

+ Number of unit: 2

+ Capacity: 3.750m3/h

Garbage collection area is designed to ensure the aeration. Waste will be collected and

transported daily by Urban Work Enterprise of Ben Cat town or other functional units in

the province.

4.1.3.2. Environmental Impact Minimization caused by wastewater

Environmental Impact Minimization caused by wastewater will access in 3R direction:

Reduce-Reuse-Recycle.

Increase of awareness

- Organize campaigns to raise awareness of students and staffs who are learning and

working in VGU on water saving. The contents will include the following:

- Domestic water should not be used for other purposes;

- Change bad habits of using water (such as bathing in short time, closing water taps

while brushing teeth or if don‘t use water, etc)

- Disseminate water recycling program of VGU.

- Such propaganda can be integrated with other contents such as reduction of water

generated, power saving. etc.

Wastewater treatment in laboratory

- Entire laboratory wastewater is collected separately and is pre-treated by chemical and

physical methods such as flocculation, neutralization, then connected to the combined

wastewater collection system of VGU and discharged to the concentrated wastewater

treatment station for treatment to reach Class A, QCVN 14: 2008 / BTNMT before

being discharged into the environment.

Premilinary treatment option: Depending on sources of arising, laboratory wastewater

will be collected in clusters (5 clusters) and pretreated for each cluster. The premilinary

treatment tanks were built underground, just below the building where laboratory is

located. Currently, the expected area for the construction of each treatment cluster is

around 4 m2.

Page 110: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

103

Perform the neutralization and precipitation reactions to remove metals from wastewater.

Therefore, during construction, each treatment tank is divided into small compartments

suitable for wastewater treatment in each separate collection cluster.

A premilimary treatment facility in laboratory can be shown as follows:

Wastewater treatment from kitchen

Wastewater from kitchen sinks, floor cleaning will be discharged into steel groove

system on the floor, and then flowed into receiving pits in the kitchen, which collect

kinds of dirt, waste with large diameters in order not avoid the clogging of drainage

pipes. Water collected from pits in the kitchen will be released to the grease trap.

According the QVCN, wastewaterdischarged from the kitchen contains a lot of grease

and leftovers, it is necessary to construct grease traps to ensure thatdischarged

wastewater will not contain fat and to avoid clogging. After filtering by the grease trap,

wastewaterwill be discharged tomanholes of the combineddrainage system, then to the

concentrated treatment plant. Grease trap is designed to ensure the water retention for 1-2

hours.

Operating principle of the grease trap: Install grease trap on thedrainage way.

Wastewater will flow directly into the grease trap after passing through the sieve layes

inside the grease trap in order to retain dregs and impurities such as bone fragments,

vegetables, plastic bags, etc. After that, wastewater containing grease will go into the

second compartment, where its time retention of 1-2 hours is enough for grease to float

on the water surface, and oil accumulated gradually forms a layer on the water surface,

periodically use valve to discharge such oil out. After that, water will be draind into the

sewer system to the centralized wastewater treatment plant. Such amount of oil extracted

will be collected and processed together with daily domestic waste by urban work by

enterprise of the town.

Lab wastewater

(2-5 m3/day)

Neutralized by lime.

Increase pH = 11-12.

Precipitate metal

hydroxide

Ca (OH)2

Sedimentatio

n

Sludge (hazardous

waste)

Adjust pH

(6,5-8,5)

Centralized

wastewater

treatment plant

Other hazardous

wastes shall also be

treated

Page 111: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

104

Figure 11: Grease trap picture

Treatment of wastewater from sanitary area

Wastewater from toilets, urine tubs is collected and treated with 3-compartment septic

tank installed in buildings, then connected to the combined collection system to the

centralized treatment plant.

Wastewater from medical center: As assessed in the Chapter 3, the Medical center of

the University jus provide conventional medical care, not perform the surgery, or

treatment of diseases that involvetoxic chemicals, so wastewater from the medical

center is non-toxic and can be connected to the combined sewerage system and

transported to the centralized wastewater treatment plant.

Reuse of water

Wastewater of VGU shall be treated for reuse purposes instead of discharging all.

Reused water will be utilized for other purposes such as watering, water tower, and

water for flushing in toilets.

According to calculations of the project, the largest wastewater flow in phase 1 is 737

m3/day, while the non-potable water demand (water reuse) is 862,598 m3. Thus, it can

be seen in the phase 1 of the project, the entire amount of waste being treated at the

centralized plant will be reused and shall not be discharged into the environment.

In phase 2 of the project, the largest wastewater flow is 1,762 m3 / day, and the non-

potable water demand is 430 m3/day. Thus, in phase 2 of the project, the amount of

wastewater after being treated and discharged into the environment is about 1,332 m3 /

day.

Concentrated treatment plant

The drainage system is collected by both methods, which are gravity and pressure

pipes and will collect entire domestic wastewater. The majority of wastewater will

flow by gravity to the wastewater collection system, howerver, lifting stations will

be installed for buildings in the North. Wastewater after treatment will meet column

A, QCVN 14:2008/BTNMT, and most of treated wastewater is reused for different

purposes, the remaining will be discharged into the canal K1 at coordinate (X =

1228688.4966; Y = 594402.8061).

Wastewater collection shall be presented in the following figure.

Page 112: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

105

Figure 12:Wastewater collection diagram

Manhole

Manhole

Grease

separating tank

Manhole

Toilet wastewater Wastewater from washbasin

and collection hopper on

floor

Laboratory

wastewater

Kitchen

wastewater

Digestion tank

Manhole

Neutralization tank/

preliminary treatment

Centralized wastewater

treatment system

Wastewater sewage Wastewater sewage

Wastewater reaches to value C, column A of QCVN 14:2008/MONRE and

able to reuse or discharge out at the discharging point (Channel K1)

Page 113: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

106

No. Criteria Unit Value C of Column A

(QCVN14:2008/BTNMT)

1 pH - 5-9

2 BOD5 mg/l 30

3 Total suspended solid waste mg/l 50

4 Total dissolved solid waste mg/l 500

5 Sunfulate (Acording to H2S) mg/l 1

6 Amoni (Acording to N) mg/l 5

7 NO3(Acording to N) mg/l 30

8 Oil and grease mg/l 10

9 Total working on the surface mg/l 5

10 Phosphate (PO43-) P mg/l 6

11 Total coliform MNP/

100ml

3000

The calculations of the project show that the average wastewater flow of phase 1 is 567 m3

/day, and the largest wastewater flow is 737 m3/day.

Phase 2 of the Project: the average discharge of wastewater from buildings in phase 2 of

the project is 1,355 m3 and the largest wastewater flow is 1,762 m3/day.

In phase 1, a wastewater treatment plant of 1000 m3/day will be used under the project and

apply the bioremediation method to treat the entire volume of wastewater generated in

phase 1. The wastewater treatment plant for Phase 2 will be built simultaneously with other

construction works of Phase 2 of the project. It is expected that the capacity of the

treatment plant of Phase 1 will be upgraded and still use this technology, but a new module

with the capacity to meet the demand of wastewater treatment of the Project‘s phase 2 will

be constructed.

Page 114: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

107

Figure 13: Wastewater Treatment Technological line

Operating principle of the centralized Wastewater Treatment Technological line is as

follows:

After being preliminarily treated at its sources, wastewater generated from laboratory,

kitchen, toilet wastewater will be connected to the sewer system of the whole univeristy

and total wastewater will be taken to the centralized treatment plant for processing.

Wastewater shall flow through the automatic raw and fined waste trash rack in order to

separate waste before being discharged into sand filter and wastewater pumping pits.

Waste from raw and fined trash racks shall be collected into plastic bags and discharged

with solidwaste.

Then, wastewater is pumped to the conditioning tank to make balance the wastewater flow

and organic matter before being pumped to the anoxic tank. Nitrogen in wastewater will be

treated in this tank. Anoxic tank will be installed with mixing machines to continuously stir

wastewater into tanks. After the anoxic tank, wastewater will come to the aeration tank to

perform the biological treatment. In the aeration tank, aerobic microorganisms oxidizes

organic components in wastewater to become less harmful substances. Air is supplied by

the nozzles placed in the tank to increase the efficiency of the biological treatment. To

increase treatment efficiency of nitrogen, two hundred percent of wastewater in the

Wastewater reaches to value C, column A – QCVN 14:2008/MONRE and able to

reuse or discharge out at the discharging point (Channel K1)

Bar screen

Sand separating pit and pumping pit

Equalization tank

Anoxic tank

Secondary sedimentation tanks

Disinfection tank

Pressure filtration system

Input wastewater

Aeration tank

Sludge collecting

vehicle

Sludge compression

tank

Sludge storage

tank

Sludge

dewatering

Waste

sludge

Sludge waste

Recirculation

sludge

Page 115: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

108

aeration tank is circulating to the anoxic tank. After the biological treatment, wastewater

enters the secondary clarifier to separate sludge from wastewater. Wastewater then goes

into an disinfection tank where chlorine is provided to ensure the destruction of the

remaining microorganisms in wastewater. Disinfected wastewater will pass through the

pressure filter to increase quality of wastewater for other reuse purposes. Pressure filter is

used to remove suspended solids, control phosphorus and nitrogen.

Besides, in the secondary settling tank, sludge will settle and be compressed in the hopper

of the tank. The sludge is then pumped periodically to the sludge compression tank prior to

the sludge tank. Sludge after being out of compression tank usually have a moisture about

from 95% to 50 %, concentration of 1.5%. Then sludge is pumped through sludge

dewatering machine. After being pressed, sludge with humidity of about 43% to 85%, the

concentration from 15% to 25%, is contained in plastic bags and transported to solid waste

treatment site of the town for buried or used for other purposes.

In case of incidents, such accidents can occur in the anoxic and aerobic tank, and during

the air supply. Then the sewage system will not work properly asper the designed

technology,and the quality of effluent is not guaranteed to be reused. Non-potable water

supply using reused water will be replaced temporarily by drinking water source.

Wastewateris treated unsatisfactorilyfor the reuse will be discharged into the environment -

receiving channel K1. However, during the dry season, the water flow in channel K1 is

low, that does not guarantee the ability to dilute the wastewater. Therefore, in order to

minimize the impacts on the quality of surface water channel K1, wastewater before

discharging into this channel will be pumped from the tank into the pressure filter to

minimizeconcentration of suspended solids and some other pollutants in wastewater.

Table 56. Technical speficiation of wastewater treatment facilities

No. Work items Unit Description

Input wastewater flow m3/day 1000

Average wastewater flow m3/s 0.0116

Input BOD mg/l 353

Input suspended solid waste mg/l 220

1 Sand sedimentation tank

Water retention tank minute 4

Number of tank(s) 1

Volume m3 8

2 Equalization tank

Water retention time Hour 1.5

Volume m3 243

Solid waste after treated by

regulatory tank

mg/l 132

BOD after treated by regulatory

tank

mg/l 282

3 Anoxic tank

Water retention time Hour 2.5

Volume m3 104

Page 116: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

109

4 Aerobic tank

Total ammonia in the wastewater

in the aerobic tank

mg/l 40

Total ammonia in the wastewater

out of the aerobic tank

mg/l 30

BOD in the wastewater in the

aerobic tank

mg/l 282

BOD in the wastewater out of

the aerobic tank

mg/l 30

SS in the wastewater in the

aerobic tank

mg/l 132

SS in the wastewater out of the

aerobic tank

mg/l 50

Water retention time day 12

Number of tank(s) 1

Volume m3 188

Total air demand m3/hour 1521

5 Secondary sedimentationtank

Number of tank(s) 1

Volume m3 159.65

Water retention time Hour 2.11

6 Disinfection tank

Time of exposure minute 30

Amount of chlorine used l/hour 2

Number of tank(s) 1

Volume m3 20.83

Coliform MNP/100ml 3000

7 Sand filter

Surface hydraulic load m3/m2.day 216

Number of tank(s) 1

Volume m3 22.52

8 Sludge compressor

Surface hydraulic load m3/m2. day 6

Volume m3 39,62

9 Sludge tank

Number of tank(s) 1

Volume m3 14.88

Page 117: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

110

Rainwater

Rainwater drainage system is calculated on the basis of sustainable development, paying

attention to the drainage, water reuse, minimization of wastewater and environmental

proection with the design called "Water Sensitive Urban Design"(WSUD). The WSUD

have many environmental benefits, including the improvement of urban landscape,

reducing pollution and slow down stormwater runoff and decreasing the need for

irrigation. Surface rainwater from the entire southern region of the Project is collected to

the concentrated lake in the South of the Project. The lake is used to slow down the flow of

rainwater in biggest rainy period with 10-year cycle. Rainwater in the project will be

collected by the sump pit and water receiving pits. All internal roads in the project are

provided with the stormwater system. Rainwater collected is led by gravity or pressure

pipe to the rainwater regulatory tank and stormwater treatment system, including:

o Manholes with sediment container at the bottom and trash screens at all points of

flushing out the sewer system from the seepage pit;

o Grease trap/mechanical oil system;

o Tank for slowing underground rainwater;

o Resettling lagoon;

o Biology permeability system;

o Filtering areas for planting trees.

80% of suspended solids of rainwater collected from the impervious area of the project

will be removed before being discharged into the drainage canal, or come to the lower

position on the site or connected to the watering system where rainwater is returned to the

environment through evaporation or seepage. Stormwater discharged into the ground or the

canal will be less after going through irrigation systems to ensure the flow and volume

flow through the system that will not be larger than previous peak flow and volume flow

before going through the system. The maximum distance between manholes is 20m - 60m,

depending on pipe diameter. The slope along the sewer line is 0003-0005.

Positions of rainwater discharge: rainwater is discharged into K1 canal in the North and

South areas.

Therefore, if pollution sources coming from domestic wastewater and pollutants in

rainwater are treated thoroughly, quality of K1 surface water, where is the receiving points

of treated wastewater and overflowed rainwater on VGU surface, will not be affected by

pollution factors.

4.1.3.3. Environmental Impact Minimization caused by solid waste

a. Domestic solid waste

VGU aims at providing domestic solid waste in 3 R: Reduce – Reuse – Recycle. To

achieve this, the following should be applied:

(i). Construction of waste classification at sources

VGU has equipped two kinds of rubbish bins: the green contain organic waste, and the

yellow contains remainders. Or in other places, 3 compartment bin can be used for storage

of recyclable waste. The bins are placed in dormitories, faculty housing, offices, campuses

and public areas. Bins with covers are used to minimize the spreading of smell and avoid

rodents. This bins come in many sizes, different forms to suit each specific place.

Page 118: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

111

Figure 14: A number of rubbish bins can be used for buildings

Every day, housekeeping staff of VGU will collect organic waste and other waste, then

transport to collecting points. Bins of from 140 - 240 liters capacity with wheels and lids to

collect garbage from the smaller can be used. This will be easy for them to pull to garbage

collecting location of the University.

Buildings of the University are not too high, gabarge collection pipeline system is not

constructed for each building. The garbage collecttion shall be done by sanitation worker

by gathering it in large bins from 140 -240 liters with wheels, lids and transporting down

through the elevator system.

Page 119: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

112

Figure 15: Some bins with wheels and lids are used for waste collection and

transportation to waste gathering site

VGU will sign a contract with a functional unit who will perform the services for daily

collection and transportation of waste under regulations. It is expected that the waste

garthering points will be constructed insite technical engineering works with an area of

approprimately of 600m2. The design of such works will have cover, high elevation and

sewerage ditches, system to collect and transport wastewater or wastewater from floor

cleaning to concentrated wastewater treatment of VGU.

(ii). Increasre awareness

Organize campaigns for students and staff who are learing and working at the University

on minimization of waste issues and waste classiffication at source.

b. For hazadous waste

Waste considered as hazardous must be collected and properly treated under current

regulations of the Government on the management and disposal of hazardous solid waste:

- Hazardous solid waste must be collected and stored in containers to separate with non-

hazardous waste, and containers should be painted with warning signs of danger;

- Chemical waste from laboratories must be kept under strict safety regulations on

chemical and biological subtances. These regulations must be disseminated for those

working in the laboratory;

- all types of hazardous waste must be lablled as prescribed;

Page 120: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

113

- Registration of hazardous waste generators with the Department of Natural Resources

and Environment of Binh Duong province; Types of hazardous waste generated from

these sources will be collected and gathered in separated bins for hazardous waste at

general waste gathering points of the University.

- Contract with functional units for collection and treatment of hazardous waste in

accordance with current regulations. This unit must be licensed to collect and transport

hazardous waste issued by the licensing authority (Binh Duong Water Supply,

Sewerage and Environment Company).

Figure 16: Solid waste and hazardous waste collection diagram

Page 121: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

114

HAZARDOUS

WASTE

LAB WASTE

Gather

point

HAZARDOUS

WASTE

MEDICAL

WASTE

Periodic

treatment

SLUDGE

WASTE

DOMESTIC

WASTE

DOMESTIC

WASTE

BUILDINGS

INORGANIC

ORGANIC

transport for

treatment

YARDS,

GARDENS

labelling

labelling

labelling

labelling

Gabarge bin/ truck

INORGANIC

ORGANIC

Gabarge bin/ truck

transport for treatment

Page 122: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

115

B. Sources of impacts that are not related to waste

4.1.3.4. Culture - society impact mitigation measures to in the area

- According to the above assessment, in the long run when the project is put into

operation, there will have many positive impacts on socioeconomic conditions in the

region. However, it is unadvoidable with negative effects but they will be at low

levels. In order to restrict negative impacts of the project to a minimum level, the

following plan has been set out: the University Management Board ensure the

compliance with the "Cultural lifestyle, urban civilization‖ which related to the

addressing of violations as stipulated by the town.

- Determining specific provisions on rules of University, learning rules and activities of

students. Besides, the Cultural lifestyle, urban civilizationwill cooperate with the Thoi

Hoa CPC to ensure the security in the region in order to avoid changing the living

conditions of people in the region.

- The University also set out the rules for meals, accommodation and activities of

students;

- For boarding students: The University Management Board shall establish the

dormitory management unit, which students have to abide with the distribution of

University accommodation. Do not arbitrarily change the accommodation, students in

other rooms are not allowed to come and sleep in others; do not move the furniture in

the room. Accommodations must ensure in a neat, clean and order manner. Each

student must have a sense of protection, preservation of buildings, home equipment.

