MICROSOFT PROJECT 2013 FULL TUTORIAL

211
MICROSOFT PROJECT 2013 A PRESENTATION BY: VISMAY SHAH 16014111028

Transcript of MICROSOFT PROJECT 2013 FULL TUTORIAL

Page 1: MICROSOFT PROJECT 2013 FULL TUTORIAL

MICROSOFTPROJECT

2013A PRESENTATION BY: VISMAY SHAH16014111028

Page 2: MICROSOFT PROJECT 2013 FULL TUTORIAL

Hello!I am Vismay ShahWelcome to Microsoft Project 2013 Microsoft Project (or MSP) is a project management software program.

Page 3: MICROSOFT PROJECT 2013 FULL TUTORIAL

BRIEF DETAILS OF PRESENTATIONIn this Presentation you will cover following topics.

1. INTRODUCTION TO THE SCREEN2. A PRACTICLE EXMAPLE3. DETERMINE CRITICAL TASKS4. FORMATING OF BAR5. PROJECT SUMMARY TASK6. ALL ABOUT CALENDAR IN MS

PROJECT7. EXCEPTION RECURRING AS WEEKLY,

MONTHLY, YEARLY8. ADDING NEW COLUMNS TO THE

PROJECT9. USE OF FILTER10.USE OF GROUP

11.ADD WBS TO THE PROJECT12.USE OF SWTICH FORMULA13.ADDING RESOURCES TO THE

PROJECT14.WHOLE RESOURCE SHEET15.ASSIGNING OF RESOURCES16.RESOURCE LEVLING17.RESOURCE GRAPH18.EARNED VALUE CONCEPT.19.MACRO CONCEPT.20.LETS CREATE A SWITCH (VISUAL

BASIC)21.CREATE YOUR OWN FACILIATED

MENU

Page 4: MICROSOFT PROJECT 2013 FULL TUTORIAL

LET’S HAVE AN INTRODUCTION TO THE SCREEN1

Page 5: MICROSOFT PROJECT 2013 FULL TUTORIAL

• TASK MODE can be of Two types ,

1. Manually Scheduled

2. Auto Scheduled

• TASK NAME is nothing but the activity name, For ex. Excavation, PCC, Brickwork Etc.

• DURATION is Total time taken to complete an activity.

• This will be in terms of Days.

• START is you start date of the Activity,

• It can be the Current Date or Any date of the calendar.

• FINISH is the date on/by which the activity will be completed.

• PREDECESSORS contains main 4 constraints that can decide that which activities will start together or parallel or will finish together.

• RESOURCE NAME allocates the resource and let you know which resource is being used for particular activity.

Page 6: MICROSOFT PROJECT 2013 FULL TUTORIAL

THINGS TO SET UP BEFORE USEI. OPEN THE MS PROJEC 2013.II. Before Start using it , you need to set

certain things on it for that Go to the file menu on the right hand side upper corner.

III. You will see the Last tab of OPTIONS there. Click on it

IV. A dialogue box will prompt up as shown in Image.

GO TOFILE MENU

LAST TAB“OPTIONS”

PROMPT OFDIALOGUE

BOX

Page 7: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 8: MICROSOFT PROJECT 2013 FULL TUTORIAL

“The 1st TAB you will see of General, In this particular tab You need to set the DATE & TIME Format from any of the options above but for the work Convenience go for the DAY DD-MM-YY.

GENERAL TAB

Page 9: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 10: MICROSOFT PROJECT 2013 FULL TUTORIAL

“In the next tab named Display ; You can see the currency options for this Project. Go to the Currency as shown selected in image & change it to the INR as shown in Next slide.

DISPLAY TAB

Page 11: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 12: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 13: MICROSOFT PROJECT 2013 FULL TUTORIAL

“In the Schedule Tab you can see another label named Schedule Which denoted that Shows assignment unit as a : Percentage. Change it to the “Decimal” From dropdown list.

SCHEDULE TAB

Page 14: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 15: MICROSOFT PROJECT 2013 FULL TUTORIAL

“As you can see ; MS Project takes each New Task Manually Scheduled but for the work Convenience change it to the Auto Schedule.

SCHEDULE TAB

Page 16: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 17: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 18: MICROSOFT PROJECT 2013 FULL TUTORIAL

“In MS Project , We usually work with Fix Duration and not with Fix Units. But By default MS Project take it as Fixed Unit , so we need to change it as Fixed Duration.

SCHEDULE TAB

Page 19: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 20: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 21: MICROSOFT PROJECT 2013 FULL TUTORIAL

“In MS Project , There are chances of make mistakes in entries , to overcome that we can undo them by Ctrl+Z , but there is an option in this TAB by which you can increase this Undo level , By default it is 20. I have changed it to 35.

ADVANCED TAB

Page 22: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 23: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 24: MICROSOFT PROJECT 2013 FULL TUTORIAL

TRY OUT A PRACTICAL EXMAPLE2

Page 25: MICROSOFT PROJECT 2013 FULL TUTORIAL

• Now As shown in Image Add some Activities. But you can see that Each activity starts parallel to each other but this is not possible in real time practice . For ex. Tracing of the Soil can not be started before/ parallel to Excavation so as Shuttering can not be started before/parallel to Bar Bending.

• So we need to give predecessors to the activates in the column of predecessors by just putting the row number there.

Page 26: MICROSOFT PROJECT 2013 FULL TUTORIAL

• As you can see now the bar has been shifted to after the completion of the preceding activity.

• But now we can say that if tracing is of 2 days then after the day 1 of that activity some of the work will be completed and by next day the PCC work in traced part can be started parallel to it.

• To do Such thing Just double click on the Activity of PCC & screen will be prompt following dialogue box.

