Metrolink Fleet Plan

30
Metrolink Fleet Plan 2012 - 2017 Item No. 11 - Attachment

Transcript of Metrolink Fleet Plan

Page 1: Metrolink Fleet Plan

Metrolink Fleet Plan

2012 - 2017

Item No. 11 - Attachment

Page 2: Metrolink Fleet Plan

1

Table of Contents Executive Summary ............................................................................................................... 2

I. Equipment Needs ........................................................................................................ 4

A. Trailer Cars B. Current Capacity Capabilities C. Current Service Usage D. Methodology E. Ridership Assumptions F. Reasons Why an Annualized Ridership Growth Rate of 7.5 Percent

May Be Too High G. Reasons Why Annualized Ridership Growth Rate of 7.5 Percent

May Be Too Low H. Reasons Why Annualized Ridership Growth Rate of 3 Percent

May Most Realistic Assumption

II. Excess Cars .............................................................................................................. 10

III. Specialty Cars ........................................................................................................... 12

A. Bike Car B. Café/Lounge Car C. Business Car D. Possible Other New Service

IV. Railcar Rehab ............................................................................................................ 13

A. BANDAID Overhauls B. Major Overhauls

V. Locomotives ............................................................................................................... 14

A. Current Service Usage B. Locomotive Overhauls C. EPA Tier Requirements D. BANDAID Overhauls E. Mid-life Overhauls

VI. Funding Discussion ................................................................................................... 22

A. South Coast Air Quality Management District B. Notes on Rehab Funding

Page 3: Metrolink Fleet Plan

2

Metrolink Fleet Plan

January 10, 2012

Executive Summary

The aging Metrolink fleet consisting of passenger cars and locomotives will require continuous

rehabilitation, and due to the age of the fleet, rehab needs will be extensive over the next five

years to extend service life. The introduction of the Guardian cars made by Hyundai Rotem

gives the agency a unique opportunity to defer passenger car maintenance for several years.

The locomotive fleet is the initial focus in the plan as approximately 30 units have passed the

million-mile milestone. With regulatory requirements demanding cleaner burning locomotives,

Metrolink has a unique opportunity to stretch scarce monies and attract grant funds to improve

the emissions of 30 locomotives from Tier 0 up to Tier 4, and plan for the future upgrade of the

remaining 22 locomotives from Tier 2 to Tier 4 to standardize the fleet. When completed,

Metrolink would be the first commuter agency in the U.S. to have an entirely standardized Tier

4 locomotive fleet.

Metrolink estimates that it will need between 220 and 250 passenger cars by the end of the

proposed five-year horizon. This assumption is based on an aggressive ridership growth of 7.5

percent per year and a more moderate growth of approximately 3 to 3.5 percent growth per

year. With the introduction of the Guardian cars, the decision to sell or keep approximately 20

older passenger car vehicles will need to be made. One recommended benefit of selling these

20 vehicles would be to use the proceeds to leverage clean air funds to bring.30 of Metrolink’s

aging locomotives up to Tier 4 standards.

The funding considered in this Plan is a combination of carried-over rehab funds from past

years, annual rehab funds from Member Agencies, bond funds designated to Metrolink through

the State of California, grant funds and potential loans.

Currently, available funds limit the amount of work that may be accomplished; hence, the initial

option of upgrading the entire locomotive fleet of 52 locomotives to Tier 3+ was first explored.

Tier 4 technology has made considerable development and Metrolink continues to work with

various vendors on Tier 4 possibilities and funding scenarios as the best option for maximum

performance, reliability, and environmental impact (cleanest fleet). Funding sources, such as

incentive programs through the Air Quality Management District (AQMD) or potential loans

have not been applied for or secured at this date. The Plan estimates the annual cost

requirement to keep the fleet stored in serviceable and reliable condition. Should future rehab

funds be necessary from Member Agencies for this program, they must be approved each

budget year.

D R A F T

Page 4: Metrolink Fleet Plan

ROLLING STOCK REHABILITATION PLAN

RAIL CARS 5-YEAR PLAN (UNITS)

Rehabilitation ItemsFY 11-12

(Present) FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17 TOTAL

1 Basic Rehabilitation (HVAC) 0 0 Coaches 20 Coaches 20 Coaches 20 Coaches 37 Coaches 97 Cars

2 Mid-Life Overhaul 4 Coaches 4 Cars

LOCOMOTIVES 5-YEAR PLAN (UNITS)

1 Basic Rehabilitation10 EMD

Locomotives

10 EMD

Locomotives

10 EMD

Locomotives30 Locomotives

2

Upgrade 30 EMD Locomotives from

Tier 0 to Tier 4, incl Reliability

Improvments

5 EMD

Locomotives

15 EMD

Locomotives

10 EMD

Locomotives30 Locomotives

RAIL CARS REHABILIBATION COSTS ($M 2011 CONSTANT DOLLARS)

Rehabilitation ItemsFY 11-12

(Present) FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17 TOTAL

1 Basic Rehabilitation (HVAC) $0.40 $0.40 $0.40 $0.59 $1.79

2 Mid-Life Overhaul $5.82 $5.82

TOTAL CAR REHAB (Estimated Cost) $0.00 $0.00 $0.40 $0.40 $0.40 $6.41 $7.61

LOCOMOTIVE REHABILIBATION COSTS ($M 2011 CONSTANT DOLLARS)

1Basic Rehabilitation (10/year using 11-

12 Funds)$5.00 $5.00

2

Upgrade 30 EMD Locomotives from

Tier 0 to Tier 4, incl Reliability

Improvments

$18.92 $56.77 $37.84 $113.53

TOTAL LOCOMOTIVE REHAB (Estimated

Cost)$5.00 $18.92 $56.77 $37.84 $0.00 $0.00 $118.53

TOTAL EXPENSES ($M IN 2011 CONSTANT DOLLARS)

CAR & LOCOMOTIVE COST ($M) $5.0 $18.9 $57.2 $38.2 $0.4 $6.4 $126.1

CUMULATIVE COST ($M) $5.0 $23.9 $81.1 $119.3 $119.7 $126.1

Page 5: Metrolink Fleet Plan

4

I. Equipment Needs

Metrolink’s consists are planned to be a mix of Guardian and Bombardier (dubbed

“Sentinel”) cars. Each consist will include a Guardian CEM-equipped Cab car. The Sentinel

fleet is the older fleet with three generations dating back to the service start up. The already

in-service newer Guardian cars manufactured in South Korea will be fully in service by the

time the Fleet Plan goes into effect in 2013. Based on the assumptions in this Plan, we will

discuss the proposed fleet mix through the next five years including storage requirements

and other recommendations. We will also discuss options for Sentinel cars tied up in

financial agreements (LILO/SILO) that limit salability options.

A. Trailer Cars

CURRENT METROLINK INVENTORY

Type Count Mileage LILO/SILO

Sentinel Gen 1 60 trailer cars 28 cabs

1.3 Million Bank of America

Sentinel Gen 2 18 trailer cars 5 cabs

950,000 M & T Enterprises

Sentinel Gen 3 26 trailer cars 650,000 Wells Fargo

Guardian Fleet (base + option)

80 trailer cars 57 cabs

45,000 (est.) n/a

Table I.1

With Metrolink’s established benchmark in safety, upgrades and passenger comfort,

there are differences between the newer Guardian fleet and the aging Sentinel fleet

which can be updated, wherever feasible, in the rehab/scheduled maintenance and

refurbishment process. For example, there are differences in car structure (stainless

steel Guardian cars versus aluminum shell, steel alloy Sentinel cars) and the Guardian

Fleet has Crash Energy Management (CEM) features on each end of both cab and

trailer cars. Car flooring features also differ (fiberglass composite Guardian versus

plywood/metal Sentinel) as does seat and table arrangements (Guardian layout and

table type for CEM benefits versus retrofitting Sentinel with energy absorbing tables.)

