Metro North, Dublin - Construction Explained

97
Metro North Dublin Construction 2.4bn Included Route Programme Graphic Tunnelling Construction Stations Construction Cost Details Lengths Overall 18 km Tunnel 7.5 km Cut & Cover 2.7 km Viaduct 2.25 km Road Level 5.5 km Stations 15 Nr. Underground 9 Nr. Road Level 6 Nr. Tunnels & Underground Stations Route 3D image to show Sequence, Method & Plant. David H Moloney 29 th June 2016 Purpose of presentation to give the Public, Stakeholders and Politicians an understanding of the Construction, Cost and Timeline David H Moloney Schematic Longitudinal Profile Project Execution Plan

Transcript of Metro North, Dublin - Construction Explained

Page 1: Metro North, Dublin  - Construction Explained

Metro North Dublin – Construction €2.4bn

IncludedRoute Programme GraphicTunnelling ConstructionStations ConstructionCost

DetailsLengths

Overall 18 kmTunnel 7.5 kmCut & Cover 2.7 kmViaduct 2.25 kmRoad Level 5.5 km

Stations 15 Nr.Underground 9 Nr.Road Level 6 Nr.

Tunnels & Underground Stations

Route

3D image to show Sequence, Method & Plant.

David H Moloney

29th June 2016

Purpose of presentation to give the Public,

Stakeholders and Politicians an understanding of

the Construction, Cost and Timeline ⓒ David H Moloney

Schematic Longitudinal Profile

Project Execution Plan

Page 2: Metro North, Dublin  - Construction Explained

Table of Contents

Page 3: Metro North, Dublin  - Construction Explained

Overview

Page 4: Metro North, Dublin  - Construction Explained

Route of Metro Northⓒ David H Moloney

Page 5: Metro North, Dublin  - Construction Explained

Schematic with Principal QuantitiesDavid H Moloney

Schematic Longitudinal Profile

ⓒ David H Moloney

Page 6: Metro North, Dublin  - Construction Explained

Programme - Time Chainage Diagram

ⓒ David H Moloney

Page 7: Metro North, Dublin  - Construction Explained

Tunnels & Underground Stations

TBM TBM

Tunnel TunnelTunnelViaduct Along Street

Programme Animation

ⓒ David H Moloney

Schematic Longitudinal Profile

Page 8: Metro North, Dublin  - Construction Explained

Cost Comparisons of Metro Projects

Dubai Route 2020UAE (To Start)

Red Line North DohaQatar (In Progress)

Red Line South DohaQatar( In Progress)

Metro NorthDublin

(Proposed)

Dart UndergroundDublin (Proposed)

Port Tunnel Dublin

(2005)

Overall Cost €2,450 million €1,803 million €1,500 million €2,400 million €2,000 million ? €752 million

Cost per km €158 million /k m €140 million / km €108 million / km €134 million / km €400 million / km ? €134 million / km

Overall Length 15.5 km 13 km 14m 18 km 5 km 5.6 km

Tunnel 4 kmSingle Tunnel

11.6 km Twin Tunnels

14 kmTwin Tunnels

7.5 km Twin Tunnels

5 km Twin Tunnel

4.5 kmRoad Tunnel x 2

Cut & Cover 0 2.7 km 0

Elevated 10.5 km 2.2 km 0 Not applicable

Road Level 0 5.5 km 0

Stations 7 Nr. 7 Nr. 5 Nr. 14 Nr. 3 Nr. Not applicable

Capacity 13,000 Passengers per hour

19,800 Passengers per hour

? Not applicable

ⓒ David H Moloney

Page 9: Metro North, Dublin  - Construction Explained

Advantages of Rail Benefits of Metro to commuters

1. Time saving for commuters 4. Reduction in accident

2. Reliable and safe journey 5. Reduced fuel consumption

3. Reduction in atmospheric pollution 6. Reduced traffic congestion

Page 10: Metro North, Dublin  - Construction Explained

Contractor’s General Items

Page 11: Metro North, Dublin  - Construction Explained

Contractor’s Temporary Site Facilities

ⓒ David H Moloney

Brief Description

Contractors Site facilities comprise:Offices, Canteens, Toilets, Drying Rooms, Stores, Plant Yard, generators and Workshops.

