MICE Target Report Chris Booth (for target team) Sheffield 24 th March 2010.
-
date post
21-Dec-2015 -
Category
Documents
-
view
216 -
download
0
Transcript of MICE Target Report Chris Booth (for target team) Sheffield 24 th March 2010.
MICE Target Report
Chris Booth (for target team)Sheffield
24th March 2010
Chris Booth University of Sheffield 2
History & Overview• T1 – DLC bearings – running in ISIS
– >155k + 50 k actuations
• T2 – nominally identical to T1– Bearing failed rapidly
• T2.2 – like T1, improved QA– Failed after ~80k actuations
• T2.3 – same stator & shaft as T2.2– New Vespel (polyimide) bearings– Tested for >2.1M pulses in R78
Results of T1 running, T2.3 tests, and plans
3University of Sheffield
BCD (beam centre distance) Histograms
(analysis by Paul Hodgson)
T2 distribution 3-4 times as broad
Can be interpreted as a result of the target “sticking”
Use the BCD histograms as a diagnostic to spot changes in target performance
T1
T2
Chris Booth
T1 Calibration PlotsRunning in ISIS allowed subject to •“target integrity tests” every 10k (formerly 5k) actuations•400 pulses taken under standard conditions•Check for changes in behaviour•Inspections for dust every 50k actuations
0.4 mm
Overlay of Calibration Plots
Chris Booth University of Sheffield 6
Conclusions for Target 1
• Target continues to perform reliably• No sign of significant change in BCD distributions• No sign of dust production on view port
• Keep running!
Status of Target 2• T2 Vespel installed in R78 Jan 25th 2010• DLC coated shaft (from T2.2) – Vespel bearings• Same stator body as previous T2• Pulsed target continuously for 2.15×106 pulses• Approx. one month of operation at ~1 Hz• Two short interruptions, chiller failed 1/2/2010,
UPS failed 8/2/2010(!)• Neither problem associated with target mechanical
performance• Target was deliberately stopped for inspection• Very little dust on view-port (~ daily photos)
Chris Booth University of Sheffield 7
Early Mid Late
720k s 1680k s
Changeover ~1 day
T2 BCD over month
Start up periodDAQ gain changes
1×106 pulses
University of Sheffield
Look at BCD histograms in 3 regions
Region 1 Early operation120k – 360k pulses
RMS 0.135Asymmetric tail
Region 2 Mid operation720k – 960k pulses
RMS 0.122Asymmetric tail
Region 3 late operation1860k – 2100k pulses
RMS 0.155More symmetric with double peak
structure but broader
Chris Booth 9
Comparison of BCD plots for T1 (DLC) and T2 Vespel
RMS of T2 Vespel is approximately twice that of T1(Note different scales)
T2 Region 3 T1
Chris Booth University of Sheffield 10
T2 Acceleration over month
Chiller failure
Test power off
UPS failure
Chris Booth University of Sheffield 11
T2 Acceleration regions
Steady decline 848 to 838 ms-2
Stable operation (838 ± 5) ms-2
Increasedvariability
Early Mid Late
720k s 1680k s
Chris Booth University of Sheffield 12
Questions and CommentsHow would the target have performed if we had carried on pulsing ?
Remember we arbitrarily stopped at 2.15 × 106 pulses.
Does the early period correspond to the target “bedding in” ?
The mid period lasted approx. 1 million pulses where the target seemed to wear gradually.
There was a reasonably rapid (1 day) change in performance after which the target parameters were (slightly) more variable.
None of the variation seen above would compromise the normal target operation.
The typical beam centre varies more than the target BCD.
Chris Booth University of Sheffield 13
Disassembly & Inspection of Target 2(Jason Tarrant)
• Target stopped after 2.16M actuations
• Optics block removed & upper bearing exposed
• Bellows removed & lower bearing exposed
• Significant amounts of vespel dust, adhered to surfaces
Chris Booth University of Sheffield 14
• Disassembly – View of upper Bearing MICE Target
First look
Little dust(polished flat)
Most dust(rough flat)
Polished flat
Rough flat
Amalgamateddust balls
DustOn shaft,
On bearing,On lock ring
Survey point
University of Sheffield
• Disassembly – View of lower Bearing MICE Target
Dust around bearing,lock ring removed
Internal face
External face
Chris Booth 16
MICE Target• Observation – Dust
– Amount• Most at upper bearing – esp. anti-rotate rough flat side• (Only one flat on shaft polished)• Amalgamated at bearings – scraped off
– Location• Coated internal components, has escaped externally• How does it move / defy gravity?
– Thrown off?– Electrostatic attraction?– Vibration movement?– When let up to air?
– Attachment• Fixed – by what?
Chris Booth University of Sheffield 17
University of Sheffield
Next Steps?• Reduce wear & dust
production– Polished flats, burnished
bearing faces
– Possibly harder plastic (Duratron or Celazole)
– Improved stator? (See below)
• Observe when dust produced
• Trap dust in catcher
• Further tests start in May
Chris Booth 18
Stator QA• Is stator 2 different from stator 1?
– Map field, with assistance of group at Diamond
– Support rig built by Geoff Barber
– Chiller, PSU, temperature interlocksready
– Measurements to start this week
– Stator 3 (unwelded) built in Sheffield
– Permanent magnets will be (re-)measured
– Modelling (Paul Smith, Owen Taylor?) to connect field asymmetries with off-axis forces
Chris Booth University of Sheffield 19
Target Electronics & DAQ Upgrade• Phase 1 hardware complete,
tested (Paul Smith)
• USB interface to PC– Menu-driven interface in use
(see screen shots)
– GUI under development (James Leaver)
• Control, monitoring, error notification
• Much simpler interface (for non-experts!)
• Plan to exercise thoroughly in R78 before installation in ISIS– Soak-test during next bearing evaluation
Chris Booth University of Sheffield 20
Menu-driven controls
12-Mar-10 P J Smith - University of Sheffield
Framework for terminal code
programmed by James Leaver
21
Prototype GUI for Target Control
12-Mar-10 P J Smith - University of Sheffield
GUI screenshot provided by James.
The exact layout may change a bit
over the next weeks
22
Chris Booth University of Sheffield 23
Summary• Target 1 installed and operating well in ISIS
• Target 2 with plastic bearings performed reliably for >2M actuations
– Stopped for inspection, not due to failure
• Test & measurement programme for reducing and trapping dust
• Stators will be mapped to improve QA
• FPGA-based control essentially ready
– will give easier operation and enhanced monitoring