As Guardian Cab cars come into service, they are replacing Sentinel Cab cars, which

are being stored. (Note: see attachment, Metrolink Bombardier/Sentinel Storage Plan.)

For more in-depth information on fleet differences, see “Metrolink Status of Fleet

Rehabilitation Projects Second Submittal Draft”, pages 25-38; prepared by LTK

Engineering Services, March 12, 2010.

Page 6: Metrolink Fleet Plan

5

B. Current Capacity Capabilities (People to Seat)

The chart below illustrates the seating capacity in our current mixed-consist fleet.

Sentinel cars have greater seating capacity, at 140 to 149 seats per trailer car,

depending on the generation. Guardian fleet Coach/trailer cars seat 132 customers,

which represents a reduction in capacity. The Sentinel Cab car seat capacity is from

135 to 142 seats (Gen 1 and 2) and Guardian Cab cars seat up to 121 customers. With

the new addition of the "Bike Car", seating capacity also changes with Sentinel (Gen 1)

cars seating 120 customers. In summary, the newer cars have fewer seats, thus more

cars are needed to carry the same number of passengers.

Currently, with a total fleet of 274 passenger cars, including trailer, cab and bike cars

the overall total seat capacity is in excess of 36,000.

RAIL CAR CAPACITY CAPABILITIES

RAIL CARS Sentinel Gen 1

Sentinel Gen 2

Sentinel Gen 3

Guardian Fleet

TOTAL

# Trailer Cars 25 18 26 80 149

# Bike Cars 35 n/a n/a n/a 35

# Cab Cars 28 5 0 57 90

TOTAL Cars 88 23 26 137 274

# Seats Trailer Cars 149 140 141 132

# Seats Bike Cars 120 n/a n/a n/a

# Seats Cab Cars 142 135 n/a 121

Capacity Trailer Cars 3,725 2,520 3,666 10,560 20,471

Capacity Bike Cars 4,200 n/a n/a n/a 4,200

Capacity Cab Cars 3,976 675 0 6,897 11,548

TOTAL SEAT CAPACITY 11,901 3,195 3,666 17,457 36,219

Table I.2

C. Current Service Usage

Currently, ridership numbers average 41,739 weekday trips (June 2011) on 163

weekday trains. The number of train cars required to accomplish moving this amount of

people on a daily basis (based on our current published schedule) is 157 cars (with a

spare ratio of 10 percent =16 cars) totaling 173 cars. This number includes the 35

cycles/turns throughout the system.

Page 7: Metrolink Fleet Plan

6

D. Methodology

The methodology for calculating fleet size requirements is based on demand estimates

at the individual train level given current service characteristics. Load factors calculated

on July 2011 cycle patterns and ridership levels. Future load factors estimated

assuming both approximately 3 – 3.5 percent and a 7.5 percent annualized growth rate.

Capacity needs determined by the demand for peak travel. After analyzing historical

trends, it was assumed that the proportion of weekday travel occurring in peak direction

during the AM peak would remain stable at current levels. Capacity requirements were

calculated on a train-by-train basis and translated into the number of cars required per

consist to meet demand based on a 95 percent load factor policy standard. An average

seating capacity of 137 seats per car was used which reflects the fleet mix as of August

2011. The resulting number of in-service cars was further adjusted to account for

planned new services, after which an applied 10 percent spare ratio. Consists requiring

seven or eight cars were identified to help estimate the need for additional locomotives.

However, these fleet size estimates do not reflect considerations to standardize consist

sizes to at least six (6) cars, which would increase the number of total cars required.

These results were verified through separate analysis of the correlation between

ridership levels and car requirements.

E. Ridership Assumptions

Metrolink has been working with the Southern California Association of Governments

(SCAG) to obtain ridership projections for the next five years. Unfortunately, SCAG

recently informed Metrolink that the regional travel demand model is currently being

updated for the development of the 2012 Regional Transportation Plan (RTP) and is not

yet ready to produce ridership forecasts. Older forecasts have become invalid due to

the effects of the economic recession. As Metrolink does not have the resources to

develop its own 5-year ridership forecast, assumptions had to be made for ridership

growth to allow estimation of fleet size requirements.

Table I.3 identifies the number of cars required at different ridership levels during the

next five years. These numbers should not be interpreted as an annual forecast of

actual ridership and cars required in a given year. Rather, they assume an annualized

growth rate of 7.5 percent to provide the basis for calculating the required number of

cars at a given ridership level. Although the numbers indicate Metrolink ridership

reaching 60,000 in 2016, it does not imply that this ridership level could not be reached

earlier or later.

Page 8: Metrolink Fleet Plan

7

RIDERSHIP LEVELS AND CAR REQUIREMENTS AT 7.5 % ANNUALIZED GROWTH

Table I.3

F. Reasons Why an Annualized Ridership Growth Rate of 7.5 Percent May Be Too

High

Macro-economic projections for the coming five years call for moderate rates of growth.

According to latest projections from SCAG for the period 2011 to 2021, employment in

the five-county region is expected to grow at an annualized rate of 1.6 percent. The

same projections also call for an annualized population growth rate of 0.9 percent. In its

Annual Energy Outlook for 2011, the Energy Information Agency (EIA) projects the price

of gasoline to increase at an annualized rate of 3.6 percent during the next five years.

For comparison, average weekday Metrolink ridership growth during the past five years

averaged 0.1 percent annually. If the economy should continue at the current state or

enter into another recession, Metrolink ridership may face another period of zero to

negative growth.

G. Reasons Why Annualized Ridership Growth Rate of 7.5 Percent May Be Too Low

Annualized growth rates are misleading to project resource requirements to meet peak

demand. The average annual ridership growth rate for the past five years was 0.1

percent, which seems to indicate no change in the required number of cars during this

period. Annualized rates, however, mask the significant fluctuations during that period.

Although Metrolink ridership appears not to have grown during the past five years, the

period included the record ridership spike in July 2008, which resulted in a ridership

increase of 15.7 percent. None of the prevailing economic projections accounted for the

dramatic run-up in oil prices and Metrolink was unprepared for the increase in demand,

which forced the agency to lease dozens of additional rail cars in 2008. There is no

indication that the next five years will be free of disruptions in the supply of oil, and fuel

prices reaching new highs. Barron’s warned that oil prices may spike to $150 as early

as next spring (“Get ready for $150 oil,” Barron’s, July 4, 2011).

H. Reasons Why Annualized Ridership Growth Rate of 3 Percent May Most Realistic

Assumption

Year 2011 2012 2013 2014 2015 2016

Average weekday ridership

41,739 44,882 48,262 51,896 55,803 60,005

In service cars

157 166 173 183 197 207

+ New Svc.

0 8 8 24 24 24

10% spare ratio

16 17 18 21 22 23

Grand Total

173 191 199 228 243 254

Page 9: Metrolink Fleet Plan

8

Metrolink’s FY11/12 Budget assumes a ridership growth of 7.6 percent, based on the

addition of new service as well as an enhanced marketing program. There are concerns

that this rate of growth may not be sustainable for the next five years. The Marketing

and Sales Department is assuming ridership growth of 3.5 percent in FY11/12 which will

slow to 3 percent in each of the subsequent years (Table I.4) based on marketing

opportunities and historical trends.