Ge

ne

ral It

em

s

Page 12: Metro North, Dublin  - Construction Explained

Concrete Batching Plant David H Moloney

ⓒ David H Moloney

Concrete batching plant comprises -concrete mixer, control cabin, silos for cement and fly ash, aggregate bins and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks. The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage capacity to match two days concrete production

Page 13: Metro North, Dublin  - Construction Explained

Quarry & Aggregate Production

3D image to show Sequence, Method & Plant.

ⓒ David H Moloney

Page 14: Metro North, Dublin  - Construction Explained

Reinforcement Cutting & Bending Yard David H Moloney

ⓒ David H Moloney

Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine

Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site

Page 15: Metro North, Dublin  - Construction Explained

Site Hoarding examples

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 16: Metro North, Dublin  - Construction Explained

Wheel Wash Drive-throughG

en

era

l It

em

s

Page 17: Metro North, Dublin  - Construction Explained

Weighbridge & Sheeting Access

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 18: Metro North, Dublin  - Construction Explained

Sheet Pile Temporary Shaft

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Sheet Pile Temporary shaft is used to enable an excavation for a deep structure.The construction sequence is:Install sheet-piles.Excavate and install bracing.Excavate to final level.Construct concrete structure.Backfill, remove bracing and sheet-piles

Page 19: Metro North, Dublin  - Construction Explained

Sheet Pile Temporary Shaft

ⓒ David H Moloney

Ge

ne

ral It

em

s

3D Animation to show Sequence

Page 20: Metro North, Dublin  - Construction Explained

FalseworkG

en

era

l It

em

s

Brief Description

Falsework to support Bridge deck formwork

Page 21: Metro North, Dublin  - Construction Explained

Dewatering

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Construction dewatering is the removal or drainage of

groundwater and or surface / rain water usually by

pumping to keep the works dry.

Page 22: Metro North, Dublin  - Construction Explained

Dewatering

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 23: Metro North, Dublin  - Construction Explained

Dewatering by Wellpoints

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 24: Metro North, Dublin  - Construction Explained

Dust Suppression

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 25: Metro North, Dublin  - Construction Explained

Temporary Fence type 2

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Temporary fence on precast beam for airport.

Page 26: Metro North, Dublin  - Construction Explained

Traffic Management

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Traffic management plans are necessary when working on or beside roads

Page 27: Metro North, Dublin  - Construction Explained

Traffic Management - Realign Motorway under new Bridges

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 28: Metro North, Dublin  - Construction Explained

Health, Safety & Environmental

Page 29: Metro North, Dublin  - Construction Explained

Existing Underground Utilities

ⓒ David H Moloney

Ea

rth

wo

rks

Brief Description

Before digging

establish the location

and route of

underground utilities.

Locator to find Utilities

Spray Paint to mark pavement

Page 30: Metro North, Dublin  - Construction Explained

Existing Underground Utilities & Overhead Cables - Safety Measures

ⓒ David H Moloney

Ea

rth

wo

rks

Page 31: Metro North, Dublin  - Construction Explained

Safety Precautions

Page 32: Metro North, Dublin  - Construction Explained

HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of

current HSE Issues and historical trends

Page 33: Metro North, Dublin  - Construction Explained

Environmentally Friendly Site Air, Noise, Water & Soil Pollution

Page 34: Metro North, Dublin  - Construction Explained

Water Pollution PreventionG

en

era

l It

em

s

Page 35: Metro North, Dublin  - Construction Explained

Geotechnical

Page 36: Metro North, Dublin  - Construction Explained

Diaphragm Wall Construction - Sequence, Plant & Methods

3D image to show Sequence, Method & Plant.

