1 MID2030 Customer Consultation October 2011 Mike Budahazy MID2030 Project Director Clinton Rodda Managing Director 2 Why are we here? SRW will ask the state government to consider a bid for the 2012/13 for 8 years of MID 2030 works based on government and irrigators funding 50% each; and irrigators keeping the water savings SRW needs to decide how much to bid for and what modernisation works to include by the beginning of December 2011. We need customers input on: The proposed physical works for that money; and The affordability of that work for their (50%) share of the project costs

Transcript of MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water...

Page 1: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

1

MID2030 Customer Consultation

October 2011

Mike BudahazyMID2030 Project Director

Clinton RoddaManaging Director

2

Why are we here?

• SRW will ask the state government to consider a bid for the 2012/13 for 8 years of MID 2030 works● based on government and irrigators funding 50% each; and

● irrigators keeping the water savings

• SRW needs to decide how much to bid for and what modernisation works to include by the beginning of December 2011.

• We need customers input on:● The proposed physical works for that money; and

● The affordability of that work for their (50%) share of the project costs

Page 2: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

2

3

Agenda

• Background

• Work done since strategy

• Developments in project funding

• Proposed works● Overall project plan

● Zone plan

● MID2030 Leading Works Program

• Use of water savings

• Pricing and affordability

• Next Steps

4

MID2030 Background

Page 3: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

3

5

MID2030 Strategy background

• The largest strategic review undertaken by SRW

• Significant consultation● MID2030 Atlas

● Discussion Paper

● Draft Strategy

● Strategy

• General customer support

• Strong stakeholder support

• Strategy completed in 2007

6

MID2030 Strategy background

SRW

upgrades

supply

Water savings

Improved service

More production

Regional economic growth

Improved environment

Accelerates

on-farm

investment

Improved

irrigation

More production

Less runoff

Less nutrients

Page 4: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

4

7

District wide modernisation

Mainly piping with main carriers as open channels

Channel automation

1 Northern-Macalister

2 Northern-Avon3Southern-Tinamba

4Southern-Cowwarr5 Eastern

8

MID2030 Strategy outcomes

● Water Savings● 37,000 ML

● Project Cost ● Original (2006) Estimate - $120 million

● Service Levels● Increased flow rates

● Reduced order lead time

● Facilitates high flow flood or spray irrigation

● Opens opportunity for even greater water savings on farm

● Significant regional economic and social benefits

● Environment● Water used on farm stays on farm

● Drainage wetlands reducing impact of key drains

● Reduced nutrients in Gippsland lakes

Page 5: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

5

9

Work since 2007

• Detailed planning project ($500,000 Fed’s funding)● Design and cost study for the Southern-Tinamba pipeline

● Southern-Cowwarr balancing storage design

● MID LIDAR survey (high resolution digital imagery and 3D model)

• Detailed cost estimate - verified by an independent cost estimator

• Detailed assessment of water savings - externally reviewed

• Discussions with MCCC and MICI on scoping and affordability

• Government discussions

• Planned MID2030 “Leading Works”

10

Current cost estimate

• 2009 estimate - $280m validated by Evans and Peck

• 2011 estimate - $310m

• Changes since 2006● Detailed project scope

● Completed channel automation projects

● Southern-Tinamba Conceptual Pipeline design

● GMW/NVIRP cost structures

• Overall Changes (to 2011)● $60m construction cost changes

● $60m change in cost estimates > escalation

● $60m change in contingency allowance

● $10m to address capacity constraints

Page 6: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

6

11

Developments in Project Funding

12

Gaining government funding…

• Customer and Stakeholder support

• Minister’s support

• Meet Treasury investment guidelines● Engage with Department of Treasury and Finance (DTF)

● Prepare business case in accordance with DTF guidelines

• Rank well against competing projects across the whole of Government portfolio

● Transport

● Energy

● Hospitals

● Schools

● Housing

● Other water sector

Page 7: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

7

13

Feedback from the Minister for Water, Agriculture and Food Security…

• Met with SRW and MCCC reps three times

• Minister strongly supports the principle of projects that create regional economic development

• SRW to submit bid late 2011 to early in 2012●government and irrigators pay 50% of costs each