RIDERSHIP LEVELS AND CAR REQUIREMENTS AT APPROXIMATELY THREE

PERCENT ANNUALIZED GROWTH

Table I.4

This estimate does not factor in any fare increases, a dramatic increase or decrease in

gas prices, impacts to parking, or any major disruption caused by natural disaster or act

of terrorism, etc., but based on the following factors for growth:

1. Corporate Pass Program: Metrolink will continue to grow the Corporate Pass

Program over the next five years. Metrolink anticipates growth from adding new

accounts and growing existing accounts. To help grow accounts, Metrolink is

creating a “tool kit” to help CPPs grow ridership internally. This “tool kit” has

collateral items, posters, and other items necessary to encourage ridership.

2. I-5 Caltrans/ Metrolink Partnership: Over 300,000 automobiles travel the I-5 corridor

between the 605 and the 91 freeway on a daily basis. Caltrans will be widening the

corridor with construction starting in 2012. This project is expected to last seven (7)

years. Metrolink anticipates adding 175 new riders each month due to the project,

which equates to 2,100 peak-time riders each year.

3. Connectivity: LA Metro is working to complete two (2) major connectivity projects

(the Expo Line and the Orange Line extension) in Calendar Year 2012. These lines

have the potential to efficiently connect passengers from job centers to Metrolink,

and we anticipate ridership growth from the added connectivity. In 2015, Metro

anticipates to have the Expo line finished to Santa Monica. If construction is

Year 2011 2012 2013 2014 2015 2016

Avg wk-day ridership

41,739 43,200 44,496 45,831 47,206 48,622

Cars in svc. 157 162 165 167 172 174

+ New Svc. 0 8 8 24 24 24

10% spare ratio

16 17 17 19 20 20

Grand Total

173 187 190 210 216 218

Page 10: Metrolink Fleet Plan

9

complete as planned, Metrolink anticipates additional incremental ridership due to

the area’s dense job market.

4. Special Service Trains During Peak Hours: Metrolink anticipates continued requests

for service to special events. During the 2011/12 year, Metrolink ran special service

trains during peak hours for Angel games and a popular U2 concert for Live Nation.

Metrolink is also currently in discussion with AEG regarding adding special service

trains to serve the proposed Farmers Field.

5. Increased “Special Car” Options: Implementing special cars that provide

passengers options such as Quiet Cars and Bike Cars and proposed Business

Class Cars, and Café/Lounge Cars, may provide for additional growth and will affect

fleet management.

Table I.5

In 2013, with average weekday ridership increasing to between 44,496 and 48,262

(based on 3 – 3.5 and 7.5 percent annual ridership growth, see section, II. e. Ridership

Assumptions), the estimated need of cars increases from 173 cars (based on seating

capacity with a spare ratio of 10 percent of 18 cars) to between 190 to 199 cars.

23.9%

15.6%

9.4%

5.2%

11.6%

6.6%

3.2%

7.4% 7.3%

5.2%6.7%

4.2% 4.7%

2.7%

-8.2%

-1.6%

7.5% 7.5% 7.5% 7.5% 7.5%

3.5% 3.0% 3.0% 3.0% 3.0%

-10.0%

-5.0%

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

FY 95

/96

FY 96/97

FY 97/98

FY 98/99

FY 99

/00

FY 00

/01

FY 01/02

FY 02/03

FY 03/04

FY 04

/05

FY 05

/06

FY 06/07

FY 07/08

FY 08/09

FY 09

/10

FY 10

/11

FY 11/12

FY 12/13

FY 13/14

FY 14

/15

FY 15

/16

ANNUAL RIDERSHIP GROWTH

Assumed Growth Rates at 7.5% and 3%-3.5%

Page 11: Metrolink Fleet Plan

10

AVERAGE RIDERSHIP THROUGH JUNE 2016 HIGH AND LOW PERCENTAGES

YEAR AVG. HIGH RIDERSHIP

AM PEAK DIRECTION

AVG. LOW RIDERSHIP

AM PEAK DIRECTION

June 2011 41,739 14,191 41,739 14,191

June 2012 44,882 15,260 43,200 14,688

June 2013 48,262 16,409 44,496 15,128

June 2014 51,896 17,645 45,831 15,582

June 2015 55,803 18,973 47,206 16,050

June 2016 60,005 20,402 48,622 16,531

Table I.6 *Assumptions

High ridership estimated at 7.5% annual ridership growth

Low ridership estimated at 3 to 3.5% annual ridership growth

Peak demand (AM Peak, peak direction) at 34% of total

REQUIRED FLEET SIZE

YEAR CARS* NEW

SERVICE 10% SPARES

HIGH TOTAL

LOW TOTAL

2011 157 0 16 173 173

2012 166 8 17 191 187

2013 173 8 18 199 190

2014 183 24 21 228 210

2015 197 24 22 243 216

2016 207 24 23 254 218

Table I.7

As ridership increases, train consists will need to increase in size to accommodate

capacity. The purpose of the Fleet Management Plan is to prepare for future peak

demand. This may be best accomplished by looking beyond annualized ridership

growth rates, which may under-estimates peak demand patterns. The best practice in

fleet management planning may depend not so much on predicting the most probable

growth scenario – the last five years were not the most likely outcome – as on weighing

the benefits of selling cars against the risk of having to lease additional cars to meet

unexpected increases in demand.

II. Excess Cars

Metrolink’s five-year high projection requires 254 cars, suggesting there may be an excess

of twenty (20) Sentinel cars. All 137 Sentinel cars financed through a Lease-in, Lease-out

(LILO) defeased lease agreements held by either Bank of America, M & T Enterprises (M &

T) and Wells Fargo.

Page 12: Metrolink Fleet Plan

11

In order for Metrolink to sell, lease or dispose of any amount of excess railcars, each

defeased lease has a provision whereby Metrolink would have to purchase at the then

termination value, all the cars in that defease lease. Of the three financial institutions, M &

T Enterprises previously indicated in other prior discussions that it would consider selling

the cars in lots, and in accordance with Metrolink’s needs, as long as cars are acquired

over time (M & T has not been approached recently to discuss this issue). Due to M & T’s

prior perceived flexibility and its lower termination value, it is likely that if cars are sold, they

will come from the Generation 2 category covered by the M & T agreement, which covers

23 Sentinel cars.

Table II.1 illustrates the above scenario, where it would only be necessary for Metrolink to

sell the M & T Sentinel cars at current market rate to cover the cost of the termination value

for the Gen 2 LILO agreement.

The passenger railcar market today is very tight, and the demand for older Bombardier

generation bi-level railcar is high. Therefore, should Metrolink consider to acquire then sell

the 23 railcars suggested above, there appears to be a market for resale of such railcars.

Staff is however, evaluating what additional requirements need to be met in order to sell the

railcars covered by the M & T Agreement, and whether the original grant funding agencies

would need to approve the resale of such cars and any subsequent use of the sale

proceeds.

A. LILO / SILO

RAIL CARS Sentinel Gen 1

Sentinel Gen 2

Sentinel Gen 3 TOTAL

Bank/Fund Bank of America M & T Wells Fargo

# Trailer Cars 25 18 25 68

# Bike Cars 35 35

# Cab Cars 28 5 0 33

TOTAL Cars 88 23 25 136

Purchase Cost (each.)

$1,241,168 $1,431,088 $1,869,390

NLV* (Blended Rate)

$376,400 $501,845 $774,114

Termination Value $210,533 $166,721 $910,171

Purchase Cost Total

$109,222,152 $32,915,034 $46,734,741

NLV $33,123,171 $11,542,445 $19,352,840

Termination Value $18,526,882 $3,834,583 $22,754,264

Per Unit NLV Termination

$165,867 $335,124 -$136,057

Total NLV Termination

$14,596,289 $7,707,862 ($3,401,424)

Table II.1

Page 13: Metrolink Fleet Plan

12

Metrolink had an appraisal of the Sentinel fleet prepared (for details on this appraisal,

see Estimates of Current Net Liquidation Value of Equipment Owned by Metrolink, June

24, 2011). This in-depth analysis provided two views of estimated costs. Table II.1

shows the lower value and suggests the results of selling cars in each deal. The

termination value is the additional amount of money that must be paid to the respective

banks.