For construction details see my YouTube Channel

ⓒ David H Moloney

Page 37: Metro North, Dublin  - Construction Explained

Earthworks

Page 38: Metro North, Dublin  - Construction Explained

Tunnels & Underground Stations

3D image to show Sequence, Method & Plant.

David H Moloney

ⓒ David H Moloney

Page 39: Metro North, Dublin  - Construction Explained

Excavate & Load, Cart, Tip & Return

Brief Description

Cycle Time for 7km haulage distance using an Excavator 45 tonne weight and Dumper with a 40 tonne capacity, the cycle time is 34 minutes

Ea

rth

wo

rks

7 minutes

14 minutes

3 minutes

14 minutes 7 km

7 km

Page 40: Metro North, Dublin  - Construction Explained

Underground Station Excavation

Page 41: Metro North, Dublin  - Construction Explained

Underground Station Construction

Page 42: Metro North, Dublin  - Construction Explained

Rock Excavation Underground

Excavate with Roadheader

Drill & Fit Rock Bolts

Spray Mortar as Lining

Excavators with Rock Breaker& Rock Rotary Cutter

Roadheader

ⓒ David H Moloney

Using Mining Techniques

Page 43: Metro North, Dublin  - Construction Explained

Bed Rock - Type & Depth

Ground ConditionsThe limestone bedrock is between 5 and 25 metres below ground level. The overlying deposits are generally boulder clay with thin layers of sand and gravel. The water table is between 2 and 4 metres below ground level.The Bedrock Geology Map of Ireland, gives the rock as limestone and mudstone, along the tunnel route.

Page 44: Metro North, Dublin  - Construction Explained

Rock - Excavability

Brief Description

The excavability of rock depends

mainly on the rock strength and the

layer thickness. This diagram shows

excavation methods for rock of

various strengths and thicknesses,

with a free face.

ⓒ David H Moloney

Ea

rth

wo

rks

Page 45: Metro North, Dublin  - Construction Explained

Station Excavation - Soil on Rock Situation

Rock Nailing, Rock breaking & Excavation

ⓒ David H Moloney

Page 46: Metro North, Dublin  - Construction Explained

Concrete

Page 47: Metro North, Dublin  - Construction Explained

Tunnel Wall Segments Casting

Clean Mould

Lift Precast Segment out of mould

after 18 hours.

Reinforcement

fabricate

Reinforcement

into Mould

Concreting

Segment Storage

Casting Cycle Time 24 hrs

ⓒ David H Moloney

Page 48: Metro North, Dublin  - Construction Explained

Tunnel Precast Segments

Page 49: Metro North, Dublin  - Construction Explained

Reinforced Wall Construction Sequence

ⓒ David H Moloney

Co

ncre

te

Brief Description

The sequence to construct a reinforced concrete wall is as

follows:

Tie the reinforcement.

Erect stop-ends and the wall shutters.

Pour and vibrate the concrete mix.

Remove the shutters after the concrete has hardened.

.

Cycle Time Pour per Day

Page 50: Metro North, Dublin  - Construction Explained

Reinforced Wall Construction Sequence

ⓒ David H Moloney

Co

ncre

te

Page 51: Metro North, Dublin  - Construction Explained

Reinforced Structure Construction Sequence

ⓒ David H Moloney

Co

ncre

te

Brief Description

The general sequence to construct a reinforced concrete tank

is as follows-

1. Construct the floor and wall panels in a hit and miss pattern.

2. Construct the floor and wall corners and T shape panels.

3. Construct the roof working outwards from the back.

Page 52: Metro North, Dublin  - Construction Explained

Reinforced Structure Construction Sequence David H Moloney

ⓒ David H Moloney

Page 53: Metro North, Dublin  - Construction Explained

Bridge & Post-tensioningC

on

cre

te

Brief Description

The sequence to post-tension a bridge

deck is as follows;

Fix the ducts and anchorages.

Install the stressing strand.

Concrete the deck.

Stress the strands and lock at

anchorages.

Grout the ducts.