Page 27: MICROSOFT PROJECT 2013 FULL TUTORIAL

• Go to the Predecessor

s Tab.

Page 28: MICROSOFT PROJECT 2013 FULL TUTORIAL

• In this tab you will find the preceding activity for PCC as Tracing .

• In that you need to change the Type of Activity to Finish to Start to Start to start. But we need to start PCC exactly after the next day so give Lag time in next column as 1day.

Page 29: MICROSOFT PROJECT 2013 FULL TUTORIAL

• After Selecting it Just Click on Ok.

Page 30: MICROSOFT PROJECT 2013 FULL TUTORIAL

• Now you can see the change in BAR as well as Predecessors.

Page 31: MICROSOFT PROJECT 2013 FULL TUTORIAL

• Similarly the activity of “BAR BENDING” has no relation with excavation, so that can be started parallel with Excavation.

• To do so remove the predecessor given.

Page 32: MICROSOFT PROJECT 2013 FULL TUTORIAL

HOW TO DETERMINE CRITICAL TASKS IN WORKING PROJECT3

Page 33: MICROSOFT PROJECT 2013 FULL TUTORIAL

• Now to highlight the critical path go to the FORMAT Menu, There you will see a option for Critical Task as shown in image.

• Now click on it.

Page 34: MICROSOFT PROJECT 2013 FULL TUTORIAL

• YOU CAN SEE THE CHANGE NOW.

Page 35: MICROSOFT PROJECT 2013 FULL TUTORIAL

FORMATING OF BAR4

Page 36: MICROSOFT PROJECT 2013 FULL TUTORIAL

• So you can see that the critical path has been highlighted by red bars.

• Now if you look at bars the only gives the duration of activity as bar , no other information can be obtained by them.

• To do that we need to Format the Bars. Just Go To

FORMAT BAR STYLEFORMATMENU

• By clicking on it you will have a dialogue box like below.

Page 37: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 38: MICROSOFT PROJECT 2013 FULL TUTORIAL

“• Go to the TEXT tab on the right side corner as

shown , you will have the things shown in next slide.

• You need to change it. SO in the TEXT Tab just change & write as following

1.Left- start 2.Right –Finish 3.Top – Name 4.Bottom – Duration.

TEXT TAB

Page 39: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 40: MICROSOFT PROJECT 2013 FULL TUTORIAL

• Now Just Click on Ok.

Page 41: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 42: MICROSOFT PROJECT 2013 FULL TUTORIAL

• In the appeared dialogue box scroll through bottom & you will find the critical name showing red bar. See the Text tab , it is blank. So we need to repeat the procedure as we did for task.

• You can see the Change now but also there is no change in critical path. So go again to ,

FORMAT BAR STYLEFORMATMENU

Page 43: MICROSOFT PROJECT 2013 FULL TUTORIAL

• After changing it as per slide no. 28 just click on OK.

Page 44: MICROSOFT PROJECT 2013 FULL TUTORIAL

• So now you can see the critical task are also changed and they are showing information like normal tasks.

Page 45: MICROSOFT PROJECT 2013 FULL TUTORIAL

HOW TO GET PROJECT SUMMARY TASK5

Page 46: MICROSOFT PROJECT 2013 FULL TUTORIAL

“• It is used to determine total summary or total

duration of entire project.

• To do the same, select the whole project data from left corner of screen & …..

PROJECT SUMMARY TASK

UPPER LEFT CORNER

DO CHECKMARK TO PROJECT

SUMMARYTASK BUTTON

FORMATMENU

Page 47: MICROSOFT PROJECT 2013 FULL TUTORIAL

• You will see something like show in next slide.

Page 48: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 49: MICROSOFT PROJECT 2013 FULL TUTORIAL

LET’S TALK ALL ABOUT CALENDAR IN MS PROJECT6

Page 50: MICROSOFT PROJECT 2013 FULL TUTORIAL

“■ Then, as You can see a dialogue box , To CREATE a new

calendar of your convince , click on “Create New Calendar…”

■ After clicking on that another dialogue box will appear , asking a name along with 2 radio buttons asking if you want to create new base calendar or Make a copy some other calendar.

■ Here I have given my own name “VISMAY” as calendar Name and Making new Base calendar.

HOW TO CREATE NEW CALENDAR CHANGE

WORKINGTIME

PROJECTMENU

Page 51: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 52: MICROSOFT PROJECT 2013 FULL TUTORIAL

“• Here as you can see the standard calendar has 2

nonworking days & the general working time is 8.00 to 17.00 am.

STANDARD CALENDAR

Page 53: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 54: MICROSOFT PROJECT 2013 FULL TUTORIAL

“• As you can see in this calendar named “ VISMAY” I

have changed the working days & working hours as well.

VISMAY CALENDAR

Page 55: MICROSOFT PROJECT 2013 FULL TUTORIAL

• TO DO so go to Work Weeks tab in Change Working Time dialogue box.

• To change the working times of each day select the days from the left side panel & click on third radio button named “Set day(s) to these specific working time”

• Now click on Details in right side.

• Initially in standard calendar it was 8.00 to 12.00 & 13.00 to 17.00. from which I have changed it to 9.30 to 13.00 & 14.00 to 18.30.

Page 56: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 57: MICROSOFT PROJECT 2013 FULL TUTORIAL

“• Also I have changed the Saturday as the

working day from Nonworking day.• But for the timings are as follows : 9.00 to

12.00 & 13.00 to 17.00.

VISMAY CALENDAR

Page 58: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 59: MICROSOFT PROJECT 2013 FULL TUTORIAL

“• As now to add holidays on working days Go To the

Exceptions TAB as shown.

• ADD THE HOLIDAYS as per the CALENDAR And you will se the day current working day will be changed to NON-WORKING DAY & shown by Underline.

