Mid-term Review 2/Jul/15 Project SLOPE 1 WP 8 – Openness with other activities, dissemination and exploitation of results

Transcript of Mid-term Review Meeting - WP8

Page 1: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Project SLOPE1

WP 8 – Openness with other activities, dissemination and exploitation of results

Page 2: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Project SLOPE2

T.8.1 – Dissemination planning and publications results

Brussels, July 2th, 2015

Page 3: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Overview

• Status: On going (50%)• Length: 36 months (from M1 to M36)• Involved Partners

• Leader: ITENE • Participants: All

• Aim: Manage dissemination activities and publications.• Output:

• Deliverable D8.01 Project website (Online)• Deliverable D8.21 Dissemination strategy I (Submitted)• Deliverable D8.22 Dissemination strategy II (Draft)

Page 4: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Overview

Articles published in the popular press 4Exhibitions 1Flyers 2Interviews 3Media briefings 9Oral presentation to a scientific event 9Oral presentation to a wider public 12Organisation of Workshops 2Posters 5Press releases 5Web sites/Applications 2publications (proceeedings, book sections) 8Total general 62

Already Introduced in ECAS Dissemination Portal

Page 5: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

1) DISSEMINATION PLAN

Document of Strategy and materials (version 1) produced at thebeginning of the project

Submitted

Version 2 finalised

Page 6: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

2) BROCHURE:

Page 7: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

2) BROCHURE

Page 8: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

2) PROJECT WEBSITE. www.slopeproject.eu

Page 9: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

3)SOCIAL MEDIA.

Channels in social media available:

http://www.slideshare.net/Slope_Project

https://www.facebook.com/pages/SLOPE-project/351131505025437?fref=ts

http://www.linkedin.com/groups/SLOPE-Project-7450879

http://twitter.com/SLOPEProject

https://www.youtube.com/user/SlopeProject

Implemented in the website

Page 10: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

3) SOCIAL MEDIA.

Regularly update of the different Social Media Channels:

Page 11: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

4) NEWSLETTER

Newsletter 1 and 2 Published (Available in Newsletter section at www.slopeproject.eu)

Next issues: July 2015, December 2015

Page 12: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

5) POSTER

• Physical roll-up with a brief presentation of the project

• Available for the partners which will need it.

• To be used during conferences and dissemination activities.

Page 13: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

6) EVENTS

Trade Fairs attended by partners presenting SLOPE project:

NAME TYPE PLACE STARTING DATE PERIOD CWL COASTWAY

SAM Trade Fair Grenoble, France 23/04/2014 23-24/4/2014 GREIFENBERG

Worldbioenergy 2014 Trade Fair Jönköping, Sweden 03/05/2014 3-5/6/2014 MHG

GEO Bussines Show Trade Fair London, England 28/05/2014 28-29/5/2014 CWL COASTWAY

Boster nord- est Trade Fair Piana del Cansiglio, Italy 06/06/2014 6-8/6/2014 GREIFENBERG

EIMA ENERGY Trade Fair Bologna (Italy) 12/11/2014 16/11/2014 CNR-IVALSA

ASTURFORESTA Trade Fair Asturias (Spain) 18/06/2015 20/06/2015 GREIFENBERG

Page 14: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

6) EVENTS: Conferences attended by partners presenting Slope Projects:

NAME TYPE PLACE STARTING DATE PERIOD MHG SYSTEMS

Aebiom Bioenergy Conference Conference Brussels, Belgium 12/05/2014 12-14/5/2014 MHG

SENTINEL-2 for Science Workshop Conference Frascati (Rome) Italy 20/05/2014 20-22/05/2014FLYBY

OSCAR 2014 Conference Uppsala, Sweden 25/06/2014 25-27/06/2014 BOKU

FORMEC/FEC Conference Conference Gerarmed, France 23/09/2014 25/09/2014 CNR-IVALSA

Hyperspectral Imaging and Applications Conference Conference Coventry, UK 15/10/2014 15/10/2014

BOKU

IASIM conference in spectral imaging Conference Rome, Italy 03/12/2014 05/12/2014

