Metro North, Dublin - Construction Explained
-
Upload
david-h-moloney -
Category
Engineering
-
view
900 -
download
2
Transcript of Metro North, Dublin - Construction Explained
Metro North Dublin – Construction €2.4bn
IncludedRoute Programme GraphicTunnelling ConstructionStations ConstructionCost
DetailsLengths
Overall 18 kmTunnel 7.5 kmCut & Cover 2.7 kmViaduct 2.25 kmRoad Level 5.5 km
Stations 15 Nr.Underground 9 Nr.Road Level 6 Nr.
Tunnels & Underground Stations
Route
3D image to show Sequence, Method & Plant.
David H Moloney
29th June 2016
Purpose of presentation to give the Public,
Stakeholders and Politicians an understanding of
the Construction, Cost and Timeline ⓒ David H Moloney
Schematic Longitudinal Profile
Project Execution Plan
Table of Contents
Overview
Route of Metro Northⓒ David H Moloney
Schematic with Principal QuantitiesDavid H Moloney
Schematic Longitudinal Profile
ⓒ David H Moloney
Programme - Time Chainage Diagram
ⓒ David H Moloney
Tunnels & Underground Stations
TBM TBM
Tunnel TunnelTunnelViaduct Along Street
Programme Animation
ⓒ David H Moloney
Schematic Longitudinal Profile
Cost Comparisons of Metro Projects
Dubai Route 2020UAE (To Start)
Red Line North DohaQatar (In Progress)
Red Line South DohaQatar( In Progress)
Metro NorthDublin
(Proposed)
Dart UndergroundDublin (Proposed)
Port Tunnel Dublin
(2005)
Overall Cost €2,450 million €1,803 million €1,500 million €2,400 million €2,000 million ? €752 million
Cost per km €158 million /k m €140 million / km €108 million / km €134 million / km €400 million / km ? €134 million / km
Overall Length 15.5 km 13 km 14m 18 km 5 km 5.6 km
Tunnel 4 kmSingle Tunnel
11.6 km Twin Tunnels
14 kmTwin Tunnels
7.5 km Twin Tunnels
5 km Twin Tunnel
4.5 kmRoad Tunnel x 2
Cut & Cover 0 2.7 km 0
Elevated 10.5 km 2.2 km 0 Not applicable
Road Level 0 5.5 km 0
Stations 7 Nr. 7 Nr. 5 Nr. 14 Nr. 3 Nr. Not applicable
Capacity 13,000 Passengers per hour
19,800 Passengers per hour
? Not applicable
ⓒ David H Moloney
Advantages of Rail Benefits of Metro to commuters
1. Time saving for commuters 4. Reduction in accident
2. Reliable and safe journey 5. Reduced fuel consumption
3. Reduction in atmospheric pollution 6. Reduced traffic congestion
Contractor’s General Items
Contractor’s Temporary Site Facilities
ⓒ David H Moloney
Brief Description
Contractors Site facilities comprise:Offices, Canteens, Toilets, Drying Rooms, Stores, Plant Yard, generators and Workshops.
Ge
ne
ral It
em
s
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Concrete batching plant comprises -concrete mixer, control cabin, silos for cement and fly ash, aggregate bins and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks. The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage capacity to match two days concrete production
Quarry & Aggregate Production
3D image to show Sequence, Method & Plant.
ⓒ David H Moloney
Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
Site Hoarding examples
ⓒ David H Moloney
Ge
ne
ral It
em
s
Wheel Wash Drive-throughG
en
era
l It
em
s
Weighbridge & Sheeting Access
ⓒ David H Moloney
Ge
ne
ral It
em
s
Sheet Pile Temporary Shaft
ⓒ David H Moloney
Ge
ne
ral It
em
s
Brief Description
Sheet Pile Temporary shaft is used to enable an excavation for a deep structure.The construction sequence is:Install sheet-piles.Excavate and install bracing.Excavate to final level.Construct concrete structure.Backfill, remove bracing and sheet-piles
Sheet Pile Temporary Shaft
ⓒ David H Moloney
Ge
ne
ral It
em
s
3D Animation to show Sequence
FalseworkG
en
era
l It
em
s
Brief Description
Falsework to support Bridge deck formwork
Dewatering
ⓒ David H Moloney
Ge
ne
ral It
em
s
Brief Description
Construction dewatering is the removal or drainage of
groundwater and or surface / rain water usually by
pumping to keep the works dry.