VISMAY CALENDAR

Page 60: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 61: MICROSOFT PROJECT 2013 FULL TUTORIAL

“• IT WON’T WORK OR APPLY YOUR CALENDAR UNTILL

& UNLESS YOU CHANGED IT.• To do so …

VISMAY CALENDAR

PROJECTINFORMATION

PROJECTMENU

Page 62: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 63: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 64: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 65: MICROSOFT PROJECT 2013 FULL TUTORIAL

EXCEPTION RECURRING AS WEEKLY, MONTHLY, YEARLY7

Page 66: MICROSOFT PROJECT 2013 FULL TUTORIAL

YEARLY EXCEPTION

Let us take the example of 15th August that occurs as Holiday in Calendar Every Year.

So, You don’t need to add exception every year manually.

To do so 1st create the exception of Independence day for current year & double click on it.

You will have a dialogue box shown in next slide.

Page 67: MICROSOFT PROJECT 2013 FULL TUTORIAL

• As you can see this dialogue box have different facilities such as you can set time for exceptions.

• The very next label is of Recurrence Pattern. This label faciliets you that you can repeat the exception as daily/weekly/monthly/yearly.

• As we are going for the independence day it occurs yearly.

Page 68: MICROSOFT PROJECT 2013 FULL TUTORIAL

• As you can see it is asking for the date on which it needs to be repeated yearly.

• The third label is of Range of recurrence.

• Currently it is showing that it will end after 1 occurrence, let us change to 5.

Page 69: MICROSOFT PROJECT 2013 FULL TUTORIAL

• You can see that it will occur for next 5 years and will end by 15-8-2020.

Page 70: MICROSOFT PROJECT 2013 FULL TUTORIAL

• YOU CAN SEE THE CHANGE

NOW.

Page 71: MICROSOFT PROJECT 2013 FULL TUTORIAL

MONTHLY EXCEPTION

Let us take the example of a company that has 1st Saturday holiday.

To do so create an exception on any 1nd Saturday of current month & double click on it.

You will have a dialogue box shown in next slide.

In the prompted dialogue box ,go to the recurrence label click on recurrence pattern as monthly.

Page 72: MICROSOFT PROJECT 2013 FULL TUTORIAL

• It will ask recurrence time in terms of Date of particular or Day e.g. This exception should recur on 1st Saturday of each month.

• Set the recur time as The “First Saturday of Every 1 month”.

• Click on ok. You will see that exception has created on every 1st Saturday of each month.

Page 73: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 74: MICROSOFT PROJECT 2013 FULL TUTORIAL

WEEKLY EXCEPTION

Let us take the example of a company that has alternate Sunday working. E.g. 2nd & 4th Saturday will be Holiday.

To do so create an exception on any 2nd Saturday of current month & double click on it.

You will have a dialogue box shown in next slide.

In the prompted dialogue box ,go to the recurrence label click on recurrence pattern as weekly.

Page 75: MICROSOFT PROJECT 2013 FULL TUTORIAL

• It will ask recurrence time in terms of week e.g. This exception should recur after 1 week or 2 week etc.

• To set alternate , set the recur time as 2 weeks & Saturday as the day to recur in the below days.

• Click on ok. You will see that exception has created on each alternate Saturday.• Also I have changed the range of recurrence as 15.

Page 76: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 77: MICROSOFT PROJECT 2013 FULL TUTORIAL

ADDING NEW COLUMNS TO THE PROJECT8

Page 78: MICROSOFT PROJECT 2013 FULL TUTORIAL

Now , let us assume that in a Large project there are number of engineers are working to the same project & each one have different responsibilities.

To show or to keep record that who has what responsibility we need to add a new column in MSP.

But you will find that it has no in built column as responsibilities.

Page 79: MICROSOFT PROJECT 2013 FULL TUTORIAL

• You can see there is no inbuilt option such as responsibility.

• So we have to create it manually. To do so, right click on the column of “Add new Column” & go to the custom fields.

Page 80: MICROSOFT PROJECT 2013 FULL TUTORIAL

• By clicking on custom fields, you will prompt a dialogue box.

Page 81: MICROSOFT PROJECT 2013 FULL TUTORIAL

• You can see the different option to add texts e.g. text1, text2 etc.

• We rename the field as responsibility. & click on OK.

• In the next label name custom attribute you will find the button of Lookup. Basically lookup stands for entering the value for manually created field.

• After clicking on that button you will have dialogue box shown in next slide.

Page 82: MICROSOFT PROJECT 2013 FULL TUTORIAL

• It has options for adding the values as well as descriptions for it.

• I have added 3 names as responsibility consist of engineer name.

• Then click on Close.

Page 83: MICROSOFT PROJECT 2013 FULL TUTORIAL

• As you can see that it is created now.

• Lets go to the main screen & add the new created column.

Page 84: MICROSOFT PROJECT 2013 FULL TUTORIAL

• As you can see it has three values to add.

• Now let us add this for activities.

Page 85: MICROSOFT PROJECT 2013 FULL TUTORIAL

• Now , let us assume that in a project there are number of activities that has values as Billed or not.

• To show or to keep record that which activities are billed or not. We need to add a new column in MSP.

• Repeat the same procedure. Only the difference will be this time look up value will have Yes or No option

Page 86: MICROSOFT PROJECT 2013 FULL TUTORIAL

• Similarly we can show the PHASES of the project.

• Repeat the procedure , the only difference that it will have lookup values as Phase1 , Phase2 etc.

Page 87: MICROSOFT PROJECT 2013 FULL TUTORIAL

HOW TO USE FILTER TO THE PROJECT9

Page 88: MICROSOFT PROJECT 2013 FULL TUTORIAL

• As you can see there is a filter option in VIEW menu.