Do not write texts or stick paper on the wall. Must abide by the regulations on power

savings, when there is any power failure, report promptly to the dorm management

board; absolutely do not repair or connect other equipment power consumption; use

and keep maintenance ancillary works, prevent fire, ensure general hygiene in public,

keep firefighting equipment; don‘t create screaming loud in the dorm ... Perform well

regulations on management of boarding students.

- All boarding students must register temporary residence with the University according

to the residence law;

- Management organization of dormitory:

- For non-boarding students: students are subject to the management of the University,

local authorities and are obliged to strictly implement the guidelines, policies and laws

and regulations of the state and University as well as local governments in the

management of non-boarding students. Seriously implement regulations on

Head

Deputy Head

Staff Staff

Staff

Page 123: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

116

management of non-boarding students issued by the Ministry of Education and

Training (Decision No. 43/2002-QD-BGDDT 22.10.2002).

- Besides, the University also stipulates a number of regulations that students are not

allowed to do:

+ Cause offence to dignity, honor or abuse the body of teachers, staff, University

staff and other students.

+ Fraud in learning such as cheating, bringing materials into the examination,

asking for point; learning, doing tests, being on probation for someone else or

ask someone else to learn, do test, be on probation, be on duty; copying, asking

others to writing essays, projects, graduation thesis; organizing or participating

the testing frauds or other fraudulent behaviors.

+ Smoking, drinking beer during University hours; drunken in class time.

+ Disturbing security and order in the University or public place.

+ Join racing or encouragement of illegal racing.

+ Gambling in all forms.

+ Production, trading, transporting, distributing, storage, use or manipulating

others to use weapons, explosives, narcotics, chemicals prohibited, reactionary

documents and publications and other documents prohibited by the State;

organization; participation, dissemination of superstitious activities, religious

activities in University and the other moral violations.

+ Establishing and participating in illegal political activities; organizing and

participating in collective action on behalf of the University without the

approval of the Headmaster.

4.1.3.5. Mininization of traffic accidents:

- During the operation of the project, because the project is located on the Highway 13,

Ring Road 4, the University will coordinate with relevant agencies to install

signboards, road signs to reduce congestion and traffic accidents. In addition, the

University will disseminate rules on traffic safety to all students of the University.

4.2. Prevention, management and response measures to incidents of the Project during

construction

4.2.1. Prevention, management and response measures to incidents of the Project during

construction period

4.2.1.1 Traffic impact mitigation measures

- Organize traffic separation management, arrange separation signs, marine speed limit

sign, warning signs for roads that are near construction areas. Must have remote

warning lights in construction sites at night.

- Operating regulations, including regulations on prescribed route/ moving itinerary,

coverage and cleaning truck before departing from the site to the receiving and

unloading points have to be pasted on construction machineries, material transport

vehicles.

- Work closely with local authorities and traffic police to control traffic conditions in

the area.

- Disseminate and provide training to drivers on strict compliance with traffic rules

and requirements of contractors during transport.

Page 124: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

117

- Collect rocks and soil scattered on the roads and on the construction site every day

during construction.

- Gather materials neatly in the construction areas, do not spill out into the street.

- Implement under the construction schedule

4.2.1.2. Labor safety and firefighting measures

- The contractor must organize training and dissemination programs on safety and

environmental hygiene for all staff and workers, especially new staff, employees.

+ First aid: staff and workers who come to the site at the first time.

+ Periodically (6 months/time): supervisors and senior managment staff

- The service facilities for construction workers such as camp, bathing, first aid kit,

toilet ... must be equipped.

- Equipping of equipment such as fire extinguishers for timely rescue when the

problem occurrs. Each construction unit will be equipped with 2-4 fire sprays.

- Do not store the combustible waste and materials which have to be transported

regularly out of University. Arrange barriers to isolate sensitive, dangerous,

flammable materials areas...

- Design the full lighting system for night work where necessary and for work

protection.

- Installation of good fire alarm, lighting and communication system.

- Training on labor safety for workers.

- Have rules and warning signs on safety on construction sites.

- Periodically check safety devices, operating modes of such devices.

- Arrange first-aid facilities at the sites;

- Construction workers or operation staff must be provided with training and practicing

properly and follow the rules in case of incidents and be always available at their

positions, and must operate properly.

- Measures for workplace safety protection for construction workers is an

indispensable part. Consequently, workers will be fully equipped with necessary

occupational safety clothes and limit the adverse effects on workers. The clothes

include workwear clothing, hats, gloves, eye protection, boots ...

- Tools as well as the necessary contact address when problems occurs will be clearly

marked as: medicine cabinet and eye wash utensils; address and telephone number of

hospitals.

- Work on the site must be given periodically a health test every 6 months to check

their health status in order to arrange work reasonably.

- Full installation of signs at the site.

Construction Signaling System (Road Works Ahead' sign, speed limit at 5km/h, marker,

turning lights, etc.) are designed in compliance with provisions in the Regulations on

Road Signs No. 22TCN 237-01 issued by the Ministry of Transport under its Decision

No.4393/2001/QĐ-BGTVT dated 20 December 2001. Luminous paint and sheet metal

are used for signboard.

Page 125: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

118

4.2.2. Prevention, management and response measures to incidents of the Project during

operation

4.2.2.1. Firefighting preventive measures

To prevent the possibility of fire and buring of electrical equipment, it is required to issue

and strictly enforce regulations on fire prevention. Some primary and general measures are

proposed as follows:

- VGU will be prepared a Firefighting plan which will be approved and verified by

Department Firefighting Police of Binh Duong under the law.

- Must have a natural or local ventilation system.

- Internal road in the University should be easy and smooth for firefighting operations,

ensuring that the water jets from fire hoses of fire trucks is possible to control any fire

arisen in any position in the University.

- Always fully equip fire protection tools and equipment in place and be ready to work.

- No smoking, lighters ... in potentially explosive areas (parking area, warehouses for

chemicals, gases)

- With the motto " Prevention is better than cure", officers and employees often are

disseminated with rules, communication, education, and asked for monitoring and

reminded of spirit, improvement of watchfullness, actively take prevention and

performing well fire protection ordinance.

- Connection and arbitrary use power is prohibited. After work, electrical staff will

check and cutoff electricity in some places if necessary.

- Use silver paper or copper for fuse;

- Use the power wire to connect directly into the socket;

- Do not allow wiring to the ground;

- Don‘t carry out flammable materials in vehicles when leaving and entering the site,

turn off the vehicles when drive the head towards the outside.

- Do not use electrical power to be overloaded;

- Do not bring explosives and combustible materials;

- Well perform rules and regulations on fire prevention and fighting.

- Regularly inspect and supervise the compliance of regulations on work safety;

- The electrical wiring must consider reasonable cross section with current intensity,

protection device must be installed in case of overloading.

- Wiring and lighting system is designed separately from other works to easy the repair,

prevent from short circuit causing fire in chain reaction. Electrical motors must be

protected by shield to prevent water.

- Regularly check the wiring in the whole area of the University where activities are

taken. Breaker box must be closed, and breaker connecting to electricity must be good

too.

- The University should pay attention to the organization to raise awareness of all

officers and employees in fire prevention and firefighting. Organize periodically fire

prevention training with the close collaboration of professional firefighting agencies.

Page 126: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

119

- Smoke absorption system in case of fire and wind system in the AHU: The Smoke

absorption system in case of fire will be designed according to the standards of

Vietnam. (Update Firefighting plan)

Design of firefighting system

+ Automatic sprinkler system for buildings;

+ Wall fire system, wheeled extinguishers, fire extinguishers for buildings, garages,

safeguard house, gas storage, corridors ... and the whole works.

+ Outdoor firefighting and watering system

The followings should be taken in case of incidents:

- Inform to relevant agencies (especially firefighting police).

- Rescue those in danger zones.

- Proactively isolate the fire by the existing facilities on the site (fire extinguishers,

sprinklers, fire extinguisher (if any);

- Support under the guidance of functional units until they are available at the site;

- Support functional units, local authorities to set up security perimeter around

hazardous areas;

- Inspect the fire safety conditions on the construction site to ensure that this problem

will not recur.

- Suspend those who violate fire safety conditions.

4.2.2.2. Mitigation measures to the risk of leakage of chemical vapor and chemical

accidents

- Operate properly machinery and technical procedures;

- Maintenance of machinery periodically;

- Seriously implement measures of labor safety: workers will be equipped with

workwear to prevent them from directly contacting chemicals;

- Chemical storage must ensure that they are kept below its ignition temperature, and

regularly control oil temperature;

- Chemical storage have to meet fire safety standards and chemical safety warning;

- Establish an emergency response plan in case of incidents;

4.2.2.3. In case of electricity failure (short circuit, electrical accidents)

- Disconnect the power source in questioned area and surrounding areas;

- Immediately rescue the objects in danger zones;

- Find out causes of the accident, check the power source, wires and contacts;

4.2.2.4. In case of epidemic diseases

- If there are dangerous diseases, it is necessary to isolate pathogens;

- Inform the health authorities to follow the instructions of the health authorities;

- Inform all officers and employees of epidemic diseases;

- Carry out testing, zoning and disinfecting outbreak areas;

- Provide medical treatment to all employees to ensure timely prevention and treatment;

Page 127: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

120

4.2.2.5 Supporting measures

In addition to technical solutions and technologies, which are crucial for mitigation of the

pollution caused to humans and the environment, the supporting measures also contribute

to the limit of pollution and improvement of the environment.

Provide education on consciousness of environmental sanitation for workers and

employees in the whole University. Perform regularly and scienctifically sanitation

programs, and waste management in the whole University.

Page 128: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

121

CHAPTER 5

ENVIRONMENTAL MANAGEMENT AND MONITORING PROGRAM

5.1. Environmental Management Program

5.1.1. Responsible units

The implementation of the Environmental Management Plan (EMP) for the project must

comply with the regulations of Vietnam and meet requirements on safeguards of the World

Bank's policies. The following units will be involved in the EMP of the project:

i. Project Management Unit (PMU)

The PMU is the focal contact between relevant agencies at the national level, the provincial

level, and local towns where project implementation is undertaken; and is the unit taking

prime responsibility for the implementation and monitoring of the Environmental

Management Plan (EMP). The PMU should arrange one or two specialized staff to perform

necessary tasks. The PMU will officially appoint qualified members serving as

environmental staff, who will perform environmental monitoring in the entire process of

project implementation, to ensure that the environmental plan outlined in the approved EIA

report will be implemented in a sufficient way.

Local people of the project area will also participate in the monitoring of compliance with

the management plan, environmental protection during the project implementation. The

PMU also need to work closely with environmental staff of DONRE, the Natural Resources

and Environment Office of Ben Cat Town in the management, operation and supervision of

the project.

To ensure the compliance with the EMP, the PMU should monitor contractors in

implementing mitigation measures. For environmental monitoring, PMU‘s tasks are as

follows:

- Monitor project performance indicators relating to environmental issues;

- Regularly check to make sure that contractors are implementing mitigation measures as

specified in the construction contract;

- Review periodic reports prepared by construction management consultant (CMC) to

ensure the compliance with mitigation measures;

- Review reports made by the construction supervision consultant (CSC) of the overall

impacts of the sub-project;

- Based on the report of the CMC, the PMU will report to WB and DONRE on

environmental compliance of the sub-project, which is part of the semi-annual progress

report submitted to WB;

- PMU should closely coordinate with relevant agencies in charge of water supply,

sanitation, waste collection, etc to monitor the operation and maintenance during the

project operation;

Because the EMP implementation needs to conduct the environmental quality monitoring in

the course of the project implementation, the PMU will engage functional units to support

the monitoring of environmental parameters in order to make an evaluation of the general

impacts of the project and will be responsbilefor making environmental monitoring reports

filed to DONRE and WB.

ii. Constuction Monitoring Consultant (CMC)

Page 129: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

122

The main tasks of Constuction Monitoring Consultant (CMC) include: monitoring the order

and procedures for basic construction including the compliance with EMP, monitoring the

implementaion of environmental impact mitigation measures performed by contractors as

described in the EIA report. These tasks will be detailed in the Terms of Reference of the

CMC and the contract between the PMU and CMC which should be reviewed and agreed by

the World Bank without any objection. Under the guidance of the PMU, the main tasks of

CMC in monitoring and environmental mitigation include but not limited to:

- Support, collaborate with the Environmental specialized staff of PMU in establishing,

collecting and providing information on the environmental criteria required in the field

and information on the project implementation;

- Ensure construction activities are carried out in a way that fully complies with the

approved EMP and the relevant norms and standard operating procedures as provided in

the contract documents for the mitigation and monitoring of environmental impacts;

- Monitor the implementation of the mitigation measures of contractors, promptly propose

and implement additional interventions to complete the mitigation measures to meet the

safety requirements on environment management of the project;

- Prepare an action plan/emergency plan to deal with environmental issues, potential

emergencies and damages that may occur during the construction stage;

- Give recommendation to the PMU for a part or whole suspension of the construction if

the construction does not meet the requirements on occupational safety and

environmental protection as agreed or stipulated in the contract;

- Organize regular meetings to coordinate with stakeholders of the project in order to

provide information and implementation plans as well as necessary working program of

the project. These aim at raising awareness of environmental protection in construction

of project items.

iii. Construction contractors

Construction Contractors shall be responsible for implementing Environmental Impact

mitigation measures and complying with the approved EMP during the construction of

project packages. While preparing technical proposals, the contractors will be given a chance

to assess to and study EIA report approved by the Project and then, to propose in their

proposals an Environmental Management Plan, including environmental protection measures

and environmental impacts mitigation measures which are consistent with the approved EIA

report.

The environmental management plan of contractors will be submitted to the PMU and CMC

to review any changes (if any) in terms of legislation (laws, decrees, circulars and other

regulations), feasibility or necessary adjustments in each particular case at the site. During

the construction stage, construction contractors will be subject to strict supervision of the

PMU, the CMC, the environmental authorities and the local community regarding the

compliance with EMP.

5.1.2. Environmental management and monitoring

Environmental management and monitoring, responsibilities and reporting are presented in

the following figure and table:

Page 130: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

123

Figure 17: Diagram of environmental management and monitoring

Table 57. Detailed explanation of the environmental management and monitoring

diagram

NO. Line Responsibility

1

(1a) (1b)

PMU will preside over the implementation of semi-annual

progress report submitted to the WB and DONRE.

(1c)

PMU will appoint staff, who is incharge of environmental

issues, to monitor, manage and perform related tasks, as well as

to implement monitoring programs;

Inform a hotline in charge by staff, who is incharge of

environmental issues, in order to receive the reflection,

recommendation and suggestions from the participants of

environmental monitoring;

2

CMC submit to PMU monthly monitoring reports on

implementation of the Environmental Impact Mitigation

Measures performed by contractors; Recommend PMU to

suspend a part or whole of the construction work if they fail to

meet requirements on occupational safety and environmental

protection as agreed or stated in the contract. In case of any

malfunction: Call the hotline.

PMU will review periodic reports of the CMC to ensure the

compliance with mitigation measures.

3 (3a) Contractors: Prior to the construction, an Environmental

Management Plan shall be prepared in order to manage

WB PMU DONRE

Office of

Natural

Resource and

Environment of

Ben Cat town

Environmental staff

Monitoring

unit

CMC

Contractors

Community

(1a) (1b)

(1c)

(2) (3a) (4a)

(4b) (3b)

(5)

Page 131: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

124

NO. Line Responsibility

environmental issues during construction of the project and then

shall be submited to the PMU for review; During the

construction, contractors must keep a daily diary recorded

continuously until the end of the project. In case of malfunction:

Call the hotline.

PMU reconsider proposals on impact mitigation measure of the

Contractor to decide if there are any changes in the legislation or

stuitable adjustments in each specific circumstances at site. And

monitor and check working diary of contractors to ensure their

compliane with the mitigation measures during the construction.

(3b) Contractors: Implement Environmental Management Plan

during construction or operation of every item they undertake;

Working diary will be recodred continuously until the end of the

project implementation.

CMC: Monitor the implementation of mitigation measures taken

by contractor on daily basis.

4 (4a) Community: The community is entitled and encouraged to

participate in environmental monitoring implementation and

reflect environmental pollution issues during the project

implementation. In case of malfunction: Call immediately to the

hotline.

PMU: To encourage, support and facilitate local community in

the participation of environmental monitoring in the locality

where the project is implemented; Address and consider

comments, feedbacks of the community to ensure the

compliance with mitigation measures.

(4b) Community: Monitor contractors in the implementation of

environmental protection measures.

5 (5) Monitoring unit: outsourced by the PMU to peridically take

sample and analyze the quality of environment.

5.1.3. Grievance redress mechanism

The Grievance Settlement Mechanism mentioned below are a guide to resolve all

grievances of the public about the impacts and the nuisances caused by the project. The

principles of Grievance Settlement Mechanism are handled through negotiations to achieve

consensus. In the case of negotiations don‘t achieve the desired result, the grievance may

bring to court as a last resort. The implementation of resolving grievances includes

- PMU will set up a hot line managed by specialized staff to receive and reslove

recommendations, reflection and suggestions from the community and other stakeholders

of environmental monitoring.

- Or on the other hand, the complainant who is not satisfied, can bring their grievance or

petition to the Ward People‘s Committee by written or verbal. The other rievances can

also be given in the consultations and interviews with local residents during construction

projects. Ward People‘s Committee will meet privately with the complainant and will have

15 days to file a complaint for resloving those grievances. Ward PCs can be recieved the

support from Department of Natural Resource and Environment in the assessment on

Page 132: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

125

grievances relating to environmental impacts and the risks may occur during project

implementation process.Ward People's Committee Secretariat will be responsible for

keeping a record of all complaints filed with the People's Committee of the ward.

If the grievances are not resolved at the ward People's Committee, the complainant can

complain to the higher level People's Committees (districts). If after 15 days the damaged

party or the grievances did not receive any information from the ward People's Committee,

or if the complainant is not satisfied with the results of settling complaints. In the district

level, also will have 15 days to resolve the grievance. County Committee Secretariat is

responsible for keeping a record of all grievances filed with the county committee.

