Mid-term Review Meeting - WP5

24
Project SLOPE 1 WP 5 – Forest information system development

Transcript of Mid-term Review Meeting - WP5

Page 1: Mid-term Review Meeting - WP5

Project SLOPE1

WP 5 – Forest information system development

Page 2: Mid-term Review Meeting - WP5

Project SLOPE

WP5 T5.1 – Database to support novel inventory data content

Brussels, 2nd July, 2015

Mid-term Review 2/Jul/15

Page 3: Mid-term Review Meeting - WP5

Overview

Mid-term Review 2/Jul/2015

• Status: Completed (100%)• Length: 10 Months (From M08 to M17)• Involved Partners

• Leader: MHG• Participants: GRAPHITECH, CNR, COAST, FLY, TRE, ITENE

• Aim: Design and implement database and web service interfaces to support inventory and spatial data

• Output: D5.01 Inventory module of the FIS (Prototype)

Page 4: Mid-term Review Meeting - WP5

Objectives

• Design the database to support inventory and spatial data• Implement database to relation database management

system (RDBMS)• Design and implement interfaces to this database• Construct deployment platform for the database and the

web service module• Deploy prototype to the deployment platform• Make technical description about the implementation

Mid-term Review 2/Jul/15

Page 5: Mid-term Review Meeting - WP5

Inventory module of the FIS Very central component of whole SLOPE system architecture

Mid-term Review 2/Jul/15

Page 6: Mid-term Review Meeting - WP5

Milestones

M08 M09 M10 M11 M12 M13 M14 M15 M16 M17

Start M08 – End M17

1. First databasedesign

2. Web Service design

3. Database readyv3.3

4. Web Service module

and source codemanagement

6. Report and task ready

5. Deployment platform

Mid-term Review 2/Jul/15

Page 7: Mid-term Review Meeting - WP5

Deliverable overviewSpecified in System Architecture Specifications

Mid-term Review 2/Jul/15

Page 8: Mid-term Review Meeting - WP5

Deliverable – FIS Database

• Implemented on MySQL database engine• MySQL Spatial Extensions for storing spatial data• Database includes four logical sections:

• User management• Real estate management• Tree and product management• Storage and logistics

• Integration of the logistic model by ITENE

Mid-term Review 2/Jul/15

Page 9: Mid-term Review Meeting - WP5

Deliverable – FIS Database

Mid-term Review 2/Jul/15

Page 10: Mid-term Review Meeting - WP5

Deliverable – Web Service

• Light weight Web Service -module to read and write data from FIS database• Implemented with Java, easy to extend• Standard REST interface with XML and JSON support• Source code of this module is hosted on BitBucket Git repository • Secured with Basic authentication and Secure Socket Layer (HTTPS)

Mid-term Review 2/Jul/15

Page 11: Mid-term Review Meeting - WP5

Deliverable – Deployment

• FIS components are hosted on Jelasticcloud platform (Platform as a Service)

• Platform is hosted in Helsinki, Finland• Own independent environment for

SLOPE FIS• Apache Tomcat, Java 8, and MySQL 5.7• Jelastic works well on mission critical

and high availability cloud services• Scales horizontally and vertically for

our performance needs• Domain: slopefis.mhgsystems.com

Mid-term Review 2/Jul/15

Page 12: Mid-term Review Meeting - WP5

Summary

• Overall, this task went very well. • Communication with partners worked well, all needed feedback returned

on time• The deliverable was finished on time• Goals were reached correctly• This prototype gives us very good base for SLOPE platform development

and integration work• The prototype will be developed further during the project

• New interfaces• Database extensions

• Deliverable report can be found from project’s Dropbox• Web Service is published on https://slopefis.mhgsystems.com/slope-fis/

Mid-term Review 2/Jul/15

Page 13: Mid-term Review Meeting - WP5

Mid-term Review 2/Jul/2015

Contact info

Veli-Matti Plosila [email protected]

Seppo Huurinainen [email protected]

Thank you for your attention

Page 14: Mid-term Review Meeting - WP5

T5.2- Platform for near real time control of operations

Introduction

Task: T5.02 Platform for near real time control of operations

Task Leader: Treemetrics

Partners involved: GRAPHITECH, CNR, MHG, ITENE

Deliverable: D5.02 Real Time supply chain control module of FIS

Status: On going

Mid-term Review 2/July/15

Page 15: Mid-term Review Meeting - WP5

PRESENTATION:

Part 1: Scope of work

Part 2: Definion of workflow

Part 3: Module achitecture

Part 4: Planned activities

T5.2- Platform for near real time control of operations

Introduction

Objective:Develop a system that allows for the near real time control of operations .

