Michael Abbondante Construction Management
-
Upload
merritt-davidson -
Category
Documents
-
view
20 -
download
0
description
Transcript of Michael Abbondante Construction Management
Michael AbbondanteConstruction Management
Michael Abbondante
Construction Management
Presentation Outline
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Question & Answer
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
PROJECT OVERVIEW
Name:American Speech Language – Hearing National Headquarters
Location:Rockville, MD
Function:Office Space
Size:137,000 sq. ft.
Stories:5 Stories above grade; 7 Total stories
Construction Dates:July 1, 2006 – October 15, 2007
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
PROJECT OVERVIEW
Project Team
Owner:American Speech Language – Hearing Association
Construction Manager:Davis Construction
Development Team:AtSite Construction
Building Architect:Boggs and Partners Architecture
Structural Engineer:Cagley and Associates
MEP Engineer:Vanderweil Engineers
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
PROJECT OVERVIEW
Relevant Background Information
Sustainability Rating:LEED Silver Rating: 33 – 38 Points
Procurement Method:Traditional: Design – Bid – Build
Architectural Façade:
• Three types of pre-caste concrete walls with metal panels• Glass Curtain wall using seven different types
Mechanical System:• (2) 200 ton chillers with condenser and evaporator• (2) Cooling Towers• Four assorted sized Air Handling Units
Structural System:• Slab on Grade with C.I.P. Piers, foundation walls, grade beams• Structural steel columns used above grade
Sustainability Systems
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Sustainability Systems
Problem:
• Lack of one standard sustainable building rating system
• Multiple rating systems used for different reasons
• Which system is most progressive for the future of sustainability
Research:
• Analysis and comparison of LEED and Green Globes
• Industry surveys of owners and contractors on each
• ASHA LEED point and Green Globes Point Comparison
• University of Minnesota’s courthouse case study analysis
Goals:• Determine rating system aligned with owner’s goals• Determine most progressive system to be used in the future
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Sustainability Systems
LEED Analysis
Certification:
• 26 – 69 Points
• 4 Levels:• Certification• Silver• Gold • Platinum
• Scored on:• Sustainable Sites• Water Efficiency• Energy and Atmosphere• Materials and Resources• Indoor Environmental Quality• Innovation and Design Process
• Most widely used system
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Sustainability Systems
Green Globes Analysis
Certification:
• 350 – 1000 Points
• 4 Levels:• 1 Globe• 2 Globes• 3 Globes • 4 Globes
• Scored on:• Project Management: Policies and Practices• Site• Energy• Water• Resources, Building Materials, & Solid Wastes• Emissions and Effluents• Indoor Environment
• Distribution began in 2004 by the GBI
• ANSI accreditation in 2005
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Sustainability Systems
LEED & Green Globes Comparison
80% of Green Globes represented in LEED
85% of LEED represented in Green Globes
LEED:• Popularity in industry due to history• System developed by Consensus of those in the USGBC• Vast knowledge of point system required creating a “complexity label” to the system• Points scored solely on completion of project• Can be expensive
Green Globes:• New system introduced to the U.S. in 2004• ANSI accredited in 2005• Online system that is considered “simple”• Points awarded for not only completion but also design
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Sustainability Systems
Industry Surveys
Interviews of Owners & General Contractors
• LEED most popular system between both• Most common in industry• Wishing to remain competitive• Many GC’s have LEED certified individuals• Complexity of rating still a concern
• Green Globes not well known• Not widely used• Worries of staying power of Green Globes• Simplicity and cost peaked interests
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Sustainability Systems
ASHA Analysis
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Sustainability Systems
ASHA Analysis
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Sustainability Systems
University of Minnesota Case Study
• LEED focuses primarily on Materials
• Green Globes also focuses on “durability” of materials
• Green Globes focuses on Energy
• No Management or Emission Effluents for LEED scorecard
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Sustainability Systems
Conclusion
• LEED currently controls sustainability due to popularity
• Green Globes presents more points as well as a simpler system
• Green Globes may allow for higher scores and ratings while being the only ANSI accredited system
Procurement Methods
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Procurement Methods
Problem:
• The industry’s lack of progression involving procurement
• Lack of knowledge and potential savings of Design - Build
• Which projects could greatly benefit from Design - Build
Research:
• Analysis and comparison of Design – Bid – Build and Design – Build methods
• Industry surveys of owners and contractors on each
Goals:• Determine procurement method aligned with owner’s goals
• Will Design – Build make a strong influence in the future?