If the grievancesare not resolved at the County PCs, the complainants can appeal to the

Provincial People's Committee. Provincial PCs Secretariat is responsible for keeping a

record of all grievances filed with the Province committee

If after 15 days, the damaged party do not recieve any information from the provincial

People's Committee, or if the complainant is not satisfied with the decisions to resolve the

grievances, the matter will be brought to court for review and processing.

5.2. Detailed Environmental Management Program

5.2.1. Construction stage

Before the construction of the project, the PMU will establish an Environmental

Management Department who is capable of project management, responsible for managing

and supervising the implementation of environmental protection projects, and responsible

reporting to the management agencies and the Bank..

Responsibility of the parties involved in the implementation of environmental management

plan.

1. Construction contractors:

- Implement mitigation measures as proposed for the construction phase of the project.

- Report to the project management unit on the implementation of the Environmental

Impact minimization caused by the project construction phase.

2. Environmental Management Department of PMU

- Monitor and evaluate the implementation of environmental protection measures of

construction contractors.

- Report the Management Board of the University the monitoring results of, Natural

Resources and Environment Department of Ben Cat Town, Natural Resources and

Environment Department of Binh Duong province and the World Bank.

3. Community

Monitor contractors in the implementation of environmental protection measures.In case of

malfunction: Call immediately to the hotline to inform PMU or the local communities.

4. Authorities: DONRE and Office of Natural Resource and Environment of Ben Cat town

Supervising and checking the compliance of legal regulations on environmental protection

of PMU and Contractor. Coordinating with Inspector, environmental police in the

implementation inspection, detection and handling of law violations on environmental

protection of the project.

Monitoring and inspection of the observance of the provisions of the law on environmental

protection of the PMU and contractors. coordinate with the Inspectorate, environmental

police in carrying out inspections and detect and handle violations of law on environmental

Page 133: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

126

protection projects, participate in solving complaints and denunciations related to

environmental protection project

5.1.2. Operation stage

Vietnamese - German University will establish an Environmental Management

Department for the Project in order to manage items of waste treatment project of the

Project. The contents to be carried out are as follows:

- Prepare planning and action program for environmental protection in the project,

closely collaborate with the local environmental management authorities in the

inspection, testing, and monitoring of environmental quality; coordinate the appraisal

and inspection of facilities, architectural items, environmental treatment technical

systems, prevention of incidents under the regulations and environmental standards of

Vietnam.

- Collaborate with the fire protection authorities, and authorities for environmental

accident prevention to establish fire incident prevention plans.

- Regularly inspect environmental protection activities taken in the project.

- Organize regular propaganda and education on awareness and environmental

responsibility in University for workers and employees as well as students of the

University. Signs, tables of University rules and regulations are also prepared.

Table 58. A summary of Environmental Management Program

Page 134: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

127

Activities Environmental impact Environmental protection measures and

works

Cost for

implementa

tion of

Environme

ntal

protection

measures

and works

Time for

implementatio

n

Implement

ation

Supervisor

1 2 3 4 5 6 7

SITE PREPARATION PERIOD

Trees

clearance

Impacts on ecosystem During the implementation of the project, we

will plant green trees to compensate for the

lost vegetable system due to clearance. The

area of green trees shall account for 40% of

land lot area of VGU. The suitable crops to

the local conditions and standards on green

trees in the urban areas shall be planted

Included in

the contract

value of

construction

contractor

Site preparation

period.

Complete

before 9/2016

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province (DONRE)

- Division of

Natural Resources

and Environment of

Ben Cat Town

CONSTRUCTION PERIOD

- Land

excavation

for grading

for the

foundation

of

construction

works,

Impacts on air

environment

- Erect the fence around the construction site

at the minimum height of 2m

- Cover the material yards by sheet metal,

plywood, temporary walls located at the end

of wind direction.

- Means of transport shall be covered, the

deck of the track must be carefully lined to

Included in

the contract

value of

construction

contractor

During the

construction

period

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province

- Division of

Natural Resources

Page 135: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

128

installing

the water

supply and

drainage

system,

electric and

communicat

ion systems

- Operations

of machines

for

construction

using diesel

oil as power

generator

- Operations

of transport

vehicles for

the project

such as soil

and

construction

material

truck

-

Transportati

on, storage

and

unloading

the material

maximize the falling of the materials

- Wash the wheels before leaving the

construction site

- Use the watering truck for twice a day at the

point of highly arising dust

- Apply the execution manner and advanced

construction equipment in accordance with

the standards of Bureau of Register

- Mechanical equipment and machine shall be

regularly serviced

- Coordinate the in and out truck schedule to

the construction site on the Ring Road No. 4

to prevent the traffic jam on the highway No.

13 of the high traffic flow

and Environment of

Ben Cat Town

Page 136: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

129

and

excavated

soil

- Operation

of transport

vehicles,

vehicles and

construction

equipment

on the

construction

site as

cranes,

crane

drilling ...

-The

process of

loading and

unloading

materials,

removal of

construction

works,

excavation

of

foundation,

construction

-Excavation

Noise and vibration

- Erect the fence around the construction site

at the minimum height of 2 m

- Apply the execution manner and advanced

construction equipment of the low noise in

accordance with the standards of Bureau of

Register

-Construction equipment of high noise as

hammers, drills, excavators ... are not allowed

to operate at night. In case of necessary to

construct at night, the consent of local

governments and consultation to the local

people around the project is required.

-Only operate the equipment of high noise in

the short period of time during the day. It is

not allowed to use multi equipment of high

no'ise at the same time to avoid resonance

- Mechanical equipment and machine shall be

regularly serviced

-Equip the local noise resistance devices for

workers as noise resistance earplugs and the

workers are required to wear when working

-Install the noise eliminating device for

machines

Included in

the contract

value of

construction

contractor

During the

construction

period

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province

- Division of

Natural Resources

and Environment of

Ben Cat Town

Page 137: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

130

and piling

-Coordinate the in and out truck schedule

-Apply the pile compress method to reduce

the noise to 10-50 times compared to other

methods.

Constructio

n activities:

- Piling

-

Constructio

n of work

items

- Concrete

mixing

- Cleaning

transport

vehicles

Impacts on aquatic

environment (canal K1

and underground

water")

Wastewater from

construction activities:

- Execution of

construction items in

the aquatic

environmental shall

make the sand, stone,

construction material

falling, chemicals

leaking; the

construction of bored

cast-in-place pile for

abutment shall disorder

the mud in the water

and waste due to the

-Clean the construction site and site hut on

daily basis, cover the material yards, dumping

area, chemical and gasoline storage to avoid

the overflow rain water from bringing along

the chemical material causing pollution to the

water source

-Closely manage the construction, chemicals

and machinery maintenance to avoid chemical

from leaking to the water

- Sign contracts with functional units of solid

and hazardous waste treatment to process the

waste in accordance with the law during the

construction phase

-Integrate environmental provisions into the

rules of construction site and communicate to

the workers

-Provide enough mobile toilets with septic

tank, waste bin located in the construction site

and site hut to collect the wastewater and

living waste of workers

Included in

the contract

value of

construction

contractor

During the

construction

period from

2016-2019

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province

- Division of

Natural Resources

and Environment of

Ben Cat Town

Page 138: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

131

Overflow

rainwater:

Daily

activities of

workers

drilling into the water.

Waste oil from

cleaning, maintenance

of construction

equipment.

- Bring with rock, waste

oil, leveling materials,

waste, etc.

Domestic wastewater of

workers:

-Due to the living

activities. It is

estimated of 20-

30m3/day

Constructio

n of:

earthwork,

grading and

transportatio

n of

construction

materials

Construction solid

waste:

-Mostly digging soil,

rubble, scrap of cement,

broken bricks. The

largest percentage of

excavated soil will be

reused for levelling,

earthworks for green

trees planting area to

create the landscape.

The excavated soil shall

be transported outside

-Mostly the excavated soil shall be reused to

level and embank the green trees planting area

-The other construction wastes are utilized for

leveling in the area, or transported for

processing by contracted functional units

-For hazardous waste, it is required to

thoroughly collect and temporarily store in the

warehouse with the steady shelter and sign

contracts with functional units of collecting

and processing the hazardous waste in

accordance with applicable law. This unit

must be licensed to collect and transport

hazardous waste by the competent authority.

Included in

the contract

value of

construction

contractor

During the

construction

period from

2016-2019

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province

- Division of

Natural Resources

and Environment of

Ben Cat Town

Page 139: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

132

Activities of

workers and

staff

working at

construction

site

the construction site of

approximately

Phrase 1: 54,022 m3

Phrase 2: 60,776 m3

Hazardous waste: from

construction activities

such as waste oil,

disposed paint

container, chemical

containers, oil

contaminated rags,

viscous. It is estimated

of about 105 – 115

liters of waste oil/day.

Domestic solid waste:

of workers as can,

packaging, paper,

plastics, glass, food

waste. It is estimated of

about 250 kg/day

Water supply and Sewerage and Environment

of Binh Duong has been licensed to operate in

the area of collection and disposal of

hazardous waste. Project owner can sign

contract with this unit to process the

hazardous waste for the project.

- Provide enough waste bin located in the

construction site and site hut;

-Sign contracts with functional units of

domestic solid waste treatment to collect and

process the domestic waste for the project.

Project owner may sign contract with Urban

Works Company of Ben Cat Town to

transport domestic waste to process at the

general dumping area of the Township at

Chanh Phu Hoa Commune

Digging and

leveling,

foundation

Impacts on soil

environment

-The process of

construction of works

items, earthworks

would make the

stability of the land on

-Calculation in design of the construction for

minimizing the landslide risks.

-Implement the mitigation measures on

impacts of wastewater and solid waste

Included in

the contract

value of

construction

contractor

During the

construction

period from

2016-2019

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province

- Division of

Natural Resources

Page 140: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

133

both sides of K1

channel broken causing

landslides

The type of activity

generated wastewater

as mentioned above

collected improperly is

also the source of soil

contamination

-The solid waste

generated by the

construction and living

activities of workers is

also the cause of land

pollution.

and Environment of

Ben Cat Town

Concentrati

on of a large

number of

workers at

the sute

-

Concentrati

on of

construction

machines

-

Mobilizatio

n of many

machines,

Impacts on the socio-

cultural environment;

The concentrate of

large number of

workers in the region

will arise issues of

social evil and general

hygiene

-Gathering of workers

and movement of

machines shall cause

impacts on street,

transportations resulting

in noise, dust and street

-Establish provisions in the construction site

as well as in the site hut to manage workers

(prohibit gambling, fighting and must keep the

public hygiene)

-Regularly educate the awareness of workers

-Provide the hot line for local people to timely

send feedback

-Encourage recruitment of construction

workers of unskilled workers locally for

reducing the need of setting site hut

Included in

the contract

value of

construction

contractor

During the

construction

period from

2016-2019

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province

- Division of

Natural Resources

and Environment of

Ben Cat Town

Page 141: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

134

vehicles

transporting

waste,

construction

materials

- Using of

water,

electricity

and

infrastructur

e for

construction

damage

-Mobilize an idle

workforce locally

thereby contributing to

solve the labor issues

and rise the temporary

income for workers

- Construction shall

increase the level of

power consumption and

water supply

-Stimulate development

of some types of food

services, activities and

entertainment to serve

the daily needs of

workers in the project

site

Transportin

g

construction

materials

and waste

Impacts on transport

-The means of transport

for the project will

increase the volume of

traffic on the highway

No. 13, Ring Road No.

4. However, the traffic

flow on these two road

route is not so high that

the traffic jam is not

likely to occur

-The schedule for traffic coordination and

guidance at the in and out position of the

construction site is available. Avoid

concentration of too many vehicles of being in

and out at the same time causing traffic jam

on the road.

-Locate the entry gate to the construction site

in Ring Road No. 4 or D9 to avoid traffic

obstruction on highway No. 13, this route has

higher traffic flow than Ring Road no. 4.

-Install the necessary traffic signs

Included in

the contract

value of

construction

contractor

During the

construction

period from

2016-2019

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province

- Division of

Natural Resources

and Environment of

Ben Cat Town

Page 142: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

135

-Increase in the means

of road transport during

the construction time

shall cause the traffic

accident

-Contact to the competent authority to resolve

promptly traffic jams and incidents

-

Constructio

n activities

-

Transportati

on of

construction

materials

- Storage of

oil for

construction

machinery,

waste oil

during

maintenance

of

machinery

and

equipment

- Activities

of workers:

Labour accidents and

explosion:

- The employees do not

properly implement

regulations on

occupational safety

during the construction

under ground and from

height;

-Employees tread on

rust nail, zinc wire, saw

blade ... in the ground

-Crane, trucks, road

rollers entering the

construction site can

lead to accidents caused

by vehicles

-Labour incidents

related to electricity

-Not equipping the

workers with the means

of protection

-Air pollution, thermal

-Workers who directly construct and operate

the machine shall be trained and practised in

proper way in case of issue and always

available at his position to check and operate

as per the techniques;

-Workers shall be equipped with the necessary

cloths as protection cloth, boot, gloves, hat,

glasses…

-Ensure the provisions on lighting for workers

depending on each work types and

characteristics

-Tools and equipment as well as the contact

address when necessary in case of issues shall

be clearly displayed

-Water tap for washing in case of issue,

medical box, eye washing tool kit, oxygen

container.

-Contact address in case of emergency:

hospital, firefighting

-Firefighting and prevention measures in the

construction site

- Strictly comply with provisions on

Included in

the contract

value of

construction

contractor

During the

construction

period from

2016-2019

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province

- Division of

Natural Resources

and Environment of

Ben Cat Town

Page 143: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

136

living,

cooking

pollution caused by the

activities of the project

shall have an adverse

effect on the health of

workers and residents

-Due to carelessness of

workers as smoke

during welding,

cooking place near

flammable source

-Fuels (fuel oil, diesel

oil) is always available

in the construction site

acting as the important

explosion source

-On construction sites,

there are many

inflammable and

combustible materials

in use

-Risk of fire due to

short-circuit and

welding process

firefighting and prevention. Do not leave

flammable materials in the area of arising

ignition as welding area; do not concentrate

fuels such as gasoline, oil near combustible

and high temperature area. It is required to

have the sign at the easily flammable area.

-To prevent fire caused by electricity, it is

required to equip auto shut down devices in

case of overload and incident.

PROJECT OPERATION PERIOD

- Vehicles

of students

and staff in

the

University

Impacts on atmospheric

environment

-Traffic operation at the

university

-Contact to the public bus service unit of the

Province and Becamex to collaborate for the

development of bus route from VGU to the

important locations of Binh Duong and Ho

Chi Minh city at the best price for students

Operating

cost of the

centralized

wastewater

treatment

During

operation stage.

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province

Page 144: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

137

- Operation

of

generators

- Operation

of

laboratory

system

- Activities

of students

and school

staff (office,

kitchen)

- Operation

of

centralized

sewage

treatment

plants

-Operation of back-up

generators

-Emitted air from

laboratory

- Odors from the

kitchen area

- Odors from the

wastewater treatment

and waste area…

and staffs of VGU

-Design the entry gate of VGU from Ring

Road no. 4 to avoid the traffic flow from

highway no. 13

-Install the chimney with suitable height for

the generator. Regularly service the system of

generators

-Use diesel oil of low sulphur or bio-diesel oil

when applicable

-For emissions from lab, equip hoods to

ensure the health of people working in the lab.

Due to the small and irregular emission

volume, it is not necessary to install the

exhaust treatment system, just mount the

exhaust vents to take the exhaust gas to the

outside

- Ensure the distance from the WWTp to other

works is 15m, plant strips of green trees as

prescribed, make works generating many

odors closed and install odor handling

equipment

plant:

Approximat

ely 3,000

VND/1m3/

day.

The cost for

periodic

environment

al

monitoring:

7,957,640

VND/quarte

r

- Division of

Natural Resources

and Environment of

Ben Cat Town

Transport

activities

Operation of

backup

Noise

-Traffic operation at the

university

-Operation of back-up

generator

-Encourage to use the public means of

transport for reducing the noise from means of

transportation to the university.

-The parking area shall be located far from the

classroom with the green trees fence to reduce

the noise

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province

- Division of

Page 145: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

138

generator

Operation of

other

equipment

such as

pumps, air-

conditioners

,

-Design the entry gate of VGU on Ring Road

no. 4 to avoid the traffic flow on highway no.

13

-Regularly service the system of generators,

air conditioners, ventilators and other noise

causing machines

-Put the noise causing equipment in the

soundproof room

Natural Resources

and Environment of

Ben Cat Town

Daily

activities,

learning of

students and

staff in the

University

Impacts of waste water:

-Domestic wastewater

of VGU from kitchen,

toilets, etc. it is

estimated that domestic

wastewater in Phase 1

is about 737 m3/day

and 1,762m3/day in

phase 2.

-Wastewater from

laboratory of about:

5m3/day in the phrase 1

and about 10m3/day in

the Phase 2.

-Overflow rain water

brings along the waste,

leaked oil.

-Organize a campaign to raise awareness for

students and staffs in VGU about saving water

-Wastewater from laboratory shall be

preliminarily treated by neutralization,

precipitation or flocculation methods.

Wastewater respecting category B shall be

connected to the collection system and taken

to the concentrated wastewater plant

-Most of wastewater from concentrated

wastewater plant after treatment meeting the

standard of category A, QCVN

14:2008/BTNMT shall be reused and the

remainer shall be discharged to the channel

K1 at (X=1228688.4966; Y=594402.8061)

Project

owner and

Contractor

Page 146: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

139

Activities of

living,

learning of

students and

staff in the

University

Impacts of solid waste

-Non-hazardous waste:

mainly the domestic

living waste from

office, kitchen,

restaurant, hostel. It is

estimated to be

4100kg/day (phase 1)

and about 9700 kg/day

(in phase 2).

-Hazardous waste:

waste from laboratory,

oil, lubricant, medical

waste of all types,

sludge from the WTP.