● irrigators keep 100% of water savings

14

SRW’s strategy to gain funding…

• Break MID 2030 into at least two phases

• Maximise early water savings

• Projects ready to go

• Keep price change affordable for customers

• Maximise project benefits• Regional growth

• Irrigator production

• Service improvement

• Resilience to climate change

• Environmental impact

Page 8: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

8

15

Revised MID2030 Project

16

MID2030 Project Phase 1

• $140.5 million (2011$) investment : 28,300 ML of water savings

• Pipelining of entire Southern-Tinamba supply zone• Elimination of 147 regulators

• Addressing 384 outlets

• Channel automation (regulators) in:• Nambrok-Denison 204 regulators

• Heyfield 32 regulators

• Eastern 122 regulators

• Construction of Southern-Cowwarr Balancing Storage

• Some outlet modernisation and rationalisation

• At least one end of drain wetland

• Preparation for phase 2● Planning study for Newry Pipeline

● Meter market analysis

Page 9: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

9

17

MID2030 Project Phase 1

Existing Channel Automation

Proposed Phase 1 Channel Automation

Existing Pipeline

Proposed Phase 1 Pipeline (Preliminary)

Balancing Storage

18

MID2030 Project Phase 1

CUSTOMERS RECEIVING SERVICE BENEFITS

0%

20%

40%

60%

80%

100%

Zone 1Northern-Macalister

Zone 2Northern-

Avon

Zone 3Southern-Tinamba

Zone 4Southern-Cowwarr

Zone 5Eastern

MID

Per

cen

tag

e o

f se

rvic

e p

oin

ts

0%

10%

20%

30%

40%

50%

Per

cen

tag

e o

f w

ater

del

iver

ed i

n z

on

e

Service Benefits Pre Phase 1 Implementation

Service Benefits Post Phase 1 Implementation

Percentatage of water delivered in zone

Page 10: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

10

19

MID2030 Project Phase 1 (after gov’t investment)

COST PER MEGALITRE OF WATER SAVINGS

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

$3,500

Zone 1Northern-Macalister

Zone 2Northern-

Avon

Zone 3Southern-Tinamba

Zone 4Southern-Cowwarr

Zone 5Eastern

MID

Wat

er S

avin

gs

(201

1$ p

er M

L)

20

Cost Breakdown, Timelines and Water Savings

DeliveryDate

Zone 3 - Southern-Tinamba Pipeline $92.5 13,500 end 2020 mid 2022

Zone 3 - Heyfield Regulator Retrofit $2.5 1,200 end 2013 mid 2015

Zone 4 - Southern-Cowwarr Regulator Retrofit $17.6 5,200 end 2017 mid 2019

Zone 4 - Southern-Cowwarr Balancing Storage $9.2 1,800 end 2016 mid 2018

Zone 5 - Eastern Regulator Retrofit $10.7 5,300 end 2018 mid 2020

Rationalisation $5.0 1,300 end 2015 mid 2017

Wetlands $3.0 - end 2020

Total $140.5 28,300

Supply ZoneWater

Savings Available

Water Savings

(ML)

Total Cost (2011$

millions)

Page 11: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

11

21

MID2030 Project Phase 1 - Outcomes

Results

Cost of project (2011$) $ 140.5 million

Water savings 28,300 ML

Cost to customers per ML with 50/50 funding $ 2,480 per ML

Construction period 8 years

Deliveries through modern meters 40%

Customers receiving service benefits 86%

Regulators replaced with pipelines or retrofitted 70%

Estimated regional economic benefit $80 million per annum

22

MID2030 Project Phase 2

• $169.5 million (2011$) investment generating 8,700 ML of water savings

• Zone 1 - Pipelining of entire Northern-Macalister supply zone

• Newry Pipeline Project

• Based on planning study from Phase 1

• Zone 2 - Balancing storages and various modernisation works

• Valencia Creek balancing storage

• Main Sale balancing storage

• Channel automation and pipelining to address system constraints

• Wide scale meter modernisation program

• Defer decisions on major metering program until meter market more competitive and funding may be available

