RT55 Micro Trench03/02/2010
427 Feet Cut
1.25” Wide x 12” Deep
4”– 6” AC over Class 2 Base Rock
Start Time: 8:15am
Finish Time: 10:45pm
![Page 2: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/2.jpg)
RT55 Micro Trench
Start & Finish Times
Include waiting for 350 gallon capacity vacuum to return,
average 45 minutes down time, waiting, each day.
![Page 3: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/3.jpg)
![Page 4: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/4.jpg)
![Page 5: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/5.jpg)
![Page 6: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/6.jpg)
![Page 7: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/7.jpg)
![Page 8: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/8.jpg)
![Page 9: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/9.jpg)
![Page 10: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/10.jpg)
![Page 11: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/11.jpg)
RT55 Micro Trench
03/03/2010
583 Feet Cut “Clean”
1.25” Wide x 12” Deep
4”– 6” AC over Class 2 Base Rock
Start Time: 8:37am
Finish Time: 10:43am
![Page 12: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/12.jpg)
![Page 13: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/13.jpg)
![Page 14: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/14.jpg)
![Page 15: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/15.jpg)
![Page 16: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/16.jpg)
![Page 17: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/17.jpg)
![Page 18: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/18.jpg)
![Page 19: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/19.jpg)
![Page 20: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/20.jpg)
![Page 21: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/21.jpg)
![Page 22: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/22.jpg)
![Page 23: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/23.jpg)
![Page 24: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/24.jpg)
![Page 25: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/25.jpg)
RT55 Micro Trench
03/04/2010
538 Feet Cut “Clean”
1.25” Wide x 12” Deep
4”– 6” AC over Class 2 Base Rock
Start Time: 8:45AM
Finish Time: 10:15AM
![Page 26: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/26.jpg)
![Page 27: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/27.jpg)
![Page 28: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/28.jpg)
![Page 29: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/29.jpg)
![Page 30: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/30.jpg)
![Page 31: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/31.jpg)
![Page 32: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/32.jpg)
![Page 33: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/33.jpg)
![Page 34: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/34.jpg)
![Page 35: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/35.jpg)
![Page 36: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/36.jpg)
![Page 37: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/37.jpg)
![Page 38: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/38.jpg)
![Page 39: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/39.jpg)
![Page 40: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/40.jpg)
![Page 41: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/41.jpg)
![Page 42: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/42.jpg)
![Page 43: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/43.jpg)
![Page 44: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/44.jpg)
RT55 Micro Trench Summary
1,548 Feet Cut “Clean”
1.25” Wide x 12” Deep
4”– 6” AC over Class 2 Base Rock
Total “Cutting” Time:
4 hours 15 minutes
6.07 feet per minute
![Page 45: Micro Trenching In Long Beach](https://reader035.fdocuments.in/reader035/viewer/2022062514/559647201a28ab78368b4764/html5/thumbnails/45.jpg)
RT55 Micro Trench Summary
RT55 easily averaged 6 + feet per minute in solid 5-6 inches of asphalt. All cutting was 100% “dry” cut. Trench was 99% clean to 12” depth. FX60-800 gallon cyclonic vacuum would increase productivity. 1.25 inch conical bit blade used. Standard slurry backfill of 2-sack slurry. Almost no labor necessary to clean surface roadway post cut. No dust control necessary, vacuum eliminates all airborne particles. All photos are when machine is operating. Attachment is “quick change” wheel, taking less than 3 minutes to change. Next generation attachment available April 1st, will have:
● Adjustable depth in one inch increments.● Fully hydraulic traversing.
Airless tires will be added to production RT55 for micro-trenching.