BOKU

Workshop on Hyperspectral Imaging Workshop Vienna 20/03/2015 20/03/2015BOKU

9th GEO European Projects Workshop - Workshop Copenhagen 15/06/2015 15/06/2015

GRAPHITEC

20th International Conference on 3D Web Technology (Web3D 2015). Conference Crete, Greece 18/06/2015 21/06/2015

GRAPHITEC

15th International Multidisciplinary Scientific GeoConference & Expo SGEM 2015 Conference Albena (Bulgaria) 16/06/2015 25/06/2016

GRAPHITEC

Page 15: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

6) EVENTS

Poster presentations:

CNR IVALSA:

Sentinel-2 for Science Workshop, 2014 May 20 -22, ESA-ESRIN Frascati

M.Morelli, A.Masini, “Sentinel-2 Imagery for the Development of Innovative Decision Support Systems Dedicated to Sustainable Forest Management”.

Page 16: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

6) EVENTS

Poster presentations:CNR IVALSA: September 2014 (23-26th) we presented SLOPE as visual presentation at the FORMEC/FEC conference

Page 17: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

6) EVENTS

Poster presentations:BOKU: results at IASIM 2014 conference on spectral imaging in Rome

Page 18: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

7) PRESS RELEASES

First Press release completed and sent to internacional media.

Translated into different partners’ languages.

Sent on june 2014

Next: 1st week of July 2015 with initial results and advances

Page 19: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

7) PRESS RELEASES

Page 20: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

8) SCIENTIFIC ARTICLES- Project SLOPE: Introducing new technologies in mountain forestry operationsPicchi G, Huurinainen S, Gort-Oromi J, Nolan E, Keane E, Kuhmaier M, De Amicis, RProceeding at the join 5th Forest Forestry Conferences (FEC) ans 2014 Forest Mechanization Conference (FORMEC)

- WebGL virtual Globe for efficient forest production planning in mountain areasPrandi F, Panizzoni G, Magliocchetti D, Devigili F, De Amicis FProceedings of the 20th International Conference on 3D Web Technology Web3D 2015

- Inspection of log quality by hyperspectral imagingA. Zitek1, F. Firtha2, K. Böhm, V. Parrag, J. Sandak, B. HinterstoisserIASIM 2014 conference on spectral imaging in Rome

- Survival test of RFID UHF tags in timber harvesting operationsPicchi G, Kühmaier M, Diaz J48th International Symposium on Forestry Mechanization (submitted)

Page 21: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

ITALY (CNR-IVALSA)9) DISSEMINATION ARTICLES

Page 22: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

• Article in austrianmagazine FORSTZEITUNG (“Forschung für die Praxis”). October 2014:

9)DISSEMINATION ARTICLES

• “Tecniko & Pratiko” (number 104) of the “Sherwood: Foreste ed Alberi Oggi” journal, n. 203, published in June 2014. “Sherwood: Foreste ed Alberi Oggi” is one of the main technical and scientific journals of forest sciences in Italy.

Page 23: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

9) DISSEMINATION ARTICLES

The article entitled “Sperimentazione di rilievo UAV a supporto della pianificazioneforestale”, written by Federico Prandi, Daniele Magliocchetti and Raffaele De Amicis has been published in the GEOmedia magazine, the first Italian magazine on geomatics and intelligent geography

Page 24: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

Workshop on Hyperspectral Imaging - 20 March 2015 -University of Natural Resources and Life Sciences in Vienna (Austria). Presentation of other projects:

Philippe Vermeulen, Belgium presented work accomplished within the FP7 project n°211326 CONFFIDENCE (CONtaminants in Food and Feed: Inexpensive DEtectioN for Control of Exposure. http://cordis.europa.eu/result/rcn/143666_en.html

Professor Kessler also mentioned work financed by the EU: HypErspectraL Imaging Cancer Detection, FP7 project n°618080 Funded under: FP7-ICT http://cordis.europa.eu/project/rcn/111274_en.html

10) COOPERATION / OTHER PROJECTS

Page 25: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

Fondazione GraphiTech @ Fraunhofer HHI & Hasso-Plattner Institute in Germany27 May 2014

GraphiTech research team went to visit Fraunhofer Heinrich Hertz Institute in Berlin (Germany) on 27 May 2014, and the Hasso-Plattner-Institute in Potsdam (Germany). SLOPE project and the performed activities performed so far were presented.

