MICROTUNNELLING OVERCOMES DESIGN AND CONSTRUCTION CHALLANGES · MICROTUNNELLING OVERCOMES DESIGN...
Transcript of MICROTUNNELLING OVERCOMES DESIGN AND CONSTRUCTION CHALLANGES · MICROTUNNELLING OVERCOMES DESIGN...
TRENCHLESS TECHNOLOGY ROADSHOW
May 28-29, 2014 – Scotiabank Convention Centre, Niagara Falls, ON
MICROTUNNELLING
OVERCOMES DESIGN AND
CONSTRUCTION CHALLANGES The Keswick Outfall Project
PRESENTATION OUTLINE
• Project Overview
• Design Challenges
• Construction Challenges
• Lessons Learned
PROJECT OVERVIEW
• Where exactly is Keswick, Ontario?
PROJECT OVERVIEW
• Where exactly is Keswick, Ontario?
York Region
PROJECT OVERVIEW
• Where exactly is Keswick, Ontario?
PROJECT OVERVIEW
• Community of Keswick is a growing commuter hub for the Greater Toronto Area
• York Region has been expanding the Keswick Water Pollution Control Plant (WPCP) to accommodate growth
• With expansion of the WPCP came the need to expand the existing outfall
PROJECT OVERVIEW
Keswick WPCP
LEGEND
Existing Outfall Open-Cut
Microtunneling
Dredging
Cook’s Bay
DESIGN CHALLANGES
• Poor ground conditions
• Maintaining traffic flows
• Existing utilities
• Abandoned shoring
• Undercrossing with minimal cover
• Inability to obtain property
• Onshore to offshore transition
DESIGN CHALLANGES
POOR GROUND CONDITIONS
• Groundwater at/near ground surface
• Up to 20ft above tunnel obvert
• Lacustrine deposits of fine sand, silt and clay
• Mainly SPT N = 0 – 4 in the tunnel zone
• Silts and clays highly sensitive
DESIGN CHALLANGES
POOR GROUND CONDITIONS
• Added specification requirements to deal with poor ground
• Soft ground cutterhead
• Minimum length of trailing cans or restrained pipe joints
• Provisional requirement for ground improvement by jet grouting
MAINTAINING TRAFFIC FLOWS
• Key item of concern
• Alignment crossed the town’s main intersection
• “5 Corner” design
• Fire and ambulance stations
• No full closures would be permitted
DESIGN CHALLANGES
DESIGN CHALLANGES
MAINTAINING TRAFFIC FLOWS
• Located shafts outside of intersection
• Limited, partial lane closures only
• Coordinated traffic controls with nearby Fire and Ambulance stations
DESIGN CHALLANGES
EXISTING UTILITIES
• Existing outfall predated many utilities in the intersection
• Original plan was to have the new outfall parallel the existing
DESIGN CHALLANGES
EXISTING UTILITIES
• Reviewed record drawings
• Town’s main trunk sewer (30in) crossed alignment
• Sewer had been constructed using 36ft deep steel sheet pile shoring
• Shoring was abandoned in place
DESIGN CHALLANGES
EXISTING UTILITIES
• Re-routed outfall crossed under existing trunk sewer with less than 18in of cover
• Specification requirements added to protect existing trunk sewer included:
• Advance jet grout support
• Monitoring during grouting and tunneling
• Bypass pumping
• CIPP liner stocked and ready
DESIGN CHALLANGES
INABILITY TO OBTAIN PROPERTY
• If permanent easements were needed, the project would have lost it’s “Pre-Approved” environmental assessment status.
• Locally, separation between the pipe springline and property lines was on the order of 18in
• Microtunnelling was key to maintaining such tight clearances
DESIGN CHALLANGES
ONSHORE TO OFFSHORE TRANSITION
• Traditional cofferdam transition would have significant impacts to shoreline and nearshore aquatic habitat
• Permits would be difficult to obtain
• If obtained, would have onerous conditions of approval.
DESIGN CHALLANGES
ONSHORE TO OFFSHORE TRANSITION
• Design called for transition to be completed by microtunnelling
• MTBM reception to take place 330ft offshore
• MTBM received in a dredged trench
• Shoreline and nearshore habitats unaffected.
CONSTRUCTION CHALLANGES
• Curved Drives
• Wet Reception
CONSTRUCTION CHALLANGES
CURVED DRIVES
• Original design called for straight drives
• Drive length based on 30in pipe installation
4
5 6
7 8 9
ORIGINAL DESIGN
CONSTRUCTION CHALLANGES
CURVED DRIVES
• Contractor proposed curved drives as a means to eliminate two shafts
• Required upsizing from 30in to 48in pipe
REVISED DESIGN
4
6
7 9 Plan Curve Drive Rad. = 22,500ft
Spatial Curve Drive Plan Rad. = 21,650ft Profile Rad. = 2,870ft
CONSTRUCTION CHALLANGES
CURVED DRIVES
• No curved drives had been completed in Canada
• No spatial curved drives had been completed in North America
• Contractor was able to demonstrate Corporate, MTBM Operator and Surveyor experience with curves
• Analysis showed that pipe deflections would be minor
• Credit of $1 million CDN (shared between owner and contractor)
CONSTRUCTION CHALLANGES
CURVED DRIVES
• Once technical (and financial) merit had been established, Owner, Designer and Contractor collaborated to implement the change
• Revisions required to several permits/approvals
• Had to demonstrate that upsizing of pipe was done for constructability reasons, and not to add capacity
CONSTRUCTION CHALLANGES
WET RECEPTION
• Specifications gave contractor flexibility in methods
• Contractor submitted a detailed wet reception plan:
• Hydraulic power pack removed for offshore drive
• Last 30ft of pipe internally restrained with strapping
• Mechanical bulkhead installed at shaft, and water pumped through bulkhead to equalize pressure
CONSTRUCTION CHALLANGES
WET RECEPTION
• Contractor submitted a detailed wet reception plan:
• Suction dredge used to expose MTBM
• MTBM removed and a fabricated tee attached to pipe and grouted in place
LESSONS LEARNED
• Be open to change, and encourage collaboration in implementing change.
• Maintain flexibility for unique or high-risk elements
• A good contractor can make all the difference