• The current status of filter option is “ [No Filter] ”.

Page 89: MICROSOFT PROJECT 2013 FULL TUTORIAL

• In Filter option There are many in-built filters ready to use.

• But in some case we need to filter the project as per our need or client need.

• To do so we need to create a new filter,

• For example in this project I want to see only those acivities assigned to VRAJ.

Page 90: MICROSOFT PROJECT 2013 FULL TUTORIAL

• NAME of the filter required

(Responsibility in our case)

FIELD NAME required to be filtered

TEST to be performed in filter.

• VALUES to be checked by filter.

Page 91: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 92: MICROSOFT PROJECT 2013 FULL TUTORIAL

FILTER FOR THE TEST “DOES NOT EUQAL”

• The Highlighted Part in the Image can be summarized as follows:

“ Filter the Project & show only such Activities that “Does not Equal to” (test) “ VRAJ” (value) in the field name “RESPONSIBILITY” .

• NOW JUST CLICK ON SAVE.

Page 93: MICROSOFT PROJECT 2013 FULL TUTORIAL

• As you can see that New Custom filter is now created.

• Apply it to the project & see the change in your Activity List.

Page 94: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 95: MICROSOFT PROJECT 2013 FULL TUTORIAL

FILTER FOR THE TEST “EUQAL”

• The Highlighted Part in the Image can be summarized as follows:

“ Filter the Project & show only such Activities that “ Equals to” (test) “ ISHAN” (value) in the field name “RESPONSIBILITY” .

• NOW JUST CLICK ON SAVE.

Page 96: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 97: MICROSOFT PROJECT 2013 FULL TUTORIAL

TWO LINE FILTER

• The Highlighted Part in the Image can be summarized as follows:

“ Filter the Project & show only such Activities that “ Equals to” (test) “ VRAJ” (value) in the field name “RESPONSIBILITY” OR show only such Activities that “ Does not Equal to” (test) “ NO” (value) in the field name “BILL”.

• NOW JUST CLICK ON SAVE.

Page 98: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 99: MICROSOFT PROJECT 2013 FULL TUTORIAL

HOW TO USE GROUP TO THE PROJECT10

Page 100: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 101: MICROSOFT PROJECT 2013 FULL TUTORIAL

• In Group By option There are many in-built groups ready to use.

• But in some case we need to group the project as per our need or client need.

• To do so we need to create a new group,

• For example in this project I want to group the project for those acivities which are assigned to VRAJ.

Page 102: MICROSOFT PROJECT 2013 FULL TUTORIAL

FILED NAME by which you want to create the group

FILED TYPE by which you want to create the group

Nature of ORDER either Ascending or Descending

Page 103: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 104: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 105: MICROSOFT PROJECT 2013 FULL TUTORIAL

HOW TO ADD WBS TO THE PROJECT11

Page 106: MICROSOFT PROJECT 2013 FULL TUTORIAL

WBSPROJECTMENU DEFINE CODE

PROJECT CODE PROFILE, PROJECT INITIALS LIKE AM, VS ETC.

Page 107: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 108: MICROSOFT PROJECT 2013 FULL TUTORIAL

HOW TO CHANGE ALREADY ASSIGNED RESPONSIBILTY IN CURRENT WORKING PROJECT ( USE OF SWTICH FORMULA)

12

Page 109: MICROSOFT PROJECT 2013 FULL TUTORIAL

USE OF SWITCH FORMULA

■ TO UNDERSTAND THIS CASE LET US TAKE AN CLASSIC EXAMPLE , THAT IN A WORKING PROJECT AN ENGINEER NAMED “ISHAN” IS GOING TO REPLACED BY NEW ENGINEER “KUSH”

■ IN SUCH CASE WHEN WE HAVE ALREADY ASSIGNED THE RESPONSIBILITY , NOW WE HAVE TO CHANGE ALL THE RESPONSIBILITY ASSIGNED TO ISHAN TO KUSH.

Page 110: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 111: MICROSOFT PROJECT 2013 FULL TUTORIAL

• NOW FIRST ADD A NEW COLUMN NAMED “NEW RESPONSIBILITY”.

Page 112: MICROSOFT PROJECT 2013 FULL TUTORIAL

• AS YOU CAN SEE THAT NOW A NEW COLUMN IS CREATED.

• DO NOTE THAT WE ARE NOT GOING TO ADD NEW LOOK UP VALUES THIS TIME.

Page 113: MICROSOFT PROJECT 2013 FULL TUTORIAL

• GO TO THE FORMULA BUTTON IN THE CUSTOM FILED.

• YOU WILL SEE SOMETHING LIKE AS SHOWN IN NEXT SLIDE.

Page 114: MICROSOFT PROJECT 2013 FULL TUTORIAL

• THIS IS THE DIALOUGE BOX FOR FORMULA.

Page 115: MICROSOFT PROJECT 2013 FULL TUTORIAL

FUNCTION

GENERAL

SWITCH FORMULA

Page 116: MICROSOFT PROJECT 2013 FULL TUTORIAL

• YOU CAN SEE NOW THAT WE HAVE ADDED THE FORMULA TO OUR NEW FLIED

Page 117: MICROSOFT PROJECT 2013 FULL TUTORIAL

• NAME OF THE FIELD WHERE CHANGE IS REQUIRED

• BY WHAT VALUE YOU NEED TO CHANGE THAT FUNCTION

Page 118: MICROSOFT PROJECT 2013 FULL TUTORIAL

• NOW TO ADD THE FILED NAME WHICH REQUIRES CHANGES GO TO

FIELD TEXT

CUSTOM TEXT

RESPONSIBILTY

Page 119: MICROSOFT PROJECT 2013 FULL TUTORIAL

• AS YOU CAN SEE NOW THAT RESPONSIBILTY FIELD IS ADDED.