There is an

appropriately of 540

kg/month (phase 1) and

1340 kg/month (phase

2)

-Build the waste sorting program at source in

accordance with existing regulations and

capabilities, plan for solid waste management

of Binh Duong Province

-Organize the communication campaign for

students and establish the habit of sorting the

waste at source

-On daily basis, staffs of VGU will collect

organic waste to the waste collecting point

-Sign contract with functional units for

collection and treatment of these types of

waste in accordance with the regulations

- Hazardous waste shall be managed in

accordance with the regulations at Circular

No. 12/2006/TT-BTNMT dated 26 December

2012 and solid waste shall be collected,

managed and treated in accordance with the

provisions of Decree No. 59/2007/NĐ-CP and

Decree No. 38 on management of waste and

residue.

-Hazardous waste must be collected and

stored in separate containers from non-

hazardous waste, the tank must be painted by

dangerous sign.

-Waste chemical from laboratories must be

kept in accordance with the regulations on

chemical and biological safety. These

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province

- Division of

Natural Resources

and Environment of

Ben Cat Town

Page 147: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

140

regulations shall be open for all staffs in the

laboratories

- Register the owner of hazardous waste

source with Department of Natural Resources

and Environment of Binh Duong Province

-Sign contract with hazardous waste collection

and treatment units in accordance with the

applicable law. This unit must be licensed to

collect and transport hazardous waste by the

competent authority. In Binh Duong, Water

supply, Sewerage and Environment of Binh

Duong is licensed for processing the

hazardous waste and it is one of prestigious

company in Binh Duong Province in this field.

Training

and

activities of

the

university

Socio-economic impact

Positive impacts;

-Develop and improve

the quality of higher

education and post-

graduate in Vietnam in

general and in

particular in Binh

Duong

-Attract and create jobs

for human resources in

the region

-Facilitate the cultural

development of the

- VGU has full services for students, staffs

and lecturers thus it can decrease the exchange

activities with business operation outside the

university. This contributes to reducing the

loss of order and security, external trade

business.

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province

- Division of

Natural Resources

and Environment of

Ben Cat Town

Page 148: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

141

region

-Contribute to solving

jobs for some local

people

Negative impacts:

The concentration of

business people shall

cause the disorder and

insecurity, at the result,

the traffic accidents and

social evil shall

increase in the region.

Risks on community

health and explosion

-Concentration of many

people from many

regions shall increase

the risks of spreading

the diseases

-At the laboratory, due

to wrongly storing and

manipulating with

chemical, the chemical

can spill or the

provisions on chemical

safety have not

provided and the

necessary training for

those working in the

-VGU has invested in medical station for

regular examination for students, lecturers and

staffs in the university

-Establish procedures for operation and safety

management of chemicals in the laboratory.

Educate these procedures for staffs working in

the laboratories

-Regularly service the electric system and

machines

-Setting up the infrastructure systems and

procedures for fire prevention and periodically

practise the fire protection situation for

students and staffs

-Have the regime for regular health

examination for staffs and students

Project

owner and

Contractor

- Department of

Natural Resources

and Environment of

Binh Duong

Province

- Division of

Natural Resources

and Environment of

Ben Cat Town

Page 149: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

142

laboratory has not been

held

-Incidents of short

circuit, carelessness in

the living activities of

students and staffs

-When a disease outbreak, VGU must conduct

following steps:

+ Strictly comply with the guidance of

Ministry/Department of Health, Ministry and

Department of Education

+To set up the prevention division in

university to link with relevant authorities to

conduct guidance and monitor the disease

situation, guide how to prevent the disease for

students and staff

+ Migrate the students when necessary

For the implementation of mitigation measures of environmental impacts in project construction process, Investor and Contractor should co-operate to

deploy good the proposed mitigation measures and further refer Environmental Code of Practices (ECOPs) that achieved at Appendix 1.

Page 150: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

143

5.3. Environmental compliance framework

A compliance framework, based on the environmental requirements established by the

EMP and Environmental Specifications included in bidding documents, will be strictly

enforced by Supervision engineers. Minor and major infringements will be determined

according to the following categorization table:

Category of Infringement Definition Remediation

Minor Infringement Incident which causes

temporary but reversible

damage to the environment,

community property, people.

Minor clean up operations

Minor restoration

activities

Adjustments/eliminations

to construction practices

Compliance with EMP

Major Infringement Incident where there is long-

term or irreversible damage

to the environment,

community property, and

people

Major clean up operations

Major restoration

requiring engineering

measures

Major restoration of

community property

Compensation to affected

communities or persons.

For minor infringements—an incident which causes temporary but reversible damage—the

contractor will be given a reasonable period of time to remediate the problem and to

restore the environment. If restoration is done satisfactorily during this period, no further

actions will be taken. If it is not done during this period, the PMU will immediately

arrange for another contractor to do the restoration, and deduct the cost from the offending

contractor‘s next payment. For major infringements—an incident where there is long-term

or irreversible damage—there will be a financial penalty in addition to the cost for

restoration activities. To minimize the damage, the restoration activities will be

implemented without delay.

The compliance framework will be applied as follows:

- The CMC will identify or be notified of an infringement (community member,

local government)

- The CMC in consultation with relevant stakeholders will assess whether it is a

minor or major infringement.

For minor infringements:

- The CMC will establish the required mitigation measures, and the time period,

which is a maximum of five days to remedy the situation.

- The CMC will review the recommendation and confirm (i) the level of

infringement (minor/major); (ii) the mitigation measures; and (iii) the mitigation

time period. If they do not agree, they will work with the PMU to reach mutually

acceptable recommendations.

Page 151: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

144

- The Contractor will be informed of the infringement, the required mitigation

measures, and time period for resolution.

- The Contractor shall remedy the infringement in accordance with the

recommendations within the agreed time period.

- The CMC shall confirm the infringement is satisfactory remedied in the time

period.

- If the infringement is not remedied satisfactorily in the time period the CMC shall

inform the PMU. The PMU shall immediately arrange for a separate contractor to

undertake the necessary works and the cost of this shall be deducted from the next

payment to the offending contractor.

For significant infringements:

- The CMC shall immediately inform the PMU of the incident

- The PMU shall inform the appropriate provincial authorities if appropriate

- The PMU, in consultation with the CMC and other provincial authorities as

appropriate, shall agree upon mitigation and clean up measures to be undertaken

immediately by the contractor or by specialists to be procured at the contractor‘s

expense. To minimize the environmental impacts the restoration activities should

be completed within ten days.

- The PMU shall apply a financial penalty, not to exceed 1% of the contract cost, for

each major infringement, in addition to any costs associated with the infringement

not borne by the contractor.

Any conflicts between the Contractor and CMC shall be resolved by the PMU.

Page 152: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

145

5.4. Estimated costs for construction of environmental treatment works

Including the costs for implementing environmental remediation measures during the

project construction and operation phases.

- Fencing system surrouding the Project

- Hiring Water Sprinkler

- Solid waste container at site

- Construction of temporary toilets/renting of portable toilets at construction site

- Equipped with garbage containers for buildings, dormitories and public houses;

- Wastewater treatment system.

- Sewerage system.

- Drainage system.

- Collection system, solid waste treatment

- Fire protection system.

- Lightning protection system.

- Green trees.

Table 59. Estimated costs for construction of environmental treatment works

No. Work items Cost (package)

Stage 1 Stage 2

I. Construction stage

1 Temporary fence to prevent dust

and noise

50,000,000

30,000,000

2 Hiring Water Sprinkler or

arrangement of artesian water

hoses

70,000,000

70,000,000

3 Equipped with garbage

containers and waste oil tank,

solid hazardous waste

15,000,000

15,000,000

4 Construction of temporary

toilets/renting of portable toilets

30,000,000

30,000,000

Sub-total (I) 165,000,000 145,000,000

II Operation stage

1 Equipped with bins for buildings,

dormitories, public service

buildings and public areas

500,000,000

500,000,000.00

2 Drainage system 55,062,987,000 18,354,329,000

3 Sewerage system and WWTP,

wastewater monitoring station 9,376,059,000 2,344,014,750

4 Fire alarm and firefighting 77,612,295,744 25,870,765,248

Page 153: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

146

system

5 Landscape, green trees 106,505,990 21,301,198

Sub-total (II) 142,657,847,734 47,090,410,196

Total 142,822,847,734 47,235,410,196

The cost estimated for operation of wastewater treatment plant is 3,000 Vietnam

Dong/m3/day and paid by VGU.

For the operation of the wastewater treatment plant of VGU, the cost is estimated at VND

3,000 / m3 / day and will be paid by VGU budget.

5.5. Environmental monitoring program

5.5.1. Construction stage

Table 60. Contents of Environmental monitoring in construction stage

No. Contents Positions Qty

(position/

sample)

Parameters Comparative

standards

1 Air

environment

1. Entrance gate

2. Intersetion

between

National

Highway 13 and

Ring Road 4

3. Residential

areas of hamlet

3, border with

Road D9

4. Residential

areas in the

South, border

with the project.

04 Noise, dust, SO2,

CO, NO2.

QCVN

05:2013/BTN

MT and

QCVN

06:2009/BTN

MT

2 Surface

water

environment

Construction

area, on K1

canal

01 Monitoring the

collection and

treatment of

preliminary

wastewater in the

construction

process.

The surface

water monitoring

parameters

include: pH,

TSS, grease,

NH4+, NO3

-,

QCVN

08:2008/BTN

MT

Page 154: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

147

coliform

3

Solid waste,

hazardous

solid waste

Construction

areas and

gathering area

of waste and

hazardous waste

-

Regularly

inspectthe

collection,

storage and

treatment of

wastewater and

domestic waste

and hazardous

solid waste in

areas.

5.5.2. Operation stage

Table 61. Contents of waste monitoring in operation stage of the project

No.

Contents Positions Qty

(position/

sample)

Parameters QCVN

1 Water environment

Treated wastewater

Discharge

points of the

WWTP

01 pH, TSS,

BOD5, COD,

Total N, total

P, Nitrate,

NH3, Cu, Pb,

Zn, Cd, As,

grease,

Coliform,

wastewater

flow

QCVN 14:2008/BTNMT

(Column A)

Air environment at

centralized

wastewater

treatment

plant

01 Monitoring

unpleasant

ordors:NH3,

H2S

QCVN 06:2009/BTNMT

Lab 01 acidic gas,

volatile

organic

compound

(VOCs)

Decision No.

3733/2002/QĐ - BYT

2 Solid waste,

hazardous solid

waste

Solid waste

concentrated

areas

(rubbish

bins,

hazardous

solid waste

bins..)

- Regularly

check the

collection,

storage and

treatment of

wastewater

and domestic

waste and

-

Page 155: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

148

hazardous

solid waste in

areas.

5.5.3. Monitoring frequency:

5.5.3.1. During construction stage of the project:

- Monitor periodically every 3 months.

- Unscheduled monitoring: In case of environmental incidents or complaints of local

authorities or people.

5.5.3.2. During operation stage of the project:

- Monitor periodically when the project is put into operation:

Water Environment Monitoring: every 03 months. However, VGUcommits to keep

monitoring on daily basis by automatic monitoring system to inspect the effluent

quality and ensure that the operation of the wastewater treatment plant works well. This

is also a good implementation of regulations on environmental protection of Binh

Duong province for wastewater treatment plants with a capacity of 1000 m3/day or

higher. This requirement is stipulated in Article 29 – Regulations on environmental

protection, Binh Duong province, issued together with Decision No. 63/2012/QĐ-

Committee dated December 18, 2012 of Binh Duong PPC.

- Unscheduled monitoring: When there are any environmental incidents or complaints

of local authorities or people

5.5.4. Estimated cost for monitoring

Pursuant to the unit price of environmental sample analysis taken at the Document No.

3078/QD-UBND dated November 18, 2011 of Binh Duong province on issuing unit price

of environmental monitoring in Binh Duong province, the estimated funding for

monitoring activities of the project are as follows:

5.5.4.1. Construction stage

- Regular monitoring cost is about 10,668,870 VND/quarter

+ Monitoring of waste: 3,000,0000 VND/v.

+ Monitoring of air environment: 5,044,160 VND/quarter.

+ Monitoring of surface water environment: 1,035,100 VND/quarter.

- Unscheduled monitoring: depends on level of incidents or in each specific case.

5.5.4.2. Operation stage

- Regular monitoring cost is about 7,957,640 VND/quarter:

+ Monitoring of waste: 3,000,0000 VND/quarter.

+ Monitoring of effluent quality: 4,457,640 VND/quarter.

+ Monitoring of air quality: 500,000 VND/quarter.

- Unscheduled monitoring: depends on level of incidents or in each specific case.

Page 156: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

149

CHAPTER 6

PUBLIC CONSULTATION

The project is located in Thoi Hoa ward, Ben Cat Town. Prior to public consultation, the

Project owner has sent a Letter No. 65/CV –DA ĐHVĐ dated 20 April, 2015 to the

People's Committee of Thoi Hoa ward to inform the basic contents of the project, the

negative impacts of the project on the environment, the adverse impact mitigation

measures to be tentatively applied and request Thoi Hoa Ward PC for response in writing.

Thoi Hoa Ward PC also gave comments via the letter No. 43/CV-UBND dated 24 april,

2015 to the Project owner.

The following is the summary of comments and feedbacks from Thoi Hoa Ward People's

Committee and other departments, units and households in the project areas:

6.1. Comments made by Thoi Hoa Ward People's Committee and local communities

A public consultation meeting in the project area in Thoi Hoa ward was held with the

cooperation between Thoi Hoa ward PC, Project Owner and EIA Consultant. The followings

are contents of the meeting:

- Information dissemniation: the summary of the project, summary of project‘s

potential environmental and social impacts, proposed mitigation measures for

negative environmentl and social impacts, and construction items in each project

period.

- Plan for EIA study;

- Consultation with local authorities and people about environmental issues through

discussion in the meeting.

Date Loation of

meeting

No. Of

participants

Participants

23/4/2015 Thoi Hoa

ward

21 o Representatives of the PMU;

o Representatives of the local

authorities;

o Representatives of local

organizations;

o Affected households in the project

area;

o The EA Consultant.

Comments made by Thoi Hoa ward PC and the community are presented as follows:

a) Positive impacts of the Project:

+ Contribute to the improvement of the quality of higher education, of human

resources for Binh Duong province, attracting highly qualified personnel to work in Binh

Duong province.

+ Improve the educational level in the areas;

+ Change the conditions of living of local people in a positive way.

Page 157: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

150

+ Increase local budgets through entrepreneurial activities, supply

of catering services to students, University staff.

b) Negative impacts of the Project:

Besides the positive impacts as mentioned above, when the project is put into operation,

the following shortcomings may occur:

+ The construction as well as operation of the University will generate factors that

will have negative impacts to the environment in locality.

+ During the construction, machinery and construction material transport will

create noise, increase concentrations of airborne dust, traffic accidents on

transport routes and the surrounding project areas.

+ The security in the area will be affected if there are not any worker and student

management plan in the construction stage.

+ Because the project is located on the Highway 13 and Ring Road 4, it may cause

traffic problems if there are no reasonable plans.

c) Conclusion and recommendation

- Conclusion: Agree and support the project implementation in locality.

- Recommendations:

+ The project owner must comply with the environmental protection measures as

stated in the Community Consultation Report.

+ During the project implementation, the project owner is requested to fully

implement the provisions of the relevant laws.

+ Take part in the implementation of environmental protection programs in the

province.

+ Coordinate with local authorities in maintaining order and social security.

+ Well implement social policies in locality.

6.2. Feedbacks and commitment of the Project owner on comments of Thoi Hoa WPC

and local communities in the project area.

The project owner totally agrees with the comments on positive, negative impacts, and

recommendations as well as the requirements of the People's Committee of Thoi Hoa ward

and local communities in the project area as aforementioned.

The project owner has been committed to take measures to control and mitigate negative

impacts that may occur during the construction and operation phase of the project, to

comply with the Environmental Protection Act under the current regulations. Regarding

the recommendations of local authorities, the project owner confirmed that they will

coordinate with local authorities during project implementation to ensure good working

order and security in the area, fully implement its obligations to the locality and have no

effects on the lives of people in resident areas.

6.3. Disclosure

Before public consultation, the project owner has provided relevant material

including project description, project‘s objectives, and the summary of project‘s potential

environmental and social impacts and proposed mitigation measures for negative

environmental and social impacts in Vietnamese to project affected groups who will be

consulted. The updated EIA report in Vietnamese language will be locally disclosed at the

office of Thới Hoa Ward People‘s Committee and the office of PMU at No. 12 A, Hai Ba

Page 158: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

151

Trung Street, Hoan Kiem District, Hanoi, Vietnam, VGU website and VDIC. The English

version will be disclosed at the Bank‘s InfoShop in Washington D.C.

Page 159: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

152

CONCLUSION, RECOMMENDATION AND COMMITMENT

1. Conclusion

The Construction of Vietnamese - German University Project plays an important role in

developing and improving the quality of higher and postgraduate education in Vietnam in

general and in Binh Duong in particular. This is an engineering university under the

German model - a widely known and very successful model in the world. The objective is

to make VGU become a leading research university, bringing about positive impacts on the

country's education system. The project will also attract and create jobs for talented human

resources in the area.

The environmental impact assessment report of the Vietnamese - German University

construction project has identified and listed the entire environmental impacts in the site

preparation stage, construction stage and operation stage, from which mitigation measures

and environmental management and monitoring program will be prepared.

Within the scale of Vietnamese - German University, the environmental impacts arising

from construction and operation stage are not big, but the impacts of air emissions,

wastewater, solid waste and environmental risks and incidents should be paid attention.

However, these impacts can be prevented and minimized. Negative impact mitigation

measures as well as prevention of environmental incidents as proposed are highly feasible

and lies in the ability of the VGU.

2. Recommendation

The VGU recommend that the Natural Resources and Environment Department of Binh

Duong province will review and approve the environmental impact assessment report of

the Vietnamese - German University Project so that the Project can proceed the next steps.

3. Commitment

3.1. Commitment to measures, regulations on environmental protection related to the

Project

3.1.1. Air environment in the area shall have to attain the following standards:

- QCVN 05:2013/BTNMT – National Technical Regulations on Ambient Air Quality.