The initial recommendation for the use of sale proceeds is to match these funds with

additional Carl Moyer Funds, if they are secured to upgrade the remaining 22

locomotives to Tier 4. If the Carl Moyer Funds are not available, then the sale proceeds

can fund continuous car rehabilitation.

III. Specialty Cars

A. Bike Car

Metrolink has already introduced the successful Bike car into the system. Twenty-nine

passenger seats have been removed from the lower level of the Sentinel Gen 1 car, and

space created for at least 18 bicycles; 120 passenger seats remain, with the goal to

introduce a Bike car on each of the thirty-five Metrolink consists. In addition to rehab

requirements for each car, the retrofit by in-house resources costs approximately

$20,000 each. The Bike car upgrade will not affect capacity account first generation

coaches and cab cars are available to support service in the event they are needed.

B. Café/Lounge Car

Metrolink’s potential Café/Lounge cars are still in the initial investigatory stages, with

staff evaluating the legal requirements for, and feasibility of such a car. If such a car is

feasible, conceptually, it could include an open lounge area with bench-type seating for

passengers to enjoy their train community and purchases from the bar/café including

specialty coffees, beer and wine, upscale snacks and sundries. In addition to what

rehab each car requires, costs are approximately $400,000 each.

C. Business Car

The (potential) Business car will include a complete interior upgrade, larger airline-style

reclining seats, more legroom, and specialized service and amenities to include

possible Wi-Fi, satellite television and more. In addition to what rehab each car requires,

costs are estimated to be $500,000 each.

D. Possible Other New Service

Upcoming new service possibilities include MSEP, IEOC, Perris Valley Line, Special

Event trains (such as baseball and prom and trains that run through Union Station).

Page 14: Metrolink Fleet Plan

13

IV. Railcar Rehab

Guardian cars allow Metrolink to defer major overhauls for several years. Some work must

occur to keep even the best of the Sentinel fleet in good order.

A. “BAND-AID” Overhauls

Due to the wide variety of temperature variances (110 degrees F in the summer and 10

degrees F in the winter) throughout the Metrolink system, a reliable HVAC system is

required. Failure of the HVAC can result in an uncomfortable ride for passengers, and

pose other concerns. Each passenger car has two HVAC units, which are overhauled

every four years in conjunction with the scheduled COT&S four-year major inspection. A

complete overhaul of the HVAC units includes an inspection, thorough cleaning, re-

painting as required, replacement of thermal insulation, latches, seals and gaskets, and

other parts are required, re-building of the compressor units and all other tasks and

testing required ensuring a fully functioning unit. In addition to the HVAC units, the door

operators are overhauled and replaced during the same scheduled COT&S inspection

every four years. The purpose of the door operator overhaul is to replace motors during

scheduled intervals to minimize opportunity of failure due to the very high duty cycle.

Existing Sentinel car HVAC units must be to a new refrigerant as required by the EPA.

B. Major Overhauls (Note: costs are estimates)

1. Exterior upgrades include repair car body and paint or wrap cars ($60,000), HVAC

modification to include new refrigerant and overhaul the units ($50,000), install push

back couplers ($150,000), overhaul trucks ($120,000) and airbrake systems

($20,000) and replace all window rubber components. Total exterior upgrades

approximately $410,000.

2. Interior upgrade examples include, install frangible tables ($10,000), replace seating

to match CEM seating of Guardian cars ($150,000), replace carpet and rubber

flooring ($20,000) and install composite material subfloors ($40,000), install

emergency wireless crew communication with rail cars ($20,000), install Passenger

Emergency Intercom (PEI) system ($25,000), install GPS based automated

announcement system ($5,000), install new destination signs, same as Guardian

cars ($40,000), new side door opening mechanisms ($20,000) and upgrade

emergency release feature so that both door panels open when emergency release

is activated. Upgrade side door panel to a composite material, upgrade lighting

system ($30,000), upgrade/replace interior material to match current color scheme,

same as Guardian interiors ($50,000). Total interior upgrades approximately

$840,000.

3. Sentinel Cab Car Conversion: There are two basic options for the cabs in the

Sentinel Cab cars. The first option is to use the Cab cars in regular service as

Trailer/Coach cars without any (structural) changes. The COT&S

service/inspection that is required every four years will cost an additional $1,000

Page 15: Metrolink Fleet Plan

14

per Cab car. For the fleet of 33 Sentinel Cab cars the yearly cost will be about

$8,250.

The second option is to convert the Cab cars to Trailer/Coach cars at an

approximate cost of $100,000 each. This cost estimate includes items such as

the removal of vehicle operating capabilities and cab area, and installing four

passenger seats to match the Trailer/Coach seat configuration. This cost is in

addition to overhaul required for the Sentinel fleet. Metrolink staff does not

recommend this option because it reduces the Cab car value and does not

provide enough value (seating area) for the costs involved.

V. Locomotives

A. Current Service Usage

Today there are 35 train consists (groups of cars that become a train set) that serve the

163 weekday trains throughout the Metrolink system. Each consist is assigned one (1)

locomotive and one (1) Cab car (there is one train that requires two locomotives to

maintain express train service schedule) with 36 locomotives in daily service. At any

given time, there are four (4) locomotives shopped for preventative maintenance (PM)

and approximately three (3) for non-scheduled repair.

Over the next two years, all locomotives will require installation of Positive Train Control

(PTC) equipment. Up to three (3) locomotives at a time may be out of service for the

PTC installation and test program. This installation is not included in this particular

budget and discussion.

LOCOMOTIVES IN SERVICE

Type Count Mileage Condition Horsepower

F59 PH 15 1M Due overhaul 3,000 HP

F59 PHI 14 600K Due overhaul 3,200 HP

F40 PH 1 1M Due overhaul 3,200 HP

MP36 PH-C 15 100K

New

(2 years) 3,600 HP

F59 PH 7 50K Re-configure

(1 year) 3,000 HP

Total 52

Table V.1

Page 16: Metrolink Fleet Plan

15

B. Locomotive Overhauls

The age and condition of Metrolink’s locomotive fleet calls for two basic overhaul types.

The first, dubbed “Band-Aid” relates to the Service Life Extension Program and focuses

on allowing high-mileage locomotives to function up to the next necessary renovation.

The second type are called, “Mid-Life” which look to both short and long-term solutions

for locomotives typically ten years or older.

A comprehensive locomotive overhaul plan, especially one that is long term, must

involve consideration of the environment.

C. EPA Tier Requirements (Source: Dieselnet.com)

In order to make environmental considerations a primary focus to the Railroad Industry,

the EPA developed standards and regulations for locomotives and locomotive engines

that can be found in the US Code of Federal Regulations, 40 CFR Parts 85, 89 and 92.

The applicability of the standards depends on the original locomotive manufacture date.

United States emission standards for locomotives apply to newly manufactured, as well

as remanufactured railroad locomotives and locomotive engines. The EPA adopted the

standards in two regulatory actions (1997 and 2008).