• NOW ADD ‘=‘ RIGHT AFTER THE SQAURE BRACET IS COMPLETED.

• AND JUST AFTER THAT INSERT THE ORIGINAL VALUE, i.e. “ISHAN”

• NOW PUT ‘,’ & INSERT THE NEW VALUE, i.e. “KUSH”

Page 120: MICROSOFT PROJECT 2013 FULL TUTORIAL

• UP TO THIS COMMAND WE HAVE CHANGED RESPONSIBILITY OF ISHAN TO KUSH BUT WHAT ABOUT OTHERS?

• WE ARE NOT CHANGING THEM , SO WE NEED TO ADD THAT TOO.

• TO DO SO FOLLOW NEXT SLIDE.

Page 121: MICROSOFT PROJECT 2013 FULL TUTORIAL

• JUST CLICK ON OK.

Page 122: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 123: MICROSOFT PROJECT 2013 FULL TUTORIAL

• SEE THAT NOW THE RESPONSIBILITY HAS CHANGED FOR ISHAN TO KUSH BUT NOT FOR VISMAY.

Page 124: MICROSOFT PROJECT 2013 FULL TUTORIAL

ADDING RESOURCES TO THE PROJECT13

Page 125: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 126: MICROSOFT PROJECT 2013 FULL TUTORIAL

NAME OF THE RESOURCESFOR EX. MASON, MISTRY,RMCCEMENT, SAND ETC.

TYPE OF RESOURCE FOR EX. WORK, MATERIAL OR COST

WHAT TYPE OF QUANTITY YOU USE FOR RESOURCE FOR EX. CUBIC MT. , CUBIC FT., KG ETC.

INITIALS OF RESOURCE NAME FOR EX. “L FOR LABOUR”

MAXIMUM UNITS WHICH CAN BE USED FOR RESOURCE.

STANDARD RATE OF RESOURCE IN PER DAY OR PER HOUR UNITS.

Page 127: MICROSOFT PROJECT 2013 FULL TUTORIAL

RESOURCE TYPE : WORK

• BASICALLY WORK TYPE RESOURCES INCLUDES ONLY THOSE RESOURCES WHICH ARE BEING USED FOR SPECIFIC WORK/TASK SUCH AS JCB,VIBRATORS, MACHINE MIXER, TRACTORS, DUMPERS ETC.

• HERE IN THIS CASE I HAVE ADDED JCB RESOURCE WITH ITS MAXIMUM UNITS AS 2 & STANDARD RATE AS “700RS/DAY.”

• YOU CAN ADD MANY RESOURCE OF WORK TYPE AS SHOWN IN NEXT SLIDE.

Page 128: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 129: MICROSOFT PROJECT 2013 FULL TUTORIAL

RESOURCE TYPE : MATERIAL

• BASICALLY MATERIAL TYPE RESOURCES INCLUDES ONLY THOSE RESOURCES WHICH ARE BEING USED FOR SPECIFIC WORK/TASK SUCH AS JCB,VIBRATORS, MACHINE MIXER, TRACTORS, DUMPERS ETC.

• HERE IN THIS CASE I HAVE ADDED RMC RESOURCE WITH ITS UNITS AS M3[METERE CUBE] & STANDARD RATE AS “3200RS.”

• IN COMPARE OF WORK TYPE RESOURCES , THE MATERIAL TYPE RESOURCES DOESN’T CONTAIN ANY MAX. UNITS [ IT IS ASSUMED THAT YOU CAN USE AS MUCH AS YOU CAN]

• YOU CAN ADD MANY RESOURCE OF MATERIAL TYPE AS SHOWN IN NEXT SLIDE.

Page 130: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 131: MICROSOFT PROJECT 2013 FULL TUTORIAL

RESOURCE TYPE : COST

• BASICALLY COST TYPE RESOURCES INCLUDES ONLY THOSE RESOURCES WHICH ARE BEING USED ON SOME SPECIFIC COST SUCH AS CONTAINER, MUSTER , LEVEL TUBE , GLOVES & SHOES ETC.

• HERE IN THIS CASE I HAVE ADDED MUSTER RESOURCE WITHOUT ADDING ANYTHING.

• YOU CAN ADD MANY RESOURCE OF MATERIAL TYPE AS SHOWN IN NEXT SLIDE.

YOU CAN’T ADD COST TO THIS TYPE OF RESOURCE

Page 132: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 133: MICROSOFT PROJECT 2013 FULL TUTORIAL

WHOLE RESOURCE SHEET14

Page 134: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 135: MICROSOFT PROJECT 2013 FULL TUTORIAL

• NOW WHEN YOU ARE WORKING WITH 2 OR MORE PROJECT , YOU DON’T NEED TO CREATE RESOURCE SHEET EVERYTIME.

• MICROSOFT PROJECT GIVES US A FACILTY NAMED “RESOURCE PULLING” BY WHICH WE CAN PULL THE WHOLE RESOURCE SHEET TO ANOTHER PROJECT FILE.

• LET’S SEE THE PROCEDURE OF IT.

Page 136: MICROSOFT PROJECT 2013 FULL TUTORIAL

STEP 1: CREATE A NEW FILE ( I AM TAKING A BLANK FILE JUST FOR UNDERSTANDING PURPOSE)

STEP 2: GO TO THE RESOURCE MENU , THERE YOU WILL FIND AN OPTION NAME RESOURCE POOL , IN THAT OPTION YOU WILL FIND ANOTHER OPTION SHARE RESOURCE.

STEP 3: CLICK ON IT.