- QCVN 06:2009/BTNMT-2005 – National Technical Regulations on hazardous

substances in ambient air.

- QCVN 26:2010/BTNMT: National Technical Regulations on noise.

3.1.2. Labour environment in the area shall have to attain the following standards:

For ambient air in the working area: respect to occupational health standard under the

Decision No. 3733/2002/QD-BYT dated 10/10/2002 of the Minister of Health

promulgating "21 labor hygiene standards, 05 principles and 07 labor hygiene

measurements".

3.1.3. Water environment

Treated domestic wastewater shall have to respect QCVN 14:2008/BTNMT- National

Technical Regulations on Domestic Wastewater (Column A).

Installation of wastewater automatic monitoring systems as defined at the Decision No.

63/2012/QĐ-UBUND dated December 18, 2012 of the Binh Duong PPC.

Page 160: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

153

3.1.4. Waste

Waste is collected neatly and classified as follows:

- Recycled waste shall be sold to recycling collectors.

- Domestic waste shall be collected by Urban Work Enterprise of Ben Cattown and

transported to the landfill of Chanh Hoa Phu commune, Ben Cat town.

- Hazardous solid waste: a list of hazardous solid waste of the University shall be

prepared and wastewater shall be registered as stipulated collected and treated under

current regulations under the Circular No. 36/2015/TT-BTNMT dated 30/6/2015 a

contract with Binh Duong Water Supply, Sewerage and Environment Company.

VGU commits the solid waste management will comply with Decree 59/2007/ND-CP

dated 09/4/2007 of the Government on Solid waste management and Decree No.

38/2015/ND-CP dated 24/4/2015 of the government on the management of waste and

scrap.

3.2. Commitment to completion time of environmental treatment facilities

During the project construction, a waste treatment system shall be installed concurenetly

and the treatment works shall be completed before the project is put into operation.

Where there are environmental incidents and risks caused by the project implementation,

the University commits to the compensation and remedy for environmental pollution and

environmental rehabilitation measures under regulations.

We commit to take full responsibility before the law of the Socialist Republic of Vietnam

if violate international conventions, environmental standards of Vietnam and the

occurrence of accidents caused environmental pollution.

Page 161: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

154

APPENDICES

Page 162: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

155

APPENDIX 1. STANDARDIZED ENVIRONMENTAL CODES OF PRACTICE (ECOP)

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

1. Dust generation The Contractor is responsible for compliance with relevant Vietnamese

legislation with respect to ambient air quality.

The Contractor shall ensure that the generation of dust is minimized and is not

perceived as a nuisance by local residents and shall implement a dust control

program to maintain a safe working environment and minimize disturbances for

surrounding residential areas/dwellings.

The Contractor shall implement dust suppression measures (e.g. use water

spraying vehicles to water roads, covering of material stockpiles, etc.) as

required.

Material loads shall be suitably covered and secured during transportation to

prevent the scattering of soil, sand, materials, or dust.

Exposed soil and material stockpiles shall be protected against wind erosion and

the location of stockpiles shall take into consideration the prevailing wind

directions and locations of sensitive receptors.

QCVN 05:

2013/BTNMT:

National technical

regulation on

ambient air quality

Page 163: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

156

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

2. Air pollution All vehicles must comply with Vietnamese regulations controlling allowable

emission limits of exhaust gases.

Vehicles in Vietnam must undergo a regular emissions check and get certified

named: ―Certificate of conformity from inspection of quality, technical safety and

environmental protection” following Decision No. 35/2005/QD-BGTVT;

There should be no burning of waste or materials on site.

TCVN 6438-2005:

Road vehicles.

Maximum permitted

emission limits of

exhaust gas.

No. 35/2005/QD-

BGTVT on

inspection of quality,

technical safety and

environmental

protection;

QCVN

05:2013/BTNMT:

National technical

regulation on

ambient air quality

Page 164: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

157

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

3. Impacts from noise

and vibration The contractor is responsible for compliance with the relevant Vietnamese

legislation with respect to noise and vibration.

All vehicles must have appropriate ―Certificate of conformity from inspection of

quality, technical safety and environmental protection” following Decision No.

35/2005/QD-BGTVT; to avoid exceeding noise emission from poorly maintained

machines.

When needed, measures to reduce noise to acceptable levels must be

implemented and could include silencers, mufflers, acoustically dampened panels

or placement of noisy machines in acoustically protected areas.

QCVN

26:2010/BTNMT:

National technical

regulation on noise

QCVN

27:2010/BTNMT:

National technical

regulation on

vibration

Page 165: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

158

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

4. Water pollution The Contractor must be responsible for compliance with the relevant Vietnamese

legislation relevant to wastewater discharges into watercourses.

Portable or constructed toilets must be provided on site for construction workers.

Wastewater from toilets as well as kitchens, showers, sinks, etc. shall be

discharged into a conservancy tank for removal from the site or discharged into

municipal sewerage systems; there should be no direct discharges to any

waterbody.

Wastewater over permissable values set by relevant Vietnam technical

standards/regulations must be collected in a conservancy tank and removed from

site by licensed waste collectors.

Before construction, all necessary wastewater disposal permits/licenses and/or

wastewater disposal contract have been obtained

At completion of construction works, water collection tanks and septic tanks

shall be covered and effectively sealed off.

QCVN

09:2008/BTNMT:

National Technical

Standard on

underground water

Quality

QCVN

14:2008/BTNMT:

National technical

regulation on

domestic wastewater;

TCVN 7222: 2002:

General requirements

on centralized

wastewater treatment

plant;

Page 166: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

159

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

5. Drainage and

sedimentation

control

The Contractor shall follow the detailed drainage design included in the

construction plans, intended to prevent storm water from causing local flooding

or scouring slopes and areas of unprotected soil resulting in heavy sediment loads

affecting local watercourses.

Ensure drainage system is always maintained cleared of mud and other

obstructions.

Areas of the site not disturbed by construction activities shall be maintained in

their existing conditions.

Earthworks, cuts, and fill slopes shall be properly maintained, in accordance with

the construction specifications, including measures such as installation of drains,

use of plant cover.

To avoid sediment-laded runoff that could adversely impact watercourses, install

sediment control structures where needed to slow or redirect runoff and trap

sediment until vegetation is established. Sediment control structures could

include windrows of logging slash, rock berms, sediment catchment basins, straw

bales, storm drain inlet protection systems,or brush fences.

Site de-watering and water diversions: In the case that construction activities

require that work be carried out within the watercourse (e.g. culvert or bridge

crossing construction, retaining wall construction, erosion protection works), the

work area must be dewatered to provide for construction in dry conditions. The

sediment laden water pumped from the work area must be discharged to an

appropriate sediment control measure for treatment before re-release to the

stream.

Stream diversions or construction of cofferdams would require site-specific

TCVN 4447:1987:

Earth works-Codes

for construction

Decree No.

22/2010/TT-BXD on

regulation of

construction safety

QCVN

08:2008/BTNMT–

National technical

regulation on quality

of surface water

Page 167: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

160

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

mitigation measures in the EMP.

6. Management of

stockpiles, quarries,

and borrow pits

Large scale borrow pits or stockpiles will need site-specific measures that go

beyond those in these ECOPs.

All locations to be used must be previously identified in the approved

construction specifications. Sensitive sites such as scenic spots, areas of natural

habitat, areas near sensitive receptors, or areas near water should be avoided.

An open ditch shall be built around the stockpile site to intercept wastewater.

Stockpile topsoil when first opening a borrow pit and use it later to restore the

area to near natural conditions.

If needed, disposal sites shall include a retaining wall.

If the need for new sites arises during construction, they must be pre-approved by

the Construction Engineer.

If landowners are affected by use of their areas for stockpiles or borrow pits, they

must be included in the project resettlement plan.

If access roads are needed, they must have been considered in the environmental

assessment.

Page 168: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

161

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

7. Solid waste Before construction, a solid waste control procedure (storage, provision of bins,

site clean-up schedule, bin clean-out schedule, etc.) must be prepared by

Contractors and it must be carefully followed during construction activities.

Before construction, all necessary waste disposal permits or licenses must be

obtained.

Measures shall be taken to reduce the potential for litter and negligent behavior

with regard to the disposal of all refuse. At all places of work, the Contractor

shall provide litter bins, containers and refuse collection facilities.

Solid waste may be temporarily stored on site in a designated area approved by

the Construction Supervision Consultant and relevant local authoritiesprior to

collection and disposal through a licensed waste collector, for example,

URENCO.

Waste storage containers shall be covered, tip-proof, weatherproof and scavenger

proof.

No burning, on-site burying or dumping of solid waste shall occur.

Recyclable materials such as wooden plates for trench works, steel, scaffolding

material, site holding, packaging material, etc shall be collected and separated

on-site from other waste sources for reuse, for use as fill, or for sale.

If not removed off site, solid waste or construction debris shall be disposed of

only at sites identified and approved by the Construction Supervision Consultant

and included in the solid waste plan. Under no circumstances shall the contractor

dispose of any material in environmentally sensitive areas, such as in areas of

natural habitat or in watercourses.

Decree No.

59/2007/ND-CP on

solid waste

management

Page 169: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

162

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

Page 170: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

163

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

8. Chemical or

hazardous wastes Chemical waste of any kind shall be disposed of at an approved appropriate

landfill site and in accordance with local legislative requirements. The Contractor

shall obtain needed disposal certificates.

The removal of asbestos-containing materials or other toxic substances shall be

performed and disposed of by specially trained and certified workers.

Used oil and grease shall be removed from site and sold to an approved used oil

recycling company.

Used oil, lubricants, cleaning materials, etc. from the maintenance of vehicles

and machinery shall be collected in holding tanks and removed from site by a

specialized oil recycling company for disposal at an approved hazardous waste

site.

Used oil or oil-contaminated materials that could potentially contain PCBs shall

be securely stored to avoid any leakage or affecting workers. The local DONRE

must be contacted for further guidance.

Unused or rejected tar or bituminous products shall be returned to the supplier‘s

production plant.

Relevant agencies shall be promptly informed of any accidental spill or incident.

Store chemicals appropriately and with appropriate labeling

Appropriate communication and training programs should be put in place to

prepare workers to recognize and respond to workplace chemical hazards

Prepare and initiate a remedial action following any spill or incident. In this case,

the contractor shall provide a report explaining the reasons for the spill or

Decision No.

23/2006/QD-

BTNMT with list of

hazardous substance

Circular No.

36/2015/TT-BTNMT

on management of

hazardous substance

Page 171: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

164

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

incident, remedial action taken, consequences/damage from the spill, and

proposed corrective actions.

Page 172: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

165

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

9. Management of small

amounts of sludge Dredging plan should be established including time schedule, method statement

to meet the requirements of traffic safety, public health and environmental

sanitation. In order to ensure dredging that is consistent with environmental

regulations, key decision makers (local authority, DONRE, utility company,

CSC, etc.) must be involved and concur in each key decision point in the process

leading to preparation and implementation of a plan.

Characteristics of sludge/sediment shouldbe determined by sampling and analysis

if not already fully evaluated during the EIA. Sludge that is heavily contaminated

would require measures that go beyond the scope of these ECOPs.

Ensure that dredged material management plans incorporate environmental

considerations in the identification of short-term and long-term disposal

alternatives, consider methods to reduce dredging, and maximize the beneficial

use of dredged materials.

Dredging work should be conducted when water flow is high to allow the

dredged materials can be separated into the sediment and the supernatant water

(i.e., spoil) by settling.

Lixiviate from dredged materials should not be allowed to enter watercourses

without appropriate filtering or treatment.

Collected dredged materials have to be processed, as per Vietnamese regulations

on waste collection, to ensure safe and environmentally secure transportation,

storage, treatment and management

Those involved in handling of sludge should be specialized and have certification

of sludge handling. Guidelines for certification of sludge handling is in the

Circular No. 12/2011/TT-BTNMT on management of hazardous substance

Decision No.

23/2006/QD-

BTNMT with list of

hazardous substance

Decree No.

59/2007/ND-CP on

solid waste

management

Decree No.

38/2015/ND-CP on

managing waste and

wastage

Circular No.

36/2015/TT-BTNMT

on management of

hazardous substance

Page 173: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

166

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

Sanitary landfill site should meet technical requirements, based on level of

potential contamination.

10. Disruption of

vegetative cover and

ecological resources

The Contractor shall prepare a Clearance, Re-vegetation and Restoration

Management Plan for prior approval by the Construction Engineer, following

relevant regulations. The Clearance Plan shall be approved by Construction

Supervision Consultant and followed strictly by contractor. Areas to be cleared

should be minimized as much as possible.

The Contractor shall remove topsoil from all areas where topsoil will be

impacted on by rehabilitation activities, including temporary activities such as

storage and stockpiling, etc; the stripped topsoil shall be stockpiled in areas

agreed with the Construction Supervision Consultant for later use in re-

vegetation and shall be adequately protected.

The application of chemicals for vegetation clearing is not permitted.

Prohibit cutting of any tree unless explicitly authorized in the vegetation clearing

plan.

When needed, erect temporary protective fencing to efficiently protect the

preserved trees before commencement of any works within the site.

No area of potential importance as an ecological resource should be disturbed

unless there is prior authorization from CMS. This could include areas of

breeding or feeding of birds or animals, fish spawning areas, or any area that is

protected as a green space.

The Contractor shall ensure that no hunting, trapping shooting, poisoning of

fauna takes place.

Law on Environment

protection No.

55/2014/QH13 dated

23/06/2014

Page 174: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

167

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

11. Traffic management Before construction, carry out consultations with local government and

community and with traffic police.

Significant increases in number of vehicle trips must be covered in a construction

plan previously approved. Routing, especially of heavy vehicles, needs to take

into account sensitive sites such as schools, hospitals, and markets.

Installation of lighting at night must be done if this is necessary to ensure safe

traffic circulation.

Place signs around the construction areas to facilitate traffic movement, provide

directions to various components of the works, and provide safety advice and

warning.

Employing safe traffic control measures, including road/rivers/canal signs and

flag persons to warn of dangerous conditions.

Avoid material transportation for construction during rush hour.

Passageways for pedestrians and vehicles within and outside construction areas

should be segregated and provide for easy, safe, and appropriate access. Signpost

shall be installed appropriately in both water-ways and roads where necessary.

Law on traffic and

transportation No.

23/2008/QH12

Law on construction

No. 50/2014/QH13

Page 175: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

168

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

12. Interruption of

utility services Planned and unplanned interruptions to water, gas, power, internet services: the

Contractor must undertake prior consultation and contingency planning with

local authorities about the consequences of a particular service failure or

disconnection.

Coordinate with relevant utility providers to establish appropriate construction

schedules.

Provide information to affected households on working schedules as well as

planned disruptions (at least 5 days in advance).

Interruptions of water supply to agricultural areas must also be avoided.

The contractor should ensure alternative water supply to affected residents in the

event of disruptions lasting more than one day.

Any damages to existing utility systems of cable shall be reported to authorities

and repaired as soon as possible.

Decree No.

73/2010/ND-CP on

administrative

penalization security and

society issues

Page 176: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

169

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

13. Restoration of

affected areas Cleared areas such as borrow pits no longer in use, disposal areas, site facilities,

workers‘ camps, stockpiles areas, working platforms and any areas temporarily

occupied during construction of the project works shall be restored using

landscaping, adequate drainage and re-vegetation.

Start re-vegetation at the earliest opportunity. Appropriate local native species of

vegetation shall be selected for the planting and restoration of the natural

landforms.

Spoil heaps and excavated slopes shall be re-profiled to stable batters, and

grassed to prevent erosion;

All affected areas shall be landscaped and any necessary remedial works shall be

undertaken without delay, including green-spacing, roads, bridges and other

existing works

Trees shall be planted at exposed land and on slopes to prevent or reduce land

collapse and keep stability of slopes

Soil contaminated with chemicals or hazardous substances shall be removed and

transported and buried in waste disposal areas.

Restore all damaged road and bridges caused by project activities

Law on Environment

protection No.

55/2014/QH13

Page 177: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

170

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

14. Worker and public

Safety Contractor shall comply with all Vietnamese regulations regarding worker safety.

Prepare and implement action plan to cope with risk and emergency

Preparation of emergency aid service at construction site

Training workers on occupational safety regulations

If blasting is to be used, additional mitigation measures and safety precautions

must be outlined in the EMP.

Ensure that ear pieces are provided to and used by workers who must use noisy

machines such as piling, explosion, mixing, etc., for noise control and workers

protection.

During demolition of existing infrastructure, workers and the general public must

be protected from falling debris by measures such as chutes, traffic control, and

use of restricted access zones.

Install fences, barriers, dangerous warning/prohibition site around the

construction area which showing potential danger to public people

The contractor shall provide safety measures as installation of fences, barriers

warning signs, lighting system against traffic accidents as well as other risk to

people and sensitive areas.

If previous assessments indicate there could be unexploded ordnance (UXO),

clearance must be done by qualified personnel and as per detailed plans approved

by the Construction Engineer.

Decree No.

22/2010/TT-BXD on

regulation of

construction safety

Instruction No. 02

/2008/CT-BXD on

safety and sanitation

issues in construction

agencies

TCVN 5308-91:

Technical regulation

on safety in

construction

Decision No.

96/2008/QD-TTg on

clearance of UXO.

Page 178: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

171

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

15. Communication with

local communities Maintain open communications with the local government and concerned

communities; the contractor shall coordinate with local authorities (leaders of

local wards or communes, leader of villages) for agreed schedules of construction

activities at areas nearby sensitive places or at sensitive times (e.g., religious

festival days).

Copies in Vietnamese of these ECOPs and of other relevant environmental

safeguard documents shall be made available to local communities and to

workers at the site.

Reduced playground space, loss of playing fields and car parking: The loss of

amenities during the construction process is often an unavoidable source of

inconvenience to users in sensitive areas. However, early consultation with those

affected, provides the opportunity to investigate and implement alternatives.

Disseminate project information to affected parties (for example local authority,

enterprises and affected households, etc) through community meetings before

construction commencement;

Provide a community relations contact from whom interested parties can receive

information on site activities, project status and project implementation results;

Provide all information, especially technical findings, in a language that is

understandable to the general public and in a form of useful to interested citizens

and elected officials through the preparation of fact sheets and news release,

when major findings become available during project phase;

Monitor community concerns and information requirements as the project

progresses;

Decree No.