1. Tier 0-2 Standards: The first emission regulation for railroad locomotives, adopted

on Dec. 17, 1997, [63 FR 18997-19084, 16 Apr 1998] became effective from 2000,

and applies to locomotives originally manufactured from 1973 (manufactured or

remanufactured). Tier 0-2 standards are met though engine design methods, without

the use of exhaust gas after-treatment. The 2008 regulation also includes more

stringent emission standards for remanufactured Tier 0-2 locomotives:

a. Tier 0: The first set of standards applies (effective 2000) to locomotives and

locomotive engines originally manufactured from 1973 through 2001, any time

they are manufactured or remanufactured.

b. Tier 1: These standards apply to locomotives and locomotive engines originally

manufactured from 2002 through 2004. These locomotives and locomotive

engines are required to meet the Tier 1 standards at the time of the manufacture

and each subsequent remanufacture.

c. Tier 2: This set of standards applies to locomotives and locomotive engines

originally manufactured in 2005 and later. Tier 2 locomotives and locomotive

engines are required to meet the applicable standards at the time of original

manufacture and each subsequent remanufacture.

2. Tier 3-4 Standards: The second regulation signed on March 14, 2008 introduced

more stringent emission requirements [73 FR 88 25098-25352, 6 May 2008] and is

scheduled to become effective from 2015.

Page 17: Metrolink Fleet Plan

16

a. Tier 3 standards: Near-term engine-out emission standards for newly built and

remanufactured locomotives. Tier 3 standards are to be met using engine

technology.

b. Tier 4 standards: Longer-term standards for newly built and remanufactured

locomotives. Tier 4 standards, expected to require the use of exhaust gas after-

treatment technologies, such as particulate filters for PM control, and urea-SCR

for NOx emission control.

3. Test Cycles: Locomotive emissions measured over two steady-state test cycles,

represent two different types of service including line-haul and switch locomotives.

(Metrolink is regulated under the line haul category.) The duty cycles include

different weighting factors for each of the eight (8) throttle notch modes, which used

to operate locomotive engines at different power levels, as well as for idle and

dynamic brake modes. The switch operation involves much time in idle and low

power notches, whereas the line-haul operation characterized by a much higher

percentage of time in the high power notches, especially notch eight (8).

Locomotive certification and compliance programs include several provisions,

including production line testing (PLT) program, in-use compliance emission testing,

as well as averaging, banking and trading (ABT) of emissions.

4. Fuels: To enable catalytic after-treatment methods at the Tier 4 stage, the EPA

regulated (as part of the non-road Tier 4 rule) the availability of low sulfur diesel fuel

for locomotive engines. Sulfur limit of 500 ppm is effective as of June 2007, sulfur

limit of 15 ppm from June 2012.

EPA EMISSIONS REQUIREMENTS

Tier Level Allowable PM

Discharge

Allowable NOx

Discharge

Non-Tier .32 grams / BHP*hr 13.00 grams / BHP*hr

T0 .22 grams / BHP*hr 8.0 grams / BHP*hr

T2 .18 grams / BHP*hr 5.5 grams / BHP*hr

T3 .08 grams / BHP*hr 5.5 grams / BHP*hr

T3+ 0.075 g / BHP*hr 5.5 grams / BHP*hr

T4 0.03 grams / BHP*hr 1.3 grams / BHP*hr

Table V.2 (source, Metrolink)

Page 18: Metrolink Fleet Plan

17

D. “BAND-AID” Overhauls

“Band-Aid” overhauls for locomotives, referred to as the Service Life Extension Program

is a strategically focused revitalization of specific locomotive functions. The program is

not a “parts changing process” but rather a strategic process that uncovers weaknesses

in the locomotive through intensive diagnostic testing and analysis not typically

performed during routine maintenance. Locomotives exhibit symptoms of “potential”

failure; therefore, this process will reveal problems at the deepest level so technical

personnel can mitigate the problems before they affect reliability. The Service Life

Extension program will allow high mileage locomotives to operate with improved

reliability until a complete renovation is possible.

E. Mid-life Overhauls

Because Metrolink’s oldest 30 units (PH and PHI, and one F40) have not been

overhauled, they are subject to “wear and fatigue” type failures.

1. Failure Types

Many of the items replaced during a mid-life overhaul (typically after 10 years) are

failing at a higher rate. Examples of such parts are main-gen bearings, motorized

switchgear, relays and power contactors, rigid water and air piping, etc.

Additionally, 19 locomotives have HEP engines that are beyond their recommended

over-haul/replacement. These HEP units also have outdated/obsolete control

systems. This causes a high rate of HEP failures resulting in loss of “hotel power” to

the train.

2. Short-term Solutions

Continue rehab of the equipment through the past and on-going capital and

operations rehab programs. As a part of these programs, we have replaced HVACs

(air-conditioning units), turbochargers, traction motors, cooling fans, fuel injectors,

main engine water pumps, etc.

3. Long-term Solutions The locomotive fleet requires a comprehensive overhaul in which all systems are

qualified and/or rebuilt to a level of reliability and efficiency that will be acceptable to

meet the demands of the service. Horsepower is important when determining

service demand because higher horsepower allows the locomotive to pull longer

train consists. Horsepower decreases if problems exist such as poor locomotive

performance due to electrical and mechanical component malfunctions because

they have reached the end of their useful life. Some examples include major

component replacement such as new HEP engine and generators, main generator

reconditioning, upgraded control systems, cab refresh (new carpet, flooring, paint,

Page 19: Metrolink Fleet Plan

18

update switches, interior renewal), rust mitigation and refurbishment of trucks and

traction motors. Estimates, including labor, shipping and contingency repairs are

projected to cost approximately $2 million+.

Long term planning involves consideration of the environment. This plan includes

adherence to legislative dictates for environmental protection.

a. Tier 0 to Tier 2

Currently, Metrolink’s fleet consists of 30 Tier 0, (non tier) and 22 Tier 2

locomotives. The possibility of an all-Metrolink locomotive upgrade option to Tier

2 was reviewed. As background, in 2010, seven (7) F59 PH locomotives were

upgraded to Tier 2 at a cost of $2.4 million each. Metrolink chose this option

because these locomotives required mid-life overhaul. A re-power with a partial

overhaul was viewed as the best way to extend the life of the units. At that time,

Tier 4 technology was not developed. Staff does not recommend upgrading all 30

locomotives to Tier 2 then again to Tier 4 because it requires an engine change,

is more costly, and does not increase reliability.

b. Tier 0 to Tier 3+

This plan originally discussed an upgrade option for the 30 Tier 0 locomotives to be

upgraded to Tier 3+. Tier 3+ is defined as meeting the Tier 3 requirements for PM and

NOx and 80 percent of the NOx requirements for Tier 4, hence “3+”. Tier 3 falls far short

of the more restrictive emissions requirements of Tier 4. Because of the advancing Tier

4 technology, the ability to obtain maximum performance and environmental benefits

and funding constraints, Staff does not recommend this option.

c. Tier 0 to Tier 4

Rapidly advancing technology has allowed the consideration of the Tier 4

upgrade option, which provides added environmental benefits and addresses

fleet reliability issues. To meet Tier 4 requirements and maximum locomotive

performance a complete overhaul or replacement of all components and systems

is required. Locomotives with a complete Tier 4 overhaul will set the stage for

maximum performance and reliability of the fleet. Tier 4 overhaul are

approximately $2.4 million per locomotive.

d. Choosing an Option

In early 2011, Metrolink proposed a new locomotive purchase program that

suggested purchasing 52 new Tier 4 locomotives, estimated costs between $6

million to $8 million each, based on using new concepts such as combining air

quality credits, performance-based contracting of equipment maintenance,

demonstration grants and federal loan programs.

Page 20: Metrolink Fleet Plan

1

Because of emerging technologies and information from several vendors moving

forward with Tier 4 technology, Metrolink staff made another proposal to

investigate Tier 4 funding possibilities, also authorized by the Board in 2011.

Several discussions ensued regarding what would be the most fiscally

responsible for our Member Agencies and provide the most benefits

environmentally (provide the cleanest fleet), efficiently and fulfill future growth

projections. In addition, a locomotive “Tier Level and Timeline” discussion, held

at the November Board meeting, included a comparison between upgrading to

Tier 3+ and Tier 4. Metrolink staff recommended the Tier 4 upgrade/timeline

during this discussion.

