Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever...

27
Mid-Coast Bacteria TMDL: LSAC Update Mid Coast Bacteria TMDL: LSAC Update Kevin Brannan Oregon DEQ Jl 15 2015 July 15, 2015

Transcript of Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever...

Page 1: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Mid-Coast Bacteria TMDL: LSAC UpdateMid Coast Bacteria TMDL: LSAC Update

Kevin BrannanOregon DEQJ l 15 2015July 15, 2015

Page 2: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Main TMDL Efforts

• Freshwater streams and rivers– Load Duration Curves (LDC)Load Duration Curves (LDC)– Watershed Modeling

• Estuarine • Beaches

Slide 2

Page 3: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Freshwater Streams and Rivers:Freshwater Streams and Rivers:Load Duration Curves

Slide 3

Page 4: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Process Update: Watershed using LDC

TMDL PlanDevelopmentp

Implementation PlanDevelopment

Slide 4

Page 5: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Load Duration Curve Estimation Process

• Wherever possible, use scripts (small list of computer commands) to perform actions to ensure steps are ) p preproducible and transparent

• Almost all of the LDC process is automated and performed i th R t ti ti l i lin the R statistical programming language

• R is :– Open source eliminating the need for proprietary software toOpen source eliminating the need for proprietary software to

reproduce analysis– Developed and maintained by a global community

S

Slide 5

– Source code and scripts can be accessed by anyone

Page 6: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Load Duration Curve Results Review

• Developed a standard report form• TWG members (and some people outside TWG) reviewedTWG members (and some people outside TWG) reviewed

results:– Commented on adequacy of data– Commented on Methods for LDC estimation– Recommended potential sources

• Compiled reviews and reported back to TWG• Compiled reviews and reported back to TWG

Slide 6

Page 7: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Load Duration Curve Results Review

• Found 46 out of 93 stations with reductionsF d 13 t f 15• Found 13 out of 15 basins in the Mid-Coast with reductions

Slide 7

Page 8: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Load Duration Curve Results Review

• Shellfish growing• Water contact

recreation

Slide 8

Page 9: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Load Duration Curve Work Scheduling Watersheds

• Develop TMDL documents and Implementation plans for watersheds within the Mid-Coast Basins

• Watersheds are better size for implementation than entire Mid-Coast Basins

• Work done in parallel for watersheds• Learn from earlier watershed work to improve process• Consider multiple factors when scheduling work• Consider multiple factors when scheduling work

Slide 9

Page 10: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Load Duration Curve Work Scheduling Watersheds

WatershedWatershedSalmon RiverDevils LakeUpper Yaquina RiverUpper Yaquina RiverSchooner CreekSiuslawTenmile CreekTenmile CreekYachats RiverBeaver CreekUpper Alsea RiverUpper Alsea RiverEckman LakeLower Drift CreekL Y i Ri

Slide 10

Lower Yaquina RiverSiletz River

Page 11: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Big Elk Creek Watershed Modeling

Slide 11

Page 12: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Process Update: Big Elk Creek Watershed Modeling

TMDL PlanDevelopmentp

Implementation PlanDevelopment

Slide 12

Page 13: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Model Setup and Parameter Estimation

Slide 13

Page 14: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Example of Wildlife-Elk habitat and sub-model

Wi t H bit tWinter Habitat

Summer Habitat

Slide 14

Page 15: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

On-site estimation and sub-model

Slide 15

Page 16: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Cow-calf estimation and sub-model

Slide 16

Page 17: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Watershed Modeling: Big Elk Creek

• Extended the simulation period– New simulation period 1995-10-01 to 2014-05-31New simulation period 1995 10 01 to 2014 05 31– Previous simulation period 1995-10-01 to 2010-12-31

• Contractor reviewing overall model– Funded form USEPA– Methods for review developed

Completion estimated toward end of 2015– Completion estimated toward end of 2015

Slide 17

Page 18: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Watershed Modeling: Big Elk Creek (continued)

• Current ODEQ work– Conduct hydrologic parameter estimation/uncertaintyConduct hydrologic parameter estimation/uncertainty

analysis for new simulation period– Setup bacteria model for new simulation period

C ti t i t TWG f db k i t b t i b– Continue to incorporate TWG feedback into bacteria sub-model input

• Begin writing report documentg g p

Slide 18

Page 19: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Watershed Modeling: Upper Yaquina River

• Develop watershed model like Big Elk CreekS t i l t ti• Support implementation

• Begin model development for Yaquinadevelopment for Yaquina River

• Contractor began work J 2015June-2015

Slide 19

Page 20: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Beach Bacteria TMDL

• Identify % Reductions from concentration datafrom concentration data

• Collect responses via electronic form

• Provide geographic and water quality information

Slide 20Slide 20

Page 21: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Process Update: Beach Bacteria TMDL

TMDL PlanDevelopmentp

Implementation PlanDevelopment

Slide 21

Page 22: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Beach Results Packet: Electronic Review

• Google Earth– Interface of systemInterface of system

• R (statistical programming language)– Download, clean and format data– Create spatial data– Analyze data

• Google Docs• Google Docs– Form for review response– Sheet for automatic tabulating reponses

Slide 22

g p

Slide 22

Page 23: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Beaches Bacteria TMDL

Slide 23

Page 24: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Beach Review Results

Slide 24

Page 25: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Beach Review Results

Slide 25

Page 26: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Beach Review Results: Overview

• End date: May 30, 2015• Total responses: 64p• Stations reviewed: 87• Stations/Reviewer: 102 • Beaches reviewed:18

Slide 26

Page 27: Mid-Coast Bacteria Update LSAC 09 (final)Load Duration Curve Estimation Process • Wherever possible, use scripts (small list of computer commands))p p to perform actions to ensure

Questions?

Slide 27