STEP 4: A DIALOUGE BOX WILL APPEAR AS SHOWN IN NEXT SLIDE.

Page 137: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 138: MICROSOFT PROJECT 2013 FULL TUTORIAL

• JUST CLICK ON OK.

• AND NOW CHECK IN IN NEW PROJECT FILE’S RESOURCE SHEET , EVERY RESOURCE IS COPIED OR YOU CAN SAY PULLED FROM THE OLD FILE.

Page 139: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 140: MICROSOFT PROJECT 2013 FULL TUTORIAL

ASSIGNING OF RESOURCES15

Page 141: MICROSOFT PROJECT 2013 FULL TUTORIAL

STEP 1: GO TO THE GANTT CHART VIEW

Page 142: MICROSOFT PROJECT 2013 FULL TUTORIAL

STEP 2: ADD NEW COLUMN OF RESOURCE NAME

Page 143: MICROSOFT PROJECT 2013 FULL TUTORIAL

YOU CAN SEE THE LIST OF RESOURCES WHICH YOU HAVE ADDED IN RESOUECE SHEET

Page 144: MICROSOFT PROJECT 2013 FULL TUTORIAL

STEP 3: ASSIGN RESOURCE TO THE ACTIVITIES BY CHECKING THE BOX AHEAD OF THEM

Page 145: MICROSOFT PROJECT 2013 FULL TUTORIAL

• IT MAY HAPPEN THAT ANY ACTIVITY CONTAINS MORE THAN 1 RESOURCE , SO YOU CAN ADD MULTIPLE RESOURCE TO ONE ACTIVITY.

SEE HERE I HAVE ADDED JCB & LABOUR TO THE EXCAVATION ACTIVITY.

Page 146: MICROSOFT PROJECT 2013 FULL TUTORIAL

IT MAY HAPPEN THAT ANY ACTIVITY CONTAINS MORE THAN 1 UNIT OF A RESOURCE , SO TO INCREASE UNITS OF A PARTICULAR RESOURCES , DOUBLE CLICK ON THE ACTIVITY.

• YOU WILL HAVE A DIALOUGE BOX AS ABOVE.

• GO TO THE RESOURCE TAB NOW.

Page 147: MICROSOFT PROJECT 2013 FULL TUTORIAL

GO TO THE UNITS COLUMN AND CHANGE AS PER YOUR REQUIREMENTS

Page 148: MICROSOFT PROJECT 2013 FULL TUTORIAL

NOW CLICK ON OK.

Page 149: MICROSOFT PROJECT 2013 FULL TUTORIAL

SEE NOW REINFORCEMENT ACTIVITY HAS 2 RESOURCES WITH MORE THAN 1 UNIT.

Page 150: MICROSOFT PROJECT 2013 FULL TUTORIAL

THE EARLIER PROCEDURE IS LITTLE DIFFUCLUT & TEDIOUS , SO WE HAVE AN ALTERNATE OF IT. GO TO

TASK

GANTT CHART

MORE VIEWS

Page 151: MICROSOFT PROJECT 2013 FULL TUTORIAL

YOU WILL HAVE DIALOUGE BOX LIKE THIS. NOW SELECT “TASK DETAILS FORM”

Page 152: MICROSOFT PROJECT 2013 FULL TUTORIAL

BY SELECTING “TASK DETAILS FORM” YOU WILL HAVE A SCREEN LIKE THIS.

Page 153: MICROSOFT PROJECT 2013 FULL TUTORIAL

TASK DETAILS FORM WILL SHOW YOU ONE ACTIVITY AT TIME WITH FOLLOWING DETAILS

1. NAME2. DURATION3. START4. FINISH5. CONSTRAINT6. TASK TYPE7. WBS CODE8. % COMPLETE

& LAST BUT NOT THE LEAST YOU CAN ADD RESOURCE EASILY.

Page 154: MICROSOFT PROJECT 2013 FULL TUTORIAL

RESOURCE LEVLING16

Page 155: MICROSOFT PROJECT 2013 FULL TUTORIAL

LET US TAKE FOLLOWING EXAMPLE IN ORDER TO UNDERSTAND RESOURCE LEVELINGACTIVITY DURATION MASONS LABOURS

1-2 (A) 2 1 2

2-3 (B) 3 2 2

2-4 (C) 4 3 2

2-5 (D) 2 1 3

3-10 ( E) 4 2 2

4-6 (F) 2 3 2

4-7 (G) 4 3 3

5-9 (H) 4 5 3

6-8 (I) 2 1 2

7-9 (J) 5 1 3

8-9 (K) 3 0 4

9-11 (L) 2 1 1

10-11 (M) 3 1 2

11-12 (N) 2 1 2

Page 156: MICROSOFT PROJECT 2013 FULL TUTORIAL

I HAVE DRAFTED & ALLOCATED THE RESOURCES IN NEW MSP FILE.

Page 157: MICROSOFT PROJECT 2013 FULL TUTORIAL

BY THE CONVENTIONAL METHOD YOU KNOW THAT 13 & 10 IS THE MAXIMUM UNIT FOR MASON & LABOUR RESPECTIVELY.

SO YOU CAN SEE AS PER THE ALLOCATION IT IS HIGHLIGHTED BY RED, THAT MEANS YOU NEED TO BALANCE IT.

Page 158: MICROSOFT PROJECT 2013 FULL TUTORIAL

THIS IS THE SIGN OF OVERALLOCATION

Page 159: MICROSOFT PROJECT 2013 FULL TUTORIAL

RESOURCE GRAPH17

Page 160: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 161: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 162: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 163: MICROSOFT PROJECT 2013 FULL TUTORIAL

TO LEVEL THE RESOURCES GO TO

CLICK ON LEVEL ALL & THEN OK.