Dewatering
ⓒ David H Moloney
Ge
ne
ral It
em
s
Dewatering by Wellpoints
ⓒ David H Moloney
Ge
ne
ral It
em
s
Dust Suppression
ⓒ David H Moloney
Ge
ne
ral It
em
s
Temporary Fence type 2
ⓒ David H Moloney
Ge
ne
ral It
em
s
Brief Description
Temporary fence on precast beam for airport.
Traffic Management
ⓒ David H Moloney
Ge
ne
ral It
em
s
Brief Description
Traffic management plans are necessary when working on or beside roads
Traffic Management - Realign Motorway under new Bridges
ⓒ David H Moloney
Ge
ne
ral It
em
s
Health, Safety & Environmental
Existing Underground Utilities
ⓒ David H Moloney
Ea
rth
wo
rks
Brief Description
Before digging
establish the location
and route of
underground utilities.
Locator to find Utilities
Spray Paint to mark pavement
Existing Underground Utilities & Overhead Cables - Safety Measures
ⓒ David H Moloney
Ea
rth
wo
rks
Safety Precautions
HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE Issues and historical trends
Environmentally Friendly Site Air, Noise, Water & Soil Pollution
Water Pollution PreventionG
en
era
l It
em
s
Geotechnical
Diaphragm Wall Construction - Sequence, Plant & Methods
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
ⓒ David H Moloney
Earthworks
Tunnels & Underground Stations
3D image to show Sequence, Method & Plant.
David H Moloney
ⓒ David H Moloney
Excavate & Load, Cart, Tip & Return
Brief Description
Cycle Time for 7km haulage distance using an Excavator 45 tonne weight and Dumper with a 40 tonne capacity, the cycle time is 34 minutes
Ea
rth
wo
rks
7 minutes
14 minutes
3 minutes
14 minutes 7 km
7 km
Underground Station Excavation
Underground Station Construction
Rock Excavation Underground
Excavate with Roadheader
Drill & Fit Rock Bolts
Spray Mortar as Lining
Excavators with Rock Breaker& Rock Rotary Cutter
Roadheader
ⓒ David H Moloney
Using Mining Techniques
Bed Rock - Type & Depth
Ground ConditionsThe limestone bedrock is between 5 and 25 metres below ground level. The overlying deposits are generally boulder clay with thin layers of sand and gravel. The water table is between 2 and 4 metres below ground level.The Bedrock Geology Map of Ireland, gives the rock as limestone and mudstone, along the tunnel route.
Rock - Excavability
Brief Description
The excavability of rock depends
mainly on the rock strength and the
layer thickness. This diagram shows
excavation methods for rock of
various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
Ea
rth
wo
rks
Station Excavation - Soil on Rock Situation
Rock Nailing, Rock breaking & Excavation
ⓒ David H Moloney
Concrete
Tunnel Wall Segments Casting
Clean Mould
Lift Precast Segment out of mould
after 18 hours.
Reinforcement
fabricate
Reinforcement
into Mould
Concreting
Segment Storage
Casting Cycle Time 24 hrs
ⓒ David H Moloney
Tunnel Precast Segments
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Co
ncre
te
Brief Description
The sequence to construct a reinforced concrete wall is as
follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.
.
Cycle Time Pour per Day
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Co
ncre
te
Reinforced Structure Construction Sequence
ⓒ David H Moloney
Co
ncre
te
Brief Description
The general sequence to construct a reinforced concrete tank
is as follows-
1. Construct the floor and wall panels in a hit and miss pattern.
2. Construct the floor and wall corners and T shape panels.
3. Construct the roof working outwards from the back.
Reinforced Structure Construction Sequence David H Moloney
ⓒ David H Moloney
Bridge & Post-tensioningC
on
cre
te
Brief Description
The sequence to post-tension a bridge
deck is as follows;
Fix the ducts and anchorages.
Install the stressing strand.
Concrete the deck.
Stress the strands and lock at
anchorages.
Grout the ducts.
Bridge & Post-tensioningC
on
cre
te
Bridge & Post-tensioningC
on
cre
te
Bridge Construction Sequence David H Moloney
Piling Surcharge Abutments
Remove Surcharge AbutmentsDeck centre
Post-tensioning Fascia & Waterproof deckComplete Bridge
PiersOverview
Deck Ends
Images with Schematic 3D view, Photos & Timeline
ⓒ David H Moloney
Post-tensioning Bridge Deck David H Moloney
Waterproofing Spray on SystemM
isce
llan
eo
us
Waterproofing Spray on TestsM
isce
llan
eo
us
Underground Stations David H Moloney
ⓒ David H Moloney
Large Floor Concrete Pour
Rail ViaductC
on
cre
te
Brief Description
Shown is the construction of a light rail viaduct where
an overhead gantry was used to lift and place the
precast concrete viaduct segments.