73/2010/ND-CP on

administrative

penalization security

and society issues

Page 179: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

172

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

Respond to telephone inquiries and written correspondence in a timely and

accurate manner;

Inform local residents about construction and work schedules, interruption of

services, traffic detour routes and provisional bus routes, blasting and demolition,

as appropriate;

Provide technical documents and drawings to PC‘s community, especially a

sketch of the construction area and the EMP of the construction site;

Notification boards shall be erected at all construction sites providing

information about the project, as well as contact information about the site

managers, environmental staff, health and safety staff, telephone numbers and

other contact information so that any affected people can have the channel to

voice their concerns and suggestions.

Page 180: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

173

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

16. Chance find

procedures

If the Contractor discovers archeological sites, historical sites, remains and objects,

including graveyards and/or individual graves during excavation or construction, the

Contractor shall:

Stop the construction activities in the area of the chance find;

Delineate the discovered site or area;

Secure the site to prevent any damage or loss of removable objects. In cases of

removable antiquities or sensitive remains, a night guard shall be arranged until

the responsible local authorities or the Department of Culture and Information

takes over;

Notify the Construction Supervision Consultant who in turn will notify

responsible local or national authorities in charge of the Cultural Property of

Viet Nam (within 24 hours or less);

Relevant local or national authorities would be in charge of protecting and

preserving the site before deciding on subsequent appropriate procedures. This

would require a preliminary evaluation of the findings to be performed. The

significance and importance of the findings should be assessed according to the

various criteria relevant to cultural heritage; those include the aesthetic, historic,

scientific or research, social and economic values;

Decisions on how to handle the finding shall be taken by the responsible

authorities. This could include changes in the layout (such as when finding an

irremovable remain of cultural or archeological importance) conservation,

preservation, restoration and salvage;

If the cultural sites and/or relics are of high value and site preservation is

Law on Cultural

Heritage (2002)

Law on Cultural

Heritage (2009) for

supplementary and

reformation

Decree No.

98/2010/ND-CP for

supplementary and

reformation

Page 181: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

174

ENVIRONMENTAL –

SOCIAL ISSUES

MITIGATION MEASURE

VIETNAM

CODE/REGULATION

recommended by the professionals and required by the cultural relics authority,

the Project‘s Owner will need to make necessary design changes to

accommodate the request and preserve the site;

Decisions concerning the management of the finding shall be communicated in

writing by relevant authorities;

Construction works could resume only after permission is granted from the

responsible local authorities concerning safeguard of the heritage.

Page 182: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

175

APPENDIX 2. LEGAL DOCUMENTS

Approval decision the EIA report of the Viet Names – German University construction project in 2011

Page 183: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

176

Page 184: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

177

Page 185: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

178

Page 186: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

179

(Translation)

APPENDIX 2. LEGAL DOCUMENTS

Approval decisions on the EIA report of the New Model University Project

BINH DUONG PROVINCIAL PEOPLE’S COMMITTEE

SOCIALIST REPUBLIC OF VIETNAM Independence – Freedom - Happiness

No. 2412/ QD-UBND

Binh Duong, 26th August, 2011

DECISION ON Approval of the Environmental Impact Assessment Report of New Model University

Project with a Scale of 50 hectares in the Industrial Zone and Thoi Hoa Residential Area, Thoi Hoa commune, Ben Cat district (under the Ministry of Education and Training)

CHAIRMAN OF BINH DUONG PROVINCIAL PEOPLE’S COMMITTEE

Pursuant to the Law on Organization of People’ Council and People’s Committee dated 26 November 2003;

Pursuant to the Law on Environmental Protection dated 29 November 2005;

Pursuant to the Decree No. 80/2006/ND-CP dated 09 August, 2006 of the GOV regulating details and guiding the implementation of number articles of the Law on Environmental Protection;

Pursuant to the Decree No.21/2008/ND-CP dated 28 February, 2008 of the GOV on amendment, supplementation of a number of articles of the No. 80/2006/ND-CP dated 09 August, 2006 of the GOV regulating details and guiding the implementation of a number articles of the Law on Environmental Protection;

Pursuant to the Decree No.29/2011/ND-CP dated 18 April, 2011 of the GOV stipulating the strategic environment assessment, environment impact assessment and environment protection commitment;

Pursuant to the Circular No. 05/2008/TT-BTNMT dated 08 December 2008 of the Ministry of Natural Resources and Environment guiding the strategic environment assessment, environment impact assessment and environment protection commitment;

At the proposal of the Director of the Department of Natural Resources and Environment at the Letter no. 352/TTr-STNMT dated 22 August, 2011.

DECIDES

Article 1. To approve the EIA report of Vietnamese German University Construction Project with a Scale of 50 hectares in the Industrial Zone and Thoi Hoa Residential Area, Thoi Hoa commune, Ben Cat district of Vietnamese German University (under the Ministry of Education and Training).

Article 2. Vietnamese German University is responsible for properly implementing contents of such mentioned report and mandatory requirements:

Construction of a separated rainwater and wastewater drainage system, wastewater shall be collected and treated in a way to meet the QCVN 14:2008/BTNMT, Column A(K=1) before being discharged into the C1 channel;

Exhaust gas shall be treated respecting the QCVN 19:2009/BTNMT and QCVN 20:2009/BTNMT;

Page 187: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

180

Noise, vibration must meet requirements of QCVN 26:2010/BTNMT, QCVN 27:2010/BTNMT and TCVS3733/2002/QD-BYT;

Solid waste shall be collected, managed and treated in accordance with regulations as stipulated at the Decree No.59/2007/ND-CP dated 09 April 2007 of the GOV on solid waste management;

Hazardous waste generator have to register and obtain the hazardous waste management licenses under the Circular No. 12/2011/TT-BTNMT dated 14 April, 2011 of the Ministry of Natural Resources and Environment; Organize monitoring, assessment current conditions of the environment, make report on environment every 3 months, and report the Department of Natural Resources and Environment for inspection; Install wastewater monitoring equipment in accordance with Article 30 and construct wastewater source points in accordance with technical requirements as provided for in Article 31 of the environmental protection regulations of Binh Duong province enclosed the Decision 68/2008-QD-UBND dated 12 December 2008 of Binh Duong PPC. Implement management measures and techniques to prevent and overcome incidents caused by fire, explosion, risks and other environmental incidents;

Strictly adhere to information and reporting regime on implementation of the contents of approved EIA report and requirements of this Decision at the Decree No.80/2006/ND-CP dated 09 Auguts, 2006 of the GOV detailing and guiding the implementation of a number articles of the Law on Environmental Protection and Circular No. 05/2008/TT-BTNMT dated 08 December 2008 of the Ministry of Natural Resources and Environment guiding the strategic environment assessment, environmental impact assessment and environmental protection commitment.

Article 3. The EIA report of the Project and mandatory requirements as stipulated in the Article 2 of this Decision are basis for the State Competent Authority to appraise, contraol the implementation of environment protection performed by the Project;

Article 4. During the implementation of the Project, Vietnamese German University is requested to report in a written document for any changes in the approved EIA report which shall be considered and approved by competent authorities. Vietnamese German University shall have to implement appropriately in accordance with such changes after being approved.

Article 5. Department of Natural Resources and Environment is authorized to monitor, inspect, and consider any adjustment, and confirm the implementation of environmental protection contents as presented in the approved EIA report and requirements as stated in Article 2 and Article 4 of this Decision.

Article 6. Secretarial of the PPC office, Director of the Department of Natural Resources and Environment, Chairman of Ben Cat DPC, Vietnamese German University and heads of related authorizes are responsible for implementing this Decision from the signing date.

Recipients: - MONRE; - Chairman and Vice Chairmen - DONRE, DOC; - Ben Cat DPC - Project owner;

FOR THE CHAIRMAN THE DEPUTY CHAIRMAN

(signed and sealed)

Tran Van Nam

Page 188: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

181

Approval decision the detail plan of the New Model University Project, 2014

Page 189: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

182

Page 190: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

183

Page 191: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

184

Page 192: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

185

Page 193: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

186

Page 194: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

187

Page 195: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

188

Page 196: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

189

Page 197: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

190

Page 198: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

191

Page 199: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

192

BINH DUONG PROVINCIAL PEOPLE’S COMMITTEE

SOCIALIST REPUBLIC OF VIETNAM Independence – Freedom – Happiness

No. 1865/ QD-UBND

Binh Duong, 5th August, 2014

DECISION ON Approval of the Detailed Planning of Vietnamese German University located in Thoi Hoa

commune, Ben Cat district BINH DUONG PROVINCIAL PEOPLE’S COMMITTEE

Pursuant to the Law on Organization of People’ Council and People’s Committee dated 26 November 2003;

Pursuant to the Law on Urban Planning No. 30/2009/QH12 dated 17 June, 2009;

Pursuant to the Decree No. 37/2010/ND-CP dated 07 April, 2010 of the GOV on preparation, appraisal, approval and management of urban planning;

Pursuant to the Circular No. 10/2010/TT-BXD dated 11 August 2010 of the Ministry of Construction regulating documents of each type of urban planning;

At the proposal of the Director of the Department of Construction at the Letter No. 1403/TTr-SXD dated 29 July, 2014 on the approval of the detailed the Detailed Planning of Vietnamese German University located in Thoi Hoa commune, Ben Cat district.

DECIDES

Article 1. To approve the detailed the Detailed Planning of Vietnamese German University located in Thoi Hoa commune, Ben Cat district with the following contents:

1. Location, area, characteristics of the detailed planning area:

Location of the project is as follows:

+ Borders with: National Road No. 13 to the East

+ Borders with: D9 Road and Hamlet 5C Residential Area to the West

+ Borders with: existing residential area to the South

+ Borders with: Ring road No. 4 and Hamlet 3 Residential Area to the North.

Area: 505,004.8m2 (about 50.5 hectares);

Characteristics: Construction of a training and research university of regional and international standards. The University is equipped with facilities which meet requirements on learning, accommodating, and working of its employees, lectures and students.

2. Basic criteria on population, land, social infrastructure and technical infrastructure:

a) Population:

It is expected that number of students and lecturers are in the University, excluding nonresidents.

Page 200: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

193

To 2030: the number of students is expected to be 12.000,and the number of regular lecturers is expected to be 160 (equivalent to about 40-50 households).

b) Landing

Total natural land is about 50.5 hectares, in which land for construction of the University is 436,701.8 m2, the remaining land is used for construction of K1 channel and channel protection corridor of 38,412.2m2 and road safety corridor of NH 13 of 2,288.8m2.

Construction area of the whole university accounts for an appropriately 23% of total land area.

Land for construction of the University is 38.6m2/ student;

Land for dormitory and canteen: 7.1 m2/ student;

Land for construction of building for lecturers: 82.5m2/ person.

c) Social Infrastructure and technical Infrastructure

Social Infrastructure criteria: ensure the internal development, support and enhance the rapid development of surrounding areas; promote mutually beneficial relationship between academic organizations and surrounding residential areas.

Transport land use criteria (dynamic and static): about 2.8m2/ student.

Criteria for ground leveling and rainwater drainage: The design is changed from 4.5m at the Northwest to 8.0m at Southeast. Slope of the foundation is designed to be within the minimum slop of 0.5& and the maximum of 5%.

Criteria for electricity supply: Houses for lecturers and guest houses: 80W/m2 in use, dormitory: 25W/m2 in use, public works: 20-100W/m2 in use.

Criteria for water supply: Houses for lecturers and guest houses: 200l/c/d, dormitory: 120l/c/d, lecture hall: 20l/c/d, visitors and those who attend lectures 6l/c/d, canteen and sport area: 25l/c/d, watering and road cleaning: 1l/m2/d; grass watering: 3l/m2/d; supporting area: 5l/m2/d; landscaping: 17.8l/m2/d;

Criteria for sewerage: Wastewater flow is equivalent to 80% of total amount of domestic water supplied. Maximum use coefficient a day is 1.3 under TCXDVN33-2006. Loss due to leakage is assumed to be 10% of generated wastewater amount.

Criteria for solid waste: Average solid waste in the area is 0.8 – 1kg/person/ day, in academic area: 0.3 – 0.5 kg/person/day. Rate of collected waste is 90-100%. Organic waste is collected each day and inorganic waste is collected every 2-3 times/ a week.

3. Land use structure:

a) Land use structure cover the following functional areas:

Administration, academic and public areas: include Scientific exhibition area, administration building, hall, library, lecture hall, foundation year building, academic clusters, entry court, roofed walkway.

Dormitories and canteen.

Houses for lecturers and guest houses

Sport area: includes roofed sport hall, swimming pool and stadium, roofed walkway

Page 201: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

194

Green tree area, yards

Road and technical infrastructure: consists of two bridges crossing K1 channel, internal road, electromechanical works, WWTP, water tower, etc.

In addition, there area land for channel and protection corridor of k1 channel and protection corridor of NH13.

No. Types Area (m2) Percentage (%)

I Land for construction of University 463,701.8 91.8

1 Administration, academic and public areas

111,844.3 24.1

2 Dormitories and canteen 85,276.3 18.4

3 Houses for lecturers and guest houses

13,202.5 2.8

4 Sport area 19,899.7 4.3

5 Green tree area, yards 192,495.9 41.5

6 Road and technical infrastructure 40,938.2 8.8

II Land for channel and protection corridor of k1 channel

38,414.2 7.6

III Land for protection corridor of NH13

2,888.3 0.6

Total land 5000,004.8 100.0

4. Criteria for urban planning land use, spatial organization solution,

architecture, urban design or each plot of land:

a. Criteria for urban planning land use

* Planning criteria for the whole area:

- Use of construction land: 38.63m2/person;

- Total construction land in use: 105,603.50m2

- Construction density: 22.77%

- Land use coefficient: 0.8

- Largest number of floors: 9 floors

- Number of parking spaces: 960 for cars, 2,900 for motorbikes

* Criteria for design of functional building areas are shown as follows:

Page 202: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

195

No. Functional areas Phase Total for construction land area (m2)

Construction density (%)

Number of floors

Height (m)

AL Administration, academic and public areas park

1.1+1.2

Scientific Exhibition Area 1 4,172

0.90 2 11

2.1 Administration building 1 4,865 1.05 7-8 37

2.7 Hall 1 2,733 0.59 3 22

2.16.1 Library in Phase 1 1 2,802 0.60 7 27

2.16.2 Library in Phase 2 2 1,864 0.40 7 27

2.15.1 Lecture Hall on Phase 1 1 3,442 0.74 8 37

2.15.2 Lecture Hall on Phase 2 2 4,317 0.93 8 37

2.4 Foundation Year Building 1 2,190 0.47 5-7 35

2.8 Academic Cluster I 1 1,461 0.32 5-7 35

2.9 Academic Cluster II 1

1,743 0.38 5-7 35

2.10 Academic Cluster III 1 2,029 0.44 5-7 35

2.12 Academic Cluster V 1 1,770 0.38 5-7 35

2.11+2.13

Academic Cluster VI 2 1,983

0.43 5-7 35

2.14 Academic Cluster VII 1 2,421 0.52 5-7 35

X.1 Academic Cluster VIII 2 2,272 0.49 5-7 35

X.2 Academic building Group IX 2 1,822 0.39 5-7 35

Z1 Entry Court 1 506 0.11 20

Z.2.1 Roof of walkway crossing administration building, academic buildings and CC

1-2 5,229 1.13 5

DL Dormitories and canteen

3.1.1 Canteen in Phase 1 1 1,698 0.37 4 18

3.1.2 Canteen in Phase 2 2 2,000 0.43 5 22

4.1.1 Dormitory 1 1 2,825 0.61 9 34

4.1.2 Dormitory 2 1 2,872 0.62 9 34

4.1.3 Dormitory 3 1 2,777 0.64 9 34

5.1.4 Dormitory 4 2 2,974 0.61 7-9 34

4.1.5 Dormitory 5 2 2,821 0.61

4.1.6 Dormitory 6 2 2,974 0.64

4.1.7 Dormitory 7 2 2,952 0.59

4.1.8 Dormitory 8 2 1,842 0.38

4.1.9 Dormitory 9 1 1,982 0.43

4.1.10 Dormitory 10 2 2,033 0.44

4.1.11 Dormitory 11 2 2,590 0.56

4.1.12 Dormitory 12 2 2,778 0.60

4.2 Community House 2 729 0.16 1-2 10

Z.2.2 Roof for walkway through dormitory area

1 1,560

0.34 1 5

HL House for lecturers and Guest House

Page 203: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

196

No. Functional areas Phase Total for construction land area (m2)

Construction density (%)

Number of floors

Height (m)

5.1 House for lecturers (single village)

1 2,350

0.51 1-2 8

5.2 House for lecturers (double villa)

1 1,410

0.30 1-2 8

5.3 Guest house 1 (multi-family house)

1 609

0.13 2-3 10

5.3 Guest house 2 (multi-family house)

1 492

0.11 2-3 10

5.4 Community House 1 377 0.08 1-2 8

SL Sport area

3.3 Roofed sport hall 1 4.531 1.11 2-4 14-15

Roof of walkway 1 652 1 5

Swimming pool 1 2,537 0.55 0

Outdoor Sport Yard 1-2 0.00 0

IL Technical Infrastructure area

A.1 Electromechanical technical infrastructure works and WWTP

1-2 5.200 1.12 1-3 10-15

A2+A3

Water tower and water tower equipment

1-2 900 0.19 1-2 45

Other buildings

Z3 Bridges for pedestrians 1 560 0.12

Z4R Bridges for pedestrians 1 447 0.10

Roof for walkway crossing road and landscaping area

1-2 829 0.18

b) Spatial, architecture and urban design organization solutions

* Design of open space

Utilize outdoor space, resting space and sport areas in which weather conditions are taken into consideration. The design should reflect the combination of square, green space and supporting spaces with purpose of creating an attractive ecological environment for everybody to learn, work and live here as well as to residents surrounding.