Page 54: Metro North, Dublin  - Construction Explained

Bridge & Post-tensioningC

on

cre

te

Page 55: Metro North, Dublin  - Construction Explained

Bridge & Post-tensioningC

on

cre

te

Page 56: Metro North, Dublin  - Construction Explained

Bridge Construction Sequence David H Moloney

Piling Surcharge Abutments

Remove Surcharge AbutmentsDeck centre

Post-tensioning Fascia & Waterproof deckComplete Bridge

PiersOverview

Deck Ends

Images with Schematic 3D view, Photos & Timeline

ⓒ David H Moloney

Page 57: Metro North, Dublin  - Construction Explained

Post-tensioning Bridge Deck David H Moloney

Page 58: Metro North, Dublin  - Construction Explained

Waterproofing Spray on SystemM

isce

llan

eo

us

Page 59: Metro North, Dublin  - Construction Explained

Waterproofing Spray on TestsM

isce

llan

eo

us

Page 60: Metro North, Dublin  - Construction Explained

Underground Stations David H Moloney

ⓒ David H Moloney

Page 61: Metro North, Dublin  - Construction Explained

Large Floor Concrete Pour

Page 62: Metro North, Dublin  - Construction Explained

Rail ViaductC

on

cre

te

Brief Description

Shown is the construction of a light rail viaduct where

an overhead gantry was used to lift and place the

precast concrete viaduct segments.

Page 63: Metro North, Dublin  - Construction Explained

Viaduct Construction

3D image to show Sequence, Method & Plant.

For construction details see my YouTube Channel

David H Moloney

ⓒ David H Moloney

Page 64: Metro North, Dublin  - Construction Explained

Viaduct Construction David H Moloney

ⓒ David H Moloney

Page 65: Metro North, Dublin  - Construction Explained

Viaduct Segments Launching

ⓒ David H Moloney

Page 66: Metro North, Dublin  - Construction Explained

Viaduct Segments Casting David H Moloney

Casting Method

The concrete segments are manufactured

using the short-line, match-casting method.

Match-casting is when sequential segments are poured against the previous cast segment, this ensures that the segments will fit perfectly on site. Horizontal and vertical curves are achieved by setting the cast segment at a rotation in either or both axis to the mould used to cast the next segment.

ⓒ David H Moloney

Page 67: Metro North, Dublin  - Construction Explained

Viaduct Segments – Short-line, Match Casting Method

David H MoloneyMatch-casting is when sequential segments are poured against the previous cast segment, this ensures that the segments will fit perfectly on site.

Cycle Time 24 hrs

Page 68: Metro North, Dublin  - Construction Explained

Piling

Page 69: Metro North, Dublin  - Construction Explained

Piling Construction - Plant & Methods

Brief Description

Piling Plant, Equipment and Material;

Crawler Crane, Piling Hammer, Temporary Casing,

Piling Rig, Concrete Pump, Concrete Mixer Trucks,

Tremie Pipe and Reinforcement Cage

Pili

ng

Page 70: Metro North, Dublin  - Construction Explained

Piling Construction - Plant, Methods & SequenceP

ilin

g

Page 71: Metro North, Dublin  - Construction Explained

Piling Construction - Plant & MethodsP

ilin

g

Page 72: Metro North, Dublin  - Construction Explained

Piling Construction - Vertical PilesP

ilin

g

Page 73: Metro North, Dublin  - Construction Explained

Piling Construction - Raking PilesP

ilin

g

Page 74: Metro North, Dublin  - Construction Explained

Piling Construction - Raking PilesP

ilin

g

Page 75: Metro North, Dublin  - Construction Explained

Pile Load Test

ⓒ David H Moloney

Pili

ng

Brief Description

A jack is used to load the pile in steps and

gauges measure any settlement.

Page 76: Metro North, Dublin  - Construction Explained

Secant Pile Construction - Sequence, Plant & Methods

3D image to show Sequence, Method & Plant.