It was determined there were four distinct opportunities for fleet upgrades. The

30 Tier 0 locomotives upgrade to Tier 2, Tier 3+ and/or Tier 4; and the 22 Tier 2

locomotives upgrade to Tier 4.

TIER LEVEL COST COMPARISON

PROJECT COSTS NOTES

Tier 0 to Tier 2

(30)

$1.7 M

(+ $800K non-emissions related

upgrades)

2008 pricing, re-power with minimum overhaul ($2.75 M est. 2012 pricing); to upgrade (again) to Tier 4 requires additional costs (average $2.2 M* each) requires engine change and taking equipment out of service a second time

Tier 0 to Tier 3+

(30)

$1.75 M

(+ $800K

non-emissions related

upgrades)

$4.5 M

After upgrading to Tier 3+, use existing 710 engine; to upgrade (again) to Tier 4 requires additional costs ($1.7 M each) requires engine change and taking equipment out of service a second time. New Tier 3+ Locomotive

Tier 0 to Tier 4

(30)

$2.4 M

(+ $800K non-emissions related

upgrades)

$6.5 M

Re-configure PH/PHI includes overhaul New Tier 4 Locomotive

Tier 2 to Tier 4

(22)

$2.2 M*

(Includes non-

emissions related

upgrades)

Re-configure locomotives with limited overhaul

Table V.3

*(7) F59(R) @ $1.7 M each and (15) MP36 @ $2.5 M each

The following document represents the Locomotive Tier 4 upgrade strategy, (tier and timeline as mentioned above) including the potential timeline and funding plan:

Page 21: Metrolink Fleet Plan

Loco_Fleet_Tier_Level_Discussion_Jan_10_AS Confidential Attorney Client Work Product

Metrolink Locomotive Tier Level & Timeline Discussion

Dec 2011 Jan 2012 Oct 2012 Jan 2013 Jan 2014 Jan 2015 Jan. 2016 Jan. 2017

RECOMMENDATION:

Upgrade 30 Locomotives From Tier 0 to Tier 4

Pro: Increased reliability with HP @ 3700/4500 to 5000 (HEP at Tier 4)

Tier 4 provides added environmental benefits

Option may consider more vendor options/competition due to technology development Fulfills longer-term strategy for ridership increases; more HP equals longer train consists

Additional time for development allows for increased funding options such as loans

Con:

Tier 4 technology is under development, analysis continues to be refined Proposed (early 2013) start date delay possible as technology develops

Requires planning for additional Service Life funding until Tier 4 overhauls are complete Requires engine swap, additional engine type added to inventory

Tier 0 Tier 4 (15) PH $3.2 M each (16-20 Cylinder) (14) PHI (1) F40

PH Base Price: $ Estimated costs include main engine, HEP & overhaul PHI Base Price: $ Cat engine (16 Cyl. @ 3700 or 4500 HP -or- 20 Cyl. @ 5000 HP) HEP to Tier 4: $ $3.2 M x 30= $ 105.4 M including sales tax @ 9.75% Overhaul: $ Loco Lease: $350 / day *2 yrs. x 5= $ 1.7 M Agency Costs: @6% $ 6.4 M TOTAL ESTIMATED PROJECT COST: $113.5 M Note: Pricing is for upgrading (30) Tier 0 locomotives to Tier 4, Tier 2 locomotive upgrade not considered in pricing

EMD Tier 0 to Tier 4 estimate and timeline is VERBAL ONLY and for discussion purposes only

Tier 4 technology, development and refinement continues

Page 22: Metrolink Fleet Plan

21

4. Utilization Rate vs. Fleet Size:

Older fleets, which have not been through the recommended mid-life overhaul, tend

to have higher failure rates of all major assemblies (engine power assemblies,

turbochargers, HEP engines, radiators, air compressors, etc.). These added failures

cause the locomotives to spend more time in the shop, as defects are found and

repaired. As a result, dwell times increase for regularly scheduled inspections, and

the numbers of unscheduled “shoppings” also increases. When these factors are

considered overall, a higher “protective spares ratio” is usually required, or, stated

differently, fewer trains can be supported with the same number of (less reliable)

units. As a result, utilization rate decreases.

5. Rehab – Mid-Life Overhaul

The emissions upgrade will include all items that are needed to ensure the

operation of a Tier 4 main engine and HEP (HEP will be at Tier 4.) This will include

the two engines respectively and a number of engine-support subassemblies.

Support items would include new engine cooling fans, new main electrical cabinets,

engine control systems to allow for the application of Fuel injection, etc., possibly

even exterior paint. Overhaul items would also be rolled into the project, to ensure

that all systems receive the rework required for reliable performance. Overhaul

rework will be performed on traction motors and trucks, operator’s cab refresh,

replacement of air compressor, car-body rust mitigation, etc. to add service life.

a. Production limitations for rehabilitation: To upgrade 30 Tier 0 (non-tier)

locomotives, production is expected to be 15-16 units per year for two years.

b. Duration of program and impact: The bulk of the program would be the

conversion of non-tier units to Tier 4, expected to occur over a two-year period.

Phase two (conversion of the 22 Tier 2 units to Tier 4) would likely require

another two years.

c. Locomotive leasing requirements and impact: As locomotives are taken out of

service for rehabilitation work, other locomotives will need to be leased to

maintain flexibility and reliability during the rehab process. When the number of

locomotives undergoing overhaul is determined, leased locomotives are

necessary to maintain service levels. It is expected to require at least five (5)

leased locomotives to meet the power needs of our present operation.

d. Define equipment rehab budget including FY planning; funding for equipment needs, known costs/unknown costs; potential triggers. Current projections indicate $2.4 million needed for the emission upgrade. The overhaul program is in conjunction with the emissions upgrade and estimated to cost approximately $800,000 per locomotive.

Page 23: Metrolink Fleet Plan

22

VI. Funding Discussion

Metrolink had multiple meetings with potential vendors who provided locomotive

manufacturing and maintenance services to discuss re-powering engines to meet Tier 3+

and Tier 4 emissions standards. At the same time the re-powering would occur, a mini-

overhaul of the engine would also need to be scheduled.

Separately, Metrolink staff has been working with the Southern California Air Quality

Management District (SCAQMD) to determine how much funding might be available in Carl

Moyer funding for this project.

Of the 52 locomotives in the fleet, 30 will need to be re-powered from Tier 0 to Tier 4. This

plan previously discussed Tier 3+ as an option, however, the recommendation has moved

to Tier 4. For future planning, the remaining 22 locomotives will need re-powering from Tier

2 to Tier 4. In both cases, SCAQMD funding could be eligible for re-powering costs, with

the balance coming from Metrolink funding sources. The result would be Metrolink as the

first commuter railroad in the nation with a standardized locomotive Tier 4 fleet.

The following sources have been identified for the locomotive engine upgrade to Tier 4

engines:

A. South Coast Air Quality Management District: The SCAQMD manages incentive

programs that provide monetary grants to private companies and public agencies that

clean up their heavy-duty engines more than required by air pollutions standards. The

Carl Moyer Program specifically targets projects that reduce emissions from heavy-duty

on and off-road equipment such as construction, farm equipment, marine vessels and

locomotives. These grants are determined based on the “incremental cost” and the

emission benefits of the project. The program currently generates approximately $135

million annually statewide from three sources: smog abatement fee, new tire purchase

and motor vehicle registration.

The following is a description of three sources of Carl Moyer funding:

1. Smog Abatement: Fee SB 1107 adjusted the smog abatement fee from $6 to $12

while extending the newer-vehicle Smog Check exemption. This additional fee is

directed to fund the Carl Moyer Program, securing up to $60 million in annual

funding for the program). This legislation does not have a sunset date.