Utilize landscaping of K1 channel which is incorporated into design solutions;

* Phasing

After the completion of Phase 1, a separate space for Phase 2 will be used temporarily without being dependent as a design solution.

Plant summer trees which are suitable with requirements on security.

* Urban Planning

Page 204: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

197

Open space and setback space of works: determine height of works and construction density in order to ensure the utilization of light, air and make most use of wind ventilation.

Establish strategies to enhance the continuous connection of ground floor plan among buildings and various locations in the project areas.

Study the open space and cover materials to create a roofed outdoor areas which are connected to buildings.

Optimize sustainable design originated from planning solutions to solve issues related to energy, water and temperature inversion effects.

Eliminate contacts with the sun and heat increase related to buildings and outdoor space;

* Detailed urban design for each area

Criteria on urban planning, social and technical infrastructure for spaces of the University area under the Project’s objectives and Vietnamese standards will be determined in the Master Plan.

Planning maps shall present adequate planning specifications as in accordance with regulations.

5. Supply sources and solutions for organization of technical infrastructure network in each plot of land

a) Transport system

Walkways, roads for vehicles, and entry roads shall be designed in a way to facilitate the safety connection to works and transport/ external transport systems in accordance with regulations of Vietnamese standards and international standards of the Sector.

Construct two bridges crossing K1 channel in order to create a connection to the University’s campus.

Total outdoor and indoor parking lots is expected to be 960 lots for cars, 2.900 for motorbikes, accounting for 21,075m2 in total.

The following table presents detailed transport system:

Code Name of roads Right of way (m) Length (m)

External transport

NH NO. 13 62 280

Ring road No.4 7,25+4,5+4,25+24+4,5+7,25=62 890

Road D9 4+12+4 = 20 740

Internal road

H1 Road H1 8 310

H1a Road H1a 5 83

H1r Turning of H1 8-12 304

H1b Supporting road 5 270

Page 205: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

198

H1b

H2 Road H2 5 370,5

H2a Road H2a 5 192

H2b Road H2b 5 192

H3 Road H3 7 574,5

H4a Supporting road H4a

5 302

H4b Supporting road H4b

5 164

H5 Road H5 1+5+2,5=8,5 349

H6 Road H6 3,5+7=10,5; 4+1+4=9 336

V1 Road V1 5 396,5

V1a Supporting road V1a

5 325

V1b Supporting road V1b

5 122

V2 Road V2 5 227,5

V3 Road V3 5-8,5 348,5

V4 Road V4 7;2+7+1=10 82

Z3 Z3 bridge for pedestrians

10 51

Z4 Z4 bridge for pedestrians

5,5 76

Z.2.3 Roof for pedestrians

4 120

b) Leveling and rainwater drainage system

The design of leveling elevation is changed from 4.5m at the Northwest to 8.0m at Southeast. Slope of the foundation is designed to be within the minimum slop of 0.5& and the maximum of 5%. Amount of Excavated soil is 58,663m3; amount of backfilling soil is 78,689m3.

Rainwater in the campus shall be collected through leaching pits and water receiving pits. All internal roads in the project shall be served by the rainwater drainage system. Rainwater is collected by gravity or pressure pipes and discharged to rainwater regulatory tank and rainwater treatment system.

Maximum distance between two holes is 60m, and slope along road is 0.03.

Rainwater discharge points are connected directly to K1 channel in the North and South areas.

Page 206: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

199

c) Water supply system

Ensure the water supply flow to be in accordance with criteria as set.

Water supply for firefighting: Ensure to supply water for 2 concurrent fires with the outdoor firefighting flow of 15l/s during 3 hours and automatic firefighting water supply of 9.5l/s during 0.5 hour and 5l/s during 3 hours for Indoor hose-reel fire fighting system (total indoor firefighting water amount is 29.2l/s)

Largest water-use coefficient is 1.3. Amount of water leaked out is about 10% of total domestic water.

Water resources: Domestic water is divided into 2 types, namely portable water and non- portable water.

Portable water: it is expected that it will be connected to the existing main water supply pipeline of D400 (inner diameter of 400mm) along K1 channel to the South.

Non - portable water: is supplied from water treatment system for re-use purposes.

Total water demand: Average: Portable water: 1,850 m3/day; and non-portable water: 2,050 m3/day; Largest demand: Portable water: 2,410m3/day; and non-portable water: 2,670 m3/day

Water supply pipeline shall be installed under the pavement (walkway) at the depth of from 0.7 to 1m. Water shall be distributed through a ring system in various flows into a number of directions and to prevent from being obstructed inside pipelines. Diameter of the main water pipeline is 200mm, and of branch pipeline is 25-100mm.

Water for firefighting is supplied from treated water pipeline. Diameter of the main water pipeline is 200mm, and of branch pipeline is 32-100mm. Inside the main water network, fire hydrants of D100 shall be installed with a distance of no more than 150m between each other.

d) Electricity supply system

Total power load is expected to be at 11,615KW.

Power source: the primary power source of the project is the 22 KV national grid electricity - is at the east of the work and is located on the NH 13 – from 110KV Ben Cat substation. The emergency power source of the project is the existing 22 KV national grid electricity at the North of the work.

In the future, construct a new line and medium voltage branch of 22KV from the NH 13 to the main medium voltage cutout box of the planning area and agree on the main points connected to the 22KVgrid.

Solutions for power supply includes:

+ Provide a medium voltage supply of 22kV, low voltage of 0.4kV for daily activities, and low voltage for lighting. Power supply cable are placed underground at the minimum of depth of 0.8m, cable under and crossing roads must be inserted into pressure plastic pipe at the depth of 1m. Lighting cables are installed underground at the depth of 0.5m.

Page 207: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

200

+ Substation: Total low voltage capacity for work items and road lighting for entire project is expected to be at 11,615kW. Low voltage substation of 22/0.4kV for entire project is the outdoor type or indoor type including readily installed RMU to connect to the ring circuit.

e) Communication system

Distribution network: copper cable and fiber cable lines placed underground (pipeline and manholes) shall be constructed from center substations to work items in the planning area. Cables are inserted inside PVC pipes and placed underground at the depth of 0.8m at least. Depth of cables placed underground and crossing roads shall be at least 1m.

g) Sewerage system and wastewater and solid waste treatment system

Wastewater flow is equivalent to 80% of total of domestic water supply sources. Maximum water-use coefficient is 1.3. The water leakage is about 10% of wastewater generated. Total wastewater treated in the centralized wastewater treatment plant: 3,200m3/day at average and 4,000 m3/day at maximum.

Sewerage system is designed to be consistent with the project’s characteristics. Road-bed and pavement do not have steps but it is sloping, therefore, sewers are not only located under the road-bed but also under walkways and construction boundary of works in order to ensure the thorough collection of wastewater.

Gravity pipes and pressure pipes are both used in the sewerage system to collect total amount of wastewater from construction activities. Wastewater of most of wastewater collection systems will flow by gravity, however, plants will better meet requirements of buildings in the North.

Pipe burial depth under the pavements (walkways) is 0.4 at least, width of carriage way is at least 0.7m.

Solid waste: Average waste generated from dormitories is 1kg/person/day, from academic cluster is 0.3-0.5kg/person/day. Rate of collected waste is 90-100%. Organic waste is collected each day and inorganic waste is collected every 2-3 times/ a week.

Domestic organic and inorganic waste generated per day is 17,690m2 and 4,423m3 respectively. Waste should be classified into organic, inorganic and hazardous types. Waste collection points should be arranged at the site.

6. Environmental protection solutions

The Project assesses the strategic environment for specific impacts as follows:

- Impacts to socioeconomic environment;

- Impacts to Ecological environment;

- These impacts are analyzed in three stages: pre-construction, construction and operation.

- The Planning also proposes suitable solution to minimize these impacts.

7. Items to be given priority for investment and resources

The following work items are given priority for investment:

Page 208: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

201

- Academic clusters which need to be ensure a studying space for about 5,000 students in Phase 1;

- Dormitories in Phase 1 which is the accommodation for at least 2,500 students;

- Administration building ensures working space for lecturers and management staff

- Canteen in Phase 1

- Technical infrastructure system meets the requirements on operation of the University in Phase 1;

- Public spaces, sport areas, landscaping in Phase 1 and a number of other public functional works.

Resources for implementation:

- The Employer is the Vietnamese German University PMU under the Ministry of Education and Training will hire specialized units who will perform tasks related to the investment organization and construction of the Project’s work items to ensure that the Project shall be implemented in accordance with the progress and quality as stated in the approved tasks.

- The Project is under the state budget granting regime in the form of ODA loan financed by the World Bank.

8. List of construction works in planning areas:

Works are constructed in two Phases as shown and detailed in Section 4.

9. List of project documents:

a) Report

b) Parts of Drawings are as follows:

- Location and scope of land, a scale of 1/5,000;

- Current landscaping architecture and construction land assessment, scale of 1/500;

- Map of current technical infrastructure system, scale of 1/500;

- Land Use Master Plan, scale of 1/500;

- Spatial, architecture and landscaping map

- Redline, construction boundary and protection corridors of infrastructure lines, scale of 1/500;

- Infrastructure and environment system planning, scale of 1/500;

- Synthesis of lines, technical pipelines, scale of 1/500;

- Strategic Environmental Assessment, scale of 1/500;

Article 2: As the Employer, Vietnamese German University PMU under the Ministry of Education and Training is responsible for the following tasks:

Page 209: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

202

Solely be responsible for the accuracy of technical infrastructure positioning which are shown in drawings and prepared by the Consultant to ensure the synchronous connection to technical infrastructure systems of surrounding construction projects;

The technical infrastructure shall be invested and constructed in a way that it will be synchronous with surrounding infrastructure systems and suitable with the project’s progress, assure required leveling and drainage and sewerage system. The plan backfilling and construction does not affect negatively surrounding residential areas.

Organize the work quality management system and be responsible for the work quality of the Project as in accordance with regulations on construction work quality management.

Comply with regulations on environmental protection;

Make agreement on firefighting;

Announce detailed planning and implement in accordance with approved planning design.

Article 3. Secretarial of the PPC office, Directors of the Departments of: Planning and Investment, Finance, Construction, Natural Resources and Environment, Education – Training; Chairman of Ben Cat TPC, Vietnamese German University and heads of related authorizes are responsible for implementing this Decision from the signing date.

Recipients: - MOET; - Chairman and Vice Chairmen - As mentioned in Article 3; - LDVP,Km,TH; - Office filing

FOR THE CHAIRMAN THE STANDING DEPUTY CHAIRMAN

(signed and sealed)

Tran Van Nam

Page 210: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

203

APPENDIX 3. BASELINE ENVIRONMENTAL MONITORING MAP

Page 211: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

204

Page 212: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

205

Page 213: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

206

Page 214: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

207

Page 215: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

208

APPENDIX 4. ENVIRONMENTAL MONITORING MAP IN CONSTRUCTION

STAGE

Page 216: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

209

Page 217: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

210

APPENDIX 5. ENVIRONMENTAL MONITORING MAP IN OPERATION STAGE

Page 218: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

211

Page 219: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

212

APPENDIX 6. BASELINE ENVIRONMENTAL ANALYSIS RESULTS

Page 220: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

213

Page 221: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

214

RESULTS GEODESIC, ANALYSIS AIR Name request LacViet Investment, Environment and

Infrastructure Engineering., JSC

Code samples 150423001_KK01-05

Sampling sites New Model University Project Date of sampling 23/04/2015

Address Thoi Hoa, Ben Cat, Binh Duong Date analysis 23/04/2015

The sampling Ta Tien Lap, Dinh Quang Trieu, Tran Cao Tri Date returning results 04/05/2015

Conditions

sampling

Sunny, light wind Issuance 01

Sampling

Location:

KK01: head road VD4 intersect with Highway 13 (X = 1228914, Y = 594597 according coordinates VN2000) 7h

KK02: head road VD4 intersect with D9 (X = 1228619, Y = 593818 according coordinates VN2000) 7h

KK03: Residential end road D9 (X = 1228032, Y = 594067 according coordinates VN2000) 7h

KK04: Southern Residential Project, located between KK01 and KK05 (X = 1228124, Y = 594357 according coordinates

VN2000) 7h

KK05: Highway 13 near residential (X = 1228707, Y = 594731 according coordinates VN2000) 7h

No. Parameter Unit Result QCVN

26:2010/

BTNMT

QCVN

05:2013/

BTNMT

QCVN

27:2010/

BTNMT

Analysis method KK01 KK02 KK03 KK04 KK05

1 The temperature oC 31,5 32,6 32,8 32,9 32,4 - - - QCVN 46:2012/BTNMT

2 Humidity % 64,6 56,3 58,6 57,3 63,2 - - - QCVN 46:2012/BTNMT

3 Wind speed m/s 1,3 0,2 0,9 0,7 1,4 - - - QCVN 46:2012/BTNMT

4 Wind direction - Southwest - - -

- The results are only valid on the specimen/At the time of measurement unless otherwise noted;

- Sampling name, Name request is recorded as required by the customer;

- Save results: no save

- Not to criticize stars partial vote results without the written consent of the Investment Corporation Development

Environment Dai Viet company.

MS: BM.04.66

LBH: 01

NBH: 28/05/2012

Page: 1/2

Page 222: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

215

Page 223: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

216

No. Parameter Unit Result QCVN

26:2010/

BTNMT

QCVN

05:2013/

BTNMT

QCVN

27:2010/

BTNMT

Analysis method KK01 KK02 KK03 KK04 KK05

5 Noise bBA 65,5 53,5 55,2 53,6 65,3 70 - - TCVN 7878-2 : 2010

6 Total suspended

dust

mg/m3

0,20 0,15 0,16 0,12 0,19 - 0,3 - TCVN 5067 : 1995

7 NO2 mg/m3 0,067 0,070 0,081 0,068 0,070 - 0,2 - TCVN 6137 : 2009

8 SO2 mg/m3 0,079 0,062 0,070 0,059 0,086 - 0,35 - TCVN 5971 : 1995

9 CO mg/m3 5,21 5,28 5,37 5,10 5,37 - 30 - HD.TN.04

10 Vibration dB 46 59 51 56 65 - - 75 TCVN 6963 :2001

Note:

- Laboratory of the Investment Corporation Development Environment Dai Viet company has been recognized by Decision No. 578/QĐ-

BTNMT date 19/3/2015 code VIMCER TS 066.

- (*) Parameter has been recognized by VILAS

- The method of using subcontractors

- QCVN 26 : 2010/BTNMT: National technical regulations on noise

- QCVN 06 : 2013/BTNMT: National technical regulations on ambient air quality

- QCVN 27: 2010/BTNMT: National technical regulations on vibration.

Page 224: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

217

Page 225: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

218

RESULTS GEODESIC, ANALYSIS AIR Name request LacViet Investment, Environment and

Infrastructure Engineering., JSC

Code samples 150423001_KK06-10

Sampling sites New Model University Project Date of sampling 23/04/2015

Address Thoi Hoa, Ben Cat, Binh Duong Date analysis 23/04/2015

The sampling Ta Tien Lap, Dinh Quang Trieu, Tran Cao Tri Date returning results 04/05/2015

Conditions

sampling

Sunny, light wind Issuance 01

Sampling

Location:

KK06: head road VD4 intersect with Highway 13 (X = 1228914, Y = 594597 according coordinates VN2000) 11h

KK07: head road VD4 intersect with D9 (X = 1228619, Y = 593818 according coordinates VN2000) 11h

KK08: Residential end road D9 (X = 1228032, Y = 594067 according coordinates VN2000) 11h

KK09: Southern Residential Project, located between KK06 and KK10 (X = 1228124, Y = 594357 according coordinates

VN2000) 11h

KK10: Highway 13 near residential (X = 1228707, Y = 594731 according coordinates VN2000) 11h

No. Parameter Unit Result QCVN

26:2010/

BTNMT

QCVN

05:2013/

BTNMT

QCVN

27:2010/

BTNMT

Analysis method KK06 KK07 KK08 KK09 KK10

1 The temperature oC 35,6 34,7 34,0 32,6 34,1 - - - QCVN 46:2012/BTNMT

2 Humidity % 62,8 59,3 61,7 59,4 61,0 - - - QCVN 46:2012/BTNMT

3 Wind speed m/s 1,0 0,4 0,5 0,2 1,0 - - - QCVN 46:2012/BTNMT

4 Wind direction - Southwest - - - QCVN 46:2012/BTNMT

- The results are only valid on the specimen/At the time of measurement unless otherwise noted;

- Sampling name, Name request is recorded as required by the customer;

- Save results: no save

- Not to criticize stars partial vote results without the written consent of the Investment Corporation Development

Environment Dai Viet company.

MS: BM.04.06

LBH: 01

NBH: 28/05/2012

Page: 1/2

Page 226: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

219

Page 227: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

220

No. Parameter Unit Result QCVN

26:2010/

BTNMT

QCVN

05:2013/

BTNMT

QCVN

27:2010/

BTNMT

Analysis method KK06 KK07 KK08 KK09 KK10

5 Noise bBA 60,5 56,7 52,4 55,8 63,7 70 - - TCVN 7878-2 : 2010

6 Total suspended

dust

mg/m3

0,22 0,17 0,15 0,13 0,18 - 0,3 - TCVN 5067 : 1995

7 NO2 mg/m3 0,071 0,077 0,077 0,071 0,079 - 0,2 - TCVN 6137 : 2009

8 SO2 mg/m3 0,083 0,072 0,083 0,067 0,082 - 0,35 - TCVN 5971 : 1995

9 CO mg/m3 5,34 5,38 5,43 5,17 5,45 - 30 - HD.TN.04

10 Vibration dB 51 64 53 50 62 - - 75 TCVN 6963 :2001

Note:

- Laboratory of the Investment Corporation Development Environment Dai Viet company has been recognized by Decision No. 578/QĐ-

BTNMT date 19/3/2015 code VIMCER TS 066.

- (*) Parameter has been recognized by VILAS

- The method of using subcontractors

- QCVN 26 : 2010/BTNMT: National technical regulations on noise

- QCVN 06 : 2013/BTNMT: National technical regulations on ambient air quality

- QCVN 27: 2010/BTNMT: National technical regulations on vibration.