For construction details see my YouTube Channel

ⓒ David H Moloney

Page 77: Metro North, Dublin  - Construction Explained

Roads & Paving

Page 78: Metro North, Dublin  - Construction Explained

Asphalt Batching YardR

oa

ds &

Pa

vin

gs

Page 79: Metro North, Dublin  - Construction Explained

Road Construction Sequence Animation

Page 80: Metro North, Dublin  - Construction Explained

Tunnel

Page 81: Metro North, Dublin  - Construction Explained

Tunnel Design

Twin Tunnels single track with Cross passages at 250m intervals for emergency evacuation

Tunnels in rock to avoid ground & building settlement. Depth 25 metres on average

ⓒ David H Moloney

Page 82: Metro North, Dublin  - Construction Explained

Cut & Cover Tunnel Construction

Sequence -Traffic and utilities are diverted, excavate trench, construct & backfill to bury.

To prevent the faces of the excavation from collapsing, different measures are used –

batter the faces, diaphragm walls, secant piles or a combination of soil nailing and

shotcreting.

Page 83: Metro North, Dublin  - Construction Explained

Ramp Construction

Sequence -Traffic and utilities are diverted, excavate, construct and backfill to sides.

To prevent the faces of the excavation from collapsing, different measures are used – batter

faces, diaphragm walls, secant piles or a combination of soil nailing and shotcreting.

ⓒ David H Moloney

Page 84: Metro North, Dublin  - Construction Explained

Tunnel Boring Machine (TBM)

Cutting Head rotates to Dig

Excavated material removed by conveyor belt

Lifting muck to surface with skip

Placing Concrete Segments

Page 85: Metro North, Dublin  - Construction Explained

Tunnel Boring Machine (TBM)

Cutting Head rotates

7 nr. Precast segments form rings that line the tunnel Excavated material removed

by conveyor belt

ⓒ David H Moloney

Page 86: Metro North, Dublin  - Construction Explained

Tunnel Fit-out Rail, Electricals, Ventilation

Page 87: Metro North, Dublin  - Construction Explained

Tunnel Fit-out

Install Sleepers & Rails

Concrete Batching Train for Floor Slab

Drilling Machine for Utilities Brackets

Page 88: Metro North, Dublin  - Construction Explained

Commissioning, Testing, Handover & Opening

Purpose to test and ensure that everything (e.g. trains, escalators, lifts, ticket barriers) works as it should.

ⓒ David H Moloney

Page 89: Metro North, Dublin  - Construction Explained

Miscellaneous Works

Page 90: Metro North, Dublin  - Construction Explained

Fencing

ⓒ David H Moloney

Sequence of Construction

Clear Scrub & Grade ground

Fix Corner & Strainer Posts

Fix Intermediate Posts

Fix Line Wire, Chain-link & Razer wire

Concrete ground beam

Page 91: Metro North, Dublin  - Construction Explained

Progress Monthly, Monitoring & Reporting - DashboardDashboard is a single page, graphical representation of current

progress and historical trends

Page 92: Metro North, Dublin  - Construction Explained

Histogram Charts for Resources & Outputs

Concrete, Manpower, TBM,

Manpower per Discipline Concrete per Location

Numbers for each month of the Project Quantity for each month of the Project

ⓒ David H Moloney

Page 93: Metro North, Dublin  - Construction Explained

Plant & Equipment List & Worker’s Job Titles

ⓒ David H Moloney

Page 94: Metro North, Dublin  - Construction Explained

Organogram

Brief Description

Shown are the line and

lateral relationships

between the various team

members and their relative

position in the site

organisation.

Page 95: Metro North, Dublin  - Construction Explained

Other Projects

Page 96: Metro North, Dublin  - Construction Explained

Luas – Dublin, Tram / Light Rail System Construction Sequence & Methods

Install Traffic Control Fencing & Welfare Facilities Divert Underground Utilities Excavate

Prepare Formation Reinforcement & Rails Paving

Paving Information Sign Trams in Operation Trams in Operation

Reinforcement & Rails

ⓒ David H Moloney

Page 97: Metro North, Dublin  - Construction Explained

Production by David H Moloney

See my YouTube Video on Dublin Metro North

My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ

ⓒ David H Moloney