MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters...

4
MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters Marshalling for all other quadrupole & dipole units Houses controls VME crate & magnet ON lamp monitoring Awaiting delivery of monitoring crate. Due end July-07 Rack 95% complete Wiring & Termination drawings complete Electrical & controls checkout w/c 30-July-07

description

MICE Project Progress Update Cable Management Basic tray & trunking layout complete Drawing sheets 1 to 7 issued –Installation can now proceed Main MICE Hall cable routes & to LCR design complete Cable schedule complete for magnet power converters Mains distribution for power converters & LCR complete Mains distribution boards to be purchased & installed LCR tray work design complete –Rack support frames to be manufactured –Tray work to be installed –Raised floor to be installed Phase 2 electrical requirements under review –Detailed information for all systems required

Transcript of MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters...

Page 1: MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling…

MICE Project Progress Update Power Converters

• Rack housing MQ1 to MQ3 magnet power converters – Marshalling for all other

quadrupole & dipole units – Houses controls VME crate &

magnet ON lamp monitoring– Awaiting delivery of monitoring

crate. Due end July-07– Rack 95% complete– Wiring & Termination drawings

complete– Electrical & controls checkout

w/c 30-July-07

Page 2: MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling…

MICE Project Progress Update Decay Solenoid

• Solenoid power supply tested & ready for return to RAL– To be located on mezzanine floor– Mezzanine floor requires

strengthening– Control interface requirements

known– Drawings to be updated to show

requirements

Page 3: MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling…

MICE Project Progress Update Cable Management

• Basic tray & trunking layout complete • Drawing 204-70002 sheets 1 to 7 issued

– Installation can now proceed• Main MICE Hall cable routes & to LCR design complete• Cable schedule complete for magnet power converters• Mains distribution for power converters & LCR complete• Mains distribution boards to be purchased & installed• LCR tray work design complete

– Rack support frames to be manufactured– Tray work to be installed– Raised floor to be installed

• Phase 2 electrical requirements under review– Detailed information for all systems required

Page 4: MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling…

MICE Project Progress UpdatePersonnel Safety Rack

• Internal wiring 75% complete• Terminals & relays installed • Control crates in build• UPS on order• Testing at DL mid-August• Delivery to RAL end August