2. Tire Fee: AB 923 adjusted the tire fee assessed on purchasers of new tires from $1

to $1.75 per tire. The adjustments to the tire fee translate to up to $25 million

available for the Carl Moyer Program. This legislation will sunset in 2015.

3. Motor Vehicle Registration Fee: AB 923 also gave air district governing boards the

authority to increase the vehicle registration surcharge by $2 to pay for four specific

clean air incentive program.

Projects eligible for grants under the Carl Moyer Program:

Page 24: Metrolink Fleet Plan

23

The Agricultural Assistance Program

The new purchase of school buses pursuant to the Lower-Emission School Bus

Program

An accelerated vehicle retirement or repair program

To date, 20 statewide air districts have adopted the $2 Motor Vehicle Registration fee.

In FY 11/12, AQMD estimates that the air districts will receive approximately $50 million

from this fee. This legislation will sunset in 2015, whereby funding for this program by

this resource will cease. The timeline for submitting an expedient application to obtain

funding is consistent with the manufacturer’s ability to do the work and our ability to

cycle in our locomotives for the upgrades.

B. Locomotive Rehab Funding

Locomotive funding, managed through the annual SCRRA rehabilitation budget, is

approved by the member agencies. These funds, provided by member agencies

annually, are mostly composed of federal formula funds and local sources. The latter is

primarily made up of county sales tax measures designated for transportation purposes.

Within this category there are three (3) sets of rehab funding:

1. State Proposition 1B Public Transit Modernization Improvement Safety and

Efficiency Account (PTMISEA): Metrolink receives funding from this source based

on revenue generated in each member county. These funds come directly to

Metrolink with authorization from its member agencies. Metrolink staff is

recommending programming a portion of these funds to the Tier 4 upgrade project.

Receipt of the majority of these funds is dependent on future bond sales. This

funding is very flexible in that it does not require a match and can be reviewed by

member agencies and reprogrammed as often as once a year.

2. Carryover from previous years: this represents unspent funds designed for

rehabilitation purposes available from previous budget years.

3. Locomotive rehab funding for FY 10/11 and FY 11/12: These funds have been

approved in annual budgets for the respective years, FY 10/11 and FY 11/12. The

higher amount for FY 11/12 as compared to other years reflects the priority that

locomotive rehab was given in the current year approved budget. $5 million of FY

11/12 rehab funding will be used to keep the existing locomotive fleet functioning

until each unit goes through the re-power program.

4. Locomotive rehab funding FY 12/13 - FY 18/19: The annual amount shown in future

budget years is based on recent historic annual levels for locomotive rehab. To

ensure this program is fully funded, commitments from seven (7) future fiscal years

are planned. It is important to note that the board would have to take action each

fiscal year to approve this funding as SCRRA only budgets on a yearly basis.

Page 25: Metrolink Fleet Plan

24

The following represents ten years of budget history from its five Member Agencies:

SCRRA REHABILITATION/RENOVATION NEW PROJECTS

FY LACMTA OCTA RCTC SANBAG VCTC

TOTAL BUDGET

2002-2003 $10,802 $5,100 $686 $2,979 $1,500 $21,068

2003-2004 $8,817 $2,195 $526 $3,720 $1,800 $17,058

2004-2005 $10,800 $6,980 $974 $3,090 $1,200 $23,044

2005-2006 $14,248 $4,329 $2,251 $4,552 $1,628 $27,007

2006-2007 $14,458 $6,432 $1,201 $4,100 $1,500 $27,691

2007-2008 $15,458 $5,975 $1,453 $3,358 $1,500 $27,742

2008-2009 $16,058 $18,865 $1,557 $5,213 $1,851 $43,543

2009-2010 $16,298 $17,500 $3,067 $6,148 $2,060 $45,072

2010-2011 $8,000 $4,968 $1,225 $4,950 $1,500 $20,643

2011-2012 $7,892 $3,841 $1,256 $2,480 $1,500 $16,968

Table VI.1

Table VI.2

*Data source: SCRRA Adopted Budget Documents, Tables VI.1 & 2

$0

$5,000

$10,000

$15,000

$20,000

$25,000

$30,000

$35,000

$40,000

$45,000

$50,000

VCTC

SANBAG

RCTC

OCTA

LACMTA

SCRRA Rehab Budgets by County ($K)

Excludes Other External Funds such as State, Amtrak, UPRR, Leveraged Lease, etc.

Page 26: Metrolink Fleet Plan

25

C. Notes on Rehab Funding

The fleet plan reflected in this document is structured to maximize the amount of work

that can be performed with rehabilitation/renovation funds from Metrolink’s Member

Agencies each year. Staff has based the availability of rolling stock rehab funds on

average member contributions over the past several years. It should be noted that the

overall agency rehabilitation/renovation budgets for last two years are significantly lower

than years prior to FY 10/11. For the last two years, the annual rehab budgets are $22

million dollars in FY 10/11, and $18 million dollars in FY 11/12. Member Agency

contributions are determined by type and location of project.

Systemwide project expenses are allocated to each Member Agency based on a well-

established “All-Share” formula. The funds that are made available to Metrolink for

rehab include local transportation funds, Federal 5307 and 5309 funds, state PTA

funds, PTMISEA funds, leveraged lease proceeds, and AQMD funds for specific air

quality projects, Federal funds are matched against local contributions, and in the case

of FY 11/12, Toll Revenue Credits available for Member Agencies. At the federal level,

section 5307 and section 5309 funds are allocated to Urbanized Areas (UZAs)

nationwide based on funding formulae, and operating statistics such as Directional

Route Miles, Revenue Vehicle Miles, and Passenger Miles. Metrolink reports those

statistics for Metrolink operations each year and this helps bring federal transit dollars

into the Southern California region. Funds allocated to local-area UZAs are further sub-

divided and allocated to each county, and are then available to the Member Agencies to

be programmed to projects. Some Member Agencies use these funds on the Metrolink

system while others do not, opting to provide other types of funds for their share of the

annual rehabilitation/renovation budget.

Historically the funds that comprise agency rehabilitation/renovation budget are applied

to three major categories: Signal/Communications, Maintenance-of-Way (Track and

Structures) and Mechanical. Occasionally rehab funds also go to a range of IT projects

including ticket machine projects, rubber-tire and maintenance vehicle replacement and

facilities projects. Metrolink’s Mechanical department has received $4.7 million in FY

10/11, and $6.4 million dollars in FY 11/12. The higher amount in FY 11/12 recognized

the increasing rehabilitation needs of an aging locomotive fleet, and reflected

management’s desire to maintain, if not improve equipment reliability. This funding level

appears to be sustainable and allows remaining funds allocated to the other project

categories.

The Metrolink Fleet Plan is based on using a sustainable amount of funds focused on

specific rehabilitation requirements. This plan suggests that $4 million per year should

go to specific overhaul projects while the “Band-Aid” costs will be approximately another

$1 million per year. To the extent that other areas of the organization can defer

rehabilitation on other parts of the system, Metrolink may be able to provide additional

funding. However, that is a balance that will be addressed in the future

rehabilitation/renovation program, of which, the Fleet Plan is but one part.

