    Pekerjaan Persiapan

     Bowplank Rp736,750 Rp736,750

    Pekerjaan Galian dan Pondasi

    Galian Tanah Rp382,500 Rp382,500

    Urgan Pasir Bawah Pondasi Rp255,000 Rp255,000

    Pasangan Pondasi batu kali Rp190,000 Rp760,000 Rp950,000

    Urugan Tanah Kembali Bekas Galian Rp165,000 Rp165,000

    Pekerjaan Beton

     Pemasangan Bekisting Sloof Pagar Rp403,500 Rp403,500

    Pemasangan Bekisting Kolom Rp403,500 Rp403,500

    Pemasangan Bekisting Ring Balok Rp403,500 Rp403,500

     Kolom Beton Pagar Rp2,940,000 Rp2,940,000

    Ring Balok Beton pagar Rp1,435,000 Rp1,505,000 Rp2,940,000

    Pekerjaan Dinding

    Pas Dinding batu bata 1:4 Rp1,285,500 Rp142,500 Rp1,428,000

    Plesteran Dinding Pagar 1:2 Rp1,924,000 Rp1,924,000

     Acian Rp1,474,500 Rp172,500 Rp1,647,000

    Cat-Catan Rp1,040,750 Rp1,557,500 Rp778,750 Rp3,377,000

    Total Rp3,603,263 Rp2,661,750 Rp7,495,500 Rp2,790,500 Rp4,581,750 Rp1,730,000 Rp778,750 Rp23,641,513

    Total5/29/16 6/5/16 6/12/16 6/19/16 6/26/16 7/3/16 7/10/16 7/17/16

    Cash Flow as of Wed 6/1/16

    pembangunan pagar tembok