Mid-term Review 2/July/15

Task: T5.02 Platform for near real time control of operations

Page 16: Mid-term Review Meeting - WP5

Development phasesDESIGN DEVELOPMENT TESTING /

DEMOSTRATION

Load harvesting dataand demonstrate

functionalities

Real Time Supply Chain Control

GUI

Harvesting Data Analysis

Integration with harvesting plan tools

T5.2- Platform for near real time control of operations

Scope of work

Mid-term Review 2/July/15

Page 17: Mid-term Review Meeting - WP5

Scope of the work1. Develop Real Time Supply Chain Control module - MHG

a. Integration of Harvesting Plan modules (task 5.1)i. Tree and products information display –FID tagged- (task 2.4)ii. Storage and logistics data entry (task 2.5)iii. Timber Supply Plan –MHG/CNR/ITENE-

b. Real Time Harvesting Controli. Integrate Intelligent Processing Head data (task 3.6) -CNR/MHG-ii. Harvesting Data Analysis (predicted vs. estimated) -TREiii. Harvest vs. predicted tree and products information (GUI)-MHG-iv. Storage and logistics (modify data when required) -CNR/ITENE-v. Review Timber Supply Plan -CNR-

T5.2- Platform for near real time control of operations

Scope of work

Mid-term Review 2/July/15

Page 18: Mid-term Review Meeting - WP5

Task performed 1. Definition of the workflow and actors involved.

• Overview of the Real Time Supply Chain Control platform architecture

T5.2- Platform for near real time control of operations

Scope of work

Mid-term Review 2/July/15

Page 19: Mid-term Review Meeting - WP5

2. - HARVESTING PLAN (ITENE/ MHG)

3. PROCESSING HEAD SOFTWARE (Task 3.6) - CNR-Real timber products data- Timber products summary- Quality indexes

5. MONITORING PLATFORM - MHG

4.2.- Planning review (logistic) ITENE-Review or point 2

4.1.- Monitoring - CNR-Review Timber Supply Plan

4. HARVESTING DATA ANALYSIS - TRE- Compare predicted vs. estimated

- Infrastructure (roads, access)- No./ harvesting machines- Storage location- Location of machines, ETC

1. INVENTORY DATA (TRE)1.1.- Timber assets-Expected amount of timber to cut-Expected Products assortments-Tree location

Workflow

T5.2- Platform for near real time control of operations

Definion of workflow

Mid-term Review 2/July/15

Page 20: Mid-term Review Meeting - WP5

T5.2- Platform for near real time control of operations

Module achitecture

Mid-term Review 2/July/15

Page 21: Mid-term Review Meeting - WP5

Related Funtional Modules

T5.2- Platform for near real time control of operations

Module achitecture

Mid-term Review 2/July/15

Page 22: Mid-term Review Meeting - WP5

T5.2- Platform for near real time control of operations

Platform achitecture

• Integration of Processing Head• GPRS/UMTS data transfer (Task 3.6)• Decompression of data and storage in the database• Access to the data from Harvesting Control platform

• Data comparison analysis• Access to the Processing Head data (timber products and quality

indexes)• Compare harvested vs. predicted timber products and quality

indexes information• Real Time Harvesting Control platform

• Display predicted timber products and Processing Head data • Display data comparison analysis (harvested vs. predicted)• Facilitate modification of storage and logistics (when required)

Mid-term Review 2/July/15

Page 23: Mid-term Review Meeting - WP5

T5.2- Platform for near real time control of operations

Platform achitecture

Mid-term Review 2/July/15

Task 1.3

Page 24: Mid-term Review Meeting - WP5

Planned Activities 1. Agree module architecture design with partners (next

weeks)

2. Develop for near real time control platform (M20)

3. Test near real time harvesting control in the demo area (M22).

T5.2- Platform for near real time control of operations

Planned activities

Mid-term Review 2/July/15