Page 164: MICROSOFT PROJECT 2013 FULL TUTORIAL

SEE ALMOST EACH ACIVITY IS LEVELED NOW. THAT RED HEAD ARE GONE FROM MOST OF THE ACTIVITY.

Page 165: MICROSOFT PROJECT 2013 FULL TUTORIAL

BY THIS OPTION YOU CAN CLEAR THE LEVELING FROM THE ENTIRE PROJECT.

Page 166: MICROSOFT PROJECT 2013 FULL TUTORIAL

EARNED VALUE CONCEPT.18

Page 167: MICROSOFT PROJECT 2013 FULL TUTORIAL

LET US TAKE AN EXAMPLE THAT WE ARE WORKING ON THE PROJECT WHICH IS ABOUT 80,000RS IN TOTAL COST.

BY THE TIME OF INITAIL SCHEDULING WE FOUND THAT COST OF 1ST DAY IS 8000 , COST OF 2ND DAY IS 16000, BUT ON THE THIRD DAY RAIN OCCURRED & NO WORK HAPPENED.

LET , RS24000=Budgeted cost for work schedule (BCWS)

The value of work done = 0.25 * planning cost = 20000Rs (this is called BCWP – Budgeted cost for work performance) Actual work done, on site = 22000Rs. (ACWP Actual cost for work progress)

Page 168: MICROSOFT PROJECT 2013 FULL TUTORIAL

Cost performance index (CPI) = BCWP / ACWP = 20000/22000 = 0.90 If CPI. = 1 – On schedule>1 under the Budget<1 Over the Budget

FORECAST COST = Planning cost / CPI = 80000/0.90 = 88000Rs.

SPI = Schedule Performance index = BCWP/ BCWS = 20000/24000 = 0.83If SPI =1 on schedule >1 Ahead the Schedule <1 Behind the schedule FORECAST DURATION = Planned duration/ SPI = 10/0.83 = 12Days

Page 169: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 170: MICROSOFT PROJECT 2013 FULL TUTORIAL

NOW SET A BASE LINE TO THE PROJECT , FOR THAT GO TO PROJECT

MENUSET

BASE LINESET

BASE LINE

& YOU WILL HAVE SCREEN AS SHOWN IN NEXT SLIDE.

Page 171: MICROSOFT PROJECT 2013 FULL TUTORIAL

CLICK ON OK & HENCE A BASE LINE OF THE PROJECT IS SET UP.

Page 172: MICROSOFT PROJECT 2013 FULL TUTORIAL

NOW GO TO

PROJECT MENU

PROJECTINFORMATION

Page 173: MICROSOFT PROJECT 2013 FULL TUTORIAL

TO HAVE THE IDEA THAT WE ARE OVER BUDGET OR UNDER BUDGET , WE NEED TO SET A STATUS DATE ON WHICH WE NEED THE EARNED VALUE DATA.

I HAVE SELECTED 28TH NOV. (3RD DAY FROM THE STARTING DATE OF THE PROJECT.)

Page 174: MICROSOFT PROJECT 2013 FULL TUTORIAL

TO SEE THE TABLE OF EARN VALUE GO AS SHOWN IN FIGURE.

Page 175: MICROSOFT PROJECT 2013 FULL TUTORIAL

SELECT THE “EARNED VALUE COST INDICATORS” TABLE

Page 176: MICROSOFT PROJECT 2013 FULL TUTORIAL

YOU WILL HAVE A SCREEN LIKE ABOVE IMAGE.

NOW ADD 2 NEW COLUMN TO IT “ACTUAL COST” & “% COMPLETE.”

CHANGE THE VALUE OF THEM AS “22,000RS & 25%” RESPECTIVELY.

Page 177: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 178: MICROSOFT PROJECT 2013 FULL TUTORIAL

YOU CAN SEE THE VALUES OF CPI & SPI.

Page 179: MICROSOFT PROJECT 2013 FULL TUTORIAL

MACRO CONCEPT.19

Page 180: MICROSOFT PROJECT 2013 FULL TUTORIAL

TO GO THE MACROS

VIEW MACROS

Page 181: MICROSOFT PROJECT 2013 FULL TUTORIAL

TO RECORD A MACRO.

VIEW MACROS RECORDMACRO

Page 182: MICROSOFT PROJECT 2013 FULL TUTORIAL

HERE IN THIS CASE I AM RECORDING A MACRO FOR SHOWING CRITICAL ACTIVITY.

STEP1 : START RECORDING A MACRO.STEP 2: RENAME THE MACRO AS “CRITICAL”

STEP 3: CLICK ON OK.

STEP 4: NOW GO TO FORMAT MENU & CLCIK ON CRITICAL PATH.

STEP 5: AGAIN GO TO VIEW MENU & STOP THE MACRO.

Page 183: MICROSOFT PROJECT 2013 FULL TUTORIAL

“HENCE MACROS CAN BE SUMMRIESED AS A RECORED THING/SCRIPT WHICH WE NEED TO PERFORM REPETETIVE IN A PROJECT.

SO MACRO WILL WORK LIKE , YOU RECORD IT THE WHOLE SEQUENCE 1ST TIME NOW FOR THE 2ND OR 3RD TIME JUST RUN THE MACRO INSTEAD OF DOING WHOLE PROCEDURE AGAIN

Page 184: MICROSOFT PROJECT 2013 FULL TUTORIAL

NOW TO RUN THAT RECORED MACRO

VIEW MACROS VIEWMACRO

SELECT THE MACRO & CLICK ON RUN.

Page 185: MICROSOFT PROJECT 2013 FULL TUTORIAL

ONLY CRITICAL ACTIVITIES ARE SHOWN AFTER RUNNING THE MACRO.

