![Page 1: Michael Petterson Vice President Finance & Treasury Status of Open Audit Points Finance &Audit Committee Meeting July 16, 2012.](https://reader036.fdocuments.in/reader036/viewer/2022082711/56649f205503460f94c391c0/html5/thumbnails/1.jpg)
Michael PettersonVice President Finance & Treasury
Status of Open Audit Points
Finance &Audit Committee MeetingJuly 16, 2012
![Page 2: Michael Petterson Vice President Finance & Treasury Status of Open Audit Points Finance &Audit Committee Meeting July 16, 2012.](https://reader036.fdocuments.in/reader036/viewer/2022082711/56649f205503460f94c391c0/html5/thumbnails/2.jpg)
2 ERCOT PublicJuly 16, 2012
All audit points expected to be complete by 10/31/12
Committee Brief ICMP: Status of Open Audit Points
Totals
![Page 3: Michael Petterson Vice President Finance & Treasury Status of Open Audit Points Finance &Audit Committee Meeting July 16, 2012.](https://reader036.fdocuments.in/reader036/viewer/2022082711/56649f205503460f94c391c0/html5/thumbnails/3.jpg)
3 ERCOT PublicJuly 16, 2012
Audits Completed(last 3 months)
Internal Audits• Congestion Revenue Rights
Processes• Annual Report on Fraud
Prevention, Monitoring and Testing
• Identity Management System
• Audit of Shared Drives• Review of Vendors for
Compliance with Contract Terms and Conditions
• Accounts Payable• Protocol 1.4 – Confidentiality
Compliance Audit• Consulting on ERCOT’s
Vulnerability Assessments
External Audits• 2011 Financial Audit (Ernst
& Young, LLP)• DoE Grant OMB A-133 audit
(Ernst and Young)
Audits in Progress
Internal Audits• Change Control / Release
Management• Cash and Investments• Audit of Critical Spreadsheets• Review of the Capacity, Demand,
and Reserves (CDR) Report and the Seasonal Assessment of Resources Adequacy (SARA) Report
• Consulting on ERCOT’s Federal Visa and Permanent Residency Program for Foreign Nationals
External Audits• Nodal Program Audit (Navigant
Consulting, LLC)• 2012 Type 2 SSAE16 Audit
(BrightLine CPAs & Associates, Inc.)
Planned Audits(next 3 months)
Internal Audits• Business Continuity Plan &
Disaster Recovery Plan• Nodal Protocol 3.10(5) –
Consistent Information in Operations Models
• Credit Quality Assessment• Annual Corporate Controls
Testing Summary• Audit of Project
Prioritization• Annual Employee and
Contractor Ethics Compliance
• Audit of Renewable Energy Credits (REC) Program Processes and Controls
External Audits• None
Committee Brief: ICMP – Audits
![Page 4: Michael Petterson Vice President Finance & Treasury Status of Open Audit Points Finance &Audit Committee Meeting July 16, 2012.](https://reader036.fdocuments.in/reader036/viewer/2022082711/56649f205503460f94c391c0/html5/thumbnails/4.jpg)
4 ERCOT PublicJuly 16, 2012
Committee Brief: ICMP – Security Assessments
Consultation/Analysis Reports Completed
(last 3 months)
Assessments• None
Open Consultation/ Analysis Reviews
(in progress)
Assessments• None
Planned Consultation/ Analysis Reviews
(next 3 months)
Assessments• None