Page 12: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

12

23

MID2030 Project Phase 2

Cost Breakdown and Water Savings

Zone 1 - Newry River Pipeline $52.6 3,500

Zone 1 - Compliant Metering Program $3.5 -

Zone 2 - Balancing Storages $6.8 -

Zone 2 - Various Modernisation Works $44.8 2,000

Zone 4 - Compliant Metering Program $37.2 2,000

Zone 5 - Compliant Metering Program $24.6 1,200

Total $169.5 8,700

Supply ZoneTotal Cost

(2011$ millions)

Water Savings

(ML)

Page 13: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

1

61

MID2030 Leading Works Program

62

MID2030 Leading Works Program

Infrastructure

• Detailed design of Southern-Cowwarr balancing storage

• Smaller scale regulator retrofit program for:• Eastern supply zone

• Nambrok-Denison supply zone

• Heyfield channels

Rationalisation

• Start of a rationalisation program to address demand for customer initiated rationalisation projects – e.g. customer outlets

On-farm Productivity Program

• On-farm productivity program (coordinated program with DPI)

Contribution from SRW – auction funds

Page 14: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

2

63

Eastern RegulatorRetrofit (36 No.)

Heyfield RegulatorRetrofit (32 No.)

Balancing Storage Design (min 150 ML)

Nambrok-Denison Regulator Retrofit (27 No.)

MID2030 Leading Works Program

64

MID2030 Leading Works Program

Nambrok-Denison Regulator Retrofit $ 2.4 M 820 ML

Eastern Regulator Retrofit $ 3.0 M 980 ML

Heyfield Regulator Retrofit $ 2.3 M 1200 ML

Southern-Cowwarr Balancing Storage Design $ 0.8 M - ML

Rationalisation Program Stage 1 $ 4.6 M 1280 ML

On Farm Productivity Program $ 0.5 M - ML

Total $ 13.6 M 4280 ML

Outlets replaced 80

Regulators retrofitted 95

Project completion 2014

• SRW has contributed $1m for this from auction proceeds – with more planned to reduce project costs

Page 15: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

3

65

How do we deal with Water Savings?

66

How do we deal with water savings?

• Sale via auction

• Sale via “shelf price”

• Allocate water at zero capital cost

Page 16: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

4

67

Auctions…

• Water goes to auction with reserve price

• Advantages● Water goes to people who value it most

● Keeps prices lower

● Develops water market

● Generally supported by Treasury

• Disadvantages● Capital cost of water may hinder other on farm investment

● How big is the auction market?● Demand for water?

● Seasonal conditions

68

Shelf Price…

• Water available for purchase at a pre-determined price either by allocation or afterwards

• Advantages● Water goes to people who value it

● Keeps prices lower

• Disadvantages● Capital cost of water may hinder other on farm investment

● Sets water market price

● How big is the market?● Demand for water?

● Seasonal conditions

Page 17: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

5

69

Allocate Water…

• Water savings offered to customers proportional to entitlement at no capital cost. A second round offer would be made for remaining water

• Advantages● Water goes to people who want it

● Use it or sell it

● Capital money could be used for on farm investment

● Likely that all water would be allocated

• Disadvantages● Higher water prices

● Permanent water market impacted – could you sell it?

● Some water may not be used

● Would need strong justification to Treasury

70

Pricing

Page 18: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

6

71

Pricing

• A detailed financial model has been built • A number of factors influence future water prices

● Business As Usual costs● Corporate cost changes

● Business cost changes

● Asset renewal and maintenance costs

● Project costs● Capital works● Changes to operations and maintenance costs● Whether we allocate or auction water savings● Interest rates

● Essential Services Commission rules and “determinations”

• Estimates have been provided to provide a guide• Current “re-bundled” price assumed at $68 per ML

72

Estimated MID2030 project cost impact

PRICE INCREASE $/ML FOR EACH 5 YEAR WATER PLAN PERIOD (REAL 2011$)

-

$5.00

$10.00

$15.00

$20.00

$25.00

$30.00

$35.00

2014

- 20

18

2019

- 20

23

2024

- 20

28

2029

- 20

33

2034

- 203

8

2039

- 20

43

2044

- 20

48

2049

- 20

53

2054

- 20

58

2059

- 20

63

2064

- 20

68

2069

- 20

73

2074

- 207

8

Water Plan Period

Eff

ecti

ve D

oll

ars

per

ML

(20

11$/

ML

)

$/ML - real

Average

Page 19: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

7

73

Net price impact over timeRENEWALS

MID2030 COMPARISON TO BUSINESS AS USUAL (BAU)