Contact with TREES4FUTURE Project and consortium.

The project aims to integrate, develop and improve major forest genetics and forestry research infrastructures. BOKU is also part of the project.

10) COOPERATION / OTHER PROJECTS

Page 26: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

11) WORKSHOPS

• Four technical workshops are planned as far as results are available for dissemination. One has already taken place.

• Related tasks:• Selecting potential stakeholders• Making invitations• Setting up the program• Communication• Secretariat and logistics

Page 27: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

Workshop 1

Workshop on Hyperspectral Imaging at BOKU-UFT 20/03/2015

A workshop on Hyperspectral Imaging was organized on 20 March 2015 at the University of Natural Resources and Life Sciences in Vienna (Austria). The workshop was very successful; it hosted 58 participants from 11 countries and was a real international, transdisciplinary and interdepartmental scientific event.

Page 28: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Tasks and ResultsT.8.1 – Dissemination planning and publications results.

Workshop 2

Forest engineering: Making a positive contribution in Linz (Austria), 04-08/10/2015

250 researchers, practitioners and government officials from different countries are expected to share state-of-the-art knowledge of harvesting operations, with a focus on steep terrain. The meeting consists of a two day technical conference on new developments in forest engineering, followed by an optional one or two-day visit to AUSTROFOMA machine exhibition to watch innovative harvesting technology.

Page 29: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

ConclusionT.8.1 – Dissemination planning and publications results.

M1 to M18 Good dissemination accomplished Focused in raising awareness of the project

M19 to M36 Maintain awareness Focus in specific areas:

Foresty industry (main) Web development E-commerce Hyperspectral imaginering

Page 30: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Contact info

Antonio Monsalve ([email protected]) Juan de Dios Díaz ([email protected])Emilio Gonzalez([email protected])

Thank you for your attention

Page 31: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Project SLOPE

WP5 T8.4 – Industrial Advisory BoardBrussels, 2nd July, 2015

Page 32: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Overview

• Status: Progress (50%)• Length: 9 Months (From M1 to M25)• Involved Partners

• Leader: MHG• Participants: Combolab, COAST, BOKU, FLY, TRE

• Aim: Set up an advisory board in order to follow all project activities

• Output: D8.04, due M25; Presenting Industrial Advisory

Page 33: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Task 8.4 - Objective

• The main objective of this task is to involve industrial members from the forestry, agricultural and related logistics and machinery industry. The main activities of the advisory board will be interchange opinions and knowledge by means of meetings and discussions. This information will be used as inputs for the execution of the tasks defined in SLOPE project, and redefine them when needed.

• The Advisory board will be set up at an early stage (first project meeting) of the project in order to follow all the activities starting from the requirements analysis.

Page 34: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Task 8.4 – Actions completed

• Workshop 1 in Trento (kick-off meeting)• Workshop 2 in Mikkeli (semiannual meeting 2014)

• Agreed in Mikkeli that every country partner starts to search for goodcanditate(s) for this board

• Presentation given (10/2014) to Finnish Forest Technology experts in Helsinki (Annual Scientific Conference)

• Metsäteho interested to become a board member• Metsäteho running similar projects including Big Forest Data ..\..\WP8\Industrial Advisory Board\mtp2014_tekn_hamalainen.pdf• 3-5 members: one from Metsäteho, Finland, one more suggested byBoku and CNR each• Profiles TBD by the end of September (M21)

Page 35: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Summary

• Profiles and commitment of the members crucial• Final committed members to be mapped and decided by the end of the

year (M24)

Page 36: Mid-term Review Meeting - WP8

Mid-term Review2/Jul/15

Contact info

Seppo Huurinainen