Viaduct Construction
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
David H Moloney
ⓒ David H Moloney
Viaduct Construction David H Moloney
ⓒ David H Moloney
Viaduct Segments Launching
ⓒ David H Moloney
Viaduct Segments Casting David H Moloney
Casting Method
The concrete segments are manufactured
using the short-line, match-casting method.
Match-casting is when sequential segments are poured against the previous cast segment, this ensures that the segments will fit perfectly on site. Horizontal and vertical curves are achieved by setting the cast segment at a rotation in either or both axis to the mould used to cast the next segment.
ⓒ David H Moloney
Viaduct Segments – Short-line, Match Casting Method
David H MoloneyMatch-casting is when sequential segments are poured against the previous cast segment, this ensures that the segments will fit perfectly on site.
Cycle Time 24 hrs
Piling
Piling Construction - Plant & Methods
Brief Description
Piling Plant, Equipment and Material;
Crawler Crane, Piling Hammer, Temporary Casing,
Piling Rig, Concrete Pump, Concrete Mixer Trucks,
Tremie Pipe and Reinforcement Cage
Pili
ng
Piling Construction - Plant, Methods & SequenceP
ilin
g
Piling Construction - Plant & MethodsP
ilin
g
Piling Construction - Vertical PilesP
ilin
g
Piling Construction - Raking PilesP
ilin
g
Piling Construction - Raking PilesP
ilin
g
Pile Load Test
ⓒ David H Moloney
Pili
ng
Brief Description
A jack is used to load the pile in steps and
gauges measure any settlement.
Secant Pile Construction - Sequence, Plant & Methods
3D image to show Sequence, Method & Plant.
For construction details see my YouTube Channel
ⓒ David H Moloney
Roads & Paving
Asphalt Batching YardR
oa
ds &
Pa
vin
gs
Road Construction Sequence Animation
Tunnel
Tunnel Design
Twin Tunnels single track with Cross passages at 250m intervals for emergency evacuation
Tunnels in rock to avoid ground & building settlement. Depth 25 metres on average
ⓒ David H Moloney
Cut & Cover Tunnel Construction
Sequence -Traffic and utilities are diverted, excavate trench, construct & backfill to bury.
To prevent the faces of the excavation from collapsing, different measures are used –
batter the faces, diaphragm walls, secant piles or a combination of soil nailing and
shotcreting.
Ramp Construction
Sequence -Traffic and utilities are diverted, excavate, construct and backfill to sides.
To prevent the faces of the excavation from collapsing, different measures are used – batter
faces, diaphragm walls, secant piles or a combination of soil nailing and shotcreting.
ⓒ David H Moloney
Tunnel Boring Machine (TBM)
Cutting Head rotates to Dig
Excavated material removed by conveyor belt
Lifting muck to surface with skip
Placing Concrete Segments
Tunnel Boring Machine (TBM)
Cutting Head rotates
7 nr. Precast segments form rings that line the tunnel Excavated material removed
by conveyor belt
ⓒ David H Moloney
Tunnel Fit-out Rail, Electricals, Ventilation
Tunnel Fit-out
Install Sleepers & Rails
Concrete Batching Train for Floor Slab
Drilling Machine for Utilities Brackets
Commissioning, Testing, Handover & Opening
Purpose to test and ensure that everything (e.g. trains, escalators, lifts, ticket barriers) works as it should.
ⓒ David H Moloney
Miscellaneous Works
Fencing
ⓒ David H Moloney
Sequence of Construction
Clear Scrub & Grade ground
Fix Corner & Strainer Posts
Fix Intermediate Posts
Fix Line Wire, Chain-link & Razer wire
Concrete ground beam
Progress Monthly, Monitoring & Reporting - DashboardDashboard is a single page, graphical representation of current
progress and historical trends
Histogram Charts for Resources & Outputs
Concrete, Manpower, TBM,
Manpower per Discipline Concrete per Location
Numbers for each month of the Project Quantity for each month of the Project
ⓒ David H Moloney
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
Other Projects
Luas – Dublin, Tram / Light Rail System Construction Sequence & Methods
Install Traffic Control Fencing & Welfare Facilities Divert Underground Utilities Excavate
Prepare Formation Reinforcement & Rails Paving
Paving Information Sign Trams in Operation Trams in Operation
Reinforcement & Rails
ⓒ David H Moloney
Production by David H Moloney
See my YouTube Video on Dublin Metro North
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