60

70

80

90

100

110

120

2008-2013 2013-2018 2018-2023 2023-2028 2028-2033

Water Plan Period

Eff

ecti

ve D

olla

rs p

er M

L (

2011

$/M

L) MID2030

BAU

74

Estimated Price as at 2023 (no auction)

Current Price (Estimated) $68 NA

Business As Usual (BAU) Price $84 23%

BAU + MID2030 Price $10840%

(19% BAU + 21% MID2030)

Scenario2011$ per ML

Percentage Change

Page 20: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

8

75

Affordability

76

Water costs for Dairy

Page 21: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

9

77

Case studies

• Understanding impacts of extra water and increased prices

• 6 case-studies: selected to cover● Sectors dairy/grazing/horticultural

● Scale 40ha - 447ha

● Soils Low - Moderate - High Permeability

● Delivery Reliable - Very unreliable

● Water Use Adequate - Undersupplied

• Marginal cost of water worked out● How much extra water is available?

● What will the extra cost be?

● Marginal cost approx $141 and $171 per ML depending on assumptions

78

Marginal price example..

• Customer has existing entitlement 100 ML• Current price $68 per ML• Current water cost $6,800

• New allocation as a result of works (5%) 5 ML

• New entitlement (100 ML + 5 ML) 105 ML• New cost of entitlement $ 7,505• New average cost $ 71.50 per ML

• Additional cost = ($7,505 - $6,800) $ 705

• Marginal cost = Additional Cost $705 = $ 141 per MLAdditional Entitlement 5 ML

Page 22: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

10

79

Case studies

BusinessNew Water Allocation

Other Benefit / Opportunity

Marginal Net Benefit $/ML Water End use

Large Dairy A RequiredNew High Flow outlet on 41ha 250 offset feed supplement

Grazier RequiredChannel Deliv Serv completed 96* increase stocking rate

Horticulture Sell Nil. 160 offset interest (8%)

SM Dairy A Sell Nil. 120*off farm investment (6%)

SM Dairy B RequiredImp Channel Delivery Serv. 180 offset feed supplement

Large Dairy B Required Nil. 314 increase stocking rate

Additional Water Cost $141/ML to $171 per ML

80

Case study outcomes

BusinessMarginal Net Benefit $/ML

Marginal Cost $/ML (M Benefit – M Cost) x ML = Net

Large Dairy A 250 141 $250 - $141 x 227ML = $24,743

Grazier 96* 141 $96 - $141 x 64ML = - $2,880

Horticulture 160 141 $160 - $141 x 22ML = $418

SM Dairy A 120* 141 $120 - $141 x 71ML = - $1,491

SM Dairy B(Imp Delivery) 180 @ 40ML 0 $180 - $0 x 40ML = $7,200

SM Dairy B 180 141 $180 - $141 x 48ML = $1,872 ($9,072)

Large Dairy B 314 141 $314 - $141 x 377ML = $65,221

Additional Water Cost of $141/ML used as basis of comparison.

Page 23: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

11

81

Greater benefits apply when…

• Poor levels of service now● Allows improved watering systems

● Promotes greater productivity

• Permeable soils● Gains benefits from improved watering

● Look at sprinkler V’s flood cost:benefits

• Water constrained● Expanding production

● Replacing high cost feeds

82

Next Steps?

Page 24: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

12

83

Next Steps for Business Case…

• Review questions and feedback from these sessions

• Review and discuss with MCCC (early November)

• Potential further feedback session with customers (Mid November?)

• Business case finalised and reviewed by Board (December)

• Submission to DSE / Treasury (December / January)

• Advice on outcome – mid year

84

Processes should we get funding…

• Governance Committee● Government departments

● SRW

● MCCC

• Individual Business Cases● Consultation with SRW staff and affected customers

● Review value for money

● Validate costs estimates and water savings

● Project approval

• Project review● Regular cost, scope, quality, time reviews

Page 25: MID2030 Customer Consultation - Southern Rural …MID2030 Project Phase 2 Cost Breakdown and Water Savings Zone 1 - Newry River Pipeline $52.6 3,500 Zone 1 - Compliant Metering Program

13

85

An opportunity to maximise the full potential of the MID