Page 228: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

221

Page 229: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

222

RESULTS GEODESIC, ANALYSIS AIR Name request LacViet Investment, Environment and

Infrastructure Engineering., JSC

Code samples 150423001_KK11-15

Sampling sites New Model University Project Date of sampling 23/04/2015

Address Thoi Hoa, Ben Cat, Binh Duong Date analysis 23/04/2015

The sampling Ta Tien Lap, Dinh Quang Trieu, Tran Cao Tri Date returning results 04/05/2015

Conditions

sampling

Sunny, light wind Issuance 01

Sampling

Location:

KK11: head road VD4 intersect with Highway 13 (X = 1228914, Y = 594597 according coordinates VN2000) 16h

KK12: head road VD4 intersect with D9 (X = 1228619, Y = 593818 according coordinates VN2000) 16h

KK13: Residential end road D9 (X = 1228032, Y = 594067 according coordinates VN2000) 16h

KK14: Southern Residential Project, located between KK06 and KK10 (X = 1228124, Y = 594357 according coordinates

VN2000) 16h

KK15: Highway 13 near residential (X = 1228707, Y = 594731 according coordinates VN2000) 16h

No. Parameter Unit Result QCVN

26:2010/

BTNMT

QCVN

05:2013/

BTNMT

QCVN

27:2010/

BTNMT

Analysis method KK11 KK12 KK13 KK14 KK15

1 The temperature oC 32,4 31,3 32,0 31,1 31,9 - - - QCVN 46:2012/BTNMT

2 Humidity % 61,2 62,3 57,4 60,5 62,1 - - - QCVN 46:2012/BTNMT

3 Wind speed m/s 0,7 0,6 1,2 0,4 1,0 - - - QCVN 46:2012/BTNMT

4 Wind direction - Southwest - - - QCVN 46:2012/BTNMT

- The results are only valid on the specimen/At the time of measurement unless otherwise noted;

- Sampling name, Name request is recorded as required by the customer;

- Save results: no save

- Not to criticize stars partial vote results without the written consent of the Investment Corporation Development

Environment Dai Viet company.

MS: BM.04.06

LBH: 01

NBH: 28/05/2012

Page: 1/2

Page 230: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

223

Page 231: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

224

No. Parameter Unit Result QCVN

26:2010/

BTNMT

QCVN

05:2013/

BTNMT

QCVN

27:2010/

BTNMT

Analysis method KK11 KK12 KK13 KK14 KK15

5 Noise bBA 63,2 61,7 60,8 50,6 66,2 70 - - TCVN 7878-2 : 2010

6 Total suspended

dust

mg/m3

0,18 0,14 0,18 0,14 0,20 - 0,3 - TCVN 5067 : 1995

7 NO2 mg/m3 0,071 0,072 0,076 0,073 0,072 - 0,2 - TCVN 6137 : 2009

8 SO2 mg/m3 0,080 0,083 0,083 0,067 0,081 - 0,35 - TCVN 5971 : 1995

9 CO mg/m3 5,37 5,30 5,27 5,24 5,30 - 30 - HD.TN.04

10 Vibration dB 51 52 55 53 62 - - 75 TCVN 6963 :2001

Note:

- Laboratory of the Investment Corporation Development Environment Dai Viet company has been recognized by Decision No. 578/QĐ-

BTNMT date 19/3/2015 code VIMCER TS 066.

- (*) Parameter has been recognized by VILAS

- The method of using subcontractors

- QCVN 26 : 2010/BTNMT: National technical regulations on noise

- QCVN 06 : 2013/BTNMT: National technical regulations on ambient air quality

- QCVN 27: 2010/BTNMT: National technical regulations on vibration.

Page 232: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

225

Page 233: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

226

RESULTS OF UNDERGROUND WATER QUALITY ANALYSIS Name of the Project: New Model University Project

Name of sample: Underground water sample

Date of Sampling: 24th

April, 2015

No. Name of Criteria Analysis method Unit Results

QCVN 09:2008/BTNMT Resource 1 Resource 2 Resource 3 Resource 4 Resource 5

1. Temperature SMEWW 2550-B 0C 27.7 28.1 27.6 27.5 28 –

2. pH TCVN 6492:99 - 5.69 6.02 6.15 6.24 6.56 5.5 – 8.5

3. Entire hardness TCVN 6224:96 mg/l CaCO3 205 210 212 200 205 500

4. NH4+ TCVN 6179-1:96 mg/l 0.028 0.023 0.025 0.023 0.024 0,1

5. NO3-

TCVN 6180:96 mg/l 0.5 0.5 0.3 0.3 0.5 15

6. Fe TCVN 6177:96 mg/l 0.05 0.05 0.03 0.04 0.03 5

7. Coliforms TCVN 6187-1,2:96 MNP/100m

l 0 0 0 0 0 3

Sampling position:

Resource 1: (X = 1228033, Y = 594260), at 14h20, located within Ngu Sac Printing and Design Company (323, Group 10, Street 4, Thoi Hoa ward,

Ben Cat town, Binh Duong)

Resource 2: (X = 1227984, Y = 594192), at15h00, underground water located in the house of Mrs. Nguyen Thi Thanh Nga household (Group 10B,

Street area 4, Thoi Hoa ward, Ben Cat town, Binh Duong)

Resource 3: (X = 1228006, Y = 593896), at 15h20, underground water located in the house of Mr. Truong Van Ly household (365 Group 10, Street

area 4, Thoi Hoa ward, Ben Cat town, Binh Duong)

Resource 4: (X = 1228334, Y = 593827, according to the Coordinate VN 2000), at 15:30, in Dinh Thoi Hoa (Ben Cat town, Binh Duong)

Resource 5: (X = 1228610, Y =593803), at 15:40, located in the house of Mr. Vinh household (in the area of Road DV4 crossing D9)

APPROVED BY LABORATORY’S

REPRESENTATIVE

ANALYSED BY

(Signed)

(Signed)

Nguyen Le Phu

(Signed)

Nguyen Hung Anh

Page 234: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

227

Page 235: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

228

RESULTS OF MUD/ SOIL QUALITY ANALYSIS Name of the Project: New Model University Project

Name of sample: Mud/ soil sample

Date of Sampling: 25th

April, 2015

No. Name of Criteria Analysis method Unit Results QCVN

03:2008/BTNMT Point 1 Point 2 Point 3 Point 4 Point 5

8. Zn TCVN 6496:2009 mg/kg 2.0 1.8 1.8 1.7 1.9 300

9. Cd TCVN 6496:2009 mg/kg 0.01 0.01 0.03 0.01 0.01 200

10. Cu TCVN 6496:2009 mg/kg 0.8 0.7 0.8 0.8 0.9 100

11. Pb TCVN 6496:2009 mg/kg 0.3 0.28 0.28 0.27 0.29 12

12. As

TCVN 8467:2010 mg/kg 0.015 0.013 0.012 0.012 0.011 5

Sampling position:

Point 1: (X = 1228757, Y = 594 061), mud on K1 channel, the bridge section across NH. 13, on the Project‗s area

Point 2: (X = 1228062, Y = 594 090), in the middle of the project area, depth of 30 cm

Point 3: (X = 1228062, Y = 594 090), in the middle of the project area, depth of 60 cm

Point 4: (X = 1228154, Y = 594 351, in the middle of the project area, depth of 30 cm

Point 5: (X = 1228154, Y = 594 351), in the middle of the project area, depth of 60 cm

APPROVED BY LABORATORY’S

REPRESENTATIVE

ANALYSED BY

(Signed)

Nguyen Le Phu

(Signed)

Nguyen Hung Anh

Page 236: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

229

Page 237: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

230

RESULTS OF SURFACE WATER QUALITY ANALYSIS Name of the Project: New Model University Project

Name of sample: Surface water sample

Date of Sampling: 23th

April, 2015

No. Name of Criteria Analysis method Unit Results QCVN 03:2008/BTNMT

Column 1 Plant 1 Plant 2 Plant 3 Plant 4 Plant 5

13. Temperature SMEWW 2550-B 0C 43.1 43.7 35.6 32.4 31.6 –

14. pH TCVN 6492:99 - 7.96 7.82 8.01 7.90 7.68 5.5 – 9

15. BOD5 TCVN 6001:95 mg/lO2 14.8 14.6 13.1 14.5 13.9 15

16. COD TCVN 6491:99 mg/lO2 29.5 29.1 28.9 23.5 21.5 30

17. TSS

SMEWW 2540D mg/l 43.8 43.1 40.5 42.7 40.3 50

18. NH4+ TCVN 6179-1:96 mg/l 0.05 0.05 0,11 0.26 0.1 0,5

19. NO3- TCVN 6180:96 mg/l 7.6 6.5 7.5 6.5 4.1 10

20. PO43-

TCVN 6202:96 mg/l 0.56 0.57 0.28 0.24 0,21 0.3

21. Coliforms TCVN 6187-1,2:96 MNP/100ml 1900 600 200 350 250 7500

Sampling position:

Plant 1: (X = 1228781, Y = 594633), 13h15, Channel K1, the bridge section across NH.13, within the Project‗s area

Plant 2: (X = 1228654, Y = 594171), 13h45, Channel K1, between NH 13 and Ring Road 4; 4

Plant 3: (X = 1228682, Y =594016), 14h05, Channel K1, under the bridge across Ring Road 4, within the Project‗s area

Plant 4: (X = 1228867, Y = 593884), 14h50, Channel K1, 400m far from the bridge across Ring Road 4 to the downstream

Plant 5: (X = 1228093, Y = 592276), 15h20, Thi Tinh river, under the bridge across Ring Road 4.

APPROVED BY LABORATORY’S

REPRESENTATIVE

ANALYSED BY

(signed)

(signed)

Nguyen Le Phu

(signed)

Nguyen Hung Anh

Page 238: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

231

APPENDIX 7. MINUTES OF PUBLIC CONSULTATION

Page 239: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

232

Page 240: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

233

MINISTRY OF EDUCATION AND

TRAINING

PMU OF NEW MODEL UNIVERSITY

PROJECT

SOCIALIST REPUBLIC OF VIETNAM

Independence – Freedom – Happiness

No. 65/CV-DADHVD

Subject: Request for consulting opinions in the

preparation of EIA report for the New Model

University Project

Hanoi, 20 April, 2015

Attn: Thoi Hoa ward People’s Committee

Currently, the PMU of the New Model University Project is preparing the environmental

impact assessment for the New Model University Project in accordance with the Law on

Environmental Protection and regulations on environmental impact assessment.

On the basis for implementation of the next steps, the PMU of the New Model University

Project would like to submit the summary of main investment items, environmental issues, and

environmental protection solutions of the Project and wish to receive your consulting opinions.

The PMU of the New Model University Project would highly appreciate for your kind

attention and strong cooperation in the coming time.

Recipients:

- As mentioned above;

- Director (to report)

- Basic Construction - Investment Dept(to

implement)

- Office filing

DEPUTY DIRECTOR

(Signed and sealed)

Ngo Toan Thang

Page 241: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

234

Page 242: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

235

Page 243: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

236

THOI HOA WARD PEOPLE’S

COMMITTEE

SOCIALIST REPUBLIC OF VIETNAM

Independence – Freedom – Happiness

No. 43/CV-UBND

Subject: Comments on the New Model

University Project

Hanoi, 24 April, 2015

Attn: PMU of the New Model University Project

We, Thoi Hoa Ward PC received the summary of main investment items, environmental

issues, and environmental protection solutions of the Project enclosed to your Letter No. 65/CV-

DADHVD dated 20 April, 2015 from the PMU of Vietnamese German University Construction

Project. After reviewing these mentioned documents, we have the following opinions:

1. Negative impacts of the Project to the Socio-economic situation and the

environment:

According to the Summary of the EIA Report of New Model University Project, total

construction area is about 50.5 hectares, and the project will be constructed within 24 months.

Therefore, the machines and transport vehicles used in the Project will create noise, increase

concentration of dust in the air, traffic accidents on transportation roads and project‘s

surrounding area during the construction period.

The concentration of about 650 construction workers will probably cause social and

security disorders, arise conflicts between workers and local people, as well as increase social

evils.

2. Environmental Impact Mitigation Measures of the Project

Vechiles transporting construction materials need to be covered tightly in order to

prevent materials from falling down on transport roads. Construction materials should be

gathered neatly inside construction sites which should be installed with shielding meshes.

Signboards and traffic signs should be arranged at entry and exit locations where are

intersections between the sites and NH 13 and Ring Road 4.

The cooperation with the local authority is highly encouraged in order to manage

construction workers at the sites well.

3. Recommendation to the Employer:

The Employer is requested to implement the environmental monitoring effectively as in

accordance with the EIA summary Report of the Vietnamese German University Construction

Project in construction and operation periods.

Additionally, the Employer is requested to promptly finalize the EIA Report of the

Project and carry out next steps for the early approval and implementation.

The above comments are made by Thoi Hoa WPC. The PMU of Vietnamese German

University Construction Project is requested to review and finalize the IEA report of the Project.

Recipients:

- As mentioned above;

- Chairman of Fatherland Front Committee

of the Ward;

- Chairman, Deputy Chairmen, WPC;

- Office filing

FOR THE CHAIRMAN

DEPUTY CHAIRMAN

(Signed and sealed)

Nguyen Thi Phi Long

Page 244: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

237

Page 245: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

238

Page 246: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

239

Page 247: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

240

MINUTE OF COMMUNITY CONSULTATION

Name of the meeting: Community Consultation for preparation of EIA Report of VGU

Project

Time: 08:00 Date: 23 April 2015

Location: Thoi Hoa WPC, Ben Cat town, Binh Duong province.

Participants:

1. Representatives of the Employer:

Mr/ Mrs.: Huynh Khanh Vu Position: Member

Mr/ Mrs.: ………………………………………… Position:

…………………………………………………..

2. Representatives of Thoi Hoa WPC:

Mr/ Mrs.: Nguyen Thi Phi Long Position: Deputy Chairman of Thoi Hoa

WPC

Mr/ Mrs.: Ho Van Sinh Position: Person in charge of Environment

3. Representatives of the Consultant:

Mrs.: Bui Thai Bach Duong Position: Environmental Specialist

Mr/ Mrs.: Ho Thi Huong Position: Environmental Specialist

4. Representatives of the Community

Mr/ Mrs.: Phan Van Chinh Position: Member

Mr/Mrs.:……………………………………Position:

Contents of the Meeting:

1. Introduce participants and purposes of the meeting: mobilize the enthusiastic

participation of the community in the design preparatory period and project

implementation period; get community opinions in the project preparation period.

2. Provide brief information about the Vietnamese German University Construction

Project (scale, plans, funds, implementation period);

3. Give summary impacts to the natural environment and society during the project

implementation.

4. Get community opinions in the project areas and feedback from the Employer and

Consultant.

Contents discussed in the meeting;

- The Project mostly bring about positive impacts such as: contribution to the increase of

education and higher education quality in Vietnam and in locality as well as in the region.

- The Project contributes to the socio-economic development in the locality, create jobs for

laborers in the locality, and enhance the economic development in which increase types of

services.

However, the Project will cause some impacts to the natural environment and society where the

Project is implemented:

- Construction machines, transport vehicles will create noise, increase concentration of dust in

the air on transportation roads and surrounding areas;

Page 248: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

241

- A large number of vehicles transporting construction materials will be mobilized for the

construction activities, which will increase the traffic density on NH 13 and ring road 4, and

high risk of traffic accidents.

- The concentration of construction workers will probably cause social and security disorders

in the locality, arise conflicts between workers and local people, as well as increase social

evils.

Therefore, the Employer is requested to strictly comply with environmental impact mitigation

measures as proposed in the EIA report as follows:

- Vehicles transporting construction materials need to be covered tightly in order to prevent

materials from falling down on transport roads. Construction materials should be gathered

neatly inside construction sites which should be installed with shielding meshes. Signboards

and traffic signs should be arranged at entry and exit locations where are intersections

between the sites and NH 13 and Ring Road 4.

- The cooperation with the local authority is highly encouraged in order to manage

construction workers at the sites well.

Conclusions: Thoi Hoa WPC and residential community in the project areas both support the project

implementation in the locality.

Thoi Hoa WPC kindly requests the PMU of VGU Construction Project to promptly finalize

the EIA Report of the project and implement next steps so that the Project will be approved

soon and implemented.

The meeting ended at 10:30 of the same date. The minute, after being read loudly in front of

participants, is agreed and signed by all stakeholders.

Representative of

the Employer

Representative of

the Consultant

(signed)

Ho Thi Huong

Representative of

WPC

(Signed and sealed)

Deputy Chairman

Nguyen Thi Phi

Long

Representative of

Community

(signed)

Phan Van Chinh

Page 249: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

242

Page 250: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

243

Page 251: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

244

Page 252: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

245

APPENDIX 8. SOME PICTURES OF ENVIRONMENTAL SAMPLING

Page 253: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

246

APPENDIX 9. RELATED DRAWINGS

Page 254: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

247

Ground Layout

Page 255: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

248

Storm water system

Page 256: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

249

Potable Water System

Page 257: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

250

Non Potable Water System

Page 258: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

251

Masterplan Sewage System

Page 259: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

252

Wastewater treatment plant layout

Page 260: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

253

APPENDIX 10. BASIS FOR CALCULATION OF WATER SUPPLYAND

DRAINAGE

Water supply demand:

Demand for domestic water supply is calculated basing on types of work and are used to

set up calculation demand.

- Dormitory: 120 l/c/d

- Guest house: 200 l/c/d

- Visitors and participants in lectures, exhibitions and memories: 6 l/c/d

- Visitors and students in canteens and sport areas: 25 l/c/d

- Road cleaning: 0.5 l/m2/day

- Watering: 3 l/ m2/day

- Auxiliary works of the University: 5 l/ m2/day

- Landscape: 17.8 l/ m2/day

The total water demand is calculated and shown in the following table:

Page 261: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

254

Page 262: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

255

Page 263: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

256

Page 264: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

257

Page 265: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

258

Calculation of wastewater flow

Page 266: MINISTRY OF EDUCATION AND TRAINING PROJECT … · 2/25/2016  · ministry of education and training project management unit of vietnamese-german university development vietnamese

259