MICE Project Progress Update Power Converters
• Rack housing MQ1 to MQ3 magnet power converters – Marshalling for all other
quadrupole & dipole units – Houses controls VME crate &
magnet ON lamp monitoring– Awaiting delivery of monitoring
crate. Due end July-07– Rack 95% complete– Wiring & Termination drawings
complete– Electrical & controls checkout
w/c 30-July-07
MICE Project Progress Update Decay Solenoid
• Solenoid power supply tested & ready for return to RAL– To be located on mezzanine floor– Mezzanine floor requires
strengthening– Control interface requirements
known– Drawings to be updated to show
requirements
MICE Project Progress Update Cable Management
• Basic tray & trunking layout complete • Drawing 204-70002 sheets 1 to 7 issued
– Installation can now proceed• Main MICE Hall cable routes & to LCR design complete• Cable schedule complete for magnet power converters• Mains distribution for power converters & LCR complete• Mains distribution boards to be purchased & installed• LCR tray work design complete
– Rack support frames to be manufactured– Tray work to be installed– Raised floor to be installed
• Phase 2 electrical requirements under review– Detailed information for all systems required
MICE Project Progress UpdatePersonnel Safety Rack
• Internal wiring 75% complete• Terminals & relays installed • Control crates in build• UPS on order• Testing at DL mid-August• Delivery to RAL end August