Page 186: MICROSOFT PROJECT 2013 FULL TUTORIAL

SELECT THE NON-CRITICAL MACRO & CLICK ON RUN.

Page 187: MICROSOFT PROJECT 2013 FULL TUTORIAL

SEE , CRITICAL & NON CRITICAL ACTIVITIES ARE TOGETHER NOW.

Page 188: MICROSOFT PROJECT 2013 FULL TUTORIAL

LETS CREATE A SWITCH (VISUAL BASIC)20

Page 189: MICROSOFT PROJECT 2013 FULL TUTORIAL

SWITCH IS BASICALLY NOTHING BUT A VISUAL AID ADDED TO THE PROJECT. IT SERVES AS FACILITY TO THE PLANNER.

IT WORKS ABSOLUTE FUNDAMENTALS OF MACROS, BUT WHEN WE DON’T NEED TO REPEAT THOSE STEP, SWITCH HELPS US TO PUT THEM TOGETHER & BY THE TIME WE JUST NEED TO CLICK THE SWITCH TO PERFORM PARTICULAR TASK.

IN THIS CASE I AM CREATING THE SWITCH FOR THE CRITICAL & NON CRITICAL COMMAND.

Page 190: MICROSOFT PROJECT 2013 FULL TUTORIAL

NOW TO ADD A VISUAL AID TO THE PROJECT GO TO

VIEW MACROS VISUAL BASIC

AFTER CLICKING ON IT YOU WILL PROMPT A TOTALLY NEW SCREEN AS SHOWN IN NEXT SLIDE.

Page 191: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 192: MICROSOFT PROJECT 2013 FULL TUTORIAL

NOW IN THAT SCREEN GO TO INSERT

USERFORM

AFTER THIS YOU WILL HAVE A SCREEN AS SHOWN IN NEXT SLIDE.

Page 193: MICROSOFT PROJECT 2013 FULL TUTORIAL

NOW INSERT A SWITCH FROM TOOL BOX.

Page 194: MICROSOFT PROJECT 2013 FULL TUTORIAL

RENAME THIS COMMAND BUTTON AS CRITICAL

Page 195: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 196: MICROSOFT PROJECT 2013 FULL TUTORIAL

ADD ANOTHER SWITCH NAMED AS “ NON CRITICAL”

THIS IS HOW WE JUST CREATE THE SWITCH, FOR FUNCTIONING OF THIS SWITCHES WE NEED SOME COMMAND & TO DO SPO, FOLLOW THE NEXT SLIDE.

Page 197: MICROSOFT PROJECT 2013 FULL TUTORIAL

VIEW MACROS VIEW MACROS

EDIT OPTION

AFTER CLICKING ON EDIT , YOU WILL HAVE A SCREEN AS SHOWN IN NEXT SLIDE.

Page 198: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 199: MICROSOFT PROJECT 2013 FULL TUTORIAL

COPY THE HIGHLIGHTED COMMAND.

NOW PASTE THIS COMMAND IN “CRITICAL SWITCH” BY DOUBLE CLICKING ON IT.

Page 200: MICROSOFT PROJECT 2013 FULL TUTORIAL

BEFORE

AFTER

NOW DO THE SAME PROCEDURE FOR NON-CRITICAL SWITCH

Page 201: MICROSOFT PROJECT 2013 FULL TUTORIAL

NOW TO RUN THE SWITCH, GO TO RUN MENU & THEN RUN OPTION, AFTER CLICKING ON IT YOU WILL HAVE A SCREEN AS SHOWN IN NEXT SLIDE.

Page 202: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 203: MICROSOFT PROJECT 2013 FULL TUTORIAL

YOU CAN SEE THAT 2 SWITCHES ARE PROMPTED TO OUR MSP SCREEN & BY CLICKING ON IT, WE CAN FIND THE CRITICAL & NON-CRITICAL TASK DIRECTLYA

Page 204: MICROSOFT PROJECT 2013 FULL TUTORIAL

CREATE YOUR OWN FACILIATED MENU21

Page 205: MICROSOFT PROJECT 2013 FULL TUTORIAL

MICROSOFT PROJECT PROVIDE US THE FACILITY TO CREATE A MENU LIKE PROJECT , VIEW ,TASK, WHICH HAS OUR OWN USEFUL FUNCTIONS IN IT.

TO DO SO GO TO THE TASK MENU & ON THE VERY LEFT SIDE OF IT, YOU WILL FIND A BLANK PART.

YES! RIGHT CLICK ON THAT BLANK PART & SELECT THE SECOND LAST OPTION.

Page 206: MICROSOFT PROJECT 2013 FULL TUTORIAL

YOU WILL HAVE DIALOUGE BOX LIKE THIS IN WHICH AT BOTTOM PART YOU CAN ADD YOUR NEW TAB.

JUST CLICK ON IT & THEN CLICK ON RENAME BUTTON.

YOU CAN SEE THAT YOUR REQUIRED TAB IS CREATED NOW AS SHOWN IN NEXT SLIDE.

Page 207: MICROSOFT PROJECT 2013 FULL TUTORIAL
Page 208: MICROSOFT PROJECT 2013 FULL TUTORIAL

NOW FROM THE LIST OF POPULAR COMMANDS YOU CAN ADD YOUR DESIRED COMMANDS.

I HAVE ADDED 1. CUT2. INFORMATION3. SAVE4. STATUS DATE

Page 209: MICROSOFT PROJECT 2013 FULL TUTORIAL

JUST CLICK ON OK

Page 210: MICROSOFT PROJECT 2013 FULL TUTORIAL

DONE!!

Page 211: MICROSOFT PROJECT 2013 FULL TUTORIAL

Thanks!Any questions?You can find me at■ Fb.me/vismay30■ [email protected]