1 MICE Schedule CM35 Alan Grant, STFC

description

MICE Schedule CM35. Alan Grant, STFC. Schedule Overview. Magnetic Field Mitigation is not included in this schedule Further scheduling required once decision is taken Aim is to install S tep IV before long ISIS shutdown Aug 2014 - PowerPoint PPT Presentation

Transcript of MICE Schedule CM35

Page 1: MICE Schedule CM35

1

MICE ScheduleCM35

Alan Grant, STFC

Page 2: MICE Schedule CM35

Schedule Overview

• Magnetic Field Mitigation is not included in this schedule–Further scheduling required once decision is taken

• Aim is to install Step IV before long ISIS shutdown Aug 2014

• Delivery of Step V & VI driven by resources and budget restrictions in UK and USA

• Commissioning run for each step - no detail as yet

• Aim to field map upstream & downstream spectrometers solenoids in series with approx 1 week time lag

• Schedule includes Public Holidays – RAL closure

2

Page 3: MICE Schedule CM35

MICE INSTALLATION SCHEDULE – SUMMARY 1

3

Long Shutdown05/08/14 to 29/01/15

Step IV commissioningends 5mths before RFCC delivery to prepare for step V installation

Page 4: MICE Schedule CM35

MICE INSTALLATION SCHEDULE – SUMMARY 2

4

EMR initial tests, Survey target network & Air con - complete

AFC#1 training - ongoing

Upstream Solenoid mapping prior to Christmas break

Downstream Solenoid mapping after Christmas break

• Mapping sequence was discussed with CERN group in December

Page 5: MICE Schedule CM35

Shipping 1

5

RF distribution component quotes received for systems 1 & 2. Delivery approx 12 weeks. Don Summers ready to place orders.

Dummy loads already ordered.

Amplifier #1. Commissioning snags & resource issues. Delivery date may slip.

Page 6: MICE Schedule CM35

Shipping 2

6Magnet Deliveries at RAL

Spectrometer Solenoids shipped together delivery late August 2013.

RFCC’s module#1 delivery Jan 2017 RFCC’s module#2 delivery Jan 2018

AFC module #2 delivery delayed, resource issues at Tesla.

Diffuser complete currently at Oxford ready to be shipped when required.

Page 7: MICE Schedule CM35

Pre Installation

7

• AFC commissioning going well, achieved required current in solenoid mode.• Flip mode commissioning now in progress.

EMR initial tests, complete

Page 8: MICE Schedule CM35

STEP IVSubsystem Date

Spectrometer solenoid #1 + #2 Q3 2013Fibre tracker #1 + #2 ReadyFocus coil #1 Nov ’12

LH2 system A TBC

Solid absorber(s) TBCLiquid absorber ReadyDiffuser ReadyVirostek plate & TOF cage assy

Ready

Substation upgrade ReadyEMR installation Mar’13Radiation shutter ReadyAFC Moving platform #1 Ready

SS platforms Installation Ready

Magnetic shielding plan TBC

Step IV ready Q2, 2014, courtesy Andy Nichols

Page 9: MICE Schedule CM35

Step IV Installation - 1

9

Need to agree and re-schedule EMR final test.

Important to complete installation of AFC & mapping in step IV position before Delivery of Spectrometer Solenoids in late August to free up space.

Some slack but need to watch

AFC parked position TBA

Absorber installation work to be carried out in parked position.

Page 10: MICE Schedule CM35

Step IV Installation - 2

10Magnet training

Step IV installation complete 19/5/14

Upstream SS installation directly followed by downstream SS installation.

Upstream SS is pumped and cooled down whilst downstream SS is being installed.

Training of upstream SS only happens when downstream SS is installed.

Upstream SS is parked after mapping to allow tracker installation then downstream SS is mapped.

US team required from Sept thru Jan 14 for installation.

Page 11: MICE Schedule CM35

Step IV - Magnet Measurement & Magnet Movements

11

Page 12: MICE Schedule CM35

Step V Installation

12 Step V installation complete 26/6/17

RFCC’s module#1 delivery Jan 2017

Delivery of Step V & VI driven by resources and budget restrictions in UK and USA

Run step IV to July 16 then prepare for installation of step V

Page 13: MICE Schedule CM35

Step VI Installation

13 Step VI installation complete 17/9/18

Page 14: MICE Schedule CM35

Hydrogen System Installation

14

System A installed.

System B & C procurement & installed shifted back to suit budget constraints & MICE schedule

Page 15: MICE Schedule CM35

Milestones - 1

15

Milestones allow us to track slippage.

AFC testing in R9 has slipped but not serious at this moment.

AFC module 2 likely to slip. Not serious. Tesla effort directed on completion of module 1

Concern over RF amplifier delivery. Still commissioning and likely to slip. Required to meet TIARA deadline which is to demonstrate RF working system in hall by end Sept 13.

Magnet deliveries at RAL

Page 16: MICE Schedule CM35

Milestones - 2

16

Magnet deliveries at RAL

MICE steps:- Installation completion

Page 17: MICE Schedule CM35

Summary

• Magnetic Field Mitigation is not included in this schedule–Further scheduling required once decision is taken

• Need to complete AFC installation & mapping in step IV position before Spectrometer Solenoids arrive

• Need to meet TIARA milestone of September 2013 demonstrating RF working system in MICE Hall

• No detailed commissioning schedule for each step as yet

• Schedule includes Public Holidays – RAL closure