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Procurement Methods
Traditional & Design – Build Comparison
Traditional:• Most commonly used system• Allows owner involvement in design• Separates all aspects of construction• Simplifies bid awarding• Easily understood
Design - Build:• Allows GC to become involved in the design phase• Can allow for less change orders and mistakes during construction• Hurries schedule• Owners feel a loss of control in design phase
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Procurement Methods
Traditional & Design – Case Study Comparison
Construction Management Fundamentals by Richard Mayo:• Low Bid regulations are firmly entrenched in most government systems for the purpose of promoting fairness• It is easy to justify the selection of a low bidder• Contractors understand the system• There is always resistance to change
DBIA Project Analysis:• Savings in unit cost of at least 6.1%• Construction speed at least 12% faster• Overall project delivery at least 35.5% faster• Cost growth at least 3.5% less• Schedule growth at least 11.4% less• Quality equal or better
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Sustainability Systems
Industry Surveys
Interviews of Owners & General Contractors• Owners
• Prefer the traditional method• Owners wish to have an impact on design• Understanding by all parties involved• Government Restrictions• Lack of confidence in Design – Build Savings3• Belief Design – Build allows for GC mark up
• General Contractors• Prefer Design – Build; but are at mercy of owners• Would allow for less change orders
• improving schedule and costs• GMP allows project savings for both the owner and GC
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Procurement Methods
Conclusion• Procurement
• Depends on project• Speed• Cost• Owner
• ASHA• Inexperienced Owner
• Non – profit Organization• Cost highly important
• Back rent costs• Schedule speed crucial
• Follow Design – Build Procurement
Window EfficiencyRe-design
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Window Efficiency Re-design
Problem:
• The energy absorbent windows on the curtain wall are single low energy windows
• With a more efficient glass energy may be saved improving long term costs over up front costs
• A higher LEED rating may be reached with a more efficient system
Research:
• EQuest analysis of different windows and their overall effect on energy consumption
• R.S. Means and industry analysis of new material costs
Goals:• Determine if the energy savings of a more efficient window outweighs the initial costs of the materials
• Can more LEED points be attained with the new system?
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Window Efficiency Re-design
EQuest Window Analysis
Single Low E Triple Low E
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Window Efficiency Re-design
Industry Cost Analysis
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Window Efficiency Re-design
Conclusion
Energy vs. Cost Analysis• Triple Low Energy windows
• Preserve 5% electrical energy but are 1.5 x more expensive
• LEED • 15% energy increase required for addition of 1 point• 20% energy increase required for addition of 2 points
Final Conclusion• The low energy coating is sufficient• Initial costs are extremely high• Unless the entire mechanical system were re-
designed LEED points could not be scored
Structural Steel ColumnRe-design
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Structural Steel Column Re-design
Problem:
• The D.C. metro area is known for its C.I.P. construction
• In order to increase schedule speed steel columns were used on above grade levels
• Concrete may increase the schedule but will lower initial costs
Research:
• pcaColumn analysis of equivalent concrete columns to replace the steel columns
• ICE estimation of new column costs
• Newly estimated schedule based upon C.I.P. Columns
Goals:• Determine the overall savings of converting to C.I.P.• Determine schedule and impact of paying back rent• Finalize which method would be more cost effective
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Structural Steel Column Re-design
pcaColumn Analysis
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Structural Steel Column Re-design
Cost Analysis
Assumptions: Steel: 1” Mineral Fire Proofing Concrete: 4000 psi Square Columns Rebar in Corners
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Structural Steel Column Re-design
Schedule Analysis
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Structural Steel Column Re-design
Conclusion
• Overall cost of concrete is cheaper than that of steel columns
• If back rent of former building is less than $50,000 concrete columns may have been an option to pursue
Conclusions
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Conclusions
Sustainability Systems:
• Green Globes is an outstanding system that with the growth of knowledge and popularity may become the official rating system
• LEED however controls the market and with “competition” always important it may maintain its overwhelming popularity
Procurement Methods:
• Owners prefer control, and the ability to affect design while having a simple method that everyone can understand
• Design – Build presents many financial and scheduling opportunities, but it will take greater knowledge and use if it is ever going to be popular with owners
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Conclusions
Window Efficiency Re-design:
• Although windows may conserve energy on a project initial costs must always be considered
• The initial costs for all of the windows presented are too great for the future energy conservation. While LEED points cannot even be affected by the new systems
Structural Steel Column Re-design:
• The columns may present a longer schedule however the initial savings are tremendous
• If the project could afford the 66 day delay then perhaps a concrete system would have been economical
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Conclusions
Acknowledgements
• The Pennsylvania State University Department of Architectural Engineering
• Industry Professionals especially those at:• Davis Construction• Barton – Malow Construction
• Fellow Students and Friends
• My Family
Michael Abbondante
Construction Management
Project Overview
Sustainability Systems
Procurement Methods
Window Efficiency Re-design
Structural Steel Column Re-design
Conclusions
Q & A
Questions?