Planning Table
Definition:-
Detailed Plan for any given period will be maintained in the Planningtable in Repetitive manufacturing.Any distribution of the manufacturing quantity across differentproduction version will be done with the planning table.
Objective :-
Production plan is available and one has to schedule the plan acrossdifferent production version and resources using the planning Table.
At the end of this document one will be able to perform planning usingplanning table.
Prerequisites:-
Production PlanProduction versions and Resources
Menu path :-
Logistics → Production → MRP → Planning → Planning Table → MF50- Change Mode
8/15/2019 MF50-Planning Table Change
http://slidepdf.com/reader/full/mf50-planning-table-change 2/9
1. Press Twice MF50 – Change Mode.
8/15/2019 MF50-Planning Table Change
http://slidepdf.com/reader/full/mf50-planning-table-change 3/9
8/15/2019 MF50-Planning Table Change
http://slidepdf.com/reader/full/mf50-planning-table-change 4/9
Note:For repetitive production, ensure Rate-based planning button isselected and ifthe products are subject to PPPI, ensure detailed planning button isselected.
6. Select Forward scheduling in dropdown to ensure that theplanning table shows the dates calculated from start times.
7. Press tab Control data .
8. Press checkboxes Only mats with production and Only mats withreqmts.
9. Press Planning table Button .
Planning Table for Repetitive Manufacturing: Change Mode
8/15/2019 MF50-Planning Table Change
http://slidepdf.com/reader/full/mf50-planning-table-change 5/9
Note: The top part of the table shows the work centers. The bottom part of the screen shows the products that can bemanufactured at the work centers and the present productionschedule.
Note: To optimize the production , sequence of production may bemanaged by moving scheduled quantities forwards or backwards. Youmay do this as shown in the example below.
10. For the material you want to plan, select the Production Versionrows and the date columns you want to modify.
Planning Table for Repetitive Manufacturing: Change Mode
11. Press .
8/15/2019 MF50-Planning Table Change
http://slidepdf.com/reader/full/mf50-planning-table-change 6/9
Planning Table: Choose Period
12. Press
Selection Days
13. Enter the required Start and Fin. dates
14. Press
Note: Following example shows how to schedule producito to tadifferent work center.
8/15/2019 MF50-Planning Table Change
http://slidepdf.com/reader/full/mf50-planning-table-change 7/9
15. Select the Production version rows and the date columns youwant to modify.
Planning Table for Repetitive Manufacturing: Change Mode
16. Select to move the load to different production versions.
Distribute Prod. Quantities
8/15/2019 MF50-Planning Table Change
http://slidepdf.com/reader/full/mf50-planning-table-change 8/9
17. Update the following required and optional fields:
Field Name ValuesQuota (VR1) Enter value in
Column Quota.
Quota (VR2) Enter value inColumn Quota.
18. Press Copy Button .
Planning Table for Repetitive Manufacturing: Change Mode
8/15/2019 MF50-Planning Table Change
http://slidepdf.com/reader/full/mf50-planning-table-change 9/9
19. Press Save .