Transcript of Microsoft Project - Cash Flow
-
8/16/2019 Microsoft Project - Cash Flow
1/1
Pekerjaan Persiapan
Bowplank Rp736,750 Rp736,750
Pekerjaan Galian dan Pondasi
Galian Tanah Rp382,500 Rp382,500
Urgan Pasir Bawah Pondasi Rp255,000 Rp255,000
Pasangan Pondasi batu kali Rp190,000 Rp760,000 Rp950,000
Urugan Tanah Kembali Bekas Galian Rp165,000 Rp165,000
Pekerjaan Beton
Pemasangan Bekisting Sloof Pagar Rp403,500 Rp403,500
Pemasangan Bekisting Kolom Rp403,500 Rp403,500
Pemasangan Bekisting Ring Balok Rp403,500 Rp403,500
Kolom Beton Pagar Rp2,940,000 Rp2,940,000
Ring Balok Beton pagar Rp1,435,000 Rp1,505,000 Rp2,940,000
Pekerjaan Dinding
Pas Dinding batu bata 1:4 Rp1,285,500 Rp142,500 Rp1,428,000
Plesteran Dinding Pagar 1:2 Rp1,924,000 Rp1,924,000
Acian Rp1,474,500 Rp172,500 Rp1,647,000
Cat-Catan Rp1,040,750 Rp1,557,500 Rp778,750 Rp3,377,000
Total Rp3,603,263 Rp2,661,750 Rp7,495,500 Rp2,790,500 Rp4,581,750 Rp1,730,000 Rp778,750 Rp23,641,513
Total5/29/16 6/5/16 6/12/16 6/19/16 6/26/16 7/3/16 7/10/16 7/17/16
Cash Flow as of Wed 6/1/16
pembangunan pagar tembok
Page 1