Page 27: Metrolink Fleet Plan

1

Attachments: Five-Year Rolling Stock Rehabilitation Plan Draft Funding Plan for 30 Locomotive Engine Repowers from Tier 0 to Tier 4 Metrolink Bombardier/Sentinel Car Storage Plan 12/2011

Page 28: Metrolink Fleet Plan

ROLLING STOCK REHABILITATION PLAN

RAIL CARS 5-YEAR PLAN (UNITS)

Rehabilitation ItemsFY 11-12

(Present) FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17 TOTAL

1 Basic Rehabilitation (HVAC) 0 0 Coaches 20 Coaches 20 Coaches 20 Coaches 37 Coaches 97 Cars

2 Mid-Life Overhaul 4 Coaches 4 Cars

LOCOMOTIVES 5-YEAR PLAN (UNITS)

1 Basic Rehabilitation10 EMD

Locomotives

10 EMD

Locomotives

10 EMD

Locomotives30 Locomotives

2Upgrade 30 EMD Locomotives from Tier 0 to Tier

4, incl Reliability Improvments

5 EMD

Locomotives

15 EMD

Locomotives

10 EMD

Locomotives30 Locomotives

RAIL CARS REHABILIBATION COSTS ($M 2011 CONSTANT DOLLARS)

Rehabilitation ItemsFY 11-12

(Present) FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17 TOTAL

1 Basic Rehabilitation (HVAC) $0.40 $0.40 $0.40 $0.59 $1.79

2 Mid-Life Overhaul $5.82 $5.82

TOTAL CAR REHAB (Estimated Cost) $0.00 $0.00 $0.40 $0.40 $0.40 $6.41 $7.61

LOCOMOTIVE REHABILIBATION COSTS ($M 2011 CONSTANT DOLLARS)

1 Basic Rehabilitation (10/year using 11-12 Funds) $5.00 $5.00

2Upgrade 30 EMD Locomotives from Tier 0 to Tier

4, incl Reliability Improvments $18.92 $56.77 $37.84 $113.53

TOTAL LOCOMOTIVE REHAB (Estimated Cost) $5.00 $18.92 $56.77 $37.84 $0.00 $0.00 $118.53

TOTAL EXPENSES ($M IN 2011 CONSTANT DOLLARS)

CAR & LOCOMOTIVE COST ($M) $5.0 $18.9 $57.2 $38.2 $0.4 $6.4 $126.1

CUMULATIVE COST ($M) $5.0 $23.9 $81.1 $119.3 $119.7 $126.1

POTENTIAL FUNDING SOURCES

RAIL CAR REHABILIBATION FUNDING

Rehabilitation ItemsFY 11-12

(Present) FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17 TOTAL

1Basic Rehabilitation - Leveraged Lease

Revenues$0.40 $0.40 $0.40 $0.59 $1.79

2 Midlife Overhaul - PTMISEA $4.77 $4.77

2 Midlife Overhaul - Additional FTA funds or loan $1.04 $1.04

TOTAL CAR REHAB FUNDING $0.00 $0.00 $0.40 $0.40 $0.40 $6.41 $7.61

LOCOMOTIVE REHABILIBATION FUNDING

1Basic Rehabilitation - FY 11-12 Rolling Stock

Rehab Funds In Budget$5.00 $5.00

2Upgrade 30 EMD Locomotives - Rolling Stock

Rehab Funds & Leveraged Lease$6.91 $5.32 $5.00 $5.00 $22.22

2Upgrade 30 EMD Locomotives - Loan &

Incentives$9.33 $28.00 $18.67 $56.01

2 Upgrade 30 EMD Locomotives - PTMISEA $13.53 $2.39 $2.39 $18.30

2Upgrade 30 EMD Locomotives - Rehab Program

Carryover and Other Rehab Funds$10.00 $10.00

2 Upgrade 30 EMD Locomotives - Gen 2 Sale $7.00 $7.00

TOTAL LOCOMOTIVE REHAB FUNDING $25.43 $14.65 $45.39 $33.06 $0.00 $0.00 $118.53

TOTAL POTENTIAL FUNDS

$11.91M is prior-year carryover + FY 10-11 + FY 11-12 rolling stock rehab funds

CAR & LOCOMOTIVE FUNDING ($M) $25.4 $14.6 $45.8 $33.5 $0.4 $6.4 $126.1

CUMULATIVE FUNDING ($M) $25.4 $40.1 $85.9 $119.3 $119.7 $126.1

Page 29: Metrolink Fleet Plan

DRAFT FUNDING PLAN FOR 30 LOCOMOTIVE ENGINE REPOWERS FROM TIER-0 TO TIER-4Updated 1-10-2012

Cost: Overhaul Cost

Cost Incl Sales Tax @

9.75%

$3.2M for C175 Cat or Cummins engine (30 Locomotives) 96,000,000$ 105,360,000$

HEP engine upgrade included in overhaul price -$ -$

$350/day to lease 5 locomotives for 2.5 years while repower

underway + maintenance (non-taxable) 1,746,875$ 1,746,875$

Sub - Total 97,746,875$ 107,106,875$ Agency Costs @ 6% 6,426,413$

Total Cost 113,533,288$

Revenue:

Loan & Incentives* 56,009,179$

Locomotive Rehab Carryover from prior years + Locomotive Rehab FY

10-11 + Locomotive Rehab FY 11-12 (Balance) 6,906,000$

Locomotive Rehab for Service Life Extension Program - $5.0M/year for

3 years (FY 12-13, FY 13-14, FY 14-15) 15,000,000$

Other Rehab Project Carryover & Possible Rehab Project Deferrals 10,000,000$

State Prop 1B (PTMISEA) Renov/Rehab Locomotive Life Extension (FY

09/10=$1,000,000, 10/11=$12,528,404, 13/14=$2,387,214,

14/15=$2,387,214) 18,302,832$

Sale of Gen 2 Rail Cars 7,000,000$

Leveraged Lease Revenues 315,277$

Total Revenue 113,533,288$

Difference between Cost and Revenue -$

*Loan & Incentives

RRIF loan interest payments are excluded from the funding analysis

RRIF loan interest rate is equal to the cost of borrowing to the government

RRIF loan term can be up to 35 years

RRIF loans are available to improve, or rehabilitate intermodal, rail equipment or facilities

(Combined amount needed in the form of incentive payments and a loan. Most likely loan source is the FRA Railroad

Rehabilitation & Improvement Financing (RRIF) program.

Page 30: Metrolink Fleet Plan

Bombardier/Sentinel Rail Car Storage Plan

SCRRA Storage LocationsRail Car

Capacity

Rail Cars

in StorageSecurity April M Ju J A S O N Dec Jan F M A M Ju J A S O N Dec Jan F M A M Ju

Keller Yard (2) 18 18 Required 18

Moorpark station 18 15 Fenced 6 9 3

Central Maintenance Facility (3) 18 0 Provided 3 1

Saugus Siding (2,670 Ft) (4) 30 0 Fenced 5 5 5 3 5 5

MOW Spur Laguna Niguel 0 0 Fenced

MOW Spur Fullerton (1,000 Ft) 0 0 Fenced

MOW El Toro (1,500 Ft) 0 0 Required

Siding at Katella (3,000 Ft) 0 0 Required

Total Rail Car storage

capacity 84

Rail Cars currently stored 33 6 18 9

Rail Cars to be stored 35 5 5 8 3 5 5 3 1

NOTES:1. Current estimate is for 68 Bombardier rail cars to be stored after all 137 Rotem cars are in service (1Q 2013).

The 23 second generation rail cars estimated to be sold by June 2012.

The 15 NJT rail cars currently in storage at Saugus, estimated to be sold by June 2012.

2. After the PTC program is completed in 2013, the Keller yard storage capacity will increase to 25 rail cars. Currently there is security due to PTC program.

3. Storage at CMF will be available when rail car maintenance at EMF will start in 2013.

4. Additional services in 2012:

By March 2012 one 4 car train will be used for "Fullerton to Newhall" train.

By March 2012 one 4 car train will be used for the IEOC line.

By March 2012 three 4 car trains will be use for Perris Valley (PVL) line.

20132011 2012